INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

Quebrada Blanca Fase 2 (QB2)

PO/Contract Number: 25800-220-HC1-A00Z-00002

Supplier/Contractor Name: Consorcio Modular

Document Title: Informe Cierre de Calidad

Document Number: 25800-220-V02-A00Z-16180

Document Revision: 1

Document Submittal: 002

Equipment Number (if applicable): N/A

DOCUMENT REVIEW STATUS STAMP (To be filled by Bechtel)

Job No 25800 Project


SELLER/CONTRACTOR DOCUMENT REVIEW

Permission to proceed does not constitute acceptance or approval of design detail, calculations, analysis, test
methods, or materials developed or selected by Seller/Contractor, and does not relieve the Seller/Contractor from
full compliance with contractual obligations

WORK MAY PROCEED, Editorial comments need only be


1
incorporated if document revised and resubmitted

REVISE & RESUBMIT - WORK MAY PROCEED


X 2
SUBJECT TO INCORPORATION OF CHANGES

3 REVISE & RESUBMIT - WORK MAY NOT PROCEED

4 REVIEW NOT REQUIRED. WORK MAY PROCEED

5 CANCELLED / SUPERSEDED

REVIEWER: Ramón Sanhueza Cruces DATE: 23-12-2021


DISCIPLINE: Quality Assurance DDR No.:

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 1 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

INF-CAL-021
INFORME CIERRE DE CALIDAD

TIPO DE DOCUMENTO: DEPARTAMENTO / PROCESO / OBRA CÓDIGO TECNOFAST SA

CAMPAMENTOS DE CONSTRUCCIÓN
INFORME MENSUAL CONTRATO TECK N° 8013-CC-2001 25800-220-V02-A00Z-16180

CLAUSULAS DE LAS NORMAS REVISIÓN FECHA EMITIDO PARA

ISO 9001: 2008 7.5.1 1 29-11-2021 EMITIDO PARA APROBACION

ISO 14001: 2015 4.4.6 0 12-10-2021 EMITIDO PARA APROBACION

OHSAS 18001:
4.4.6 B 31-08-2021 REVISION INTERNA TF
2018
ELABORO APROBO APROBO TOMA CONOCIMIENTO

NOMBRE LUIS GUERRERO MAURICIO CONTRERAS CRISTIAN RIQUELME YURI VASQUEZ C.


ENCARGADO DE GERENTE CONSORCIO
JEFE DE CALIDAD ADMINISTRADOR OBRA
CARGO CALIDAD TECNO MODULAR
TECNO FAST TECNO FAST
FAST

FIRMA
Yuri
Nombre de reconocimiento (DN):

Cristian
Nombre de reconocimiento cn=Yuri Vasquez, o=Consorcio

Mauricio
Nombre de reconocimiento (DN):

Luis
Nombre de reconocimiento (DN): cn=Mauricio Contreras, Modular, ou=Administrador
cn=Cristian Riquelme, o=Tecno
(DN): cn=Luis Guerrero, o=Tecno Fast S.A., ou=QA-QC, Consorciomodular,

Vasquez
Fast S.A., ou=Administrador,
o=Tecno Fast S.A, ou=QA-QC, email=mcontreras@tecnofast. email=yvasquez@consorciomodular.

Riquelme
email=criquelme@tecnofast.cl,

Contreras
email=lguerrero@tecnofast.cl, cl, c=CL
cl, c=CL

Guerrero
c=CL
c=CL Fecha: 2021.11.29 10:06:43 -03'00'
Fecha: 2021.11.29 10:07:17 Fecha: 2021.11.29 10:06:58 -03'00'
Fecha: 2021.11.29 10:07:47
-03'00'
-03'00'

FECHA 29-11-2021 29-11-2021 29-11-2021 29-11-2021

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 2 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

