CURVA S

AMIENTO DEL CAMINO VECINAL ENTRE LAS COMUNIDADES DE SANTA INES - MIMIRINI ALTA Y TRAMO INTEGRACION AGRICOLA DEL DISTRITO DE UNION ASHANINKA - LA CONVENCION - CUSCO" CON CODICO UNICO N° 2557659

ENTIDAD : MUNICIPALIDAD DISTRITAL DE UNION ASHANINKA


CONTRATISTA : CONSORCIO SANTA INES
SUPERVISOR DE OBRA : ING. OMAR MENDOZA MUEDAS
RESIDENTE DE OBRA : ING. ROLY K. CAMPOS HERRERA

PROGRAMADO EJECUTADO
MONTO PARCIAL PORCENTAJES MONTO PARCIAL PORCENTAJES ESTADO DE
PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL ACUMULADPARCIAL ACUMULADO AVANCE
MES MES
S/. S/. % % S/. S/. % %
INICIO 0 0
MAYO 749,664.15 749,664.15 28.66% 28.66% MAYO 1,402,754.03 1,402,754.03 53.63% 53.63% Adelantado
JUNIO 726,957.41 1,476,621.56 27.79% 56.45% JUNIO 959,277.86 2,362,031.89 36.67% 90.30% Adelantado
JULIO 527,984.76 2,004,606.32 20.18% 76.64% JULIO 179,306.22 2,541,338.11 6.85% 97.15% Adelantado
AGOSTO 599,776.50 2,604,382.82 22.93% 99.56% AGOSTO
SETIEMBRE 11,388.96 2,615,771.78 0.44% 100.00% SETIEMBRE
TOTAL 2,615,771.78 100.00% TOTAL 2,541,338.11 97.15%

120.00%
CUADRO DE AVANCE FÍSICO - PROGRAMADO VS EJECUTADO ACUMULADO(PRINCIPAL)

97.15% 99.56% 100.00%


100.00%
PRO- 90.30%
GRA-
80.00%
MADO
Column L 76.64%

53.63%
60.00%
56.45%

40.00%
28.66%

20.00%
0.00%
0.00% 0 0
0.00%
INICIO MAYO JUNIO JULIO AGOSTO SETIEMBRE
CURVA S
NAL ENTRE LAS COMUNIDADES DE SANTA INES - MIMIRINI ALTA Y TRAMO INTEGRACION AGRICOLA DEL DISTRIT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE UNION ASHANINKA
CONTRATISTA : CONSORCIO SANTA INES
SUPERVISOR DE OBRA : ING. EDWARD CHALE PEREZ CORDOVA
RESIDENTE DE OBRA : ING. ROLY K. CAMPOS HERRERA

PROGRAMADO
MONTO PARCIAL PORCENTAJES
MES VALORIZACIO PARCIAL ACUMULADO PARCIAL ACUMULADO

S/. S/. % %
INICIO INICIO 0 0
MAYO MAYO S/ 749,664.15 S/ 749,664.15 28.66% 28.66%
JUNIO JUNIO S/ 726,957.41 S/ 1,476,621.56 27.79% 56.45%
JULIO JULIO S/ 527,984.76 S/ 2,004,606.32 20.18% 76.64%
AGOSTO AGOSTO S/ 599,776.50 S/ 2,604,382.82 22.93% 99.56%
SETIEMBRE SETIEMBRE S/ 11,388.96 S/ 2,615,771.78 0.44% 100.00%
TOTAL 2,615,771.78 100.00%
RVA S
ON AGRICOLA DEL DISTRITO DE UNION ASHANINKA - LA CONVENCION - CUSCO" CON CODICO UNICO N° 2557659
UNION ASHANINKA

EJECUTADO
MONTO PARCIAL PORCENTAJES
ESTADO DE
PARCIAL ACUMULADO PARCIALACUMULADO AVANCE

S/. S/. % %

S/ 1,402,754.03 S/ 1,402,754.03 53.63% 53.63% Adelantado

1,402,754.03 53.63%
0 0
53.63% 53.63%
º

VALORIZACION PRINCIPAL N°- 03


( MES DEL 26 DE AGOSTO AL 25 DE SETIEMBRE 2019)
PLAZO DE EJECUCION: 06 MESES
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-
ACTIVIDAD: FECHA DE INICIO DE OBRA : 7/1/2019
CUSCO(QUISTO CENTRAL)"
FECHA DE TERMINO DE OBRA PR 12/27/2019
SUPERVISOR: ING. MARIO JOSEPH HUAYHUA BERROCAL MODALIDAD DE EJECUCION: ADM. DIRECTA
RESIDENTE : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.02 FLETE TERRESTRE
01.02.01 FLETE TERRESTRE A OBRA GLB 1 29,543.90 29,543.90 0.40 11,817.56 40% 0.20 5,908.78 20% 0.60 ### 17,726.34 60% 0.40 11,817.56 40%
01.02.02 MOVILIZACION Y DESMOVILIZACION GLB 1 13,499.20 13,499.20 0.40 5,399.68 40% 0.20 2,699.84 20% 0.60 ### 8,099.52 60% 0.40 5,399.68 40%
01.03 SEGURIDAD Y SALUD
01.03.01 CAPACITACION DE PLAN DE SEGURIDAD Y SALUD GLB 1 2,950.00 2,950.00 0.20 590.00 20% 0.20 590.00 20% 0.40 ### 1,180.00 40% 0.60 1,770.00 60%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 1194.75 25.87 30,908.18 253.13 6,548.34 21% 759.38 19,645.03 64% 1,012.50 ### 26,193.38 85% 182.25 4,714.81 15%
01.10.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 89.1 32.01 2,852.09 0.00 0.00 0% 47.25 1,512.47 53% 47.25 ### 1,512.47 53% 41.85 1,339.62 47%
01.10.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 121.13 34.26 4,149.91 0.00 0.00 0% 63.75 2,184.08 53% 63.75 ### 2,184.08 53% 57.38 1,965.84 47%
01.10.01.04 EJECUCION DE BRUÑAS m 642.6 8.22 5,282.17 93.75 770.63 15% 300.75 2,472.17 47% 394.50 ### 3,242.79 61% 248.10 2,039.38 39%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.02 OBRAS DE CONCRETO SIMPLE
01.11.02.04 FALSO PISO
01.11.02.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 165.27 31.87 5,267.15 0.00 0.00 0% 165.27 5,267.15 100% 165.27 ### 5,267.15 100% 0.00 0.00 0%
01.11.03 OBRAS DE CONCRETO ARMADO
01.11.03.03 COLUMNAS
01.11.03.03.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 24.75 498.90 12,347.78 6.77 3,376.93 27% 12.84 6,407.63 52% 19.61 ### 9,784.56 79% 5.14 2,563.21 21%
01.11.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 265.03 77.61 20,568.98 70.50 5,471.51 27% 138.13 10,720.15 52% 208.63 ### 16,191.65 79% 56.40 4,377.33 21%
01.11.03.04 VIGAS
01.11.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 31.73 415.22 13,174.93 0.00 0.00 0% 17.14 7,116.04 54% 17.14 ### 7,116.04 54% 14.59 6,058.89 46%
01.11.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 254.51 77.61 19,752.52 0.00 0.00 0% 155.36 12,057.49 61% 155.36 ### 12,057.49 61% 99.15 7,695.03 39%
01.11.03.04.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 3637.79 5.19 18,880.13 0.00 0.00 0% 2,130.09 11,055.17 59% 2,130.09 ### 11,055.17 59% 1,507.70 7,824.96 41%
01.11.03.05 LOSAS ALIGERADAS
01.11.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. m3 44.55 404.08 18,001.76 0.00 0.00 0% 21.80 8,810.26 49% 21.80 ### 8,810.26 49% 22.75 9,191.51 51%
01.11.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 509.12 93.30 47,500.90 0.00 0.00 0% 205.44 19,167.55 40% 205.44 ### 19,167.55 40% 303.68 28,333.34 60%
01.11.03.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS ALIGERADAS. kg 1906.24 5.19 9,893.39 0.00 0.00 0% 1,098.07 5,698.99 58% 1,098.07 ### 5,698.99 58% 808.17 4,194.39 42%
01.11.03.05.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 4240.97 4.81 20,399.07 0.00 0.00 0% 1,711.32 8,231.43 40% 1,711.32 ### 8,231.43 40% 2,529.65 12,167.64 60%
01.11.03.06 LOZA MASCIZA DE CONCRETO
01.11.03.06.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS MACIZAS. kg 806.35 5.19 4,184.96 0.00 0.00 0% 591.22 3,068.43 73% 591.22 ### 3,068.43 73% 215.13 1,116.53 27%
01.11.03.07 ESCALERA DE CONCRETO
01.11.03.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 3.35 498.90 1,671.32 0.00 0.00 0% 3.35 1,671.32 100% 3.35 ### 1,671.32 100% 0.00 0.00 0%
01.11.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 33.09 132.71 4,391.37 0.00 0.00 0% 33.09 4,391.37 100% 33.09 ### 4,391.37 100% 0.00 0.00 0%
01.11.03.07.03 ACERO DE REFUERZO FY=4200 KG/CM2.PARA ESCALERAS kg 521.28 5.19 2,705.44 0.00 0.00 0% 521.28 2,705.44 100% 521.28 ### 2,705.44 100% 0.00 0.00 0%
01.11.03.08 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.11.03.08.01 ACERO DE REFUERZO FY=4200 KG/CM2.. kg 999.72 5.19 5,188.55 379.74 1,970.85 38% 619.98 3,217.70 62% 999.72 ### 5,188.55 100% 0.00 0.00 0%
01.11.03.08.02 ENCOFRADO Y DESENCOFRADO m2 308.25 47.77 14,725.10 0.00 0.00 0% 18.75 895.69 6% 18.75 ### 895.69 6% 289.50 13,829.42 94%
01.11.03.08.03 CONCRETO F'C=175 KG/CM2 m3 14.72 413.40 6,085.25 0.00 0.00 0% 4.46 1,842.94 30% 4.46 ### 1,842.94 30% 10.26 4,242.31 70%
01.11.04 MUROS Y TABIQUES DE ALBAÑILERIA
01.11.04.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 E=1.5 CM m2 131.88 108.41 14,297.11 68.57 7,433.78 52% 63.31 6,863.33 48% 131.88 ### 14,297.11 100% 0.00 0.00 0%
01.11.04.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 154.52 63.52 9,815.11 36.87 2,342.11 24% 0.00 0% 36.87 ### 2,342.11 24% 117.65 7,473.00 76%
01.11.15 INSTALACIONES SANITARIAS
01.11.15.01 SALIDA DE PVC SAL PARA DESAGUE DE 2" pto 1 67.73 67.73 0.00 0.00 0% 1.00 67.73 100% 1.00 ### 67.73 100% 0.00 0.00 0%
01.11.15.04 TUBERIA PVC SAL Ø 2" m 15 10.58 158.70 0.00 0.00 0% 15.00 158.70 100% 15.00 ### 158.70 100% 0.00 0.00 0%
01.11.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.11.16.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2". pto 1 57.79 57.79 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 57.79 100%
01.11.16.02 TUBERIA PVC - SAP DE 1/2" m 15 9.81 147.15 0.00 0.00 0% 15.00 147.15 100% 15.00 ### 147.15 100% 0.00 0.00 0%
01.11.19 INSTALACIONES ELECTRICAS
01.11.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.11.19.01.01 CENTROS DE LUZ EN TECHOS pto 38 140.21 5,327.98 0.00 0.00 0% 18.00 2,523.78 47% 18.00 ### 2,523.78 47% 20.00 2,804.20 53%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.02 MOVIMIENTO DE TIERRAS
01.12.02.02 EXCAVACIONES
01.12.02.02.01 EXCAVACION MANUAL DE ZANJAS Y ZAPATAS m3 34.47 42.46 1,463.60 0.00 0.00 0% 34.47 1,463.60 100% 34.47 ### 1,463.60 100% 0.00 0.00 0%
01.12.02.04 ELIMINACION DE MATERIAL EXEDENTE
01.12.02.04.01 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 28.54 17.69 504.87 0.00 0.00 0% 28.54 504.87 100% 28.54 ### 504.87 100% 0.00 0.00 0%
01.12.02.04.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 28.54 8.47 241.73 0.00 0.00 0% 28.54 241.73 100% 28.54 ### 241.73 100% 0.00 0.00 0%
01.12.02.05 REFINE Y NIVELACION
01.12.02.05.01 REFINE Y NIVELACION EN TERRENO m2 94.16 6.74 634.64 0.00 0.00 0% 94.16 634.64 100% 94.16 ### 634.64 100% 0.00 0.00 0%
01.12.02.05.02 AFIRMADO DE 4" CON MAT. DE PRESTAMO m2 94.16 13.44 1,265.51 0.00 0.00 0% 94.16 1,265.51 100% 94.16 ### 1,265.51 100% 0.00 0.00 0%
01.12.03 OBRAS DE CONCRETO SIMPLE
01.12.03.01 CIMIENTO CORRIDO
01.12.03.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 7.5 193.75 1,453.13 0.00 0.00 0% 7.50 1,453.13 100% 7.50 ### 1,453.13 100% 0.00 0.00 0%
01.12.03.02 SOLADO
01.12.03.02.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 7.78 36.45 283.58 0.00 0.00 0% 7.78 283.58 100% 7.78 ### 283.58 100% 0.00 0.00 0%
01.12.04 OBRAS DE CONCRETO ARMADO
01.12.04.01 ZAPATAS
01.12.04.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 6.48 398.47 2,582.09 0.00 0.00 0% 6.48 2,582.09 100% 6.48 ### 2,582.09 100% 0.00 0.00 0%
01.12.04.02 VIGAS DE CIMENTACION
01.12.04.02.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGA DE CIMENTACION. kg 272.08 5.19 1,412.10 0.00 0.00 0% 272.08 1,412.10 100% 272.08 ### 1,412.10 100% 0.00 0.00 0%
01.12.04.03 COLUMNAS
01.12.04.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 420.25 5.19 2,181.10 0.00 0.00 0% 420.25 2,181.10 100% 420.25 ### 2,181.10 100% 0.00 0.00 0%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.02 MOVIMIENTO DE TIERRAS
01.13.02.02 RELLENOS
01.13.02.02.01 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO m3 2.9 67.32 195.23 0.00 0.00 0% 2.90 195.23 100% 2.90 ### 195.23 100% 0.00 0.00 0%
01.13.04 OBRAS DE CONCRETO ARMADO
01.13.04.01 CONCRETO EN CISTERNA
01.13.04.01.01 CONCRETO F´C=210KG/CM2 EN CISTERNA m3 7.84 501.55 3,932.15 0.00 0.00 0% 7.84 3,932.15 100% 7.84 ### 3,932.15 100% 0.00 0.00 0%
01.13.04.01.02 ENCOFRADO Y DESENCOFRADO PARA CISTERNA m2 50.65 103.27 5,230.63 0.00 0.00 0% 50.65 5,230.63 100% 50.65 ### 5,230.63 100% 0.00 0.00 0%
01.13.04.02 COLUMNAS
01.13.04.02.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.05 498.90 1,521.65 0.00 0.00 0% 3.05 1,521.65 100% 3.05 ### 1,521.65 100% 0.00 0.00 0%
01.13.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 6.28 77.61 487.39 0.00 0.00 0% 6.28 487.39 100% 6.28 ### 487.39 100% 0.00 0.00 0%
01.13.04.03 VIGAS
01.13.04.03.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 1.03 415.22 427.68 0.00 0.00 0% 1.03 427.68 100% 1.03 ### 427.68 100% 0.00 0.00 0%
01.13.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 2.79 77.61 216.53 0.00 0.00 0% 2.79 216.53 100% 2.79 ### 216.53 100% 0.00 0.00 0%
01.13.04.04 LOZA MASCIZA
01.13.04.04.01 CONCRETO EN LOSAS MACIZAS ESCALERA F'C=210 KG/CM2 m3 0.87 414.23 360.38 0.00 0.00 0% 0.87 360.38 100% 0.87 ### 360.38 100% 0.00 0.00 0%
01.13.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 5.5 93.30 513.15 0.00 0.00 0% 5.50 513.15 100% 5.50 ### 513.15 100% 0.00 0.00 0%
01.13.04.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS MACIZAS. kg 19.89 5.19 103.23 0.00 0.00 0% 19.89 103.23 100% 19.89 ### 103.23 100% 0.00 0.00 0%
01.13.04.05 TANQUE ELEVADO
01.13.04.05.01 CONCRETO EN TANQUE ELEVADO F'C=210 KG/CM2 m3 8.34 515.70 4,300.94 0.00 0.00 0% 8.34 4,300.94 100% 8.34 ### 4,300.94 100% 0.00 0.00 0%
01.13.04.05.02 ENCOFRADO Y DESENCOFRADO EN MUROS Y PLACAS m2 67.89 118.28 8,030.03 0.00 0.00 0% 67.89 8,030.03 100% 67.89 ### 8,030.03 100% 0.00 0.00 0%
01.13.04.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN EN MUROS REFORZADOS Y/O PLkg 206.71 5.19 1,072.82 0.00 0.00 0% 206.71 1,072.82 100% 206.71 ### 1,072.82 100% 0.00 0.00 0%
01.13.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.13.05.01 MURO DE LADRILLO KK SOGA
01.13.05.01.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 E=1.5 CM m2 0.62 108.41 67.21 0.00 0.00 0% 0.62 67.21 100% 0.62 ### 67.21 100% 0.00 0.00 0%
01.13.05.01.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 6.13 63.52 389.38 0.00 0.00 0% 6.13 389.38 100% 6.13 ### 389.38 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.03 OBRAS DE CONCRETO ARMADO
01.14.01.03.01 TRIBUNAS
01.14.01.03.01.05 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS Y VIGAS kg 479.54 5.19 2,488.81 0.00 0.00 0% 161.87 840.12 34% 161.87 ### 840.12 34% 317.67 1,648.69 66%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 114.32 109.80 12,552.34 0.00 0.00 0% 4.62 507.28 4% 4.62 ### 507.28 4% 109.70 12,045.06 96%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 27.03 104.62 2,827.88 0.00 0.00 0% 9.29 971.52 34% 9.29 ### 971.52 34% 17.74 1,856.36 66%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 58.29 413.40 24,097.09 0.00 0.00 0% 21.67 8,957.47 37% 21.67 ### 8,957.47 37% 36.62 15,139.62 63%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 4877.83 5.19 25,315.94 2,135.00 11,080.66 44% 605.69 3,143.52 12% 2,740.69 ### 14,224.19 56% 2,137.14 11,091.75 44%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 180.22 62.00 11,173.64 0.00 0.00 0% 61.91 3,838.30 34% 61.91 ### 3,838.30 34% 118.31 7,335.34 66%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 15.39 30.00 461.70 0.00 0.00 0% 9.00 270.00 58% 9.00 ### 270.00 58% 6.39 191.70 42%
COSTO DIRECTO 2,278,432.36 264,597.85 11.61% 214,496.72 9.41% ### 479,094.58 21.03% 1,799,337.72 78.97%
GASTOS GENERALES (11.13 %CD) 253,654.58 29,457.30 23,879.60 ### 53,336.90 200,317.69
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 8,978.84 7,278.71 16,257.55 61,058.57
SUB TOTAL 2,609,403.06 303,033.99 11.61% 245,655.04 9.41% 548,689.02 21.03% 2,060,713.98 78.97%
º

VALORIZACION PRINCIPAL N°- 10


( MES DE 26 DE JUNIO AL 25 JULIO DEL 2020)
FECHA DE INICIO DE OBRA : ´01/07/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° : 75 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 8/30/2020

PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR


MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.02 PINTURAS 0.00
01.08.02.05 PINTURA EN ZOCALOS m 209.8 9.31 1,953.24 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 209.80 1,953.24 100%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.01 PINTURAS
01.09.01.05 PINTURA EN ZOCALOS m 193.93 9.31 1,805.49 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 193.93 1,805.49 100%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 1194.75 25.87 30,908.18 1,103.63 28,550.91 92% 0.00 0% 1,103.63 ### 28,550.91 92% 91.12 2,357.27 8%
01.10.02 PINTURAS
01.10.02.01 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 1194.75 12.41 14,826.85 0.00 0.00 0% 243.00 3,015.63 20% 243.00 ### 3,015.63 20% 951.75 11,811.22 80%
01.10.02.02 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 89.1 14.34 1,277.69 0.00 0.00 0% 16.88 241.99 19% 16.88 ### 241.99 19% 72.23 1,035.71 81%
01.10.02.03 PINTURA AL LATEX DOS MANOS EN VIGAS m2 106.88 14.34 1,532.66 0.00 0.00 0% 13.50 193.59 13% 13.50 ### 193.59 13% 93.38 1,339.07 87%
01.10.02.04 PINTURA EN ZOCALOS m 800.62 9.31 7,453.77 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 800.62 7,453.77 100%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.13 PINTURA
01.11.13.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 608.28 12.41 7,548.75 304.14 3,774.37 50% 0.00 0% 304.14 ### 3,774.37 50% 304.14 3,774.38 50%
01.11.13.05 PINTURA EN ZOCALOS m 130.4 9.31 1,214.02 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 130.40 1,214.02 100%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.07 PISOS Y PAVIMENTOS
01.12.07.02 PISOS
01.12.07.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 49.35 63.25 3,121.39 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 49.35 3,121.39 100%
01.12.07.03 VEREDAS Y RAMPAS
01.12.07.03.02 JUNTAS DE DILATACION EN E=1" m 70 31.99 2,239.30 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 70.00 2,239.30 100%
01.12.13 PINTURA
01.12.13.01 PINTURA EN GENERAL
01.12.13.01.01 PINTURA AL LATEX EN CIELO RASO m2 76.67 14.34 1,099.45 0.00 0.00 0% 38.34 549.72 50% 38.34 ### 549.72 50% 38.34 549.72 50%
01.12.13.01.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 131.6 12.41 1,633.16 0.00 0.00 0% 65.70 815.34 50% 65.70 ### 815.34 50% 65.90 817.82 50%
01.12.13.01.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 19.89 14.34 285.22 0.00 0.00 0% 9.50 136.23 48% 9.50 ### 136.23 48% 10.39 148.99 52%
01.12.13.01.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 53.58 14.34 768.34 0.00 0.00 0% 27.80 398.65 52% 27.80 ### 398.65 52% 25.78 369.69 48%
01.12.13.01.05 PINTURA EN ZOCALOS m 8.88 9.31 82.67 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 8.88 82.67 100%
01.12.14 APARATOS SANITARIOS Y ACCESORIOS
01.12.14.01 INODORO TANQUE BAJO COLOR pza 10 200.00 2,000.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 10.00 2,000.00 100%
01.12.15 INSTALACIONES SANITARIAS
01.12.15.03 SUMIDEROS DE BRONCE 4" pza 5 102.56 512.80 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 5.00 512.80 100%
01.12.15.04 REGISTROS DE BRONCE DE 4" pza 8 73.32 586.56 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 8.00 586.56 100%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.12 PINTURA
01.13.12.01 PINTURA EN GENERAL
01.13.12.01.03 PINTURA ESMALTE SINTETICO 2 MANOS EN ZOCALO Y CONTRAZOCALO m 15.99 9.31 148.87 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 15.99 148.87 100%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.03 OBRAS DE CONCRETO ARMADO
01.14.02.03.03 TARRAJEO EN GENERAL
01.14.02.03.03.01 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 28.8 37.15 1,069.92 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 28.80 1,069.92 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.03 PISOS Y PAVIMENTOS
01.15.03.01 VEREDAS Y RAMPAS
01.15.03.01.03 JUNTAS DE DILATACION EN VEREDAS m 134.05 31.99 4,288.26 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 134.05 4,288.26 100%
01.15.07 INSTALACIONES ELECTRICAS EXTERIORES
01.15.07.03 CANALIZACION Y TUBERIAS
01.15.07.03.01 EXCAVACION DE ZANJAS PARA REDES EXT. ELECTRICAS m3 149.27 42.46 6,338.00 116.84 4,960.86 78% 0.00 0% 116.84 ### 4,960.86 78% 32.43 1,377.15 22%
01.15.07.03.02 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 144.4 67.32 9,721.01 109.93 7,400.59 76% 0.00 0% 109.93 ### 7,400.59 76% 34.47 2,320.42 24%
01.15.07.03.03 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 6.34 17.69 112.15 5.85 103.49 92% 0.00 0% 5.85 ### 103.49 92% 0.49 8.67 8%
01.15.07.03.04 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 6.34 8.47 53.70 5.85 49.55 92% 0.00 0% 5.85 ### 49.55 92% 0.49 4.15 8%
01.15.07.03.05 TUBERIA PVC-P 35mm m 412.56 11.51 4,748.57 337.00 3,878.87 82% 0.00 0% 337.00 ### 3,878.87 82% 75.56 869.70 18%
01.15.07.05 CONEXIONES A RED EXTERNA Y MEDIDORES
01.15.07.05.01 ALIMENTADOR CABLE NYY(3x25)MM2 m 11.59 43.38 502.77 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 11.59 502.77 100%
01.15.07.05.02 ALIMENTADOR CABLE NYY(2X6+1X2.5)MM2 m 11.59 14.57 168.87 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 11.59 168.87 100%
01.15.07.05.03 ALIMENTADOR CABLE NYY(2X10+1X6)MM2 m 464.44 20.09 9,330.60 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 464.44 9,330.60 100%
02 COMPONENTE 02: EQUIPAMIENTO Y MOBILIARIO
02.01 EQUIPAMIENTO MÓDULO PEDAGÓGICO
02.01.02 EQUIPAMIENTO SALA DE USOS MULTLIPE GLB 1 27,233.09 27,233.09 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 27,233.09 100%
02.02 EQUIPAMIENTO MÓDULO COMPLEMENTARIO
02.02.01 EQUIPAMIENTO LABORATORIO GLB 1 41,314.62 41,314.62 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 41,314.62 100%
02.02.02 EQUIPAMIENTO DE GUARDIANIA GLB 1 1,086.09 1,086.09 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 1,086.09 100%
02.02.03 EQUIPAMIENTO DIRECCION GLB 1 6,953.78 6,953.78 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 6,953.78 100%
02.02.04 EQUIPAMIENTO SALA DE PROFESORES GLB 1 2,814.04 2,814.04 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 2,814.04 100%
02.02.05 EQUIPAMIENTO TOPICO GLB 1 2,852.97 2,852.97 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 2,852.97 100%
02.02.06 EQUIPAMIENTO ARCHIVOS GLB 1 936.67 936.67 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 936.67 100%
02.02.07 EQUIPAMIENTO DE DEPOSITO DE LIMPIEZA GLB 1 1,892.12 1,892.12 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 1,892.12 100%
02.02.08 EQUIPAMIENTO DE COCINA GLB 1 11,542.23 11,542.23 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 11,542.23 100%
02.02.09 EQUIPAMIENTO SALA DE COMPUTO GLB 1 119,755.77 119,755.77 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 119,755.77 100%
02.02.10 EQUIPAMIENTO BIBLIOTECA GLB 1 54,224.09 54,224.09 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 54,224.09 100%
COSTO DIRECTO 2,278,432.36 1,462,930.04 64.21% 91,772.88 4.03% ### 1,554,702.92 68.24% 723,729.37 31.76%
GASTOS GENERALES (11.13 %CD) 253,654.58 162,865.89 10,216.93 ### 173,082.82 80,571.77
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 49,642.94 3,114.21 52,757.15 24,558.97
SUB TOTAL 2,609,403.06 1,675,438.86 64.21% 105,104.03 4.03% 1,780,542.89 68.24% 828,860.11 31.76%
º

VALORIZACION FINAL DE OBRA PRINCIPAL N°- 12


( MES DE SETIEMBRE DEL 2020)

MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL


ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
COSTO COSTO
ÍTEM PARTIDA
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01.05 MEJORAMIENTO DE LOSA DEPORTIVA EXISTENTE
01.14.01.05.07 PINTURA EN CAMPO DE JUEGO ML 550 8.26 4,543.00 0.00 0.00 0% 550.00 4,543.00 100% 550.00 ### 4,543.00 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.01 TRABAJOS PRELIMINARES
01.15.01.01 REUBICACIÓN E INSTALACIÓN A SERVICIO PÚBLICO DE LUZ, AGUA Y DESAGÜE
01.15.01.01.01 REUBICACION Y INSTALACIÓN DE ACOMETIDA DE LUZ, MEDIDORES DE GLB 1 1,500.00 1,500.00 0.00 0.00 0% 1.00 1,500.00 100% 1.00 ### 1,500.00 100% 0.00 0.00 0%
02 COMPONENTE 02: EQUIPAMIENTO Y MOBILIARIO
02.01 EQUIPAMIENTO MÓDULO PEDAGÓGICO
02.01.01 EQUIPAMIENTO AULAS GLB 7 13,435.71 94,049.97 3.00 40,307.13 43% 4.00 53,742.84 57% 7.00 ### 94,049.97 100% 0.00 0.00 0%
02.01.02 EQUIPAMIENTO SALA DE USOS MULTLIPE GLB 1 27,233.09 27,233.09 0.40 10,893.24 40% 0.60 16,339.85 60% 1.00 ### 27,233.09 100% 0.00 0.00 0%
02.02.10 EQUIPAMIENTO BIBLIOTECA GLB 1 54,224.09 54,224.09 0.50 27,112.05 50% 0.50 27,112.05 50% 1.00 ### 54,224.09 100% 0.00 0.00 0%
04 COMPONENTE 04: MITIGACION AMBIENTAL
04.01 MANEJO AMBIENTAL Y PLAN DE CIERRE
04.01.06 NIVELACION DEL AREA DE BOTADERO und 800 4.49 3,592.00 200.00 898.00 25% 600.00 2,694.00 75% 800.00 ### 3,592.00 100% 0.00 0.00 0%
04.01.07 INSTALACION DE AREAS VERDES m2 2325.07 11.37 26,436.05 500.00 5,685.00 22% 1,825.07 20,751.05 78% 2,325.07 ### 26,436.05 100% 0.00 0.00 0%
04.01.08 SEMBRADO DE PLANTAS ORNAMENTALES und 150 16.04 2,406.00 0.00 0.00 0% 150.00 2,406.00 100% 150.00 ### 2,406.00 100% 0.00 0.00 0%
04.01.09 LIMPIEZA FINAL DE OBRA m2 2225.85 0.20 445.17 500.00 100.00 22% 1,725.85 345.17 78% 2,225.85 ### 445.17 100% 0.00 0.00 0%
COSTO DIRECTO 2,278,432.36 1,891,409.38 83.01% 129,433.95 5.68% ### 2,020,843.33 88.69% 257,589.02 11.31%
GASTOS GENERALES (11.13 %CD) 253,654.58 210,567.87 14,409.69 ### 224,977.56 28,677.03
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 64,182.92 4,392.20 68,575.12 8,741.00
SUB TOTAL 2,609,403.06 2,166,160.17 83.01% 148,235.84 5.68% 2,314,396.01 88.69% 295,007.06 11.31%
º

VALORIZACION PRINCIPAL N°- 10


( MES DE 26 JUNIO AL 25 DE JULIO DEL 2020)

MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL


ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
COSTO COSTO
ÍTEM PARTIDA
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 ALMACEN DE OBRA m2 60 168.37 10,102.20 60.00 10,102.20 100% 0.00 0% 60.00 ### 10,102.20 100% 0.00 0.00 0%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und 1 1,122.33 1,122.33 1.00 1,122.33 100% 0.00 0% 1.00 ### 1,122.33 100% 0.00 0.00 0%
01.01.03 CERCO DE OBRA CON POSTES ROLLIZOS Y ARPILLERA m 141.08 20.04 2,827.24 141.08 2,827.24 100% 0.00 0% 141.08 ### 2,827.24 100% 0.00 0.00 0%
01.01.04 INSTALACION PROVISIONAL DE SS.HH und 2 3,115.20 6,230.40 2.00 6,230.40 100% 0.00 0% 2.00 ### 6,230.40 100% 0.00 0.00 0%
01.01.05 INSTALACION PROVISIONAL DE ENERGIA ELECTRICA GLB 1 1,003.00 1,003.00 1.00 1,003.00 100% 0.00 0% 1.00 ### 1,003.00 100% 0.00 0.00 0%
01.01.06 INSTALACION PROVISIONAL DE AGUA PARA OBRA GLB 1 767.00 767.00 1.00 767.00 100% 0.00 0% 1.00 ### 767.00 100% 0.00 0.00 0%
01.02 FLETE TERRESTRE
01.02.01 FLETE TERRESTRE A OBRA GLB 1 29,543.90 29,543.90 1.00 29,543.90 100% 0.00 0% 1.00 ### 29,543.90 100% 0.00 0.00 0%
01.02.02 MOVILIZACION Y DESMOVILIZACION GLB 1 13,499.20 13,499.20 1.00 13,499.20 100% 0.00 0% 1.00 ### 13,499.20 100% 0.00 0.00 0%
01.03 SEGURIDAD Y SALUD
01.03.01 CAPACITACION DE PLAN DE SEGURIDAD Y SALUD GLB 1 2,950.00 2,950.00 1.00 2,950.00 100% 0.00 0% 1.00 ### 2,950.00 100% 0.00 0.00 0%
01.03.02 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1 12,177.60 12,177.60 1.00 12,177.60 100% 0.00 0% 1.00 ### 12,177.60 100% 0.00 0.00 0%
01.03.03 EQUIPOS DE PROTECCION COLECTIVA GLB 1 3,363.00 3,363.00 1.00 3,363.00 100% 0.00 0% 1.00 ### 3,363.00 100% 0.00 0.00 0%
01.03.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1 542.80 542.80 1.00 542.80 100% 0.00 0% 1.00 ### 542.80 100% 0.00 0.00 0%
01.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DUGLB 1 387.63 387.63 1.00 387.63 100% 0.00 0% 1.00 ### 387.63 100% 0.00 0.00 0%
01.05 DEMOLICION DE CAFETIN
01.05.01 DEMOLICION DE CONSTRUCCIÓN DE ALBAÑILERIA Y CONCRETO ARMADO m3 115.08 7.95 914.89 115.08 914.89 100% 0.00 0% 115.08 ### 914.89 100% 0.00 0.00 0%
01.05.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 143.85 11.66 1,677.29 143.85 1,677.29 100% 0.00 0% 143.85 ### 1,677.29 100% 0.00 0.00 0%
01.06 LIMPIEZA DE TERRENO
01.06.01 LIMPIEZA DE TERRENO MANUAL m2 352.87 3.22 1,136.24 352.87 1,136.24 100% 0.00 0% 352.87 ### 1,136.24 100% 0.00 0.00 0%
01.07 TRAZO, NIVELES Y REPLANTEO 0.00
01.07.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 352.87 10.08 3,556.93 352.87 3,556.93 100% 0.00 0% 352.87 ### 3,556.93 100% 0.00 0.00 0%
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.01 REVOQUES ENLUCIDOS Y MOLDURAS
01.08.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 26.45 25.87 684.26 26.45 684.26 100% 0.00 0% 26.45 ### 684.26 100% 0.00 0.00 0%
01.08.02 PINTURAS 0.00
01.08.02.01 PINTURA AL LATEX EN CIELO RASO m2 356 14.34 5,105.04 356.00 5,105.04 100% 0.00 0% 356.00 ### 5,105.04 100% 0.00 0.00 0%
01.08.02.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 816 12.41 10,126.56 816.00 10,126.56 100% 0.00 0% 816.00 ### 10,126.56 100% 0.00 0.00 0%
01.08.02.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 84.6 14.34 1,213.16 84.60 1,213.16 100% 0.00 0% 84.60 ### 1,213.16 100% 0.00 0.00 0%
01.08.02.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 209.79 14.34 3,008.39 209.79 3,008.39 100% 0.00 0% 209.79 ### 3,008.39 100% 0.00 0.00 0%
01.08.02.05 PINTURA EN ZOCALOS m 209.8 9.31 1,953.24 0.00 0.00 0% 209.80 1,953.24 100% 209.80 ### 1,953.24 100% 0.00 0.00 0%
01.08.03 REPOSICION DE CANALETA PLUVIAL 0.00
01.08.03.01 CANAL SEMICIRCULAR PLANCHA DE ALUMINIO m 94 97.96 9,208.24 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 94.00 9,208.24 100%
01.08.04 REPOSICION DE PISOS 0.00
01.08.04.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 208 63.25 13,156.00 208.00 13,156.00 100% 0.00 0% 208.00 ### 13,156.00 100% 0.00 0.00 0%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.01 PINTURAS
01.09.01.01 PINTURA AL LATEX EN CIELO RASO m2 162 14.34 2,323.08 162.00 2,323.08 100% 0.00 0% 162.00 ### 2,323.08 100% 0.00 0.00 0%
01.09.01.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 408.6 12.41 5,070.73 408.60 5,070.73 100% 0.00 0% 408.60 ### 5,070.73 100% 0.00 0.00 0%
01.09.01.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 111.3 14.34 1,596.04 111.30 1,596.04 100% 0.00 0% 111.30 ### 1,596.04 100% 0.00 0.00 0%
01.09.01.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 209.38 14.34 3,002.51 209.38 3,002.51 100% 0.00 0% 209.38 ### 3,002.51 100% 0.00 0.00 0%
01.09.01.05 PINTURA EN ZOCALOS m 193.93 9.31 1,805.49 0.00 0.00 0% 193.93 1,805.49 100% 193.93 ### 1,805.49 100% 0.00 0.00 0%
01.09.02 REPOSICION DE PISOS
01.09.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 248.4 63.25 15,711.30 248.40 15,711.30 100% 0.00 0% 248.40 ### 15,711.30 100% 0.00 0.00 0%
01.09.03 PUERTAS SS.HH.
01.09.03.01 PUERTAS DE MADERA TORNILLO APANELADA m2 4 565.23 2,260.92 4.00 2,260.92 100% 0.00 0% 4.00 ### 2,260.92 100% 0.00 0.00 0%
01.09.03.02 PUERTA METALICA m2 8.64 548.11 4,735.67 8.64 4,735.67 100% 0.00 0% 8.64 ### 4,735.67 100% 0.00 0.00 0%
01.09.03.03 BISAGRA CAPUCHINA DE 4" X4" und 30 19.69 590.70 30.00 590.70 100% 0.00 0% 30.00 ### 590.70 100% 0.00 0.00 0%
01.09.03.04 MANIJA DE BRONCE PARA PUERTAS und 10 57.53 575.30 10.00 575.30 100% 0.00 0% 10.00 ### 575.30 100% 0.00 0.00 0%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 1194.75 25.87 30,908.18 1,114.77 28,839.03 93% 29.36 759.48 2% 1,144.13 ### 29,598.51 96% 50.63 1,309.67 4%
01.10.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 89.1 32.01 2,852.09 81.00 2,592.81 91% 0.00 0% 81.00 ### 2,592.81 91% 8.10 259.28 9%
01.10.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 121.13 34.26 4,149.91 101.25 3,468.83 84% 0.00 0% 101.25 ### 3,468.83 84% 19.88 681.09 16%
01.10.01.04 EJECUCION DE BRUÑAS m 642.6 8.22 5,282.17 591.00 4,858.02 92% 0.00 0% 591.00 ### 4,858.02 92% 51.60 424.15 8%
01.10.02 PINTURAS
01.10.02.01 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 1194.75 12.41 14,826.85 243.00 3,015.63 20% 901.13 11,182.96 75% 1,144.13 ### 14,198.59 96% 50.63 628.26 4%
01.10.02.02 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 89.1 14.34 1,277.69 16.88 241.99 19% 64.13 919.55 72% 81.00 ### 1,161.54 91% 8.10 116.15 9%
01.10.02.03 PINTURA AL LATEX DOS MANOS EN VIGAS m2 106.88 14.34 1,532.66 13.50 193.59 13% 87.75 1,258.34 82% 101.25 ### 1,451.93 95% 5.63 80.73 5%
01.10.02.04 PINTURA EN ZOCALOS m 800.62 9.31 7,453.77 0.00 0.00 0% 724.62 6,746.21 91% 724.62 ### 6,746.21 91% 76.00 707.56 9%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.01 MOVIMIENTO DE TIERRAS
01.11.01.01 CORTES
01.11.01.01.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 M3/DIA m3 1222.68 6.83 8,350.90 1,222.68 8,350.90 100% 0.00 0% 1,222.68 ### 8,350.90 100% 0.00 0.00 0%
01.11.01.02 NIVELACION
01.11.01.02.01 NIVELACION DE TERRENO m2 352.37 4.31 1,518.71 352.37 1,518.71 100% 0.00 0% 352.37 ### 1,518.71 100% 0.00 0.00 0%
01.11.01.03 EXCAVACIONES
01.11.01.03.01 EXCAVACION MANUAL DE ZANJAS Y ZAPATAS m3 164.81 42.46 6,997.83 164.81 6,997.83 100% 0.00 0% 164.81 ### 6,997.83 100% 0.00 0.00 0%
01.11.01.04 RELLENOS
01.11.01.04.01 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 149.87 67.32 10,089.25 149.87 10,089.25 100% 0.00 0% 149.87 ### 10,089.25 100% 0.00 0.00 0%
01.11.01.04.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 38.95 109.80 4,276.71 38.95 4,276.71 100% 0.00 0% 38.95 ### 4,276.71 100% 0.00 0.00 0%
01.11.01.05 ELIMINACION DE MATERIAL EXEDENTE
01.11.01.05.01 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 197.77 17.69 3,498.55 197.77 3,498.55 100% 0.00 0% 197.77 ### 3,498.55 100% 0.00 0.00 0%
01.11.01.05.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 197.77 8.47 1,675.11 197.77 1,675.11 100% 0.00 0% 197.77 ### 1,675.11 100% 0.00 0.00 0%
01.11.01.06 REFINE Y NIVELACION
01.11.01.06.01 REFINE Y NIVELACION EN TERRENO m2 84.04 6.74 566.43 84.04 566.43 100% 0.00 0% 84.04 ### 566.43 100% 0.00 0.00 0%
01.11.01.06.02 AFIRMADO DE 4" CON MAT. DE PRESTAMO m2 165.27 13.44 2,221.23 165.27 2,221.23 100% 0.00 0% 165.27 ### 2,221.23 100% 0.00 0.00 0%
01.11.02 OBRAS DE CONCRETO SIMPLE
01.11.02.01 CIMIENTO CORRIDO
01.11.02.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 14 192.96 2,701.44 14.00 2,701.44 100% 0.00 0% 14.00 ### 2,701.44 100% 0.00 0.00 0%
01.11.02.02 SOLADO
01.11.02.02.01 SOLADO e = 10 cm f'c = 100 Kg/cm2 m2 83.15 34.31 2,852.88 83.15 2,852.88 100% 0.00 0% 83.15 ### 2,852.88 100% 0.00 0.00 0%
01.11.02.03 SOBRECIMIENTOS CORRIDOS
01.11.02.03.01 SOBRECIMIENTO CORRIDO C-H 1:8 + 25% P.M. m3 12.88 281.74 3,628.81 12.88 3,628.81 100% 0.00 0% 12.88 ### 3,628.81 100% 0.00 0.00 0%
01.11.02.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS HASTA 0.60 M m2 165.73 57.69 9,560.96 165.73 9,560.96 100% 0.00 0% 165.73 ### 9,560.96 100% 0.00 0.00 0%
01.11.02.04 FALSO PISO
01.11.02.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 165.27 31.87 5,267.15 165.27 5,267.15 100% 0.00 0% 165.27 ### 5,267.15 100% 0.00 0.00 0%
01.11.03 OBRAS DE CONCRETO ARMADO
01.11.03.01 ZAPATAS
01.11.03.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 36.42 398.47 14,512.28 36.42 14,512.28 100% 0.00 0% 36.42 ### 14,512.28 100% 0.00 0.00 0%
01.11.03.01.02 ACERO DE REFUERZO FY=4200 KG/CM2 ZAPATAS. kg 978.5 5.19 5,078.42 978.50 5,078.42 100% 0.00 0% 978.50 ### 5,078.42 100% 0.00 0.00 0%
01.11.03.02 VIGAS DE CIMENTACION
01.11.03.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 5.72 398.47 2,279.25 5.72 2,279.25 100% 0.00 0% 5.72 ### 2,279.25 100% 0.00 0.00 0%
01.11.03.02.02 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION m2 32.1 70.68 2,268.83 32.10 2,268.83 100% 0.00 0% 32.10 ### 2,268.83 100% 0.00 0.00 0%
01.11.03.02.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGA DE CIMENTACION. kg 776.8 5.19 4,031.59 776.80 4,031.59 100% 0.00 0% 776.80 ### 4,031.59 100% 0.00 0.00 0%
01.11.03.03 COLUMNAS
01.11.03.03.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 24.75 498.90 12,347.78 24.75 12,347.78 100% 0.00 0% 24.75 ### 12,347.78 100% 0.00 0.00 0%
01.11.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 265.03 77.61 20,568.98 265.03 20,568.98 100% 0.00 0% 265.03 ### 20,568.98 100% 0.00 0.00 0%
01.11.03.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 8710.85 5.19 45,209.31 8,710.85 45,209.31 100% 0.00 0% 8,710.85 ### 45,209.31 100% 0.00 0.00 0%
01.11.03.04 VIGAS
01.11.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 31.73 415.22 13,174.93 31.73 13,174.93 100% 0.00 0% 31.73 ### 13,174.93 100% 0.00 0.00 0%
01.11.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 254.51 77.61 19,752.52 254.51 19,752.52 100% 0.00 0% 254.51 ### 19,752.52 100% 0.00 0.00 0%
01.11.03.04.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 3637.79 5.19 18,880.13 3,637.79 18,880.13 100% 0.00 0% 3,637.79 ### 18,880.13 100% 0.00 0.00 0%
01.11.03.05 LOSAS ALIGERADAS
01.11.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. m3 44.55 404.08 18,001.76 44.55 18,001.76 100% 0.00 0% 44.55 ### 18,001.76 100% 0.00 0.00 0%
01.11.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 509.12 93.30 47,500.90 509.12 47,500.90 100% 0.00 0% 509.12 ### 47,500.90 100% 0.00 0.00 0%
01.11.03.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS ALIGERADAS. kg 1906.24 5.19 9,893.39 1,906.24 9,893.39 100% 0.00 0% 1,906.24 ### 9,893.39 100% 0.00 0.00 0%
01.11.03.05.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 4240.97 4.81 20,399.07 4,240.97 20,399.07 100% 0.00 0% 4,240.97 ### 20,399.07 100% 0.00 0.00 0%
01.11.03.06 LOZA MASCIZA DE CONCRETO
01.11.03.06.01 CONCRETO EN LOSAS MACIZAS ESCALERA F'C=210 KG/CM2 m3 2.79 414.23 1,155.70 2.79 1,155.70 100% 0.00 0% 2.79 ### 1,155.70 100% 0.00 0.00 0%
01.11.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 27.88 93.30 2,601.20 27.88 2,601.20 100% 0.00 0% 27.88 ### 2,601.20 100% 0.00 0.00 0%
01.11.03.06.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS MACIZAS. kg 806.35 5.19 4,184.96 806.35 4,184.96 100% 0.00 0% 806.35 ### 4,184.96 100% 0.00 0.00 0%
01.11.03.07 ESCALERA DE CONCRETO
01.11.03.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 3.35 498.90 1,671.32 3.35 1,671.32 100% 0.00 0% 3.35 ### 1,671.32 100% 0.00 0.00 0%
01.11.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 33.09 132.71 4,391.37 33.09 4,391.37 100% 0.00 0% 33.09 ### 4,391.37 100% 0.00 0.00 0%
01.11.03.07.03 ACERO DE REFUERZO FY=4200 KG/CM2.PARA ESCALERAS kg 521.28 5.19 2,705.44 521.28 2,705.44 100% 0.00 0% 521.28 ### 2,705.44 100% 0.00 0.00 0%
01.11.03.08 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.11.03.08.01 ACERO DE REFUERZO FY=4200 KG/CM2.. kg 999.72 5.19 5,188.55 999.72 5,188.55 100% 0.00 0% 999.72 ### 5,188.55 100% 0.00 0.00 0%
01.11.03.08.02 ENCOFRADO Y DESENCOFRADO m2 308.25 47.77 14,725.10 308.25 14,725.10 100% 0.00 0% 308.25 ### 14,725.10 100% 0.00 0.00 0%
01.11.03.08.03 CONCRETO F'C=175 KG/CM2 m3 14.72 413.40 6,085.25 14.72 6,085.25 100% 0.00 0% 14.72 ### 6,085.25 100% 0.00 0.00 0%
01.11.04 MUROS Y TABIQUES DE ALBAÑILERIA
01.11.04.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 E=1.5 CM m2 131.88 108.41 14,297.11 131.88 14,297.11 100% 0.00 0% 131.88 ### 14,297.11 100% 0.00 0.00 0%
01.11.04.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 154.52 63.52 9,815.11 154.52 9,815.11 100% 0.00 0% 154.52 ### 9,815.11 100% 0.00 0.00 0%
01.11.04.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 205.44 23.16 4,757.99 205.44 4,757.99 100% 0.00 0% 205.44 ### 4,757.99 100% 0.00 0.00 0%
01.11.05 REVOQUES, ENLUCIDOS Y MLDURAS
01.11.05.01 TARRAJEO EN GENERAL
01.11.05.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 608.28 25.87 15,736.20 608.28 15,736.20 100% 0.00 0% 608.28 ### 15,736.20 100% 0.00 0.00 0%
01.11.05.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 587.56 32.01 18,807.80 587.56 18,807.80 100% 0.00 0% 587.56 ### 18,807.80 100% 0.00 0.00 0%
01.11.05.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 292.02 34.26 10,004.61 292.02 10,004.61 100% 0.00 0% 292.02 ### 10,004.61 100% 0.00 0.00 0%
01.11.05.01.04 EJECUCION DE BRUÑAS m 342 8.22 2,811.24 342.00 2,811.24 100% 0.00 0% 342.00 ### 2,811.24 100% 0.00 0.00 0%
01.11.05.01.05 VESTIDURA DE DERRAMES m 241.78 22.02 5,324.00 241.78 5,324.00 100% 0.00 0% 241.78 ### 5,324.00 100% 0.00 0.00 0%
01.11.05.01.06 TARRAJEO CON IMPERMEABILIZANTES m2 266.93 31.17 8,320.21 266.93 8,320.21 100% 0.00 0% 266.93 ### 8,320.21 100% 0.00 0.00 0%
01.11.06 CIELO RASOS
01.11.06.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 463.01 44.01 20,377.07 463.01 20,377.07 100% 0.00 0% 463.01 ### 20,377.07 100% 0.00 0.00 0%
01.11.07 PISOS Y PAVIMENTOS
01.11.07.01 CONTRAPISOS
01.11.07.01.01 CONTRAPISO DE 48 MM. m2 454.39 35.84 16,285.34 454.39 16,285.34 100% 0.00 0% 454.39 ### 16,285.34 100% 0.00 0.00 0%
01.11.07.02 PISOS
01.11.07.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 333.45 63.25 21,090.71 333.45 21,090.71 100% 0.00 0% 333.45 ### 21,090.71 100% 0.00 0.00 0%
01.11.07.03 VEREDAS Y RAMPAS
01.11.07.03.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 108.41 59.66 6,467.74 108.41 6,467.74 100% 0.00 0% 108.41 ### 6,467.74 100% 0.00 0.00 0%
01.11.07.03.02 JUNTAS DE DILATACION EN VEREDAS m 108.41 31.99 3,468.04 108.41 3,468.04 100% 0.00 0% 108.41 ### 3,468.04 100% 0.00 0.00 0%
01.11.08 CONTRAZOCALOS
01.11.08.01 CONTRAZOCALOS DE CEMENTO Y CERAMICO
01.11.08.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 89.3 15.69 1,401.12 89.30 1,401.12 100% 0.00 0% 89.30 ### 1,401.12 100% 0.00 0.00 0%
01.11.08.01.02 ZOCALO DE MAYOLICA DE COLOR 20X30 1RA m2 186.6 96.43 17,993.84 186.60 17,993.84 100% 0.00 0% 186.60 ### 17,993.84 100% 0.00 0.00 0%
01.11.09 CUBIERTAS
01.11.09.01 COBERTURA CON TEJA
01.11.09.01.01 COBERTURA CON TEJA ANDINA DECORATIVA m2 306.54 64.49 19,768.76 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 306.54 19,768.76 100%
01.11.09.01.02 CUMBRERA CON TEJA ANDINA DECORATIVA m 28.15 75.21 2,117.16 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 28.15 2,117.16 100%
01.11.10 CARPINTERIA DE MADERA
01.11.10.01 PUERTAS
01.11.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 21.6 565.23 12,208.97 21.60 12,208.97 100% 0.00 0% 21.60 ### 12,208.97 100% 0.00 0.00 0%
01.11.11 CARPINTERIA METALICA Y ALUMINIO
01.11.11.01 VENTANAS METALICAS
01.11.11.01.01 VENTANA DE ALUMINIO m2 80.5 188.19 15,149.30 80.50 15,149.30 100% 0.00 0% 80.50 ### 15,149.30 100% 0.00 0.00 0%
01.11.11.02 PASAMANO DE FoGo 2" SEGUN MODELO
01.11.11.02.01 PASAMANO DE FoGo 2" SEGUN MODELO m 69.42 58.83 4,083.98 69.42 4,083.98 100% 0.00 0% 69.42 ### 4,083.98 100% 0.00 0.00 0%
01.11.12 CERRAJERIA
01.11.12.01 BISAGRAS
01.11.12.01.01 BISAGRA CAPUCHINA DE 4" X4" und 27 19.69 531.63 27.00 531.63 100% 0.00 0% 27.00 ### 531.63 100% 0.00 0.00 0%
01.11.12.02 CERRADURAS
01.11.12.02.01 CERRADURA PARA PUERTA PRINCIPAL PESADA pza 6 105.06 630.36 6.00 630.36 100% 0.00 0% 6.00 ### 630.36 100% 0.00 0.00 0%
01.11.12.02.02 MANIJA DE BRONCE PARA PUERTAS und 6 57.53 345.18 6.00 345.18 100% 0.00 0% 6.00 ### 345.18 100% 0.00 0.00 0%
01.11.13 PINTURA
01.11.13.01 PINTURA AL LATEX EN CIELO RASO m2 463.01 14.34 6,639.56 463.01 6,639.56 100% 0.00 0% 463.01 ### 6,639.56 100% 0.00 0.00 0%
01.11.13.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 608.28 12.41 7,548.75 304.14 3,774.37 50% 304.14 3,774.38 50% 608.28 ### 7,548.75 100% 0.00 0.00 0%
01.11.13.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 587.56 14.34 8,425.61 587.56 8,425.61 100% 0.00 0% 587.56 ### 8,425.61 100% 0.00 0.00 0%
01.11.13.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 292.02 14.34 4,187.57 292.02 4,187.57 100% 0.00 0% 292.02 ### 4,187.57 100% 0.00 0.00 0%
01.11.13.05 PINTURA EN ZOCALOS m 130.4 9.31 1,214.02 0.00 0.00 0% 130.40 1,214.02 100% 130.40 ### 1,214.02 100% 0.00 0.00 0%
01.11.14 APARATOS SANITARIOS Y ACCESORIOS
01.11.14.01 LAVADERO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 3,572.01 3,572.01 1.00 3,572.01 100% 0.00 0% 1.00 ### 3,572.01 100% 0.00 0.00 0%
01.11.14.02 BANCA DE CONCRETO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 2,324.46 2,324.46 1.00 2,324.46 100% 0.00 0% 1.00 ### 2,324.46 100% 0.00 0.00 0%
01.11.15 INSTALACIONES SANITARIAS
01.11.15.01 SALIDA DE PVC SAL PARA DESAGUE DE 2" pto 1 67.73 67.73 1.00 67.73 100% 0.00 0% 1.00 ### 67.73 100% 0.00 0.00 0%
01.11.15.02 SUMIDEROS DE BRONCE 4" pza 1 102.56 102.56 1.00 102.56 100% 0.00 0% 1.00 ### 102.56 100% 0.00 0.00 0%
01.11.15.03 CAJA DE REGISTRO 12" X 24" pza 1 224.99 224.99 1.00 224.99 100% 0.00 0% 1.00 ### 224.99 100% 0.00 0.00 0%
01.11.15.04 TUBERIA PVC SAL Ø 2" m 15 10.58 158.70 15.00 158.70 100% 0.00 0% 15.00 ### 158.70 100% 0.00 0.00 0%
01.11.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.11.16.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2". pto 1 57.79 57.79 1.00 57.79 100% 0.00 0% 1.00 ### 57.79 100% 0.00 0.00 0%
01.11.16.02 TUBERIA PVC - SAP DE 1/2" m 15 9.81 147.15 15.00 147.15 100% 0.00 0% 15.00 ### 147.15 100% 0.00 0.00 0%
01.11.16.03 VALVULA COMPUERTA DE BRONCE 1/2" pza 1 115.64 115.64 1.00 115.64 100% 0.00 0% 1.00 ### 115.64 100% 0.00 0.00 0%
01.11.16.04 CAJA PARA MEDIDOR 12"X12" pza 1 198.46 198.46 1.00 198.46 100% 0.00 0% 1.00 ### 198.46 100% 0.00 0.00 0%
01.11.16.05 ACCESORIOS PVC GLB 1 33.53 33.53 1.00 33.53 100% 0.00 0% 1.00 ### 33.53 100% 0.00 0.00 0%
01.11.17 SISTEMA DE BAJADA PLUVIAL
01.11.17.01 BAJANTES DE PVC-SAP 4" pto 4 280.32 1,121.28 4.00 1,121.28 100% 0.00 0% 4.00 ### 1,121.28 100% 0.00 0.00 0%
01.11.18 VIDRIOS, CRISTALES Y SIMILARES
01.11.18.01 VIDRIOS DOBLES NACIONALES m2 80.55 194.93 15,701.61 80.55 15,701.61 100% 0.00 0% 80.55 ### 15,701.61 100% 0.00 0.00 0%
01.11.19 INSTALACIONES ELECTRICAS
01.11.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.11.19.01.01 CENTROS DE LUZ EN TECHOS pto 38 140.21 5,327.98 38.00 5,327.98 100% 0.00 0% 38.00 ### 5,327.98 100% 0.00 0.00 0%
01.11.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 36 140.38 5,053.68 36.00 5,053.68 100% 0.00 0% 36.00 ### 5,053.68 100% 0.00 0.00 0%
01.11.19.02 TABLEROS Y CUCHILLAS
01.11.19.02.01 TABLEROS DE DISTRIBUCION CAJA METALICA TD-1 und 1 343.18 343.18 1.00 343.18 100% 0.00 0% 1.00 ### 343.18 100% 0.00 0.00 0%
01.11.19.02.02 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 1.00 2,007.28 100% 0.00 0% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.11.19.03 ARTEFACTOS DE ILUMINACION
01.11.19.03.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2x36/840 AHP-A und 26 69.18 1,798.68 26.00 1,798.68 100% 0.00 0% 26.00 ### 1,798.68 100% 0.00 0.00 0%
01.11.19.03.02 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 12 99.17 1,190.04 12.00 1,190.04 100% 0.00 0% 12.00 ### 1,190.04 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.01 TRABAJOS PRELIMINARES
01.12.01.01 LIMPIEZA DE TERRENO
01.12.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 94.16 1.88 177.02 94.16 177.02 100% 0.00 0% 94.16 ### 177.02 100% 0.00 0.00 0%
01.12.01.02 TRAZO, NIVELES Y REPLANTEO
01.12.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 94.16 10.08 949.13 94.16 949.13 100% 0.00 0% 94.16 ### 949.13 100% 0.00 0.00 0%
01.12.02 MOVIMIENTO DE TIERRAS
01.12.02.01 NIVELACION
01.12.02.01.01 NIVELACION DE TERRENO m2 94.16 4.31 405.83 94.16 405.83 100% 0.00 0% 94.16 ### 405.83 100% 0.00 0.00 0%
01.12.02.02 EXCAVACIONES
01.12.02.02.01 EXCAVACION MANUAL DE ZANJAS Y ZAPATAS m3 34.47 42.46 1,463.60 34.47 1,463.60 100% 0.00 0% 34.47 ### 1,463.60 100% 0.00 0.00 0%
01.12.02.03 RELLENOS
01.12.02.03.01 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 4.7 67.32 316.40 4.70 316.40 100% 0.00 0% 4.70 ### 316.40 100% 0.00 0.00 0%
01.12.02.03.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 0.6 109.80 65.88 0.60 65.88 100% 0.00 0% 0.60 ### 65.88 100% 0.00 0.00 0%
01.12.02.04 ELIMINACION DE MATERIAL EXEDENTE
01.12.02.04.01 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 28.54 17.69 504.87 28.54 504.87 100% 0.00 0% 28.54 ### 504.87 100% 0.00 0.00 0%
01.12.02.04.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 28.54 8.47 241.73 28.54 241.73 100% 0.00 0% 28.54 ### 241.73 100% 0.00 0.00 0%
01.12.02.05 REFINE Y NIVELACION
01.12.02.05.01 REFINE Y NIVELACION EN TERRENO m2 94.16 6.74 634.64 94.16 634.64 100% 0.00 0% 94.16 ### 634.64 100% 0.00 0.00 0%
01.12.02.05.02 AFIRMADO DE 4" CON MAT. DE PRESTAMO m2 94.16 13.44 1,265.51 94.16 1,265.51 100% 0.00 0% 94.16 ### 1,265.51 100% 0.00 0.00 0%
01.12.03 OBRAS DE CONCRETO SIMPLE
01.12.03.01 CIMIENTO CORRIDO
01.12.03.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 7.5 193.75 1,453.13 7.50 1,453.13 100% 0.00 0% 7.50 ### 1,453.13 100% 0.00 0.00 0%
01.12.03.02 SOLADO
01.12.03.02.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 7.78 36.45 283.58 7.78 283.58 100% 0.00 0% 7.78 ### 283.58 100% 0.00 0.00 0%
01.12.03.03 SOBRECIMIENTOS CORRIDOS
01.12.03.03.01 SOBRECIMIENTO CORRIDO C-H 1:8 + 25% P.M. m3 6.75 279.29 1,885.21 6.75 1,885.21 100% 0.00 0% 6.75 ### 1,885.21 100% 0.00 0.00 0%
01.12.03.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS HASTA 0.60 M m2 25.68 57.69 1,481.48 25.68 1,481.48 100% 0.00 0% 25.68 ### 1,481.48 100% 0.00 0.00 0%
01.12.03.04 FALSO PISO
01.12.03.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 47.88 29.42 1,408.63 47.88 1,408.63 100% 0.00 0% 47.88 ### 1,408.63 100% 0.00 0.00 0%
01.12.04 OBRAS DE CONCRETO ARMADO
01.12.04.01 ZAPATAS
01.12.04.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 6.48 398.47 2,582.09 6.48 2,582.09 100% 0.00 0% 6.48 ### 2,582.09 100% 0.00 0.00 0%
01.12.04.01.02 ACERO DE REFUERZO FY=4200 KG/CM2 ZAPATAS. kg 194.18 5.19 1,007.79 194.18 1,007.79 100% 0.00 0% 194.18 ### 1,007.79 100% 0.00 0.00 0%
01.12.04.02 VIGAS DE CIMENTACION
01.12.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 3.46 398.47 1,378.71 3.46 1,378.71 100% 0.00 0% 3.46 ### 1,378.71 100% 0.00 0.00 0%
01.12.04.02.02 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION m2 28.48 70.68 2,012.97 28.48 2,012.97 100% 0.00 0% 28.48 ### 2,012.97 100% 0.00 0.00 0%
01.12.04.02.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGA DE CIMENTACION. kg 272.08 5.19 1,412.10 272.08 1,412.10 100% 0.00 0% 272.08 ### 1,412.10 100% 0.00 0.00 0%
01.12.04.03 COLUMNAS
01.12.04.03.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.57 498.90 1,781.07 3.57 1,781.07 100% 0.00 0% 3.57 ### 1,781.07 100% 0.00 0.00 0%
01.12.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 42.18 77.61 3,273.59 42.18 3,273.59 100% 0.00 0% 42.18 ### 3,273.59 100% 0.00 0.00 0%
01.12.04.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 420.25 5.19 2,181.10 420.25 2,181.10 100% 0.00 0% 420.25 ### 2,181.10 100% 0.00 0.00 0%
01.12.04.04 VIGAS
01.12.04.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 4.87 415.22 2,022.12 4.87 2,022.12 100% 0.00 0% 4.87 ### 2,022.12 100% 0.00 0.00 0%
01.12.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 34.11 77.61 2,647.28 34.11 2,647.28 100% 0.00 0% 34.11 ### 2,647.28 100% 0.00 0.00 0%
01.12.04.04.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 448.24 5.19 2,326.37 448.24 2,326.37 100% 0.00 0% 448.24 ### 2,326.37 100% 0.00 0.00 0%
01.12.04.05 LOSAS ALIGERADAS
01.12.04.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. m3 7.5 404.08 3,030.60 7.50 3,030.60 100% 0.00 0% 7.50 ### 3,030.60 100% 0.00 0.00 0%
01.12.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 22.34 93.30 2,084.32 22.34 2,084.32 100% 0.00 0% 22.34 ### 2,084.32 100% 0.00 0.00 0%
01.12.04.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS ALIGERADAS. kg 363.83 5.19 1,888.28 363.83 1,888.28 100% 0.00 0% 363.83 ### 1,888.28 100% 0.00 0.00 0%
01.12.04.05.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 843.55 4.81 4,057.48 843.55 4,057.48 100% 0.00 0% 843.55 ### 4,057.48 100% 0.00 0.00 0%
01.12.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.12.05.01 MURO DE LADRILLO KK SOGA
01.12.05.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 100.24 63.52 6,367.24 100.24 6,367.24 100% 0.00 0% 100.24 ### 6,367.24 100% 0.00 0.00 0%
01.12.06 REVOQUES, ENLUCIDOS Y MLDURAS
01.12.06.01 TARRAJEO EN GENERAL
01.12.06.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 208.08 25.87 5,383.03 208.08 5,383.03 100% 0.00 0% 208.08 ### 5,383.03 100% 0.00 0.00 0%
01.12.06.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 19.89 32.01 636.68 19.89 636.68 100% 0.00 0% 19.89 ### 636.68 100% 0.00 0.00 0%
01.12.06.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 53.58 34.26 1,835.65 53.58 1,835.65 100% 0.00 0% 53.58 ### 1,835.65 100% 0.00 0.00 0%
01.12.06.01.04 TARRAJEO PRIMARIO RAYADO m2 58.28 43.98 2,563.15 58.28 2,563.15 100% 0.00 0% 58.28 ### 2,563.15 100% 0.00 0.00 0%
01.12.06.01.05 EJECUCION DE BRUÑAS m 216 8.22 1,775.52 216.00 1,775.52 100% 0.00 0% 216.00 ### 1,775.52 100% 0.00 0.00 0%
01.12.06.01.06 VESTIDURA DE DERRAMES m 47.96 22.02 1,056.08 47.96 1,056.08 100% 0.00 0% 47.96 ### 1,056.08 100% 0.00 0.00 0%
01.12.06.01.07 TARRAJEO CON IMPERMEABILIZANTES m2 12.32 31.17 384.01 12.32 384.01 100% 0.00 0% 12.32 ### 384.01 100% 0.00 0.00 0%
01.12.06.02 CIELO RASOS
01.12.06.02.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 76.67 44.01 3,374.25 76.67 3,374.25 100% 0.00 0% 76.67 ### 3,374.25 100% 0.00 0.00 0%
01.12.07 PISOS Y PAVIMENTOS
01.12.07.01 CONTRAPISOS
01.12.07.01.01 CONTRAPISO DE 48 MM. m2 47 35.84 1,684.48 47.00 1,684.48 100% 0.00 0% 47.00 ### 1,684.48 100% 0.00 0.00 0%
01.12.07.02 PISOS
01.12.07.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 49.35 63.25 3,121.39 0.00 0.00 0% 49.35 3,121.39 100% 49.35 ### 3,121.39 100% 0.00 0.00 0%
01.12.07.03 VEREDAS Y RAMPAS
01.12.07.03.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 40.76 59.66 2,431.74 40.76 2,431.74 100% 0.00 0% 40.76 ### 2,431.74 100% 0.00 0.00 0%
01.12.07.03.02 JUNTAS DE DILATACION EN E=1" m 70 31.99 2,239.30 36.70 1,173.92 52% 33.30 1,065.38 48% 70.00 ### 2,239.30 100% 0.00 0.00 0%
01.12.08 CONTRAZOCALOS
01.12.08.01 CONTRAZOCALOS DE CEMENTO
01.12.08.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 28.9 15.69 453.44 28.90 453.44 100% 0.00 0% 28.90 ### 453.44 100% 0.00 0.00 0%
01.12.08.02 ZOCALOS
01.12.08.02.01 ZOCALOS DE MAYOLICA
01.12.08.02.01.01 ZOCALO DE MAYOLICA DE COLOR 20X30 1RA m2 141.06 96.43 13,602.42 141.06 13,602.42 100% 0.00 0% 141.06 ### 13,602.42 100% 0.00 0.00 0%
01.12.09 CUBIERTAS
01.12.09.01 COBERTURA CON TEJA
01.12.09.01.01 COBERTURA CON PLANCHA DE TEJA ANDINA m2 78.38 55.65 4,361.85 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 78.38 4,361.85 100%
01.12.09.01.02 CUMBRERA CON TEJA ANDINA DECORATIVA m 10.1 74.96 757.10 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 10.10 757.10 100%
01.12.10 CARPINTERIA DE MADERA
01.12.10.01 PUERTAS
01.12.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 5.58 565.23 3,153.98 5.58 3,153.98 100% 0.00 0% 5.58 ### 3,153.98 100% 0.00 0.00 0%
01.12.11 CARPINTERIA METALICA Y ALUMINIO
01.12.11.01 VENTANAS METALICAS
01.12.11.01.01 VENTANA DE ALUMINIO m2 6.32 188.19 1,189.36 6.32 1,189.36 100% 0.00 0% 6.32 ### 1,189.36 100% 0.00 0.00 0%
01.12.11.02 PUERTAS METALICAS Y OTRAS
01.12.11.02.01 PUERTA METALICA m2 13.68 548.11 7,498.14 13.68 7,498.14 100% 0.00 0% 13.68 ### 7,498.14 100% 0.00 0.00 0%
01.12.12 CERRAJERIA
01.12.12.01 BISAGRAS
01.12.12.01.01 BISAGRA CAPUCHINA DE 4" X4" und 24 19.69 472.56 24.00 472.56 100% 0.00 0% 24.00 ### 472.56 100% 0.00 0.00 0%
01.12.12.02 CERRADURAS
01.12.12.02.01 CERRADURA PARA PUERTA PRINCIPAL PESADA pza 2 105.06 210.12 2.00 210.12 100% 0.00 0% 2.00 ### 210.12 100% 0.00 0.00 0%
01.12.12.02.02 MANIJA DE BRONCE PARA PUERTAS und 2 57.53 115.06 2.00 115.06 100% 0.00 0% 2.00 ### 115.06 100% 0.00 0.00 0%
01.12.13 PINTURA
01.12.13.01 PINTURA EN GENERAL
01.12.13.01.01 PINTURA AL LATEX EN CIELO RASO m2 76.67 14.34 1,099.45 38.34 549.72 50% 38.34 549.72 50% 76.67 ### 1,099.45 100% 0.00 0.00 0%
01.12.13.01.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 131.6 12.41 1,633.16 65.70 815.34 50% 65.90 817.82 50% 131.60 ### 1,633.16 100% 0.00 0.00 0%
01.12.13.01.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 19.89 14.34 285.22 9.50 136.23 48% 10.39 148.99 52% 19.89 ### 285.22 100% 0.00 0.00 0%
01.12.13.01.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 53.58 14.34 768.34 27.80 398.65 52% 25.78 369.69 48% 53.58 ### 768.34 100% 0.00 0.00 0%
01.12.13.01.05 PINTURA EN ZOCALOS m 8.88 9.31 82.67 0.00 0.00 0% 8.88 82.67 100% 8.88 ### 82.67 100% 0.00 0.00 0%
01.12.14 APARATOS SANITARIOS Y ACCESORIOS
01.12.14.01 INODORO TANQUE BAJO COLOR pza 10 200.00 2,000.00 0.00 0.00 0% 10.00 2,000.00 100% 10.00 ### 2,000.00 100% 0.00 0.00 0%
01.12.14.02 COLOCACION DE APARATOS SANITARIO pza 10 48.33 483.30 10.00 483.30 100% 0.00 0% 10.00 ### 483.30 100% 0.00 0.00 0%
01.12.14.03 URINARIO CONSTRUIDO EN OBRA und 1 1,761.77 1,761.77 1.00 1,761.77 100% 0.00 0% 1.00 ### 1,761.77 100% 0.00 0.00 0%
01.12.14.04 LAVADERO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 3,572.01 3,572.01 1.00 3,572.01 100% 0.00 0% 1.00 ### 3,572.01 100% 0.00 0.00 0%
01.12.14.05 BANCA DE CONCRETO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 2,324.46 2,324.46 1.00 2,324.46 100% 0.00 0% 1.00 ### 2,324.46 100% 0.00 0.00 0%
01.12.14.06 BARANDA DE TUBO F. G. PASAMANO PARA DISCAPACITADOS pza 4 249.99 999.96 4.00 999.96 100% 0.00 0% 4.00 ### 999.96 100% 0.00 0.00 0%
01.12.15 INSTALACIONES SANITARIAS
01.12.15.01 SALIDA DE PVC SAL PARA DESAGUE DE 4" pto 10 87.28 872.80 10.00 872.80 100% 0.00 0% 10.00 ### 872.80 100% 0.00 0.00 0%
01.12.15.02 SALIDA DE PVC SAL PARA DESAGUE DE 2" pto 7 76.53 535.71 7.00 535.71 100% 0.00 0% 7.00 ### 535.71 100% 0.00 0.00 0%
01.12.15.03 SUMIDEROS DE BRONCE 4" pza 5 102.56 512.80 0.00 0.00 0% 5.00 512.80 100% 5.00 ### 512.80 100% 0.00 0.00 0%
01.12.15.04 REGISTROS DE BRONCE DE 4" pza 8 73.32 586.56 0.00 0.00 0% 8.00 586.56 100% 8.00 ### 586.56 100% 0.00 0.00 0%
01.12.15.05 CAJA DE REGISTRO 12" X 24" pza 1 223.57 223.57 1.00 223.57 100% 0.00 0% 1.00 ### 223.57 100% 0.00 0.00 0%
01.12.15.06 TUBERIA PVC SAL Ø 4" m 26.8 30.00 804.00 26.80 804.00 100% 0.00 0% 26.80 ### 804.00 100% 0.00 0.00 0%
01.12.15.07 TUBERIA PVC SAL Ø 2" m 12.85 15.29 196.48 12.85 196.48 100% 0.00 0% 12.85 ### 196.48 100% 0.00 0.00 0%
01.12.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.12.16.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2". pto 26 57.79 1,502.54 26.00 1,502.54 100% 0.00 0% 26.00 ### 1,502.54 100% 0.00 0.00 0%
01.12.16.02 TUBERIA PVC - SAP DE 1/2" m 35.53 19.48 692.12 35.53 692.12 100% 0.00 0% 35.53 ### 692.12 100% 0.00 0.00 0%
01.12.16.03 VALVULA COMPUERTA DE BRONCE 1/2" pza 4 115.64 462.56 4.00 462.56 100% 0.00 0% 4.00 ### 462.56 100% 0.00 0.00 0%
01.12.16.04 CAJA PARA MEDIDOR 12"X12" pza 1 188.20 188.20 1.00 188.20 100% 0.00 0% 1.00 ### 188.20 100% 0.00 0.00 0%
01.12.16.05 TUBERIA PVC - SAP DE 3/4" m 5.6 22.62 126.67 5.60 126.67 100% 0.00 0% 5.60 ### 126.67 100% 0.00 0.00 0%
01.12.16.06 VALVULA COMPUERTA DE BRONCE 3/4". pza 1 62.66 62.66 1.00 62.66 100% 0.00 0% 1.00 ### 62.66 100% 0.00 0.00 0%
01.12.16.07 ACCESORIOS PVC GLB 1 30.03 30.03 1.00 30.03 100% 0.00 0% 1.00 ### 30.03 100% 0.00 0.00 0%
01.12.17 SISTEMA DE BAJADA PLUVIAL
01.12.17.01 BAJANTES DE PVC-SAP 4" pto 4 280.32 1,121.28 4.00 1,121.28 100% 0.00 0% 4.00 ### 1,121.28 100% 0.00 0.00 0%
01.12.18 VIDRIOS, CRISTALES Y SIMILARES
01.12.18.01 VIDRIOS DOBLES NACIONALES m2 9.92 1,845.63 18,308.65 9.92 18,308.65 100% 0.00 0% 9.92 ### 18,308.65 100% 0.00 0.00 0%
01.12.19 INSTALACIONES ELECTRICAS
01.12.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.12.19.01.01 CENTROS DE LUZ EN TECHOS pto 4 140.21 560.84 4.00 560.84 100% 0.00 0% 4.00 ### 560.84 100% 0.00 0.00 0%
01.12.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 2 140.38 280.76 2.00 280.76 100% 0.00 0% 2.00 ### 280.76 100% 0.00 0.00 0%
01.12.19.02 TABLEROS Y CUCHILLAS
01.12.19.02.01 TABLEROS DE DISTRIBUCION CAJA METALICA TD-3 und 1 343.18 343.18 1.00 343.18 100% 0.00 0% 1.00 ### 343.18 100% 0.00 0.00 0%
01.12.19.02.02 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 1.00 2,007.28 100% 0.00 0% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.12.19.03 ARTEFACTOS DE ILUMINACION
01.12.19.03.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 4 99.17 396.68 4.00 396.68 100% 0.00 0% 4.00 ### 396.68 100% 0.00 0.00 0%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.01 TRABAJOS PRELIMINARES
01.13.01.01 LIMPIEZA DE TERRENO
01.13.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 16 3.22 51.52 16.00 51.52 100% 0.00 0% 16.00 ### 51.52 100% 0.00 0.00 0%
01.13.01.02 TRAZO, NIVELES Y REPLANTEO
01.13.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 16 10.08 161.28 16.00 161.28 100% 0.00 0% 16.00 ### 161.28 100% 0.00 0.00 0%
01.13.02 MOVIMIENTO DE TIERRAS
01.13.02.01 EXCAVACIONES
01.13.02.01.01 EXCAVACION PARA ESTRUCTURA m3 11.43 42.46 485.32 11.43 485.32 100% 0.00 0% 11.43 ### 485.32 100% 0.00 0.00 0%
01.13.02.02 RELLENOS
01.13.02.02.01 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO m3 2.9 67.32 195.23 2.90 195.23 100% 0.00 0% 2.90 ### 195.23 100% 0.00 0.00 0%
01.13.02.03 ELIMINACION DE MATERIAL EXEDENTE
01.13.02.03.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 10.24 8.47 86.73 10.24 86.73 100% 0.00 0% 10.24 ### 86.73 100% 0.00 0.00 0%
01.13.03 OBRAS DE CONCRETO SIMPLE
01.13.03.01 SOLADO
01.13.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 1.4 36.45 51.03 1.40 51.03 100% 0.00 0% 1.40 ### 51.03 100% 0.00 0.00 0%
01.13.04 OBRAS DE CONCRETO ARMADO
01.13.04.01 CONCRETO EN CISTERNA
01.13.04.01.01 CONCRETO F´C=210KG/CM2 EN CISTERNA m3 7.84 501.55 3,932.15 7.84 3,932.15 100% 0.00 0% 7.84 ### 3,932.15 100% 0.00 0.00 0%
01.13.04.01.02 ENCOFRADO Y DESENCOFRADO PARA CISTERNA m2 50.65 103.27 5,230.63 50.65 5,230.63 100% 0.00 0% 50.65 ### 5,230.63 100% 0.00 0.00 0%
01.13.04.01.03 ACERO DE REFUERZO FY=4200 KG/CM2 . kg 437.57 5.19 2,270.99 437.57 2,270.99 100% 0.00 0% 437.57 ### 2,270.99 100% 0.00 0.00 0%
01.13.04.02 COLUMNAS
01.13.04.02.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.05 498.90 1,521.65 3.05 1,521.65 100% 0.00 0% 3.05 ### 1,521.65 100% 0.00 0.00 0%
01.13.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 6.28 77.61 487.39 6.28 487.39 100% 0.00 0% 6.28 ### 487.39 100% 0.00 0.00 0%
01.13.04.02.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 765.68 5.19 3,973.88 765.68 3,973.88 100% 0.00 0% 765.68 ### 3,973.88 100% 0.00 0.00 0%
01.13.04.03 VIGAS
01.13.04.03.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 1.03 415.22 427.68 1.03 427.68 100% 0.00 0% 1.03 ### 427.68 100% 0.00 0.00 0%
01.13.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 2.79 77.61 216.53 2.79 216.53 100% 0.00 0% 2.79 ### 216.53 100% 0.00 0.00 0%
01.13.04.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 325.22 5.19 1,687.89 325.22 1,687.89 100% 0.00 0% 325.22 ### 1,687.89 100% 0.00 0.00 0%
01.13.04.04 LOZA MASCIZA
01.13.04.04.01 CONCRETO EN LOSAS MACIZAS ESCALERA F'C=210 KG/CM2 m3 0.87 414.23 360.38 0.87 360.38 100% 0.00 0% 0.87 ### 360.38 100% 0.00 0.00 0%
01.13.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 5.5 93.30 513.15 5.50 513.15 100% 0.00 0% 5.50 ### 513.15 100% 0.00 0.00 0%
