C R O N O G R A M A V A L O R I Z A D O D E E J E C U C I O N D E O B R A

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO

Nº MES 01 MES 02 MES 03 TOTAL


ITEM ACTIVIDAD Dias ( S/. )

OBRAS CIVILES 10,032.50 7,022.75 7,022.75 24,077.99


1.00 OBRAS PROVISIONALES 24
36,806.15 24,537.43 61,343.58
2.00 OBRAS PRELIMINARES 20
31,962.68 19,669.34 51,632.02
3.00 MOVIMIENTO DE TIERRAS 42
334,552.30 66,910.46 401,462.76
4.00 PISOS Y PAVIMENTOS 36
67,002.67 67,002.67
5.00 SARDINELES ARMADOS 28
27,613.48 27,613.48
6.00 PORTICO DE INGRESO ORNAMENTAL CON COBERTURA 12
14,839.48 14,839.48
7.00 PORTICO ORNAMENTAL DE CIRCULACIÓN VEHICULAR CON COBERTURA (TIJERAL) 18
33,932.32 33,932.32
8.00 COLUMNAS ORNAMENTALES INCLINADAS 10
44,136.40 44,136.40
9.00 PORTICO ORNAMENTAL CIRCUNDANTE A PILETA CON COBERTURA DE MADERA 10
33,802.48 33,802.48
10.00 ESTRUCTURA PILETA 8
23,268.19 23,268.19
11.00 BANCAS CURVAS SEGUN DISEÑO 7
2,172.36 2,172.36
12.00 PODIOS DE ASTAS 8
6,597.93 13,195.87 19,793.80
13.00 SALA DE MAQUINAS 12
12,125.66 12,125.66
14.00 CISTERNA (CAP 15M3) 7
5,758.01 5,758.01
15.00 SISTEMA DE RIEGO 2
2,364.24 2,364.24
16.00 JARDINERIA Y AREAS VERDES 22
16,594.20 16,594.20
17.00 OTROS 10

ALUMBRADO PUBLICO 2,008.13 2,008.13


1.00 OBRAS PRELIMINARES 4
10,192.87 10,192.87
2.00 SUM. E INSTALACION DE DUCTOS 12
5,374.04 5,374.04
3.00 SUM. E INSTALACION DE MANHOLES 8
7,027.10 7,027.10 14,054.19
4.00 SUM. E INSTALACION DE CABLES 12
22,329.95 22,329.95
5.00 SUM. E INSTALACION DE POSTES Y PASTORALES 10
15,962.72 15,962.72
6.00 SUM. E INSTALACION DE LUMINARIAS 8
5,442.37 5,442.37
7.00 SUM. E INSTALACION DE ACOMETIDA 6
503.02 503.02
8.00 PRUEBAS ELECTRICAS 2

COSTO DIRECTO TOTAL 105,455.29 684,769.04 127,562.60 917,786.93


GASTOS GENERALES 10.00 % 10,545.53 68,476.90 12,756.26 91,778.69
UTILIDADES 10.00 % 10,545.53 68,476.90 12,756.26 91,778.69
SUB TOTAL 126,546.34 821,722.85 153,075.12 1,101,344.32
I.G.V. 19.00% 19.00 % 24,043.81 156,127.34 29,084.26 209,255.42
TOTAL PRESUPUESTO 150,590.15 977,850.19 182,159.39 1,310,599.73
DESEMBOLSO PARCIAL PROGRAMADO ( S/. ) 150,590.15 977,850.19 182,159.39
DESEMBOLSO ACUMULADO PROGRAMADO ( S/. ) 150,590.15 1,128,440.34 1,310,599.73
AVANCE PARCIAL DE OBRA (%) 11.49 74.61 13.90
AVANCE ACUMULADO DE OBRA (%) 11.49 86.10 100.00
RESUMEN DE PRESUPUESTO

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE

FECHA : MARZO DEL 2010

TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO

TOTAL GASTOS UTILIDAD SUB TOTAL I.G.V. TOTAL


SECCION COSTO GENERALES VALOR 19.00% VALOR
DESCRIPCION
N° DIRECTO 10.00% 10.00% REFERENCIAL REFERENCIAL
(S/.) (S/.) (S/.) (S/.) (S/.) (S/.)

