PROYECTO INCENTIVOS A LA OFERTA REGIÓN CARIBE

UNION TEMPORAL ITAC

CONTRATO DE APORTE No. 861 del 26 de diciembre de 2.019

INFORME MENSUAL DE SEGUIMIENTO

MES 25
PERIODO: 1 al 31 de Diciembre de 2.021
Contenido
1 INTRODUCCIÓN ...................................................................................................................... 7
2. OBJETIVO .................................................................................................................................. 8
2.2. OBJETIVOS ESPECÍFICOS ........................................................................................... 8
3. RESUMEN EJECUTIVO .......................................................................................................... 9
4. ACTIVIDADES TECNICAS .................................................................................................... 10
4.1. DOCUMENTOS DE PLANEACIÓN ............................................................................. 10
4.2. EJECUCION DEL PLAN DE ADQUISICIONES ......................................................... 11
4.3. ESTUDIOS DE CAMPO, CENSO Y MAPPING ......................................................... 13
4.4. DISEÑO ............................................................................................................................ 14
4.5. CUBICACIÓN DEL NODO............................................................................................. 16
4.6. PERMISOS USO DE INFRAESTRUCTURA .............................................................. 20
4.7. CONSTRUCCIÓN E INSTALACIÓN ........................................................................... 22
4.8. AVANCES DE LAS METAS DE INSTALACIÓN Y OPERACIÓN ........................... 24
4.9. SISTEMA DE GESTION DE LA INFORMACION ...................................................... 27
4.10. INDICADORES DEL PROYECTO............................................................................ 28
5. ACTIVIDADES FINANCIERAS ............................................................................................. 33
6. ACTIVIDADES JURIDICAS ................................................................................................... 36
7. ACTIVIDADES ADMINISTRATIVAS .................................................................................... 36
7.1. REUNIONES REALIZADAS .......................................................................................... 37
7.2. ESTADO DE LAS GARANTIAS .................................................................................... 38
7.3. SEGUIMIENTO AL CRONOGRAMA ........................................................................... 39
7.4. GESTION DE RIESGOS DEL PROYECTO ............................................................... 42
7.5. LECCIONES APRENDIDAS ......................................................................................... 43
7.6. PRINCIPALES CASOS DE EXITO .............................................................................. 43
7.7. PRINCIPALES DIFICULTADES ENCONTRADAS.................................................... 43
7.8. RECOMENDACIONES PARA MITIGAR LAS MISMAS EN EL SIGUIENTE
PERIODO ..................................................................................................................................... 43
7.9. CONCLUSIONES............................................................................................................ 43
ANEXOS
ANEXO 1 – CUADRO POLIZAS DEL PROYECTO

ANEXO 2 – MATRIZ DE RIESGOS

ANEXO 3 – FINANCIERO

ANEXO 4 – ADMINISTRATIVO

ANEXO 5 – ACCESOS POR METAS

ANEXO 6 – LICENCIAS Y PERMISOS MATRIZ

ANEXO 7 – PERMISOS

ANEXO 8 – CERTIFICADOS RETIE

ANEXO 9 - INDICADORES

ANEXO 10 - CERTIFICADO CUMPLIMIENTO OBLIGACIÓN CONFIDENCIALIDAD


LISTA DE FIGURAS
No table of figures entries found.
LISTA DE TABLAS

Tabla 1 – Documentos de Planeación ................................................................................................ 10


Tabla 2 - Elementos del plan de adquisiciones que están reportados a la fiducia............................. 12
Tabla 4 – Ejecución Meta 1................................................................................................................. 13
Tabla 5 – Ejecución Meta 2................................................................................................................. 13
Tabla 6 – Ejecución Meta 3................................................................................................................. 14
Tabla 7 – Avances del Diseño ............................................................................................................. 15
Tabla 8 – Contratos de arrendamiento espacio del nodo .................................................................. 17
Tabla 9 – Avances adecuación del nodo............................................................................................. 19
Tabla 10 – Estado solicitud de permisos ............................................................................................ 21
Tabla 11 – Avances construcción de nodos........................................................................................ 23
Tabla 12 – Avance metas de instalación y operación......................................................................... 24
Tabla 13 –Total de accesos instalados ............................................................................................... 25
Tabla 14 – Estado solicitud de permisos ............................................................................................ 26
Tabla 15 – Disponibilidad OLT junio 2021 .......................................................................................... 29
Tabla 16 – Disponibilidad CORE junio 2021........................................................................................ 30
Tabla 17 - Velocidad promedio de navegación junio 2021 ................................................................ 31
Tabla 18 – Calidad de Atención de junio 2021 ................................................................................... 32
Tabla 19 – Accesos Activos en junio 2021 .......................................................................................... 32
Tabla 20 – Seguimiento compromisos del comité No. 17 .................................................................. 38
Tabla 21 – Compromisos adquiridos en el Comité No. 17 ................................................................. 38
Tabla 22 - Pólizas ................................................................................................................................ 38
Tabla 23 – Documentos de Planeación .............................................................................................. 39
Tabla 24 – Seguimiento cronograma de actividades.......................................................................... 41
Tabla 25 – Seguimiento cronograma de accesos instalados .............................................................. 42
CONTROL DE CAMBIOS

No. VERSIÓN FECHA


MODIFICACIONES
MODIFICACIÓN MODIFICACIÓN
Versión 1.0 5/1/2022 Se presenta el documento para verificación por parte
de la Interventoría.
1 INTRODUCCIÓN

De conformidad a lo establecido en la cláusula segunda Obligaciones del Contratista


del Contrato de aporte 00861, La Unión Temporal ITAC, se permite presentar para
revisión y pronunciamiento de la Interventoría del Proyecto el presente Informe
Mensual de Seguimiento correspondiente al mes 25 del Contrato (1 al 31 de
diciembre de 2021).

En el presente informe de seguimiento se presenta de forma clara y concisa la


información que permite realizar un seguimiento detallado de la ejecución del
proyecto siguiendo las recomendaciones de presentación establecidas por la
dirección de infraestructura en el numeral 4.1.1 del Anexo Técnico.

El contenido del presente informe se detalla a continuación:

a. Resumen ejecutivo.

b. Actividades realizadas.
• Documentos de Planeación.
• Selección y Contratación de Talento humano para el desarrollo del
proyecto.
• Ejecución del Plan de Adquisiciones.
• Sistema de Gestión de la Información.
• Reuniones Realizadas.
• Aspectos Financieros y Contables.
• Aspectos Jurídicos.
• Estado de las Garantías.
• Aspectos Administrativos.

c. Informe por actividades respecto a las obligaciones.


d. Seguimiento al Cronograma.
e. Avance de ejecución presupuestal.
f. Relación de subcontratistas involucrados en el proyecto.
g. Dificultades encontradas durante la ejecución del proyecto.
h. Gestión de Riesgos del proyecto.
2. OBJETIVO

2.1. OBJETIVO GENERAL

Presentar de manera ordenada, clara y detallada el estado de avance de las


actividades y obligaciones contractuales a cargo de la Unión Temporal ITAC,
en desarrollo del contrato de aporte No 861 del 26 de diciembre de 2019 para
el mes 25 del Contrato (1 al 31 de diciembre de 2021).

2.2. OBJETIVOS ESPECÍFICOS

• Hacer seguimiento a la ejecución del contrato de aporte suscrito por la


Unión Temporal ITAC con el Fondo Único de las Tecnologías de la
Información y las comunicaciones FONTIC en los términos legales
establecidos por la Dirección de Infraestructura.
• Realizar la respectiva verificación para el cumplimiento de pago de
aportes de parafiscales, seguridad social.
• Planear, organizar, dirigir y controlar las actividades necesarias para
seleccionar el personal requerido para la ejecución del proyecto.
• Dar a conocer las actividades desarrolladas en el mes de diciembre, en
cuanto a las responsabilidades contractuales, las dificultades y riesgos
que se han presentado a partir de la ejecución, seguimiento y control de
las mismas.
• Dar a conocer las actividades desarrolladas en el mes de diciembre
respecto del plan de inversión del anticipo y la gestión de Fiducia.
• Planear y llevar a cabo las acciones necesarias para el cumplimiento de
la Etapa de Planeación.
• Planear y llevar a cabo las acciones necesarias para el cumplimiento de
la Etapa de operación.
• Presentar el avance de los documentos de planeación
• Presentar el avance de las demás obligaciones estimadas Anexo Técnico
del Proyecto para este período.
3. RESUMEN EJECUTIVO

3.1 Aspectos Técnicos: La construcción de las redes y la instalación de los accesos en los
47 municipios obligación en el marco del Contrato de Aporte 0861 de 2019 ya se cumplió al
100%, logrando así la aprobación de la totalidad de los 15.811 accesos en los 47 municipios
en los departamentos de Bolívar, Córdoba y Sucre en la Región Caribe, para lo cual la
interventoría emitió concepto de aprobación de la Meta 3 y por consiguiente de la Meta
Regional de los 15.811 accesos, mediante comunicado PIO-C&M-UTITAC-2908-21 con
Radicado 20213640984581.

3.2 Aspectos Administrativos y Financieros:


A la fecha de corte de este informe el FONDO ÚNICO DE TIC ha transferido además del
anticipo a la Unión Temporal, el primer, segundo, tercer, cuarto, quinto, sexto y séptimo
desembolso por un valor total de $41.427.860.080, el séptimo desembolso se giró a la
Fiduciaria el día 26 de noviembre y el 21 de diciembre se radicaron en Mintic los documentos
para el trámite del octavo desembolso.
A la fecha de presentación de este informe se han ejecutado el 100% de los recursos del
anticipo equivalentes a $11.018.850.024 y de los desembolsos primero a tercero se han
ejecutado recursos por $24.360.089.929 para un total de recursos ejecutados de
$35.378.939.953, en el mes de diciembre se aprobó la orden de pago 016, no obstante, por
temas internos de la Fiducia solo se desembolsó hasta el 4 de enero.
El detalle de la información se desarrolla en el respectivo punto del informe.

En este período los miembros de la Unión Temporal cumplieron oportunamente con las
obligaciones del Art. 50 de la ley 789 de 2002 al igual que el pago de los impuestos, la
información se detalla en el capítulo correspondiente.

3.3. Aspectos de los sistemas:

Mediante comunicado PIO-C&M-UTITAC-1917-21 con radicado 20213640944291 la


interventoría emite concepto de Cumplimiento del sistema de información, conforme lo
concertado mediante el acta No. 1-ITAC del 22/01/2020 y la aprobación de la concertación
de campos por parte de la Entidad Contratante emitida por medio del comunicado PIO-
DIRINFRA-UTITAC-09-20 – (20203211441892) RM 202023308 del 16/03/2020.
Mediante comunicado PIO-UTITAC-C&M-234-2021 del 5/11/2021 con radicado
20213211600282 la UT ITAC entregó respuesta a las observaciones en la LISTA DE
CHEQUEO NO. 14 APLICADA AL SISTEMA DE INFORMACIÓN.
Mediante comunicado PIO-C&M-UTITAC-4056-21 del 30/11/2021 con radicado
20213641050051 la interventoría envía observaciones en la LISTA DE CHEQUEO NO. 15
APLICADA AL SISTEMA DE INFORMACIÓN, las cuales fueron subsanadas por UT ITAC
mediante comunicado PIO-UTITAC-C&M-255-2021 del 15/12/2021 con radicado MINTIC
211102045 y radicado interventoría 20213211641732.
Se realizaron actualizaciones de los módulos de: gestión documental, indicadores y PQRs.
A continuación, presentamos cada una de las obligaciones contractuales presentadas y/o
aprobadas en el presente periodo:

4. ACTIVIDADES TECNICAS

4.1. DOCUMENTOS DE PLANEACIÓN

Se concluyó la entrega de todos los documentos de planeación conforme las fechas


establecidas en el Anexo Técnico del Contrato de Aporte No. 861 de 2019, como se aprecia
en la siguiente tabla:

Tabla 1 – Documentos de Planeación

El Informe Detallado de Ingeniería y Operación se radico en MINTIC el 28/02/2020 con Rad


MINTIC. 201011111 y se dio aprobación por parte de la Supervisión con el Registro MINTIC
202036968 el 06 de mayo del 2020.
El Plan de instalación y puesta en servicio se entregó el 30/03/2020, se recibieron
observaciones el 15/04/2020 comunicado PIO-C&M-UTITAC-171-20 RM 201019191,
subsanación presentada el 22/04/2020 comunicado PIO-UTITAC-C&M-00-20 RM
201020543, se presentó alcance al plan de instalación y puesta en servicio con el
comunicado PIO-UTITAC-C&M-007-20 radicado Interventoría 20203641457322 atendiendo
todas las solicitudes y observaciones presentadas, la interventoría dio concepto favorable
con el comunicado PIO-C&M-DIRINFRA-331-20 el 13 de mayo del 2020 y aprobación por
parte de la Supervisión el 26-MAY-2020 mediante comunicado PIO-DIRINFRA-UTITAC-14-
2020 y registro 202042217.
El Plan de Comercialización se entregó el 30/03/2020 mediante radicado MINTIC
201016474 y la interventoría dio concepto favorable con el comunicado PIO-C&M-MINTIC-
330-20 del 13-MAY-2020.
El Plan de Mantenimiento se entregó con el oficio PIO-UTITAC-DIRINFRA-020-2020 del 28-
04-2020 por correo electrónico RM 201021638 el cual fue aprobado por la Supervisión el
19-06-2020 mediante comunicado PIO-DIRINFRA-UTITAC-16-2020 y registro 202048861.
El 24-JUL-2020 se presentó la primera solicitud de ajustes al Plan de Instalación y Puesta
en Servicio (Versión 2) mediante comunicado PIO-UTITAC-C&M-030-2020 y radicado
MINTIC 201041480. Esta solicitud fue aprobada por la Interventoría el 11-AGO-2020
mediante comunicado PIO-C&M-DIRINFRA-739-20 y radicado 20203640912531, y la
supervisión dio su aprobación mediante comunicado PIO-DIRINFRA-UTITAC-23-2020 del
11-AGO-2020 y radicado 201045685.
El 3-NOV-2020 mediante comunicado PIO-UTITAC-C&M-068-2020 con radicado MINTIC
201065814 se hizo la segunda solicitud de ajustes al Plan de Instalación y Puesta en
Servicio (Versión 3), la cual fue aprobada por la interventoría el 9-NOV-2020 mediante
comunicado PIO-C&M-DIRINFRA-1346-20 y radicado 20203640928321 y aprobado por la
supervisión el 16-DIC-2020 mediante comunicado PIO-DIRINFRA-UTITAC-37-2020 y
radicado MINTIC 202113708.