01.13.04.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS MACIZAS. kg 19.89 5.19 103.23 19.89 103.23 100% 0.00 0% 19.89 ### 103.23 100% 0.00 0.00 0%
01.13.04.05 TANQUE ELEVADO
01.13.04.05.01 CONCRETO EN TANQUE ELEVADO F'C=210 KG/CM2 m3 8.34 515.70 4,300.94 8.34 4,300.94 100% 0.00 0% 8.34 ### 4,300.94 100% 0.00 0.00 0%
01.13.04.05.02 ENCOFRADO Y DESENCOFRADO EN MUROS Y PLACAS m2 67.89 118.28 8,030.03 67.89 8,030.03 100% 0.00 0% 67.89 ### 8,030.03 100% 0.00 0.00 0%
01.13.04.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN EN MUROS REFORZADOS Y/O PLA kg 206.71 5.19 1,072.82 206.71 1,072.82 100% 0.00 0% 206.71 ### 1,072.82 100% 0.00 0.00 0%
01.13.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.13.05.01 MURO DE LADRILLO KK SOGA
01.13.05.01.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 E=1.5 CM m2 0.62 108.41 67.21 0.62 67.21 100% 0.00 0% 0.62 ### 67.21 100% 0.00 0.00 0%
01.13.05.01.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 6.13 63.52 389.38 6.13 389.38 100% 0.00 0% 6.13 ### 389.38 100% 0.00 0.00 0%
01.13.06 REVOQUES, ENLUCIDOS Y MLDURAS
01.13.06.01 TARRAJEO EN GENERAL
01.13.06.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 20.52 25.87 530.85 20.52 530.85 100% 0.00 0% 20.52 ### 530.85 100% 0.00 0.00 0%
01.13.06.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 21.33 32.01 682.77 21.33 682.77 100% 0.00 0% 21.33 ### 682.77 100% 0.00 0.00 0%
01.13.06.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 6.14 34.26 210.36 6.14 210.36 100% 0.00 0% 6.14 ### 210.36 100% 0.00 0.00 0%
01.13.06.01.04 TARRAJEO CON IMPERMEABILIZANTES m2 74.29 31.17 2,315.62 74.29 2,315.62 100% 0.00 0% 74.29 ### 2,315.62 100% 0.00 0.00 0%
01.13.07 CIELO RASOS
01.13.07.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 2.56 44.01 112.67 2.56 112.67 100% 0.00 0% 2.56 ### 112.67 100% 0.00 0.00 0%
01.13.08 PISOS Y PAVIMENTOS
01.13.08.01 PISOS
01.13.08.01.01 PISO DE CEMENTO PULIDO CON OCRE ROJO, E=2" S/COLOREAR m2 3 27.71 83.13 3.00 83.13 100% 0.00 0% 3.00 ### 83.13 100% 0.00 0.00 0%
01.13.08.01.02 PISO LADRILLO PASTELERO m2 8.94 22.05 197.13 8.94 197.13 100% 0.00 0% 8.94 ### 197.13 100% 0.00 0.00 0%
01.13.08.02 VEREDAS Y RAMPAS
01.13.08.02.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 5.81 59.66 346.62 5.81 346.62 100% 0.00 0% 5.81 ### 346.62 100% 0.00 0.00 0%
01.13.08.02.02 JUNTAS DE DILATACION EN E=1" m 10.78 31.99 344.85 10.78 344.85 100% 0.00 0% 10.78 ### 344.85 100% 0.00 0.00 0%
01.13.09 CONTRAZOCALOS
01.13.09.01 CONTRAZOCALOS DE CEMENTO
01.13.09.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 16.7 15.69 262.02 16.70 262.02 100% 0.00 0% 16.70 ### 262.02 100% 0.00 0.00 0%
01.13.10 CARPINTERIA METALICA Y ALUMINIO
01.13.10.01 PUERTAS METALICAS Y OTRAS
01.13.10.01.01 PUERTA METALICA 0.70X1.65 m2 1.16 548.11 635.81 1.16 635.81 100% 0.00 0% 1.16 ### 635.81 100% 0.00 0.00 0%
01.13.10.01.02 ESCALERA DE GATO DE TUBO F°G° DE 1 1/2" Y 1" m 8.68 173.79 1,508.50 8.68 1,508.50 100% 0.00 0% 8.68 ### 1,508.50 100% 0.00 0.00 0%
01.13.11 CERRAJERIA
01.13.11.01 BISAGRAS
01.13.11.01.01 BISAGRA CAPUCHINA DE 4" X4" und 4 19.69 78.76 4.00 78.76 100% 0.00 0% 4.00 ### 78.76 100% 0.00 0.00 0%
01.13.11.02 CERRADURAS
01.13.11.02.01 CERRADURA DE 3 GOLPES PARA PUERTA und 1 102.55 102.55 1.00 102.55 100% 0.00 0% 1.00 ### 102.55 100% 0.00 0.00 0%
01.13.12 PINTURA
01.13.12.01 PINTURA EN GENERAL
01.13.12.01.01 PINTURA AL LATEX 2 MANOS EN CIELO RASO m2 2.66 14.34 38.14 2.66 38.14 100% 0.00 0% 2.66 ### 38.14 100% 0.00 0.00 0%
01.13.12.01.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 44.92 12.41 557.46 44.92 557.46 100% 0.00 0% 44.92 ### 557.46 100% 0.00 0.00 0%
01.13.12.01.03 PINTURA ESMALTE SINTETICO 2 MANOS EN ZOCALO Y CONTRAZOCALO m 15.99 9.31 148.87 0.00 0.00 0% 15.99 148.87 100% 15.99 ### 148.87 100% 0.00 0.00 0%
01.13.13 INSTALACIONES SANITARIAS
01.13.13.01 LINEA DE SUCCION E IMPULSION GLB 1 1,703.82 1,703.82 1.00 1,703.82 100% 0.00 0% 1.00 ### 1,703.82 100% 0.00 0.00 0%
01.13.13.02 LINEA DEL ALIMENTADOR GLB 1 1,584.86 1,584.86 1.00 1,584.86 100% 0.00 0% 1.00 ### 1,584.86 100% 0.00 0.00 0%
01.13.13.03 LINEA DE REBOSE Y LIMPIEZA GLB 1 1,458.26 1,458.26 1.00 1,458.26 100% 0.00 0% 1.00 ### 1,458.26 100% 0.00 0.00 0%
01.13.14 INSTALACIONES ELECTRICAS
01.13.14.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.13.14.01.01 CENTROS DE LUZ EN TECHOS pto 2 140.21 280.42 2.00 280.42 100% 0.00 0% 2.00 ### 280.42 100% 0.00 0.00 0%
01.13.14.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 1 140.38 140.38 1.00 140.38 100% 0.00 0% 1.00 ### 140.38 100% 0.00 0.00 0%
01.13.15 TABLEROS Y CUCHILLAS
01.13.15.01 TABLEROS DE DISTRIBUCION GENERAL und 1 414.42 414.42 1.00 414.42 100% 0.00 0% 1.00 ### 414.42 100% 0.00 0.00 0%
01.13.15.02 TABLERO DE MANDO ELECTROBOMBA und 1 907.46 907.46 1.00 907.46 100% 0.00 0% 1.00 ### 907.46 100% 0.00 0.00 0%
01.13.15.03 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 1.00 2,007.28 100% 0.00 0% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.13.16 EQUIPOS ELECTRICOS
01.13.16.01 EQUIPOS ELECTRICOS GLB 1 1,700.24 1,700.24 1.00 1,700.24 100% 0.00 0% 1.00 ### 1,700.24 100% 0.00 0.00 0%
01.13.17 ARTEFACTOS DE ILUMINACION
01.13.17.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 1 99.17 99.17 1.00 99.17 100% 0.00 0% 1.00 ### 99.17 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.01 TRABAJOS PRELIMINARES
01.14.01.01.01 LIMPIEZA DE TERRENO
01.14.01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 145.56 3.22 468.70 54.56 175.69 37% 0.00 0% 54.56 ### 175.69 37% 91.00 293.01 63%
01.14.01.01.02 TRAZO, NIVELES Y REPLANTEO
01.14.01.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 145.56 10.08 1,467.24 54.56 550.00 37% 0.00 0% 54.56 ### 550.00 37% 91.00 917.24 63%
01.14.01.02 MOVIMIENTO DE TIERRAS
01.14.01.02.01 EXCAVACIONES
01.14.01.02.01.01 EXCAVACION MANUAL P LOSA, TRIBUNA, /UÑA Y CUNETA m3 51.65 42.46 2,193.06 21.83 926.71 42% 0.00 0% 21.83 ### 926.71 42% 29.82 1,266.35 58%
01.14.01.02.01.02 REFINE Y NIVELACION EN TERRENO m2 119.4 6.74 804.76 54.56 367.76 46% 0.00 0% 54.56 ### 367.76 46% 64.84 437.00 54%
01.14.01.02.01.03 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 54.56 22.56 1,230.87 54.56 1,230.87 100% 0.00 0% 54.56 ### 1,230.87 100% 0.00 0.00 0%
01.14.01.02.01.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 64.56 17.69 1,142.07 27.28 482.62 42% 0.00 0% 27.28 ### 482.62 42% 37.28 659.45 58%
01.14.01.02.01.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 64.56 8.47 546.82 27.28 231.08 42% 0.00 0% 27.28 ### 231.08 42% 37.28 315.75 58%
01.14.01.03 OBRAS DE CONCRETO ARMADO
01.14.01.03.01 TRIBUNAS
01.14.01.03.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 16.86 192.96 3,253.31 16.86 3,253.31 100% 0.00 0% 16.86 ### 3,253.31 100% 0.00 0.00 0%
01.14.01.03.01.02 CONCRETO CICLOPEO FC=140KG/CM2 GRADAS m3 3.88 233.57 906.25 3.88 906.25 100% 0.00 0% 3.88 ### 906.25 100% 0.00 0.00 0%
01.14.01.03.01.03 CONCRETO EN TRIBUNAS F'C=175 KG/CM2 m3 22.33 413.40 9,231.22 22.33 9,231.22 100% 0.00 0% 22.33 ### 9,231.22 100% 0.00 0.00 0%
01.14.01.03.01.04 ENCOFRADO Y DESENCOFRADO EN TRIBUNA m2 221.56 62.00 13,736.72 221.56 13,736.72 100% 0.00 0% 221.56 ### 13,736.72 100% 0.00 0.00 0%
01.14.01.03.01.05 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS Y VIGAS kg 479.54 5.19 2,488.81 479.54 2,488.81 100% 0.00 0% 479.54 ### 2,488.81 100% 0.00 0.00 0%
01.14.01.03.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS m2 40.04 77.61 3,107.50 40.04 3,107.50 100% 0.00 0% 40.04 ### 3,107.50 100% 0.00 0.00 0%
01.14.01.03.01.07 CONCRETO PARA COLUMNAS Y VIGAS F'C=210 KG/CM2 m3 3.99 498.90 1,990.61 3.99 1,990.61 100% 0.00 0% 3.99 ### 1,990.61 100% 0.00 0.00 0%
01.14.01.03.01.08 TARRAJEO PULIDO EN SUPEERF. DE TRIBUNA m2 151.2 55.17 8,341.70 151.20 8,341.70 100% 0.00 0% 151.20 ### 8,341.70 100% 0.00 0.00 0%
01.14.01.03.01.09 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 27.42 67.32 1,845.91 27.42 1,845.67 100% 0.00 0% 27.42 ### 1,845.67 100% 0.00 0.24 0%
01.14.01.03.01.10 CURADO DE TRIBUNA CON AGUA m2 190.03 0.42 79.81 190.03 79.81 100% 0.00 0% 190.03 ### 79.81 100% 0.00 0.00 0%
01.14.01.03.01.11 JUNTAS DE DILATACION EN TRIBUNAS m 29.7 31.99 950.10 29.70 950.10 100% 0.00 0% 29.70 ### 950.10 100% 0.00 0.00 0%
01.14.01.04 CANALETA PLUVIAL DE LOSA DEPORTIVA
01.14.01.04.01 CONCRETO EN CANALETA F'C=175 KG/CM2 m3 14.1 413.40 5,828.94 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 14.10 5,828.94 100%
01.14.01.04.02 ENCOFRADO Y DESENCOFRADO EN CANALETA m2 146.86 62.00 9,105.32 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 146.86 9,105.32 100%
01.14.01.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN CANALETAS kg 206.19 5.19 1,070.13 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 206.19 1,070.13 100%
01.14.01.05 MEJORAMIENTO DE LOSA DEPORTIVA EXISTENTE
01.14.01.05.01 PICADO DE SUPERFICIE DE LOSA DEPORTIVA E=0.05 m m2 720 7.09 5,104.80 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 5,104.80 100%
01.14.01.05.02 CAPA DE CONCRETO E=0.05m ACABADO SEMIPULIDO EN LOSA m2 720 41.08 29,577.60 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 29,577.60 100%
01.14.01.05.03 PICADO LIMPIEZA Y REPOSICION DE JUNTAS DE DILATACION CON SELLO AS m 299.73 5.08 1,522.63 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.73 1,522.63 100%
01.14.01.05.04 CURADO DE LOSA DEPORTIVA CON AGUA m2 720 0.42 302.40 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 302.40 100%
01.14.01.05.05 REPOSICION DE ARCOS und 2 2,154.98 4,309.96 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2.00 4,309.96 100%
01.14.01.05.06 REPOSICION DE PARANTES DE VOLEY und 1 504.98 504.98 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 504.98 100%
01.14.01.05.07 PINTURA EN CAMPO DE JUEGO ML 550 8.26 4,543.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 550.00 4,543.00 100%
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.01 MOVIMIENTO DE TIERRAS
01.14.02.01.01 EXCAVACIONES
01.14.02.01.01.01 EXCAVACION MANUAL DE ZANJA P/CIMENTACION - ZAPATAS m3 63 39.80 2,507.40 63.00 2,507.40 100% 0.00 0% 63.00 ### 2,507.40 100% 0.00 0.00 0%
01.14.02.01.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 27 67.32 1,817.64 27.00 1,817.64 100% 0.00 0% 27.00 ### 1,817.64 100% 0.00 0.00 0%
01.14.02.01.01.03 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 45 13.27 597.15 45.00 597.15 100% 0.00 0% 45.00 ### 597.15 100% 0.00 0.00 0%
01.14.02.02 OBRAS DE CONCRETO SIMPLE
01.14.02.02.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 9 30.55 274.95 9.00 274.95 100% 0.00 0% 9.00 ### 274.95 100% 0.00 0.00 0%
01.14.02.03 OBRAS DE CONCRETO ARMADO
01.14.02.03.01 ZAPATAS
01.14.02.03.01.01 ACERO DE REFUERZO FY=4200 KG/CM2 ZAPATAS. kg 624.96 5.19 3,243.54 624.96 3,243.54 100% 0.00 0% 624.96 ### 3,243.54 100% 0.00 0.00 0%
01.14.02.03.01.02 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 21.6 403.61 8,717.98 21.60 8,717.98 100% 0.00 0% 21.60 ### 8,717.98 100% 0.00 0.00 0%
01.14.02.03.02 COLUMNAS
01.14.02.03.02.01 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS kg 386.94 5.19 2,008.22 386.94 2,008.22 100% 0.00 0% 386.94 ### 2,008.22 100% 0.00 0.00 0%
01.14.02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 28.8 82.27 2,369.38 28.80 2,369.38 100% 0.00 0% 28.80 ### 2,369.38 100% 0.00 0.00 0%
01.14.02.03.02.03 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.24 511.53 1,657.36 3.24 1,657.36 100% 0.00 0% 3.24 ### 1,657.36 100% 0.00 0.00 0%
01.14.02.03.03 TARRAJEO EN GENERAL
01.14.02.03.03.01 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 28.8 37.15 1,069.92 0.00 0.00 0% 28.80 1,069.92 100% 28.80 ### 1,069.92 100% 0.00 0.00 0%
01.14.02.04 ESTRUCTURA METALICA Y COBERTURA
01.14.02.04.01 COLUMNA METALICA
01.14.02.04.01.01 COLUMNAS METALICAS SCH-40 DE 8" e=8.2MM und 16 1,163.31 18,612.96 16.00 18,612.96 100% 0.00 0% 16.00 ### 18,612.96 100% 0.00 0.00 0%
01.14.02.04.02 VIGAS METALICA
01.14.02.04.02.01 CERCHA PRINCIPAL und 8 12,732.24 101,857.92 8.00 101,857.92 100% 0.00 0% 8.00 ### 101,857.92 100% 0.00 0.00 0%
01.14.02.04.02.02 CERCHA SECUNDARIA TIPO I und 3 2,496.58 7,489.74 3.00 7,489.74 100% 0.00 0% 3.00 ### 7,489.74 100% 0.00 0.00 0%
01.14.02.04.02.03 CERCHA SECUNDARIA TIPO II und 10 2,435.95 24,359.50 10.00 24,359.50 100% 0.00 0% 10.00 ### 24,359.50 100% 0.00 0.00 0%
01.14.02.04.03 COBERTURA PANEL DE ALUZINC e=0.4MM
01.14.02.04.03.01 PANEL DE ALUZINC PERFIL TP-4 PREPINTADO COLOR AZUL 5.80Mx1.00Mx0. m2 1228.38 49.75 61,111.91 1,228.38 61,111.91 100% 0.00 0% 1,228.38 ### 61,111.91 100% 0.00 0.00 0%
01.14.02.04.03.02 CANALETA DE F°G° P/ PERFIL TP-4 m 80.2 38.49 3,086.90 80.20 3,086.90 100% 0.00 0% 80.20 ### 3,086.90 100% 0.00 0.00 0%
01.14.02.04.03.03 PINTURA ANTICORROSIVA EN ESTRUCTURAS METALICAS m2 239.03 16.29 3,893.80 239.03 3,893.80 100% 0.00 0% 239.03 ### 3,893.80 100% 0.00 0.00 0%
01.14.02.04.04 EQUIPAMIENTO ELECTRICO
01.14.02.04.04.01 REFLECTOR C/LAMP 400W HG LUXIOD E40 und 6 614.04 3,684.24 6.00 3,684.24 100% 0.00 0% 6.00 ### 3,684.24 100% 0.00 0.00 0%
01.14.02.04.05 SISTEMA DE BAJADA PLUVIAL
01.14.02.04.05.01 BAJANTES DE PVC-SAP 4" pto 4 286.48 1,145.92 4.00 1,145.92 100% 0.00 0% 4.00 ### 1,145.92 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.01 TRABAJOS PRELIMINARES
01.15.01.01 REUBICACIÓN E INSTALACIÓN A SERVICIO PÚBLICO DE LUZ, AGUA Y DESAGÜE
01.15.01.01.01 REUBICACION Y INSTALACIÓN DE ACOMETIDA DE LUZ, MEDIDORES DE AGU GLB 1 1,500.00 1,500.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.00 1,500.00 100%
01.15.01.02 LIMPIEZA DE TERRENO
01.15.01.02.01 LIMPIEZA DE TERRENO MANUAL m2 600.28 3.22 1,932.90 600.28 1,932.90 100% 0.00 0% 600.28 ### 1,932.90 100% 0.00 0.00 0%
01.15.01.03 TRAZO, NIVELES Y REPLANTEO
01.15.01.03.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 600.28 10.08 6,050.82 600.28 6,050.82 100% 0.00 0% 600.28 ### 6,050.82 100% 0.00 0.00 0%
01.15.02 MOVIMIENTO DE TIERRAS
01.15.02.01 CORTES
01.15.02.01.01 CORTE DE TERRENO m3 120.06 42.46 5,097.75 120.06 5,097.75 100% 0.00 0% 120.06 ### 5,097.75 100% 0.00 0.00 0%
01.15.02.02 EXCAVACIONES
01.15.02.02.01 EXCAVACION MANUAL m3 2.49 42.46 105.73 2.49 105.73 100% 0.00 0% 2.49 ### 105.73 100% 0.00 0.00 0%
01.15.02.03 RELLENOS
01.15.02.03.01 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 60.03 67.32 4,041.22 60.03 4,041.22 100% 0.00 0% 60.03 ### 4,041.22 100% 0.00 0.00 0%
01.15.02.04 ELIMINACION DE MATERIAL EXEDENTE
01.15.02.04.01 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 147.05 17.69 2,601.31 147.05 2,601.31 100% 0.00 0% 147.05 ### 2,601.31 100% 0.00 0.00 0%
01.15.02.04.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 147.05 8.47 1,245.51 147.05 1,245.51 100% 0.00 0% 147.05 ### 1,245.51 100% 0.00 0.00 0%
01.15.02.05 REFINE Y NIVELACION
01.15.02.05.01 REFINE Y NIVELACION EN TERRENO m2 600.28 6.74 4,045.89 600.28 4,045.89 100% 0.00 0% 600.28 ### 4,045.89 100% 0.00 0.00 0%
01.15.02.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 600.28 22.56 13,542.32 600.28 13,542.32 100% 0.00 0% 600.28 ### 13,542.32 100% 0.00 0.00 0%
01.15.03 PISOS Y PAVIMENTOS
01.15.03.01 VEREDAS Y RAMPAS
01.15.03.01.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 108.35 59.66 6,464.16 108.35 6,464.16 100% 0.00 0% 108.35 ### 6,464.16 100% 0.00 0.00 0%
01.15.03.01.02 ENCOFRADO Y DESENCOFRADO m2 29.49 62.00 1,828.38 29.49 1,828.38 100% 0.00 0% 29.49 ### 1,828.38 100% 0.00 0.00 0%
01.15.03.01.03 JUNTAS DE DILATACION EN VEREDAS m 134.05 31.99 4,288.26 0.00 0.00 0% 134.05 4,288.26 100% 134.05 ### 4,288.26 100% 0.00 0.00 0%
01.15.03.02 PISOS ADOQUINADOS
01.15.03.02.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 295.5 29.42 8,693.61 295.50 8,693.61 100% 0.00 0% 295.50 ### 8,693.61 100% 0.00 0.00 0%
01.15.03.02.02 BASE DE ARENA E=0.04 NIVELACION MANUAL m2 295.5 12.00 3,546.00 295.50 3,546.00 100% 0.00 0% 295.50 ### 3,546.00 100% 0.00 0.00 0%
01.15.03.02.03 PISO CON ADOQUINES DE CONCRETO 20x10x4cm - GRIS m2 295.5 69.36 20,495.88 295.50 20,495.88 100% 0.00 0% 295.50 ### 20,495.88 100% 0.00 0.00 0%
01.15.03.02.04 SELLADO DE JUNTAS EN ADOQUINES m2 50.24 4.81 241.65 50.24 241.65 100% 0.00 0% 50.24 ### 241.65 100% 0.00 0.00 0%
01.15.03.02.05 VIBRADO Y COMPACTADO DE VEREDAS DE ADOQUINES DE CONCRETO m2 295.5 14.13 4,175.42 295.50 4,175.42 100% 0.00 0% 295.50 ### 4,175.42 100% 0.00 0.00 0%
01.15.04 ASTA DE BANDERA
01.15.04.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 2.25 10.08 22.68 2.25 22.68 100% 0.00 0% 2.25 ### 22.68 100% 0.00 0.00 0%
01.15.04.02 EXCAVACION MANUAL m3 0.56 42.46 23.78 0.56 23.78 100% 0.00 0% 0.56 ### 23.78 100% 0.00 0.00 0%
01.15.04.03 REFINE Y NIVELACION EN TERRENO m2 2.25 6.74 15.17 2.25 15.17 100% 0.00 0% 2.25 ### 15.17 100% 0.00 0.00 0%
01.15.04.04 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 2.25 22.56 50.76 2.25 50.76 100% 0.00 0% 2.25 ### 50.76 100% 0.00 0.00 0%
01.15.04.05 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 0.7 17.69 12.38 0.70 12.38 100% 0.00 0% 0.70 ### 12.38 100% 0.00 0.00 0%
01.15.04.06 TARRAJEO PULIDO EN SUPEERF. DE PEDESTAL m2 3 55.17 165.51 3.00 165.51 100% 0.00 0% 3.00 ### 165.51 100% 0.00 0.00 0%
01.15.04.07 PEDESTAL 1.5X1.5X0.6, CONCRETO F'C=175 KG/CM2 m3 0.98 413.67 405.40 0.98 405.40 100% 0.00 0% 0.98 ### 405.40 100% 0.00 0.00 0%
01.15.04.08 ENCOFRADO Y DESENCOFRADO m2 3 62.00 186.00 3.00 186.00 100% 0.00 0% 3.00 ### 186.00 100% 0.00 0.00 0%
01.15.04.09 ASTA DE BANDERA TIPICO und 1 1,193.27 1,193.27 1.00 1,193.27 100% 0.00 0% 1.00 ### 1,193.27 100% 0.00 0.00 0%
01.15.04.10 PINTURA ESMALTE SINTETICO EN OBRA DE CONCRETO m2 4.8 19.50 93.60 4.80 93.60 100% 0.00 0% 4.80 ### 93.60 100% 0.00 0.00 0%
01.15.04.11 PINTURA ESMALTE SINTETICO C/BLANCO EN TUBO DE ACERO m 10 3.16 31.60 10.00 31.60 100% 0.00 0% 10.00 ### 31.60 100% 0.00 0.00 0%
01.15.04.12 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 10 4.65 46.50 10.00 46.50 100% 0.00 0% 10.00 ### 46.50 100% 0.00 0.00 0%
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 112.17 10.08 1,130.67 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 112.17 1,130.67 100%
01.15.05.02 EXCAVACION MANUAL m3 44.87 42.46 1,905.18 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 44.87 1,905.18 100%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 280.42 1,890.03 100%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 56.08 17.69 992.06 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 56.08 992.06 100%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 56.08 8.47 475.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 56.08 475.00 100%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 28.04 413.67 11,599.31 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 28.04 11,599.31 100%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 168.25 62.00 10,431.50 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 168.25 10,431.50 100%
01.15.05.08 REJILLA PARA CANALETA m 394.92 76.78 30,321.96 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 394.92 30,321.96 100%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 394.92 4.65 1,836.38 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 394.92 1,836.38 100%
01.15.06 INSTALACIONES SANITARIAS EXTERIORES
01.15.06.01 SISTEMA DE AGUA FRIA
01.15.06.01.01 TRABAJOS PRELIMINARES
01.15.06.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 98.36 10.08 991.47 98.36 991.47 100% 0.00 0% 98.36 ### 991.47 100% 0.00 0.00 0%
01.15.06.01.02 MOVIMIENTO DE TIERRAS
01.15.06.01.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 31.48 42.46 1,336.64 31.48 1,336.64 100% 0.00 0% 31.48 ### 1,336.64 100% 0.00 0.00 0%
01.15.06.01.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 98.36 6.74 662.95 98.36 662.95 100% 0.00 0% 98.36 ### 662.95 100% 0.00 0.00 0%
01.15.06.01.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.93 136.53 536.56 3.93 536.56 100% 0.00 0% 3.93 ### 536.56 100% 0.00 0.00 0%
01.15.06.01.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 98.36 5.75 565.57 98.36 565.57 100% 0.00 0% 98.36 ### 565.57 100% 0.00 0.00 0%
01.15.06.01.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 11.8 139.08 1,641.14 11.80 1,641.14 100% 0.00 0% 11.80 ### 1,641.14 100% 0.00 0.00 0%
01.15.06.01.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 15.74 67.32 1,059.62 15.74 1,059.62 100% 0.00 0% 15.74 ### 1,059.62 100% 0.00 0.00 0%
01.15.06.01.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 20.46 17.69 361.94 20.46 361.94 100% 0.00 0% 20.46 ### 361.94 100% 0.00 0.00 0%
01.15.06.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 20.46 8.47 173.30 20.46 173.30 100% 0.00 0% 20.46 ### 173.30 100% 0.00 0.00 0%
01.15.06.01.03 REDES DE ALIMENTACION EXTERIORES
01.15.06.01.03.01 RED DE ALIMENTACION TUBERIA PVC CLASE 10 DE 1/2" m 28.37 18.21 516.62 28.37 516.62 100% 0.00 0% 28.37 ### 516.62 100% 0.00 0.00 0%
01.15.06.01.03.02 RED DE ALIMENTACION TUBERIA PVC CLASE 10 DE 3/4" m 69.99 19.20 1,343.81 69.99 1,343.81 100% 0.00 0% 69.99 ### 1,343.81 100% 0.00 0.00 0%
01.15.06.01.03.03 PRUEBA HIDRAULICA+DESINFECCION m 98.36 1.97 193.77 98.36 193.77 100% 0.00 0% 98.36 ### 193.77 100% 0.00 0.00 0%
01.15.06.01.04 ACCESORIO DE REDES
01.15.06.01.04.01 CODO PVC 90° SAP C-10 DE 1/2" und 3 10.07 30.21 3.00 30.21 100% 0.00 0% 3.00 ### 30.21 100% 0.00 0.00 0%
01.15.06.01.04.02 CODO PVC-SAP CLASE 10 R 3/4' x 90º und 3 11.25 33.75 3.00 33.75 100% 0.00 0% 3.00 ### 33.75 100% 0.00 0.00 0%
01.15.06.01.04.03 TEE PVC SAP C-10 DE 3/4” und 2 20.27 40.54 2.00 40.54 100% 0.00 0% 2.00 ### 40.54 100% 0.00 0.00 0%
01.15.06.01.05 VALVULAS Y LLAVES
01.15.06.01.05.01 VALVULA DE COMPUERTA DE BRONCE PESADA Ø1/2" und 2 111.23 222.46 2.00 222.46 100% 0.00 0% 2.00 ### 222.46 100% 0.00 0.00 0%
01.15.06.01.05.02 VALVULA DE COMPUERTA DE BRONCE PESADA Ø3/4" und 1 126.04 126.04 1.00 126.04 100% 0.00 0% 1.00 ### 126.04 100% 0.00 0.00 0%
01.15.06.01.06 CAJA DE CONCRETO PARA VALVULA
01.15.06.01.06.01 MOVIMIENTO DE TIERRAS
01.15.06.01.06.01.01 EXCAVACION PARA ESTRUCTURAS m3 0.74 42.46 31.42 0.74 31.42 100% 0.00 0% 0.74 ### 31.42 100% 0.00 0.00 0%
01.15.06.01.06.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 0.96 17.69 16.98 0.96 16.98 100% 0.00 0% 0.96 ### 16.98 100% 0.00 0.00 0%
01.15.06.01.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 0.96 8.47 8.13 0.96 8.13 100% 0.00 0% 0.96 ### 8.13 100% 0.00 0.00 0%
01.15.06.01.06.02 CONCRETO ARMADO
01.15.06.01.06.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA VALVULA kg 39.45 5.19 204.75 39.45 204.75 100% 0.00 0% 39.45 ### 204.75 100% 0.00 0.00 0%
01.15.06.01.06.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE VALVULA m2 4.26 62.00 264.12 4.26 264.12 100% 0.00 0% 4.26 ### 264.12 100% 0.00 0.00 0%
01.15.06.01.06.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 0.29 413.67 119.96 0.29 119.96 100% 0.00 0% 0.29 ### 119.96 100% 0.00 0.00 0%
01.15.06.01.07 VARIOS
01.15.06.01.07.01 TAPA METALICA ESTRIADA DE 0.6 X 0.3 /1/4" INC MARCO Y PINTURA und 3 235.33 705.99 3.00 705.99 100% 0.00 0% 3.00 ### 705.99 100% 0.00 0.00 0%
01.15.06.01.07.02 SALIDA DE HIDRANTES pto 2 331.07 662.14 2.00 662.14 100% 0.00 0% 2.00 ### 662.14 100% 0.00 0.00 0%
01.15.06.01.07.03 EMPALME A RED EXISTENTE DE AGUA und 1 80.02 80.02 1.00 80.02 100% 0.00 0% 1.00 ### 80.02 100% 0.00 0.00 0%
01.15.06.02 SISTEMA DE DESAGUE
01.15.06.02.01 TRABAJOS PRELIMINARES
01.15.06.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 68.27 10.08 688.16 68.27 688.16 100% 0.00 0% 68.27 ### 688.16 100% 0.00 0.00 0%
01.15.06.02.02 MOVIMIENTO DE TIERRAS
01.15.06.02.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 27.31 42.46 1,159.58 27.31 1,159.58 100% 0.00 0% 27.31 ### 1,159.58 100% 0.00 0.00 0%
01.15.06.02.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 68.27 6.74 460.14 68.27 460.14 100% 0.00 0% 68.27 ### 460.14 100% 0.00 0.00 0%
01.15.06.02.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.41 136.53 465.57 3.41 465.57 100% 0.00 0% 3.41 ### 465.57 100% 0.00 0.00 0%
01.15.06.02.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 68.27 5.75 392.55 68.27 392.55 100% 0.00 0% 68.27 ### 392.55 100% 0.00 0.00 0%
01.15.06.02.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 10.24 139.08 1,424.18 10.24 1,424.18 100% 0.00 0% 10.24 ### 1,424.18 100% 0.00 0.00 0%
01.15.06.02.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 13.65 67.32 918.92 13.65 918.92 100% 0.00 0% 13.65 ### 918.92 100% 0.00 0.00 0%
01.15.06.02.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 17.75 17.69 314.00 17.75 314.00 100% 0.00 0% 17.75 ### 314.00 100% 0.00 0.00 0%
01.15.06.02.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 17.75 8.47 150.34 17.75 150.34 100% 0.00 0% 17.75 ### 150.34 100% 0.00 0.00 0%
01.15.06.02.03 INSTALACION DE TUBERIA COLECTORA
01.15.06.02.03.01 RED COLECTORA CON TUBERIA PVC-SAL Ø 4' m 68.27 50.01 3,414.18 68.27 3,414.18 100% 0.00 0% 68.27 ### 3,414.18 100% 0.00 0.00 0%
01.15.06.02.03.02 PRUEBA HIDRAULICA DE TUBERIA EN ZANJA m 68.27 1.86 126.98 68.27 126.98 100% 0.00 0% 68.27 ### 126.98 100% 0.00 0.00 0%
01.15.06.02.04 CAJA DE REGISTRO
01.15.06.02.04.01 MOVIMIENTO DE TIERRAS
01.15.06.02.04.01.01 EXCAVACION DE PARA ESTRUTURAS m3 2.02 42.46 85.77 0.92 39.06 46% 0.00 0% 0.92 ### 39.06 46% 1.10 46.71 54%
01.15.06.02.04.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 2.63 17.69 46.52 1.19 21.05 45% 0.00 0% 1.19 ### 21.05 45% 1.44 25.47 55%
01.15.06.02.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 2.63 8.47 22.28 1.19 10.08 45% 0.00 0% 1.19 ### 10.08 45% 1.44 12.20 55%
01.15.06.02.04.02 CONCRETO ARMADO
01.15.06.02.04.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA DE REGISTRO kg 114.11 5.19 592.23 76.08 394.86 67% 0.00 0% 76.08 ### 394.86 67% 38.03 197.38 33%
01.15.06.02.04.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE REGISTRO m2 19.03 62.00 1,179.86 11.90 737.80 63% 0.00 0% 11.90 ### 737.80 63% 7.13 442.06 37%
01.15.06.02.04.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 3.01 413.67 1,245.15 1.69 699.10 56% 0.00 0% 1.69 ### 699.10 56% 1.32 546.04 44%
01.15.06.02.05 VARIOS
01.15.06.02.05.01 EMPALME A RED DE ALCANTARILLADO EXISTENTE und 1 374.38 374.38 1.00 374.38 100% 0.00 0% 1.00 ### 374.38 100% 0.00 0.00 0%
01.15.07 INSTALACIONES ELECTRICAS EXTERIORES
01.15.07.01 TRABAJOS PRELIMINARES
01.15.07.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 412.56 10.08 4,158.60 412.56 4,158.60 100% 0.00 0% 412.56 ### 4,158.60 100% 0.00 0.00 0%
01.15.07.02 EQUIPAMIENTO INSTALACIONES ELECTRICA EXTERIORES
01.15.07.02.01 POSTE METALICOS P/FAROLAS INC. INSTALACION und 17 869.89 14,788.13 17.00 14,788.13 100% 0.00 0% 17.00 ### 14,788.13 100% 0.00 0.00 0%
01.15.07.02.02 SISTEMA PARA RAYOS pto 1 7,297.05 7,297.05 1.00 7,297.05 100% 0.00 0% 1.00 ### 7,297.05 100% 0.00 0.00 0%
01.15.07.02.03 FAROLA ESFERICA JOSFEL und 34 232.96 7,920.64 34.00 7,920.64 100% 0.00 0% 34.00 ### 7,920.64 100% 0.00 0.00 0%
01.15.07.02.04 BUZON DE CONCRETO PREFABRICADO DE .60X.60X.80M und 1 583.55 583.55 1.00 583.55 100% 0.00 0% 1.00 ### 583.55 100% 0.00 0.00 0%
01.15.07.03 CANALIZACION Y TUBERIAS
01.15.07.03.01 EXCAVACION DE ZANJAS PARA REDES EXT. ELECTRICAS m3 149.27 42.46 6,338.00 145.34 6,171.11 97% 3.93 166.89552 3% 149.27 ### 6,338.00 100% 0.00 0.00 0%
01.15.07.03.02 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 144.4 67.32 9,721.01 109.93 7,400.59 76% 34.47 2,320.42 24% 144.40 ### 9,721.01 100% 0.00 0.00 0%
01.15.07.03.03 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 6.34 17.69 112.15 5.85 103.49 92% 0.49 8.67 8% 6.34 ### 112.15 100% 0.00 0.00 0%
01.15.07.03.04 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 6.34 8.47 53.70 5.85 49.55 92% 0.49 4.15 8% 6.34 ### 53.70 100% 0.00 0.00 0%
01.15.07.03.05 TUBERIA PVC-P 35mm m 412.56 11.51 4,748.57 337.00 3,878.87 82% 75.56 869.70 18% 412.56 ### 4,748.57 100% 0.00 0.00 0%
01.15.07.04 TABLEROS Y CUCHILLAS
01.15.07.04.01 TABLEROS DISTRIBUCION CAJA METALICA CON 08 POLOS und 1 417.51 417.51 1.00 417.51 100% 0.00 0% 1.00 ### 417.51 100% 0.00 0.00 0%
01.15.07.04.02 TABLEROS DISTRIBUCION CAJA METALICA CON 04 POLOS und 6 374.26 2,245.56 6.00 2,245.56 100% 0.00 0% 6.00 ### 2,245.56 100% 0.00 0.00 0%
01.15.07.04.03 TABLEROS DISTRIBUCION CAJA METALICA CON 04 POLOS-ALUMBRADO EXT und 1 374.26 374.26 1.00 374.26 100% 0.00 0% 1.00 ### 374.26 100% 0.00 0.00 0%
01.15.07.05 CONEXIONES A RED EXTERNA Y MEDIDORES
01.15.07.05.01 ALIMENTADOR CABLE NYY(3x25)MM2 m 11.59 43.38 502.77 0.00 0.00 0% 11.59 502.77 100% 11.59 ### 502.77 100% 0.00 0.00 0%
01.15.07.05.02 ALIMENTADOR CABLE NYY(2X6+1X2.5)MM2 m 11.59 14.57 168.87 0.00 0.00 0% 11.59 168.87 100% 11.59 ### 168.87 100% 0.00 0.00 0%
01.15.07.05.03 ALIMENTADOR CABLE NYY(2X10+1X6)MM2 m 464.44 20.09 9,330.60 0.00 0.00 0% 464.44 9,330.60 100% 464.44 ### 9,330.60 100% 0.00 0.00 0%
01.15.07.06 SISTEMA PUESTA TIERRA
01.15.07.06.01 POZO PUESTA A TIERRA P-1 ( R<15 Ohms) und 1 2,007.28 2,007.28 1.00 2,007.28 100% 0.00 0% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 40.48 3.22 130.35 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 130.35 100%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 40.48 10.08 408.04 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 408.04 100%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 4.05 42.46 171.96 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 4.05 171.96 100%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 60.72 109.80 6,667.06 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 60.72 6,667.06 100%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 5.06 8.47 42.86 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 5.06 42.86 100%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 40.48 6.74 272.84 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 272.84 100%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 7.21 413.40 2,980.61 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 7.21 2,980.61 100%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 11.88 62.00 736.56 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 11.88 736.56 100%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 80.89 3.22 260.47 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 260.47 100%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 80.89 10.08 815.37 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 815.37 100%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 121.34 42.46 5,152.10 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 121.34 5,152.10 100%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 114.32 109.80 12,552.34 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 114.32 12,552.34 100%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 27.03 104.62 2,827.88 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 27.03 2,827.88 100%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 151.67 8.47 1,284.64 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 151.67 1,284.64 100%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 80.89 6.74 545.20 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 545.20 100%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 80.89 36.45 2,948.44 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 2,948.44 100%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 58.29 413.40 24,097.09 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 58.29 24,097.09 100%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 4877.83 5.19 25,315.94 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 4,877.83 25,315.94 100%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 180.22 62.00 11,173.64 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 180.22 11,173.64 100%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 15.39 30.00 461.70 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 15.39 461.70 100%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 3.07 23.16 71.10 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 3.07 71.10 100%
01.15.10 MANTENIMIENTO DE CANAL
01.15.10.01 DESCOLMATACION DE SECCION HIDRAULICA DE CANAL m3 149.04 48.07 7,164.35 149.04 7,164.35 100% 0.00 0% 149.04 ### 7,164.35 100% 0.00 0.00 0%
02 COMPONENTE 02: EQUIPAMIENTO Y MOBILIARIO
02.01 EQUIPAMIENTO MÓDULO PEDAGÓGICO
02.01.01 EQUIPAMIENTO AULAS GLB 7 13,435.71 94,049.97 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 7.00 94,049.97 100%
02.01.02 EQUIPAMIENTO SALA DE USOS MULTLIPE GLB 1 27,233.09 27,233.09 0.00 0.00 0% 0.20 5,446.62 20% 0.20 ### 5,446.62 20% 0.80 21,786.47 80%
02.02 EQUIPAMIENTO MÓDULO COMPLEMENTARIO
02.02.01 EQUIPAMIENTO LABORATORIO GLB 1 41,314.62 41,314.62 0.00 0.00 0% 0.50 20,657.31 50% 0.50 ### 20,657.31 50% 0.50 20,657.31 50%
02.02.02 EQUIPAMIENTO DE GUARDIANIA GLB 1 1,086.09 1,086.09 0.00 0.00 0% 0.20 217.22 20% 0.20 ### 217.22 20% 0.80 868.87 80%
02.02.03 EQUIPAMIENTO DIRECCION GLB 1 6,953.78 6,953.78 0.00 0.00 0% 0.20 1,390.76 20% 0.20 ### 1,390.76 20% 0.80 5,563.02 80%
02.02.04 EQUIPAMIENTO SALA DE PROFESORES GLB 1 2,814.04 2,814.04 0.00 0.00 0% 0.20 562.81 20% 0.20 ### 562.81 20% 0.80 2,251.23 80%
02.02.05 EQUIPAMIENTO TOPICO GLB 1 2,852.97 2,852.97 0.00 0.00 0% 0.50 1,426.49 50% 0.50 ### 1,426.49 50% 0.50 1,426.49 50%
02.02.06 EQUIPAMIENTO ARCHIVOS GLB 1 936.67 936.67 0.00 0.00 0% 0.50 468.34 50% 0.50 ### 468.34 50% 0.50 468.34 50%
02.02.07 EQUIPAMIENTO DE DEPOSITO DE LIMPIEZA GLB 1 1,892.12 1,892.12 0.00 0.00 0% 1.00 1,892.12 100% 1.00 ### 1,892.12 100% 0.00 0.00 0%
02.02.08 EQUIPAMIENTO DE COCINA GLB 1 11,542.23 11,542.23 0.00 0.00 0% 0.50 5,771.12 50% 0.50 ### 5,771.12 50% 0.50 5,771.12 50%
02.02.09 EQUIPAMIENTO SALA DE COMPUTO GLB 1 119,755.77 119,755.77 0.00 0.00 0% 1.00 119,755.77 100% 1.00 ### 119,755.77 100% 0.00 0.00 0%
02.02.10 EQUIPAMIENTO BIBLIOTECA GLB 1 54,224.09 54,224.09 0.00 0.00 0% 0.50 27,112.05 50% 0.50 ### 27,112.05 50% 0.50 27,112.05 50%
03 COMPONENTE 03: FORTALECIMIENTO Y CAPACITACION
03.01 FORTALECIMIENTO DE CAPACIDADES CON UN CONSULTOR EN DISEÑO CURRICULAR Y ENFOQUE PEDAGOGICO
03.01.01 CAPACITACION EN PROYECTO EDUCATIVO NACIONAL-PEN und 2 1,346.99 2,693.98 2.00 2,693.98 100% 0.00 0% 2.00 ### 2,693.98 100% 0.00 0.00 0%
03.01.02 CAPACITACION EN PROYECTO EDUCATIVO REGIONAL-PER und 2 1,046.99 2,093.98 2.00 2,093.98 100% 0.00 0% 2.00 ### 2,093.98 100% 0.00 0.00 0%
03.01.03 CAPACITACION EN DIVERSIFICACION CURRICULAR und 2 1,121.99 2,243.98 2.00 2,243.98 100% 0.00 0% 2.00 ### 2,243.98 100% 0.00 0.00 0%
03.01.04 CAPACITACION EN ELABORACION DE MATERIALES EDUCATIVOS und 2 1,121.99 2,243.98 2.00 2,243.98 100% 0.00 0% 2.00 ### 2,243.98 100% 0.00 0.00 0%
03.01.05 CAPACITACION EN PREPARACION PARA LA EDUCACION EN SALUD und 2 1,593.99 3,187.98 2.00 3,187.98 100% 0.00 0% 2.00 ### 3,187.98 100% 0.00 0.00 0%
03.02 CAPACITACION EN GERENCIA EDUCATIVA
03.02.01 CAPACITACION EN GERENCIA EDUCATIVA und 2 936.00 1,872.00 2.00 1,872.00 100% 0.00 0% 2.00 ### 1,872.00 100% 0.00 0.00 0%
03.02.02 CAPACITACION EN LIDERAZGO, CALIDAD Y COMPETENCIAS DOCENTES und 2 1,185.99 2,371.98 2.00 2,371.98 100% 0.00 0% 2.00 ### 2,371.98 100% 0.00 0.00 0%
03.02.03 CAPACITACION PARA LA PAZ Y RESOLUCION DE CONFILCTOS und 2 1,408.00 2,816.00 2.00 2,816.00 100% 0.00 0% 2.00 ### 2,816.00 100% 0.00 0.00 0%
03.02.04 CAPACITACION EN ELABORACION DE LINEA BASE PARA EVALUACION und 2 1,421.99 2,843.98 2.00 2,843.98 100% 0.00 0% 2.00 ### 2,843.98 100% 0.00 0.00 0%
03.03 CAPACITACION APAFA
03.03.01 ESCUELA DE PADRES GLB 2 936.00 1,872.00 2.00 1,872.00 100% 0.00 0% 2.00 ### 1,872.00 100% 0.00 0.00 0%
04 COMPONENTE 04: MITIGACION AMBIENTAL
04.01 MANEJO AMBIENTAL Y PLAN DE CIERRE
04.01.01 CONTENEDORES DE RESIDUOS SOLIDOS und 3 170.09 510.27 3.00 510.27 100% 0.00 0% 3.00 ### 510.27 100% 0.00 0.00 0%
04.01.02 TACHOS DE BASURA METALICOS und 10 572.41 5,724.10 10.00 5,724.10 100% 0.00 0% 10.00 ### 5,724.10 100% 0.00 0.00 0%
04.01.03 INDUCCION AL PERSONAL EN EL MANEJO DE RR.SS und 1 9,330.00 9,330.00 1.00 9,330.00 100% 0.00 0% 1.00 ### 9,330.00 100% 0.00 0.00 0%
04.01.04 PROGRAMA DE SENSIBILIZACION A LA POBLACION EN TEMAS DE RR.SS und 1 9,240.00 9,240.00 1.00 9,240.00 100% 0.00 0% 1.00 ### 9,240.00 100% 0.00 0.00 0%
04.01.05 LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und 2 480.62 961.24 2.00 961.24 100% 0.00 0% 2.00 ### 961.24 100% 0.00 0.00 0%
04.01.06 NIVELACION DEL AREA DE BOTADERO und 800 4.49 3,592.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 800.00 3,592.00 100%
04.01.07 INSTALACION DE AREAS VERDES m2 2325.07 11.37 26,436.05 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2,325.07 26,436.05 100%
04.01.08 SEMBRADO DE PLANTAS ORNAMENTALES und 150 16.04 2,406.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 150.00 2,406.00 100%
04.01.09 LIMPIEZA FINAL DE OBRA m2 2225.85 0.20 445.17 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2,225.85 445.17 100%
COSTO DIRECTO 2,278,432.36 1,554,702.93 68.24% 242,448.39 10.64% ### 1,797,151.32 78.88% 481,280.98 21.12%
GASTOS GENERALES (11.13 %CD) 253,654.58 173,082.83 26,991.42 ### 200,074.25 53,580.34
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 52,757.15 8,227.22 60,984.37 16,331.75
SUB TOTAL 2,609,403.06 1,780,542.91 68.24% 277,667.03 10.64% 2,058,209.94 78.88% 551,193.07 21.12%
º

