ACTIVIDAD. PROYECTO
PAVIMENTO
COAPECHACA UNIDAD
3
INSTITUTO TECNOLÓGICO DE CERRO
LOPEZ PIEDAD BEATRIZ
AZUL 20500046 RAMIREZ
BAUTISTA JAIME GAEL
205000
MAQUINARIA PESADA Y MOVIMIENTO DE TIERRA
DOCENTE INGENIERO
SERGIO ARRIETA VERA
CONTENIDO
PRESUPUESTO DE OBRA___________________________________________3
DIAGRAMA DE MASAS_____________________________________________34
PRESUPUESTO DE OBRA
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
EQUIPO RENDIMIENTO
Desmonte. 111.8m2/hr
TRACTOR DE CADENAS CATERPILLAR D6D DE 140
HP.
Despalme. 83.32m3/hr
Desalojo. 89.32m3/hr
RETROEXCAVADORA CATERPILLAR 225 DE 90HP.
Excavación 88.72m3/hr
60∗E∗Q∗K
R= ; ( M 3/ H )
T∗FV
Donde:
Cambio de
2 0.33min
engranaje
Velocidad ida 2.4km/h 0.75min
Velocidad vuelta 4km/h 0.45min
1.53min
SUSTITUCION DE DATOS
DATOS:
· E = 81%
· Q = 3.2M
· K = 0.75
· FV= 1
· T= 1.53m
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
60∗E∗Q∗K
R= ; ( M 3/ H )
T∗FV
60∗0.81∗3.2m∗1.1
R= =111.8 m 2/h
1.53 m∗1
60∗E∗Q∗K
R= ; ( M 3/ H )
T∗FV
Donde:
PORCENTAJE DE
CLASES DE TIERRA
ABUNDAMIENTO
ARCILLA de 30 a 60%
Cambio de
2 0.33min
engranaje
Velocidad ida 2.4km/h 0.75min
Velocidad vuelta 4km/h 0.45min
1.53min
SUSTITUCION DE DATOS
DATOS:
· E = 81%
· Q = 3.1m3
· K = 1.1
· FV= 1.30
· T= 1.53m
60∗E∗Q∗K
R= ; ( M 3/ H )
T∗FV
60∗0.81∗3.1m 3∗1.1
R= =80.23 m 3/h
1.53m∗1.30
( 3600 ) Q E K
R=
T∗FV
Donde:
· R = rendimiento de la maquina (M3/H medidos en el banco)
· Q = capacidad o volumen del cucharon
· F = factor de conversión de los suelos
· E= factor de rendimiento de la maquina
· K= factor de llenado del cucharon (depende de las dimensiones y capacidad del cucharon)
· FV = factor de abundamiento
· T = tiempo de ciclo (segundos)
Material excavado
Arcilla húmeda o arenosa 1.15 1.15 1.15 1.16 1.16 1.16 1.20 1.22
Arena o grava 0.93 0.93 0.96 0.96 0.96 0.98 1.02 1.02
Tierra común compactada 1.00 1.00 1.00 1.05 1.05 1.05 1.08 1.08
Arcilla dura y tenaz 1.10 1.10 1.10 1.12 1.12 1.12 1.16 1.18
Arcilla cohesiva humeda 1.10 1.10 1.10 1.12 1.12 1.12 1.16 1.18
Roca bien tronada 0.60 0.70 0.70 0.80 0.80 0.90 0.95 0.95
Escombros con piedras 0.85 0.85 0.90 0.90 0.90 0.95 0.95 0.95
ABUNDAMIENTO
ARCILLA de 30 a 60%
SUSTITUCION DE DATOS
Datos:
· Q = 0.8m3
· E= 0.81
· K= 1.0
· FV = 1.30
· T = 20
( 3600 ) Q E K
R=
T∗FV
Q∗E∗60
R=
Cm∗F
Donde:
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
PORCENTAJE DE
CLASES DE TIERRA
ABUNDAMIENTO
ARCILLA de 30 a 60%
tf =tc+td
tf =4 MIN +1 MIN
tf =5 MIN
Dx 60 Dx 60
tv= +
Vc Vd
1 x 60 1 x 60
tv= +
15 KM / H 2 KM / H
tv=7 MIN
SUSTITUCION DE DATOS
Datos:
· Q = 14m3.
