MES 25
PERIODO: 1 al 31 de Diciembre de 2.021
Contenido
1 INTRODUCCIÓN ...................................................................................................................... 7
2. OBJETIVO .................................................................................................................................. 8
2.2. OBJETIVOS ESPECÍFICOS ........................................................................................... 8
3. RESUMEN EJECUTIVO .......................................................................................................... 9
4. ACTIVIDADES TECNICAS .................................................................................................... 10
4.1. DOCUMENTOS DE PLANEACIÓN ............................................................................. 10
4.2. EJECUCION DEL PLAN DE ADQUISICIONES ......................................................... 11
4.3. ESTUDIOS DE CAMPO, CENSO Y MAPPING ......................................................... 13
4.4. DISEÑO ............................................................................................................................ 14
4.5. CUBICACIÓN DEL NODO............................................................................................. 16
4.6. PERMISOS USO DE INFRAESTRUCTURA .............................................................. 20
4.7. CONSTRUCCIÓN E INSTALACIÓN ........................................................................... 22
4.8. AVANCES DE LAS METAS DE INSTALACIÓN Y OPERACIÓN ........................... 24
4.9. SISTEMA DE GESTION DE LA INFORMACION ...................................................... 27
4.10. INDICADORES DEL PROYECTO............................................................................ 28
5. ACTIVIDADES FINANCIERAS ............................................................................................. 33
6. ACTIVIDADES JURIDICAS ................................................................................................... 36
7. ACTIVIDADES ADMINISTRATIVAS .................................................................................... 36
7.1. REUNIONES REALIZADAS .......................................................................................... 37
7.2. ESTADO DE LAS GARANTIAS .................................................................................... 38
7.3. SEGUIMIENTO AL CRONOGRAMA ........................................................................... 39
7.4. GESTION DE RIESGOS DEL PROYECTO ............................................................... 42
7.5. LECCIONES APRENDIDAS ......................................................................................... 43
7.6. PRINCIPALES CASOS DE EXITO .............................................................................. 43
7.7. PRINCIPALES DIFICULTADES ENCONTRADAS.................................................... 43
7.8. RECOMENDACIONES PARA MITIGAR LAS MISMAS EN EL SIGUIENTE
PERIODO ..................................................................................................................................... 43
7.9. CONCLUSIONES............................................................................................................ 43
ANEXOS
ANEXO 1 – CUADRO POLIZAS DEL PROYECTO
ANEXO 3 – FINANCIERO
ANEXO 4 – ADMINISTRATIVO
ANEXO 7 – PERMISOS
ANEXO 9 - INDICADORES
a. Resumen ejecutivo.
b. Actividades realizadas.
• Documentos de Planeación.
• Selección y Contratación de Talento humano para el desarrollo del
proyecto.
• Ejecución del Plan de Adquisiciones.
• Sistema de Gestión de la Información.
• Reuniones Realizadas.
• Aspectos Financieros y Contables.
• Aspectos Jurídicos.
• Estado de las Garantías.
• Aspectos Administrativos.
3.1 Aspectos Técnicos: La construcción de las redes y la instalación de los accesos en los
47 municipios obligación en el marco del Contrato de Aporte 0861 de 2019 ya se cumplió al
100%, logrando así la aprobación de la totalidad de los 15.811 accesos en los 47 municipios
en los departamentos de Bolívar, Córdoba y Sucre en la Región Caribe, para lo cual la
interventoría emitió concepto de aprobación de la Meta 3 y por consiguiente de la Meta
Regional de los 15.811 accesos, mediante comunicado PIO-C&M-UTITAC-2908-21 con
Radicado 20213640984581.
En este período los miembros de la Unión Temporal cumplieron oportunamente con las
obligaciones del Art. 50 de la ley 789 de 2002 al igual que el pago de los impuestos, la
información se detalla en el capítulo correspondiente.