VALORIZACION PRINCIPAL N°- 08


( MES DE MARZO DEL 2020)
FECHA DE INICIO DE OBRA : ´01/07/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/10/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/24/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
COSTO COSTO
ÍTEM PARTIDA
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.02 PINTURAS 0.00
01.08.02.01 PINTURA AL LATEX EN CIELO RASO m2 356 14.34 5,105.04 0.00 0.00 0% 356.00 5,105.04 100% 356.00 ### 5,105.04 100% 0.00 0.00 0%
01.08.02.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 816 12.41 10,126.56 0.00 0.00 0% 816.00 10,126.56 100% 816.00 ### 10,126.56 100% 0.00 0.00 0%
01.08.02.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 84.6 14.34 1,213.16 0.00 0.00 0% 84.60 1,213.16 100% 84.60 ### 1,213.16 100% 0.00 0.00 0%
01.08.02.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 209.79 14.34 3,008.39 0.00 0.00 0% 209.79 3,008.39 100% 209.79 ### 3,008.39 100% 0.00 0.00 0%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.01 PINTURAS
01.09.01.01 PINTURA AL LATEX EN CIELO RASO m2 162 14.34 2,323.08 0.00 0.00 0% 162.00 2,323.08 100% 162.00 ### 2,323.08 100% 0.00 0.00 0%
01.09.01.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 408.6 12.41 5,070.73 0.00 0.00 0% 408.60 5,070.73 100% 408.60 ### 5,070.73 100% 0.00 0.00 0%
01.09.01.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 111.3 14.34 1,596.04 0.00 0.00 0% 111.30 1,596.04 100% 111.30 ### 1,596.04 100% 0.00 0.00 0%
01.09.01.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 209.38 14.34 3,002.51 0.00 0.00 0% 209.38 3,002.51 100% 209.38 ### 3,002.51 100% 0.00 0.00 0%
01.09.02 REPOSICION DE PISOS
01.09.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 248.4 63.25 15,711.30 208.00 13,156.00 84% 40.40 2,555.30 16% 248.40 ### 15,711.30 100% 0.00 0.00 0%
01.09.03 PUERTAS SS.HH.
01.09.03.02 PUERTA METALICA m2 8.64 548.11 4,735.67 0.00 0.00 0% 8.64 4,735.67 100% 8.64 ### 4,735.67 100% 0.00 0.00 0%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.07 PISOS Y PAVIMENTOS
01.11.07.03 VEREDAS Y RAMPAS
01.11.07.03.02 JUNTAS DE DILATACION EN VEREDAS m 108.41 31.99 3,468.04 0.00 0.00 0% 108.41 3,468.04 100% 108.41 ### 3,468.04 100% 0.00 0.00 0%
01.11.13 PINTURA
01.11.13.01 PINTURA AL LATEX EN CIELO RASO m2 463.01 14.34 6,639.56 0.00 0.00 0% 463.01 6,639.56 100% 463.01 ### 6,639.56 100% 0.00 0.00 0%
01.11.13.02 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 608.28 12.41 7,548.75 0.00 0.00 0% 304.14 3,774.37 50% 304.14 ### 3,774.37 50% 304.14 3,774.38 50%
01.11.13.03 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 587.56 14.34 8,425.61 0.00 0.00 0% 587.56 8,425.61 100% 587.56 ### 8,425.61 100% 0.00 0.00 0%
01.11.13.04 PINTURA AL LATEX DOS MANOS EN VIGAS m2 292.02 14.34 4,187.57 0.00 0.00 0% 292.02 4,187.57 100% 292.02 ### 4,187.57 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.08 CONTRAZOCALOS
01.12.08.02 ZOCALOS
01.12.08.02.01 ZOCALOS DE MAYOLICA
01.12.08.02.01.01 ZOCALO DE MAYOLICA DE COLOR 20X30 1RA m2 141.06 96.43 13,602.42 118.15 11,393.35 84% 22.91 2,209.07 16% 141.06 ### 13,602.42 100% 0.00 0.00 0%
01.12.11 CARPINTERIA METALICA Y ALUMINIO
01.12.11.02 PUERTAS METALICAS Y OTRAS
01.12.11.02.01 PUERTA METALICA m2 13.68 548.11 7,498.14 0.00 0.00 0% 13.68 7,498.14 100% 13.68 ### 7,498.14 100% 0.00 0.00 0%
01.12.14 APARATOS SANITARIOS Y ACCESORIOS
01.12.14.02 COLOCACION DE APARATOS SANITARIO pza 10 48.33 483.30 0.00 0.00 0% 10.00 483.30 100% 10.00 ### 483.30 100% 0.00 0.00 0%
01.12.14.04 LAVADERO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 3,572.01 3,572.01 0.00 0.00 0% 1.00 3,572.01 100% 1.00 ### 3,572.01 100% 0.00 0.00 0%
01.12.14.05 BANCA DE CONCRETO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 2,324.46 2,324.46 0.00 0.00 0% 1.00 2,324.46 100% 1.00 ### 2,324.46 100% 0.00 0.00 0%
01.12.14.06 BARANDA DE TUBO F. G. PASAMANO PARA DISCAPACITADOS pza 4 249.99 999.96 0.00 0.00 0% 4.00 999.96 100% 4.00 ### 999.96 100% 0.00 0.00 0%
01.12.15 INSTALACIONES SANITARIAS
01.12.15.05 CAJA DE REGISTRO 12" X 24" pza 1 223.57 223.57 0.00 0.00 0% 1.00 223.57 100% 1.00 ### 223.57 100% 0.00 0.00 0%
01.12.17 SISTEMA DE BAJADA PLUVIAL
01.12.17.01 BAJANTES DE PVC-SAP 4" pto 4 280.32 1,121.28 0.00 0.00 0% 4.00 1,121.28 100% 4.00 ### 1,121.28 100% 0.00 0.00 0%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.08 PISOS Y PAVIMENTOS
01.13.08.01 PISOS
01.13.08.01.02 PISO LADRILLO PASTELERO m2 8.94 22.05 197.13 0.00 0.00 0% 8.94 197.13 100% 8.94 ### 197.13 100% 0.00 0.00 0%
01.13.10 CARPINTERIA METALICA Y ALUMINIO
01.13.10.01 PUERTAS METALICAS Y OTRAS
01.13.10.01.01 PUERTA METALICA 0.70X1.65 m2 1.16 548.11 635.81 0.00 0.00 0% 1.16 635.81 100% 1.16 ### 635.81 100% 0.00 0.00 0%
01.13.10.01.02 ESCALERA DE GATO DE TUBO F°G° DE 1 1/2" Y 1" m 8.68 173.79 1,508.50 0.00 0.00 0% 8.68 1,508.50 100% 8.68 ### 1,508.50 100% 0.00 0.00 0%
01.13.11 CERRAJERIA
01.13.11.01 BISAGRAS
01.13.11.01.01 BISAGRA CAPUCHINA DE 4" X4" und 4 19.69 78.76 0.00 0.00 0% 4.00 78.76 100% 4.00 ### 78.76 100% 0.00 0.00 0%
01.13.11.02 CERRADURAS
01.13.11.02.01 CERRADURA DE 3 GOLPES PARA PUERTA und 1 102.55 102.55 0.00 0.00 0% 1.00 102.55 100% 1.00 ### 102.55 100% 0.00 0.00 0%
01.13.13 INSTALACIONES SANITARIAS
01.13.13.01 LINEA DE SUCCION E IMPULSION GLB 1 1,703.82 1,703.82 0.00 0.00 0% 1.00 1,703.82 100% 1.00 ### 1,703.82 100% 0.00 0.00 0%
01.13.13.02 LINEA DEL ALIMENTADOR GLB 1 1,584.86 1,584.86 0.00 0.00 0% 1.00 1,584.86 100% 1.00 ### 1,584.86 100% 0.00 0.00 0%
01.13.13.03 LINEA DE REBOSE Y LIMPIEZA GLB 1 1,458.26 1,458.26 0.00 0.00 0% 1.00 1,458.26 100% 1.00 ### 1,458.26 100% 0.00 0.00 0%
01.13.15 TABLEROS Y CUCHILLAS
01.13.15.03 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 0.00 0.00 0% 1.00 2,007.28 100% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.13.16 EQUIPOS ELECTRICOS
01.13.16.01 EQUIPOS ELECTRICOS GLB 1 1,700.24 1,700.24 0.00 0.00 0% 1.00 1,700.24 100% 1.00 ### 1,700.24 100% 0.00 0.00 0%
01.13.17 ARTEFACTOS DE ILUMINACION
01.13.17.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 1 99.17 99.17 0.00 0.00 0% 1.00 99.17 100% 1.00 ### 99.17 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.04 ESTRUCTURA METALICA Y COBERTURA
01.14.02.04.02 VIGAS METALICA
01.14.02.04.02.01 CERCHA PRINCIPAL und 8 12,732.24 101,857.92 0.00 0.00 0% 8.00 101,857.92 100% 8.00 ### 101,857.92 100% 0.00 0.00 0%
01.14.02.04.02.02 CERCHA SECUNDARIA TIPO I und 3 2,496.58 7,489.74 0.00 0.00 0% 3.00 7,489.74 100% 3.00 ### 7,489.74 100% 0.00 0.00 0%
01.14.02.04.02.03 CERCHA SECUNDARIA TIPO II und 10 2,435.95 24,359.50 0.00 0.00 0% 10.00 24,359.50 100% 10.00 ### 24,359.50 100% 0.00 0.00 0%
01.14.02.04.03 COBERTURA PANEL DE ALUZINC e=0.4MM
01.14.02.04.03.01 PANEL DE ALUZINC PERFIL TP-4 PREPINTADO COLOR AZUL 5.80Mx1.00Mx m2 1228.38 49.75 61,111.91 0.00 0.00 0% 1,228.38 61,111.91 100% 1,228.38 ### 61,111.91 100% 0.00 0.00 0%
01.14.02.04.03.02 CANALETA DE F°G° P/ PERFIL TP-4 m 80.2 38.49 3,086.90 0.00 0.00 0% 80.20 3,086.90 100% 80.20 ### 3,086.90 100% 0.00 0.00 0%
01.14.02.04.03.03 PINTURA ANTICORROSIVA EN ESTRUCTURAS METALICAS m2 239.03 16.29 3,893.80 0.00 0.00 0% 239.03 3,893.80 100% 239.03 ### 3,893.80 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.03 PISOS Y PAVIMENTOS
01.15.03.01 VEREDAS Y RAMPAS
01.15.03.01.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 108.35 59.66 6,464.16 55.20 3,293.23 51% 53.15 3,170.93 49% 108.35 ### 6,464.16 100% 0.00 0.00 0%
01.15.03.01.02 ENCOFRADO Y DESENCOFRADO m2 29.49 62.00 1,828.38 14.95 926.90 51% 14.54 901.48 49% 29.49 ### 1,828.38 100% 0.00 0.00 0%
01.15.04 ASTA DE BANDERA
01.15.04.09 ASTA DE BANDERA TIPICO und 1 1,193.27 1,193.27 0.00 0.00 0% 1.00 1,193.27 100% 1.00 ### 1,193.27 100% 0.00 0.00 0%
01.15.04.10 PINTURA ESMALTE SINTETICO EN OBRA DE CONCRETO m2 4.8 19.50 93.60 0.00 0.00 0% 4.80 93.60 100% 4.80 ### 93.60 100% 0.00 0.00 0%
01.15.04.11 PINTURA ESMALTE SINTETICO C/BLANCO EN TUBO DE ACERO m 10 3.16 31.60 0.00 0.00 0% 10.00 31.60 100% 10.00 ### 31.60 100% 0.00 0.00 0%
01.15.04.12 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 10 4.65 46.50 0.00 0.00 0% 10.00 46.50 100% 10.00 ### 46.50 100% 0.00 0.00 0%
01.15.06 INSTALACIONES SANITARIAS EXTERIORES
01.15.06.01.07 VARIOS
01.15.06.01.07.01 TAPA METALICA ESTRIADA DE 0.6 X 0.3 /1/4" INC MARCO Y PINTURA und 3 235.33 705.99 0.00 0.00 0% 3.00 705.99 100% 3.00 ### 705.99 100% 0.00 0.00 0%
01.15.07 INSTALACIONES ELECTRICAS EXTERIORES
01.15.07.03 CANALIZACION Y TUBERIAS
01.15.07.03.01 EXCAVACION DE ZANJAS PARA REDES EXT. ELECTRICAS m3 149.27 42.46 6,338.00 81.64 3,466.26 55% 35.20 1,494.59 24% 116.84 ### 4,960.86 78% 32.43 1,377.15 22%
01.15.07.03.02 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 144.4 67.32 9,721.01 71.43 4,808.77 49% 38.50 2,591.82 27% 109.93 ### 7,400.59 76% 34.47 2,320.42 24%
01.15.07.03.03 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 6.34 17.69 112.15 4.55 80.49 72% 1.30 23.00 21% 5.85 ### 103.49 92% 0.49 8.67 8%
01.15.07.03.04 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 6.34 8.47 53.70 4.55 38.54 72% 1.30 11.01 21% 5.85 ### 49.55 92% 0.49 4.15 8%
01.15.07.03.05 TUBERIA PVC-P 35mm m 412.56 11.51 4,748.57 300.00 3,453.00 73% 37.00 425.87 9% 337.00 ### 3,878.87 82% 75.56 869.70 18%
COSTO DIRECTO 2,278,432.36 1,155,700.83 50.72% 307,229.21 13.48% ### 1,462,930.04 64.21% 815,502.26 35.79%
GASTOS GENERALES (11.13 %CD) 253,654.58 128,662.50 34,203.37 ### 162,865.88 90,788.71
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 39,217.45 10,425.49 49,642.94 27,673.18
SUB TOTAL 2,609,403.06 1,323,580.78 50.72% 351,858.07 13.48% 1,675,438.85 64.21% 933,964.15 35.79%
º

VALORIZACION PRINCIPAL N°- 07


( MES DEL 11 AL 25 DE FEBRERO 2020)
FECHA DE INICIO DE OBRA : ´01/07/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/10/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/24/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.01 REVOQUES ENLUCIDOS Y MOLDURAS
01.08.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 26.45 25.87 684.26 0.00 0.00 0% 26.45 684.26 100% 26.45 ### 684.26 100% 0.00 0.00 0%
01.09.03 PUERTAS SS.HH.
01.09.03.04 MANIJA DE BRONCE PARA PUERTAS und 10 57.53 575.30 2.00 115.06 20% 8.00 460.24 80% 10.00 ### 575.30 100% 0.00 0.00 0%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.11 CARPINTERIA METALICA Y ALUMINIO
01.11.11.02 PASAMANO DE FoGo 2" SEGUN MODELO
01.11.11.02.01 PASAMANO DE FoGo 2" SEGUN MODELO m 69.42 58.83 4,083.98 0.00 0.00 0% 69.42 4,083.98 100% 69.42 ### 4,083.98 100% 0.00 0.00 0%
01.11.17 SISTEMA DE BAJADA PLUVIAL
01.11.17.01 BAJANTES DE PVC-SAP 4" pto 4 280.32 1,121.28 0.00 0.00 0% 4.00 1,121.28 100% 4.00 ### 1,121.28 100% 0.00 0.00 0%
01.11.19 INSTALACIONES ELECTRICAS
01.11.19.03 ARTEFACTOS DE ILUMINACION
01.11.19.03.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2x36/840 AHP-A und 26 69.18 1,798.68 0.00 0.00 0% 26.00 1,798.68 100% 26.00 ### 1,798.68 100% 0.00 0.00 0%
01.11.19.03.02 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 12 99.17 1,190.04 0.00 0.00 0% 12.00 1,190.04 100% 12.00 ### 1,190.04 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.12.05.01 MURO DE LADRILLO KK SOGA
01.12.05.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 100.24 63.52 6,367.24 40.02 2,542.07 40% 60.22 3,825.17 60% 100.24 ### 6,367.24 100% 0.00 0.00 0%
01.12.07 PISOS Y PAVIMENTOS
01.12.07.03 VEREDAS Y RAMPAS
01.12.07.03.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 40.76 59.66 2,431.74 15.57 928.91 38% 25.19 1,502.84 62% 40.76 ### 2,431.74 100% 0.00 0.00 0%
01.12.08 CONTRAZOCALOS
01.12.08.02 ZOCALOS
01.12.08.02.01 ZOCALOS DE MAYOLICA
01.12.08.02.01.01 ZOCALO DE MAYOLICA DE COLOR 20X30 1RA m2 141.06 96.43 13,602.42 60.55 5,838.98 43% 57.60 5,554.37 41% 118.15 ### 11,393.35 84% 22.91 2,209.07 16%
01.12.19 INSTALACIONES ELECTRICAS
01.12.19.03 ARTEFACTOS DE ILUMINACION
01.12.19.03.01 ARTEFACTO FLUORESCENTE RECTANGULAR 2X18/840 AHP-A und 4 99.17 396.68 0.00 0.00 0% 4.00 396.68 100% 4.00 ### 396.68 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.03 OBRAS DE CONCRETO ARMADO
01.14.02.03.02 COLUMNAS
01.14.02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 28.8 82.27 2,369.38 0.00 0.00 0% 28.80 2,369.38 100% 28.80 ### 2,369.38 100% 0.00 0.00 0%
01.14.02.03.02.03 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.24 511.53 1,657.36 0.00 0.00 0% 3.24 1,657.36 100% 3.24 ### 1,657.36 100% 0.00 0.00 0%
01.14.02.04 ESTRUCTURA METALICA Y COBERTURA
01.14.02.04.01 COLUMNA METALICA
01.14.02.04.01.01 COLUMNAS METALICAS SCH-40 DE 8" e=8.2MM und 16 1,163.31 18,612.96 8.00 9,306.48 50% 8.00 9,306.48 50% 16.00 ### 18,612.96 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.03 PISOS Y PAVIMENTOS
01.15.03.01 VEREDAS Y RAMPAS
01.15.03.01.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 108.35 59.66 6,464.16 0.00 0.00 0% 55.20 3,293.23 51% 55.20 ### 3,293.23 51% 53.15 3,170.93 49%
01.15.03.01.02 ENCOFRADO Y DESENCOFRADO m2 29.49 62.00 1,828.38 0.00 0.00 0% 14.95 926.90 51% 14.95 ### 926.90 51% 14.54 901.48 49%
01.15.07 INSTALACIONES ELECTRICAS EXTERIORES
01.15.07.03 CANALIZACION Y TUBERIAS
01.15.07.03.01 EXCAVACION DE ZANJAS PARA REDES EXT. ELECTRICAS m3 149.27 42.46 6,338.00 0.00 0.00 0% 81.64 3,466.26 55% 81.64 ### 3,466.26 55% 67.63 2,871.74 45%
01.15.07.03.02 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 144.4 67.32 9,721.01 0.00 0.00 0% 71.43 4,808.77 49% 71.43 ### 4,808.77 49% 72.97 4,912.24 51%
01.15.07.03.03 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 6.34 17.69 112.15 0.00 0.00 0% 4.55 80.49 72% 4.55 ### 80.49 72% 1.79 31.67 28%
01.15.07.03.04 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 6.34 8.47 53.70 0.00 0.00 0% 4.55 38.54 72% 4.55 ### 38.54 72% 1.79 15.16 28%
01.15.07.03.05 TUBERIA PVC-P 35mm m 412.56 11.51 4,748.57 0.00 0.00 0% 300.00 3,453.00 73% 300.00 ### 3,453.00 73% 112.56 1,295.57 27%
COSTO DIRECTO 2,278,432.36 1,105,682.88 48.53% 50,017.94 2.20% ### 1,155,700.83 50.72% 1,122,731.47 49.28%
GASTOS GENERALES (11.13 %CD) 253,654.58 123,094.08 5,568.42 ### 128,662.49 124,992.10
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 37,520.14 1,697.30 39,217.45 38,098.67
SUB TOTAL 2,609,403.06 1,266,297.10 48.53% 57,283.66 2.20% 1,323,580.77 50.72% 1,285,822.24 49.28%
º