INDICE

Tabla de contenido
1. Periodo informado del informe .......................................................................................................... 4
2. Estructura del departamento de Calidad ............................................................................................ 4
3. Actividades relevantes desarrolladas en el período: ........................................................................... 4
4. Control documental (Procedimientos) ................................................................................................ 8
5. Control de los registros (Protocolos) ................................................................................................... 8
6. Control de Ingeniería.......................................................................................................................... 9
7. Auditorías de Calidad: ........................................................................................................................ 9
8. Certificados de calibración de equipos IME ....................................................................................... 10
9. Ensayos de laboratorio..................................................................................................................... 10
10. Certificados de calidad de materiales: ............................................................................................ 10
11. No Conformidades.......................................................................................................................... 11
12. Registro Fotográfico. ...................................................................................................................... 12
13. Lecciones Aprendidas ..................................................................................................................... 12
14. Conclusion y Lecciones Aprendidas ................................................................................................. 13

Se deben incorporar comentarios realizados en revisión.


- Verificar incorporación de requisitos mencionados en Apéndice B-3 y
Apéndice B-9 para la consolidación de Informe Final de Calidad.

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 3 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

1. Periodo informado del informe


Desde: 01 de Abril de 2021 Mejorar y ajustar formato
Hasta: 31 de Agosto de 2021

2. Estructura del departamento de Calidad

2.1. Administrador de Obra:

Administrador de Obra : Cristian Riquelme P.


Administrador de Obra : Rene Gonzalez S.

2.2. Área Calidad:


§ Encargado de la Calidad : Luis Guerrero Perez
§ Asistente de Calidad : Victor Henríquez P.

3. Actividades relevantes desarrolladas en el período:

3.1. A la fecha se encuentran entregados para operación los siguientes edificios:

3.1.1. Edificio tipo


• W3-264
o 1, 2, 3, 4, 5, 6
• M/S-132
• S2-176
o 1, 2, 3, 4, 5, 6
• W-264
o 1, 2, 3, 4, 5
• Edificios Centrales
o Bomberos
o Policlinico
o Recreacion/Gimnasio Nº 1 y Nº 2
o Custodia
o Capacitation
o Control de Acceso/Administración de Campamento

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 4 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

• Edificio Bechtel
• Edificio Recepción y entrega de Ropa
• Tienda
• Edificio cocina comedor Temporal
• Edificio cocina comedor permanente
• Edificio Multicancha
• Edificio W2-264-1 COVID
• Edificio W2-264-2 COVID
• Edificio W2-386
• Edificio W2-240

3.2. Montaje cobertizo

• Trabajos de Montaje de Cobertizo finalizados, se caminaron y se levantaron Observaciones

3.3. Levantamiento de puntos Punch

• Puntos Punch a la fecha se encuentran levantados y cerrados.

Verificar estatus de puntos punch


(06 pendientes a la fecha)

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 5 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

3.4. Confección de carpetas CRP


REVISION POR ESPECIALIDAD
ITEM SUBSISTEMA/FACILITY DESCRIPCION CRP CONTRATISTA AREA STATUS FECHA ENTREGA CIVIL ESTRUCTURA ARQUITECTURA PIPING MECANICO ELECTRICO INSTRUMENTACION REVISION TOTAL

1 0880-NZC-001 EDIFICIO W3-264-1 25800-320-GTP-GSH-00098 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

2 0880-NZC-001 EDIFICIO W3-264-2 25800-320-GTP-GSH-00099 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

3 0880-NZC-001 EDIFICIO W3-264-3 25800-320-GTP-GSH-00100 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A RCC RCC FALTA REVISION FE CIVIL
4 0880-NZC-001 EDIFICIO W3-264-4 25800-320-GTP-GSH-00101 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC PR RSC RCC FALTA REVISION FE ELECTRICO

5 0850-NZC-001 EDIFICIO W3-264-5 25800-320-GTP-GSH-00102 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RCC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

6 0850-NZC-001 EDIFICIO W3-264-6 25800-320-GTP-GSH-00103 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

7 0850-NZC-001 EDIFICIO W-264-1 25800-320-GTP-GSH-00104 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC N/A PR RCC FALTA REVISION FE ELECTRICO
8 0850-NZC-001 EDIFICIO W-264-2 25800-320-GTP-GSH-00105 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC N/A PR RCC FALTA REVISION FE ELECTRICO

9 0850-NZC-001 EDIFICIO W-264-3 25800-320-GTP-GSH-00106 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