· Cm=12m
· F=1.30
· E =83%
SUSTITUCION DE DATOS
Q∗E∗60
R=
Cm∗F
14 m3∗0.83∗60
R= =44.69 m3 /h
12 m∗1.3
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
( 3600 ) Q E K
R=
T∗FV
Donde:
· R = rendimiento de la maquina (M3/H medidos en el banco)
· Q = capacidad o volumen del cucharon
· F = factor de conversión de los suelos
· E= factor de rendimiento de la maquina
· K= factor de llenado del cucharon (depende de las dimensiones y capacidad del cucharon)
· FV = factor de abundamiento
· T = tiempo de ciclo (segundos)
Material excavado
Arcilla húmeda o arenosa 1.15 1.15 1.15 1.16 1.16 1.16 1.20 1.22
Arena o grava 0.93 0.93 0.96 0.96 0.96 0.98 1.02 1.02
Tierra común compactada 1.00 1.00 1.00 1.05 1.05 1.05 1.08 1.08
Arcilla dura y tenaz 1.10 1.10 1.10 1.12 1.12 1.12 1.16 1.18
Arcilla cohesiva humeda 1.10 1.10 1.10 1.12 1.12 1.12 1.16 1.18
Roca bien tronada 0.60 0.70 0.70 0.80 0.80 0.90 0.95 0.95
Escombros con piedras 0.85 0.85 0.90 0.90 0.90 0.95 0.95 0.95
PORCENTAJE DE
CLASES DE TIERRA
ABUNDAMIENTO
ARCILLA de 30 a 60%
SUSTITUCION DE DATOS
Datos:
· Q = 0.8m3
· E= 0.81
· K= 1.0
· FV = 1.30
· T = 20
( 3600 ) Q E K
R=
T∗FV
Q∗E∗60
R=
Cm∗F
Donde:
· Q = Capacidad normal del cucharon.
· F = Factor de esponjamiento.
· E = Eficiencia
· Cm=tiempo de ciclo.
PORCENTAJE DE
CLASES DE TIERRA
ABUNDAMIENTO
ARCILLA de 30 a 60%
tf =tc+td
tf =4 MIN +1 MIN
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
tf =5 MIN
Dx 60 Dx 60
tv= +
Vc Vd
3.1 x 60 3.1 x 60
tv= +
15 KM /H 20 KM / H
tv=21.7 MIN
SUSTITUCION DE DATOS
Datos:
· Q = 14m3.
· Cm=26.7m
· F=1.30
· E =83%
SUSTITUCION DE DATOS
Q∗E∗60
R=
Cm∗F
14 m3∗0.83∗60
R= =20.08 m3/h
21 m∗1.3
D∗N D∗N
T= +
S∗E S 1∗E
Donde:
· D = distancia recorrida en cada pasada
· N = número de pasadas que se requiera para realizar el trabajo.
· E = factor de rendimiento del trabajo.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
RENDIMIENTO
D∗A
R=
T
Donde:
V × δ ×C
R=A × ×10
N
Donde:
· A= Ancho efectivo de la de la faja roturada
· V= Velocidad de operación (km/hr)
· δ=¿ Distancia
· C= Carga o copeteo
· N= Número de pasadas que se requiera para realizar el trabajo.
DATOS
SUSTITUCION DE DATOS
Km
2.5 × 470.731m× 0.7
h
R=3 m× ×10
4
R=6.16875 Km / h
60
Q=C ( )E
Tc
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
Donde:
· C= Carga o copeteo
· Tc= Tiempo total de carga del camión
· E= Factor de rendimiento del trabajo.