VALORIZACION PRINCIPAL N°- 07


( MES DEL 26 DE NOVIEMBRE AL 20 DE DICIEMBRE 2019)
PLAZO DE EJECUCION: 06 MESES
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-
ACTIVIDAD: FECHA DE INICIO DE OBRA : 7/1/2019
CUSCO(QUISTO CENTRAL)"
FECHA DE TERMINO DE OBRA PR 12/27/2019
SUPERVISOR: ING. MARIO JOSEPH HUAYHUA BERROCAL MODALIDAD DE EJECUCION: ADM. DIRECTA
RESIDENTE : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.03 SEGURIDAD Y SALUD
01.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD D GLB 1 387.63 387.63 0.80 310.10 80% 0.20 77.53 20% 1.00 ### 387.63 100% 0.00 0.00 0%
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.04 REPOSICION DE PISOS 0.00
01.08.04.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 208 63.25 13,156.00 104.00 6,578.00 50% 104.00 6,578.00 50% 208.00 ### 13,156.00 100% 0.00 0.00 0%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.02 REPOSICION DE PISOS
01.09.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 248.4 63.25 15,711.30 156.00 9,867.00 63% 52.00 3,289.00 21% 208.00 ### 13,156.00 84% 40.40 2,555.30 16%
01.09.03 PUERTAS SS.HH.
01.09.03.01 PUERTAS DE MADERA TORNILLO APANELADA m2 4 565.23 2,260.92 2.00 1,130.46 50% 2.00 1,130.46 50% 4.00 ### 2,260.92 100% 0.00 0.00 0%
01.09.03.03 BISAGRA CAPUCHINA DE 4" X4" und 30 19.69 590.70 0.00 0.00 0% 30.00 590.70 100% 30.00 ### 590.70 100% 0.00 0.00 0%
01.09.03.04 MANIJA DE BRONCE PARA PUERTAS und 10 57.53 575.30 0.00 0.00 0% 2.00 115.06 20% 2.00 ### 115.06 20% 8.00 460.24 80%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.05 REVOQUES, ENLUCIDOS Y MLDURAS
01.11.05.01 TARRAJEO EN GENERAL
01.11.05.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 608.28 25.87 15,736.20 506.90 13,113.39 83% 101.38 2,622.82 17% 608.28 ### 15,736.20 100% 0.00 0.00 0%
01.11.05.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 587.56 32.01 18,807.80 448.36 14,351.93 76% 139.20 4,455.87 24% 587.56 ### 18,807.80 100% 0.00 0.00 0%
01.11.05.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 292.02 34.26 10,004.61 282.00 9,661.46 97% 10.02 343.15 3% 292.02 ### 10,004.61 100% 0.00 0.00 0%
01.11.05.01.04 EJECUCION DE BRUÑAS m 342 8.22 2,811.24 244.40 2,008.97 71% 97.60 802.27 29% 342.00 ### 2,811.24 100% 0.00 0.00 0%
01.11.05.01.05 VESTIDURA DE DERRAMES m 241.78 22.02 5,324.00 205.78 4,531.28 85% 36.00 792.72 15% 241.78 ### 5,324.00 100% 0.00 0.00 0%
01.11.05.01.06 TARRAJEO CON IMPERMEABILIZANTES m2 266.93 31.17 8,320.21 0.00 0.00 0% 266.93 8,320.21 100% 266.93 ### 8,320.21 100% 0.00 0.00 0%
01.11.06 CIELO RASOS
01.11.06.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 463.01 44.01 20,377.07 386.87 17,026.15 84% 76.14 3,350.92 16% 463.01 ### 20,377.07 100% 0.00 0.00 0%
01.11.07 PISOS Y PAVIMENTOS
01.11.07.01 CONTRAPISOS
01.11.07.01.01 CONTRAPISO DE 48 MM. m2 454.39 35.84 16,285.34 180.69 6,475.75 40% 273.71 9,809.59 60% 454.39 ### 16,285.34 100% 0.00 0.00 0%
01.11.07.02 PISOS
01.11.07.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 333.45 63.25 21,090.71 165.07 10,440.68 50% 84.06 5,316.80 25% 249.13 ### 15,757.47 75% 84.32 5,333.24 25%
01.11.07.03 VEREDAS Y RAMPAS
01.11.07.03.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 108.41 59.66 6,467.74 0.00 0.00 0% 65.24 3,892.22 60% 65.24 ### 3,892.22 60% 43.17 2,575.52 40%
01.11.08 CONTRAZOCALOS
01.11.08.01 CONTRAZOCALOS DE CEMENTO Y CERAMICO
01.11.08.01.02 ZOCALO DE MAYOLICA DE COLOR 20X30 1RA m2 186.6 96.43 17,993.84 0.00 0.00 0% 186.60 17,993.84 100% 186.60 ### 17,993.84 100% 0.00 0.00 0%
01.11.10 CARPINTERIA DE MADERA
01.11.10.01 PUERTAS
01.11.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 21.6 565.23 12,208.97 10.80 6,104.48 50% 10.80 6,104.48 50% 21.60 ### 12,208.97 100% 0.00 0.00 0%
01.11.12 CERRAJERIA
01.11.12.01 BISAGRAS
01.11.12.01.01 BISAGRA CAPUCHINA DE 4" X4" und 27 19.69 531.63 0.00 0.00 0% 27.00 531.63 100% 27.00 ### 531.63 100% 0.00 0.00 0%
01.11.12.02 CERRADURAS
01.11.12.02.01 CERRADURA PARA PUERTA PRINCIPAL PESADA pza 6 105.06 630.36 0.00 0.00 0% 6.00 630.36 100% 6.00 ### 630.36 100% 0.00 0.00 0%
01.11.12.02.02 MANIJA DE BRONCE PARA PUERTAS und 6 57.53 345.18 0.00 0.00 0% 6.00 345.18 100% 6.00 ### 345.18 100% 0.00 0.00 0%
01.11.15 INSTALACIONES SANITARIAS
01.11.15.02 SUMIDEROS DE BRONCE 4" pza 1 102.56 102.56 0.00 0.00 0% 1.00 102.56 100% 1.00 ### 102.56 100% 0.00 0.00 0%
01.11.15.03 CAJA DE REGISTRO 12" X 24" pza 1 224.99 224.99 0.00 0.00 0% 1.00 224.99 100% 1.00 ### 224.99 100% 0.00 0.00 0%
01.11.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.11.16.03 VALVULA COMPUERTA DE BRONCE 1/2" pza 1 115.64 115.64 0.00 0.00 0% 1.00 115.64 100% 1.00 ### 115.64 100% 0.00 0.00 0%
01.11.16.04 CAJA PARA MEDIDOR 12"X12" pza 1 198.46 198.46 0.00 0.00 0% 1.00 198.46 100% 1.00 ### 198.46 100% 0.00 0.00 0%
01.11.16.05 ACCESORIOS PVC GLB 1 33.53 33.53 0.00 0.00 0% 1.00 33.53 100% 1.00 ### 33.53 100% 0.00 0.00 0%
01.11.19.02 TABLEROS Y CUCHILLAS
01.11.19.02.02 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 0.00 0.00 0% 1.00 2,007.28 100% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.12.05.01 MURO DE LADRILLO KK SOGA
01.12.05.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 100.24 63.52 6,367.24 11.76 747.00 12% 28.26 1,795.08 28% 40.02 ### 2,542.07 40% 60.22 3,825.17 60%
01.12.06 REVOQUES, ENLUCIDOS Y MLDURAS
01.12.06.01 TARRAJEO EN GENERAL
01.12.06.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 208.08 25.87 5,383.03 122.19 3,161.06 59% 85.89 2,221.97 41% 208.08 ### 5,383.03 100% 0.00 0.00 0%
01.12.06.01.04 TARRAJEO PRIMARIO RAYADO m2 58.28 43.98 2,563.15 0.00 0.00 0% 58.28 2,563.15 100% 58.28 ### 2,563.15 100% 0.00 0.00 0%
01.12.06.01.06 VESTIDURA DE DERRAMES m 47.96 22.02 1,056.08 0.00 0.00 0% 47.96 1,056.08 100% 47.96 ### 1,056.08 100% 0.00 0.00 0%
01.12.07 PISOS Y PAVIMENTOS
01.12.07.01 CONTRAPISOS
01.12.07.01.01 CONTRAPISO DE 48 MM. m2 47 35.84 1,684.48 0.00 0.00 0% 47.00 1,684.48 100% 47.00 ### 1,684.48 100% 0.00 0.00 0%
01.12.07.03 VEREDAS Y RAMPAS
01.12.07.03.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 40.76 59.66 2,431.74 0.00 0.00 0% 15.57 928.91 38% 15.57 ### 928.91 38% 25.19 1,502.84 62%
01.12.08 CONTRAZOCALOS
01.12.08.01 CONTRAZOCALOS DE CEMENTO
01.12.08.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 28.9 15.69 453.44 14.98 235.04 52% 13.92 218.40 48% 28.90 ### 453.44 100% 0.00 0.00 0%
01.12.10 CARPINTERIA DE MADERA
01.12.10.01 PUERTAS
01.12.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 5.58 565.23 3,153.98 2.79 1,576.99 50% 2.79 1,576.99 50% 5.58 ### 3,153.98 100% 0.00 0.00 0%
01.12.11 CARPINTERIA METALICA Y ALUMINIO
01.12.12 CERRAJERIA
01.12.12.01 BISAGRAS
01.12.12.01.01 BISAGRA CAPUCHINA DE 4" X4" und 24 19.69 472.56 0.00 0.00 0% 24.00 472.56 100% 24.00 ### 472.56 100% 0.00 0.00 0%
01.12.12.02 CERRADURAS
01.12.12.02.01 CERRADURA PARA PUERTA PRINCIPAL PESADA pza 2 105.06 210.12 0.00 0.00 0% 2.00 210.12 100% 2.00 ### 210.12 100% 0.00 0.00 0%
01.12.12.02.02 MANIJA DE BRONCE PARA PUERTAS und 2 57.53 115.06 0.00 0.00 0% 2.00 115.06 100% 2.00 ### 115.06 100% 0.00 0.00 0%
01.12.14 APARATOS SANITARIOS Y ACCESORIOS
01.12.14.03 URINARIO CONSTRUIDO EN OBRA und 1 1,761.77 1,761.77 0.00 0.00 0% 1.00 1,761.77 100% 1.00 ### 1,761.77 100% 0.00 0.00 0%
01.12.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.12.16.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2". pto 26 57.79 1,502.54 0.00 0.00 0% 26.00 1,502.54 100% 26.00 ### 1,502.54 100% 0.00 0.00 0%
01.12.16.02 TUBERIA PVC - SAP DE 1/2" m 35.53 19.48 692.12 0.00 0.00 0% 35.53 692.12 100% 35.53 ### 692.12 100% 0.00 0.00 0%
01.12.16.03 VALVULA COMPUERTA DE BRONCE 1/2" pza 4 115.64 462.56 0.00 0.00 0% 4.00 462.56 100% 4.00 ### 462.56 100% 0.00 0.00 0%
01.12.16.04 CAJA PARA MEDIDOR 12"X12" pza 1 188.20 188.20 0.00 0.00 0% 1.00 188.20 100% 1.00 ### 188.20 100% 0.00 0.00 0%
01.12.16.05 TUBERIA PVC - SAP DE 3/4" m 5.6 22.62 126.67 0.00 0.00 0% 5.60 126.67 100% 5.60 ### 126.67 100% 0.00 0.00 0%
01.12.16.06 VALVULA COMPUERTA DE BRONCE 3/4". pza 1 62.66 62.66 0.00 0.00 0% 1.00 62.66 100% 1.00 ### 62.66 100% 0.00 0.00 0%
01.12.16.07 ACCESORIOS PVC GLB 1 30.03 30.03 0.00 0.00 0% 1.00 30.03 100% 1.00 ### 30.03 100% 0.00 0.00 0%
01.12.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.12.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 2 140.38 280.76 0.00 0.00 0% 2.00 280.76 100% 2.00 ### 280.76 100% 0.00 0.00 0%
01.12.19.02 TABLEROS Y CUCHILLAS
01.12.19.02.01 TABLEROS DE DISTRIBUCION CAJA METALICA TD-3 und 1 343.18 343.18 0.00 0.00 0% 1.00 343.18 100% 1.00 ### 343.18 100% 0.00 0.00 0%
01.12.19.02.02 POZO-CONEXION A TIERRA P/TOMACORRIENTES und 1 2,007.28 2,007.28 0.00 0.00 0% 1.00 2,007.28 100% 1.00 ### 2,007.28 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.03 OBRAS DE CONCRETO ARMADO
01.14.01.03.01 TRIBUNAS
01.14.01.03.01.03 CONCRETO EN TRIBUNAS F'C=175 KG/CM2 m3 22.33 413.40 9,231.22 12.73 5,263.41 57% 9.60 3,967.81 43% 22.33 ### 9,231.22 100% 0.00 0.00 0%
01.14.01.03.01.04 ENCOFRADO Y DESENCOFRADO EN TRIBUNA m2 221.56 62.00 13,736.72 160.96 9,979.27 73% 60.60 3,757.45 27% 221.56 ### 13,736.72 100% 0.00 0.00 0%
01.14.01.03.01.05 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS Y VIGAS kg 479.54 5.19 2,488.81 320.70 1,664.46 67% 158.84 824.35 33% 479.54 ### 2,488.81 100% 0.00 0.00 0%
01.14.01.03.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS m2 40.04 77.61 3,107.50 26.54 2,059.77 66% 13.50 1,047.74 34% 40.04 ### 3,107.50 100% 0.00 0.00 0%
01.14.01.03.01.07 CONCRETO PARA COLUMNAS Y VIGAS F'C=210 KG/CM2 m3 3.99 498.90 1,990.61 2.45 1,224.05 61% 1.54 766.56 39% 3.99 ### 1,990.61 100% 0.00 0.00 0%
01.14.01.03.01.08 TARRAJEO PULIDO EN SUPEERF. DE TRIBUNA m2 151.2 55.17 8,341.70 75.60 4,170.85 50% 75.60 4,170.85 50% 151.20 ### 8,341.70 100% 0.00 0.00 0%
01.14.01.03.01.10 CURADO DE TRIBUNA CON AGUA m2 190.03 0.42 79.81 170.00 71.40 89% 20.03 8.41 11% 190.03 ### 79.81 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.03 PISOS Y PAVIMENTOS
01.15.03.02 PISOS ADOQUINADOS
01.15.03.02.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 295.5 29.42 8,693.61 0.00 0.00 0% 77.08 2,267.69 26% 77.08 ### 2,267.69 26% 218.42 6,425.92 74%
01.15.04 ASTA DE BANDERA
01.15.04.02 EXCAVACION MANUAL m3 0.56 42.46 23.78 0.00 0.00 0% 0.56 23.78 100% 0.56 ### 23.78 100% 0.00 0.00 0%
01.15.04.03 REFINE Y NIVELACION EN TERRENO m2 2.25 6.74 15.17 0.00 0.00 0% 2.25 15.17 100% 2.25 ### 15.17 100% 0.00 0.00 0%
01.15.04.04 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 2.25 22.56 50.76 0.00 0.00 0% 2.25 50.76 100% 2.25 ### 50.76 100% 0.00 0.00 0%
01.15.04.05 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 0.7 17.69 12.38 0.00 0.00 0% 0.70 12.38 100% 0.70 ### 12.38 100% 0.00 0.00 0%
01.15.04.06 TARRAJEO PULIDO EN SUPEERF. DE PEDESTAL m2 3 55.17 165.51 0.00 0.00 0% 3.00 165.51 100% 3.00 ### 165.51 100% 0.00 0.00 0%
01.15.04.07 PEDESTAL 1.5X1.5X0.6, CONCRETO F'C=175 KG/CM2 m3 0.98 413.67 405.40 0.00 0.00 0% 0.98 405.40 100% 0.98 ### 405.40 100% 0.00 0.00 0%
01.15.04.08 ENCOFRADO Y DESENCOFRADO m2 3 62.00 186.00 0.00 0.00 0% 3.00 186.00 100% 3.00 ### 186.00 100% 0.00 0.00 0%
01.15.06 INSTALACIONES SANITARIAS EXTERIORES
01.15.06.01 SISTEMA DE AGUA FRIA
01.15.06.01.01 TRABAJOS PRELIMINARES
01.15.06.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 98.36 10.08 991.47 10.00 100.80 10% 88.36 890.67 90% 98.36 ### 991.47 100% 0.00 0.00 0%
01.15.06.01.02 MOVIMIENTO DE TIERRAS
01.15.06.01.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 31.48 42.46 1,336.64 3.20 135.87 10% 28.28 1,200.77 90% 31.48 ### 1,336.64 100% 0.00 0.00 0%
01.15.06.01.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 98.36 6.74 662.95 10.00 67.40 10% 88.36 595.55 90% 98.36 ### 662.95 100% 0.00 0.00 0%
01.15.06.01.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.93 136.53 536.56 0.40 54.61 10% 3.53 481.95 90% 3.93 ### 536.56 100% 0.00 0.00 0%
01.15.06.01.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 98.36 5.75 565.57 10.00 57.50 10% 88.36 508.07 90% 98.36 ### 565.57 100% 0.00 0.00 0%
01.15.06.01.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 11.8 139.08 1,641.14 1.20 166.90 10% 10.60 1,474.25 90% 11.80 ### 1,641.14 100% 0.00 0.00 0%
01.15.06.01.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 15.74 67.32 1,059.62 1.60 107.71 10% 14.14 951.90 90% 15.74 ### 1,059.62 100% 0.00 0.00 0%
01.15.06.01.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 20.46 17.69 361.94 2.08 36.80 10% 18.38 325.14 90% 20.46 ### 361.94 100% 0.00 0.00 0%
01.15.06.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 20.46 8.47 173.30 2.08 17.62 10% 18.38 155.68 90% 20.46 ### 173.30 100% 0.00 0.00 0%
01.15.06.01.03 REDES DE ALIMENTACION EXTERIORES
01.15.06.01.03.01 RED DE ALIMENTACION TUBERIA PVC CLASE 10 DE 1/2" m 28.37 18.21 516.62 0.00 0.00 0% 28.37 516.62 100% 28.37 ### 516.62 100% 0.00 0.00 0%
01.15.06.01.03.02 RED DE ALIMENTACION TUBERIA PVC CLASE 10 DE 3/4" m 69.99 19.20 1,343.81 10.00 192.00 14% 59.99 1,151.81 86% 69.99 ### 1,343.81 100% 0.00 0.00 0%
01.15.06.01.03.03 PRUEBA HIDRAULICA+DESINFECCION m 98.36 1.97 193.77 10.00 19.70 10% 88.36 174.07 90% 98.36 ### 193.77 100% 0.00 0.00 0%
01.15.06.01.04 ACCESORIO DE REDES
01.15.06.01.04.01 CODO PVC 90° SAP C-10 DE 1/2" und 3 10.07 30.21 0.00 0.00 0% 3.00 30.21 100% 3.00 ### 30.21 100% 0.00 0.00 0%
01.15.06.01.05 VALVULAS Y LLAVES
01.15.06.01.05.01 VALVULA DE COMPUERTA DE BRONCE PESADA Ø1/2" und 2 111.23 222.46 0.00 0.00 0% 2.00 222.46 100% 2.00 ### 222.46 100% 0.00 0.00 0%
01.15.06.01.05.02 VALVULA DE COMPUERTA DE BRONCE PESADA Ø3/4" und 1 126.04 126.04 0.00 0.00 0% 1.00 126.04 100% 1.00 ### 126.04 100% 0.00 0.00 0%
01.15.06.01.06 CAJA DE CONCRETO PARA VALVULA
01.15.06.01.06.01 MOVIMIENTO DE TIERRAS
01.15.06.01.06.01.01 EXCAVACION PARA ESTRUCTURAS m3 0.74 42.46 31.42 0.25 10.62 34% 0.49 20.81 66% 0.74 ### 31.42 100% 0.00 0.00 0%
01.15.06.01.06.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 0.96 17.69 16.98 0.32 5.66 33% 0.64 11.32 67% 0.96 ### 16.98 100% 0.00 0.00 0%
01.15.06.01.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 0.96 8.47 8.13 0.32 2.71 33% 0.64 5.42 67% 0.96 ### 8.13 100% 0.00 0.00 0%
01.15.06.01.06.02 CONCRETO ARMADO
01.15.06.01.06.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA VALVULA kg 39.45 5.19 204.75 13.15 68.25 33% 26.30 136.50 67% 39.45 ### 204.75 100% 0.00 0.00 0%
01.15.06.01.06.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE VALVULA m2 4.26 62.00 264.12 1.42 88.04 33% 2.84 176.08 67% 4.26 ### 264.12 100% 0.00 0.00 0%
01.15.06.01.06.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 0.29 413.67 119.96 0.10 41.37 34% 0.19 78.60 66% 0.29 ### 119.96 100% 0.00 0.00 0%
01.15.06.01.07 VARIOS
01.15.06.01.07.02 SALIDA DE HIDRANTES pto 2 331.07 662.14 0.00 0.00 0% 2.00 662.14 100% 2.00 ### 662.14 100% 0.00 0.00 0%
01.15.06.02 SISTEMA DE DESAGUE
01.15.06.02.01 TRABAJOS PRELIMINARES
01.15.06.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 68.27 10.08 688.16 10.00 100.80 15% 58.27 587.36 85% 68.27 ### 688.16 100% 0.00 0.00 0%
01.15.06.02.02 MOVIMIENTO DE TIERRAS
01.15.06.02.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 27.31 42.46 1,159.58 4.00 169.84 15% 23.31 989.74 85% 27.31 ### 1,159.58 100% 0.00 0.00 0%
01.15.06.02.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 68.27 6.74 460.14 10.00 67.40 15% 58.27 392.74 85% 68.27 ### 460.14 100% 0.00 0.00 0%
01.15.06.02.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.41 136.53 465.57 0.50 68.27 15% 2.91 397.30 85% 3.41 ### 465.57 100% 0.00 0.00 0%
01.15.06.02.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 68.27 5.75 392.55 10.00 57.50 15% 58.27 335.05 85% 68.27 ### 392.55 100% 0.00 0.00 0%
01.15.06.02.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 10.24 139.08 1,424.18 1.50 208.62 15% 8.74 1,215.56 85% 10.24 ### 1,424.18 100% 0.00 0.00 0%
01.15.06.02.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 13.65 67.32 918.92 2.00 134.64 15% 11.65 784.28 85% 13.65 ### 918.92 100% 0.00 0.00 0%
01.15.06.02.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 17.75 17.69 314.00 2.60 45.99 15% 15.15 268.00 85% 17.75 ### 314.00 100% 0.00 0.00 0%
01.15.06.02.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 17.75 8.47 150.34 2.60 22.02 15% 15.15 128.32 85% 17.75 ### 150.34 100% 0.00 0.00 0%
01.15.06.02.03 INSTALACION DE TUBERIA COLECTORA
01.15.06.02.03.01 RED COLECTORA CON TUBERIA PVC-SAL Ø 4' m 68.27 50.01 3,414.18 10.00 500.10 15% 58.27 2,914.08 85% 68.27 ### 3,414.18 100% 0.00 0.00 0%
01.15.06.02.03.02 PRUEBA HIDRAULICA DE TUBERIA EN ZANJA m 68.27 1.86 126.98 10.00 18.60 15% 58.27 108.38 85% 68.27 ### 126.98 100% 0.00 0.00 0%
01.15.06.02.04 CAJA DE REGISTRO
01.15.06.02.04.01 MOVIMIENTO DE TIERRAS
01.15.06.02.04.01.01 EXCAVACION DE PARA ESTRUTURAS m3 2.02 42.46 85.77 0.44 18.68 22% 0.48 20.38 24% 0.92 ### 39.06 46% 1.10 46.71 54%
01.15.06.02.04.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 2.63 17.69 46.52 0.57 10.08 22% 0.62 10.97 24% 1.19 ### 21.05 45% 1.44 25.47 55%
01.15.06.02.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 2.63 8.47 22.28 0.57 4.83 22% 0.62 5.25 24% 1.19 ### 10.08 45% 1.44 12.20 55%
01.15.06.02.04.02 CONCRETO ARMADO
01.15.06.02.04.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA DE REGISTRO kg 114.11 5.19 592.23 19.02 98.71 17% 57.06 296.14 50% 76.08 ### 394.86 67% 38.03 197.38 33%
01.15.06.02.04.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE REGISTRO m2 19.03 62.00 1,179.86 2.94 182.28 15% 8.96 555.52 47% 11.90 ### 737.80 63% 7.13 442.06 37%
01.15.06.02.04.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 3.01 413.67 1,245.15 0.51 210.97 17% 1.18 488.13 39% 1.69 ### 699.10 56% 1.32 546.04 44%
01.15.07 INSTALACIONES ELECTRICAS EXTERIORES
01.15.07.01 TRABAJOS PRELIMINARES
01.15.07.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 412.56 10.08 4,158.60 0.00 0.00 0% 412.56 4,158.60 100% 412.56 ### 4,158.60 100% 0.00 0.00 0%
01.15.07.04 TABLEROS Y CUCHILLAS
01.15.07.04.01 TABLEROS DISTRIBUCION CAJA METALICA CON 08 POLOS und 1 417.51 417.51 0.00 0.00 0% 1.00 417.51 100% 1.00 ### 417.51 100% 0.00 0.00 0%
01.15.07.04.02 TABLEROS DISTRIBUCION CAJA METALICA CON 04 POLOS und 6 374.26 2,245.56 0.00 0.00 0% 6.00 2,245.56 100% 6.00 ### 2,245.56 100% 0.00 0.00 0%
01.15.07.04.03 TABLEROS DISTRIBUCION CAJA METALICA CON 04 POLOS-ALUMBRADO EXT und 1 374.26 374.26 0.00 0.00 0% 1.00 374.26 100% 1.00 ### 374.26 100% 0.00 0.00 0%
01.15.07.06 SISTEMA PUESTA TIERRA
01.15.07.06.01 POZO PUESTA A TIERRA P-1 ( R<15 Ohms) und 1 2,007.28 2,007.28 0.00 0.00 0% 1.00 2,007.28 100% 1.00 ### 2,007.28 100% 0.00 0.00 0%
03 COMPONENTE 03: FORTALECIMIENTO Y CAPACITACION
03.01 FORTALECIMIENTO DE CAPACIDADES CON UN CONSULTOR EN DISEÑO CURRICULAR Y ENFOQUE PEDAGOGICO
03.01.01 CAPACITACION EN PROYECTO EDUCATIVO NACIONAL-PEN und 2 1,346.99 2,693.98 0.00 0.00 0% 2.00 2,693.98 100% 2.00 ### 2,693.98 100% 0.00 0.00 0%
03.01.02 CAPACITACION EN PROYECTO EDUCATIVO REGIONAL-PER und 2 1,046.99 2,093.98 0.00 0.00 0% 2.00 2,093.98 100% 2.00 ### 2,093.98 100% 0.00 0.00 0%
03.01.03 CAPACITACION EN DIVERSIFICACION CURRICULAR und 2 1,121.99 2,243.98 0.00 0.00 0% 2.00 2,243.98 100% 2.00 ### 2,243.98 100% 0.00 0.00 0%
03.01.04 CAPACITACION EN ELABORACION DE MATERIALES EDUCATIVOS und 2 1,121.99 2,243.98 0.00 0.00 0% 2.00 2,243.98 100% 2.00 ### 2,243.98 100% 0.00 0.00 0%
03.01.05 CAPACITACION EN PREPARACION PARA LA EDUCACION EN SALUD und 2 1,593.99 3,187.98 0.00 0.00 0% 2.00 3,187.98 100% 2.00 ### 3,187.98 100% 0.00 0.00 0%
03.02 CAPACITACION EN GERENCIA EDUCATIVA
03.02.01 CAPACITACION EN GERENCIA EDUCATIVA und 2 936.00 1,872.00 0.00 0.00 0% 2.00 1,872.00 100% 2.00 ### 1,872.00 100% 0.00 0.00 0%
03.02.02 CAPACITACION EN LIDERAZGO, CALIDAD Y COMPETENCIAS DOCENTES und 2 1,185.99 2,371.98 0.00 0.00 0% 2.00 2,371.98 100% 2.00 ### 2,371.98 100% 0.00 0.00 0%
03.02.03 CAPACITACION PARA LA PAZ Y RESOLUCION DE CONFILCTOS und 2 1,408.00 2,816.00 0.00 0.00 0% 2.00 2,816.00 100% 2.00 ### 2,816.00 100% 0.00 0.00 0%
03.02.04 CAPACITACION EN ELABORACION DE LINEA BASE PARA EVALUACION und 2 1,421.99 2,843.98 0.00 0.00 0% 2.00 2,843.98 100% 2.00 ### 2,843.98 100% 0.00 0.00 0%
03.03 CAPACITACION APAFA
03.03.01 ESCUELA DE PADRES GLB 2 936.00 1,872.00 0.00 0.00 0% 2.00 1,872.00 100% 2.00 ### 1,872.00 100% 0.00 0.00 0%
04 COMPONENTE 04: MITIGACION AMBIENTAL
04.01 MANEJO AMBIENTAL Y PLAN DE CIERRE
04.01.01 CONTENEDORES DE RESIDUOS SOLIDOS und 3 170.09 510.27 0.00 0.00 0% 3.00 510.27 100% 3.00 ### 510.27 100% 0.00 0.00 0%
04.01.02 TACHOS DE BASURA METALICOS und 10 572.41 5,724.10 0.00 0.00 0% 10.00 5,724.10 100% 10.00 ### 5,724.10 100% 0.00 0.00 0%
04.01.03 INDUCCION AL PERSONAL EN EL MANEJO DE RR.SS und 1 9,330.00 9,330.00 0.00 0.00 0% 1.00 9,330.00 100% 1.00 ### 9,330.00 100% 0.00 0.00 0%
04.01.04 PROGRAMA DE SENSIBILIZACION A LA POBLACION EN TEMAS DE RR.SS und 1 9,240.00 9,240.00 0.00 0.00 0% 1.00 9,240.00 100% 1.00 ### 9,240.00 100% 0.00 0.00 0%
04.01.05 LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und 2 480.62 961.24 0.00 0.00 0% 2.00 961.24 100% 2.00 ### 961.24 100% 0.00 0.00 0%
COSTO DIRECTO 2,278,432.36 909,335.24 39.91% 196,347.64 8.62% ### 1,105,682.88 48.53% 1,172,749.41 51.47%
GASTOS GENERALES (11.13 %CD) 253,654.58 101,234.98 21,859.09 ### 123,094.07 130,560.52
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 30,857.30 6,662.84 37,520.14 39,795.98
SUB TOTAL 2,609,403.06 1,041,427.52 39.91% 224,869.57 8.62% 1,266,297.09 48.53% 1,343,105.91 51.47%
º

