Gestión del valor ganado


Edificación de 37 viviendas y garajes

2,483,090
Objetivo
BAC
Totales Variación Índice de desempeño
Valor Valor
Producción Coste real Del coste Del cronograma Del coste Del cronograma
Fase Certificación Producción ganado planificado
planificada AC CV SV CPI SPI
EV PV

EV-AC EV-PV EV/AC EV/PV


1 102,265 102,265 102,265 81,788 81,788 81,788 0 0 1.00 1.00
2 224,664 224,664 224,664 191,529 179,669 179,669 -11,860 0 0.94 1.00
3 332,524 332,524 332,524 301,529 265,949 265,949 -35,580 0 0.88 1.00
4 440,384 359,489 359,489 329,029 287,519 352,229 -41,510 -64,710 0.87 0.82
5 671,001 575,128 575,128 513,057 459,687 536,378 -53,370 -76,691 0.90 0.86
6 842,242 681,420 681,420 609,892 544,662 673,293 -65,230 -128,631 0.89 0.81
7 1,060,961 1,047,408 1,069,188 969,966 854,662 848,079 -115,304 6,583 0.88 1.01
8 1,258,697 1,173,125 1,194,905 1,075,909 955,101 1,006,204 -120,808 -51,102 0.89 0.95
9 1,461,401 1,488,716 1,510,496 1,363,356 1,207,628 1,168,449 -155,728 39,179 0.89 1.03
10 1,665,907 1,789,972 1,811,752 1,604,446 1,448,718 1,332,068 -155,728 116,650 0.90 1.09
11 1,868,790 1,494,350
12 2,066,325 1,652,400
13 2,255,704 1,803,916
14 2,433,951 1,946,666
15 2,599,543 2,079,148
16 2,749,393 2,199,039
17 2,899,609 2,319,215
18 3,002,223 2,401,273
19 3,104,720 2,483,090
19

Estimaciones Desviaciones Fechas


Coste Programación Ejecución de
EAC En programación Estimada
EAC EAC (CPI) probable En planificación ganada la producción
(CPI·SPI) SV(t) AT
EAC ES planificada

2,483,090 2,483,090 2,483,090 2,597,968 0 0 7/31/2012 7/31/2012 7/31/2012


2,494,950 2,647,000 2,647,000 2,597,968 0 0 8/31/2012 8/31/2012 8/31/2012
2,518,670 2,815,291 2,815,291 2,597,968 0 0 9/30/2012 9/30/2012 9/30/2012
2,524,600 2,841,582 3,407,067 2,597,968 -23 NA 10/31/2012 11/22/2012 Retraso
2,536,460 2,771,379 3,148,140 2,597,968 -12 NA 11/30/2012 12/12/2012 Retraso
2,548,320 2,780,471 3,293,088 2,597,968 -28 NA 12/31/2012 1/28/2013 Retraso
2,598,394 2,818,088 2,803,852 2,597,968 1 -1 1/31/2013 1/29/2013 1/31/2013
2,603,898 2,797,169 2,889,265 2,597,968 -10 NA 2/28/2013 3/9/2013 Retraso
2,638,818 2,803,294 2,756,578 2,597,968 7 -5 3/31/2013 3/23/2013 4/4/2013
2,638,818 2,750,007 2,657,767 2,597,968 22 -15 4/30/2013 4/8/2013 5/14/2013
2,638,818 2,750,007 2,657,767 2,597,968 24 -16 5/31/2013 5/7/2013 6/15/2013
2,638,818 2,750,007 2,657,767 2,597,968 26 -17 6/30/2013 6/4/2013 7/17/2013
2,638,818 2,750,007 2,657,767 2,597,968 28 -19 7/31/2013 7/2/2013 8/18/2013
2,638,818 2,750,007 2,657,767 2,597,968 30 -20 8/31/2013 7/31/2013 9/20/2013
2,638,818 2,750,007 2,657,767 2,597,968 32 -22 9/30/2013 8/28/2013 10/21/2013
2,638,818 2,750,007 2,657,767 2,597,968 35 -23 10/31/2013 9/26/2013 11/23/2013
2,638,818 2,750,007 2,657,767 2,597,968 37 -25 11/30/2013 10/24/2013 12/24/2013
2,638,818 2,750,007 2,657,767 2,597,968 39 -26 12/31/2013 11/22/2013 1/26/2014
2,638,818 2,750,007 2,657,767 2,597,968 41 -28 1/31/2014 12/21/2013 Obra finalizada
EVM. Gestión del valor ganado

4,000,000 Producción
planificada

Certificación
3,500,000
Producción

3,000,000 Estimación a
la conclusión
EAC

2,500,000 Estimación a
la conclusión
EAC (CPI)

2,000,000
Estimación a
la conclusión
EAC (CPI·SPI)
1,500,000
Coste prob-
able EAC

1,000,000 Coste real AC

Valor ganado
500,000 EV

Valor plani-
ficado PV
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19