PROGRAMA DE MANTENIMIENTO PLANTA QUIMICA SUPERINTENDENCIA

MANTENCION PLANTA
DMVE 600 601 PI 005 / R1
04/01/2024
TODOS ANTES DE COMENZAR CADA TRABAJO, DEBE REALIZARSE UN ANÁLISIS DE RIESGO Y ADOPTARSE LAS MEDIDAS DE CONTROL CORRESPONDIENTES. DEBEN RESPETARSE LAS REGLAS DE VIDA

ID OT Task Name Duration Start Finish Predecessors


Supervisor MV Resource Names SUPERVISOR
Thu Jan 4 Fri Jan 5
8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM
1 MANTENIMIENTO PLANTA QUÍMICA 7 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 3:00 PM

2 Requerimientos 1 hr Thu 1/4/24 8:00 AM Thu 1/4/24 9:00 AM M.Copper

3 Limpieza Máquina Despegadora (sector Transportador de 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4
salida) Limpieza estructura cadena de entrada MDC

4 Posicionar Cartuchera verticalmente 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4

5 Araña Porta Cátodos en posición de mantenimiento 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4

6 Limpieza de plataforma e interior báscula de pesaje paquetes 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4
de cátodos

7 Entrega de equipos a las 08:00 hrs a personal de mantención 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4

8 Detención e Caldera 10 a las 04:00 A.M para 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4
enfriamiento,"realizar drenaje de equipo" y cierre de
válvulas de corte para aislar

9 Puentes grúa 10 y 20 en posición de mantenimiento con ganchos


0 hrs
a piso Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4

10 Apoyo de operador puente grúa#10 y #20 nave EW, para 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Operaciones 1/4
pruebas sistema de protección de izaje gancho

11 Entrega de la MDC a operaciones, para pruebas 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM C. Ruiz / E. Guzman Mantención 1/4
funcionales a las 15:00 hrs

12 Disposición de grua horquilla o camión pluma para 0 hrs Thu 1/4/24 8:00 AM Thu 1/4/24 8:00 AM M.Torres Mantención 1/4
contrastación de bascula pesaje

13 Bloqueo de Equipos 1 hr Thu 1/4/24 8:00 AM Thu 1/4/24 9:00 AM

14 Bloqueo MDC, Corrugadora, Cortadora de catodos 1 hr Thu 1/4/24 8:00 AM Thu 1/4/24 9:00 AM O. Godoy / F. Urrelo Electricos MV Mantención Electricos MV

15 Bloqueo independiente puente#20 y puente#10 1 hr Thu 1/4/24 8:00 AM Thu 1/4/24 9:00 AM O. Godoy / F. Urrelo Electricos MV Mantención Electricos MV

16 MANTENCIÓN MECÁNICA 6 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 3:00 PM

17 Máquina Despegadora de Cátodos 6 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 3:00 PM

18 2000652961 Limpieza Transportador de lavado y Transportador de 1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM 14 M.Torres Op1,Op2 M.Torres Op1,Op2
salida, Retirar sedimentación de orgánico y cobre
cubriendo los eslabones y rodillos.

19 2000652961 Limpieza general Maquina Despegadora y acrílicos de 1 hr Thu 1/4/24 10:00 AM Thu 1/4/24 11:00 AM 18 M.Torres Op1,Op2 M.Torres Op1,Op2
protección a paño

20 2000651321 PM Inspección parrillas de piso cámara lavado de cátodos MDC


1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM 14 M.Cortes CB3,CB4 R.Baez CB3,CB4

21 2000651200 Estación de carga: limpieza general y pintura, Chequeo 1 hr Thu 1/4/24 10:00 AM Thu 1/4/24 11:00 AM 20 M.Cortes CB3,CB4 R.Baez CB3,CB4
de estado de estructura y chequeo de componentes

22 2000651387 Carrusel: Limpieza general y pintura, lubricación de 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 21 M.Cortes CB3,CB4 R.Baez CB3,CB4
componentes; inspección / ajuste gap Sproket, inspección
gap polines carrusel, revisar estado de bases soporte
polines guia carrusel. Inspección pasadores y bujes
superiores de carro 60°

23 2000651201 Estación de martilleo:, limpieza general, Estado General 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM 22 M.Cortes CB3,CB4 R.Baez CB3,CB4
de Estructura, flexibles hidraulicos, conectores, piping ,
Soldadura, Graseras. Fitting, Sellos, Pasadores,
lubricación, chequeo de componentes. Inspección y/o
cambio flexibles hidráulicos, pintado

RESPONSABILIDAD MV: RESPONSABILIDAD ES: Planificación: C. Contreras.