VALORIZACION PRINCIPAL N°- 05


( MES DEL 26 DE OCTUBRE AL 25 DE NOVIEMBRE 2019)
PLAZO DE EJECUCION: 06 MESES
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-
ACTIVIDAD: FECHA DE INICIO DE OBRA : 7/1/2019
CUSCO(QUISTO CENTRAL)"
FECHA DE TERMINO DE OBRA PR 12/27/2019
SUPERVISOR: ING. MARIO JOSEPH HUAYHUA BERROCAL MODALIDAD DE EJECUCION: ADM. DIRECTA
RESIDENTE : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.02 FLETE TERRESTRE
01.02.01 FLETE TERRESTRE A OBRA GLB 1 29,543.90 29,543.90 0.80 23,635.12 80% 0.20 5,908.78 20% 1.00 ### 29,543.90 100% 0.00 0.00 0%
01.02.02 MOVILIZACION Y DESMOVILIZACION GLB 1 13,499.20 13,499.20 0.80 10,799.36 80% 0.20 2,699.84 20% 1.00 ### 13,499.20 100% 0.00 0.00 0%
01.03 SEGURIDAD Y SALUD
01.03.01 CAPACITACION DE PLAN DE SEGURIDAD Y SALUD GLB 1 2,950.00 2,950.00 0.60 1,770.00 60% 0.40 1,180.00 40% 1.00 ### 2,950.00 100% 0.00 0.00 0%
01.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD D GLB 1 387.63 387.63 0.00 0.00 0% 0.80 310.10 80% 0.80 ### 310.10 80% 0.20 77.53 20%
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.04 REPOSICION DE PISOS 0.00
01.08.04.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 248.4 63.25 15,711.30 0.00 0.00 0% 104.00 6,578.00 42% 104.00 ### 6,578.00 42% 144.40 9,133.30 58%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.02 REPOSICION DE PISOS
01.09.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 208 63.25 13,156.00 0.00 0.00 0% 156.00 9,867.00 75% 156.00 ### 9,867.00 75% 52.00 3,289.00 25%
01.09.03 PUERTAS SS.HH.
01.09.03.01 PUERTAS DE MADERA TORNILLO APANELADA m2 4 565.23 2,260.92 0.00 0.00 0% 2.00 1,130.46 50% 2.00 ### 1,130.46 50% 2.00 1,130.46 50%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 1194.75 25.87 30,908.18 1,093.50 28,288.85 92% 10.13 262.06 1% 1,103.63 ### 28,550.91 92% 91.12 2,357.27 8%
01.10.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 121.13 34.26 4,149.91 108.38 3,713.10 89% 1.28 43.85 1% 109.66 ### 3,756.95 91% 11.47 392.96 9%
01.10.01.04 EJECUCION DE BRUÑAS m 642.6 8.22 5,282.17 578.10 4,751.98 90% 12.90 106.04 2% 591.00 ### 4,858.02 92% 51.60 424.15 8%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.03 OBRAS DE CONCRETO ARMADO
01.11.03.06 LOZA MASCIZA DE CONCRETO
01.11.03.06.01 CONCRETO EN LOSAS MACIZAS ESCALERA F'C=210 KG/CM2 m3 2.79 414.23 1,155.70 0.00 0.00 0% 2.79 1,155.70 100% 2.79 ### 1,155.70 100% 0.00 0.00 0%
01.11.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 27.88 93.30 2,601.20 0.00 0.00 0% 27.88 2,601.20 100% 27.88 ### 2,601.20 100% 0.00 0.00 0%
01.11.03.06.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS MACIZAS. kg 806.35 5.19 4,184.96 591.22 3,068.43 73% 215.13 1,116.53 27% 806.35 ### 4,184.96 100% 0.00 0.00 0%
01.11.03.08 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.11.03.08.02 ENCOFRADO Y DESENCOFRADO m2 308.25 47.77 14,725.10 247.28 11,812.35 80% 60.97 2,912.75 20% 308.25 ### 14,725.10 100% 0.00 0.00 0%
01.11.03.08.03 CONCRETO F'C=175 KG/CM2 m3 14.72 413.40 6,085.25 10.90 4,505.86 74% 3.82 1,579.39 26% 14.72 ### 6,085.25 100% 0.00 0.00 0%
01.11.04 MUROS Y TABIQUES DE ALBAÑILERIA
01.11.04.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 154.52 63.52 9,815.11 123.73 7,859.20 80% 30.79 1,955.91 20% 154.52 ### 9,815.11 100% 0.00 0.00 0%
01.11.04.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 205.44 23.16 4,757.99 0.00 0.00 0% 205.44 4,757.99 100% 205.44 ### 4,757.99 100% 0.00 0.00 0%
01.11.05 REVOQUES, ENLUCIDOS Y MLDURAS
01.11.05.01 TARRAJEO EN GENERAL
01.11.05.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 608.28 25.87 15,736.20 88.19 2,281.54 14% 418.70 10,831.85 69% 506.90 ### 13,113.39 83% 101.38 2,622.82 17%
01.11.05.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 587.56 32.01 18,807.80 0.00 0.00 0% 448.36 14,351.93 76% 448.36 ### 14,351.93 76% 139.20 4,455.87 24%
01.11.05.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 292.02 34.26 10,004.61 140.42 4,810.79 48% 141.58 4,850.67 48% 282.00 ### 9,661.46 97% 10.02 343.15 3%
01.11.05.01.04 EJECUCION DE BRUÑAS m 342 8.22 2,811.24 0.00 0.00 0% 244.40 2,008.97 71% 244.40 ### 2,008.97 71% 97.60 802.27 29%
01.11.05.01.05 VESTIDURA DE DERRAMES m 241.78 22.02 5,324.00 0.00 0.00 0% 205.78 4,531.28 85% 205.78 ### 4,531.28 85% 36.00 792.72 15%
01.11.06 CIELO RASOS
01.11.06.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 463.01 44.01 20,377.07 210.24 9,252.66 45% 176.63 7,773.49 38% 386.87 ### 17,026.15 84% 76.14 3,350.92 16%
01.11.07 PISOS Y PAVIMENTOS
01.11.07.01 CONTRAPISOS
01.11.07.01.01 CONTRAPISO DE 48 MM. m2 454.39 35.84 16,285.34 0.00 0.00 0% 180.69 6,475.75 40% 180.69 ### 6,475.75 40% 273.71 9,809.59 60%
01.11.07.02 PISOS
01.11.07.02.01 PISOS DE CERAMICO 30X30 ALTO TRANSITO m2 333.45 63.25 21,090.71 0.00 0.00 0% 165.07 10,440.68 50% 165.07 ### 10,440.68 50% 168.38 10,650.04 50%
01.11.08 CONTRAZOCALOS
01.11.08.01 CONTRAZOCALOS DE CEMENTO Y CERAMICO
01.11.08.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 89.3 15.69 1,401.12 0.00 0.00 0% 89.30 1,401.12 100% 89.30 ### 1,401.12 100% 0.00 0.00 0%
01.11.09 CUBIERTAS
01.11.10 CARPINTERIA DE MADERA
01.11.10.01 PUERTAS
01.11.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 21.6 565.23 12,208.97 0.00 0.00 0% 10.80 6,104.48 50% 10.80 ### 6,104.48 50% 10.80 6,104.48 50%
01.11.14 APARATOS SANITARIOS Y ACCESORIOS
01.11.14.01 LAVADERO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 3,572.01 3,572.01 0.00 0.00 0% 1.00 3,572.01 100% 1.00 ### 3,572.01 100% 0.00 0.00 0%
01.11.14.02 BANCA DE CONCRETO CONSTRUIDO EN OBRA SEGUN MODELO GLB 1 2,324.46 2,324.46 0.00 0.00 0% 1.00 2,324.46 100% 1.00 ### 2,324.46 100% 0.00 0.00 0%
01.11.16 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.11.16.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2". pto 1 57.79 57.79 0.00 0.00 0% 1.00 57.79 100% 1.00 ### 57.79 100% 0.00 0.00 0%
01.11.19 INSTALACIONES ELECTRICAS
01.11.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.11.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 36 140.38 5,053.68 14.00 1,965.32 39% 22.00 3,088.36 61% 36.00 ### 5,053.68 100% 0.00 0.00 0%
01.11.19.02 TABLEROS Y CUCHILLAS
01.11.19.02.01 TABLEROS DE DISTRIBUCION CAJA METALICA TD-1 und 1 343.18 343.18 0.00 0.00 0% 1.00 343.18 100% 1.00 ### 343.18 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.12.05.01 MURO DE LADRILLO KK SOGA
01.12.05.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 100.24 63.52 6,367.24 0.00 0.00 0% 11.76 747.00 12% 11.76 ### 747.00 12% 88.48 5,620.25 88%
01.12.06 REVOQUES, ENLUCIDOS Y MLDURAS
01.12.06.01 TARRAJEO EN GENERAL
01.12.06.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 208.08 25.87 5,383.03 0.00 0.00 0% 122.19 3,161.06 59% 122.19 ### 3,161.06 59% 85.89 2,221.97 41%
01.12.06.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 19.89 32.01 636.68 0.00 0.00 0% 19.89 636.68 100% 19.89 ### 636.68 100% 0.00 0.00 0%
01.12.06.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 53.58 34.26 1,835.65 0.00 0.00 0% 53.58 1,835.65 100% 53.58 ### 1,835.65 100% 0.00 0.00 0%
01.12.06.01.05 EJECUCION DE BRUÑAS m 216 8.22 1,775.52 0.00 0.00 0% 216.00 1,775.52 100% 216.00 ### 1,775.52 100% 0.00 0.00 0%
01.12.06.02 CIELO RASOS
01.12.06.02.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 76.67 44.01 3,374.25 0.00 0.00 0% 76.67 3,374.25 100% 76.67 ### 3,374.25 100% 0.00 0.00 0%
01.12.08 CONTRAZOCALOS
01.12.08.01 CONTRAZOCALOS DE CEMENTO
01.12.08.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 28.9 15.69 453.44 0.00 0.00 0% 14.98 235.04 52% 14.98 ### 235.04 52% 13.92 218.40 48%
01.12.10 CARPINTERIA DE MADERA
01.12.10.01 PUERTAS
01.12.10.01.01 PUERTAS DE MADERA TORNILLO APANELADA m2 5.58 565.23 3,153.98 0.00 0.00 0% 2.79 1,576.99 50% 2.79 ### 1,576.99 50% 2.79 1,576.99 50%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.08 PISOS Y PAVIMENTOS
01.13.08.01 PISOS
01.13.08.01.01 PISO DE CEMENTO PULIDO CON OCRE ROJO, E=2" S/COLOREAR m2 3 27.71 83.13 0.00 0.00 0% 3.00 83.13 100% 3.00 ### 83.13 100% 0.00 0.00 0%
01.13.08.02 VEREDAS Y RAMPAS
01.13.08.02.01 VEREDA DE CONCRETO F'C= 175 KG/CM2 E=4" m2 5.81 59.66 346.62 0.00 0.00 0% 5.81 346.62 100% 5.81 ### 346.62 100% 0.00 0.00 0%
01.13.08.02.02 JUNTAS DE DILATACION EN E=1" m 10.78 31.99 344.85 0.00 0.00 0% 10.78 344.85 100% 10.78 ### 344.85 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.02 MOVIMIENTO DE TIERRAS
01.14.01.02.01 EXCAVACIONES
01.14.01.02.01.01 EXCAVACION MANUAL P LOSA, TRIBUNA, /UÑA Y CUNETA m3 51.65 42.46 2,193.06 10.91 463.35 21% 10.91 463.35 21% 21.83 ### 926.71 42% 29.82 1,266.35 58%
01.14.01.02.01.02 REFINE Y NIVELACION EN TERRENO m2 119.4 6.74 804.76 27.28 183.88 23% 27.28 183.88 23% 54.56 ### 367.76 46% 64.84 437.00 54%
01.14.01.02.01.03 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 54.56 22.56 1,230.87 27.28 615.48 50% 27.28 615.40 50% 54.56 ### 1,230.87 100% 0.00 0.00 0%
01.14.01.02.01.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 64.56 17.69 1,142.07 13.64 241.31 21% 13.64 241.31 21% 27.28 ### 482.62 42% 37.28 659.45 58%
01.14.01.02.01.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 64.56 8.47 546.82 13.64 115.54 21% 13.64 115.54 21% 27.28 ### 231.08 42% 37.28 315.75 58%
01.14.01.03 OBRAS DE CONCRETO ARMADO
01.14.01.03.01 TRIBUNAS
01.14.01.03.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 16.86 192.96 3,253.31 8.43 1,626.85 50% 8.43 1,626.46 50% 16.86 ### 3,253.31 100% 0.00 0.00 0%
01.14.01.03.01.02 CONCRETO CICLOPEO FC=140KG/CM2 GRADAS m3 3.88 233.57 906.25 1.94 453.13 50% 1.94 453.13 50% 3.88 ### 906.25 100% 0.00 0.00 0%
01.14.01.03.01.03 CONCRETO EN TRIBUNAS F'C=175 KG/CM2 m3 22.33 413.40 9,231.22 6.37 2,631.70 29% 6.37 2,631.70 29% 12.73 ### 5,263.41 57% 9.60 3,967.81 43%
01.14.01.03.01.04 ENCOFRADO Y DESENCOFRADO EN TRIBUNA m2 221.56 62.00 13,736.72 80.48 4,989.64 36% 80.48 4,989.64 36% 160.96 ### 9,979.27 73% 60.60 3,757.45 27%
01.14.01.03.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS m2 40.04 77.61 3,107.50 20.02 1,553.75 50% 6.52 506.02 16% 26.54 ### 2,059.77 66% 13.50 1,047.74 34%
01.14.01.03.01.07 CONCRETO PARA COLUMNAS Y VIGAS F'C=210 KG/CM2 m3 3.99 498.90 1,990.61 1.99 994.56 50% 0.46 229.49 12% 2.45 ### 1,224.05 61% 1.54 766.56 39%
01.14.01.03.01.08 TARRAJEO PULIDO EN SUPEERF. DE TRIBUNA m2 151.2 55.17 8,341.70 0.00 0.00 0% 75.60 4,170.85 50% 75.60 ### 4,170.85 50% 75.60 4,170.85 50%
01.14.01.03.01.09 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 27.42 67.32 1,845.91 13.71 922.84 50% 13.71 922.84 50% 27.42 ### 1,845.67 100% 0.00 0.24 0%
01.14.01.03.01.10 CURADO DE TRIBUNA CON AGUA m2 190.03 0.42 79.81 85.00 35.70 45% 85.00 35.70 45% 170.00 ### 71.40 89% 20.03 8.41 11%
01.14.01.03.01.11 JUNTAS DE DILATACION EN TRIBUNAS m 29.7 31.99 950.10 14.85 475.05 50% 14.85 475.05 50% 29.70 ### 950.10 100% 0.00 0.00 0%
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.01 MOVIMIENTO DE TIERRAS
01.14.02.01.01 EXCAVACIONES
01.14.02.01.01.01 EXCAVACION MANUAL DE ZANJA P/CIMENTACION - ZAPATAS m3 63 39.80 2,507.40 47.25 1,880.55 75% 15.75 626.85 25% 63.00 ### 2,507.40 100% 0.00 0.00 0%
01.14.02.02 OBRAS DE CONCRETO SIMPLE
01.14.02.02.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 9 30.55 274.95 6.19 189.03 69% 2.81 85.92 31% 9.00 ### 274.95 100% 0.00 0.00 0%
01.14.02.03 OBRAS DE CONCRETO ARMADO
01.14.02.03.01 ZAPATAS
01.14.02.03.01.02 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 21.6 403.61 8,717.98 8.10 3,269.24 38% 13.50 5,448.74 63% 21.60 ### 8,717.98 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.01 TRABAJOS PRELIMINARES
01.15.01.03 TRAZO, NIVELES Y REPLANTEO
01.15.01.03.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 600.28 10.08 6,050.82 0.00 0.00 0% 600.28 6,050.82 100% 600.28 ### 6,050.82 100% 0.00 0.00 0%
01.15.02 MOVIMIENTO DE TIERRAS
01.15.02.01 CORTES
01.15.02.01.01 CORTE DE TERRENO m3 120.06 42.46 5,097.75 0.00 0.00 0% 120.06 5,097.75 100% 120.06 ### 5,097.75 100% 0.00 0.00 0%
01.15.02.02 EXCAVACIONES
01.15.02.02.01 EXCAVACION MANUAL m3 2.49 42.46 105.73 0.00 0.00 0% 2.49 105.73 100% 2.49 ### 105.73 100% 0.00 0.00 0%
01.15.02.03 RELLENOS
01.15.02.03.01 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 60.03 67.32 4,041.22 0.00 0.00 0% 60.03 4,041.22 100% 60.03 ### 4,041.22 100% 0.00 0.00 0%
01.15.02.04 ELIMINACION DE MATERIAL EXEDENTE
01.15.02.04.01 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 147.05 17.69 2,601.31 0.00 0.00 0% 147.05 2,601.31 100% 147.05 ### 2,601.31 100% 0.00 0.00 0%
01.15.02.04.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 147.05 8.47 1,245.51 0.00 0.00 0% 147.05 1,245.51 100% 147.05 ### 1,245.51 100% 0.00 0.00 0%
01.15.02.05 REFINE Y NIVELACION
01.15.02.05.01 REFINE Y NIVELACION EN TERRENO m2 600.28 6.74 4,045.89 0.00 0.00 0% 600.28 4,045.89 100% 600.28 ### 4,045.89 100% 0.00 0.00 0%
01.15.02.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 600.28 22.56 13,542.32 0.00 0.00 0% 600.28 13,542.32 100% 600.28 ### 13,542.32 100% 0.00 0.00 0%
01.15.04 ASTA DE BANDERA
01.15.04.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 2.25 10.08 22.68 0.00 0.00 0% 2.25 22.68 100% 2.25 ### 22.68 100% 0.00 0.00 0%
01.15.06 INSTALACIONES SANITARIAS EXTERIORES
01.15.06.01 SISTEMA DE AGUA FRIA
01.15.06.01.01 TRABAJOS PRELIMINARES
01.15.06.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 98.36 10.08 991.47 0.00 0.00 0% 10.00 100.80 10% 10.00 ### 100.80 10% 88.36 890.67 90%
01.15.06.01.02 MOVIMIENTO DE TIERRAS
01.15.06.01.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 31.48 42.46 1,336.64 0.00 0.00 0% 3.20 135.87 10% 3.20 ### 135.87 10% 28.28 1,200.77 90%
01.15.06.01.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 98.36 6.74 662.95 0.00 0.00 0% 10.00 67.40 10% 10.00 ### 67.40 10% 88.36 595.55 90%
01.15.06.01.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.93 136.53 536.56 0.00 0.00 0% 0.40 54.61 10% 0.40 ### 54.61 10% 3.53 481.95 90%
01.15.06.01.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 98.36 5.75 565.57 0.00 0.00 0% 10.00 57.50 10% 10.00 ### 57.50 10% 88.36 508.07 90%
01.15.06.01.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 11.8 139.08 1,641.14 0.00 0.00 0% 1.20 166.90 10% 1.20 ### 166.90 10% 10.60 1,474.25 90%
01.15.06.01.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADOm3 15.74 67.32 1,059.62 0.00 0.00 0% 1.60 107.71 10% 1.60 ### 107.71 10% 14.14 951.90 90%
01.15.06.01.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 20.46 17.69 361.94 0.00 0.00 0% 2.08 36.80 10% 2.08 ### 36.80 10% 18.38 325.14 90%
01.15.06.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 20.46 8.47 173.30 0.00 0.00 0% 2.08 17.62 10% 2.08 ### 17.62 10% 18.38 155.68 90%
01.15.06.01.03 REDES DE ALIMENTACION EXTERIORES
01.15.06.01.03.02 RED DE ALIMENTACION TUBERIA PVC CLASE 10 DE 3/4" m 69.99 19.20 1,343.81 0.00 0.00 0% 10.00 192.00 14% 10.00 ### 192.00 14% 59.99 1,151.81 86%
01.15.06.01.03.03 PRUEBA HIDRAULICA+DESINFECCION m 98.36 1.97 193.77 0.00 0.00 0% 10.00 19.70 10% 10.00 ### 19.70 10% 88.36 174.07 90%
01.15.06.01.04 ACCESORIO DE REDES
01.15.06.01.04.02 CODO PVC-SAP CLASE 10 R 3/4' x 90º und 3 11.25 33.75 0.00 0.00 0% 3.00 33.75 100% 3.00 ### 33.75 100% 0.00 0.00 0%
01.15.06.01.04.03 TEE PVC SAP C-10 DE 3/4” und 2 20.27 40.54 0.00 0.00 0% 2.00 40.54 100% 2.00 ### 40.54 100% 0.00 0.00 0%
01.15.06.01.06 CAJA DE CONCRETO PARA VALVULA
01.15.06.01.06.01 MOVIMIENTO DE TIERRAS
01.15.06.01.06.01.01 EXCAVACION PARA ESTRUCTURAS m3 0.74 42.46 31.42 0.00 0.00 0% 0.25 10.62 34% 0.25 ### 10.62 34% 0.49 20.81 66%
01.15.06.01.06.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 0.96 17.69 16.98 0.00 0.00 0% 0.32 5.66 33% 0.32 ### 5.66 33% 0.64 11.32 67%
01.15.06.01.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 0.96 8.47 8.13 0.00 0.00 0% 0.32 2.71 33% 0.32 ### 2.71 33% 0.64 5.42 67%
01.15.06.01.06.02 CONCRETO ARMADO
01.15.06.01.06.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA VALVULA kg 39.45 5.19 204.75 0.00 0.00 0% 13.15 68.25 33% 13.15 ### 68.25 33% 26.30 136.50 67%
01.15.06.01.06.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE VALVULA m2 4.26 62.00 264.12 0.00 0.00 0% 1.42 88.04 33% 1.42 ### 88.04 33% 2.84 176.08 67%
01.15.06.01.06.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 0.29 413.67 119.96 0.00 0.00 0% 0.10 41.37 34% 0.10 ### 41.37 34% 0.19 78.60 66%
01.15.06.01.07 VARIOS
01.15.06.01.07.03 EMPALME A RED EXISTENTE DE AGUA und 1 80.02 80.02 0.00 0.00 0% 1.00 80.02 100% 1.00 ### 80.02 100% 0.00 0.00 0%
01.15.06.02 SISTEMA DE DESAGUE
01.15.06.02.01 TRABAJOS PRELIMINARES
01.15.06.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 68.27 10.08 688.16 0.00 0.00 0% 10.00 100.80 15% 10.00 ### 100.80 15% 58.27 587.36 85%
01.15.06.02.02 MOVIMIENTO DE TIERRAS
01.15.06.02.02.01 EXCAVACION DE ZANJAS PARA REDES EXT. SANITARIA m3 27.31 42.46 1,159.58 0.00 0.00 0% 4.00 169.84 15% 4.00 ### 169.84 15% 23.31 989.74 85%
01.15.06.02.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m2 68.27 6.74 460.14 0.00 0.00 0% 10.00 67.40 15% 10.00 ### 67.40 15% 58.27 392.74 85%
01.15.06.02.02.03 ZARANDEO DE MATERIAL PARA CAMA DE APOYO m3 3.41 136.53 465.57 0.00 0.00 0% 0.50 68.27 15% 0.50 ### 68.27 15% 2.91 397.30 85%
01.15.06.02.02.04 RELLENO Y COMPACTADO DE CAMA DE APOYO H=10CM m 68.27 5.75 392.55 0.00 0.00 0% 10.00 57.50 15% 10.00 ### 57.50 15% 58.27 335.05 85%
01.15.06.02.02.05 RELLENO Y COMPACTADO CON MATERIAL PRESTAMO SOBRE CLAVE m3 10.24 139.08 1,424.18 0.00 0.00 0% 1.50 208.62 15% 1.50 ### 208.62 15% 8.74 1,215.56 85%
01.15.06.02.02.06 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADOm3 13.65 67.32 918.92 0.00 0.00 0% 2.00 134.64 15% 2.00 ### 134.64 15% 11.65 784.28 85%
01.15.06.02.02.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 17.75 17.69 314.00 0.00 0.00 0% 2.60 45.99 15% 2.60 ### 45.99 15% 15.15 268.00 85%
01.15.06.02.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 17.75 8.47 150.34 0.00 0.00 0% 2.60 22.02 15% 2.60 ### 22.02 15% 15.15 128.32 85%
01.15.06.02.03 INSTALACION DE TUBERIA COLECTORA
01.15.06.02.03.01 RED COLECTORA CON TUBERIA PVC-SAL Ø 4' m 68.27 50.01 3,414.18 0.00 0.00 0% 10.00 500.10 15% 10.00 ### 500.10 15% 58.27 2,914.08 85%
01.15.06.02.03.02 PRUEBA HIDRAULICA DE TUBERIA EN ZANJA m 68.27 1.86 126.98 0.00 0.00 0% 10.00 18.60 15% 10.00 ### 18.60 15% 58.27 108.38 85%
01.15.06.02.04 CAJA DE REGISTRO
01.15.06.02.04.01 MOVIMIENTO DE TIERRAS
01.15.06.02.04.01.01 EXCAVACION DE PARA ESTRUTURAS m3 2.02 42.46 85.77 0.00 0.00 0% 0.44 18.68 22% 0.44 ### 18.68 22% 1.58 67.09 78%
01.15.06.02.04.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 2.63 17.69 46.52 0.00 0.00 0% 0.57 10.08 22% 0.57 ### 10.08 22% 2.06 36.44 78%
01.15.06.02.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 2.63 8.47 22.28 0.00 0.00 0% 0.57 4.83 22% 0.57 ### 4.83 22% 2.06 17.45 78%
01.15.06.02.04.02 CONCRETO ARMADO
01.15.06.02.04.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA DE REGISTRO kg 114.11 5.19 592.23 0.00 0.00 0% 19.02 98.71 17% 19.02 ### 98.71 17% 95.09 493.52 83%
01.15.06.02.04.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE REGISTRO m2 19.03 62.00 1,179.86 0.00 0.00 0% 2.94 182.28 15% 2.94 ### 182.28 15% 16.09 997.58 85%
01.15.06.02.04.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 3.01 413.67 1,245.15 0.00 0.00 0% 0.51 210.97 17% 0.51 ### 210.97 17% 2.50 1,034.18 83%
01.15.06.02.05 VARIOS
01.15.06.02.05.01 EMPALME A RED DE ALCANTARILLADO EXISTENTE und 1 374.38 374.38 0.00 0.00 0% 1.00 374.38 100% 1.00 ### 374.38 100% 0.00 0.00 0%
COSTO DIRECTO 2,278,432.36 708,700.18 31.10% 200,635.06 8.81% ### 909,335.24 39.91% 1,369,097.05 60.09%
GASTOS GENERALES (11.13 %CD) 253,654.58 78,898.57 22,336.40 ### 101,234.97 152,419.62
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 24,048.97 6,808.33 30,857.30 46,458.82
SUB TOTAL 2,609,403.06 811,647.71 31.10% 229,779.80 8.81% 1,041,427.51 39.91% 1,567,975.50 60.09%
º

VALORIZACION PRINCIPAL N°- 04


( MES DEL 26 DE SETIEMBRE AL 25 DE OCTUBRE 2019)
PLAZO DE EJECUCION: 06 MESES
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-
ACTIVIDAD: FECHA DE INICIO DE OBRA : 7/1/2019
CUSCO(QUISTO CENTRAL)"
FECHA DE TERMINO DE OBRA PR 12/27/2019
SUPERVISOR: ING. MARIO JOSEPH HUAYHUA BERROCAL MODALIDAD DE EJECUCION: ADM. DIRECTA
RESIDENTE : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND VALORIZ. TOTAL
(S/.) (S/.) TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.02 FLETE TERRESTRE
01.02.01 FLETE TERRESTRE A OBRA GLB 1 29,543.90 29,543.90 0.60 17,726.34 60% 0.20 5,908.78 20% 0.80 ### 23,635.12 80% 0.20 5,908.78 20%
01.02.02 MOVILIZACION Y DESMOVILIZACION GLB 1 13,499.20 13,499.20 0.60 8,099.52 60% 0.20 2,699.84 20% 0.80 ### 10,799.36 80% 0.20 2,699.84 20%
01.03 SEGURIDAD Y SALUD
01.03.01 CAPACITACION DE PLAN DE SEGURIDAD Y SALUD GLB 1 2,950.00 2,950.00 0.40 1,180.00 40% 0.20 590.00 20% 0.60 ### 1,770.00 60% 0.40 1,180.00 40%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 1194.75 25.87 30,908.18 1,012.50 26,193.38 85% 81.00 2,095.47 7% 1,093.50 ### 28,288.85 92% 101.25 2,619.34 8%
01.10.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 89.1 32.01 2,852.09 47.25 1,512.47 53% 33.75 1,080.34 38% 81.00 ### 2,592.81 91% 8.10 259.28 9%
01.10.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 121.13 34.26 4,149.91 63.75 2,184.08 53% 44.63 1,529.02 37% 108.38 ### 3,713.10 89% 12.75 436.82 11%
01.10.01.04 EJECUCION DE BRUÑAS m 642.6 8.22 5,282.17 394.50 3,242.79 61% 183.60 1,509.19 29% 578.10 ### 4,751.98 90% 64.50 530.19 10%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.01 MOVIMIENTO DE TIERRAS
01.11.03 OBRAS DE CONCRETO ARMADO
01.11.03.03 COLUMNAS
01.11.03.03.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 24.75 498.90 12,347.78 19.61 9,784.56 79% 5.14 2,563.21 21% 24.75 ### 12,347.78 100% 0.00 0.00 0%
01.11.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 265.03 77.61 20,568.98 208.63 16,191.65 79% 56.40 4,377.33 21% 265.03 ### 20,568.98 100% 0.00 0.00 0%
01.11.03.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 8710.85 5.19 45,209.31 8,710.85 45,209.31 100% 0.00 0.00 0% 8,710.85 ### 45,209.31 100% 0.00 0.00 0%
01.11.03.04 VIGAS
01.11.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 31.73 415.22 13,174.93 17.14 7,116.04 54% 14.59 6,058.89 46% 31.73 ### 13,174.93 100% 0.00 0.00 0%
01.11.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 254.51 77.61 19,752.52 155.36 12,057.49 61% 99.15 7,695.03 39% 254.51 ### 19,752.52 100% 0.00 0.00 0%
01.11.03.04.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 3637.79 5.19 18,880.13 2,130.09 11,055.17 59% 1,507.70 7,824.96 41% 3,637.79 ### 18,880.13 100% 0.00 0.00 0%
01.11.03.05 LOSAS ALIGERADAS
01.11.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. m3 44.55 404.08 18,001.76 21.80 8,810.26 49% 22.75 9,191.51 51% 44.55 ### 18,001.76 100% 0.00 0.00 0%
01.11.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 509.12 93.30 47,500.90 205.44 19,167.55 40% 303.68 28,333.34 60% 509.12 ### 47,500.90 100% 0.00 0.00 0%
01.11.03.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS ALIGERADAS. kg 1906.24 5.19 9,893.39 1,098.07 5,698.99 58% 808.17 4,194.39 42% 1,906.24 ### 9,893.39 100% 0.00 0.00 0%
01.11.03.05.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 4240.97 4.81 20,399.07 1,711.32 8,231.43 40% 2,529.65 12,167.64 60% 4,240.97 ### 20,399.07 100% 0.00 0.00 0%
01.11.03.08 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.11.03.08.01 ACERO DE REFUERZO FY=4200 KG/CM2.. kg 999.72 5.19 5,188.55 999.72 5,188.55 100% 0.00 0% 999.72 ### 5,188.55 100% 0.00 0.00 0%
01.11.03.08.02 ENCOFRADO Y DESENCOFRADO m2 308.25 47.77 14,725.10 18.75 895.69 6% 228.53 10,916.66 74% 247.28 ### 11,812.35 80% 60.97 2,912.75 20%
01.11.03.08.03 CONCRETO F'C=175 KG/CM2 m3 14.72 413.40 6,085.25 4.46 1,842.94 30% 6.44 2,662.92 44% 10.90 ### 4,505.86 74% 3.82 1,579.39 26%
01.11.04 MUROS Y TABIQUES DE ALBAÑILERIA
01.11.04.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 154.52 63.52 9,815.11 36.87 2,342.11 24% 86.86 5,517.09 56% 123.73 ### 7,859.20 80% 30.79 1,955.91 20%
01.11.05 REVOQUES, ENLUCIDOS Y MLDURAS
01.11.05.01 TARRAJEO EN GENERAL
01.11.05.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 608.28 25.87 15,736.20 0.00 0.00 0% 88.19 2,281.54 14% 88.19 ### 2,281.54 14% 520.09 13,454.66 86%
01.11.05.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 292.02 34.26 10,004.61 0.00 0.00 0% 140.42 4,810.79 48% 140.42 ### 4,810.79 48% 151.60 5,193.82 52%
01.11.06 CIELO RASOS
01.11.06.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 463.01 44.01 20,377.07 0.00 0.00 0% 210.24 9,252.66 45% 210.24 ### 9,252.66 45% 252.77 11,124.41 55%
01.11.19 INSTALACIONES ELECTRICAS
01.11.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.11.19.01.01 CENTROS DE LUZ EN TECHOS pto 38 140.21 5,327.98 18.00 2,523.78 47% 20.00 2,804.20 53% 38.00 ### 5,327.98 100% 0.00 0.00 0%
01.11.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 36 140.38 5,053.68 0.00 0.00 0% 14.00 1,965.32 39% 14.00 ### 1,965.32 39% 22.00 3,088.36 61%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.02 MOVIMIENTO DE TIERRAS
01.12.02.03 RELLENOS
01.12.02.03.01 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO SELECCIONADO m3 4.7 67.32 316.40 0.00 0.00 0% 4.70 316.40 100% 4.70 ### 316.40 100% 0.00 0.00 0%
01.12.02.03.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 0.6 109.80 65.88 0.00 0.00 0% 0.60 65.88 100% 0.60 ### 65.88 100% 0.00 0.00 0%
01.12.03 OBRAS DE CONCRETO SIMPLE
01.12.03.03 SOBRECIMIENTOS CORRIDOS
01.12.03.03.01 SOBRECIMIENTO CORRIDO C-H 1:8 + 25% P.M. m3 6.75 279.29 1,885.21 0.00 0.00 0% 6.75 1,885.21 100% 6.75 ### 1,885.21 100% 0.00 0.00 0%
01.12.03.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS HASTA 0.60 M m2 25.68 57.69 1,481.48 0.00 0.00 0% 25.68 1,481.48 100% 25.68 ### 1,481.48 100% 0.00 0.00 0%
01.12.03.04 FALSO PISO
01.12.03.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 47.88 29.42 1,408.63 0.00 0.00 0% 47.88 1,408.63 100% 47.88 ### 1,408.63 100% 0.00 0.00 0%
01.12.04 OBRAS DE CONCRETO ARMADO
01.12.04.02 VIGAS DE CIMENTACION
01.12.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 3.46 398.47 1,378.71 0.00 0.00 0% 3.46 1,378.71 100% 3.46 ### 1,378.71 100% 0.00 0.00 0%
01.12.04.02.02 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION m2 28.48 70.68 2,012.97 0.00 0.00 0% 28.48 2,012.97 100% 28.48 ### 2,012.97 100% 0.00 0.00 0%
01.12.04.02.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGA DE CIMENTACION. kg 272.08 5.19 1,412.10 272.08 1,412.10 100% 0.00 0% 272.08 ### 1,412.10 100% 0.00 0.00 0%
01.12.04.03 COLUMNAS
01.12.04.03.01 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3 3.57 498.90 1,781.07 0.00 0.00 0% 3.57 1,781.07 100% 3.57 ### 1,781.07 100% 0.00 0.00 0%
01.12.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 42.18 77.61 3,273.59 0.00 0.00 0% 42.18 3,273.59 100% 42.18 ### 3,273.59 100% 0.00 0.00 0%
01.12.04.03.03 ACERO DE REFUERZO FY=4200 KG/CM2. kg 420.25 5.19 2,181.10 420.25 2,181.10 100% 0.00 0% 420.25 ### 2,181.10 100% 0.00 0.00 0%
01.12.04.04 VIGAS
01.12.04.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 4.87 415.22 2,022.12 0.00 0.00 0% 4.87 2,022.12 100% 4.87 ### 2,022.12 100% 0.00 0.00 0%
01.12.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 34.11 77.61 2,647.28 0.00 0.00 0% 34.11 2,647.28 100% 34.11 ### 2,647.28 100% 0.00 0.00 0%
01.12.04.04.03 ACERO DE REFUERZO FY=4200 KG/CM2. EN VIGAS. kg 448.24 5.19 2,326.37 0.00 0.00 0% 448.24 2,326.37 100% 448.24 ### 2,326.37 100% 0.00 0.00 0%
01.12.04.05 LOSAS ALIGERADAS
01.12.04.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. m3 7.5 404.08 3,030.60 0.00 0.00 0% 7.50 3,030.60 100% 7.50 ### 3,030.60 100% 0.00 0.00 0%
01.12.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 22.34 93.30 2,084.32 0.00 0.00 0% 22.34 2,084.32 100% 22.34 ### 2,084.32 100% 0.00 0.00 0%
01.12.04.05.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN LOSAS ALIGERADAS. kg 363.83 5.19 1,888.28 0.00 0.00 0% 363.83 1,888.28 100% 363.83 ### 1,888.28 100% 0.00 0.00 0%
01.12.04.05.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 843.55 4.81 4,057.48 0.00 0.00 0% 843.55 4,057.48 100% 843.55 ### 4,057.48 100% 0.00 0.00 0%
01.12.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.12.05.01 MURO DE LADRILLO KK SOGA
01.12.05.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 100.24 63.52 6,367.24 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 100.24 6,367.24 100%
01.12.15 INSTALACIONES SANITARIAS
01.12.15.01 SALIDA DE PVC SAL PARA DESAGUE DE 4" pto 10 87.28 872.80 0.00 0.00 0% 10.00 872.80 100% 10.00 ### 872.80 100% 0.00 0.00 0%
01.12.15.02 SALIDA DE PVC SAL PARA DESAGUE DE 2" pto 7 76.53 535.71 0.00 0.00 0% 7.00 535.71 100% 7.00 ### 535.71 100% 0.00 0.00 0%
01.12.15.06 TUBERIA PVC SAL Ø 4" m 26.8 30.00 804.00 0.00 0.00 0% 26.80 804.00 100% 26.80 ### 804.00 100% 0.00 0.00 0%
01.12.15.07 TUBERIA PVC SAL Ø 2" m 12.85 15.29 196.48 0.00 0.00 0% 12.85 196.48 100% 12.85 ### 196.48 100% 0.00 0.00 0%
01.12.19 INSTALACIONES ELECTRICAS
01.12.19.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.12.19.01.01 CENTROS DE LUZ EN TECHOS pto 4 140.21 560.84 0.00 0.00 0% 4.00 560.84 100% 4.00 ### 560.84 100% 0.00 0.00 0%
01.12.19.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 2 140.38 280.76 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2.00 280.76 100%
01.13 CONSTRUCCION DE TANQUE ELEVADO
01.13.06 REVOQUES, ENLUCIDOS Y MLDURAS
01.13.06.01 TARRAJEO EN GENERAL
01.13.06.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 20.52 25.87 530.85 0.00 0.00 0% 20.52 530.85 100% 20.52 ### 530.85 100% 0.00 0.00 0%
01.13.06.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 21.33 32.01 682.77 0.00 0.00 0% 21.33 682.77 100% 21.33 ### 682.77 100% 0.00 0.00 0%
01.13.06.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 6.14 34.26 210.36 0.00 0.00 0% 6.14 210.36 100% 6.14 ### 210.36 100% 0.00 0.00 0%
01.13.06.01.04 TARRAJEO CON IMPERMEABILIZANTES m2 74.29 31.17 2,315.62 0.00 0.00 0% 74.29 2,315.62 100% 74.29 ### 2,315.62 100% 0.00 0.00 0%
01.13.07 CIELO RASOS
01.13.07.01 TARRAJEO DE CIELORAZOS CON MEZCLA DE CEMENTO ARENA m2 2.56 44.01 112.67 0.00 0.00 0% 2.56 112.67 100% 2.56 ### 112.67 100% 0.00 0.00 0%
01.13.09 CONTRAZOCALOS
01.13.09.01 CONTRAZOCALOS DE CEMENTO
01.13.09.01.01 CONTRAZOCALO CEMENTO S/COLOREAR H = 60 CM m 16.7 15.69 262.02 0.00 0.00 0% 16.70 262.02 100% 16.70 ### 262.02 100% 0.00 0.00 0%
01.13.14 INSTALACIONES ELECTRICAS
01.13.14.01 SALIDA PARA ELECTRICIDAD Y FUERZA
01.13.14.01.01 CENTROS DE LUZ EN TECHOS pto 2 140.21 280.42 0.00 0.00 0% 2.00 280.42 100% 2.00 ### 280.42 100% 0.00 0.00 0%
01.13.14.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 1 140.38 140.38 0.00 0.00 0% 1.00 140.38 100% 1.00 ### 140.38 100% 0.00 0.00 0%
01.13.15 TABLEROS Y CUCHILLAS
01.13.15.01 TABLEROS DE DISTRIBUCION GENERAL und 1 414.42 414.42 0.00 0.00 0% 1.00 414.42 100% 1.00 ### 414.42 100% 0.00 0.00 0%
01.13.15.02 TABLERO DE MANDO ELECTROBOMBA und 1 907.46 907.46 0.00 0.00 0% 1.00 907.46 100% 1.00 ### 907.46 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.01 TRABAJOS PRELIMINARES
01.14.01.01.02 TRAZO, NIVELES Y REPLANTEO
01.14.01.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 145.56 10.08 1,467.24 54.56 550.00 37% 91.00 917.24 63% 145.56 ### 1,467.24 100% 0.00 0.00 0%
01.14.01.02 MOVIMIENTO DE TIERRAS
01.14.01.02.01 EXCAVACIONES
01.14.01.02.01.01 EXCAVACION MANUAL P LOSA, TRIBUNA, /UÑA Y CUNETA m3 51.65 42.46 2,193.06 0.00 0.00 0% 10.91 463.35 21% 10.91 ### 463.35 21% 40.74 1,729.70 79%
01.14.01.02.01.02 REFINE Y NIVELACION EN TERRENO m2 119.4 6.74 804.76 0.00 0.00 0% 27.28 183.88 23% 27.28 ### 183.88 23% 92.12 620.88 77%
01.14.01.02.01.03 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 54.56 22.56 1,230.87 0.00 0.00 0% 27.28 615.48 50% 27.28 ### 615.48 50% 27.28 615.40 50%
01.14.01.02.01.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 64.56 17.69 1,142.07 0.00 0.00 0% 13.64 241.31 21% 13.64 ### 241.31 21% 50.92 900.76 79%
01.14.01.02.01.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 64.56 8.47 546.82 0.00 0.00 0% 13.64 115.54 21% 13.64 ### 115.54 21% 50.92 431.28 79%
01.14.01.03 OBRAS DE CONCRETO ARMADO
01.14.01.03.01 TRIBUNAS
01.14.01.03.01.01 CONCRETO CIMIENTO CORRIDO 1:10 +30% P.G. m3 16.86 192.96 3,253.31 0.00 0.00 0% 8.43 1,626.85 50% 8.43 ### 1,626.85 50% 8.43 1,626.46 50%
01.14.01.03.01.02 CONCRETO CICLOPEO FC=140KG/CM2 GRADAS m3 3.88 233.57 906.25 0.00 0.00 0% 1.94 453.13 50% 1.94 ### 453.13 50% 1.94 453.13 50%
01.14.01.03.01.03 CONCRETO EN TRIBUNAS F'C=175 KG/CM2 m3 22.33 413.40 9,231.22 0.00 0.00 0% 6.37 2,631.70 29% 6.37 ### 2,631.70 29% 15.96 6,599.52 71%
01.14.01.03.01.04 ENCOFRADO Y DESENCOFRADO EN TRIBUNA m2 221.56 62.00 13,736.72 0.00 0.00 0% 80.48 4,989.64 36% 80.48 ### 4,989.64 36% 141.08 8,747.08 64%
01.14.01.03.01.05 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS Y VIGAS kg 479.54 5.19 2,488.81 161.87 840.12 34% 158.83 824.34 33% 320.70 ### 1,664.46 67% 158.84 824.35 33%
01.14.01.03.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS m2 40.04 77.61 3,107.50 0.00 0.00 0% 20.02 1,553.75 50% 20.02 ### 1,553.75 50% 20.02 1,553.75 50%
01.14.01.03.01.07 CONCRETO PARA COLUMNAS Y VIGAS F'C=210 KG/CM2 m3 3.99 498.90 1,990.61 0.00 0.00 0% 1.99 994.56 50% 1.99 ### 994.56 50% 2.00 996.05 50%
01.14.01.03.01.08 TARRAJEO PULIDO EN SUPEERF. DE TRIBUNA m2 151.2 55.17 8,341.70 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 151.20 8,341.70 100%
01.14.01.03.01.09 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO m3 27.42 67.32 1,845.91 0.00 0.00 0% 13.71 922.84 50% 13.71 ### 922.84 50% 13.71 923.08 50%
01.14.01.03.01.10 CURADO DE TRIBUNA CON AGUA m2 190.03 0.42 79.81 0.00 0.00 0% 85.00 35.70 45% 85.00 ### 35.70 45% 105.03 44.11 55%
01.14.01.03.01.11 JUNTAS DE DILATACION EN TRIBUNAS m 29.7 31.99 950.10 0.00 0.00 0% 14.85 475.05 50% 14.85 ### 475.05 50% 14.85 475.05 50%
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.01 MOVIMIENTO DE TIERRAS
01.14.02.01.01 EXCAVACIONES
01.14.02.01.01.01 EXCAVACION MANUAL DE ZANJA P/CIMENTACION - ZAPATAS m3 63 39.80 2,507.40 0.00 0.00 0% 47.25 1,880.55 75% 47.25 ### 1,880.55 75% 15.75 626.85 25%
01.14.02.02 OBRAS DE CONCRETO SIMPLE
01.14.02.02.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 9 30.55 274.95 0.00 0.00 0% 6.19 189.03 69% 6.19 ### 189.03 69% 2.81 85.92 31%
01.14.02.03 OBRAS DE CONCRETO ARMADO
01.14.02.03.01 ZAPATAS
01.14.02.03.01.02 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 21.6 403.61 8,717.98 0.00 0.00 0% 8.10 3,269.24 38% 8.10 ### 3,269.24 38% 13.50 5,448.74 63%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.09 MURO DE CONTENCION
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 121.34 42.46 5,152.10 121.34 5,152.10 100% 0.00 0% 121.34 ### 5,152.10 100% 0.00 0.00 0%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 114.32 109.80 12,552.34 4.62 507.28 4% 39.73 4,362.57 35% 44.35 ### 4,869.85 39% 69.97 7,682.49 61%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 27.03 104.62 2,827.88 9.29 971.52 34% 8.51 890.73 31% 17.80 ### 1,862.26 66% 9.23 965.62 34%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 58.29 413.40 24,097.09 21.67 8,957.47 37% 19.87 8,212.60 34% 41.53 ### 17,170.07 71% 16.76 6,927.01 29%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 4877.83 5.19 25,315.94 2,740.69 14,224.19 56% 877.79 4,555.74 18% 3,618.48 ### 18,779.93 74% 1,259.35 6,536.01 26%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 180.22 62.00 11,173.64 61.91 3,838.30 34% 56.76 3,519.12 31% 118.67 ### 7,357.42 66% 61.55 3,816.22 34%
01.15.10 MANTENIMIENTO DE CANAL
01.15.10.01 DESCOLMATACION DE SECCION HIDRAULICA DE CANAL m3 149.04 48.07 7,164.35 0.00 0.00 0% 149.04 7,164.35 100% 149.04 ### 7,164.35 100% 0.00 0.00 0%
COSTO DIRECTO 2,278,432.36 479,094.58 21.03% 229,605.60 10.08% ### 708,700.18 31.10% 1,569,732.12 68.90%
GASTOS GENERALES (11.13 %CD) 253,654.58 53,336.91 25,561.65 ### 78,898.56 174,756.03
GASTOS DE SUPERVISION (3.39 %CD) 77,316.12 16,257.55 7,791.42 24,048.97 53,267.15
SUB TOTAL 2,609,403.06 548,689.03 21.03% 262,958.67 10.08% 811,647.70 31.10% 1,797,755.30 68.90%
º