4.2. EJECUCION DEL PLAN DE ADQUISICIONES

A continuación, se relacionan las entregas de material realizadas en el desarrollo del


proyecto con corte al cierre de junio de 2021, el respectivo reporte se hizo a la fiduciaria el
27 de julio, mediante comunicado PIO-UTITAC-FIDUCARIBE-020-2021, para el trimestre
julio a septiembre este informe no presenta variaciones.
ANEXO 1 EQUIPOS
CONTRATO DE APORTE 000861
PERIODO: ABR A JUN DE 2021

CANTIDAD
PAGADA
CANTIDAD CANTIDAD VALOR
FECHA DE DESCRIPCIÓN DEL CON # FACTURA VALOR VALOR DE UBICACIÓN FINAL DEL
ITEM PROVEEDOR CATEGORIZACIÓN PLAN DE EN NUMERO DE OP VALOR OP ASOCIADO AL DESEMBOLSO UTILIZACIÓN VALOR PAGADO ESTADO
ADQUISICIÓN ELEMENTO RECURSOS DE VENTA FACTURA TRM (PAGO) ACTIVO
COMPRAS FACTURA ANTICIPO
DE
FOMENTO
1000COR001 29/10/2020 Huawei-Meltec eSight CORE 1 1 1 10502 723,76 3.793 4 2.745.200 1 2 2.745.199,62 Instalado
SmartAX
2000OLT001
29/10/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 10502 85.559,83 3.793 4 324.526.738 1 2 324.526.738,41 Instalado
1000COR002 29/10/2020 Huawei-Meltec CloudEngine S12700E-8 CORE 1 1 1 10502 35.883,8 3.793 4 136.106.474 1 2 136.106.473,52 Instalado
1000COR003 29/10/2020 Huawei-Meltec CloudEngine S12700E-4 CORE 1 1 1 10502 40.801 3.793 4 154.755.731 1 2 154.755.731,21 Instalado
1000COR004 29/10/2020 Huawei-Meltec NetEngine NE40E-M2K-B CORE 1 1 1 10502 76.209 3.793 4 289.059.274 1 2 289.059.273,89 Instalado
USG6655E(C13_North
1000COR005
29/10/2020 Huawei-Meltec America) CORE 1 1 1 10502 61.756 3.793 4 234.237.881 1 2 234.237.881,24 Instalado
20200072S 29/10/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.539 2.539 10502 184.245,58 3.793 4 698.839.807 1 2 698.839.806,86 Instalado
Network Cloud Engine-
1000COR006
29/10/2020 Huawei-Meltec FAN Lite HW CORE 1 1 1 10502 43.639 3.793 4 165.521.184 1 2 165.521.183,62 Instalado
Network Cloud Engine-
1000COR007
29/10/2020 Huawei-Meltec FAN Lite CORE 1 1 1 10502 17.890 3.793 4 67.856.126 1 2 67.856.125,83 Instalado
ODN FMC21(Field-
20200085N
29/10/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 10502 5.052 3.793 4 19.160.654 1 2 19.160.653,80 Instalado
ODN SSC28(Pre-
20200087N
29/10/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 10502 296.033 3.793 4 1.122.847.849 1 2 1.122.847.849,15 Instalado
ODN ATB31(Not Support
20200082N
29/10/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.539 2.539 10502 7.040 3.793 4 26.702.144 1 2 26.702.144,15 Instalado
SmartAX EA5800-
2000OLT002
29/10/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 10502 19.111,0 3.793 4 72.487.759 1 2 72.487.758,74 Instalado
Fibra optica 24HADSS
202000133F
29/10/2020 Huawei-Meltec span100-150 Fibra 120.000 30.000 30.000 10502 28.203 3.793 4 106.973.415 1 2 106.973.414,94 Instalado
202000134I 29/10/2020 Huawei-Meltec Implementación en sitio NODOS 6 4 4 10502 54.061 3.793 4 205.050.794 1 2 205.050.794,31 Instalado
SmartAX
2000OLT001
1/10/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 10863 85.564,83 3.745 6 320.475.377 2 3 320.475.376,67 Instalado
20200072S 1/10/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.417 2.417 10863 175.306,22 3.745 6 656.593.664 2 3 656.593.663,83 Instalado
ODN FMC21(Field-
20200085N
1/10/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 10863 4.809 3.745 6 18.011.247 2 3 18.011.246,72 Instalado
ODN SSC28(Pre-
20200087N
1/10/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 10863 281.808,6 3.745 6 1.055.488.884 2 3 1.055.488.884,11 Instalado
ODN ATB31(Not Support
20200082N
1/10/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.417 2.417 10863 6.673 3.745 6 24.992.573 2 3 24.992.572,60 Instalado
SmartAX EA5800-
2000OLT002
1/10/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 10863 19.111 3.745 6 71.578.602 2 3 71.578.602,42 Instalado
Fibra optica 24HADSS
202000133F
1/10/2020 Huawei-Meltec span100-150 Fibra 120.000 30.000 30.000 10863 28.203 3.745 6 105.631.798 2 3 105.631.798,23 Instalado
202000134I 1/10/2020 Huawei-Meltec Implementación en sitio NODOS 6 2 2 10863 27.030 3.745 6 101.240.101 2 3 101.240.100,51 Instalado
SmartAX
2000OLT001
1/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 3 3 11005 42.782,42 3.757 5 160.742.521 2 3 160.742.520,84 Instalado
20200072S 1/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.222 2.222 11005 161.162,77 3.757 5 605.522.375 2 3 605.522.374,83 Instalado
ODN FMC21(Field-
20200085N
1/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11005 4.421 3.757 5 16.610.285 2 3 16.610.285,38 Instalado
ODN SSC28(Pre-
20200087N
1/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11005 259.072,7 3.757 5 973.390.668 2 3 973.390.667,66 Instalado
ODN ATB31(Not Support
20200082N
1/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.222 2.222 11005 6.134 3.757 5 23.048.596 2 3 23.048.595,73 Instalado
SmartAX EA5800-
2000OLT002
1/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11005 29.516 3.757 5 110.896.687 2 3 110.896.686,58 Instalado
Fibra optica 24HADSS
202000133F
1/11/2020 Huawei-Meltec span100-150 Fibra 120.000 10.000 10.000 11005 9.401 3.757 5 35.321.531 2 3 35.321.531,21 Instalado
SmartAX
2000OLT001
1/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 7 7 11512 99.825,64 3.854 5 384.774.923 2 3 384.774.923,43 Instalado
20200072S 1/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.027 2.027 11512 147.019,32 3.854 5 566.681.572 2 3 566.681.571,85 Instalado
ODN FMC21(Field-
20200085N
1/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11512 4.033 3.854 5 15.544.822 2 3 15.544.822,34 Instalado
ODN SSC28(Pre-
20200087N
1/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11512 236.336,8 3.854 5 910.953.230 2 3 910.953.229,61 Instalado
ODN ATB31(Not Support
20200082N
1/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.027 2.027 11512 5.596 3.854 5 21.570.160 2 3 21.570.159,91 Instalado
SmartAX EA5800-
2000OLT002
1/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11512 19.111 3.854 5 73.662.850 2 3 73.662.850,18 Instalado
Fibra optica 24HADSS
202000133F
1/11/2020 Huawei-Meltec span100-150 Fibra 120.000 15.000 15.000 11512 14.102 3.854 5 54.353.809 2 3 54.353.808,71 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 7 7 11918 99.825,64 3.764 5 375.725.729 2 3 375.725.729,43 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 1.993 1.993 11918 144.553,29 3.764 5 544.072.551 2 3 544.072.550,79 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11918 3.167 3.764 5 11.918.475 2 3 11.918.474,77 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11918 185.575,2 3.764 5 698.471.666 2 3 698.471.666,20 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.193 2.193 11918 6.054 3.764 5 22.787.801 2 3 22.787.801,28 Instalado
SmartAX EA5800-
2000OLT002
30/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11918 19.111 3.764 5 71.930.436 2 3 71.930.436,29 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 5.000 5.000 11918 4.701 3.764 5 17.691.836 2 3 17.691.835,91 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 14808 85.564,83 3.728,09 9 318.993.394 3 4 318.993.393,79 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 358 358 14808 25.965,92 3.728,09 9 96.803.283 3 4 96.803.282,96 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 14808 1.513 3.728,09 9 5.640.119 3 4 5.640.118,50 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 14808 88.656,6 3.728,09 9 330.519.631 3 4 330.519.630,67 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 158 158 14808 436 3.728,09 9 1.626.217 3 4 1.626.216,72 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 10.000 10.000 14808 9.401 3.728,09 9 35.047.774 3 4 35.047.774,09 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 5 5 14809 71.304,03 3.728,09 9 265.827.828 3 4 265.827.828,15 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 3.502 3.502 14809 254.001,81 3.728,09 9 946.941.612 3 4 946.941.611,57 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 14809 6.966 3.728,09 9 25.968.315 3 4 25.968.315,48 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 14809 408.195,2 3.728,09 9 1.521.788.503 3 4 1.521.788.503,19 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 3.502 3.502 14809 9.668 3.728,09 9 36.044.373 3 4 36.044.373,07 Instalado
SmartAX EA5800-
2000OLT002
30/11/2020 Huawei-Meltec X2(F01T100) OLT 6 2 2 14809 38.222 3.728,09 9 142.495.199 3 4 142.495.199,14 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 20.000 20.000 14809 18.802 3.728,09 9 70.095.548 3 4 70.095.548,18 Instalado

Tabla 2 - Elementos del plan de adquisiciones que están reportados a la fiducia

El último anexo se reportó con corte a junio 30 y no se ha vuelto a radicar porque desde el
mes de mayo no se realiza adquisición de equipos con recursos del patrimonio.
4.3. ESTUDIOS DE CAMPO, CENSO Y MAPPING

Estas actividades en los municipios están ejecutadas al 100%.

• ESTUDIOS DE CAMPO, CENSO Y MAPPING

Estas actividades están cumplidas al 100%.

Se relaciona el avance de ejecución de los municipios de la Primera Meta, cumplida al 100%:

META MUNICIPIO % EJECUTADO


META 1 LA APARTADA 100%
META 1 BUENAVISTA 100%
META 1 SAN JOSE DE URE 100%
META 1 AYAPEL 100%
META 1 ALTOS DEL ROSARIO 100%
META 1 BARRANCO DE LOBA 100%
Tabla 3 – Ejecución Meta 1

Se relaciona el avance de ejecución de los municipios de la Segunda Meta, cumplida al


100%:

META MUNICIPIO % EJECUTADO


META 2 TIERRALTA 100%
META 2 MARIA LA BAJA 100%
META 2 MAJAGUAL 100%
META 2 MOÑITOS 100%
META 2 TOLU VIEJO 100%
META 2 CHINU 100%
META 2 OVEJAS 100%
META 2 MOMIL 100%
META 2 CICUCO 100%
META 2 LOS PALMITOS 100%
META 2 SAN BENITO ABAD 100%
META 2 SAN ANTERO 100%
META 2 VILLANUEVA 100%
META 2 SAMPUES 100%
META 2 SAN ESTANISLAO 100%
META 2 ZAMBRANO 100%
META 2 SOPLAVIENTO 100%
META 2 ARENAL 100%
META 2 SAN CRISTOBAL 100%

Tabla 4 – Ejecución Meta 2


Se relaciona el avance de ejecución de los municipios de la Tercera Meta, cumplida al 100%:

META MUNICIPIO % EJECUTADO


META 3 SIMITI 100%
META 3 RIO VIEJO 100%
META 3 SAN PABLO 100%
META 3 PUEBLO NUEVO 100%
META 3 SANTA ROSA DEL SUR 100%
META 3 GALERAS 100%
META 3 MONTECRISTO 100%
META 3 SAN MARTIN DE LOBA 100%
META 3 TIQUISIO 100%
META 3 MORALES 100%
META 3 SAN JACINTO 100%
META 3 VALENCIA 100%
META 3 CALAMAR 100%
META 3 SAN PEDRO 100%
META 3 ARROYOHONDO 100%
META 3 MAHATES 100%
META 3 LA UNION 100%
META 3 TUCHIN 100%
META 3 SAN JUAN DE BETULIA 100%
META 3 PURISIMA 100%
META 3 CLEMENCIA 100%
META 3 TALAIGUA NUEVO 100%

Tabla 5 – Ejecución Meta 3

4.4. DISEÑO

Esta actividad esta ejecutada al 100% en los 47 municipios.