Datos:
· C= 8000 L
· Tc= 57.97745min
· DE LA SIGUIENTE TABLA TOMAREMOS EL VALOR CORRESPONDIENTE A LA
EFICIENCIA DE TRABAJO EN LA OBRA, COMO LAS CONDICIONES DE LA OBRA SON
EXCELENTES Y LA GESTION BUENA EL COEFICIENTE SERA DE 0.81
SUSTITUCION DE DATOS:
Q=8000 L ( 57.97745
60
M)
× .83 %=6871.637 l/h
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
R=V × L× E
Donde:
· V= Velocidad de operación (km/hr)
· L= Largo de la barra espaciadora.
· E= Factor de rendimiento del trabajo.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
Datos:
· V= 12000 m/h
· L= 3m
· DE LA SIGUIENTE TABLA TOMAREMOS EL VALOR CORRESPONDIENTE A LA
EFICIENCIA DE TRABAJO EN LA OBRA, COMO LAS CONDICIONES DE LA OBRA SON
EXCELENTES Y LA GESTION BUENA EL COEFICIENTE SERA DE 0.81
R=29,880 m2/h
60 × S ×W
R=E ×D
N
Donde:
· E= Factor de eficiencia de la maquina
· S= Velocidad
· W= Factor de eficacia
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
· D= Distancia
· N= Número de pasadas que se requieren para realizar el trabajo
SUSTITUCION DE DATOS
km
60 × 2.25 ×1
h
R=81 % ×.30 m
5
3
R=6.723 m /h
V
R=E× 60 ×W × D
N
Donde:
· E= Factor de eficiencia de la maquina
· V= Velocidad de operación (km/hr)
· W=Factor de eficacia
· D= Distancia recorrida en cada pasada
· N= Número de pasadas que se requiera para realizar el trabajo.
Datos:
· E=83%
· V= 2.25 Km/h
· W=1m
· D= 3m
· N= 4
SUSTITUCION DE DATOS
2.25 Km/ H
R=83 % ×60 × × 1m ×3 m
4
3
R=8.40375 m /h
δ
R=A × V × C ×10
N
Donde:
· A= Ancho efectivo de la faja roturada
· V= Velocidad de operación (km/hr)
· D=¿ Distancia
· N= Número de pasadas que se requiera para realizar el trabajo.
Datos:
· A= 3m
· V=5 Km/h
· D=30 m
· N=3
SUSTITUCION DE DATOS
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
.30 m
R=3 m×5 Km /H (0.8)(10)
3
R=12m3 /h
60 × D × e × L
R= ×E
T ( 1+h )
Donde:
· D= Distancia
· e= Espesor
· L= Ancho
· T= Tiempo
· h= Factor de relación
· E= Eficiencia de la maquinaria
Datos:
· D= 50m
· e=0.30m
· L= 3m
· T=10min
· h= 1.00
· E= 83%
SUSTITUCION DE DATOS
60 ×50 m ×.30 m× 3 m
R= ×83 %
10 m ( 1+1 )
3
R=112.05m /h.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
COTAS ESPESOR ÁREAS A1 + A2 VOLUMEN COEF. DE ABUND. 30% VOLÚMENES ABUNDADOS SUMA ALGEBRÁICA
DISTANCIA
ESTACIÓN ORDENADA
MEDIA
T.N RAS. CORTE TERRAPLEN CORTE TERRAPLEN CORTE TERRAPLEN CORTE TERRAPLEN CORTE TERRAPLEN CORTE TERRAPLEN + (CORTE) - (TERRAPLEN)
0+000.00 197.676 198.547 0.871 0.00 18.04 0.00 18.04 0.00 5000
0+020.00 200.610 200.663 0.053 0.10 2.74 0.10 20.78 10.00 1.00 207.80 1.3 1.30 207.80 206.50 4793.50
0+040.00 203.295 203.131 0.164 5.41 0.23 5.52 2.97 10.00 55.20 29.70 1.3 71.76 29.70 42.06 4835.56
0+060.00 205.820 205.353 0.467 7.61 0.00 13.02 0.23 10.00 130.20 2.30 1.3 169.26 2.30 166.96 5002.52
0+080.00 207.857 207.200 0.657 12.33 0.00 19.94 0.00 10.00 199.40 0.00 1.3 259.22 0.00 259.22 5261.74
0+100.00 209.184 208.691 0.493 10.00 0.00 22.33 0.00 10.00 223.30 0.00 1.3 290.29 0.00 290.29 5552.03
0+120.00 210.360 209.799 0.561 9.23 0.00 19.22 0.00 10.00 192.20 0.00 1.3 249.86 0.00 249.86 5801.89