4. ACTIVIDADES TECNICAS
CANTIDAD
PAGADA
CANTIDAD CANTIDAD VALOR
FECHA DE DESCRIPCIÓN DEL CON # FACTURA VALOR VALOR DE UBICACIÓN FINAL DEL
ITEM PROVEEDOR CATEGORIZACIÓN PLAN DE EN NUMERO DE OP VALOR OP ASOCIADO AL DESEMBOLSO UTILIZACIÓN VALOR PAGADO ESTADO
ADQUISICIÓN ELEMENTO RECURSOS DE VENTA FACTURA TRM (PAGO) ACTIVO
COMPRAS FACTURA ANTICIPO
DE
FOMENTO
1000COR001 29/10/2020 Huawei-Meltec eSight CORE 1 1 1 10502 723,76 3.793 4 2.745.200 1 2 2.745.199,62 Instalado
SmartAX
2000OLT001
29/10/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 10502 85.559,83 3.793 4 324.526.738 1 2 324.526.738,41 Instalado
1000COR002 29/10/2020 Huawei-Meltec CloudEngine S12700E-8 CORE 1 1 1 10502 35.883,8 3.793 4 136.106.474 1 2 136.106.473,52 Instalado
1000COR003 29/10/2020 Huawei-Meltec CloudEngine S12700E-4 CORE 1 1 1 10502 40.801 3.793 4 154.755.731 1 2 154.755.731,21 Instalado
1000COR004 29/10/2020 Huawei-Meltec NetEngine NE40E-M2K-B CORE 1 1 1 10502 76.209 3.793 4 289.059.274 1 2 289.059.273,89 Instalado
USG6655E(C13_North
1000COR005
29/10/2020 Huawei-Meltec America) CORE 1 1 1 10502 61.756 3.793 4 234.237.881 1 2 234.237.881,24 Instalado
20200072S 29/10/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.539 2.539 10502 184.245,58 3.793 4 698.839.807 1 2 698.839.806,86 Instalado
Network Cloud Engine-
1000COR006
29/10/2020 Huawei-Meltec FAN Lite HW CORE 1 1 1 10502 43.639 3.793 4 165.521.184 1 2 165.521.183,62 Instalado
Network Cloud Engine-
1000COR007
29/10/2020 Huawei-Meltec FAN Lite CORE 1 1 1 10502 17.890 3.793 4 67.856.126 1 2 67.856.125,83 Instalado
ODN FMC21(Field-
20200085N
29/10/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 10502 5.052 3.793 4 19.160.654 1 2 19.160.653,80 Instalado
ODN SSC28(Pre-
20200087N
29/10/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 10502 296.033 3.793 4 1.122.847.849 1 2 1.122.847.849,15 Instalado
ODN ATB31(Not Support
20200082N
29/10/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.539 2.539 10502 7.040 3.793 4 26.702.144 1 2 26.702.144,15 Instalado
SmartAX EA5800-
2000OLT002
29/10/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 10502 19.111,0 3.793 4 72.487.759 1 2 72.487.758,74 Instalado
Fibra optica 24HADSS
202000133F
29/10/2020 Huawei-Meltec span100-150 Fibra 120.000 30.000 30.000 10502 28.203 3.793 4 106.973.415 1 2 106.973.414,94 Instalado
202000134I 29/10/2020 Huawei-Meltec Implementación en sitio NODOS 6 4 4 10502 54.061 3.793 4 205.050.794 1 2 205.050.794,31 Instalado
SmartAX
2000OLT001
1/10/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 10863 85.564,83 3.745 6 320.475.377 2 3 320.475.376,67 Instalado
20200072S 1/10/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.417 2.417 10863 175.306,22 3.745 6 656.593.664 2 3 656.593.663,83 Instalado
ODN FMC21(Field-
20200085N
1/10/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 10863 4.809 3.745 6 18.011.247 2 3 18.011.246,72 Instalado
ODN SSC28(Pre-
20200087N
1/10/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 10863 281.808,6 3.745 6 1.055.488.884 2 3 1.055.488.884,11 Instalado
ODN ATB31(Not Support
20200082N
1/10/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.417 2.417 10863 6.673 3.745 6 24.992.573 2 3 24.992.572,60 Instalado
SmartAX EA5800-
2000OLT002
1/10/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 10863 19.111 3.745 6 71.578.602 2 3 71.578.602,42 Instalado
Fibra optica 24HADSS
202000133F
1/10/2020 Huawei-Meltec span100-150 Fibra 120.000 30.000 30.000 10863 28.203 3.745 6 105.631.798 2 3 105.631.798,23 Instalado
202000134I 1/10/2020 Huawei-Meltec Implementación en sitio NODOS 6 2 2 10863 27.030 3.745 6 101.240.101 2 3 101.240.100,51 Instalado
SmartAX
2000OLT001
1/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 3 3 11005 42.782,42 3.757 5 160.742.521 2 3 160.742.520,84 Instalado
20200072S 1/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.222 2.222 11005 161.162,77 3.757 5 605.522.375 2 3 605.522.374,83 Instalado
ODN FMC21(Field-
20200085N
1/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11005 4.421 3.757 5 16.610.285 2 3 16.610.285,38 Instalado
ODN SSC28(Pre-
20200087N
1/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11005 259.072,7 3.757 5 973.390.668 2 3 973.390.667,66 Instalado
ODN ATB31(Not Support
20200082N
1/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.222 2.222 11005 6.134 3.757 5 23.048.596 2 3 23.048.595,73 Instalado
SmartAX EA5800-
2000OLT002
1/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11005 29.516 3.757 5 110.896.687 2 3 110.896.686,58 Instalado
Fibra optica 24HADSS