Diseño Red

1 Municipios 1 EJECUCIÓN

META 1 2 LA APARTADA 7/4/2020 100%

META 1 3 BUENAVISTA 5/30/2020 100%

META 1 4 SAN JOSE DE URE 5/30/2020 100%

META 1 5 AYAPEL 7/18/2020 100%

META 1 6 ALTOS DEL ROSARIO 5/30/2020 100%

META 1 7 BARRANCO DE LOBA 5/30/2020 100%

META 2 8 TIERRALTA 8/8/2020 100%

META 2 9 MARIA LA BAJA 8/15/2020 100%

META 2 10 MAJAGUAL 7/31/2020 100%

META 2 11 MOÑITOS 8/8/2020 100%

META 2 12 TOLU VIEJO 8/8/2020 100%

META 2 13 CHINU 9/5/2020 100%

META 2 14 OVEJAS 8/8/2020 100%

META 2 16 MOMIL 9/12/2020 100%

META 2 17 CICUCO 9/12/2020 100%

META 2 18 LOS PALMITOS 9/12/2020 100%

META 2 23 SAN BENITO ABAD 9/19/2020 100%

META 2 24 SAN ANTERO 8/29/2020 100%

META 2 25 VILLANUEVA 9/5/2020 100%

META 2 26 SAMPUES 9/19/2020 100%

META 2 27 SAN ESTANISLAO 9/30/2020 100%

META 2 28 ZAMBRANO 9/19/2020 100%

META 2 30 SOPLAVIENTO 9/19/2020 100%

META 3 42 ARENAL 12/5/2020 100%

META 2 31 SAN CRISTOBAL 9/19/2020 100%

META 3 32 SIMITI 11/21/2020 100%

META 3 33 RIO VIEJO 11/14/2020 100%

META 3 34 SAN PABLO 9/30/2020 100%

META 3 35 PUEBLO NUEVO 10/24/2020 100%

META 3 36 SANTA ROSA DEL SUR 9/30/2020 100%

META 3 37 GALERAS 11/7/2020 100%

META 3 38 MONTECRISTO 11/7/2020 100%

META 3 39 SAN MARTIN DE LOBA 11/7/2020 100%

META 3 40 TIQUISIO 10/24/2020 100%

META 3 41 MORALES 9/12/2020 100%

META 3 43 SAN JACINTO 10/31/2020 100%

META 3 44 VALENCIA 10/31/2020 100%

META 3 45 CALAMAR 11/14/2020 100%

META 3 46 SAN PEDRO 11/21/2020 100%

META 3 47 ARROYOHONDO 12/5/2020 100%

META 3 15 MAHATES 8/22/2020 100%

META 3 19 LA UNION 9/19/2020 100%

META 3 20 TUCHIN 9/19/2020 100%

META 3 21 SAN JUAN DE BETULIA 9/19/2020 100%

META 3 22 PURISIMA 9/19/2020 100%

META 3 29 CLEMENCIA 9/19/2020 100%

META 3 48 TALAIGUA NUEVO 12/19/2020 100%


%Avance Meta 1 (UT ITAC) 100%
%Avance Meta 2 (UT ITAC) 100%
%Avance Meta 3 (UT ITAC) 100%
%Avance Proyecto (UT ITAC) 100%

Tabla 6 – Avances del Diseño


4.5. CUBICACIÓN DEL NODO

Para la búsqueda y consecución de los sitios para la cubicación del nodo es necesario el
levantamiento de Site Survey, negociación y firma de contratos de arrendamiento y
adecuaciones físicas.

A continuación, se relaciona la gestión asociada a la ubicación de nodos y los contratos de


arrendamiento, en los 47 municipios:
Contrato de arrendamiento de
infraestructura de predios para
ubicación de NOC, Data Center,
Cuarto de equipos (según aplique)
Región Departamento Municipio
ESTADO
(Aprobado / En
ENTIDAD
trámite /
Subsanación)
Caribe BOLIVAR SAN PABLO PARTICULAR APROBADO
Caribe BOLIVAR SANTA ROSA DEL SUR PARTICULAR APROBADO
Caribe CORDOBA SAN ANTERO PARTICULAR APROBADO
Caribe SUCRE SAMPUES PARTICULAR APROBADO
Caribe CORDOBA VALENCIA PARTICULAR APROBADO
Caribe BOLIVAR CALAMAR PARTICULAR APROBADO
Caribe SUCRE GALERAS PARTICULAR APROBADO
Caribe BOLIVAR SAN ESTANISLAO PARTICULAR APROBADO
Caribe BOLIVAR ZAMBRANO PARTICULAR APROBADO
Caribe BOLIVAR RIO VIEJO PARTICULAR APROBADO
Caribe SUCRE SAN PEDRO PARTICULAR APROBADO
Caribe BOLIVAR CLEMENCIA PARTICULAR APROBADO
Caribe BOLIVAR SAN MARTIN DE LOBA PARTICULAR APROBADO
Caribe BOLIVAR ARROYOHONDO PARTICULAR APROBADO
Caribe BOLIVAR TIQUISIO PARTICULAR APROBADO
Caribe BOLIVAR MORALES PARTICULAR APROBADO
Caribe BOLIVAR TALAIGUA NUEVO PARTICULAR APROBADO
Caribe CORDOBA TIERRALTA PARTICULAR APROBADO
Caribe CORDOBA AYAPEL PARTICULAR APROBADO
Caribe CORDOBA CHINU PARTICULAR APROBADO
Caribe BOLIVAR MARIA LA BAJA PARTICULAR APROBADO
Caribe BOLIVAR SAN JACINTO PARTICULAR APROBADO
Caribe CORDOBA PUEBLO NUEVO PARTICULAR APROBADO
Caribe BOLIVAR VILLANUEVA PARTICULAR APROBADO
Caribe CORDOBA LA APARTADA PARTICULAR APROBADO
Caribe BOLIVAR MONTECRISTO PARTICULAR APROBADO
Caribe SUCRE OVEJAS PARTICULAR APROBADO
Caribe BOLIVAR SIMITI PARTICULAR APROBADO
Caribe BOLIVAR MAHATES PARTICULAR APROBADO
Caribe SUCRE MAJAGUAL PARTICULAR APROBADO
Caribe BOLIVAR ALTOS DEL ROSARIO PARTICULAR APROBADO
Caribe BOLIVAR SOPLAVIENTO PARTICULAR APROBADO
Caribe CORDOBA MOMIL PARTICULAR APROBADO
Caribe BOLIVAR CICUCO PARTICULAR APROBADO
Caribe SUCRE LOS PALMITOS PARTICULAR APROBADO
Caribe CORDOBA BUENAVISTA PARTICULAR APROBADO
Caribe BOLIVAR BARRANCO DE LOBA PARTICULAR APROBADO
Caribe SUCRE LA UNION PARTICULAR APROBADO
Caribe CORDOBA MOÑITOS PARTICULAR APROBADO
Caribe CORDOBA SAN JOSE DE URE PARTICULAR APROBADO
Caribe BOLIVAR SAN CRISTOBAL PARTICULAR APROBADO
Caribe BOLIVAR ARENAL PARTICULAR APROBADO
Caribe CORDOBA TUCHIN PARTICULAR APROBADO
Caribe SUCRE SAN JUAN DE BETULIA PARTICULAR APROBADO
Caribe CORDOBA PURISIMA PARTICULAR APROBADO
Caribe SUCRE SAN BENITO ABAD PARTICULAR APROBADO
Caribe SUCRE TOLU VIEJO PARTICULAR APROBADO

Tabla 7 – Contratos de arrendamiento espacio del nodo


Y a continuación se relacionan el avance de la adecuación del nodo y puesta en servicio del
mismo.
Puesta en servicio NODO

1 Municipios PLANEACIÓN EJECUCIÓN

META 1 2 LA APARTADA 8/8/2020 100%

META 1 3 BUENAVISTA 8/8/2020 100%

META 1 4 SAN JOSE DE URE 8/8/2020 100%

META 1 5 AYAPEL 8/29/2020 100%

META 1 6 ALTOS DEL ROSARIO 8/8/2020 100%

META 1 7 BARRANCO DE LOBA 8/15/2020 100%

META 2 8 TIERRALTA 9/12/2020 100%

META 2 9 MARIA LA BAJA 10/10/2020 100%

META 2 10 MAJAGUAL 9/19/2020 100%

META 2 11 MOÑITOS 9/30/2020 100%

META 2 12 TOLU VIEJO 9/30/2020 100%

META 2 13 CHINU 9/30/2020 100%

META 2 14 OVEJAS 9/19/2020 100%

META 2 16 MOMIL 10/31/2020 100%

META 2 17 CICUCO 10/19/2020 100%

META 2 18 LOS PALMITOS 9/12/2020 100%

META 2 23 SAN BENITO ABAD 10/17/2020 100%

META 2 24 SAN ANTERO 9/12/2020 100%

META 2 25 VILLANUEVA 10/24/2020 100%

META 2 26 SAMPUES 10/7/2020 100%

META 2 27 SAN ESTANISLAO 11/7/2020 100%

META 2 28 ZAMBRANO 11/16/2020 100%

META 2 30 SOPLAVIENTO 10/7/2020 100%

META 3 42 ARENAL 11/14/2020 100%

META 2 31 SAN CRISTOBAL 10/10/2020 100%

META 3 32 SIMITI 1/16/2021 100%

META 3 33 RIO VIEJO 11/21/2021 100%

META 3 34 SAN PABLO 11/30/2020 100%

META 3 35 PUEBLO NUEVO 12/5/2020 100%

META 3 36 SANTA ROSA DEL SUR 1/7/2021 100%

META 3 37 GALERAS 12/31/2020 100%

META 3 38 MONTECRISTO 12/31/2020 100%

META 3 39 SAN MARTIN DE LOBA 1/25/2021 100%

META 3 40 TIQUISIO 1/25/2021 100%

META 3 41 MORALES 11/21/2020 100%

META 3 43 SAN JACINTO 12/12/2020 100%

META 3 44 VALENCIA 12/19/2020 100%

META 3 45 CALAMAR 1/9/2021 100%

META 3 46 SAN PEDRO 1/16/2021 100%

META 3 47 ARROYOHONDO 1/23/2021 100%

META 3 15 MAHATES 12/30/2020 100%

META 3 19 LA UNION 12/7/2020 100%

META 3 20 TUCHIN 12/7/2020 100%

META 3 21 SAN JUAN DE BETULIA 12/30/2020 100%

META 3 22 PURISIMA 12/7/2020 100%

META 3 29 CLEMENCIA 11/23/2020 100%

META 3 48 TALAIGUA NUEVO 1/23/2021 100%


%Avance Meta 1 (UT ITAC) 100%
%Avance Meta 2 (UT ITAC) 100%
%Avance Meta 3 (UT ITAC) 100%
%Avance Proyecto (UT ITAC) 100%

Tabla 8 – Avances adecuación del nodo


4.6. PERMISOS USO DE INFRAESTRUCTURA

En cuanto a la gestión de la solicitud de permisos, estos se han hecho a UFINET,


entregando toda la documentación necesaria para realizar dicho trámite.

A continuación, se relaciona el estado de radicación de permisos, cabe aclarar que en el


caso de los permisos condicionados otorgados por UFINET, dicho permiso se nos entrega
con el compromiso por parte de la UT ITAC de acatar las recomendaciones y directrices de
UFINET en cuanto al uso de la postería de un municipio en particular. Una vez construida
la red de fibra óptica del municipio, UFINET procede a validar en terreno el cumplimiento de
los pactado en permiso condicionado y si constata que cumplimos nos entrega el permiso
definitivo.