10 0850-NZC-001 EDIFICIO W-264-4 25800-320-GTP-GSH-00107 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

11 0850-NZC-001 CAMPAMENTO PERMANENTE Y CASINO 25800-320-GTP-GSH-00108 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

12 0850-NZC-001 EDIFICIO S2-176-1 25800-320-GTP-GSH-00109 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

FALTA REVISION FE ELECTRICO


13 0850-NZC-001 EDIFICIO S2-176-2 25800-320-GTP-GSH-00110 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RCC N/A PR PR
FALTA REVISION FE INSTRUMENTACION
FALTA REVISION FE ELECTRICO
14 0850-NZC-001 EDIFICIO S2-176-3 25800-320-GTP-GSH-00111 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR
FALTA REVISION FE INSTRUMENTACION
15 0850-NZC-001 EDIFICIO S2-176-4 25800-320-GTP-GSH-00112 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC N/A PR RCC FALTA REVISION FE ELECTRICO
16 0850-NZC-001 EDIFICIO S2-176-5 25800-320-GTP-GSH-00113 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RCC RCC RCC RCC N/A PR RCC FALTA REVISION FE ELECTRICO
FALTA REVISION FE CIVIL
17 0850-NZC-001 EDIFICIO S2-176-6 25800-320-GTP-GSH-00114 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION
18 0850-NZC-001 EDIFICIO M/S 132 25800-320-GTP-GSH-00115 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC N/A PR RCC FALTA REVISION FE ELECTRICO
FALTA REVISION FE CIVIL
19 0850-NZC-001 EDIFICIO ESTACION DE BOMBEROS/COBERTIZO AMBULANCIA BOMBEROS 25800-320-GTP-GSH-00116 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION
20 FALTA REVISION FE CIVIL
0850-NZC-001 EDIFICIO POLICLINICO 25800-320-GTP-GSH-00117 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION

21 0850-NZC-001 EDIFICIO GIMNASIO/RECREACIÓN N°1 (PERMANENTE) 25800-320-GTP-GSH-00118 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

22 0850-NZC-001 EDIFICIO CAPACITACIÓN 25800-320-GTP-GSH-00119 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

23 0850-NZC-001 EDIFICIO RECREACION/GIMNASIO N°2 25800-320-GTP-GSH-00120 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC PR N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

24 0850-NZC-001 EDIFICIO MULTICANCHA 25800-320-GTP-GSH-00121 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC N/A N/A PR RCC FALTA REVISION FE ELECTRICO
25 0850-NZC-001 EDIFICIO RECEPCIÓN Y ENTREGA DE ROPA 25800-320-GTP-GSH-00122 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RCC N/A PR RCC FALTA REVISION FE ELECTRICO

26 0850-NZC-001 EDIFICIO CUSTODIA 25800-320-GTP-GSH-00123 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

FALTA REVISION FE CIVIL


FALTA REVISION FE MECANICO
27 0850-NZC-001 EDIFICIO COCINA COMEDOR 25800-320-GTP-GSH-00124 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC PR PR PR
FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION
FALTA REVISION FE MECANICO
28 0850-NZC-001 EDIFICIO COCINA COMEDOR (TEMPORAL) 25800-320-GTP-GSH-00125 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RCC PR RSC PR
FALTA REVISION FE INSTRUMENTACION

29 0810-NZC-001 EDIFICIO CONTROL DE ACCESO Y ADMINISTRACIÍM DE CAMPAMENTO/COBERTIZO ACCESO 25800-320-GTP-GSH-00126 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

30 0820-NZC-001 EDIFICIO TECK-BECHTEL 25800-320-GTP-GSH-00127 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RCC RCC RCC PR N/A RSC RCC FALTA REVISION FE PIPING

31 0820-NZC-001 EDIFICIO TIENDA 25800-320-GTP-GSH-00128 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

32 0881-NZC-001 SEWAGE TREATMENT PLANT 25800-320-GTP-GSH-00129 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC N/A RSC N/A RSC N/A ACTUALIZAR RFI Y SUBIR ACONEX