VALORIZACION ADICIONAL N°- 01


( MES DEL 11 AL 25 DE FEBRERO 2020)
FECHA DE INICIO DE OBRA : 7/1/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/11/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/25/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.02 COBERTURA CON ALUZINC TR4
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.11.09.02.01 m2 306.54 21,801.12 0.00 0% 0.00 0% 0.00 ### 0.00 0% 306.54 21,801.12 100%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.02 COBERTURA CON TEJA
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA
01.12.09.02.01 m2 78.38 71.12 5,574.39 0.00 0% 0.00 0% 0.00 ### 0.00 0% 78.38 5,574.39 100%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.03 LOSA DEPORTIVA
01.14.03.01 DEMOLICIONES
01.14.03.01.01 DEMOLICION DE LOSA DEPORTIVA m2 144 14.77 2,126.88 0.00 0% 0.00 0% 0.00 ### 0.00 0% 144.00 2,126.88 100%
01.14.03.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 180 25.46 4,582.80 0.00 0% 0.00 0% 0.00 ### 0.00 0% 180.00 4,582.80 100%
01.14.03.02 LIMPIEZA DE TERRENO
01.14.03.02.01 LIMPIEZA DE TERRENO MANUAL m2 608 3.22 1,957.76 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 1,957.76 100%
01.14.03.03 TRAZO, NIVELES Y REPLANTEO
01.14.03.03.01 TRAZO Y REPLANTEO m2 608 0.86 522.88 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 522.88 100%
01.14.03.04 MOVIMIENTO DE TIERRAS
01.14.03.04.01 EXCAVACION MASIVA (C/RETROEXCAVADOR) m3 136.33 18.01 2,455.30 0.00 0% 0.00 0% 0.00 ### 0.00 0% 136.33 2,455.30 100%
01.14.03.04.02 RELLENO CON GRAVA DE 4" 6" Y 8" m3 135 84.77 11,443.95 0.00 0% 0.00 0% 0.00 ### 0.00 0% 135.00 11,443.95 100%
01.14.03.04.03 ELIMINACION MANUAL DE MAT. EXEDENTE Y DESMONTE m3 170.41 14.45 2,462.42 0.00 0% 0.00 0% 0.00 ### 0.00 0% 170.41 2,462.42 100%
01.14.03.05 REFINE Y NIVELACION
01.14.03.05.01 REFINE Y NIVELACION EN TERRENO m2 608 6.74 4,097.92 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 4,097.92 100%
01.14.03.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 608 12.91 7,849.28 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 7,849.28 100%
01.14.03.06 CONCRETO SIMPLE
01.14.03.06.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA m2 60.15 72.99 4,390.35 0.00 0% 0.00 0% 0.00 ### 0.00 0% 60.15 4,390.35 100%
01.14.03.06.02 CONCRETO SIMPLE FC=175 KG/CM2 m3 92.53 540.58 50,019.87 0.00 0% 0.00 0% 0.00 ### 0.00 0% 92.53 50,019.87 100%
01.14.03.06.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 299 23.16 6,924.84 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.00 6,924.84 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 168.01 10.08 1,693.54 0.00 0% 126.00 1,270.08 75% 126.00 ### 1,270.08 75% 42.01 423.46 25%
01.15.05.02 EXCAVACION MANUAL m3 84.01 42.46 3,567.06 0.00 0% 63.00 2,674.98 75% 63.00 ### 2,674.98 75% 21.01 892.08 25%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 0.00 0% 126.00 849.24 45% 126.00 ### 849.24 45% 154.42 1,040.79 55%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 105.01 17.69 1,857.63 0.00 0% 78.75 1,393.09 75% 78.75 ### 1,393.09 75% 26.26 464.54 25%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 105.01 8.47 889.43 0.00 0% 78.75 667.01 75% 78.75 ### 667.01 75% 26.26 222.42 25%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 43.08 413.67 17,820.90 0.00 0% 32.76 13,551.83 76% 32.76 ### 13,551.83 76% 10.32 4,269.07 24%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 268.82 62.00 16,666.84 0.00 0% 201.60 12,499.20 75% 201.60 ### 12,499.20 75% 67.22 4,167.64 25%
01.15.05.08 REJILLA PARA CANALETA m 336.02 6.16 2,069.88 0.00 0% 252.00 1,552.32 75% 252.00 ### 1,552.32 75% 84.02 517.56 25%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 336.02 1.90 638.44 0.00 0% 252.00 478.80 75% 252.00 ### 478.80 75% 84.02 159.64 25%
04.01.06 NIVELACION DEL AREA DE BOTADERO und 800 4.49 3,592.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 800.00 3,592.00 100%
04.01.07 INSTALACION DE AREAS VERDES m2 2325.07 11.37 26,436.05 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2,325.07 26,436.05 100%
04.01.08 SEMBRADO DE PLANTAS ORNAMENTALES und 150 16.04 2,406.00 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 150.00 2,406.00 100%
04.01.09 LIMPIEZA FINAL DE OBRA m2 2225.85 0.20 445.17 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 2,225.85 445.17 100%
COSTO DIRECTO 173,303.51 0.00 0.00% 34,936.55 20.16% ### 34,936.55 20.16% 138,366.98 79.84%
GASTOS GENERALES (11.33 %CD) 19,635.29 0.00 3,958.31 ### 3,958.31 15,676.98
GASTOS DE SUPERVISION (3.39 %CD) 5,874.99 0.00 1,184.35 1,184.35 4,690.64
SUB TOTAL 198,813.79 0.00 0.00% 40,079.21 20.16% 40,079.21 20.16% 158,734.59 79.84%
VALORIZACION MAYORES METRADOS N°- 01
( MES DEL 11 AL 25 DE FEBRERO 2020)
FECHA DE INICIO DE OBRA : 7/1/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/11/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/25/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
MAYORES METRADOS
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 187.63 3.22 604.17 0.00 0% 0.00 0% 0.00 ### 0.00 0% 187.63 604.17 100%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 187.63 10.08 1,891.31 0.00 0% 0.00 0% 0.00 ### 0.00 0% 187.63 1,891.31 100%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 20.3 42.46 861.94 0.00 0% 0.00 0% 0.00 ### 0.00 0% 20.30 861.94 100%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 23.32 109.80 2,560.54 0.00 0% 0.00 0% 0.00 ### 0.00 0% 23.32 2,560.54 100%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 25.38 8.47 214.97 0.00 0% 0.00 0% 0.00 ### 0.00 0% 25.38 214.97 100%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 168.19 6.74 1,133.60 0.00 0% 0.00 0% 0.00 ### 0.00 0% 168.19 1,133.60 100%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 34.93 413.40 14,440.06 0.00 0% 0.00 0% 0.00 ### 0.00 0% 34.93 14,440.06 100%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 273.76 62.00 16,973.12 0.00 0% 0.00 0% 0.00 ### 0.00 0% 273.76 16,973.12 100%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.4 3.22 229.91 0.00 0% 71.40 229.91 100% 71.40 ### 229.91 100% 0.00 0.00 0%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 71.4 10.08 719.71 0.00 0% 71.40 719.71 100% 71.40 ### 719.71 100% 0.00 0.00 0%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 107.1 42.46 4,547.47 0.00 0% 107.10 4,547.47 100% 107.10 ### 4,547.47 100% 0.00 0.00 0%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 200.81 109.80 22,048.94 0.00 0% 200.81 22,048.94 100% 200.81 ### 22,048.94 100% 0.00 0.00 0%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 25.17 104.62 2,633.29 0.00 0% 25.17 2,633.29 100% 25.17 ### 2,633.29 100% 0.00 0.00 0%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 133.88 8.47 1,133.96 0.00 0% 133.88 1,133.96 100% 133.88 ### 1,133.96 100% 0.00 0.00 0%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 71.4 6.74 481.24 0.00 0% 71.40 481.24 100% 71.40 ### 481.24 100% 0.00 0.00 0%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 71.4 36.45 2,602.53 0.00 0% 71.40 2,602.53 100% 71.40 ### 2,602.53 100% 0.00 0.00 0%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 223.3 413.40 92,312.22 0.00 0% 223.30 92,312.22 100% 223.30 ### 92,312.22 100% 0.00 0.00 0%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 3624.91 5.19 18,813.28 0.00 0% 3,624.91 18,813.28 100% 3,624.91 ### 18,813.28 100% 0.00 0.00 0%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 167.79 62.00 10,402.98 0.00 0% 167.79 10,402.98 100% 167.79 ### 10,402.98 100% 0.00 0.00 0%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 29.85 30.00 895.50 0.00 0% 29.85 895.50 100% 29.85 ### 895.50 100% 0.00 0.00 0%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 2.23 23.16 51.65 0.00 0% 2.23 51.65 100% 2.23 ### 51.65 100% 0.00 0.00 0%
COSTO DIRECTO 195,552.39 0.00 0.00% 156,872.67 80.22% ### 156,872.67 80.22% 38,679.70 19.78%
GASTOS GENERALES (11.33 %CD) 22,156.09 0.00 17,773.67 ### 17,773.67 4,382.41
GASTOS DE SUPERVISION (3.39 %CD) 6,629.23 0.00 5,317.98 5,317.98 1,311.24
SUB TOTAL 224,337.70 0.00 0.00% 179,964.33 80.22% 179,964.33 80.22% 44,373.36 19.78%
º

VALORIZACION ADICIONAL N°- 03


( MES DE JUNIO 2020)
FECHA DE INICIO DE OBRA : 7/1/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/11/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/25/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.02 COBERTURA CON ALUZINC TR4
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.11.09.02.01 m2 306.54 21,801.12 0.00 0.00 0% 306.54 21,801.12 100% 306.54 ### 21,801.12 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.02 COBERTURA CON TEJA
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.12.09.02.01 m2 78.38 5,574.39 0.00 0.00 0% 78.38 5,574.39 100% 78.38 ### 5,574.39 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.03 LOSA DEPORTIVA
01.14.03.01 DEMOLICIONES
01.14.03.01.01 DEMOLICION DE LOSA DEPORTIVA m2 144 14.77 2,126.88 144.00 2,126.88 100% 0.00 0% 144.00 ### 2,126.88 100% 0.00 0.00 0%
01.14.03.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 180 25.46 4,582.80 180.00 4,582.80 100% 0.00 0% 180.00 ### 4,582.80 100% 0.00 0.00 0%
01.14.03.02 LIMPIEZA DE TERRENO
01.14.03.02.01 LIMPIEZA DE TERRENO MANUAL m2 608 3.22 1,957.76 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 1,957.76 100%
01.14.03.03 TRAZO, NIVELES Y REPLANTEO
01.14.03.03.01 TRAZO Y REPLANTEO m2 608 0.86 522.88 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 522.88 100%
01.14.03.04 MOVIMIENTO DE TIERRAS
01.14.03.04.01 EXCAVACION MASIVA (C/RETROEXCAVADOR) m3 136.33 18.01 2,455.30 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 136.33 2,455.30 100%
01.14.03.04.02 RELLENO CON GRAVA DE 4" 6" Y 8" m3 135 84.77 11,443.95 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 135.00 11,443.95 100%
01.14.03.04.03 ELIMINACION MANUAL DE MAT. EXEDENTE Y DESMONTE m3 170.41 14.45 2,462.42 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 170.41 2,462.42 100%
01.14.03.05 REFINE Y NIVELACION
01.14.03.05.01 REFINE Y NIVELACION EN TERRENO m2 608 6.74 4,097.92 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 4,097.92 100%
01.14.03.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 608 12.91 7,849.28 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 7,849.28 100%
01.14.03.06 CONCRETO SIMPLE
01.14.03.06.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA m2 60.15 72.99 4,390.35 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 60.15 4,390.35 100%
01.14.03.06.02 CONCRETO SIMPLE FC=175 KG/CM2 m3 92.53 540.58 50,019.87 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 92.53 50,019.87 100%
01.14.03.06.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 299 23.16 6,924.84 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.00 6,924.84 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 168.01 10.08 1,693.54 168.01 1,693.54 100% 0.00 0% 168.01 ### 1,693.54 100% 0.00 0.00 0%
01.15.05.02 EXCAVACION MANUAL m3 84.01 42.46 3,567.06 84.01 3,567.06 100% 0.00 0% 84.01 ### 3,567.06 100% 0.00 0.00 0%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 280.42 1,890.03 100% 0.00 0% 280.42 ### 1,890.03 100% 0.00 0.00 0%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 105.01 17.69 1,857.63 105.01 1,857.63 100% 0.00 0% 105.01 ### 1,857.63 100% 0.00 0.00 0%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 105.01 8.47 889.43 105.01 889.43 100% 0.00 0% 105.01 ### 889.43 100% 0.00 0.00 0%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 43.08 413.67 17,820.90 43.08 17,820.90 100% 0.00 0% 43.08 ### 17,820.90 100% 0.00 0.00 0%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 268.82 62.00 16,666.84 268.82 16,666.84 100% 0.00 0% 268.82 ### 16,666.84 100% 0.00 0.00 0%
01.15.05.08 REJILLA PARA CANALETA m 336.02 6.16 2,069.88 336.02 2,069.88 100% 0.00 0% 336.02 ### 2,069.88 100% 0.00 0.00 0%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 336.02 1.90 638.44 336.02 638.44 100% 0.00 0% 336.02 ### 638.44 100% 0.00 0.00 0%
COSTO DIRECTO 173,303.51 53,803.44 31.05% 27,375.51 15.80% ### 81,178.95 46.84% 92,124.57 53.16%
GASTOS GENERALES (11.33 %CD) 19,635.29 6,095.93 3,101.65 ### 9,197.58 10,437.71
GASTOS DE SUPERVISION (3.39 %CD) 5,874.99 1,823.94 928.03 2,751.97 3,123.02
SUB TOTAL 198,813.79 61,723.31 31.05% 31,405.19 15.80% 93,128.49 46.84% 105,685.31 53.16%
53803.4426 81178.953

VALORIZACION MAYORES METRADOS N°- 03


( MES DE JUNIO 2020)
FECHA DE INICIO DE OBRA : 7/1/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/11/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/25/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
MAYORES METRADOS
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 187.63 3.22 604.17 0.00 0% 59.16 190.50 32% 59.16 ### 190.50 32% 128.47 413.67 68%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 187.63 10.08 1,891.31 0.00 0% 59.16 596.33 32% 59.16 ### 596.33 32% 128.47 1,294.98 68%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 20.3 42.46 861.94 0.00 0% 6.02 255.61 30% 6.02 ### 255.61 30% 14.28 606.33 70%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 23.32 109.80 2,560.54 0.00 0% 6.19 679.66 27% 6.19 ### 679.66 27% 17.13 1,880.87 73%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 25.38 8.47 214.97 0.00 0% 7.54 63.86 30% 7.54 ### 63.86 30% 17.84 151.10 70%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 168.19 6.74 1,133.60 0.00 0% 54.00 363.96 32% 54.00 ### 363.96 32% 114.19 769.64 68%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 34.93 413.40 14,440.06 0.00 0% 12.10 5,002.14 35% 12.10 ### 5,002.14 35% 22.83 9,437.92 65%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 273.76 62.00 16,973.12 0.00 0% 83.44 5,173.28 30% 83.44 ### 5,173.28 30% 190.32 11,799.84 70%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.4 3.22 229.91 71.40 229.91 100% 0.00 0% 71.40 ### 229.91 100% 0.00 0.00 0%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 71.4 10.08 719.71 71.40 719.71 100% 0.00 0% 71.40 ### 719.71 100% 0.00 0.00 0%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 107.1 42.46 4,547.47 107.10 4,547.47 100% 0.00 0% 107.10 ### 4,547.47 100% 0.00 0.00 0%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 200.81 109.80 22,048.94 200.81 22,048.94 100% 0.00 0% 200.81 ### 22,048.94 100% 0.00 0.00 0%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 25.17 104.62 2,633.29 25.17 2,633.29 100% 0.00 0% 25.17 ### 2,633.29 100% 0.00 0.00 0%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 133.88 8.47 1,133.96 133.88 1,133.96 100% 0.00 0% 133.88 ### 1,133.96 100% 0.00 0.00 0%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 71.4 6.74 481.24 71.40 481.24 100% 0.00 0% 71.40 ### 481.24 100% 0.00 0.00 0%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 71.4 36.45 2,602.53 71.40 2,602.53 100% 0.00 0% 71.40 ### 2,602.53 100% 0.00 0.00 0%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 223.3 413.40 92,312.22 223.30 92,312.22 100% 0.00 0% 223.30 ### 92,312.22 100% 0.00 0.00 0%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 3624.91 5.19 18,813.28 3,624.91 18,813.28 100% 0.00 0% 3,624.91 ### 18,813.28 100% 0.00 0.00 0%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 167.79 62.00 10,402.98 167.79 10,402.98 100% 0.00 0% 167.79 ### 10,402.98 100% 0.00 0.00 0%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 29.85 30.00 895.50 29.85 895.50 100% 0.00 0% 29.85 ### 895.50 100% 0.00 0.00 0%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 2.23 23.16 51.65 2.23 51.65 100% 0.00 0% 2.23 ### 51.65 100% 0.00 0.00 0%
COSTO DIRECTO 195,552.39 156,872.67 80.22% 12,325.34 6.30% ### 169,198.01 86.52% 26,354.36 13.48%
GASTOS GENERALES (11.33 %CD) 22,156.09 17,773.67 1,396.46 ### 19,170.13 2,985.95
GASTOS DE SUPERVISION (3.39 %CD) 6,629.23 5,317.98 417.83 5,735.81 893.41
SUB TOTAL 224,337.70 179,964.33 80.22% 14,139.63 6.30% 194,103.96 86.52% 30,233.73 13.48%
º