Todos los permisos de uso de infraestructura están emitidos por parte de UFINET y con esto
logramos los permisos definitivos de la totalidad de los 47 municipios, cumpliendo al 100%
con este compromiso.
Uso infraestructura Pública

Departamento Municipio
ESTADO
ENTIDAD (Aprobado / En trámite /
Subsanación)

BOLIVAR ALTOS DEL ROSARIO UFINET APROBADO


BOLIVAR ARENAL UFINET APROBADO
BOLIVAR ARROYOHONDO UFINET APROBADO
CORDOBA AYAPEL UFINET APROBADO
BOLIVAR BARRANCO DE LOBA UFINET APROBADO
CORDOBA BUENAVISTA UFINET APROBADO
BOLIVAR CALAMAR UFINET APROBADO
CORDOBA CHINU UFINET APROBADO
BOLIVAR CICUCO UFINET APROBADO
BOLIVAR CLEMENCIA UFINET APROBADO
SUCRE GALERAS UFINET APROBADO
CORDOBA LA APARTADA UFINET APROBADO
SUCRE LA UNION UFINET APROBADO
SUCRE LOS PALMITOS UFINET APROBADO
BOLIVAR MAHATES UFINET APROBADO
SUCRE MAJAGUAL UFINET APROBADO
BOLIVAR MARIA LA BAJA UFINET APROBADO
CORDOBA MOMIL UFINET APROBADO
CORDOBA MOÑITOS UFINET APROBADO
BOLIVAR MONTECRISTO UFINET APROBADO
BOLIVAR MORALES CENS APROBADO
SUCRE OVEJAS UFINET APROBADO
CORDOBA PUEBLO NUEVO UFINET APROBADO
CORDOBA PURISIMA UFINET APROBADO
BOLIVAR RIO VIEJO UFINET APROBADO
SUCRE SAMPUES UFINET APROBADO
CORDOBA SAN ANTERO ALCADIA APROBADO
SUCRE SAN BENITO ABAD UFINET APROBADO
BOLIVAR SAN CRISTOBAL UFINET APROBADO
BOLIVAR SAN ESTANISLAO UFINET APROBADO
BOLIVAR SAN JACINTO UFINET APROBADO
CORDOBA SAN JOSE DE URE UFINET APROBADO
SUCRE SAN JUAN DE BETULIA UFINET APROBADO
BOLIVAR SAN MARTIN DE LOBA UFINET APROBADO
BOLIVAR SAN PABLO ESSA APROBADO
SUCRE SAN PEDRO UFINET APROBADO
BOLIVAR SANTA ROSA DEL SUR UFINET APROBADO
BOLIVAR SIMITI UFINET APROBADO
BOLIVAR SOPLAVIENTO UFINET APROBADO
BOLIVAR TALAIGUA NUEVO UFINET APROBADO
CORDOBA TIERRALTA UFINET APROBADO
BOLIVAR TIQUISIO UFINET APROBADO
SUCRE TOLU VIEJO UFINET APROBADO
CORDOBA TUCHIN UFINET APROBADO
CORDOBA VALENCIA UFINET APROBADO
BOLIVAR VILLANUEVA UFINET APROBADO
BOLIVAR ZAMBRANO UFINET APROBADO

Tabla 9 – Estado solicitud de permisos


En el ANEXO 6 – LICENCIAS Y PERMISOS MATRIZ se encuentra el estado de las licencias
y permisos y en el ANEXO 7 - PERMISOS se adjuntan los documentos PDF de los
municipios con los permisos, con esto logramos los permisos definitivos de la totalidad de
los 47 municipios, cumpliendo al 100% con este compromiso.
En el ANEXO 8 – CERTIFICADOS RETIE se encuentran la totalidad de los certificados
RETIE los cuales se gestionaron a través de la compañía SYGENERGY logrando los
certificados en la totalidad de los 47 municipios y cumpliendo al 100% este compromiso.

4.7. CONSTRUCCIÓN E INSTALACIÓN

CORE
El CORE ya se encuentra instalado, configurado y operando al cien por ciento.

CONSTRUCCIÓN DE NODOS
Constituye la construcción de las adecuaciones físicas de los nodos, adecuaciones
eléctricas, canaletas y acometidas para el ingreso de la fibra óptica.

Se relaciona el resumen de la ejecución, la cual se encuentra al 100% en los 47


municipios:
Adecuación NODO / S.
Puesta en servicio NODO
Eléctrico

1 Municipios PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN

META 1 2 LA APARTADA 7/31/2020 100% 8/8/2020 100%

META 1 3 BUENAVISTA 7/31/2020 100% 8/8/2020 100%

META 1 4 SAN JOSE DE URE 7/31/2020 100% 8/8/2020 100%

META 1 5 AYAPEL 8/22/2020 100% 8/29/2020 100%

META 1 6 ALTOS DEL ROSARIO 7/31/2020 100% 8/8/2020 100%

META 1 7 BARRANCO DE LOBA 8/8/2020 100% 8/15/2020 100%

META 2 8 TIERRALTA 9/12/2020 100% 9/12/2020 100%

META 2 9 MARIA LA BAJA 10/10/2020 100% 10/10/2020 100%

META 2 10 MAJAGUAL 9/19/2020 100% 9/19/2020 100%

META 2 11 MOÑITOS 9/30/2020 100% 9/30/2020 100%

META 2 12 TOLU VIEJO 9/30/2020 100% 9/30/2020 100%

META 2 13 CHINU 9/30/2020 100% 9/30/2020 100%

META 2 14 OVEJAS 9/19/2020 100% 9/19/2020 100%

META 2 16 MOMIL 10/31/2020 100% 10/31/2020 100%

META 2 17 CICUCO 10/19/2020 100% 10/19/2020 100%

META 2 18 LOS PALMITOS 9/12/2020 100% 9/12/2020 100%

META 2 23 SAN BENITO ABAD 10/17/2020 100% 10/17/2020 100%

META 2 24 SAN ANTERO 9/12/2020 100% 9/12/2020 100%

META 2 25 VILLANUEVA 10/24/2020 100% 10/24/2020 100%

META 2 26 SAMPUES 10/7/2020 100% 10/7/2020 100%

META 2 27 SAN ESTANISLAO 11/7/2020 100% 11/7/2020 100%

META 2 28 ZAMBRANO 11/16/2020 100% 11/16/2020 100%

META 2 30 SOPLAVIENTO 10/7/2020 100% 10/7/2020 100%

META 3 42 ARENAL 11/14/2020 100% 11/14/2020 100%

META 2 31 SAN CRISTOBAL 10/10/2020 100% 10/10/2020 100%

META 3 32 SIMITI 1/16/2021 100% 1/16/2021 100%

META 3 33 RIO VIEJO 11/21/2021 100% 11/21/2021 100%

META 3 34 SAN PABLO 11/30/2020 100% 11/30/2020 100%

META 3 35 PUEBLO NUEVO 12/5/2020 100% 12/5/2020 100%

META 3 36 SANTA ROSA DEL SUR 1/7/2021 100% 1/7/2021 100%

META 3 37 GALERAS 12/31/2020 100% 12/31/2020 100%

META 3 38 MONTECRISTO 12/31/2020 100% 12/31/2020 100%

META 3 39 SAN MARTIN DE LOBA 1/25/2021 100% 1/25/2021 100%

META 3 40 TIQUISIO 1/25/2021 100% 1/25/2021 100%

META 3 41 MORALES 11/21/2020 100% 11/21/2020 100%

META 3 43 SAN JACINTO 12/12/2020 100% 12/12/2020 100%

META 3 44 VALENCIA 12/19/2020 100% 12/19/2020 100%

META 3 45 CALAMAR 1/9/2021 100% 1/9/2021 100%

META 3 46 SAN PEDRO 1/16/2021 100% 1/16/2021 100%

META 3 47 ARROYOHONDO 1/23/2021 100% 1/23/2021 100%

META 3 15 MAHATES 12/30/2020 100% 12/30/2020 100%

META 3 19 LA UNION 12/7/2020 100% 12/7/2020 100%

META 3 20 TUCHIN 12/7/2020 100% 12/7/2020 100%

META 3 21 SAN JUAN DE BETULIA 12/30/2020 100% 12/30/2020 100%

META 3 22 PURISIMA 12/7/2020 100% 12/7/2020 100%

META 3 29 CLEMENCIA 11/23/2020 100% 11/23/2020 100%

META 3 48 TALAIGUA NUEVO 1/23/2021 100% 1/23/2021 100%


%Avance Meta 1 (UT ITAC) 100% 100%
%Avance Meta 2 (UT ITAC) 100% 100%
%Avance Meta 3 (UT ITAC) 100% 100%
%Avance Proyecto (UT ITAC) 100% 100%

Tabla 10 – Avances construcción de nodos


4.8. AVANCES DE LAS METAS DE INSTALACIÓN Y OPERACIÓN

En el Comité Operativo No. 7 del 16/JUL/2020 mediante Acta No. 15-UTITAC se autorizó
realizar ajustes al Plan de Instalación y Operación presentado el 30/MAR/2020 en razón a
las dificultades para viabilizar los municipios cuya entrega de capacidad depende de Azteca
Comunicaciones. Por tal motivo, nos vimos obligados a reemplazar dichos municipios por
nuevos municipios cuya capacidad es suministrada por UFINET. Dicho ajuste al plan fue
presentado mediante comunicación PIO-UTITAC-C&M-030-2020 y radicado MINTIC
201041480 el día 24/JUL/2020 en donde en particular los Anexos ajustados corresponden
al ANEXO No. 4 - PROGRAMACIÓN POR FASES INSTALACIÓN AJUSTADO y el ANEXO
No. 5 - PLAN DE COMERCIALIZACION AJUSTADO.
En el siguiente cuadro se evidencia la ejecución de todas las actividades al 100% en los 47
municipios:

Puesta servicio Sist. Puesta en servicio Sist. Adecuación NODO / S. Conexión proveedor Conexión red Transporte Instalación Red
Diseño Red Permisos Instalación Adecuacion NOC Puesta en servicio NODO
Informacion Gestión Eléctrico Internet / Core Distribución

1 Municipios 1 EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN

META 1 2 LA APARTADA 4/07/2020 100% 22/08/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%

META 1 3 BUENAVISTA 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%

META 1 4 SAN JOSE DE URE 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%

META 1 5 AYAPEL 18/07/2020 100% 5/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 22/08/2020 100% 29/08/2020 100% 29/08/2020 100% 31/07/2020 100% 12/09/2020 100%

META 1 6 ALTOS DEL ROSARIO 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%

META 1 7 BARRANCO DE LOBA 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 15/08/2020 100% 15/08/2020 100% 31/07/2020 100% 22/08/2020 100%

META 2 8 TIERRALTA 8/08/2020 100% 12/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 18/09/2020 100% 31/07/2020 100% 7/11/2020 100%

META 2 9 MARIA LA BAJA 15/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 10/10/2020 100% 10/10/2020 100% 17/10/2020 100% 31/07/2020 100% 21/11/2020 100%

META 2 10 MAJAGUAL 31/07/2020 100% 30/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/09/2020 100% 19/09/2020 100% 30/09/2020 100% 31/07/2020 100% 17/10/2020 100%

META 2 11 MOÑITOS 8/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 10/10/2020 100% 31/07/2020 100% 24/10/2020 100%

META 2 12 TOLU VIEJO 8/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 10/10/2020 100% 31/07/2020 100% 24/10/2020 100%

META 2 13 CHINU 5/09/2020 100% 31/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 31/10/2020 100% 31/07/2020 100% 31/10/2020 100%

META 2 14 OVEJAS 8/08/2020 100% 30/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/09/2020 100% 19/09/2020 100% 30/09/2020 100% 31/07/2020 100% 17/10/2020 100%

META 2 16 MOMIL 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/10/2020 100% 31/10/2020 100% 7/11/2020 100% 31/07/2020 100% 21/11/2020 100%

META 2 17 CICUCO 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/10/2020 100% 19/10/2020 100% 7/11/2020 100% 31/07/2020 100% 21/11/2020 100%

META 2 18 LOS PALMITOS 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 7/11/2020 100% 31/07/2020 100% 10/10/2020 100%

META 2 23 SAN BENITO ABAD 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 17/10/2020 100% 17/10/2020 100% 14/11/2020 100% 31/07/2020 100% 31/10/2020 100%

META 2 24 SAN ANTERO 29/08/2020 100% 24/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 24/10/2020 100% 31/07/2020 100% 10/10/2020 100%

META 2 25 VILLANUEVA 5/09/2020 100% 31/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 24/10/2020 100% 24/10/2020 100% 31/10/2020 100% 31/07/2020 100% 30/09/2020 100%

META 2 26 SAMPUES 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/10/2020 100% 7/10/2020 100% 14/11/2020 100% 31/07/2020 100% 30/09/2020 100%

META 2 27 SAN ESTANISLAO 30/09/2020 100% 21/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/11/2020 100% 7/11/2020 100% 21/11/2020 100% 31/07/2020 100% 14/11/2020 100%

META 2 28 ZAMBRANO 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/11/2020 100% 16/11/2020 100% 20/11/2020 100% 31/07/2020 100% 22/11/2020 100%

META 2 30 SOPLAVIENTO 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/10/2020 100% 7/10/2020 100% 14/11/2020 100% 31/07/2020 100% 30/11/2020 100%

META 3 42 ARENAL 5/12/2020 100% 6/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 14/11/2020 100% 14/11/2020 100% 20/11/2020 100% 31/07/2020 100% 21/11/2020 100%

META 2 31 SAN CRISTOBAL 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 10/10/2020 100% 10/10/2020 100% 14/11/2020 100% 31/07/2020 100% 31/10/2020 100%

META 3 32 SIMITI 21/11/2020 100% 16/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/01/2021 100% 16/01/2021 100% 23/01/2021 100% 31/07/2020 100% 23/01/2021 100%

META 3 33 RIO VIEJO 14/11/2020 100% 16/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 21/11/2021 100% 21/11/2021 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%

META 3 34 SAN PABLO 30/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/11/2020 100% 30/11/2020 100% 9/01/2021 100% 31/07/2020 100% 9/01/2021 100%