0+140.00 210.325 210.354 0.029 0.32 1.31 9.55 1.31 10.00 95.50 13.10 1.3 124.15 13.10 111.05 5912.94
0+160.00 209.902 210.616 0.714 0.00 8.87 0.32 10.18 10.00 3.20 101.80 1.3 4.16 101.80 97.64 5815.30
0+180.00 209.921 210.739 0.818 0.00 9.80 0.00 18.67 10.00 0.00 186.70 1.3 0.00 186.70 186.70 5628.60
0+200.00 210.594 210.915 0.321 0.06 4.81 0.06 14.62 10.00 0.60 146.20 1.3 0.78 146.20 145.42 5483.18
0+220.00 211.490 211.271 0.219 0.91 0.53 0.97 5.34 10.00 9.70 53.40 1.3 12.61 53.40 40.79 5442.39
0+240.00 211.761 211.666 0.095 0.39 0.64 1.30 1.17 10.00 13.00 11.70 1.3 16.90 11.70 5.20 5447.59
0+260.00 212.388 212.062 0.326 3.85 0.02 4.24 0.66 10.00 42.40 6.60 1.3 55.12 6.60 48.52 5496.11
0+280.00 213.182 212.290 0.892 9.83 0.00 13.68 0.02 10.00 136.80 0.20 1.3 177.84 0.20 177.64 5673.75
0+300.00 213.235 212.143 1.092 12.86 0.00 22.69 0.00 10.00 226.90 0.00 1.3 294.97 0.00 294.97 5968.72
0+320.00 212.056 211.746 0.310 4.48 1.78 17.34 1.78 10.00 173.40 17.80 1.3 225.42 17.80 207.62 6176.34
0+340.00 209.853 211.284 1.431 0.00 23.90 4.48 25.68 10.00 44.80 256.80 1.3 58.24 256.80 198.56 5977.78
0+360.00 209.437 211.057 1.62 0.00 22.11 0.00 46.00 10.00 0.00 460.00 1.3 0.00 460.00 460.00 5517.78
0+380.00 210.935 211.441 0.506 0.00 6.43 0.00 28.54 10.00 0.00 285.40 1.3 0.00 285.40 285.40 5232.38
0+400.00 211.969 212.046 0.077 0.34 2.42 0.34 8.86 10.00 3.40 88.60 1.3 4.42 88.60 84.18 5148.20
0+420.00 213.099 212.975 0.124 0.55 3.79 0.88 6.21 10.00 8.80 62.10 1.3 11.44 62.10 50.66 5097.54
0+440.00 214.044 213.736 0.308 2.16 0.27 2.71 4.06 10.00 27.10 40.60 1.3 35.23 40.60 5.37 5092.17
0+460.00 214.902 214.833 0.069 3.01 3.01 5.17 3.29 10.00 51.70 32.90 1.3 67.21 32.90 34.31 5126.48
0+470.75 215.130 215.080 0.05 0.00 0.00 3.01 3.01 5.375 16.18 16.18 1.3 21.03 16.18 4.85 5131.33
1654.78
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
Dentro de la tabla para el cálculo del diagrama de masas contamos con los siguientes datos:
En primer lugar, contamos con los cadenamientos los cuales se tomaron cada 20 metros de distancia, comenzamos con un cadenamiento de 0+000.00m y finalizamos con un cadenamiento de
0+470.00m, como segundo apartado tenemos las cotas las cuales se dividen en T.N (Terreno) y en RAS. (Rasante o Subrasante), para el terreno tenemos como primer dato 197.676 y para la
rasante contamos con 198.547, los datos que tendremos en el apartado de cotas (T.N Y RAS.) los necesitaremos para poder obtener los datos del siguiente apartado, el apartado siguiente es
espesor en el cual podemos encontrar el corte y el terraplén, bien para poder obtener el primer dato para el terraplén, se realiza una resta la cual será entre el valor de la RAS. y el T.N, podemos
notar que en algunos casos el valor de la RAS. es menor que el del T.N debido a esto la resta que se realizara tendrá unos cambios y quedara de la siguiente manera T.N - RAS. el dato que
obtendremos será colocado en el apartado de corte. Como siguiente apartado contamos con las Áreas la cuales las obtenemos de las secciones transversales de cada progresiva.