202000133F
1/11/2020 Huawei-Meltec span100-150 Fibra 120.000 10.000 10.000 11005 9.401 3.757 5 35.321.531 2 3 35.321.531,21 Instalado
SmartAX
2000OLT001
1/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 7 7 11512 99.825,64 3.854 5 384.774.923 2 3 384.774.923,43 Instalado
20200072S 1/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 2.027 2.027 11512 147.019,32 3.854 5 566.681.572 2 3 566.681.571,85 Instalado
ODN FMC21(Field-
20200085N
1/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11512 4.033 3.854 5 15.544.822 2 3 15.544.822,34 Instalado
ODN SSC28(Pre-
20200087N
1/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11512 236.336,8 3.854 5 910.953.230 2 3 910.953.229,61 Instalado
ODN ATB31(Not Support
20200082N
1/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.027 2.027 11512 5.596 3.854 5 21.570.160 2 3 21.570.159,91 Instalado
SmartAX EA5800-
2000OLT002
1/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11512 19.111 3.854 5 73.662.850 2 3 73.662.850,18 Instalado
Fibra optica 24HADSS
202000133F
1/11/2020 Huawei-Meltec span100-150 Fibra 120.000 15.000 15.000 11512 14.102 3.854 5 54.353.809 2 3 54.353.808,71 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 7 7 11918 99.825,64 3.764 5 375.725.729 2 3 375.725.729,43 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 1.993 1.993 11918 144.553,29 3.764 5 544.072.551 2 3 544.072.550,79 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 11918 3.167 3.764 5 11.918.475 2 3 11.918.474,77 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 11918 185.575,2 3.764 5 698.471.666 2 3 698.471.666,20 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 2.193 2.193 11918 6.054 3.764 5 22.787.801 2 3 22.787.801,28 Instalado
SmartAX EA5800-
2000OLT002
30/11/2020 Huawei-Meltec X2(F01T100) OLT 6 1 1 11918 19.111 3.764 5 71.930.436 2 3 71.930.436,29 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 5.000 5.000 11918 4.701 3.764 5 17.691.836 2 3 17.691.835,91 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 6 6 14808 85.564,83 3.728,09 9 318.993.394 3 4 318.993.393,79 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 358 358 14808 25.965,92 3.728,09 9 96.803.283 3 4 96.803.282,96 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 14808 1.513 3.728,09 9 5.640.119 3 4 5.640.118,50 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 14808 88.656,6 3.728,09 9 330.519.631 3 4 330.519.630,67 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 158 158 14808 436 3.728,09 9 1.626.217 3 4 1.626.216,72 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 10.000 10.000 14808 9.401 3.728,09 9 35.047.774 3 4 35.047.774,09 Instalado
SmartAX
2000OLT001
30/11/2020 Huawei-Meltec EA5801(F01T100) OLT 40 5 5 14809 71.304,03 3.728,09 9 265.827.828 3 4 265.827.828,15 Instalado
20200072S 30/11/2020 Huawei-Meltec EchoLife EG8141A5_1_1 EQUIPOS 15834 3.502 3.502 14809 254.001,81 3.728,09 9 946.941.612 3 4 946.941.611,57 Instalado
ODN FMC21(Field-
20200085N
30/11/2020 Huawei-Meltec mountable Connector) ODN 1 1 1 14809 6.966 3.728,09 9 25.968.315 3 4 25.968.315,48 Instalado
ODN SSC28(Pre-
20200087N
30/11/2020 Huawei-Meltec connectorized Closure) ODN 1 1 1 14809 408.195,2 3.728,09 9 1.521.788.503 3 4 1.521.788.503,19 Instalado
ODN ATB31(Not Support
20200082N
30/11/2020 Huawei-Meltec ONT Installation)_1_1 ODN 15834 3.502 3.502 14809 9.668 3.728,09 9 36.044.373 3 4 36.044.373,07 Instalado
SmartAX EA5800-
2000OLT002
30/11/2020 Huawei-Meltec X2(F01T100) OLT 6 2 2 14809 38.222 3.728,09 9 142.495.199 3 4 142.495.199,14 Instalado
Fibra optica 24HADSS
202000133F
30/11/2020 Huawei-Meltec span100-150 Fibra 120.000 20.000 20.000 14809 18.802 3.728,09 9 70.095.548 3 4 70.095.548,18 Instalado
El último anexo se reportó con corte a junio 30 y no se ha vuelto a radicar porque desde el
mes de mayo no se realiza adquisición de equipos con recursos del patrimonio.
4.3. ESTUDIOS DE CAMPO, CENSO Y MAPPING
4.4. DISEÑO
1 Municipios 1 EJECUCIÓN
Para la búsqueda y consecución de los sitios para la cubicación del nodo es necesario el
levantamiento de Site Survey, negociación y firma de contratos de arrendamiento y
adecuaciones físicas.
Todos los permisos de uso de infraestructura están emitidos por parte de UFINET y con esto
logramos los permisos definitivos de la totalidad de los 47 municipios, cumpliendo al 100%
con este compromiso.
Uso infraestructura Pública
Departamento Municipio
ESTADO
ENTIDAD (Aprobado / En trámite /
Subsanación)
CORE
El CORE ya se encuentra instalado, configurado y operando al cien por ciento.