META 3 35 PUEBLO NUEVO 24/10/2020 100% 5/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 5/12/2020 100% 5/12/2020 100% 9/01/2021 100% 31/07/2020 100% 31/12/2020 100%

META 3 36 SANTA ROSA DEL SUR 30/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/01/2021 100% 7/01/2021 100% 30/12/2020 100% 31/07/2020 100% 19/12/2020 100%

META 3 37 GALERAS 7/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/12/2020 100% 31/12/2020 100% 15/01/2021 100% 31/07/2020 100% 16/01/2021 100%

META 3 38 MONTECRISTO 7/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/12/2020 100% 31/12/2020 100% 15/01/2021 100% 31/07/2020 100% 16/01/2021 100%

META 3 39 SAN MARTIN DE LOBA 7/11/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 25/01/2021 100% 25/01/2021 100% 27/01/2021 100% 31/07/2020 100% 23/01/2021 100%

META 3 40 TIQUISIO 24/10/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 25/01/2021 100% 25/01/2021 100% 27/01/2021 100% 31/07/2020 100% 23/01/2021 100%

META 3 41 MORALES 12/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 21/11/2020 100% 21/11/2020 100% 4/12/2020 100% 31/07/2020 100% 30/11/2020 100%

META 3 43 SAN JACINTO 31/10/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/12/2020 100% 12/12/2020 100% 11/12/2020 100% 31/07/2020 100% 31/12/2020 100%

META 3 44 VALENCIA 31/10/2020 100% 19/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/12/2020 100% 19/12/2020 100% 4/12/2020 100% 31/07/2020 100% 19/12/2020 100%

META 3 45 CALAMAR 14/11/2020 100% 31/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 9/01/2021 100% 9/01/2021 100% 15/01/2021 100% 31/07/2020 100% 23/01/2021 100%

META 3 46 SAN PEDRO 21/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/01/2021 100% 16/01/2021 100% 27/01/2021 100% 31/07/2020 100% 30/01/2021 100%

META 3 47 ARROYOHONDO 5/12/2020 100% 23/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/01/2021 100% 23/01/2021 100% 11/02/2021 100% 31/07/2020 100% 13/02/2021 100%

META 3 15 MAHATES 22/08/2020 100% 17/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/12/2020 100% 30/12/2020 100% 9/01/2021 100% 31/07/2020 100% 9/01/2021 100%

META 3 19 LA UNION 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%

META 3 20 TUCHIN 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 4/12/2020 100% 31/07/2020 100% 5/12/2020 100%

META 3 21 SAN JUAN DE BETULIA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/12/2020 100% 30/12/2020 100% 30/12/2020 100% 31/07/2020 100% 31/12/2020 100%

META 3 22 PURISIMA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%

META 3 29 CLEMENCIA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/11/2020 100% 23/11/2020 100% 28/11/2020 100% 31/07/2020 100% 30/11/2020 100%

META 3 48 TALAIGUA NUEVO 19/12/2020 100% 6/02/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/01/2021 100% 23/01/2021 100% 27/01/2021 100% 31/07/2020 100% 30/01/2021 100%
%Avance Meta 1 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 2 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 3 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Proyecto (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

Tabla 11 – Avance metas de instalación y operación


A continuación, se presenta la distribución por municipios de los 15.058 accesos y de los
753 accesos adicionales, para un total de 15.811 accesos instalados, con lo cual se dio
cumplimiento al 100% de las instalaciones de Meta1, Meta y Meta 3:
TOTAL
DEPARTAMENTO MUNICIPIO META 1 META 2 META 3 TOTAL ADICIONALES
CONTRATO
BOLIVAR ALTOS DEL ROSARIO 258 1 259 236 23
BOLIVAR ARENAL 152 4 156 148 8
BOLIVAR ARROYOHONDO 186 186 184 2
CORDOBA AYAPEL 210 557 11 778 741 37
BOLIVAR BARRANCO DE LOBA 224 224 173 51
CORDOBA BUENAVISTA 196 9 205 191 14
BOLIVAR CALAMAR 361 361 360 1
CORDOBA CHINU 534 143 677 647 30
BOLIVAR CICUCO 179 29 208 199 9
BOLIVAR CLEMENCIA 163 89 252 240 12
SUCRE GALERAS 343 343 340 3
CORDOBA LA APARTADA 531 18 3 552 362 190
SUCRE LA UNION 174 174 165 9
SUCRE LOS PALMITOS 205 1 206 196 10
BOLIVAR MAHATES 270 270 267 3
SUCRE MAJAGUAL 254 12 266 251 15
BOLIVAR MARIA LA BAJA 586 586 579 7
CORDOBA MOMIL 223 223 212 11
BOLIVAR MONTECRISTO 324 324 322 2
CORDOBA MOÑITOS 163 4 167 159 8
BOLIVAR MORALES 170 170 161 9
SUCRE OVEJAS 325 1 326 310 16
CORDOBA PUEBLO NUEVO 431 431 423 8
CORDOBA PURISIMA 45 102 147 140 7
BOLIVAR RIO VIEJO 290 290 276 14
SUCRE SAMPUES 491 491 467 24
CORDOBA SAN ANTERO 509 509 484 25
SUCRE SAN BENITO ABAD 143 1 144 136 8
BOLIVAR SAN CRISTOBAL 150 2 152 148 4
BOLIVAR SAN ESTANISLAO 304 15 319 318 1
BOLIVAR SAN JACINTO 546 546 543 3
CORDOBA SAN JOSE DE URE 163 28 1 192 154 38
SUCRE SAN JUAN DE BETULIA 143 143 142 1
BOLIVAR SAN MARTIN DE LOBA 220 220 209 11
BOLIVAR SAN PABLO 845 845 841 4
SUCRE SAN PEDRO 244 244 241 3
BOLIVAR SANTA ROSA DEL SUR 687 687 684 3
BOLIVAR SIMITÍ 295 295 292 3
BOLIVAR SOPLAVIENTO 222 3 225 214 11
BOLIVAR TALAIGUA NUEVO 143 143 142 1
CORDOBA TIERRALTA 873 445 1.318 1.255 63
BOLIVAR TIQUISIO 178 178 175 3
SUCRE TOLU VIEJO 122 2 124 118 6
CORDOBA TUCHIN 161 161 148 13
CORDOBA VALENCIA 373 373 369 4
BOLIVAR VILLANUEVA 436 1 437 415 22
BOLIVAR ZAMBRANO 218 66 284 281 3
TOTAL 1.582 6.324 7.905 15.811 15.058 753

Tabla 12 –Total de accesos instalados


A continuación, se presentan resumen de la totalidad de los permisos aprobados en cada
uno de los 47 municipios:

Uso infraestructura Pública

Departamento Municipio
ESTADO
ENTIDAD (Aprobado / En trámite /
Subsanación)

BOLIVAR ALTOS DEL ROSARIO UFINET APROBADO


BOLIVAR ARENAL UFINET APROBADO
BOLIVAR ARROYOHONDO UFINET APROBADO
CORDOBA AYAPEL UFINET APROBADO
BOLIVAR BARRANCO DE LOBA UFINET APROBADO
CORDOBA BUENAVISTA UFINET APROBADO
BOLIVAR CALAMAR UFINET APROBADO
CORDOBA CHINU UFINET APROBADO
BOLIVAR CICUCO UFINET APROBADO
BOLIVAR CLEMENCIA UFINET APROBADO
SUCRE GALERAS UFINET APROBADO
CORDOBA LA APARTADA UFINET APROBADO
SUCRE LA UNION UFINET APROBADO
SUCRE LOS PALMITOS UFINET APROBADO
BOLIVAR MAHATES UFINET APROBADO
SUCRE MAJAGUAL UFINET APROBADO
BOLIVAR MARIA LA BAJA UFINET APROBADO
CORDOBA MOMIL UFINET APROBADO
CORDOBA MOÑITOS UFINET APROBADO
BOLIVAR MONTECRISTO UFINET APROBADO
BOLIVAR MORALES CENS APROBADO
SUCRE OVEJAS UFINET APROBADO
CORDOBA PUEBLO NUEVO UFINET APROBADO
CORDOBA PURISIMA UFINET APROBADO
BOLIVAR RIO VIEJO UFINET APROBADO
SUCRE SAMPUES UFINET APROBADO
CORDOBA SAN ANTERO ALCADIA APROBADO
SUCRE SAN BENITO ABAD UFINET APROBADO
BOLIVAR SAN CRISTOBAL UFINET APROBADO
BOLIVAR SAN ESTANISLAO UFINET APROBADO
BOLIVAR SAN JACINTO UFINET APROBADO
CORDOBA SAN JOSE DE URE UFINET APROBADO
SUCRE SAN JUAN DE BETULIA UFINET APROBADO
BOLIVAR SAN MARTIN DE LOBA UFINET APROBADO
BOLIVAR SAN PABLO ESSA APROBADO
SUCRE SAN PEDRO UFINET APROBADO
BOLIVAR SANTA ROSA DEL SUR UFINET APROBADO
BOLIVAR SIMITI UFINET APROBADO
BOLIVAR SOPLAVIENTO UFINET APROBADO
BOLIVAR TALAIGUA NUEVO UFINET APROBADO
CORDOBA TIERRALTA UFINET APROBADO
BOLIVAR TIQUISIO UFINET APROBADO
SUCRE TOLU VIEJO UFINET APROBADO
CORDOBA TUCHIN UFINET APROBADO
CORDOBA VALENCIA UFINET APROBADO
BOLIVAR VILLANUEVA UFINET APROBADO
BOLIVAR ZAMBRANO UFINET APROBADO

Tabla 13 – Estado solicitud de permisos


4.9. SISTEMA DE GESTION DE LA INFORMACION

El día 12 de marzo mediante comunicado PIO-UTITAC-MINTIC-003-20 Rad. Mintic


201006381 Rad. Interventoría 2020-364-142833-2 se presentó la información de la
concertación de campos del sistema de información.
Durante el mes de marzo la Unión Temporal ITAC elaboró el plan de implementación del
Sistema de Información y conforme lo acordado en el Acta de No. 2-UTITAC dicho plan de
implementación del sistema de información se incluyó como el Capítulo 7 del Plan de
Implementación y Puesta en Servicio el cual se entregó con el comunicado PIO-UTITAC-
DIRINFRA-017-2020 y número de radicado MINTIC 201016474, radicado interventoría
2020-364-144451-2.
El documento presentó observaciones y se notificaron por parte de la Interventoría con RM
201019191 del 15-04-2020 con subsanaciones presentadas con el comunicado PIO-
UTITAC-C&M-005-20 RM 201020543 del 22-04-2020 por correo electrónico, radicado
Interventoría 20203641451352. Se desarrolló reunión el 30-04-2020 y se documentó
mediante acta 8 UTITAC con el objeto de socializar las observaciones, se entregó el alcance
por correo electrónico del 11-05-2020.
Se entrega el plan de sistemas de información el 29/03/2020 mediante radicado Rad MINTIC
201016474 y el 28 05 2020 la interventoría emitió concepto de cumplimiento mediante el
oficio PIO C&M UTITAC 430 20 20203640897271 MinTIC 201027852.
Se recibe requerimiento PIO-C&M-UTITAC-526-20 con radicado 201035249 del 2-jul-2020,
con el cual la interventoría solicita las credenciales de acceso al sistema, el cual fue
respondido mediante comunicado PIO-UTITAC-C&M-023-2020 con radicado 201035858
del 3-jul-2020, con el cual el UT ITAC entregó el acceso al mismo. Se recibió el comunicado
PIO-C&M-UTITAC-678-20 en el cual la Interventoría informó la lista de chequeo que se
aplicó al sistema de información.
Mediante comunicado PIO-C&M-UTITAC-1917-21 del 28/01/2021 con radicado
20213640944291 la interventoría emite concepto de Cumplimiento del sistema de
información, conforme lo concertado mediante el acta No. 1-ITAC del 22/01/2020 y la
aprobación de la concertación de campos por parte de la Entidad Contratante emitida por
medio del comunicado PIO-DIRINFRA-UTITAC-09-20 – (20203211441892) RM 202023308
del 16/03/2020.
Mediante comunicado PIO-C&M-UTITAC-4056-21 del 30/11/2021 con radicado
20213641050051 la interventoría envía observaciones en la LISTA DE CHEQUEO NO. 15
APLICADA AL SISTEMA DE INFORMACIÓN, las cuales fueron subsanadas por UT ITAC
mediante comunicado PIO-UTITAC-C&M-255-2021 del 15/12/2021 con radicado MINTIC
211102045 y radicado interventoría 20213211641732.
Se realizaron actualizaciones de los módulos de: gestión documental, indicadores y PQRs.
4.10. INDICADORES DEL PROYECTO

Los soportes de los indicadores se encuentran en el Anexo 9 – Indicadores.

DISPONIBILIDAD OLT
A continuación, se presenta el indicador de disponibilidad de los 47 municipios en
el mes diciembre 2021.