33 0920-WY-001 CONCENTRATOR SEWAGE WATER 25800-320-GTP-GSH-00131 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC N/A N/A RCC N/A RCC N/A VERIFICAR Y LEVANTAR OBSERVACIONES

34 0850-NZC-001 URBANIZACION SANITARIA Y ALCANTARILLADO 25800-320-GTP-GSH-00132 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC N/A PR N/A N/A N/A SUBIR ACONEX

35 0850-NZC-001 URBANIZACIÓN SANITARIA AGUA POTABLE 25800-320-GTP-GSH-00133 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A RCC N/A N/A N/A VERIFICAR Y LEVANTAR OBSERVACIONES

36 0850-NZC-001 URBANIZACION RED DE INCENDIO 25800-320-GTP-GSH-00134 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A RCC N/A N/A N/A VERIFICAR Y LEVANTAR OBSERVACIONES

37 FALTA REVISION FE CIVIL


0850-NZC-001 URBANIZACIÓN ELECTRICA MT 25800-320-GTP-GSH-00135 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR N/A N/A PR N/A
FALTA REVISION FE ELECTRICO

38 0850-NZC-001 URBANIZACIÓN ELECTRICA BT Y CORRIENTES DÉBILES 25800-320-GTP-GSH-00136 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC N/A N/A N/A N/A RCC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

39 0850-NZC-001 URBANIZACION ELECTRICA PARARRAYOS Y MALLA PUESTA A TIERRA 25800-320-GTP-GSH-00137 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A N/A N/A RSC N/A SUBIR ACONEX

40 0880-NZC-001 EDIFICIO W2-264-1 25800-320-GTP-GSH-00342 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

FALTA REVISION FE CIVIL


41 0880-NZC-001 EDIFICIO W2-264-2 25800-320-GTP-GSH-00343 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION
FALTA REVISION FE ELECTRICO
42 0880-NZC-001 EDIFICIO W2-386 25800-320-GTP-GSH-00344 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RCC N/A PR PR
FALTA REVISION FE INSTRUMENTACION
43 0880-NZC-001 EDIFICIO W2-240 25800-320-GTP-GSH-00345 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC PR N/A RCC RCC FALTA REVISION FE PIPING

44 0850-NZC-001 URBANIZACION GENERAL (VEREDAS, ESTACIONAMIENTOS Y CIERRE PERIMETRAL) 25800-320-GTP-GSH-00346 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A N/A N/A N/A N/A SUBIR ACONEX

45 0131-NZC-001 EDIFICIO W3-396 25800-320-GTP-GSH-00347 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RSC N/A RCC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

46 0131-NZC-002 EDIFICIO W3-378 25800-320-GTP-GSH-00348 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RSC RSC RSC RSC N/A PR RCC FALTA REVISION FE ELECTRICO
FALTA REVISION FE CIVIL
47 0131-NZC-003 EDIFICIO W2-360-3 25800-320-GTP-GSH-00349 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A PR PR FALTA REVISION FE ELECTRICO
FALTA REVISION FE INSTRUMENTACION

48 0131-NZC-004 EDIFICIO W3-360-2 25800-320-GTP-GSH-00350 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RCC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

49 0131-NZC-005 EDIFICIO W3-360-1 25800-320-GTP-GSH-00351 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC RSC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

50 0131-NZC-006 EDIFICIO COCINA COMEDOR 25800-320-GTP-GSH-00352 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC RCC RCC RSC N/A RSC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

51 0131-NZC-007 EDIFICIO SALA DE RECREACIÓN 25800-320-GTP-GSH-00353 TECNOFAST QC REVISION POR BECHTEL 21-11-21 RCC RCC RCC N/A N/A PR RCC FALTA REVISION FE ELECTRICO
52 0131-NZC-008 CONTRO ACCESO Y ANDEN 25800-320-GTP-GSH-00354 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR N/A N/A RSC N/A RSC RSC FALTA REVISION FE CIVIL

53 0131-PW-001 AGUA POTABLE Y ESTANQUE AGUA POTABLE EL TAMBO 25800-320-GTP-GSH-00355 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC RSC N/A RSC N/A RCC N/A VERIFICAR Y LEVANTAR OBSERVACIONES