CONSTRUCCIÓN DE NODOS
Constituye la construcción de las adecuaciones físicas de los nodos, adecuaciones
eléctricas, canaletas y acometidas para el ingreso de la fibra óptica.
En el Comité Operativo No. 7 del 16/JUL/2020 mediante Acta No. 15-UTITAC se autorizó
realizar ajustes al Plan de Instalación y Operación presentado el 30/MAR/2020 en razón a
las dificultades para viabilizar los municipios cuya entrega de capacidad depende de Azteca
Comunicaciones. Por tal motivo, nos vimos obligados a reemplazar dichos municipios por
nuevos municipios cuya capacidad es suministrada por UFINET. Dicho ajuste al plan fue
presentado mediante comunicación PIO-UTITAC-C&M-030-2020 y radicado MINTIC
201041480 el día 24/JUL/2020 en donde en particular los Anexos ajustados corresponden
al ANEXO No. 4 - PROGRAMACIÓN POR FASES INSTALACIÓN AJUSTADO y el ANEXO
No. 5 - PLAN DE COMERCIALIZACION AJUSTADO.
En el siguiente cuadro se evidencia la ejecución de todas las actividades al 100% en los 47
municipios:
Puesta servicio Sist. Puesta en servicio Sist. Adecuación NODO / S. Conexión proveedor Conexión red Transporte Instalación Red
Diseño Red Permisos Instalación Adecuacion NOC Puesta en servicio NODO
Informacion Gestión Eléctrico Internet / Core Distribución
1 Municipios 1 EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN
META 1 2 LA APARTADA 4/07/2020 100% 22/08/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%
META 1 3 BUENAVISTA 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%
META 1 4 SAN JOSE DE URE 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%
META 1 5 AYAPEL 18/07/2020 100% 5/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 22/08/2020 100% 29/08/2020 100% 29/08/2020 100% 31/07/2020 100% 12/09/2020 100%
META 1 6 ALTOS DEL ROSARIO 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 8/08/2020 100% 31/07/2020 100% 22/08/2020 100%
META 1 7 BARRANCO DE LOBA 30/05/2020 100% 11/07/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 8/08/2020 100% 15/08/2020 100% 15/08/2020 100% 31/07/2020 100% 22/08/2020 100%
META 2 8 TIERRALTA 8/08/2020 100% 12/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 18/09/2020 100% 31/07/2020 100% 7/11/2020 100%
META 2 9 MARIA LA BAJA 15/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 10/10/2020 100% 10/10/2020 100% 17/10/2020 100% 31/07/2020 100% 21/11/2020 100%
META 2 10 MAJAGUAL 31/07/2020 100% 30/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/09/2020 100% 19/09/2020 100% 30/09/2020 100% 31/07/2020 100% 17/10/2020 100%
META 2 11 MOÑITOS 8/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 10/10/2020 100% 31/07/2020 100% 24/10/2020 100%
META 2 12 TOLU VIEJO 8/08/2020 100% 10/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 10/10/2020 100% 31/07/2020 100% 24/10/2020 100%
META 2 13 CHINU 5/09/2020 100% 31/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/09/2020 100% 30/09/2020 100% 31/10/2020 100% 31/07/2020 100% 31/10/2020 100%
META 2 14 OVEJAS 8/08/2020 100% 30/09/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/09/2020 100% 19/09/2020 100% 30/09/2020 100% 31/07/2020 100% 17/10/2020 100%
META 2 16 MOMIL 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/10/2020 100% 31/10/2020 100% 7/11/2020 100% 31/07/2020 100% 21/11/2020 100%
META 2 17 CICUCO 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/10/2020 100% 19/10/2020 100% 7/11/2020 100% 31/07/2020 100% 21/11/2020 100%
META 2 18 LOS PALMITOS 12/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 7/11/2020 100% 31/07/2020 100% 10/10/2020 100%
META 2 23 SAN BENITO ABAD 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 17/10/2020 100% 17/10/2020 100% 14/11/2020 100% 31/07/2020 100% 31/10/2020 100%
META 2 24 SAN ANTERO 29/08/2020 100% 24/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/09/2020 100% 12/09/2020 100% 24/10/2020 100% 31/07/2020 100% 10/10/2020 100%
META 2 25 VILLANUEVA 5/09/2020 100% 31/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 24/10/2020 100% 24/10/2020 100% 31/10/2020 100% 31/07/2020 100% 30/09/2020 100%
META 2 26 SAMPUES 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/10/2020 100% 7/10/2020 100% 14/11/2020 100% 31/07/2020 100% 30/09/2020 100%
META 2 27 SAN ESTANISLAO 30/09/2020 100% 21/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/11/2020 100% 7/11/2020 100% 21/11/2020 100% 31/07/2020 100% 14/11/2020 100%
META 2 28 ZAMBRANO 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/11/2020 100% 16/11/2020 100% 20/11/2020 100% 31/07/2020 100% 22/11/2020 100%
META 2 30 SOPLAVIENTO 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/10/2020 100% 7/10/2020 100% 14/11/2020 100% 31/07/2020 100% 30/11/2020 100%