Para medir la disponibilidad del servicio de conectividad en la OLT en cada uno de


los 47 municipios, se utiliza la siguiente ecuación, acorde a lo definido en la
resolución de la CRC 5078 de 2016 numeral 5.2-A Literal B. CÁLCULO DE
INDICADORES TÉCNICOS DE DISPONIBILIDAD DE LA RED:

𝑇𝑖𝑒𝑚𝑝𝑜 𝑇𝑜𝑡𝑎𝑙 𝑑𝑒 𝐼𝑛𝑑𝑖𝑠𝑝𝑜𝑛𝑖𝑏𝑖𝑙𝑖𝑑𝑎𝑑 (𝑚𝑖𝑛)


%𝐷𝑖𝑠𝑝. 𝑒𝑙𝑒𝑚𝑒𝑛𝑡𝑜𝑑𝑒 𝑟𝑒𝑑 = (1 − ) × 100%
𝑇𝑖𝑒𝑚𝑝𝑜 𝑡𝑜𝑡𝑎𝑙 𝑑𝑒𝑙 𝑝𝑒𝑟𝑖𝑜𝑑𝑜 (𝑚𝑖𝑛)
Municipios Disponibilidad OLT Valor objetivo CUMPLE
Altos del rosario 100% 99,80% SI
Ayapel 100% 99,80% SI
Barranco de loba 100% 99,80% SI
Buenavista 100% 99,80% SI
La apartada 100% 99,80% SI
San Jose de Ure 100% 99,80% SI
Arenal 100% 99,80% SI
Chinu 100% 99,80% SI
Cicuco 100% 99,80% SI
Clemencia 100% 99,80% SI
Los palmitos 100% 99,80% SI
Mahates 100% 99,80% SI
Majagual 100% 99,80% SI
Momil 100% 99,80% SI
Moñitos 100% 99,80% SI
Ovejas 100% 99,80% SI
Purisima 100% 99,80% SI
Sampues 100% 99,80% SI
San antero 100% 99,80% SI
San Benito abad 100% 99,80% SI
San Cristobal 100% 99,80% SI
San estanislao 100% 99,80% SI
Soplaviento 100% 99,80% SI
Tierralta 100% 99,80% SI
Toluviejo 100% 99,80% SI
Villanueva 100% 99,80% SI
Zambrano 100% 99,80% SI
Arroyohondo 100% 99,80% SI
Calamar 100% 99,80% SI
Galeras 100% 99,80% SI
la Union 100% 99,80% SI
Maria la Baja 100% 99,80% SI
Montecristo 100% 99,80% SI
Morales 100% 99,80% SI
Pueblo nuevo 100% 99,80% SI
Rio Viejo 100% 99,80% SI
San Jaciento 100% 99,80% SI
San Juan de Betulia 100% 99,80% SI
San Martin de Loba 100% 99,80% SI
San Pablo 100% 99,80% SI
San Pedro 100% 99,80% SI
Santa Rosa del Sur 100% 99,80% SI
Simiti 100% 99,80% SI
Talaigua Nuevo 100% 99,80% SI
Tiquisio 100% 99,80% SI
Tuchin 100% 99,80% SI
Valencia 100% 99,80% SI

Tabla 14 – Disponibilidad OLT diciembre 2021


DISPONIBILIDAD CORE
A continuación, se presenta el indicador de disponibilidad del CORE en el mes de
diciembre de 2021.
Para medir la disponibilidad en el CORE, se utilizado la siguiente ecuación, acorde
a lo definido en la resolución de la CRC 5078 de 2016 numeral 5.2-A Literal B.
CÁLCULO DE INDICADORES TÉCNICOS DE DISPONIBILIDAD DE LA RED:

𝑇𝑖𝑒𝑚𝑝𝑜 𝑇𝑜𝑡𝑎𝑙 𝑑𝑒 𝐼𝑛𝑑𝑖𝑠𝑝𝑜𝑛𝑖𝑏𝑖𝑙𝑖𝑑𝑎𝑑 (𝑚𝑖𝑛)


%𝐷𝑖𝑠𝑝. 𝑒𝑙𝑒𝑚𝑒𝑛𝑡𝑜𝑑𝑒 𝑟𝑒𝑑 = (1 − ) × 100%
𝑇𝑖𝑒𝑚𝑝𝑜 𝑡𝑜𝑡𝑎𝑙 𝑑𝑒𝑙 𝑝𝑒𝑟𝑖𝑜𝑑𝑜 (𝑚𝑖𝑛)

Disponibilidad
Municipios CORE Valor objetivo CUMPLE

Bogota (Jupiter) 100% 99,99% SI

Tabla 15 – Disponibilidad CORE diciembre 2021

VELOCIDAD DE NAVEGACION
A continuación, se presenta el indicador de velocidad de navegación de bajada y
de subida promedio en los 47 municipios del mes de diciembre de 2021.
Velocidad Velocidad subida
Municipios CUMPLE
bajada(Mbps) (Mbps)
Altos del rosario 1224,33 5225,16 SI
Ayapel 1224,98 5224,87 SI
Barranco de loba 1225,68 5224,97 SI
Buenavista 1224,67 5224,28 SI
La apartada 1224,98 5225,32 SI
San Jose de Ure 1224,74 5226,04 SI
Arenal 1224,74 5224,48 SI
Chinu 1224,16 5224,67 SI
Cicuco 1224,16 5224,16 SI
Clemencia 1225,22 5224,79 SI
Los palmitos 1225,24 5224,78 SI
Mahates 1224,71 5224,38 SI
Majagual 1224,17 5224,14 SI
Momil 1224,94 5225,38 SI
Monitos 1225,30 5224,22 SI
Ovejas 1224,61 5224,65 SI
Purisima 1224,60 5225,65 SI
Sampues 1225,75 5224,26 SI
San antero 1224,77 5225,05 SI
San Benito abad 1225,18 5225,47 SI
San Cristobal 1224,69 5225,48 SI
San estanislao 1224,39 5225,37 SI
Soplaviento 1225,23 5225,35 SI
Tierralta 1224,82 5224,91 SI
Toluviejo 1224,99 5225,42 SI
Villanueva 1224,44 5224,45 SI
Zambrano 1224,96 5225,24 SI
Arroyohondo 1225,33 5225,26 SI
Calamar 1225,65 5224,67 SI
Galeras 1224,77 5225,49 SI
la Union 1225,74 5224,79 SI
Maria la Baja 1225,06 5225,22 SI
Montecristo 1225,21 5224,67 SI
Morales 1224,32 5225,00 SI
Pueblo nuevo 1225,91 5224,91 SI
Rio Viejo 1224,59 5224,80 SI
San Jacinto 1225,27 5224,69 SI
San Juan de Betulia 1224,38 5225,75 SI
San Martin de Loba 1223,61 5225,41 SI
San Pablo 1225,10 5224,91 SI
San Pedro 1225,52 5224,92 SI
Santa Rosa del Sur 1224,58 5225,38 SI
Simiti 1224,29 5224,71 SI
Talaigua Nuevo 1225,92 5225,84 SI
Tiquisio 1224,15 5225,62 SI
Tuchin 1225,07 5226,21 SI
Valencia 1224,55 5225,66 SI

Tabla 16 - Velocidad promedio de navegación diciembre 2021


CALIDAD EN LA ATENCION AL USUARIO

A continuación, se presenta el indicador de calidad de atención para los 47


municipios en el mes de diciembre de 2021.

Llamadas Promedio
RED Llamadas exitosas CUMPLE
abandonadas respuesta
95,580% 4,420% 13,62 seg SI
Valor objetivo 95,000% 5,000% 30 seg

Tabla 17 – Calidad de Atención de diciembre 2021

ACCESOS ACTIVOS
A continuación, se presenta el indicador accesos activos en los municipios
aprobados en el mes de diciembre de 2021.

Porcentaje
Indicador Meta Usuarios
usuarios activos
Usuarios activos 15.811 15.811 100%
Tabla 18 – Accesos Activos en diciembre 2021
5. ACTIVIDADES FINANCIERAS

• Plan de Inversión del Anticipo: El 22 de enero de 2020 se presentó para


revisión y aprobación el Plan de inversión y manejo del anticipo mediante
comunicado con radicado MINTIC 201003059, y el 28 de enero de 2020 se
presentó la versión final atendiendo las observaciones de la Interventoría
mediante comunicado con radicado MINTIC 201004246.
El 31 de enero de 2020 con el comunicado PIO-MINTIC-C&M-025-20 la
Interventoría emitió concepto de favorabilidad y recomendó la aprobación del
Plan de inversión y manejo del anticipo.
El 24 de febrero de 2020 la Dirección de Infraestructura con comunicado PIO-
DIRINFRA-UTITAC-05-2020, radicado No. 202014189, acogiendo la
recomendación de la Interventoría aprobó el plan de inversión del anticipo.

• Con la aprobación de las órdenes de pago 001, 002, 003, 005, 007 y 008 por
$11.018.850.024 incluido el GMF se ha ejecutado recursos del anticipo
equivalentes al 100%.
• Con la aprobación de las órdenes de pago 004, 005, 006, 007, 008, 009, 010,
011, 012, 013 y 014 se han legalizado recursos por un total de
$35.378.939.953 valor que incluye el anticipo y los recursos de la segunda,
tercera y cuarta utilización.
• El 18 de septiembre se presentó la orden de pago 015 correspondiente a
computadores para el NOC por $32.571.999, la Interventoría presentó
observaciones el 27 de septiembre las cuales están en proceso de revisión
para dar respuesta.
• El 8 de octubre se radico las órdenes de pago 016 y 017 correspondiente a
los recursos de opex asociados a la quinta y sexta utilización para revisión
de la Interventoría, el día 20 de octubre se radicó en dos memorias las
facturas que soportan estas órdenes, las cuales se encuentran en proceso
de revisión por parte de la Interventoría y se unifico el cobro del opex en la
orden de pago 016.
El día 13 de diciembre teniendo en cuenta que la quinta utilización de opex
no presentaba observaciones se modificó la orden para cobrar estos recursos
y se dio respuesta a las observaciones, esta orden fue aprobada por la
Interventoría el 20 de diciembre.
• El día 16 de noviembre se presentó la orden de pago 017 correspondiente al
cobro del sistema de información por $850.850.000 a nombre de Anditel SAS,
la Interventoría presento observaciones el día 24 de noviembre, las cuales
se respondieron los días 7 y 21 de diciembre, a la fecha de presentación de
este informe las respuestas ya fueron validadas por la Interventoría y se
encuentra en proceso de firma y radicación ante la Fiduciaria.
• El día 27 de septiembre mediante comunicado PIO-UTITAC-DIRINFRA-091-
2021 radicado Mintic 211079167 y C&M 20213211578352 se presentó la
documentación para el trámite del séptimo desembolso equivalente a
$1.806.960.000, los cuales fueron desembolsados a la Fiduciaria el 21 de
noviembre.

• Los días 17 y 21 de diciembre mediante comunicados PIO-UTITAC-


DIRINFRA-102-2021 y PIO-UTITAC-DIRINFRA-103-2021 radicados Mintic
211102622 y 211103497, y C&M 20213211643932 y 20213211647032 se
presentó la documentación para el trámite del octavo desembolso a la fecha
de presentación de este informe los recursos no han sido desembolsados a
la Fiduciaria.
• Marzo de 2020 fue un mes histórico para el mundo y para los mercados de
capitales que presentaron altas desvalorizaciones originadas en diferentes
factores como la explosiva dispersión del Covid-19 en el mundo generó un
estado de emergencia global, la reacción inmediata de parte de los gobiernos
y los bancos centrales fue el recorte de las tasas de interés, políticas
monetarias para apoyar la liquidez de los mercados y amplios paquetes
fiscales para apoyar a las empresas y a las personas ampliamente
perjudicadas con el paro de la actividad económica. Adicionalmente, el
desacuerdo entre Rusia y los miembros de la OPEP acerca de los futuros
recortes de producción para estabilizar el precio del crudo ocasionó un fuerte
desplome en los precios del petróleo en el mes que profundizó la aversión al
riesgo a nivel mundial.

• Como consecuencia, los portafolios de inversión presentaron altas


desvalorizaciones, En seguimiento al comportamiento del mercado respecto de la
rentabilidad de los fondos de inversión en el que se identificó que durante el mes
de marzo se mantenía la tendencia de desvalorización, el 13 de marzo mediante
comunicado PIO-UTITAC-FIDUCARIBE-004-2020 la Unión Temporal ITAC le
solicitó a la Fiduciaria BBVA abrir una cuenta de ahorros para trasladar los recursos
de la cartera colectiva con el objeto mitigar el riesgo de rentabilidades negativas.

o A partir de la instrucción descrita en el enunciado anterior la Fiduciaria BBVA


apertura la cuenta de ahorros No. 001301350200308112 a la cual realizó la
transferencia de los recursos, durante el mes de julio los recursos de
fomento permanecieron en esta cuenta con lo cual se garantizó la
estabilidad de los mismos, mediante comunicado PIO-UTITAC-DIRINFRA-
028-2020, registro MINTIC 201033365 y radicado Interventoría 2020-364-
146739-2 se presentó al MINTIC e Interventoría el informe de los portafolios
de inversión que presentó la Fiducia a finales de mayo, el 10 de julio
mediante comunicado PIO-UTITAC-FIDUCARIBE-008-2020 registro Mintic
201037800 y radicado Interventoría 2020-364-147098-2 se solicitó a la
Fiduciaria información sobre el comportamiento de los mercados, el 24 de
julio mediante comunicado PIO-FIDU-UTITAC-009-2020, la Fiduciaria dio
respuesta a la solicitud.
El día 19 de febrero realizamos una reunión con el área de inversiones de la
Fiducia en el cual nos ampliaron la información del informe de mercado que
envían con el informe mensual en este espacio nos informaron que si bien el
panorama es más positivo aún se vislumbran algunas fluctuaciones en los
mercados de inversión que permita garantizar que no se van a presentar
desvalorizaciones de mercado.

