CURVA "S" - VALORIZACION FISICA - NOVIEMBRE 2023

OBRA : "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E.I. NRO 463 EN LA ASOCIACIÓN DE VIVIENDA 5 DE NOVIEMBRE, EN EL DISTRITO CORONEL GREGORIO ALBARRACIN LANCHIPA, PROVINCIA DE TACNA - TACNA"

ENTIDAD SUB GERENCIA DE OBRAS / GERENCIA REGIONAL DE INFRAESTRUCTURA / GOBIERNO REGIONAL DE TACNA

RESIDENTE DE OBRA ING. RAUL ALEJANDRO SALAS VARGAS PLAZO DE EJECUCION 270 D.C.

INSPECTOR DE OBRA ING. ADA VASQUEZ QUISPE PRESUPUESTO (CD + GG) S/ 3,075,951.93

AVANCE FISICO PROGRAMADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

PARCIAL S/. 0.00 S/ 61,265.18 S/ 85,884.30 S/ 582,082.22 S/ 697,196.02 S/ 326,677.01 S/ 264,636.75 S/ 514,651.94 S/ 273,758.64 S/ 141,137.91 S/ 128,661.96

% PARCIAL 0.00% 1.99% 2.79% 18.92% 22.67% 10.62% 8.60% 16.73% 8.90% 4.59% 4.18%

ACUMULADO S/. 0.00 S/. 61,265.18 S/. 147,149.48 S/. 729,231.70 S/. 1,426,427.72 S/. 1,753,104.73 S/. 2,017,741.48 S/. 2,532,393.42 S/. 2,806,152.06 S/. 2,947,289.97 S/. 3,075,951.93

% ACUMULADO 0.00% 1.99% 4.78% 23.71% 46.37% 56.99% 65.60% 82.33% 91.23% 95.82% 100.00%

AVANCE FISICO EJECUTADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

PARCIAL S/. 0.00 S/. 39,793.61 S/. 99,181.07 S/. 95,095.25 S/. 301,559.05

% PARCIAL 0.00% 1.29% 3.22% 3.09% 9.80%

ACUMULADO S/. 0.00 S/. 39,793.61 S/. 138,974.68 S/. 234,069.93 S/. 535,628.98

% ACUMULADO 0.00% 1.29% 4.52% 7.61% 17.41%

110%

100% 100.00%
95.82%
90% 91.23%

82.33%
PORCENTAJE (%)

80%

70%
65.60%
60%
56.99%
50%
46.37%
40% AVANCE FISICO PROGRAMADO AVANCE FISICO EJECUTADO

30%

20%
17.41%
23.71%
1.29% 7.61%
10% 4.52%

0% 0.00% 0.00% 1.99% 4.78%


INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

TIEMPO (MESES)
CURVA "S" - VALORIZACION FINANCIERA RECURSOS EMPLEADOS - NOVIEMBRE 2023

OBRA : "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E.I. NRO 463 EN LA ASOCIACIÓN DE VIVIENDA 5 DE NOVIEMBRE, EN EL DISTRITO CORONEL GREGORIO ALBARRACIN LANCHIPA, PROVINCIA DE TACNA - TACNA"

ENTIDAD SUB GERENCIA DE OBRAS / GERENCIA REGIONAL DE INFRAESTRUCTURA / GOBIERNO REGIONAL DE TACNA

RESIDENTE DE OBRA ING. RAUL ALEJANDRO SALAS VARGAS PLAZO DE EJECUCION 270 D.C.

INSPECTOR DE OBRA ING. ADA VASQUEZ QUISPE PRESUPUESTO (CD + GG) S/ 3,075,951.93

AVANCE FINANCIERO PROGRAMADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

PARCIAL S/. 0.00 S/ 61,265.18 S/ 85,884.30 S/ 582,082.22 S/ 697,196.02 S/ 326,677.01 S/ 264,636.75 S/ 514,651.94 S/ 273,758.64 S/ 141,137.91 S/ 128,661.96

% PARCIAL 0.00% 1.99% 2.79% 18.92% 22.67% 10.62% 8.60% 16.73% 8.90% 4.59% 4.18%

ACUMULADO S/. 0.00 S/. 61,265.18 S/. 147,149.48 S/. 729,231.70 S/. 1,426,427.72 S/. 1,753,104.73 S/. 2,017,741.48 S/. 2,532,393.42 S/. 2,806,152.06 S/. 2,947,289.97 S/. 3,075,951.93