54 0131-ESL-001 BANCO DUCTOS, MALLA A TIERRA Y PARARRAYOS 25800-320-GTP-GSH-00356 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A N/A N/A RCC N/A VERIFICAR Y LEVANTAR OBSERVACIONES

55 0131-ESHA-001 SUBESTACIÓN ELECTRICA 25800-320-GTP-GSH-00357 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 N/A N/A N/A N/A N/A RCC N/A VERIFICAR Y LEVANTAR OBSERVACIONES

56 0131-PFW-001 RED DE INCENDIO (AGUA CONTRA INCENDIO) 25800-320-GTP-GSH-00358 TECNOFAST QC REVISION POR BECHTEL 21-11-21 PR PR PR RCC N/A N/A N/A FALTA REVISION FE CIVIL

57 0131-XN-001 PTAS Y SISTEMA DE ALCANTARILLADO 25800-320-GTP-GSH-00372 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RSC N/A N/A RSC N/A N/A N/A SUBIR ACONEX

58 0131-ESL-002 ALUMBRADO PUBLICO 25800-320-GTP-GSH-00373 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 RCC N/A N/A N/A N/A RCC N/A VERIFICAR Y LEVANTAR OBSERVACIONES

59 0131-EF-001 VOZ,DATOS Y TV 25800-320-GTP-GSH-00374 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 N/A N/A N/A N/A N/A RCC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

60 0131-NZ-001 REPARACION EDIFICIOS EXISTENTES 25800-320-GTP-GSH-00375 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 N/A N/A N/A N/A N/A RSC N/A SUBIR ACONEX

61 0131-PF-001 SISTEMA DETECCION DE INCENDIO Y ALARMA 25800-320-GTP-GSH-00376 TECNOFAST QC LEVANTANDO OBS TF 21-11-21 N/A N/A N/A N/A N/A RCC RCC VERIFICAR Y LEVANTAR OBSERVACIONES

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 6 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

STATUS CRP
35

30

25

20

15

10

CRP CON OBSERVACIONES CRP PENDIENTES DE REVISON CRP SUBIR ACONEX


(TF) (BECHTEL)

FALTA REVISION FE TOTAL STATUS CRP


CIVIL 10 CRP CON OBSERVACIONES (TF) 29
ESTRUCTURA 0 CRP PENDIENTES DE REVISON (BECHTEL) 26
ARQUITECTURA 0
CRP SUBIR ACONEX 6
PIPING 2
MECANICO 2 TOTAL CRP 61
ELECTRICO 20
INSTRUMENTACION 10

Verificar y actualizar estatus

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 7 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

4. Control documental (Procedimientos)

SI bien aun estamos retrasados con la regularización de estos documentos, estos se están levando y
regularizando.

ESTATUS DOCUMENTOS TECNICOS


Desusar Documento Pendiente Aprobados
Estatus Estatus Status Total
Tipo de Documento de Aconex Enviado envío (Code 1, Only Placeholder
1 2 5 general
(Nativos) PB PTF Information)
Documento Técnico
62 1 15 58 1 137
Calidad
Ingeniería Promet 3 16 8 27
Ingeniería TF
(Permisos, EETT, 119 78 2 1 8 208
Planos)
Aprobados 16692 16692
Cancelado 2 2
Archivos Native 52 52
Total general 17118

Status: 1: Aprobado; 2: Aprobado con comentarios; 3: Rechazado; 4: Solo Informativo; PSC: Pendiente de ingreso por subcontrato; PTF:
Pendiente de ingreso por Tecno Fast; SC: Solicitado Código; PB: Pendiente Bechtel, aun se están cerrando documentación.
Se deben regularizar los documentos
5. Control de los registros (Protocolos)
pendientes en cod.2 y Placeholders
El Proceso de Cierre de protocolos se realizo, estos se encuentran en las carpetas CRP.