1.00 OBRAS CIVILES 841,919.64 84191.96 84191.96 1,010,303.56 191,957.68 1,202,261.24


2.00 ALUMBRADO PUBLICO 75,867.29 7586.73 7586.73 91,040.75 17,297.74 108,338.49

TOTAL 917,786.93 91778.69 91778.69 1,101,344.31 209,255.42 1,310,599.73


CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : OBRAS CIVILES

RECURSOS UNID CANT MES 01 MES 02 MES 03


ABRASIVOS N° 24-60-100 pza 83.43 83.43
ABRAZADERAS DE FIERRO FUNDIDO (PRECIO PROMEDIO) u 1.00 1.00
ACEITE PARA MOTOR SAE-30 gal 0.45 0.45
ADOQUIN DE CONCRETO 4x10x20CM COLOR GRIS m2 105.11 105.11
ADOQUIN DE CONCRETO 4x10x20CM COLOR ROSADO m2 471.07 471.07
AGUA m3 304.51 101.50 101.50 101.50
ALAMBRE NEGRO # 8 kg 91.59 91.59
ALAMBRE NEGRO # 16 kg 503.85 503.85
ALAMBRE NEGRO RECOCIDO # 8 kg 47.97 47.97
ANGULO DE ACERO LIVIANO DE 1 1/2" x 3/16" pza 68.60 68.60
ANGULO DE ACERO LIVIANO DE 1" x 1/8" pza 41.67 41.67
ARENA FINA m3 56.45 42.34 14.11
ARENA GRUESA m3 271.14 271.14
ASFALTO RC-250 PARA JUNTA I/FLETE gal 15.55 15.55
BANCA TIPO COLONIAL INC. SOPORTES Y ANCLAJE u 40.00 40.00
BOTADERO DE FIBRA DE VIDRIO S/DISEÑO INC. SOPORTES Y ANCLAJE u 20.00 20.00
CAJA DE CONCRETO AGUA DE 12"x12" u 20.00 20.00
CAJA DE CONCRETO PARA MEDIDOR AGUA u 1.00 1.00
CAL HIDRATADA DE 25 Kg bls 42.32 42.32
CAÑA u 185.75 185.75
CARTEL DE OBRA 3.60 X 2.40 M glb 1.00 1.00
CARTEL INFORMATIVO 1.20x1.20m u 4.00 4.00
CEMENTO BLANCO BOLSA 50 kg bls 19.40 19.40
CEMENTO PORTLAND TIPO I (42.5 kg) bls 2617.89 2617.89
CEMENTO PORTLAND TIPO MS bls 1602.44 1602.44
CERA SELLADORA PRC gal 42.04 42.04
CINTA DE SEÑALIZACION 5" C/TEXTO rll 2.00 2.00
CINTA TEFLON rll 13.50 13.50
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : OBRAS CIVILES
CLAVOS CON CABEZA P/CONSTRUCCION PROMEDIO kg 29.39 29.39
CLAVOS CON CABEZA P/CONSTRUCCION PROMEDIO kg 77.06 77.06
CLAVOS PARA MADERA CON CABEZA DE 3" kg 27.44 27.44
CODO PVC SAP 1 1/2" X 90° u 1.00 1.00
CODO PVC SAP 3/4" X 90° pza 19.00 19.00
COMPOST ORGANICO kg 5.00 5.00
CORPORATION RT-NIPLE-TUERCA-EMPAQ. 1 1/2" u 1.00 1.00
CORREA DE MADERA TORNILLO 4"x2"x6.50m u 343.80 343.80
DISCO DE CORTE pza 18.11 18.11
DISCO DE CORTE DE 9" pza 11.32 11.32
DISCO LIJADOR DE 9" pza 0.34 0.34
ESTERA DE 2.00 X 3.00 m u 122.60 122.60
FERTILIZANTE bls 2.00 2.00
FERTILIZANTE ECOLOGICO (Estiercol) kg 0.50 0.50
FICUS BENJAMINA H= 1.50M. u 1.00 1.00
FIERRO CORRUGADO kg 8167.29 8167.29
FLETE kg 200000.00 100000.00 100000.00
GASOLINA 84 OCTANOS gal 30.52 30.52
GRANALLA BLANCO N° 01 bls 155.21 155.21
GRAS EN CHAMPAS m2 1.02 1.02
HORMIGON m3 350.70 350.70
HUMUS kg 2.00 2.00
LIJA DE ACERO plg 6.00 6.00
LLAVE PASO RT-NIPLE-TUERCA-EMPAQ. 1 1/2" u 1.00 1.00
MADERA CAOBA (p2) p2 760.97 760.97
MADERA TORNILLO p2 3064.80 3064.80