A partir de los informes de mercado que periódicamente emite la fiduciaria y


del seguimiento que se hace internamente al comportamiento del mercado
hemos evidenciado que a partir de mediados de febrero se presentaron
fluctuaciones a nivel general de los fondos de inversión y pudimos evidenciar
que específicamente en la última semana se presentaron desvalorizaciones,
al igual que en los meses de marzo, abril y mayo por lo cual la Unión
Temporal ha mantenido los recursos en la cuenta de ahorros hasta se tengan
proyecciones de mejora del mercado de inversiones.
A partir de lo expuesto los recursos de aporte del contrato no presentaron
ninguna desvalorización y se mantiene el valor de los mismos.

En cuanto al otrosí al contrato de Fiducia, la Fiduciaria el mismo se suscribió


el 3 de junio y se remitió copia a la Entidad Contratante y la Interventoría
mediante comunicado PIO-UTITAC-DIRINFRA-076-2021, radicado Mintic
211044448 y C&M 20213211531952.
A la fecha y de acuerdo con la recomendación de la Fiduciaria BBVA y
estando en los términos previstos en el otrosí No.1 los recursos permanecen
en la cuenta de ahorros.
El día 6 de agosto la fiduciaria BBVA mediante comunicación informa que a
partir del análisis de mercado recomienda reinvertir los recursos en carteras
colectivas que para la fecha del comunicado presentaba una rentabilidad del
1,28 EA.
De acuerdo con las proyecciones de ITAC el comité fiduciario para acceder
a la quinta y sexta utilización se iba a llevar a cabo en el mes de agosto y por
consiguiente la ejecución de los recursos, por lo cual decidió mantener los
recursos en cuentas de ahorro hasta el 3 de septiembre que es el término
previsto en el otrosí.
En el mes de octubre la Fiduciaria conceptúo que se debían transferir los
recursos a las carteras, no obstante, en el monitoreo que hace a la Unión
Temporal evidenciamos que a nivel general las FIC presentaron una
tendencia negativa con volatilidades muy altas, por lo cual se solicitó más
información a la Fiduciaria que sustente su recomendación por lo tanto hasta
la fecha se mantienen los recursos en la cuenta de ahorros.
El día 3 de diciembre la Fiduciaria emitió comunicación en la que recomienda
que por la situación actual del mercado se mantengan los recursos en la
cuenta de ahorros, a partir de esta comunicación el día 7 de diciembre
mediante comunicado PIO-UTITAC-C&M-242-2021 radicado Mintic
211100140 y radicado C&M 20213211632802 se solicito autorización para
que acorde con lo previsto en el otrosí No. 1 al contrato de Fiducia se
mantengan los recursos 3 meses más en la cuenta de ahorros.
El día 30 de diciembre mediante comunicado PIO-C&M-UTITAC-4176-21
radicado 20213641064381acogio la solicitud de mantener los recursos en la
cuenta de ahorro hasta el día 26 de febrero de 2022.
• Dando cumplimiento a las obligaciones establecidas en el contrato de
Fiducia la Fiduciaria BBVA remitió el Informe Financiero del Fideicomiso de
noviembre, mediante correo electrónico el 10 de diciembre de 2021.
• En el mes de noviembre en la Fiduciaria se causaron rendimientos $751.533
en la cuenta de los desembolsos y $3.371 en la cuenta donde se trasladaron
los recursos del opex que no han sido autorizados para utilización.
• En el Anexo 3 Financiero se presenta la información del anticipo,
desembolsos y utilizaciones, saldos de las cuentas del fideicomiso al igual
que la información detallada de órdenes de pago.

6. ACTIVIDADES JURIDICAS

• El día 28 de diciembre se suscribió el otrosí 1 al contrato de aporte.


• El día 3 de junio se suscribió el otrosí 1 al contrato de Fiducia.

7. ACTIVIDADES ADMINISTRATIVAS

• El informe mensual No. 023 correspondiente al mes de octubre se


presentó el 5 de noviembre mediante comunicado PIO-UTITAC-
DIRINFRA-097-2021, radicado Mintic 211090583 y radicado C&M
20213211600232, la Interventoría presento observaciones el día 20 de
octubre con comunicado PIO-C&M-UTITAC-3971-21 radicado
20213641044261, las cuales fueron atendidas el 1 de diciembre con el
comunicado PIO-UTITAC-C&M-240-2021 radicado Mintic 211098140,
radicado C&M 20213211622732, el informe fue aprobado el 14 de
diciembre mediante comunicado PIO-C&M-DIRINFRA-4164-21, radicado
20213641057471.
• El informe mensual No. 024 correspondiente al mes de noviembre se
presentó el 5 de diciembre mediante comunicado PIO-UTITAC-
DIRINFRA-101-2021, radicado Mintic 211099338 y radicado C&M
20213211629142, la Interventoría presento observaciones el día 21 de
diciembre con comunicado PIO-C&M-UTITAC-4212-21 radicado
20213641060991, las cuales fueron atendidas el 28 de diciembre con el
comunicado PIO-UTITAC-C&M-257-2021 radicado Mintic 211105450 y
radicado C&M 20213211654642, a la fecha de presentación de este
informe la Interventoría se encuentra revisando la respuesta a las
observaciones.

• Los miembros de la Unión Temporal ITAC de acuerdo con lo establecido


en la cláusula segunda numeral 4 Obligaciones del Contratista realizaron
de manera oportuna el pago de los impuestos, las certificaciones se
remitieron mediante comunicado PIO-UTITAC-DIRINFRA-106-2022
radicado Mintic 221000640.

• Los miembros de la Unión Temporal ITAC de acuerdo con lo establecido


en la cláusula segunda numeral 4 Obligaciones del Contratista realizaron
de manera oportuna el pago de los aportes parafiscales, las certificaciones
se remitieron mediante comunicado PIO-UTITAC-DIRINFRA-105-2022,
radicado Mintic 221000551.

• Los miembros de la Unión Temporal ITAC sus representantes legales,


matrices o cualquier otro sujeto a ellos vinculados, no se encuentran
comprometidos en actividades delictivas, en actos de corrupción, ni
sujetos a investigaciones, medidas de aseguramiento o condenas por
dichos actos de corrupción, lo cual incluye delitos como el soborno
trasnacional, lavado de activos, enriquecimiento ilícito, cohecho, entre
otros de conformidad con la Ley penal colombiana y los tratados
internacionales sobre la materia.

• Informes mensuales: En el Anexo 4 Administrativo se presenta la


información relacionada con la presentación y estado de los informes de
seguimiento.

• Comunicados: En el Anexo 4 Administrativo se presenta la relación y


trazabilidad de los comunicados de este período.

7.1. REUNIONES REALIZADAS

El 15 de diciembre se realizó el comité operativo No. 24 con la participación de la supervisión


del contrato, la Interventoría y la Unión Temporal ITAC, el cual quedó registrado en el Acta
No. 55-UTITAC, en este se revisaron los avances del proyecto a nivel administrativo,
financiero y técnico.
En este comité se revisaron los compromisos del comité del mes de septiembre a
continuación, se presenta el seguimiento a dichos compromisos:
Tabla 19 – Seguimiento compromisos del comité No. 23

En la reunión no quedaron compromisos adquiridos:

Tabla 20 – Compromisos adquiridos en el Comité No. 24

7.2. ESTADO DE LAS GARANTIAS

En cumplimiento a lo establecido en la cláusula séptima del Anexo Técnico del pliego de


Contrato de Aporte la Unión Temporal constituyo con la Compañía Nacional de Seguros las
garantías que se relacionan en el anexo de pólizas. (Anexo 1).

El 14 de enero de 2021 mediante comunicado PIO-UTITAC-DIRINFRA-058-2021, radicado


Mintic 211001850 y C&M 20213641504102 se presentó la ampliación de la póliza, de
acuerdo a lo establecido en el otrosí No.1.
De acuerdo a lo establecido en el numeral 8.6 del contrato de mandato en el mes de julio se
constituyeron las siguientes pólizas:

POLIZA ASEGURADORA VIGENCIA AMPARO


1936 CHUBB 28/07/2021- 27/07/2022 Aparatos eléctricos
52467 CHUBB 28/07/2021- 27/07/2022 Incendio
508326 CHUBB 28/07/2021- 28/07/2022 Transportes
Tabla 21 - Pólizas
7.3. SEGUIMIENTO AL CRONOGRAMA

En el Comité Operativo No. 7 del 16/JUL/2020 mediante Acta No. 15-UTITAC se autorizó
realizar ajustes al Plan de Instalación y Operación presentado el 30/MAR/2020 en razón a
las dificultades para viabilizar los municipios cuya entrega de capacidad depende de Azteca
Comunicaciones. Por tal motivo, nos vimos obligados a reemplazar dichos municipios por
nuevos municipios cuya capacidad es suministrada por UFINET. Dicho ajuste al plan fue
presentado mediante comunicación PIO-UTITAC-C&M-030-2020 y radicado MINTIC
201041480 el día 24/JUL/2020 en donde en particular los Anexos ajustados corresponden
al ANEXO No. 4 - PROGRAMACIÓN POR FASES INSTALACIÓN AJUSTADO y el ANEXO
No. 5 - PLAN DE COMERCIALIZACION AJUSTADO.
En el mes de mayo de 2020 se concluyó la entrega de todos los documentos de planeación
conforme las fechas establecidas en el Anexo Técnico del Contrato de Aporte No. 861 de
2019, como se puede apreciar en la siguiente tabla:

Tabla 22 – Documentos de Planeación

El 6 de febrero mediante comunicado PIO-UTITAC-MINTIC 001-2020, radicado


MINTIC 201006379 y radicado Interventoría 20203641428322 se presentó la
información de los campos del sistema y los formatos en cumplimiento de las obligaciones
definidas contractualmente de los primeros 30 días calendario contados a partir del acta de
inicio del operador, la concertación de los campos que quedo en firme mediante acta
suscrita el 22 de enero de 2020 y se ratificó mediante comunicado PIO-DIRINFRA-UTITAC-
06-2020 del 24 de febrero registro 202014254.
El Plan de instalación y puesta en servicio se entregó el 30/03/2020, se recibieron
observaciones el 15/04/2020 comunicado PIO-C&M-UTITAC-171-20 RM 201019191,
subsanación presentada el 22/04/2020 comunicado PIO-UTITAC-C&M-00-20 RM
201020543, se presentó alcance al plan de instalación y puesta en servicio con el
comunicado PIO-UTITAC-C&M-007-20 radicado Interventoría 20203641457322 atendiendo
todas las solicitudes y observaciones presentadas, la interventoría dio concepto favorable
con el comunicado PIO-C&M-DIRINFRA-331-20 el 13 de mayo del 2020 y aprobación por
parte de la Supervisión el 26-MAY-2020 mediante comunicado PIO-DIRINFRA-UTITAC-14-
2020 y registro 202042217.
El Plan de Comercialización se entregó el 30/03/2020 mediante radicado MINTIC
201016474 y la interventoría dio concepto favorable con el comunicado PIO-C&M-MINTIC-
330-20 del 13-MAY-2020.
El Plan de Mantenimiento se entregó con el oficio PIO-UTITAC-DIRINFRA-020-2020 del 28-
04-2020 por correo electrónico RM 201021638 el cual fue aprobado por la Supervisión el
19-06-2020 mediante comunicado PIO-DIRINFRA-UTITAC-16-2020 y registro 202048861.
El 24-JUL-2020 se presentó la primera solicitud de ajustes al Plan de Instalación y Puesta
en Servicio (Versión 2) mediante comunicado PIO-UTITAC-C&M-030-2020 y radicado
MINTIC 201041480. Esta solicitud fue aprobada por la Interventoría el 11-AGO-2020
mediante comunicado PIO-C&M-DIRINFRA-739-20 y radicado 20203640912531, y la
supervisión dio su aprobación mediante comunicado PIO-DIRINFRA-UTITAC-23-2020 del
11-AGO-2020 y radicado 201045685.
El 3-NOV-2020 mediante comunicado PIO-UTITAC-C&M-068-2020 con radicado MINTIC
201065814 se hizo la segunda solicitud de ajustes al Plan de Instalación y Puesta en
Servicio (Versión 3), la cual fue aprobada por la interventoría el 9-NOV-2020 mediante
comunicado PIO-C&M-DIRINFRA-1346-20 y radicado 20203640928321 y aprobado por la
supervisión el 16-DIC-2020 mediante comunicado PIO-DIRINFRA-UTITAC-37-2020 y
radicado MINTIC 202113708.
Con corte al 31-MAR-2021 el avance de las diferentes actividades se resume en la siguiente
tabla:
Puesta servicio Sist. Puesta en servicio Sist. Adecuación NODO / S. Conexión proveedor Conexión red Transporte Instalación Red
Diseño Red Permisos Instalación Adecuacion NOC Puesta en servicio NODO
Informacion Gestión Eléctrico Internet / Core Distribución