EDUARDO GUZMÁN / CLAUDIO CONTRERAS / PATRICIO OSSANDON ASMECO CTO BASE: J.Fuentes Aprobación: A.Munoz
PROGRAMA DE MANTENIMIENTO PLANTA QUIMICA SUPERINTENDENCIA
MANTENCION PLANTA
DMVE 600 601 PI 005 / R1
04/01/2024
TODOS ANTES DE COMENZAR CADA TRABAJO, DEBE REALIZARSE UN ANÁLISIS DE RIESGO Y ADOPTARSE LAS MEDIDAS DE CONTROL CORRESPONDIENTES. DEBEN RESPETARSE LAS REGLAS DE VIDA

ID OT Task Name Duration Start Finish Predecessors


Supervisor MV Resource Names SUPERVISOR
Thu Jan 4 Fri Jan 5
8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM
24 2000651202 Estación de Separado y plegado: limpieza general, Estado 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 M.Cortes CB7,CB8 R.Baez CB7,CB8
General de Estructura, Soldadura, flexibles hidraulicos,
conectores, piping , Graseras. Fitting, Sellos, Pasadores,
lubricación

25 2000651203 SEMANAL MEC ESTACION CARTUCHERA MDC, 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 24 M.Cortes CB7,CB8 R.Baez CB7,CB8
Tensado de cables de cilindros neumáticos deslizador
cartuchera
26 2000637789 2S Inspeccion Goma Tope MDC 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM 25 M.Cortes CB8,CB7 R.Baez CB8,CB7

27 Pruebas operacionales MDC 1 hr Thu 1/4/24 2:00 PM Thu 1/4/24 3:00 PM 26 H.Anacona / M.CortesCB3,CB4,CB7,CB8 R.Baez CB3,CB4,CB7,CB8

28 Máquina Corrugadora de Cátodos 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM

29 2000651197 SEMANAL MEC ESTACION CORRUGADORA 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 M.Cortes CB5,CB6 R.Baez CB5,CB6

30 Máquina Cortadora de Cátodos 3 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 2:00 PM

31 2000651198 PM MEC Semanal Sierra cortadora de catodos 3 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 2:00 PM 29 M.Cortes CB5,CB6 R.Baez CB5,CB6

32 Puente Grúa 20 5 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 2:00 PM

33 2000651213 PM semanal Mtto Mecanico Puente grúa 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 M.Cortes CB9,CB10 R.Baez CB9,CB10
#20(PRUEBAS SISTEMA DE SEGURIDAD MEC DE
GANCHO PUENTE GRUA #20)(Revisión de macho
Sistema traslación Puente Grúa #20)

34 2000648376 PM MEC 1M FRENO GANCHO PTE GRUA 5 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 2:00 PM 14 M.Cortes CB9,CB10 R.Baez CB9,CB10

35 Puente Grúa 10 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM

36 2000651212 PM SEMANAL MTTO PUENTE GRUA EW N1 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 33 M.Cortes CB9,CB10 R.Baez CB9,CB10

37 Puente Grúa 30 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM

38 2000651214 PM semanal Mtto Mecanico Puente grúa #30 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 M.Cortes CB11,CB12 R.Baez CB11,CB12

39 Calentador de agua 10 1 hr Thu 1/4/24 11:00 AM Thu 1/4/24 12:00 PM

40 2000651320 SEMANAL MEC CALENTADOR 10 1 hr Thu 1/4/24 11:00 AM Thu 1/4/24 12:00 PM 38 M.Cortes CB11,CB12 R.Baez CB11,CB12

41 Planta RO 3 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 12:00 PM

42 2000641198 SEMANAL MEC FILTRO DE ARENA AGUASIN 1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM 14 M.Cortes CB1,CB2 R.Baez CB1,CB2

43 2000641479 SEMANAL MEC FILTRO FILMTEC 1 hr Thu 1/4/24 10:00 AM Thu 1/4/24 11:00 AM 42 M.Cortes CB1,CB2 R.Baez CB1,CB2