META 3 42 ARENAL 5/12/2020 100% 6/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 14/11/2020 100% 14/11/2020 100% 20/11/2020 100% 31/07/2020 100% 21/11/2020 100%
META 2 31 SAN CRISTOBAL 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 10/10/2020 100% 10/10/2020 100% 14/11/2020 100% 31/07/2020 100% 31/10/2020 100%
META 3 32 SIMITI 21/11/2020 100% 16/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/01/2021 100% 16/01/2021 100% 23/01/2021 100% 31/07/2020 100% 23/01/2021 100%
META 3 33 RIO VIEJO 14/11/2020 100% 16/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 21/11/2021 100% 21/11/2021 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%
META 3 34 SAN PABLO 30/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/11/2020 100% 30/11/2020 100% 9/01/2021 100% 31/07/2020 100% 9/01/2021 100%
META 3 35 PUEBLO NUEVO 24/10/2020 100% 5/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 5/12/2020 100% 5/12/2020 100% 9/01/2021 100% 31/07/2020 100% 31/12/2020 100%
META 3 36 SANTA ROSA DEL SUR 30/09/2020 100% 7/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/01/2021 100% 7/01/2021 100% 30/12/2020 100% 31/07/2020 100% 19/12/2020 100%
META 3 37 GALERAS 7/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/12/2020 100% 31/12/2020 100% 15/01/2021 100% 31/07/2020 100% 16/01/2021 100%
META 3 38 MONTECRISTO 7/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 31/12/2020 100% 31/12/2020 100% 15/01/2021 100% 31/07/2020 100% 16/01/2021 100%
META 3 39 SAN MARTIN DE LOBA 7/11/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 25/01/2021 100% 25/01/2021 100% 27/01/2021 100% 31/07/2020 100% 23/01/2021 100%
META 3 40 TIQUISIO 24/10/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 25/01/2021 100% 25/01/2021 100% 27/01/2021 100% 31/07/2020 100% 23/01/2021 100%
META 3 41 MORALES 12/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 21/11/2020 100% 21/11/2020 100% 4/12/2020 100% 31/07/2020 100% 30/11/2020 100%
META 3 43 SAN JACINTO 31/10/2020 100% 12/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 12/12/2020 100% 12/12/2020 100% 11/12/2020 100% 31/07/2020 100% 31/12/2020 100%
META 3 44 VALENCIA 31/10/2020 100% 19/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 19/12/2020 100% 19/12/2020 100% 4/12/2020 100% 31/07/2020 100% 19/12/2020 100%
META 3 45 CALAMAR 14/11/2020 100% 31/12/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 9/01/2021 100% 9/01/2021 100% 15/01/2021 100% 31/07/2020 100% 23/01/2021 100%
META 3 46 SAN PEDRO 21/11/2020 100% 9/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 16/01/2021 100% 16/01/2021 100% 27/01/2021 100% 31/07/2020 100% 30/01/2021 100%
META 3 47 ARROYOHONDO 5/12/2020 100% 23/01/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/01/2021 100% 23/01/2021 100% 11/02/2021 100% 31/07/2020 100% 13/02/2021 100%
META 3 15 MAHATES 22/08/2020 100% 17/10/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/12/2020 100% 30/12/2020 100% 9/01/2021 100% 31/07/2020 100% 9/01/2021 100%
META 3 19 LA UNION 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%
META 3 20 TUCHIN 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 4/12/2020 100% 31/07/2020 100% 5/12/2020 100%
META 3 21 SAN JUAN DE BETULIA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 30/12/2020 100% 30/12/2020 100% 30/12/2020 100% 31/07/2020 100% 31/12/2020 100%
META 3 22 PURISIMA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 7/12/2020 100% 7/12/2020 100% 11/12/2020 100% 31/07/2020 100% 12/12/2020 100%
META 3 29 CLEMENCIA 19/09/2020 100% 14/11/2020 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/11/2020 100% 23/11/2020 100% 28/11/2020 100% 31/07/2020 100% 30/11/2020 100%
META 3 48 TALAIGUA NUEVO 19/12/2020 100% 6/02/2021 100% 10/08/2020 100% 31/07/2020 100% 31/07/2020 100% 23/01/2021 100% 23/01/2021 100% 27/01/2021 100% 31/07/2020 100% 30/01/2021 100%
%Avance Meta 1 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 2 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 3 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Proyecto (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Departamento Municipio
ESTADO
ENTIDAD (Aprobado / En trámite /
Subsanación)
DISPONIBILIDAD OLT
A continuación, se presenta el indicador de disponibilidad de los 47 municipios en
el mes diciembre 2021.
Disponibilidad
Municipios CORE Valor objetivo CUMPLE
VELOCIDAD DE NAVEGACION
A continuación, se presenta el indicador de velocidad de navegación de bajada y
de subida promedio en los 47 municipios del mes de diciembre de 2021.