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 672.95 672.95
MARCO Y TAPA DE CONCRETO P/CAJA AGUA 12"x12" u 20.00 20.00
MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" u 1.00 1.00
MARMOL DE COLOR BEIGE E=2cm m2 248.48 248.48
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : OBRAS CIVILES
MARMOL DE COLOR CREMA MARFIL E=2cm m2 247.38 247.38
MARMOL DE COLOR GRIS E=2cm m2 311.12 311.12
MARMOL DE COLOR OCEAN FASTIC E=2cm m2 312.38 312.38
MARMOLINA N° 18 bls 48.50 48.50
MATERIAL AFIRMADO m3 375.97 375.97
NIPLE DE F° GALV. DE 3/4" X 1 1/4" pza 19.00 19.00
NIPLE DE FIERRO GALVANIZADO DE 1 1/2" X 1 1/2" pza 2.00 2.00
NIPLE PVC 7.5 X 1 1/2"-REEMP MEDIDOR u 1.00 1.00
OCRE kg 35.57 35.57
OFICINA, ALMACEN Y CASETA DE GUARDIANIA glb 1.00 1.00
OXIGENO m3 8.23 8.23
PALOS DE EUCALIPTO 3.0 M pza 122.60 122.60
PARANTES DE MADERA 2",H=1.20m C/BASE CONCRETO 0.30x0.30m u 18.00 18.00
PEGAMENTO PARA PVC AGUA FORDUIT gal 3.27 3.27
PERNO PASANTE FIERRO GALVANIZADO 1/2" X 8" pza 687.60 687.60
PIEDRA CHANCADA DE 1/2" - 3/4" m3 48.81 48.81
PIEDRA CHANCADA DE 1/2" m3 45.68 45.68
PIEDRA CHANCADA DE 2" m3 16.46 16.46
PIEDRA CHANCADA DE 3/4" m3 0.41 0.41
PINTURA ANTICORROSIVA EPOXICA gal 1.95 1.95
PINTURA ESMALTE EPOXICA gal 1.80 1.80
PLANCHA ACERO E= 3/8" APOYO Y ANCLAJES u 3.00 3.00
PLANCHA TECNOPOR DE 1.22x2.44x1" u 4.95 4.95
PLANTA PALMERAS H=8.00m u 1.00 1.00
PLANTA PONCIANA O SIMILAR H=4.00m u 1.00 1.00
PLATINA ALUMINIO COD 2510 m 205.37 205.37
PLATINA DE ACERO DE 1/8" X 2" X20 pza 0.21 0.21
REDUCCION PVC 1 1/2" A 3/4" pza 20.00 20.00
REGLA DE MADERA p2 156.49 156.49
SENAL INFORMATIVA Y/O RESTRICTIVA 0.40x0.40m u 4.00 4.00
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : OBRAS CIVILES
SOLDADURA kg 27.78 27.78
SOLDADURA CELLOCORD kg 2.40 2.40
SOPORTE DE TUBERIA FºGº PARA LUMINARIA SEGUN DETALLE u 10.00 10.00
TEE PVC SAP 1 1/2" SP P/AGUA u 20.00 20.00
TERRAZO COLOR CREMA MARRON CLARO m2 71.82 71.82
THINNER gal 1.50 1.50
TIERRA DE CULTIVO m3 1.00 1.00
TUBERIA PVC SAP C-10 DE 1 1/2" m 42.02 42.02
TUBERIA PVC SAP C-10 DE 1 1/4" m 61.80 61.80
TUBERIA PVC SAP C-10 DE 1" m 48.41 48.41
TUBERIA PVC SAP C-10 DE 2" m 39.14 39.14
TUBERIA PVC SAP C-10 DE 3/4" m 186.33 186.33
TUBO DE FIERRO DE 2 PULG. x 6.4 u 1.80 1.80
TUBO DE FIERRO DE 3 PULG. x 6.4 u 1.20 1.20
TUBO DE FIERRO DE 4 PULG. x 6.4 u 1.20 1.20
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 1 1/2" u 2.00 2.00
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 3/4" u 19.00 19.00
VALVULA CIERRE RAPIDO BRONCE 3" u 1.00 1.00
VALVULA DE GLOBO DE BRONCE DE 3/4" pza 19.00 19.00
TOTAL 224077.39 101163.46 122793.31 120.62
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : ALUMBRADO PÚBLICO