Para el siguiente apartado tenemos la suma de las áreas A1+A2, en este caso hacemos uso de los datos obtenidos en el apartado anterior (cortes y terraplén) para poder obtener los resultados
de este apartado se realizará la siguiente formula Corte1 + Corte2, para poder obtener los resultados de terraplén se hace uso de la siguiente formula Terraplen1+ Terraplen2, así sucesivamente
haciendo uso de cada uno de los datos.
El apartado siguiente que tenemos es el de distancia para este proyecto optamos por poner una distancia de 10m de principio a fin.
Para el cálculo de volúmenes hacemos uso del valor obtenido en A1+A2 tanto de corte como de terraplén y la distancia que propusimos, como ejemplo nos quedaría de la siguiente manera
0.10*10.00 =1.00 (este solo fue para obtener el primer dato de volúmenes de corte), para poder obtener el primer valor de terraplén se multiplicara el primer valor obtenido en A1+A2 por la
distancia propuesta, así se realizara con cada uno de los datos. El siguiente dato que obtenemos es el coeficiente de abundamiento este siempre ocurre cuando realizamos un movimiento de
tierra o excavamos para este dato se le dio un valor de 1.3 para el proyecto, lo que encontramos en la tabla son los datos de volúmenes abundados, para poder obtener cada dato tanto de corte
como de terraplén de hace uso de los valores obtenidos en el apartado de volúmenes y también se hace uso del factor de abundamiento, para ello se realiza una multiplicación de cada uno de los
valores de corte por el factor de abundamiento, para el terraplén es el mismo procedimiento, sería el valor de cada uno de los datos de terraplén que tenemos en volúmenes por el factor
abundamiento.
Para la suma algebraica el cual es el siguiente apartado se realiza una resta la cual se realiza con los datos obtenidos en el apartado de volúmenes abundados, si el valor de la resta sale
negativo el dato obtenido se colocará en terraplén y si el valor obtenido sale positivo se colocará en corte, así sucesivamente con todos los datos.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
DIAGRAMA DE MASAS.
6300
6100
5900
5700
ORDENADAS
5300
5100
4900
4700
4500
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .0 0 .7
00 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 47
0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+
CADENAMIENTOS
ORDENADA
DIAGRAMA DE MASAS
Un diagrama de masas presenta una vista gráfica del material desplazado al emplazamiento de diseño propuesto. Indica las regiones de puntos de equilibrio, transporte gratuito y transporte de
pago, y puntos de rasante.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
Unos propósitos que tiene el diagrama de curva masa son los siguientes:
Para el desarrollo de nuestro diagrama de masas hacemos uso de una alineación, un grupo de líneas de muestreo y una lista de materiales.
En nuestro diagrama de masas podemos observar como primer punto que se encuentra expresado en los ejes X y Y en el eje X podemos darnos cuenta que se encuentran las ordenadas, las
cuales comienzan con las medidas 4500m y finaliza en 6300m, a su vez en el eje Y contamos con el cadenamiento que como ya se expresó en la tabla para hacer el diagrama de masas es cada
20m comenzamos con un cadenamiento 0+000.00 y finalizamos con el cadenamiento 0+470.75, dentro del diagrama podemos encontrarnos con una línea recta la cual es conocida como línea
compensadora la cual corta la curva en varios puntos, se puede realizar o colocar más líneas compensadoras para poder mejorar así los movimientos, pero para este caso optamos solo con
colocar una línea compensadora, por ultimo contamos con la línea del diagrama de masas la cual cuando se eleva nos indica que se encuentra en un área de desmonte y cuando desciende se
encuentra en área de terraplén, para poder realizar esta línea es necesario recurrir a la tabla de para calcular el diagrama de masa, donde veremos los datos que tenemos en la ordenada, con
esto veremos la forma que llevara tomando la línea.