Velocidad Velocidad subida
Municipios CUMPLE
bajada(Mbps) (Mbps)
Altos del rosario 1224,33 5225,16 SI
Ayapel 1224,98 5224,87 SI
Barranco de loba 1225,68 5224,97 SI
Buenavista 1224,67 5224,28 SI
La apartada 1224,98 5225,32 SI
San Jose de Ure 1224,74 5226,04 SI
Arenal 1224,74 5224,48 SI
Chinu 1224,16 5224,67 SI
Cicuco 1224,16 5224,16 SI
Clemencia 1225,22 5224,79 SI
Los palmitos 1225,24 5224,78 SI
Mahates 1224,71 5224,38 SI
Majagual 1224,17 5224,14 SI
Momil 1224,94 5225,38 SI
Monitos 1225,30 5224,22 SI
Ovejas 1224,61 5224,65 SI
Purisima 1224,60 5225,65 SI
Sampues 1225,75 5224,26 SI
San antero 1224,77 5225,05 SI
San Benito abad 1225,18 5225,47 SI
San Cristobal 1224,69 5225,48 SI
San estanislao 1224,39 5225,37 SI
Soplaviento 1225,23 5225,35 SI
Tierralta 1224,82 5224,91 SI
Toluviejo 1224,99 5225,42 SI
Villanueva 1224,44 5224,45 SI
Zambrano 1224,96 5225,24 SI
Arroyohondo 1225,33 5225,26 SI
Calamar 1225,65 5224,67 SI
Galeras 1224,77 5225,49 SI
la Union 1225,74 5224,79 SI
Maria la Baja 1225,06 5225,22 SI
Montecristo 1225,21 5224,67 SI
Morales 1224,32 5225,00 SI
Pueblo nuevo 1225,91 5224,91 SI
Rio Viejo 1224,59 5224,80 SI
San Jacinto 1225,27 5224,69 SI
San Juan de Betulia 1224,38 5225,75 SI
San Martin de Loba 1223,61 5225,41 SI
San Pablo 1225,10 5224,91 SI
San Pedro 1225,52 5224,92 SI
Santa Rosa del Sur 1224,58 5225,38 SI
Simiti 1224,29 5224,71 SI
Talaigua Nuevo 1225,92 5225,84 SI
Tiquisio 1224,15 5225,62 SI
Tuchin 1225,07 5226,21 SI
Valencia 1224,55 5225,66 SI
Llamadas Promedio
RED Llamadas exitosas CUMPLE
abandonadas respuesta
95,580% 4,420% 13,62 seg SI
Valor objetivo 95,000% 5,000% 30 seg
ACCESOS ACTIVOS
A continuación, se presenta el indicador accesos activos en los municipios
aprobados en el mes de diciembre de 2021.
Porcentaje
Indicador Meta Usuarios
usuarios activos
Usuarios activos 15.811 15.811 100%
Tabla 18 – Accesos Activos en diciembre 2021
5. ACTIVIDADES FINANCIERAS
• Con la aprobación de las órdenes de pago 001, 002, 003, 005, 007 y 008 por
$11.018.850.024 incluido el GMF se ha ejecutado recursos del anticipo
equivalentes al 100%.
• Con la aprobación de las órdenes de pago 004, 005, 006, 007, 008, 009, 010,
011, 012, 013 y 014 se han legalizado recursos por un total de
$35.378.939.953 valor que incluye el anticipo y los recursos de la segunda,
tercera y cuarta utilización.
• El 18 de septiembre se presentó la orden de pago 015 correspondiente a
computadores para el NOC por $32.571.999, la Interventoría presentó
observaciones el 27 de septiembre las cuales están en proceso de revisión
para dar respuesta.
• El 8 de octubre se radico las órdenes de pago 016 y 017 correspondiente a
los recursos de opex asociados a la quinta y sexta utilización para revisión
de la Interventoría, el día 20 de octubre se radicó en dos memorias las
facturas que soportan estas órdenes, las cuales se encuentran en proceso
de revisión por parte de la Interventoría y se unifico el cobro del opex en la
orden de pago 016.
El día 13 de diciembre teniendo en cuenta que la quinta utilización de opex
no presentaba observaciones se modificó la orden para cobrar estos recursos
y se dio respuesta a las observaciones, esta orden fue aprobada por la
Interventoría el 20 de diciembre.
• El día 16 de noviembre se presentó la orden de pago 017 correspondiente al
cobro del sistema de información por $850.850.000 a nombre de Anditel SAS,
la Interventoría presento observaciones el día 24 de noviembre, las cuales
se respondieron los días 7 y 21 de diciembre, a la fecha de presentación de
este informe las respuestas ya fueron validadas por la Interventoría y se
encuentra en proceso de firma y radicación ante la Fiduciaria.