RECURSOS UNID CANT MES 01 MES 02 MES 03


ALAMBRE NEGRO # 16 kg 4.41 4.41
FIERRO CORRUGADO 3/8" kg 131.04 131.04
ARENA FINA m3 0.08 0.08
TIERRA DE CHACRA O VEGETAL m3 1.20 1.20
THOR GEL (Dosis 5 Kg) bls 2.00 2.00
RIPIO m3 41.01 41.01
ARENA GRUESA m3 75.96 75.96
CINTA AISLANTE 3/4"x20m rll 18.58 9.29 9.29
CABLE DE COBRE DESNUDO 25mm m 12.00
CONECTOR TIPO AB COPPERWELD pza 1.00
BASE ACOPLAMIENTO DE F°G° EMBONE Y SOPORTE LUMINARIA pza 36.00
VARILLA DE COBRE DE 1/2" x 2.40m u 1.00
ALAMBRE GUIA m 692.64
GABINETE METALICO C/CERRADURA 08 POLOS pza 1.00
LUMINARIA ORNAMENTAL C/LAMPARA V. S. 70W u 72.00
REFLECTOR SUBACUATICO 500W/12V EN BRONCE Y LUNAS DE COLOR pza 8.00
TABLERO ELECTRICO DE CONTROL ENCENDIDO DE REFLECTORES-KIT u 1.00
TABLERO ELECTRICO DE CONTROL DE BOMBAS C/TIMER - KIT u 1.00
CAJA PORTAMEDIDOR - TRIFASICO pza 1.00
CAJA PORTAFUSIBLE PARA POSTE C/FUSIBLE UNIPOLAR pza 36.00
LADRILLO ARCILLA KK 9 X13X24 CM u 150.00
CABLE ELECTRICO NYY 2 X 4 mm2 m 6.12
CABLE ELECTRICO NYY 3 - 1x 25mm2 m 69.62
CABLE ELECTRICO NYY 1 - 1x10mm2 m 69.62
CABLE ELECTRICO NYY 2 - 1x 6mm2 m 628.64
CABLE ELECTRICO NYY 2 - 1x10mm2 m 326.40
CABLE ELECTRICO NYY 3 - 1x 10mm2 m 10.00
CABLE ELECTRICO NYY 1 X 2.5 mm2 m 6.12
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : ALUMBRADO PÚBLICO

CABLE NLT EXTRAFLEXIBLE 2 X 2.5 mm2 m 378.00


CEMENTO PORTLAND TIPO I (42.5 kg) bls 113.56
TERMINAL DE COBRE PARA 16mm u 3.00
MEDIDOR ELECTRONICO TRIFASICO A1R, 5A CLASE 0.2 pza 1.00
CAL HIDRATADA DE 30 Kg bls 6.93
CINTA SEÑALADORA AMARILLA pza 69.62
EMPALME UNIPOLAR 3M-0 pza 35.95
CINTA SEÑALADORA AMARILLA m 847.04
CABLE DE ENERGIA BIPLASTOFLEX 2x4mm2 m 24.93
PEGAMENTO gal 2.43
CINTA BANDIT 3/4" m 4.00
HEBILLAS BAND IT 3/4" u 3.00
MARCO Y TAPA DE CONCRETO REFORZADO u 1.00
CURVAS PVC SAP 3" pza 2.00
HORMIGON m3 0.18
AGUA m3 6.41
MADERA TORNILLO p2 23.22
POSTE DE C.A.C. 7m/100 u 36.00
TERMINAL 25mm pza 5.46
TERMINAL 6mm2 u 43.83
TERMINAL 10mm2 u 28.60
PINTURA ESMALTE SINTETICO gal 0.69
IMPERMEABILIZANTE CRISTAFLEX gal 4.50
DUCTO DE CONCRETO DE 2 VIAS pza 9.45
TUBERIA DE FIERRO GALV. 3"x6m u 2.00
CURVA PESADO PVC SAP P/INST. ELECT. 1" u 2.00
TUB. PVC SAP P/INST. ELECT. DE 2" x 3m u 12.68
TUB. PVC SAP P/INST. ELECT. DE 1" m 207.55
TUB. PVC SAP P/INST. ELECT. DE 4" x 3m tub 23.89
CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO
SUB-PRESUPUESTO : ALUMBRADO PÚBLICO