44 2000641207 SEMANAL MEC SISTEMA DE MEMBRANAS 1 hr Thu 1/4/24 11:00 AM Thu 1/4/24 12:00 PM 43 M.Cortes CB1,CB2 R.Baez CB1,CB2

45 TANK FARM 2 hrs Thu 1/4/24 12:00 PM Thu 1/4/24 2:00 PM

46 2000410669 PM QUINCENAL MECANICA FILTRO SPINTEK 1 hr Thu 1/4/24 12:00 PM Thu 1/4/24 1:00 PM 44 M.Cortes CB1,CB2 R.Baez CB1,CB2

47 2000651205 SEMANAL MEC FILTRO PERRIN 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM 46 M.Cortes CB1,CB2 R.Baez CB1,CB2

48 Nave EW 3 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 12:00 PM

49 2000651161 PM Semanal mecánico araña porta cátodos N°1 1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM 14 M.Cortes CB13,CB14 R.Baez CB13,CB14

50 2000651162 PM Semanal mecánico araña porta cátodos N°2 1 hr Thu 1/4/24 10:00 AM Thu 1/4/24 11:00 AM 49 M.Cortes CB13,CB14 R.Baez CB13,CB14

51 2000651196 SEMANAL MEC CONJUNTO EXTRACTORES AIRE 1 hr Thu 1/4/24 11:00 AM Thu 1/4/24 12:00 PM 50 M.Cortes CB13,CB14 R.Baez CB13,CB14

52 MANTENCIÓN ELÉCTRICA 6 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 3:00 PM

53 Maquina Despegadora de Catodo 4 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 1:00 PM JTE / H. Anacona

54 2000650583 PM SEMANAL MANTENCION ELEMENTOS MDC 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 JTE / H. Anacona Elec MV1,Elec MV2 Elec MV1,Elec MV2

55 2000650679 PM MTTO ELEC CAJAS JB 17-16-19 MDC 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 54 JTE / H. Anacona Elec MV1,Elec MV2 Elec MV1,Elec MV2

RESPONSABILIDAD MV: RESPONSABILIDAD ES: Planificación: C. Contreras.


EDUARDO GUZMÁN / CLAUDIO CONTRERAS / PATRICIO OSSANDON ASMECO CTO BASE: J.Fuentes Aprobación: A.Munoz
PROGRAMA DE MANTENIMIENTO PLANTA QUIMICA SUPERINTENDENCIA
MANTENCION PLANTA
DMVE 600 601 PI 005 / R1
04/01/2024
TODOS ANTES DE COMENZAR CADA TRABAJO, DEBE REALIZARSE UN ANÁLISIS DE RIESGO Y ADOPTARSE LAS MEDIDAS DE CONTROL CORRESPONDIENTES. DEBEN RESPETARSE LAS REGLAS DE VIDA

ID OT Task Name Duration Start Finish Predecessors


Supervisor MV Resource Names SUPERVISOR
Thu Jan 4 Fri Jan 5
8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM8 PM10 PM12 AM2 AM4 AM6 AM8 AM10 AM12 PM2 PM 4 PM 6 PM
56 Máquina Corrugadora de Cátodos 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM

57 2000650581 PM SEMANAL MANTENCION CORRUGADORA 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 JTE / H. Anacona Elec MV4,Elec MV3 Elec MV4,Elec MV3

58 2000651212 Puente Grúa 10 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM

59 PM SEMANAL MTTO ELEC PUENTE GRUA EW 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 15 JTE / H. Anacona Elec MV5,Elec MV6 Elec MV5,Elec MV6
N1(Chequeo Elec de Sistema protección
movimiento de subida de gancho)

60 2000387445 PM MEC 1M FRENO GANCHO PTE GRUA 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 JTE / H. Anacona Elec MV5,Elec MV6 R.Baez Elec MV5,Elec MV6

61 Puente Grúa 20 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM

62 2000651213 PM SEMANAL MTTO ELEC PUENTE GRUA EW 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 58 JTE / H. Anacona Elec MV5,Elec MV6 Elec MV5,Elec MV6
N2(Chequeo Elec de Sistema protección
movimiento de subida de gancho)