• El día 27 de septiembre mediante comunicado PIO-UTITAC-DIRINFRA-091-
2021 radicado Mintic 211079167 y C&M 20213211578352 se presentó la
documentación para el trámite del séptimo desembolso equivalente a
$1.806.960.000, los cuales fueron desembolsados a la Fiduciaria el 21 de
noviembre.
6. ACTIVIDADES JURIDICAS
7. ACTIVIDADES ADMINISTRATIVAS
En el Comité Operativo No. 7 del 16/JUL/2020 mediante Acta No. 15-UTITAC se autorizó
realizar ajustes al Plan de Instalación y Operación presentado el 30/MAR/2020 en razón a
las dificultades para viabilizar los municipios cuya entrega de capacidad depende de Azteca
Comunicaciones. Por tal motivo, nos vimos obligados a reemplazar dichos municipios por
nuevos municipios cuya capacidad es suministrada por UFINET. Dicho ajuste al plan fue
presentado mediante comunicación PIO-UTITAC-C&M-030-2020 y radicado MINTIC
201041480 el día 24/JUL/2020 en donde en particular los Anexos ajustados corresponden
al ANEXO No. 4 - PROGRAMACIÓN POR FASES INSTALACIÓN AJUSTADO y el ANEXO
No. 5 - PLAN DE COMERCIALIZACION AJUSTADO.
En el mes de mayo de 2020 se concluyó la entrega de todos los documentos de planeación
conforme las fechas establecidas en el Anexo Técnico del Contrato de Aporte No. 861 de
2019, como se puede apreciar en la siguiente tabla:
1 Municipios 1 EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN PLANEACIÓN EJECUCIÓN
META 1 2 LA APARTADA 7/4/2020 100% 8/22/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%
META 1 3 BUENAVISTA 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%
META 1 4 SAN JOSE DE URE 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%
META 1 5 AYAPEL 7/18/2020 100% 9/5/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 8/22/2020 100% 8/29/2020 100% 8/29/2020 100% 7/31/2020 100% 9/12/2020 100%
META 1 6 ALTOS DEL ROSARIO 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/8/2020 100% 7/31/2020 100% 8/22/2020 100%
META 1 7 BARRANCO DE LOBA 5/30/2020 100% 7/11/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 8/8/2020 100% 8/15/2020 100% 8/15/2020 100% 7/31/2020 100% 8/22/2020 100%
META 2 8 TIERRALTA 8/8/2020 100% 9/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 9/18/2020 100% 7/31/2020 100% 11/7/2020 100%
META 2 9 MARIA LA BAJA 8/15/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/10/2020 100% 10/10/2020 100% 10/17/2020 100% 7/31/2020 100% 11/21/2020 100%
META 2 10 MAJAGUAL 7/31/2020 100% 9/30/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/19/2020 100% 9/19/2020 100% 9/30/2020 100% 7/31/2020 100% 10/17/2020 100%
META 2 11 MOÑITOS 8/8/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/10/2020 100% 7/31/2020 100% 10/24/2020 100%
META 2 12 TOLU VIEJO 8/8/2020 100% 10/10/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/10/2020 100% 7/31/2020 100% 10/24/2020 100%
META 2 13 CHINU 9/5/2020 100% 10/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/30/2020 100% 9/30/2020 100% 10/31/2020 100% 7/31/2020 100% 10/31/2020 100%
META 2 14 OVEJAS 8/8/2020 100% 9/30/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/19/2020 100% 9/19/2020 100% 9/30/2020 100% 7/31/2020 100% 10/17/2020 100%
META 2 16 MOMIL 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/31/2020 100% 10/31/2020 100% 11/7/2020 100% 7/31/2020 100% 11/21/2020 100%
META 2 17 CICUCO 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/19/2020 100% 10/19/2020 100% 11/7/2020 100% 7/31/2020 100% 11/21/2020 100%
META 2 18 LOS PALMITOS 9/12/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 11/7/2020 100% 7/31/2020 100% 10/10/2020 100%
META 2 23 SAN BENITO ABAD 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/17/2020 100% 10/17/2020 100% 11/14/2020 100% 7/31/2020 100% 10/31/2020 100%
META 2 24 SAN ANTERO 8/29/2020 100% 10/24/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 9/12/2020 100% 9/12/2020 100% 10/24/2020 100% 7/31/2020 100% 10/10/2020 100%
META 2 25 VILLANUEVA 9/5/2020 100% 10/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/24/2020 100% 10/24/2020 100% 10/31/2020 100% 7/31/2020 100% 9/30/2020 100%
META 2 26 SAMPUES 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/7/2020 100% 10/7/2020 100% 11/14/2020 100% 7/31/2020 100% 9/30/2020 100%
META 2 27 SAN ESTANISLAO 9/30/2020 100% 11/21/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/7/2020 100% 11/7/2020 100% 11/21/2020 100% 7/31/2020 100% 11/14/2020 100%