RESUMEN DE REGISTROS DE CALIDAD EMITIDOS


TOTAL RECEPCIONADOS 6504 100%
CERRADAS TFSA 6147 95%
PENDIENTES DE CIERRE 31 0%
PROCOLOS NULOS/RECHAZADOS 364 6%
TOMA CONOCIMIENTO BECHTEL 45 1%
TOTAL REGISTROS EMITIDOS 6542 101%

Verificar estatus de protocolización


cargada en Aconex

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 8 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

6. Control de Ingeniería

AB Pendientes
Pendientes Aprobados por Comentados por Total Ingeniería
ESPECIALIDADES As Built Emitidos Aprobación
As Built Bechtel Bechtel Proyecto
Bechtel
Arquitectura 262 262 262
C. Débiles 74 74 74
Civil 166 164 1 1 166
Clima - HVAC 41 41 41
Electricidad 178 178 178
Estructura 54 50 4 54
Gas 2 2 2
Incendio-Rociadores 62 2 45 11 6 64
Layout 6 6 6
Sanitarios 150 1 150 151
Señalética 31 31 31
Total general 1026 3 1001 14 11 1029

7. Auditorías de Calidad:

7.1. Auditorías internas

• Se realiza Auditoria Documental a Subcontratos

Hallazgos Encontrados
Empresas
No Conformidades Nº de Observaciones
CR 0 0
Petra 0 2
RS 0 0
ICG 0 0

En conclusión no se encuentra Observaciones en las empresas auditadas a excepción de Constructora Petra


en cual se encontraron 2 observaciones y como recomendación referente al organigrama que sea visible
en las oficinas de la empresa.

7.2. Auditorías externas

- Se realiza auditoría externa por parte del Cliente el lunes 28 de octubre.


Incorporar estatus de Auditorías
realizadas por Bechtel QA
Incorporar además estatus de
Vigilancias realizadas por Bechtel QA e
Ingeniería (SCSR)

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 9 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

8. Certificados de calibración de equipos IME

Tipo de Fecha Próxima N°


Ítem Marca Modelo N° Serie Laboratorio Aprobado EMPRESA STATUS
Instrumento Calibración Calibración Certificado

SI NO
ESTACION TECNO
1 TOTAL
GEOMAX ZOOM 20 1801245 02-04-2019 02-04-2020 2015-38748 GEOCOM SI CERRADO
FAST
NIVEL GEO
2 AUTOMÁTICO
FORETECH AL-132 L133630 06-11-2018 06-05-2019 4312 SI CR CERRADO
EQUIPOS
NIVEL GEO
3 AUTOMÁTICO
TOPCON AT-B4 T60671 06-11-2018 06-05-2019 4313 SI CR CERRADO
EQUIPOS

TERMO
4 ANEMÓMETRO
AZ 8996 10309403 21-01-2019 21-04-2019 9125 VETO Si CR CERRADO

TERMO
5 NEMÓMETRO
AZ 8996 10309407 21-01-2019 21-04-2019 9126 VETO Si CR CERRADO
TERMO
6 ANEMÓMETRO
AZ 8996 10309399 21-01-2019 21-04-2019 9127 VETO Si CR CERRADO
ESTACIÓN
7 TOTAL
STONEX R35 DL30098 10-04-2019 01-03-2020 CTE_1907 TOPOX Si CR CERRADO

8 TAQUÍMETRO SOUTH ET-05 T302984 08-02-2019 08-02-2020 13370-2019 GEOCAS SI CR CERRADO

SE ESTA REGULARIZANDO LA CALIBRACION DE ESTOS EQUIPOS, SE ENVIARA CERTIFICADOS DE CALIBRACION


CORRESPONDIENTES.

Regularizar certificados de calibración pendientes


9. Ensayos de laboratorio

A la fecha no se han realizado ensayos de laboratorio en terreno correspondiente a mecánica de suelo y


hormigones.