1 Municipios 1 EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN

META 1 2 LA APARTADA 7/4/2020 100% 8/22/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%

META 1 3 BUENAVISTA 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%

META 1 4 SAN JOSE DE URE 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%

META 1 5 AYAPEL 7/18/2020 100% 9/5/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 8/22/2020 100% 8/29/2020 100% 8/29/2020 100% 7/31/2020 100% 9/12/2020 100%

META 1 6 ALTOS DEL ROSARIO 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%

META 1 7 BARRANCO DE LOBA 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/15/2020 100% 8/15/2020 100% 7/31/2020 100% 8/22/2020 100%

META 2 8 TIERRALTA 8/8/2020 100% 9/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 9/18/2020 100% 7/31/2020 100% 11/7/2020 100%

META 2 9 MARIA LA BAJA 8/15/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/10/2020 100% 10/10/2020 100% 10/17/2020 100% 7/31/2020 100% 11/21/2020 100%

META 2 10 MAJAGUAL 7/31/2020 100% 9/30/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/19/2020 100% 9/19/2020 100% 9/30/2020 100% 7/31/2020 100% 10/17/2020 100%

META 2 11 MOÑITOS 8/8/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/10/2020 100% 7/31/2020 100% 10/24/2020 100%

META 2 12 TOLU VIEJO 8/8/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/10/2020 100% 7/31/2020 100% 10/24/2020 100%

META 2 13 CHINU 9/5/2020 100% 10/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/31/2020 100% 7/31/2020 100% 10/31/2020 100%

META 2 14 OVEJAS 8/8/2020 100% 9/30/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/19/2020 100% 9/19/2020 100% 9/30/2020 100% 7/31/2020 100% 10/17/2020 100%

META 2 16 MOMIL 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/31/2020 100% 10/31/2020 100% 11/7/2020 100% 7/31/2020 100% 11/21/2020 100%

META 2 17 CICUCO 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/19/2020 100% 10/19/2020 100% 11/7/2020 100% 7/31/2020 100% 11/21/2020 100%

META 2 18 LOS PALMITOS 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 11/7/2020 100% 7/31/2020 100% 10/10/2020 100%

META 2 23 SAN BENITO ABAD 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/17/2020 100% 10/17/2020 100% 11/14/2020 100% 7/31/2020 100% 10/31/2020 100%

META 2 24 SAN ANTERO 8/29/2020 100% 10/24/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 10/24/2020 100% 7/31/2020 100% 10/10/2020 100%

META 2 25 VILLANUEVA 9/5/2020 100% 10/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/24/2020 100% 10/24/2020 100% 10/31/2020 100% 7/31/2020 100% 9/30/2020 100%

META 2 26 SAMPUES 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/7/2020 100% 10/7/2020 100% 11/14/2020 100% 7/31/2020 100% 9/30/2020 100%

META 2 27 SAN ESTANISLAO 9/30/2020 100% 11/21/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/7/2020 100% 11/7/2020 100% 11/21/2020 100% 7/31/2020 100% 11/14/2020 100%

META 2 28 ZAMBRANO 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/16/2020 100% 11/16/2020 100% 11/20/2020 100% 7/31/2020 100% 11/22/2020 100%

META 2 30 SOPLAVIENTO 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/7/2020 100% 10/7/2020 100% 11/14/2020 100% 7/31/2020 100% 11/30/2020 100%

META 3 42 ARENAL 12/5/2020 100% 12/6/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/14/2020 100% 11/14/2020 100% 11/20/2020 100% 7/31/2020 100% 11/21/2020 100%

META 2 31 SAN CRISTOBAL 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/10/2020 100% 10/10/2020 100% 11/14/2020 100% 7/31/2020 100% 10/31/2020 100%

META 3 32 SIMITI 11/21/2020 100% 1/16/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/16/2021 100% 1/16/2021 100% 1/23/2021 100% 7/31/2020 100% 1/23/2021 100%

META 3 33 RIO VIEJO 11/14/2020 100% 1/16/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/21/2021 100% 11/21/2021 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%

META 3 34 SAN PABLO 9/30/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/30/2020 100% 11/30/2020 100% 1/9/2021 100% 7/31/2020 100% 1/9/2021 100%

META 3 35 PUEBLO NUEVO 10/24/2020 100% 12/5/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/5/2020 100% 12/5/2020 100% 1/9/2021 100% 7/31/2020 100% 12/31/2020 100%

META 3 36 SANTA ROSA DEL SUR 9/30/2020 100% 11/7/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/7/2021 100% 1/7/2021 100% 12/30/2020 100% 7/31/2020 100% 12/19/2020 100%

META 3 37 GALERAS 11/7/2020 100% 1/9/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/31/2020 100% 12/31/2020 100% 1/15/2021 100% 7/31/2020 100% 1/16/2021 100%

META 3 38 MONTECRISTO 11/7/2020 100% 1/9/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/31/2020 100% 12/31/2020 100% 1/15/2021 100% 7/31/2020 100% 1/16/2021 100%

META 3 39 SAN MARTIN DE LOBA 11/7/2020 100% 12/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/25/2021 100% 1/25/2021 100% 1/27/2021 100% 7/31/2020 100% 1/23/2021 100%

META 3 40 TIQUISIO 10/24/2020 100% 12/12/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/25/2021 100% 1/25/2021 100% 1/27/2021 100% 7/31/2020 100% 1/23/2021 100%

META 3 41 MORALES 9/12/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/21/2020 100% 11/21/2020 100% 12/4/2020 100% 7/31/2020 100% 11/30/2020 100%

META 3 43 SAN JACINTO 10/31/2020 100% 12/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/12/2020 100% 12/12/2020 100% 12/11/2020 100% 7/31/2020 100% 12/31/2020 100%

META 3 44 VALENCIA 10/31/2020 100% 12/19/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/19/2020 100% 12/19/2020 100% 12/4/2020 100% 7/31/2020 100% 12/19/2020 100%

META 3 45 CALAMAR 11/14/2020 100% 12/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/9/2021 100% 1/9/2021 100% 1/15/2021 100% 7/31/2020 100% 1/23/2021 100%

META 3 46 SAN PEDRO 11/21/2020 100% 1/9/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/16/2021 100% 1/16/2021 100% 1/27/2021 100% 7/31/2020 100% 1/30/2021 100%

META 3 47 ARROYOHONDO 12/5/2020 100% 1/23/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/23/2021 100% 1/23/2021 100% 2/11/2021 100% 7/31/2020 100% 2/13/2021 100%

META 3 15 MAHATES 8/22/2020 100% 10/17/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/30/2020 100% 12/30/2020 100% 1/9/2021 100% 7/31/2020 100% 1/9/2021 100%

META 3 19 LA UNION 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%

META 3 20 TUCHIN 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/4/2020 100% 7/31/2020 100% 12/5/2020 100%

META 3 21 SAN JUAN DE BETULIA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/30/2020 100% 12/30/2020 100% 12/30/2020 100% 7/31/2020 100% 12/31/2020 100%

META 3 22 PURISIMA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%

META 3 29 CLEMENCIA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/23/2020 100% 11/23/2020 100% 11/28/2020 100% 7/31/2020 100% 11/30/2020 100%

META 3 48 TALAIGUA NUEVO 12/19/2020 100% 2/6/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/23/2021 100% 1/23/2021 100% 1/27/2021 100% 7/31/2020 100% 1/30/2021 100%
%Avance Meta 1 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 2 (UT ITAC) 100% 99% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 3 (UT ITAC) 100% 97% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Proyecto (UT ITAC) 100% 99% 100% 100% 100% 100% 100% 100% 100% 100%

Tabla 23 – Seguimiento cronograma de actividades

Y el avance en cuanto a accesos instalados se presenta en el siguiente cuadro:


EJECUCIÓN (DILIGENCIAR EL NÚMERO DE ACCESOS INSTALADOS EN CADA PERIODO TRIMESTRAL)
META 1 META 2 META 3
Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
Municipios Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2
META 1 LA APARTADA 190 306 40 16
META 1 BUENAVISTA 60 131 3 11
META 1 SAN JOSE DE URE 190 2
META 1 AYAPEL 47 445 281 5
META 1 ALTOS DEL ROSARIO 22 212 25
META 1 BARRANCO DE LOBA 222 2
META 2 TIERRALTA 178 761 296 82
META 2 MARIA LA BAJA 94 104 63 282 43
META 2 MAJAGUAL 16 229 9 3 9
META 2 MOÑITOS 72 95
META 2 TOLU VIEJO 13 111
META 2 CHINU 225 442 10
META 2 OVEJAS 278 48
META 2 MOMIL 154 69
META 2 CICUCO 180 26 3
META 2 LOS PALMITOS 6 101 99
META 2 SAN BENITO ABAD 140 4
META 2 SAN ANTERO 156 342 11
META 2 VILLANUEVA 3 345 58 31
META 2 SAMPUES 189 301 1
META 2 SAN ESTANISLAO 123 184 10 2
META 2 ZAMBRANO 252 44
META 2 SOPLAVIENTO 175 49 1
META 2 ARENAL 152 4
META 2 SAN CRISTOBAL 150 1 1
META 3 SIMITI 295
META 3 RIO VIEJO 38 248 4
META 3 SAN PABLO 76 657 112
META 3 PUEBLO NUEVO 47 385
META 3 SANTA ROSA DEL SUR 155 532
META 3 GALERAS 196 147
META 3 MONTECRISTO 324
META 3 SAN MARTIN DE LOBA 220
META 3 TIQUISIO 178
META 3 MORALES 169 1
META 3 SAN JACINTO 25 470 51
META 3 VALENCIA 21 346 6
META 3 CALAMAR 253 108
META 3 SAN PEDRO 119 125
META 3 ARROYOHONDO 186
META 3 MAHATES 73 197
META 3 LA UNION 174
META 3 TUCHIN 55 106
META 3 SAN JUAN DE BETULIA 143
META 3 PURISIMA 147
META 3 CLEMENCIA 252
META 3 TALAIGUA NUEVO 143
EJECUTADO - - - - 190 800 432 486 1,184 1,124 1,869 1,911 1,168 1,152 295 1,884 1,326 2,003
ACUMULADO - - - - 190 990 1,422 1,908 3,092 4,216 6,085 7,996 9,164 10,316 10,611 12,495 13,821 15,824

Tabla 24 – Seguimiento cronograma de accesos instalados

En el mes de diciembre no se tenían programados mantenimientos preventivos, razón por


la cual no se ejecuto ninguno.

7.4. GESTION DE RIESGOS DEL PROYECTO

La red de fibra óptica se encuentra totalmente construida en los 47 municipios y tenemos la


totalidad de los 15.811 hogares beneficiados con acceso internet.
En el ANEXO 2 – MATRIZ DE RIESGOS se tiene el registro de los riesgos asociados al
desarrollo del proyecto.
7.5. LECCIONES APRENDIDAS

No aplica para el periodo del informe.

7.6. PRINCIPALES CASOS DE EXITO

No aplica para el periodo del informe.

7.7. PRINCIPALES DIFICULTADES ENCONTRADAS

No aplica para el periodo del informe.

7.8. RECOMENDACIONES PARA MITIGAR LAS MISMAS EN EL SIGUIENTE


PERIODO

Dado que ya terminamos la construcción de la red en la totalidad de los 47 municipios y la


instalación del internet en los 15.811 hogares, continuamos ajustando los procesos de
operación, mantenimiento, mesa de ayuda, facturación y recaudo con el objetivo de
minimizar las quejas y reclamos de los beneficiarios del proyecto.

7.9. CONCLUSIONES

• Cumplimos la meta regional de 15.811 accesos activos.


• Completamos el 100% de la construcción de la red en los 47 municipios.
• La interventoría emite concepto de aprobación de la Meta 3 y por consiguiente
de la Meta Regional de los 15.811 accesos, mediante comunicado PIO-C&M-
UTITAC-2908-21 con Radicado 20213640984581.
• La interventoría emite concepto de Cumplimiento del sistema de información y se
hace cesación de situación de incumplimiento el 15/03/2021mediante Radicado
MINTIC 211020475.
• Se realizaron actualizaciones de los módulos de: gestión documental,
indicadores y PQRs.
• Con corte al período del informe el FONDO ÚNICO DE TIC ha transferido a la
Unión Temporal el anticipo, el primer, segundo, tercer, cuarto, quinto, sexto y
séptimo desembolso por un valor total de $41.427.860.080.
• Del anticipo se han ejecutado el 100% de los recursos.
• A la fecha de presentación de este informe se han ejecutado recursos
equivalentes a $35.378.939.953.
• El total de rendimientos causados en la cuenta de ahorros del anticipo con corte
al informe corresponden al valor de $ 16.881.262, 03
• El total de rendimientos causados en la cuenta de ahorros de los desembolsos
con corte al informe corresponden al valor de $20.377.499.
• El total de rendimientos causados en la cuenta de ahorros de remanentes del
opex con corte al informe corresponden al valor de $7.192.
• El 21 de diciembre se radicó la documentación para el trámite del octavo
desembolso.