TUB. PVC SAP P/INST. ELECT. DE 1" m 216.00


TOTAL 4518.33 0.00 0.00 0.00
ANALISIS DE GASTOS GENERALES Y UTILIDAD

: CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE


OBRA
OCTUBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO

1,00 GASTOS GENERALES FIJOS 44,971.56


No Relacionados con el tiempo de Ejecución de la Obra

1,01 Gastos de Licitación y Contratación:


Documentos de Presentación 1,471.56
Visita a zona de ejecución de la Obra 2,000.00
Notariales 3,500.00
Póliza de Seguros contra todo riesgo (CAR) 10,000.00
Fianza por Garantía de Beneficios Sociales de los Trabajadores 6,000.00
Elaboración de la Propuesta 3,000.00
Avisos de Convocatoria y Buena Pro 1,500.00

1,02 Gastos Indirectos Varios:


Legales y Notariales de la Organización 2,500.00
Inscripción en el Registro Nacional de Contratistas 2,000.00
Seguro de las instalaciones de la Empresa 8,000.00
Obligaciones Fiscales 3,000.00
Pruebas de calidad de concreto y ensayos compactación de suelos 2,000.00

TOTAL GASTOS GENERALES FIJOS: 44,971.56

2,00 GASTOS GENERALES VARIABLES 46,807.13


Relacionados Directamente con el tiempo de Ejecución de la Obra

2,01 Gastos de Administración en Obra:


Ingeniero Residente 1X 3 Meses 10,500.00
Ingeniero Asistente 1X 3 Meses 7,500.00
Maestro de Obra 1X 3 Meses 7,500.00

Almacenero-Asistente 1X 3 Meses 4,500.00

Guardianía 1X 3 Meses 4,500.00

Vehiculos para Movilidad


Camioneta Operada 1X 3 Meses 1,507.13

2,02 Gastos de Administración en Oficina:

Sueldos, Bonif. y Benef. Personal Directivo


0,2X 3 Meses 3,600.00
Sueldos, Bonif. y Benef. Personal Administrativo
Contador 0,2X 3 Meses 3,600.00
Secretaria 0,2X 3 Meses 3,600.00

TOTAL GASTOS GENERALES VARIABLES: 46,807.13

TOTAL GASTOS GENERALES FIJOS Y VARIABLES: 91,778.69


UTILIDAD: 56,403.31

TOTAL GASTOS GENERALES Y UTILIDAD 148,182.00

DESAGREGADO DE LOS GASTOS GENERALES

* DESCONSOLIDACION DE LOS GASTOS GENERALES Y UTILIDAD

GASTOS GENERALES 91,778.69 10.00%

UTILIDAD 91,778.69 10.00%

COSTO DIRECTO 917,786.93

* DESCOMPOSICION DE LOS GASTOS GENERALES

NO RELACIONADOS DIRECTAMENTE CON EL 44,971.56 4.90%


TIEMPO DE EJECUCIÓN DE LA OBRA (FIJOS)

RELACIONADOS DIRECTAMENTE CON EL 46,807.13 5.10%


TIEMPO DE EJECUCIÓN DE LA OBRA (VARIABLES)
TOTAL 10.00%
CRONOGRAMA DE DESEMBOLSOS

OBRA : CONSTRUCCION DE PARQUE CENTRAL DEL PJ. 3 DE OCTUBRE


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE NUEVO CHIMBOTE
FECHA : MARZO DEL 2010
TIEMPO DE EJECUCIÓN : 90 DÍAS CALENDARIO

MONTO EN NUEVOS SOLES


DIAS ADELANTOS VALORIZACION TOTAL DESEMBOLSOS
CALENDARIO EFECTIVO MATERIALES TOTAL PRESUPUESTAL PRESUPUESTO I.G.V.
20% 40% PARCIAL PARCIAL 19%
(1) (2) (1+2) (3) 3-(1+2)
220,268.86 440,537.73 660,806.59 660,806.59 125,553.25
30 25,309.27 50,618.54 75,927.81 126,546.34 50,618.54 9,617.52
60 164,344.57 328,689.14 493,033.71 821,722.85 328,689.14 62,450.94
90 30,615.02 61,230.05 91,845.07 153,075.12 61,230.05 11,633.71

TOTALES 1,101,344.32 1,101,344.32 209,255.42