META 2 28 ZAMBRANO 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/16/2020 100% 11/16/2020 100% 11/20/2020 100% 7/31/2020 100% 11/22/2020 100%
META 2 30 SOPLAVIENTO 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/7/2020 100% 10/7/2020 100% 11/14/2020 100% 7/31/2020 100% 11/30/2020 100%
META 3 42 ARENAL 12/5/2020 100% 12/6/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/14/2020 100% 11/14/2020 100% 11/20/2020 100% 7/31/2020 100% 11/21/2020 100%
META 2 31 SAN CRISTOBAL 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 10/10/2020 100% 10/10/2020 100% 11/14/2020 100% 7/31/2020 100% 10/31/2020 100%
META 3 32 SIMITI 11/21/2020 100% 1/16/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/16/2021 100% 1/16/2021 100% 1/23/2021 100% 7/31/2020 100% 1/23/2021 100%
META 3 33 RIO VIEJO 11/14/2020 100% 1/16/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/21/2021 100% 11/21/2021 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%
META 3 34 SAN PABLO 9/30/2020 100% 11/7/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/30/2020 100% 11/30/2020 100% 1/9/2021 100% 7/31/2020 100% 1/9/2021 100%
META 3 35 PUEBLO NUEVO 10/24/2020 100% 12/5/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/5/2020 100% 12/5/2020 100% 1/9/2021 100% 7/31/2020 100% 12/31/2020 100%
META 3 36 SANTA ROSA DEL SUR 9/30/2020 100% 11/7/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/7/2021 100% 1/7/2021 100% 12/30/2020 100% 7/31/2020 100% 12/19/2020 100%
META 3 37 GALERAS 11/7/2020 100% 1/9/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/31/2020 100% 12/31/2020 100% 1/15/2021 100% 7/31/2020 100% 1/16/2021 100%
META 3 38 MONTECRISTO 11/7/2020 100% 1/9/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/31/2020 100% 12/31/2020 100% 1/15/2021 100% 7/31/2020 100% 1/16/2021 100%
META 3 39 SAN MARTIN DE LOBA 11/7/2020 100% 12/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/25/2021 100% 1/25/2021 100% 1/27/2021 100% 7/31/2020 100% 1/23/2021 100%
META 3 40 TIQUISIO 10/24/2020 100% 12/12/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/25/2021 100% 1/25/2021 100% 1/27/2021 100% 7/31/2020 100% 1/23/2021 100%
META 3 41 MORALES 9/12/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/21/2020 100% 11/21/2020 100% 12/4/2020 100% 7/31/2020 100% 11/30/2020 100%
META 3 43 SAN JACINTO 10/31/2020 100% 12/12/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/12/2020 100% 12/12/2020 100% 12/11/2020 100% 7/31/2020 100% 12/31/2020 100%
META 3 44 VALENCIA 10/31/2020 100% 12/19/2020 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/19/2020 100% 12/19/2020 100% 12/4/2020 100% 7/31/2020 100% 12/19/2020 100%
META 3 45 CALAMAR 11/14/2020 100% 12/31/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/9/2021 100% 1/9/2021 100% 1/15/2021 100% 7/31/2020 100% 1/23/2021 100%
META 3 46 SAN PEDRO 11/21/2020 100% 1/9/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/16/2021 100% 1/16/2021 100% 1/27/2021 100% 7/31/2020 100% 1/30/2021 100%
META 3 47 ARROYOHONDO 12/5/2020 100% 1/23/2021 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/23/2021 100% 1/23/2021 100% 2/11/2021 100% 7/31/2020 100% 2/13/2021 100%
META 3 15 MAHATES 8/22/2020 100% 10/17/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/30/2020 100% 12/30/2020 100% 1/9/2021 100% 7/31/2020 100% 1/9/2021 100%
META 3 19 LA UNION 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%
META 3 20 TUCHIN 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/4/2020 100% 7/31/2020 100% 12/5/2020 100%
META 3 21 SAN JUAN DE BETULIA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/30/2020 100% 12/30/2020 100% 12/30/2020 100% 7/31/2020 100% 12/31/2020 100%
META 3 22 PURISIMA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 12/7/2020 100% 12/7/2020 100% 12/11/2020 100% 7/31/2020 100% 12/12/2020 100%
META 3 29 CLEMENCIA 9/19/2020 100% 11/14/2020 100% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 11/23/2020 100% 11/23/2020 100% 11/28/2020 100% 7/31/2020 100% 11/30/2020 100%
META 3 48 TALAIGUA NUEVO 12/19/2020 100% 2/6/2021 90% 8/10/2020 100% 7/31/2020 100% 7/31/2020 100% 1/23/2021 100% 1/23/2021 100% 1/27/2021 100% 7/31/2020 100% 1/30/2021 100%
%Avance Meta 1 (UT ITAC) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 2 (UT ITAC) 100% 99% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Meta 3 (UT ITAC) 100% 97% 100% 100% 100% 100% 100% 100% 100% 100%
%Avance Proyecto (UT ITAC) 100% 99% 100% 100% 100% 100% 100% 100% 100% 100%