Para poder ver el curso o la forma que llevara cada una de las líneas, hacemos uso del valor de las cotas las cuales las podemos encontrar en la tabla de diseño de diagrama de curva masa,
podemos que notar que la línea de color azul tiene muchos desniveles los cuales, con ayuda de la línea de la RAS, nos indicaran cuales son los cortes y terraplén.
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
215
210
COTAS
COTAS T.N
COTAS RAS.
205
200
195
0 0 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 75
0 .0 0 .0 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0.
+00 02 0 4 0 6 0 8 1 0 1 2 1 4 1 6 1 8 2 0 2 2 2 4 2 6 2 8 3 0 3 2 3 4 3 6 3 8 4 0 4 2 4 4 4 6 4 7
0 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+ 0+
CADENAMIENTOS
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
•
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
CRONOGRAMA DE ACTIVIDADES
CANTIDA
CLAVE DESCRIPCION UNIDAD DIAS
D
I PAVIMENTACION
I.1 APERTURA DE CAMINO
TRAZO Y NIVELACION DE TERRENO CON EQUIPO TOPOGRAFICO
ESTABLECIENDO EJES Y REFERENCIAS CON CADENAMIENTO A CADA 1DIA
AP-01 20METROS DE DISTANCIA DESDE EL PUNTO DE ORIGEN. INCLUYE: M2 4,707.31
PLANOS DEL PROYECTO EN PLANTA, PERFIL TOPOGRAFICO Y SECCIONES 1 DE MARZO
TRANSVERSALES.
DESMONTE DE REGIONES SEMIARIDAS PARA UNA DENSIDAD DEL 100% A
4DIAS
MAQUINA. INCLUYE: TALA, ROZA, DESENRAICE, MANO DE OBRA,
AP-02 HA 0.56
LIMPIEZA DEL TERRENO Y TODO LO NECESARIO PARA SU CORRECTA
2,3,4,5 DE MARZO
EJECUCION.V
DESPALME CON MAQUINA HASTA 30 CM EN MATERIAL II (SUELO SEMI
3DIAS
BLANDO) TODAS LAS ZONAS. INCLUYE: MANO DE OBRA, MAQUINARIA,
AP-03 M2 5,648.77
LIMPIEZA DEL TERRENO Y TODO LO NECESARIO PARA SU CORRECTA
7,8,9 DE MARZO
EJECUCION.
DESALOJO DE MATERIAL PRODUCTO DE DESPALME POR MEDIOS
2DIAS
MECANICOS EN CAMION DE VOLTEO A BANCO DE DESPERDICIOS EN
AP-04 M3 1,276.94
CAMINO PLANO PAVIMENTADO. INCLUYE: CARGA POR MEDIOS
8,9 DE MARZO
MECANICOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.
I.2 TERRACERIAS
EXCAVACION POR MEDIOS MECANICOS EN MATERIAL TIPO II (SUELO
3DIAS
SEMI BLANDO) DE 0.00 A 2.00M DE PROFUNDIDAD EN MATERIAL TIPO II,
TE-01 M3 1,654.88
INCLUYE: AFINE DE TALUDES Y FONDO, MANO DE OBRA, HERRAMIENTA
1O,11,12 DE MARZO
Y EQUIPO NECESARIO.
1 DIA
LIM LIMPIEZA FINAL DE LA OBRA. M2 4,707.31
31 DE MARZO
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
DIAGRAMA DE GANTT
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL
UNIDAD III INSTITUTO TECNOLOGICO
RENDIMIENTO DE LA MAQUINARIA PESADA DE CERRO AZUL