10. Certificados de calidad de materiales:

Se han recepcionado certificados de Calidad


- Prefabricados de hormigón postes
- Prefabricados de hormigón fundaciones
- Dossier de módulos
- Materiales eléctricos
- Materiales sanitarios

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 10 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

11. No Conformidades

11.1. No conformidades internas

RESUMEN HALLAZGOS DE CALIDAD

PROYECTO: CAMPAMENTOS DE CONSTRUCCIÓN "CONCENTRADORA" QB2


CONTRATO Nº 8013-CC-2001
Producto No
NC Internas NC Externas Conforme TOTAL
(PNC)
Emitidas 32 0 5 37
Respondidas 32 0 5 37
Cerradas 32 0 5 37
Pendiente Respuesta 0 0 0 0
Pendiente Cierre 0 0 0 0

Incorporar estatus de hallazgos asociados a Condition Report y observaciones


generadas por Bechtel QA durante el proyecto.
Además incorporar estatus de NCRs generadas por FE Bechtel durante el proyecto

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 11 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

12. Registro Fotográfico.

N/A

13. Lecciones Aprendidas

13.1. Resultados del Proyecto

13.1.1. Cuáles fueron los resultados que el proyecto se propuso alcanzar.

Los productos esperados del proyecto era entregar un producto conforme a nuestras políticas de calidad, tanto
en nuestra misión y visión como empresa.

13.1.2. Cuáles fueron los resultados alcanzados efectivamente por el proyecto.


.
En el marco del proyecto se encontraron desviaciones que hicieron un atraso tanto constructivos como también
financieros de acuerdo con los productos que se esperaban entregar a nuestro Clientes Bechtel.

13.2. Gestion del Proyecto

13.2.1. Identifique fortalezas y desafíos en la gestión del proyecto.

El proyecto fue realizado de acuerdo con lo presupuestado y sus resultados pueden calificarse de exitosos,
puesto que se lograron los objetivos planteados por la administración del proyecto. Producidos tuvieron
desviaciones la cual creo la necesidad de replantear diversos modos de trabajos, revisiones de procesos, para
que estos resultasen exitoso dentro de lo entregado al proyecto.

Falta incorporar estatus de cumplimiento de PBQ en Proyecto,


(implementación del Programa de Calidad Basado en las personas)

Falta incorporar ítem de Informe de la Gestión de Riesgos (Risk Management)


Apéndice B-3: ítem 6.0 "Control Estadístico"
Detalle con el Registro de Riesgos del proyecto individualizando a lo menos,
todos los riesgos y oportunidades identificados en el proyecto...

Rev.: 1 Fecha de Creación doc.: 29-11-2021 Página 12 de 13


INFORME CIERRE DE CALIDAD

CAMPAMENTO DE CONSTRUCCIÓN CONCENTRADORA Rev. 1 29-11-2021


Código interno: INF-CAL-021
Contrato N°: 8013-CC-2001 “Campamentos de Construcción”
Código Proyecto: 25800-220-V02-A00Z-16180

14. Conclusion y Lecciones Aprendidas

Una importante lección aprendida del proyecto es la importancia que tiene la planificación, visualización de
estratégica de las actividades a realizar. Esto permitirá en los períodos de trabajo se deba evaluar en el proceso
inicial, para que permita que los análisis realizados esten disponibles en tiempos oportunos contribuyendo a
su mayor impacto dentro de proyectos futuros.
Otra lección aprendida es la importancia de sistematizar el trabajo realizado. Se destinó tiempo a documentar
por escrito tanto en documentos técnicos como también en los procesos de estos, así como para realizar los
análisis y evaluaciones que son requeridos en el contexto de una buena gestión de trabajo y aplicación de
nuestro sistema de gestión de calidad, lo que agregara un indudable valor a nuestro trabajo y contribuirá un
mayor impacto a proyectos futuros

Desviacion Levantamiento Leccion


Unión de Alcantarillado, Estas se cambian Revision de estos antes del
quebrados. montaje
Uso de lápiz removible Se levantan todos los protocolos Se emite instructivo indicando la
y se ingresan nuevamente prohibición e estos lápices.

Se debe incorporar las evidencias del o los talleres realizados


asociados a Lecciones Aprendidas y Buenas Prácticas.

- Apéndice B-3. ítem 2.5 Cierre de Contrato: "EL CONTRATISTA


deberá organizar y desarrollar uno o mas talleres de Lecciones
Aprendidas y Buenas Prácticas con la finalidad de capturar las
prácticas exitosas; cosas a evitar; precauciones; mejoras potenciales
con base en la experiencia de las actividades ejectuadas y la
información tecnológica utilizada".