% ACUMULADO 0.00% 1.99% 4.78% 23.71% 46.37% 56.99% 65.60% 82.33% 91.23% 95.82% 100.00%

AVANCE FINANCIERO EJECUTADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

PARCIAL S/. 0.00 S/. 85,980.43 S/. 119,226.57 S/. 152,078.56 S/. 298,446.54

% PARCIAL 0.00% 2.80% 3.88% 4.94% 9.70%

ACUMULADO S/. 0.00 S/. 85,980.43 S/. 205,207.00 S/. 198,207.00 S/. 496,653.54

% ACUMULADO 0.00% 2.80% 6.67% 11.62% 16.15%

110%

100% 100.00%
95.82%
90% 91.23%

82.33%
PORCENTAJE (%)

80%

70%
65.60%
60%
56.99%
50%
46.37%
40% AVANCE FINANCIERO PROGRAMADO AVANCE FINANCIERO EJECUTADO

30%

20%
11.62% 23.71% 16.15%
2.80% 6.67%
10%

0% 0.00% 0.00% 1.99% 4.78%


INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

TIEMPO (MESES)
CURVA "S" - VALORIZACION FINANCIERA A NIVEL DE DEVENGADOS - MES
NOVIEMBRE

OBRA : "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E.I. NRO 463 EN LA ASOCIACIÓN DE VIVIENDA 5 DE NOVIEMBRE, EN EL DISTRITO CORONEL GREGORIO
ALBARRACIN LANCHIPA, PROVINCIA DE TACNA - TACNA"

ENTIDAD SUB GERENCIA DE OBRAS / GERENCIA REGIONAL DE INFRAESTRUCTURA / GOBIERNO REGIONAL DE TACNA

RESIDENTE DE OBRA ING. RAUL ALEJANDRO SALAS VARGAS PLAZO DE EJECUCION 139 D.C.

INSPECTOR DE OBRA ING. ADA VASQUEZ QUISPE PRESUPUESTO PLAN DE TRABAJO 2023 (CD + GG) S/ 1,753,104.73

AVANCE FISICO PROGRAMADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

PARCIAL S/. 0.00 S/ 61,265.18 S/ 85,884.30 S/ 582,082.22 S/ 697,196.02 S/ 326,677.01

% PARCIAL 0.00% 3.49% 4.90% 33.20% 39.77% 18.63%

ACUMULADO S/. 0.00 S/. 61,265.18 S/. 147,149.48 S/. 729,231.70 S/. 1,426,427.72 S/. 1,753,104.73

% ACUMULADO 0.00% 3.49% 8.39% 41.60% 81.37% 100.00%

AVANCE FÍSICO EJECUTADO


DESCRIPCION
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

PARCIAL S/. 0.00 S/. 126,131.33 S/. 189,332.78 S/. 386,655.34 S/. 413,542.61

% PARCIAL 0.00% 7.19% 10.80% 22.06% 23.59%

ACUMULADO S/. 0.00 S/. 126,131.33 S/. 315,464.11 S/. 702,119.45 S/. 1,115,662.06

% ACUMULADO 0.00% 7.19% 17.99% 40.05% 63.64%

110%

100% 100.00%

90%
81.37%
PORCENTAJE (%)

80%

70%

60%

50%
40.05% AVANCE FISICO PROGRAMADO
40%
AVANCE FÍSICO EJECUTADO
41.60%
30%
17.99%
20%
7.19%
10%
8.39%
0% 0.00% 0.00% 3.49%
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

TIEMPO (MESES)
8.39%
0% 0.00% 0.00% 3.49%
INICIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

TIEMPO (MESES)
1 entrega

cant
260.00 arena gruesa 60.00
notificacion arena fina
59.00
25-setiembre-2023
85.00 hormigon 45.00

230.00 piedra chancada 1/2 60.00


notificacion piedra grande de 8 in 5.00
5.00
21-setiembre-2023
45.00 piedra chancada de 6 in 15.00
1 entrega 2 entrega 3 entrega

fecha cant fecha cant fecha


9/27/2023 22-Sep 60.00 10/27/2023 15-Nov 50.00 11/26/2023 15-Dec

22-Sep 40.00 15-Nov

9/23/2023 22-Sep 60.00 23-Oct 28-Nov 40.00 22-Nov

22-Sep 30.00 28-Nov


4 entrega 5 entrega

cant fecha cant fecha Total Saldo


45 12/26/2023 45 1/25/2024 260.00 0.00
30 29 59.00 0.00
85.00 0.00

40 22-Dec 30 21-Jan 230.00 0.00


5.00 0.00
45.00 0.00