63 Puente Grúa 30 2 hrs Thu 1/4/24 1:00 PM Thu 1/4/24 3:00 PM

64 2000651214 PM SEMANAL MTTO ELEC PUENTE GRUA EW N3 2 hrs Thu 1/4/24 1:00 PM Thu 1/4/24 3:00 PM 62 JTE / H. Anacona Elec MV5,Elec MV6 Elec MV5,Elec MV6

65 Bbas. EW Lavado 1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM

66 2000650514 PM SEMANAL MTTO ELEC BOMBAS EW LAVADO 1 hr Thu 1/4/24 9:00 AM Thu 1/4/24 10:00 AM 14 JTE / H. Anacona Elec MV7,Elec MV8 Elec MV7,Elec MV8

67 Bascula Pesaje Paquetes de Catodos 2 hrs Thu 1/4/24 10:00 AM Thu 1/4/24 12:00 PM

68 2000650577 PM SEMANAL MTTO ELEC BASCULA EW 2 hrs Thu 1/4/24 10:00 AM Thu 1/4/24 12:00 PM 66 JTE / H. Anacona Elec MV7,Elec MV8 Elec MV7,Elec MV8

69 Tank Farm 1 hr Thu 1/4/24 12:00 PM Thu 1/4/24 1:00 PM

70 2000650578 PM SEMANAL MANTENCION ELEC CALENTADOR 101 hr Thu 1/4/24 12:00 PM Thu 1/4/24 1:00 PM 68 JTE / H. Anacona Elec MV7,Elec MV8 Elec MV7,Elec MV8

71 Máquina Cortadora de Cátodos 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM

72 2000650582 PM SEMANAL MTTO ELEC CORTADORA CATODO 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM 70 JTE / H. Anacona Elec MV7,Elec MV8 Elec MV7,Elec MV8

73 Araña Porta Catodos 2 hrs Thu 1/4/24 1:00 PM Thu 1/4/24 3:00 PM

74 2000650575 PM SEMANAL MTTO ELEC ARAÑA PORTA CAT N1 1 hr Thu 1/4/24 1:00 PM Thu 1/4/24 2:00 PM 55 JTE / H. Anacona Elec MV2,Elec MV1 Elec MV2,Elec MV1

75 2000650576 PM SEMANAL MTTO ELEC ARAÑA PORTA CAT N2 1 hr Thu 1/4/24 2:00 PM Thu 1/4/24 3:00 PM 74 JTE / H. Anacona Elec MV2,Elec MV1 Elec MV2,Elec MV1

76 Planta EW 4 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 1:00 PM JTE / H. Anacona

77 2000650659 PM 2M MANTENCIÓN LUMINARIAS ALTA NAVE EW 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 57 JTE / H. Anacona Elec MV4,Elec MV3 Elec MV4,Elec MV3

78 2000650580 PM SEMANAL INSP ELEC MOT EXTRAC NAVE EW 4 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 1:00 PM 14 JTE / H. Anacona Elec MV9,Elec MV10 Elec MV9,Elec MV10

79 2000614937 PM TRIMESTRAL FLUJOMETRO PILA LIXIVIACION 2 hrs Thu 1/4/24 9:00 AM Thu 1/4/24 11:00 AM 14 JTE / H. Anacona INS MV1,INS MV2 INS MV1,INS MV2

80 2000650507 PM Mantenimiento HMI (ETOS Est Operación) 2 hrs Thu 1/4/24 11:00 AM Thu 1/4/24 1:00 PM 79 JTE / H. Anacona INS MV1,INS MV2 INS MV1,INS MV2

81 Housekeeping de área de trabajo 0 hrs Thu 1/4/24 3:00 PM Thu 1/4/24 3:00 PM Manto Verde 1/4

82 Prueba de equipos 0 hrs Thu 1/4/24 3:00 PM Thu 1/4/24 3:00 PM 81 Manto Verde 1/4

83 Entrega de equipos 0 hrs Thu 1/4/24 3:00 PM Thu 1/4/24 3:00 PM 82 Manto Verde 1/4

RESPONSABILIDAD MV: RESPONSABILIDAD ES: Planificación: C. Contreras.


EDUARDO GUZMÁN / CLAUDIO CONTRERAS / PATRICIO OSSANDON ASMECO CTO BASE: J.Fuentes Aprobación: A.Munoz