VALORIZACION ADICIONAL N°- 02


( MES DE MARZO 2020)
FECHA DE INICIO DE OBRA : 7/1/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/11/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 4/25/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.02 COBERTURA CON ALUZINC TR4
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.11.09.02.01 m2 306.54 21,801.12 0.00 0% 0.00 0% 0.00 ### 0.00 0% 306.54 21,801.12 100%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.02 COBERTURA CON TEJA
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.12.09.02.01 m2 78.38 5,574.39 0.00 0% 0.00 0% 0.00 ### 0.00 0% 78.38 5,574.39 100%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.03 LOSA DEPORTIVA
01.14.03.01 DEMOLICIONES
01.14.03.01.01 DEMOLICION DE LOSA DEPORTIVA m2 144 14.77 2,126.88 0.00 0% 144.00 2,126.88 100% 144.00 ### 2,126.88 100% 0.00 0.00 0%
01.14.03.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 180 25.46 4,582.80 0.00 0% 180.00 4,582.80 100% 180.00 ### 4,582.80 100% 0.00 0.00 0%
01.14.03.02 LIMPIEZA DE TERRENO
01.14.03.02.01 LIMPIEZA DE TERRENO MANUAL m2 608 3.22 1,957.76 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 1,957.76 100%
01.14.03.03 TRAZO, NIVELES Y REPLANTEO
01.14.03.03.01 TRAZO Y REPLANTEO m2 608 0.86 522.88 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 522.88 100%
01.14.03.04 MOVIMIENTO DE TIERRAS
01.14.03.04.01 EXCAVACION MASIVA (C/RETROEXCAVADOR) m3 136.33 18.01 2,455.30 0.00 0% 0.00 0% 0.00 ### 0.00 0% 136.33 2,455.30 100%
01.14.03.04.02 RELLENO CON GRAVA DE 4" 6" Y 8" m3 135 84.77 11,443.95 0.00 0% 0.00 0% 0.00 ### 0.00 0% 135.00 11,443.95 100%
01.14.03.04.03 ELIMINACION MANUAL DE MAT. EXEDENTE Y DESMONTE m3 170.41 14.45 2,462.42 0.00 0% 0.00 0% 0.00 ### 0.00 0% 170.41 2,462.42 100%
01.14.03.05 REFINE Y NIVELACION
01.14.03.05.01 REFINE Y NIVELACION EN TERRENO m2 608 6.74 4,097.92 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 4,097.92 100%
01.14.03.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 608 12.91 7,849.28 0.00 0% 0.00 0% 0.00 ### 0.00 0% 608.00 7,849.28 100%
01.14.03.06 CONCRETO SIMPLE
01.14.03.06.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA m2 60.15 72.99 4,390.35 0.00 0% 0.00 0% 0.00 ### 0.00 0% 60.15 4,390.35 100%
01.14.03.06.02 CONCRETO SIMPLE FC=175 KG/CM2 m3 92.53 540.58 50,019.87 0.00 0% 0.00 0% 0.00 ### 0.00 0% 92.53 50,019.87 100%
01.14.03.06.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 299 23.16 6,924.84 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.00 6,924.84 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 168.01 10.08 1,693.54 126.00 1,270.08 75% 42.01 423.46 25% 168.01 ### 1,693.54 100% 0.00 0.00 0%
01.15.05.02 EXCAVACION MANUAL m3 84.01 42.46 3,567.06 63.00 2,674.98 75% 21.01 892.08 25% 84.01 ### 3,567.06 100% 0.00 0.00 0%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 126.00 849.24 45% 154.42 1,040.79 55% 280.42 ### 1,890.03 100% 0.00 0.00 0%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 105.01 17.69 1,857.63 78.75 1,393.09 75% 26.26 464.54 25% 105.01 ### 1,857.63 100% 0.00 0.00 0%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 105.01 8.47 889.43 78.75 667.01 75% 26.26 222.42 25% 105.01 ### 889.43 100% 0.00 0.00 0%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 43.08 413.67 17,820.90 32.76 13,551.83 76% 10.32 4,269.07 24% 43.08 ### 17,820.90 100% 0.00 0.00 0%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 268.82 62.00 16,666.84 201.60 12,499.20 75% 67.22 4,167.64 25% 268.82 ### 16,666.84 100% 0.00 0.00 0%
01.15.05.08 REJILLA PARA CANALETA m 336.02 6.16 2,069.88 252.00 1,552.32 75% 84.02 517.56 25% 336.02 ### 2,069.88 100% 0.00 0.00 0%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 336.02 1.90 638.44 252.00 478.80 75% 84.02 159.64 25% 336.02 ### 638.44 100% 0.00 0.00 0%
COSTO DIRECTO 173,303.51 34,936.55 20.16% 18,866.89 10.89% ### 53,803.44 31.05% 119,500.08 68.95%
GASTOS GENERALES (11.33 %CD) 19,635.29 3,958.31 2,137.62 ### 6,095.93 13,539.36
GASTOS DE SUPERVISION (3.39 %CD) 5,874.99 1,184.35 639.59 1,823.94 4,051.05
SUB TOTAL 198,813.79 40,079.21 20.16% 21,644.10 10.89% 61,723.31 31.05% 137,090.49 68.95%
VALORIZACION FINAL DE ADICIONAL N° 01
( MES DE AGOSTO DEL 2020)
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN
ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.02 COBERTURA CON ALUZINC TR4
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.11.09.02.01 m2 306.54 21,801.12 306.54 21,801.12 100% 0.00 0% 306.54### 21,801.12 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.02 COBERTURA CON TEJA
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.12.09.02.01 m2 78.38 5,574.39 78.38 5,574.39 100% 0.00 0% 78.38 ### 5,574.39 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.03 LOSA DEPORTIVA
01.14.03.01 DEMOLICIONES
01.14.03.01.01 DEMOLICION DE LOSA DEPORTIVA m2 144 14.77 2,126.88 144.00 2,126.88 100% 0.00 0% 144.00### 2,126.88 100% 0.00 0.00 0%
01.14.03.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 180 25.46 4,582.80 180.00 4,582.80 100% 0.00 0% 180.00### 4,582.80 100% 0.00 0.00 0%
01.14.03.02 LIMPIEZA DE TERRENO
01.14.03.02.01 LIMPIEZA DE TERRENO MANUAL m2 608 3.22 1,957.76 608.00 1,957.76 100% 0.00 0% 608.00### 1,957.76 100% 0.00 0.00 0%
01.14.03.03 TRAZO, NIVELES Y REPLANTEO
01.14.03.03.01 TRAZO Y REPLANTEO m2 608 0.86 522.88 608.00 522.88 100% 0.00 0% 608.00### 522.88 100% 0.00 0.00 0%
01.14.03.04 MOVIMIENTO DE TIERRAS
01.14.03.04.01 EXCAVACION MASIVA (C/RETROEXCAVADOR) m3 136.33 18.01 2,455.30 136.33 2,455.30 100% 0.00 0% 136.33### 2,455.30 100% 0.00 0.00 0%
01.14.03.04.02 RELLENO CON GRAVA DE 4" 6" Y 8" m3 135 84.77 11,443.95 135.00 11,443.95 100% 0.00 0% 135.00### 11,443.95 100% 0.00 0.00 0%
01.14.03.04.03 ELIMINACION MANUAL DE MAT. EXEDENTE Y DESMONTE m3 170.41 14.45 2,462.42 170.41 2,462.42 100% 0.00 0% 170.41### 2,462.42 100% 0.00 0.00 0%
01.14.03.05 REFINE Y NIVELACION
01.14.03.05.01 REFINE Y NIVELACION EN TERRENO m2 608 6.74 4,097.92 608.00 4,097.92 100% 0.00 0% 608.00### 4,097.92 100% 0.00 0.00 0%
01.14.03.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 608 12.91 7,849.28 608.00 7,849.28 100% 0.00 0% 608.00### 7,849.28 100% 0.00 0.00 0%
01.14.03.06 CONCRETO SIMPLE
01.14.03.06.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA m2 60.15 72.99 4,390.35 26.94 1,966.35 45% 33.21 2,424.00 55% 60.15 ### 4,390.35 100% 0.00 0.00 0%
01.14.03.06.02 CONCRETO SIMPLE FC=175 KG/CM2 m3 92.53 540.58 50,019.87 37.09 20,052.06 40% 55.44 29,967.81 60% 92.53 ### 50,019.87 100% 0.00 0.00 0%
01.14.03.06.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 299 23.16 6,924.84 0.00 0.00 0% 299.00 6,924.84 100% 299.00### 6,924.84 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 168.01 10.08 1,693.54 168.01 1,693.54 100% 0.00 0% 168.01### 1,693.54 100% 0.00 0.00 0%
01.15.05.02 EXCAVACION MANUAL m3 84.01 42.46 3,567.06 84.01 3,567.06 100% 0.00 0% 84.01 ### 3,567.06 100% 0.00 0.00 0%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 280.42 1,890.03 100% 0.00 0% 280.42### 1,890.03 100% 0.00 0.00 0%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 105.01 17.69 1,857.63 105.01 1,857.63 100% 0.00 0% 105.01### 1,857.63 100% 0.00 0.00 0%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 105.01 8.47 889.43 105.01 889.43 100% 0.00 0% 105.01### 889.43 100% 0.00 0.00 0%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 43.08 413.67 17,820.90 43.08 17,820.90 100% 0.00 0% 43.08 ### 17,820.90 100% 0.00 0.00 0%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 268.82 62.00 16,666.84 268.82 16,666.84 100% 0.00 0% 268.82### 16,666.84 100% 0.00 0.00 0%
01.15.05.08 REJILLA PARA CANALETA m 336.02 6.16 2,069.88 336.02 2,069.88 100% 0.00 0% 336.02### 2,069.88 100% 0.00 0.00 0%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 336.02 1.90 638.44 336.02 638.44 100% 0.00 0% 336.02### 638.44 100% 0.00 0.00 0%
COSTO DIRECTO 173,303.51 133,986.88 77.31% 39,316.65 22.69% ### 173,303.53 100.00% 0.00 0.00%
GASTOS GENERALES (11.33 %CD) 19,635.29 15,180.71 4,454.58 ### 19,635.29 0.00
GASTOS DE SUPERVISION (3.39 %CD) 5,874.99 4,542.16 1,332.83 5,874.99 0.00
SUB TOTAL 198,813.79 153,709.75 77.31% 45,104.06 22.69% 198,813.81 100.00% 0.00 0.00%
VALORIZACION FINAL DE MAYORES METRADOS N° 01
( MES DE JULIO 2020)
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN
ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
MAYORES METRADOS
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 187.63 3.22 604.17 59.16 190.50 32% 128.47 413.67 68% 187.63### 604.17 100% 0.00 0.00 0%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 187.63 10.08 1,891.31 59.16 596.33 32% 128.47 1,294.98 68% 187.63### 1,891.31 100% 0.00 0.00 0%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 20.3 42.46 861.94 6.02 255.61 30% 14.28 606.33 70% 20.30 ### 861.94 100% 0.00 0.00 0%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 23.32 109.80 2,560.54 6.19 679.66 27% 17.13 1,880.87 73% 23.32 ### 2,560.54 100% 0.00 0.00 0%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 25.38 8.47 214.97 7.54 63.86 30% 17.84 151.10 70% 25.38 ### 214.97 100% 0.00 0.00 0%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 168.19 6.74 1,133.60 54.00 363.96 32% 114.19 769.64 68% 168.19### 1,133.60 100% 0.00 0.00 0%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 34.93 413.40 14,440.06 12.10 5,002.14 35% 22.83 9,437.92 65% 34.93 ### 14,440.06 100% 0.00 0.00 0%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 273.76 62.00 16,973.12 83.44 5,173.28 30% 190.32 11,799.84 70% 273.76### 16,973.12 100% 0.00 0.00 0%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.4 3.22 229.91 71.40 229.91 100% 0.00 0% 71.40 ### 229.91 100% 0.00 0.00 0%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 71.4 10.08 719.71 71.40 719.71 100% 0.00 0% 71.40 ### 719.71 100% 0.00 0.00 0%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 107.1 42.46 4,547.47 107.10 4,547.47 100% 0.00 0% 107.10### 4,547.47 100% 0.00 0.00 0%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 200.81 109.80 22,048.94 200.81 22,048.94 100% 0.00 0% 200.81### 22,048.94 100% 0.00 0.00 0%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 25.17 104.62 2,633.29 25.17 2,633.29 100% 0.00 0% 25.17 ### 2,633.29 100% 0.00 0.00 0%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 133.88 8.47 1,133.96 133.88 1,133.96 100% 0.00 0% 133.88### 1,133.96 100% 0.00 0.00 0%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 71.4 6.74 481.24 71.40 481.24 100% 0.00 0% 71.40 ### 481.24 100% 0.00 0.00 0%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 71.4 36.45 2,602.53 71.40 2,602.53 100% 0.00 0% 71.40 ### 2,602.53 100% 0.00 0.00 0%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 223.3 413.40 92,312.22 223.30 92,312.22 100% 0.00 0% 223.30### 92,312.22 100% 0.00 0.00 0%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 3624.91 5.19 18,813.28 3,624.91 18,813.28 100% 0.00 0% 3,624.91### 18,813.28 100% 0.00 0.00 0%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 167.79 62.00 10,402.98 167.79 10,402.98 100% 0.00 0% 167.79### 10,402.98 100% 0.00 0.00 0%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 29.85 30.00 895.50 29.85 895.50 100% 0.00 0% 29.85 ### 895.50 100% 0.00 0.00 0%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 2.23 23.16 51.65 2.23 51.65 100% 0.00 0% 2.23 ### 51.65 100% 0.00 0.00 0%
COSTO DIRECTO 195,552.39 169,198.01 86.52% 26,354.36 13.48% ### 195,552.37 100.00% 0.00 0.00%
GASTOS GENERALES (11.33 %CD) 22,156.09 19,170.13 2,985.95 ### 22,156.08 0.00
GASTOS DE SUPERVISION (3.39 %CD) 6,629.23 5,735.81 893.41 6,629.23 0.00
SUB TOTAL 224,337.70 194,103.96 86.52% 30,233.72 13.48% 224,337.68 100.00% 0.00 0.00%
VALORIZACION FINAL DE ADICIONAL N°02
( MES DE SETIEMBRE 2020)
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN
ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.05 MANTENIMIENTO DE PUERTAS Y VENTANAS EXISTENTES
01.08.05.01 MANTENIMIENTO DE PUERTAS Y VENTANAS GLB 1.00 6,000.00 6,000.00 0.00 0% 1.00 6,000.00 100% 1.00 ### 6,000.00 100% 0.00 0.00 0%
01.09 MEJORAMIENTO DE 03 AULAS , LABORATORIO, SS.HH Y DEPOSITOS.
01.09.04 MANTENIMIENTO DE PUERTAS Y VENTANAS EXISTENTES
01.09.04.01 MANTENIMIENTO DE PUERTAS Y VENTANAS GLB 1.00 6,000.00 6,000.00 0.00 0% 1.00 6,000.00 100% 1.00 ### 6,000.00 100% 0.00 0.00 0%
01.09.05 REPOSICION DE APARATOS SANITARIOS Y ACCESORIOS
01.09.05.01 INODORO TANQUE BAJO BLANCO pza 3.00 200.00 600.00 0.00 0% 3.00 600.00 100% 3.00 ### 600.00 100% 0.00 0.00 0%
01.09.05.02 COLOCACION DE APARATOS SANITARIO pza 3.00 232.13 696.39 0.00 0% 3.00 696.39 100% 3.00 ### 696.39 100% 0.00 0.00 0%
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.01 MOVIMIENTO DE TIERRAS
01.11.01.03 EXCAVACIONES
01.11.01.03.02 EXCAVACION DE ZANJA Y ZAPATAS EN CIMIENTO CORRIDO m3 7.40 42.46 314.20 0.00 0% 7.40 314.20 100% 7.40 ### 314.20 100% 0.00 0.00 0%
01.11.01.03.03 EXCAVACION DE ZANJA PARA FALSA ZAPATAS m3 21.97 42.46 932.85 0.00 0% 21.97 932.85 100% 21.97 ### 932.85 100% 0.00 0.00 0%
01.11.01.05 ELIMINACION DE MATERIAL EXEDENTE
01.11.01.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE CON VOLQUETE EN CIMIENTO CORRIDO m3 9.25 13.94 128.95 0.00 0% 9.25 128.95 100% 9.25 ### 128.95 100% 0.00 0.00 0%
01.11.01.05.03 ELIMINACIÓN DE MATERIAL EXCEDENTE CON VOLQUETE EN FALSA ZAPATA m3 27.46 13.94 382.79 0.00 0% 27.46 382.79 100% 27.46 ### 382.79 100% 0.00 0.00 0%
01.11.02 OBRAS DE CONCRETO SIMPLE
01.11.02.01 CIMIENTO CORRIDO
01.11.02.01.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS CON MATERIAL ORGANICOm3 7.40 390.41 2,889.03 0.00 0% 7.40 2,889.03 100% 7.40 ### 2,889.03 100% 0.00 0.00 0%
01.11.02.05 FALSA ZAPATA
01.11.02.05.01 CONCRETO 1:10 +30% P.G. EN FALSA ZAPATA m3 21.97 390.41 8,577.31 0.00 0% 21.97 8,577.31 100% 21.97 ### 8,577.31 100% 0.00 0.00 0%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.02 MOVIMIENTO DE TIERRAS
01.12.02.02 EXCAVACIONES
01.12.02.02.02 EXCAVACION DE ZANJA PARA FALSA ZAPATAS m3 5.18 42.46 219.94 0.00 0% 5.18 219.94 100% 5.18 ### 219.94 100% 0.00 0.00 0%
01.12.02.04 ELIMINACION DE MATERIAL EXEDENTE
01.12.02.04.02 ELIMINACIÓN DE MATERIAL EXCEDENTE CON VOLQUETE EN FALSA ZAPATA m3 6.48 15.32 99.27 0.00 0% 6.48 99.27 100% 6.48 ### 99.27 100% 0.00 0.00 0%
01.12.03 OBRAS DE CONCRETO SIMPLE
01.12.03.05 FALSA ZAPATA
01.12.03.05.01 CONCRETO 1:10 +30% P.G. EN FALSA ZAPATA m3 5.18 390.41 2,022.32 0.00 0% 5.18 2,022.32 100% 5.18 ### 2,022.32 100% 0.00 0.00 0%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01.01 TRABAJOS PRELIMINARES
01.14.01.01.01 LIMPIEZA DE TERRENO
01.14.01.01.01.02 LIMPIEZA DE TERRENO MANUAL DRENAJE PLUVIAL m2 103.68 2.01 208.40 0.00 0% 103.68 208.40 100% 103.68### 208.40 100% 0.00 0.00 0%
01.14.01.01.02 TRAZO, NIVELES Y REPLANTEO
01.14.01.01.02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO EN DRENAJE PLUVIAL m2 103.68 3.30 342.14 0.00 0% 103.68 342.14 100% 103.68### 342.14 100% 0.00 0.00 0%
01.14.01.02 MOVIMIENTO DE TIERRAS
01.14.01.02.01 EXCAVACIONES
01.14.01.02.01.05 EXCAVACION MANUAL DRENAJE PLUVIAL m3 29.81 42.46 1,265.73 0.00 0% 29.81 1,265.73 100% 29.81 ### 1,265.73 100% 0.00 0.00 0%
01.14.01.02.01.06 REFINE Y NIVELACION EN TERRENO DRENAJE PLUVIAL m2 64.80 8.84 572.83 0.00 0% 64.80 572.83 100% 64.80 ### 572.83 100% 0.00 0.00 0%
01.14.01.02.01.07 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA DE DRENAJE PLUVIAL m3 37.26 42.46 1,582.06 0.00 0% 37.26 1,582.06 100% 37.26 ### 1,582.06 100% 0.00 0.00 0%
01.14.01.02.01.08 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE DE DRENAJE PLUVIAL m3 37.26 15.32 570.82 0.00 0% 37.26 570.82 100% 37.26 ### 570.82 100% 0.00 0.00 0%
01.14.01.04 CANALETA PLUVIAL DE LOSA DEPORTIVA
01.14.01.04.01 CONCRETO EN CANALETA F'C=175 KG/CM2 m3 25.27 471.83 11,923.14 0.00 0% 25.27 11,923.14 100% 25.27 ### 11,923.14 100% 0.00 0.00 0%
01.14.01.04.02 ENCOFRADO Y DESENCOFRADO CANALETA m2 225.45 79.45 17,912.00 0.00 0% 225.45 17,912.00 100% 225.45### 17,912.00 100% 0.00 0.00 0%
01.14.01.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN CANALETAS kg 133.13 6.05 805.44 0.00 0% 133.13 805.44 100% 133.13### 805.44 100% 0.00 0.00 0%
01.14.01.05 MEJORAMIENTO DE TERRENO EN LOSA DEPORTIVA N 02
01.14.01.05.01 EXCAVACION CON MAQUINARIA m3 325.50 8.01 2,607.26 0.00 0% 325.50 2,607.26 100% 325.50### 2,607.26 100% 0.00 0.00 0%
01.14.01.05.02 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 406.88 13.94 5,671.91 0.00 0% 406.88 5,671.91 100% 406.88### 5,671.91 100% 0.00 0.00 0%
01.14.01.05.03 RELLENO CON GRAVA DE 4" 6" Y 8" m3 325.50 59.53 19,377.02 0.00 0% 325.50 19,377.02 100% 325.50### 19,377.02 100% 0.00 0.00 0%
01.14.01.06 PISOS ADOQUINADO
01.14.01.06.01 MOVIMIENTO DE TIERRAS
01.14.01.06.01.01 EXCAVACIONES
01.14.01.06.01.01.01 EXCAVACION MANUAL m3 43.72 42.46 1,856.35 0.00 0% 43.72 1,856.35 100% 43.72 ### 1,856.35 100% 0.00 0.00 0%
01.14.01.06.01.02 ELIMINACION DE MATERIAL EXEDENTE
01.14.01.06.01.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 54.64 13.94 761.68 0.00 0% 54.64 761.68 100% 54.64 ### 761.68 100% 0.00 0.00 0%
01.14.01.06.01.03 REFINE Y NIVELACION
01.14.01.06.01.03.01 REFINE Y NIVELACION EN TERRENO m2 87.43 8.84 772.88 0.00 0% 87.43 772.88 100% 87.43 ### 772.88 100% 0.00 0.00 0%
01.14.01.06.01.03.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 87.43 12.91 1,128.72 0.00 0% 87.43 1,128.72 100% 87.43 ### 1,128.72 100% 0.00 0.00 0%
01.14.01.06.01.04 PISOS Y PAVIMENTOS
01.14.01.06.01.04.01 PISOS ADOQUINADO
01.14.01.06.01.04.01.0 FALSO PISO DE 4" DE CONCRETO 1:10 m2 87.43 51.17 4,473.79 0.00 0% 87.43 4,473.79 100% 87.43 ### 4,473.79 100% 0.00 0.00 0%
01.14.01.06.01.04.01.0 BASE DE ARENA E=0.04 NIVELACION MANUAL m2 87.43 22.11 1,933.08 0.00 0% 87.43 1,933.08 100% 87.43 ### 1,933.08 100% 0.00 0.00 0%
01.14.01.06.01.04.01.0 PISO CON ADOQUINES DE CONCRETO 20x10x4cm - GRIS m2 87.43 73.21 6,400.75 0.00 0% 87.43 6,400.75 100% 87.43 ### 6,400.75 100% 0.00 0.00 0%
01.14.01.06.01.04.01.0 SELLADO DE JUNTAS EN ADOQUINES m2 14.86 5.33 79.20 0.00 0% 14.86 79.20 100% 14.86 ### 79.20 100% 0.00 0.00 0%
01.14.01.06.01.04.01.0 VIBRADO Y COMPACTADO DE VEREDAS DE ADOQUINES DE CONCRETO m2 87.43 15.70 1,372.65 0.00 0% 87.43 1,372.65 100% 87.43 ### 1,372.65 100% 0.00 0.00 0%
01.14.02 COBERTURA DE LOSA DEPORTIVA
01.14.02.01 MOVIMIENTO DE TIERRAS
01.14.02.01.01 EXCAVACIONES
01.14.02.01.01.05 EXCAVACION DE ZANJA PARA FALSA ZAPATAS m3 7.43 42.46 315.48 0.00 0% 7.43 315.48 100% 7.43 ### 315.48 100% 0.00 0.00 0%
01.14.02.01.01.06 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE FALSA ZAPATA m3 9.28 15.32 142.17 0.00 0% 9.28 142.17 100% 9.28 ### 142.17 100% 0.00 0.00 0%
01.14.02.02 OBRAS DE CONCRETO SIMPLE
01.14.02.02.02 CONCRETO 1:10 +30% P.G. EN FALSA ZAPATA m3 7.43 390.41 2,900.75 0.00 0% 7.43 2,900.75 100% 7.43 ### 2,900.75 100% 0.00 0.00 0%
01.14.02.02.03 CONCRETO F´C= 175 KG/CM2 EN PEDESTAL DE COLUMNA m3 1.47 509.42 748.85 0.00 0% 1.47 748.85 100% 1.47 ### 748.85 100% 0.00 0.00 0%
01.14.02.02.04 ENCOFRADO DESENCOFRADO m2 16.80 71.35 1,198.68 0.00 0% 16.80 1,198.68 100% 16.80 ### 1,198.68 100% 0.00 0.00 0%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.11 MURO DE CONTENCION TIPO II
01.15.11.01 TRABAJOS PRELIMINARES
01.15.11.01.01 LIMPIEZA DE TERRENO
01.15.11.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 27.31 2.01 54.89 0.00 0% 27.31 54.89 100% 27.31 ### 54.89 100% 0.00 0.00 0%
01.15.11.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.11.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 27.31 3.30 90.12 0.00 0% 27.31 90.12 100% 27.31 ### 90.12 100% 0.00 0.00 0%
01.15.11.02 MOVIMIENTO DE TIERRAS
01.15.11.02.01 EXCAVACIONES
01.15.11.02.01.01 EXCAVACION MANUAL m3 40.96 42.46 1,739.16 0.00 0% 40.96 1,739.16 100% 40.96 ### 1,739.16 100% 0.00 0.00 0%
01.15.11.02.01.02 RELLENO COMPACTADO C/ MATERIAL PROPIO m3 25.49 49.77 1,268.64 0.00 0% 25.49 1,268.64 100% 25.49 ### 1,268.64 100% 0.00 0.00 0%
01.15.11.02.01.03 RELLENO CON GRAVA GRUESA Ø3/4" m3 9.56 105.96 1,012.98 0.00 0% 9.56 1,012.98 100% 9.56 ### 1,012.98 100% 0.00 0.00 0%
01.15.11.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.11.02.02.01 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 51.20 15.32 784.38 0.00 0% 51.20 784.38 100% 51.20 ### 784.38 100% 0.00 0.00 0%
01.15.11.02.03 REFINE Y NIVELACION
01.15.11.02.03.01 REFINE Y NIVELACION EN TERRENO m2 27.31 8.84 241.42 0.00 0% 27.31 241.42 100% 27.31 ### 241.42 100% 0.00 0.00 0%
01.15.11.03 OBRAS DE CONCRETO SIMPLE
01.15.11.03.01 SOLADO
01.15.11.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 27.31 48.98 1,337.64 0.00 0% 27.31 1,337.64 100% 27.31 ### 1,337.64 100% 0.00 0.00 0%
01.15.11.04 OBRAS DE CONCRETO ARMADO
01.15.11.04.01 CONCRETO F'c= 175KG/CM2 m3 15.93 509.42 8,115.06 0.00 0% 15.93 8,115.06 100% 15.93 ### 8,115.06 100% 0.00 0.00 0%
01.15.11.04.02 ACERO DE REFUERZO FY=4200 KG/CM2 PARA MUROS kg 765.98 6.11 4,680.14 0.00 0% 765.98 4,680.14 100% 765.98### 4,680.14 100% 0.00 0.00 0%
01.15.11.04.03 ENCOFRADO DESENCOFRADO m2 63.71 71.35 4,545.71 0.00 0% 63.71 4,545.71 100% 63.71 ### 4,545.71 100% 0.00 0.00 0%
01.15.11.05 REVOQUES ENLUCIDOS Y MOLDURAS
01.15.11.05.01 TARRAJEO EN GENERAL
01.15.11.05.01.01 TARRAJEO DE SUPERFICIES EN MURO DE CONTENCION m2 40.08 42.42 1,700.19 0.00 0% 40.08 1,700.19 100% 40.08 ### 1,700.19 100% 0.00 0.00 0%
01.15.11.06 CARPINTERIA METALICA Y ALUMINIO
01.15.11.06.01 BARANDA DE TUBO Fe m 15.17 204.94 3,108.94 0.00 0% 15.17 3,108.94 100% 15.17 ### 3,108.94 100% 0.00 0.00 0%
01.15.11.07 OTROS
01.15.11.07.01 TUBERIA PVC SAL Ø 4" m 15.17 38.91 590.26 0.00 0% 15.17 590.26 100% 15.17 ### 590.26 100% 0.00 0.00 0%
01.15.12 REPARACION DE LOSA DEPORTIVA EXISTENTE Y PORTON PRINCIPAL
01.15.12.01 DEMOLICIONES
01.15.12.01.01 DEMOLICION DE LOSA DEPORTIVA EXISTENTE m3 13.60 15.40 209.44 0.00 0% 13.60 209.44 100% 13.60 ### 209.44 100% 0.00 0.00 0%
01.15.12.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 17.00 15.32 260.44 0.00 0% 17.00 260.44 100% 17.00 ### 260.44 100% 0.00 0.00 0%
01.15.12.02 LIMPIEZA DE TERRENO
01.15.12.02.01 LIMPIEZA DE TERRENO MANUAL. m2 62.60 1.74 108.92 0.00 0% 62.60 108.92 100% 62.60 ### 108.92 100% 0.00 0.00 0%
01.15.12.03 TRAZO, NIVELES Y REPLANTEO
01.15.12.03.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 62.60 3.30 206.58 0.00 0% 62.60 206.58 100% 62.60 ### 206.58 100% 0.00 0.00 0%
01.15.12.04 EXCAVACIONES
01.15.12.04.01 EXCAVACION MANUAL EN TERRENO m3 0.50 41.22 20.61 0.00 0% 0.50 20.61 100% 0.50 ### 20.61 100% 0.00 0.00 0%
01.15.12.04.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 0.63 15.32 9.65 0.00 0% 0.63 9.65 100% 0.63 ### 9.65 100% 0.00 0.00 0%
01.15.12.05 REFINE Y NIVELACION
01.15.12.05.01 REFINE Y COMPACTADO m2 62.60 6.96 435.70 0.00 0% 62.60 435.70 100% 62.60 ### 435.70 100% 0.00 0.00 0%
01.15.12.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 62.60 12.91 808.17 0.00 0% 62.60 808.17 100% 62.60 ### 808.17 100% 0.00 0.00 0%
01.15.12.06 OBRAS DE CONCRETO SIMPLE
01.15.12.06.01 CONCRETO F'c= 175KG/CM2 LOSA Y PORTON m3 12.24 464.99 5,691.48 0.00 0% 12.24 5,691.48 100% 12.24 ### 5,691.48 100% 0.00 0.00 0%
01.15.12.06.02 ENCOFRADO DESENCOFRADO m2 14.04 71.35 1,001.75 0.00 0% 14.04 1,001.75 100% 14.04 ### 1,001.75 100% 0.00 0.00 0%
01.15.12.06.03 JUNTAS ASFALTICAS m 25.80 19.26 496.91 0.00 0% 25.80 496.91 100% 25.80 ### 496.91 100% 0.00 0.00 0%
01.15.12.06.04 REPOSICION DE PORTON PRINCIPAL und 1.00 6,121.96 6,121.96 0.00 0% 1.00 6,121.96 100% 1.00 ### 6,121.96 100% 0.00 0.00 0%
01.15.12.06.05 REPOSICION DE ARCOS und 2.00 1,360.98 2,721.96 0.00 0% 2.00 2,721.96 100% 2.00 ### 2,721.96 100% 0.00 0.00 0%
01.15.12.06.06 PINTADO EN LOSA DEPORTIVA m2 2.00 2,500.00 5,000.00 0.00 0% 2.00 5,000.00 100% 2.00 ### 5,000.00 100% 0.00 0.00 0%
01.15.13 CANALETA DE DRENAJE PLUVIAL EN MODULO EXISTENTE
01.15.13.01 OBRAS DE CONCRETO SIMPLE
01.15.13.01.01 CONCRETO FC= 175 KG/CM2 DRENAJE PLUVIAL m3 1.35 490.26 661.85 0.00 0% 1.35 661.85 100% 1.35 ### 661.85 100% 0.00 0.00 0%
01.15.13.01.02 ENCOFRADO DESENCOFRADO m2 9.00 71.35 642.15 0.00 0% 9.00 642.15 100% 9.00 ### 642.15 100% 0.00 0.00 0%
COSTO DIRECTO 169,453.93 0.00 0.00% 169,453.93 100% ### 169,453.93 100.00% 0.00 0.00%
GASTOS GENERALES (11.13 %CD) 18,860.22 0.00 18,860.22 ### 18,860.22 0.00
GASTOS DE SUPERVISION (3.39 %CD) 5,744.49 0.00 5,744.49 5,744.49 0.00
SUB TOTAL 194,058.64 0.00 0.00% 194,058.65 100% 194,058.65 100.00% 0.00 0.00%
º

VALORIZACION ADICIONAL N°- 04


( MES DE 26 DE JUNIO AL 25 DE JULIO DE 2020)
FECHA DE INICIO DE OBRA : ´01/07/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° : 75 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 8/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.02 COBERTURA CON ALUZINC TR4
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.11.09.02.01 m2 306.54 21,801.12 306.54 21,801.12 100% 0.00 0% 306.54 ### 21,801.12 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.02 COBERTURA CON TEJA
SUMINISTRO E INST. DE COBERTURA ALUZINC TR4 E=0.04 MM PINTURA 71.12
01.12.09.02.01 m2 78.38 5,574.39 78.38 5,574.39 100% 0.00 0% 78.38 ### 5,574.39 100% 0.00 0.00 0%
E=25MICRAS INCLUYE CUMBRERA Y CABALLETE
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.03 LOSA DEPORTIVA
01.14.03.01 DEMOLICIONES
01.14.03.01.01 DEMOLICION DE LOSA DEPORTIVA m2 144 14.77 2,126.88 144.00 2,126.88 100% 0.00 0% 144.00 ### 2,126.88 100% 0.00 0.00 0%
01.14.03.01.02 ELIMINACIÓN DE MATERIAL DEDEMOLICIÓN CON VOLQUETE m3 180 25.46 4,582.80 180.00 4,582.80 100% 0.00 0% 180.00 ### 4,582.80 100% 0.00 0.00 0%
01.14.03.02 LIMPIEZA DE TERRENO
01.14.03.02.01 LIMPIEZA DE TERRENO MANUAL m2 608 3.22 1,957.76 0.00 0.00 0% 608.00 1,957.76 100% 608.00 ### 1,957.76 100% 0.00 0.00 0%
01.14.03.03 TRAZO, NIVELES Y REPLANTEO
01.14.03.03.01 TRAZO Y REPLANTEO m2 608 0.86 522.88 0.00 0.00 0% 608.00 522.88 100% 608.00 ### 522.88 100% 0.00 0.00 0%
01.14.03.04 MOVIMIENTO DE TIERRAS
01.14.03.04.01 EXCAVACION MASIVA (C/RETROEXCAVADOR) m3 136.33 18.01 2,455.30 0.00 0.00 0% 136.33 2,455.30 100% 136.33 ### 2,455.30 100% 0.00 0.00 0%
01.14.03.04.02 RELLENO CON GRAVA DE 4" 6" Y 8" m3 135 84.77 11,443.95 0.00 0.00 0% 135.00 11,443.95 100% 135.00 ### 11,443.95 100% 0.00 0.00 0%
01.14.03.04.03 ELIMINACION MANUAL DE MAT. EXEDENTE Y DESMONTE m3 170.41 14.45 2,462.42 0.00 0.00 0% 170.41 2,462.42 100% 170.41 ### 2,462.42 100% 0.00 0.00 0%
01.14.03.05 REFINE Y NIVELACION
01.14.03.05.01 REFINE Y NIVELACION EN TERRENO m2 608 6.74 4,097.92 0.00 0.00 0% 608.00 4,097.92 100% 608.00 ### 4,097.92 100% 0.00 0.00 0%
01.14.03.05.02 NIVELACION Y COMPACTACION BASE DE 0.20 M. m2 608 12.91 7,849.28 0.00 0.00 0% 608.00 7,849.28 100% 608.00 ### 7,849.28 100% 0.00 0.00 0%
01.14.03.06 CONCRETO SIMPLE
01.14.03.06.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA m2 60.15 72.99 4,390.35 0.00 0.00 0% 26.94 1,966.35 45% 26.94 ### 1,966.35 45% 33.21 2,424.00 55%
01.14.03.06.02 CONCRETO SIMPLE FC=175 KG/CM2 m3 92.53 540.58 50,019.87 0.00 0.00 0% 37.09 20,052.06 40% 37.09 ### 20,052.06 40% 55.44 29,967.81 60%
01.14.03.06.03 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 299 23.16 6,924.84 0.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.00 6,924.84 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 168.01 10.08 1,693.54 168.01 1,693.54 100% 0.00 0% 168.01 ### 1,693.54 100% 0.00 0.00 0%
01.15.05.02 EXCAVACION MANUAL m3 84.01 42.46 3,567.06 84.01 3,567.06 100% 0.00 0% 84.01 ### 3,567.06 100% 0.00 0.00 0%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 280.42 1,890.03 100% 0.00 0% 280.42 ### 1,890.03 100% 0.00 0.00 0%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 105.01 17.69 1,857.63 105.01 1,857.63 100% 0.00 0% 105.01 ### 1,857.63 100% 0.00 0.00 0%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 105.01 8.47 889.43 105.01 889.43 100% 0.00 0% 105.01 ### 889.43 100% 0.00 0.00 0%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 43.08 413.67 17,820.90 43.08 17,820.90 100% 0.00 0% 43.08 ### 17,820.90 100% 0.00 0.00 0%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 268.82 62.00 16,666.84 268.82 16,666.84 100% 0.00 0% 268.82 ### 16,666.84 100% 0.00 0.00 0%
01.15.05.08 REJILLA PARA CANALETA m 336.02 6.16 2,069.88 336.02 2,069.88 100% 0.00 0% 336.02 ### 2,069.88 100% 0.00 0.00 0%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 336.02 1.90 638.44 336.02 638.44 100% 0.00 0% 336.02 ### 638.44 100% 0.00 0.00 0%
COSTO DIRECTO 173,303.51 81,178.95 46.84% 52,807.93 30.47% ### 133,986.88 77.31% 39,316.65 22.69%
GASTOS GENERALES (11.33 %CD) 19,635.29 9,197.58 5,983.14 ### 15,180.71 4,454.57
GASTOS DE SUPERVISION (3.39 %CD) 5,874.99 2,751.97 1,790.19 4,542.16 1,332.83
SUB TOTAL 198,813.79 93,128.49 46.84% 60,581.25 30.47% 153,709.75 77.31% 45,104.06 22.69%
VALORIZACION MAYORES METRADOS N°- 04
( MES DE 26 DE JUNIO AL 25 DE JULIO DE 2020)
FECHA DE INICIO DE OBRA : ´01/07/2019
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL
ACTIVIDAD: FECHA DE PARALIZACION DE OBRA 12/20/2019
DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° : 75 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 8/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
MAYORES METRADOS
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 187.63 3.22 604.17 59.16 190.50 32% 128.47 413.67 68% 187.63 ### 604.17 100% 0.00 0.00 0%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 187.63 10.08 1,891.31 59.16 596.33 32% 128.47 1,294.98 68% 187.63 ### 1,891.31 100% 0.00 0.00 0%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 20.3 42.46 861.94 6.02 255.61 30% 14.28 606.33 70% 20.30 ### 861.94 100% 0.00 0.00 0%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 23.32 109.80 2,560.54 6.19 679.66 27% 17.13 1,880.87 73% 23.32 ### 2,560.54 100% 0.00 0.00 0%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 25.38 8.47 214.97 7.54 63.86 30% 17.84 151.10 70% 25.38 ### 214.97 100% 0.00 0.00 0%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 168.19 6.74 1,133.60 54.00 363.96 32% 114.19 769.64 68% 168.19 ### 1,133.60 100% 0.00 0.00 0%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 34.93 413.40 14,440.06 12.10 5,002.14 35% 22.83 9,437.92 65% 34.93 ### 14,440.06 100% 0.00 0.00 0%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 273.76 62.00 16,973.12 83.44 5,173.28 30% 190.32 11,799.84 70% 273.76 ### 16,973.12 100% 0.00 0.00 0%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.4 3.22 229.91 71.40 229.91 100% 0.00 0% 71.40 ### 229.91 100% 0.00 0.00 0%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 71.4 10.08 719.71 71.40 719.71 100% 0.00 0% 71.40 ### 719.71 100% 0.00 0.00 0%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 107.1 42.46 4,547.47 107.10 4,547.47 100% 0.00 0% 107.10 ### 4,547.47 100% 0.00 0.00 0%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 200.81 109.80 22,048.94 200.81 22,048.94 100% 0.00 0% 200.81 ### 22,048.94 100% 0.00 0.00 0%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 25.17 104.62 2,633.29 25.17 2,633.29 100% 0.00 0% 25.17 ### 2,633.29 100% 0.00 0.00 0%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 133.88 8.47 1,133.96 133.88 1,133.96 100% 0.00 0% 133.88 ### 1,133.96 100% 0.00 0.00 0%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 71.4 6.74 481.24 71.40 481.24 100% 0.00 0% 71.40 ### 481.24 100% 0.00 0.00 0%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 71.4 36.45 2,602.53 71.40 2,602.53 100% 0.00 0% 71.40 ### 2,602.53 100% 0.00 0.00 0%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 223.3 413.40 92,312.22 223.30 92,312.22 100% 0.00 0% 223.30 ### 92,312.22 100% 0.00 0.00 0%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 3624.91 5.19 18,813.28 3,624.91 18,813.28 100% 0.00 0% 3,624.91 ### 18,813.28 100% 0.00 0.00 0%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 167.79 62.00 10,402.98 167.79 10,402.98 100% 0.00 0% 167.79 ### 10,402.98 100% 0.00 0.00 0%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 29.85 30.00 895.50 29.85 895.50 100% 0.00 0% 29.85 ### 895.50 100% 0.00 0.00 0%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 2.23 23.16 51.65 2.23 51.65 100% 0.00 0% 2.23 ### 51.65 100% 0.00 0.00 0%
COSTO DIRECTO 195,552.39 169,198.01 86.52% 26,354.36 13.48% ### 195,552.37 100.00% 0.00 0.00%
GASTOS GENERALES (11.33 %CD) 22,156.09 19,170.13 2,985.95 ### 22,156.08 0.00
GASTOS DE SUPERVISION (3.39 %CD) 6,629.23 5,735.81 893.41 6,629.23 0.00
SUB TOTAL 224,337.70 194,103.96 86.52% 30,233.72 13.48% 224,337.68 100.00% 0.00 0.00%
RESUMEN GENERAL DE VALORIZACION N° 12
CORRESPONDIENTE DEL MES SETIEMBRE DEL 2020

PROYECTO MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE PICHARI
MODALIDAD DE EJECUCI
: ADMINISTRACIÓN DIRECTA RESIDENTE : ING. MARIO J.HUAYHUA BERROCAL
PRESUPUESTO EXP. T : S/. 2´278,432.36 SOLES SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA
AMPLIACION PRESUP. :NS/. 167,313.75 SOLES FECHA DE INICIO DE OBRA : 01 DE JULIO DEL 2019
AMPLIACION PRESUP. :NS/. 171,296.96 SOLES FECHA DE PARALIZACION DE OBR : 20 DE DICIEMRE DEL 2019
PLAZO DE EJECUCIÓN: 06
DEMESES (180 DIAS CALENDARIOS) FECHA DE REINICIO : 10 DE FEBRERO DEL 2020
AMPL. DE PLAZO N° 01 : 02 MESES + 15 DIAS (75 DIAS CALENDARIOS) FECHA DE PARALIZACION DE OBR : 16 DE MARZO DEL 2020
AMPL. DE PLAZO N° 02 : 01 MES (30 DIAS CALENDARIOS) FECHA DE REINICIO : 22 DE JUNIO DEL 2020
FECHA : SETIEMBRE DEL 2020 FECHA DE CULMINACION DE OBRA: 30 DE SETIEMBRE DEL 2020
PRESUPUESTO VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
ITEM DESCRIPCION
PROGRAMADO MONTO S/. % MONTO S/. % MONTO S/. % MONTO S/. %
01 VALORIZACION PRINCIPAL 2,278,432.36 1,891,409.38 83.01% 129,433.95 5.68% 2,020,843.33 88.69% 257,589.02 11.31%
02 VALORIZACION DE MAYORES METRADOS 195,552.39 195,552.39 100.00% - 0.00% 195,552.39 100.00% - 0.00%
03 VALORIZACION DE OBRAS ADICIONALES N 173,303.51 173,303.51 100.00% - 0.00% 173,303.51 100.00% - 0.00%
04 VALORIZACION DE OBRAS ADICIONALES N 169,453.93 - 0.00% 169,453.93 100.00% 169,453.93 100.00% - 0.00%
05 DEDUCTIVOS -257,589.02 - 0.00% - 0.00% - 0.00% -257,589.02 -11.31%
TOTAL COSTO DIRECTO 2,816,742.19 2,260,265.28 298,887.89 2,559,153.17 257,589.02

% AVANCE FISICO EJECUTADO 80.24% 10.61% 90.86% 9.14%


º

VALORIZACION DE ADICIONAL N° 01 APROBADO CON RESOLUCION N°0377-2020-MDP/CM.


( SETIEMBRE DEL 2020)

MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y


ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.11 CONSTRUCCIÓN DE MÓDULO COMPLEMENTARIO
01.11.09 CUBIERTAS
01.11.09.01 COBERTURA CON TEJA
01.11.09.01.01 COBERTURA CON TEJA ANDINA DECORATIVA m2 306.54 64.49 19,768.76 0.00 0% 0.00 0% 0.00 ### 0.00 0% 306.54 19,768.76 100%
01.11.09.01.02 CUMBRERA CON TEJA ANDINA DECORATIVA m 28.15 75.21 2,117.16 0.00 0% 0.00 0% 0.00 ### 0.00 0% 28.15 2,117.16 100%
01.12 CONSTRUCCIÓN DE SS.HH.
01.12.09 CUBIERTAS
01.12.09.01 COBERTURA CON TEJA
01.12.09.01.01 COBERTURA CON PLANCHA DE TEJA ANDINA m2 78.38 55.65 4,361.85 0.00 0% 0.00 0% 0.00 ### 0.00 0% 78.38 4,361.85 100%
01.12.09.01.02 CUMBRERA CON TEJA ANDINA DECORATIVA m 10.1 74.96 757.10 0.00 0% 0.00 0% 0.00 ### 0.00 0% 10.10 757.10 100%
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01.05 MEJORAMIENTO DE LOSA DEPORTIVA EXISTENTE
01.14.01.05.01 PICADO DE SUPERFICIE DE LOSA DEPORTIVA E=0.05 m m2 720 7.09 5,104.80 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 5,104.80 100%
01.14.01.05.02 CAPA DE CONCRETO E=0.05m ACABADO SEMIPULIDO EN LOSA m2 720 41.08 29,577.60 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 29,577.60 100%
01.14.01.05.03 PICADO LIMPIEZA Y REPOSICION DE JUNTAS DE DILATACION CON SELLO AS m 299.73 5.08 1,522.63 0.00 0% 0.00 0% 0.00 ### 0.00 0% 299.73 1,522.63 100%
01.14.01.05.04 CURADO DE LOSA DEPORTIVA CON AGUA m2 720 0.42 302.40 0.00 0% 0.00 0% 0.00 ### 0.00 0% 720.00 302.40 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.05 SISTEMA DE DRENAJE PLUVIAL
01.15.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 112.17 10.08 1,130.67 0.00 0% 0.00 0% 0.00 ### 0.00 0% 112.17 1,130.67 100%
01.15.05.02 EXCAVACION MANUAL m3 44.87 42.46 1,905.18 0.00 0% 0.00 0% 0.00 ### 0.00 0% 44.87 1,905.18 100%
01.15.05.03 REFINE Y NIVELACION EN TERRENO m2 280.42 6.74 1,890.03 0.00 0% 0.00 0% 0.00 ### 0.00 0% 280.42 1,890.03 100%
01.15.05.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 56.08 17.69 992.06 0.00 0% 0.00 0% 0.00 ### 0.00 0% 56.08 992.06 100%
01.15.05.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 56.08 8.47 475.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 56.08 475.00 100%
01.15.05.06 CANALETA CONCRETO F'C=175 KG/CM2 m3 28.04 413.67 11,599.31 0.00 0% 0.00 0% 0.00 ### 0.00 0% 28.04 11,599.31 100%
01.15.05.07 ENCOFRADO Y DESENCOFRADO m2 168.25 62.00 10,431.50 0.00 0% 0.00 0% 0.00 ### 0.00 0% 168.25 10,431.50 100%
01.15.05.08 REJILLA PARA CANALETA m 394.92 76.78 30,321.96 0.00 0% 0.00 0% 0.00 ### 0.00 0% 394.92 30,321.96 100%
01.15.05.09 PINTURA ANTICORROSIVA EPOXI ZINCROMATO m 394.92 4.65 1,836.38 0.00 0% 0.00 0% 0.00 ### 0.00 0% 394.92 1,836.38 100%
01.15.08 RAMPAS Y GRADERIAS
01.15.08.01 TRABAJOS PRELIMINARES
01.15.08.01.01 LIMPIEZA DE TERRENO
01.15.08.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 40.48 3.22 130.35 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 130.35 100%
01.15.08.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.08.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 40.48 10.08 408.04 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 408.04 100%
01.15.08.02 MOVIMIENTO DE TIERRAS
01.15.08.02.01 EXCAVACIONES
01.15.08.02.01.01 EXCAVACION MANUAL m3 4.05 42.46 171.96 0.00 0% 0.00 0% 0.00 ### 0.00 0% 4.05 171.96 100%
01.15.08.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 60.72 109.80 6,667.06 0.00 0% 0.00 0% 0.00 ### 0.00 0% 60.72 6,667.06 100%
01.15.08.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.08.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 5.06 8.47 42.86 0.00 0% 0.00 0% 0.00 ### 0.00 0% 5.06 42.86 100%
01.15.08.02.03 REFINE Y NIVELACION
01.15.08.02.03.01 REFINE Y NIVELACION EN TERRENO m2 40.48 6.74 272.84 0.00 0% 0.00 0% 0.00 ### 0.00 0% 40.48 272.84 100%
01.15.08.03 OBRAS DE CONCRETO SIMPLE
01.15.08.03.01 CONCRETO F'C=175 KG/CM2 m3 7.21 413.40 2,980.61 0.00 0% 0.00 0% 0.00 ### 0.00 0% 7.21 2,980.61 100%
01.15.08.03.02 ENCOFRADO Y DESENCOFRADO m2 11.88 62.00 736.56 0.00 0% 0.00 0% 0.00 ### 0.00 0% 11.88 736.56 100%
01.15.09 MURO DE CONTENCION
01.15.09.01 TRABAJOS PRELIMINARES
01.15.09.01.01 LIMPIEZA DE TERRENO
01.15.09.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 80.89 3.22 260.47 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 260.47 100%
01.15.09.01.02 TRAZO, NIVELES Y REPLANTEO
01.15.09.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 80.89 10.08 815.37 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 815.37 100%
01.15.09.02 MOVIMIENTO DE TIERRAS
01.15.09.02.01 EXCAVACIONES
01.15.09.02.01.01 EXCAVACION MANUAL m3 121.34 42.46 5,152.10 0.00 0% 0.00 0% 0.00 ### 0.00 0% 121.34 5,152.10 100%
01.15.09.02.01.02 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 114.32 109.80 12,552.34 0.00 0% 0.00 0% 0.00 ### 0.00 0% 114.32 12,552.34 100%
01.15.09.02.01.03 RELLENO CON MATERIAL GRAVA DE 3/4" m3 27.03 104.62 2,827.88 0.00 0% 0.00 0% 0.00 ### 0.00 0% 27.03 2,827.88 100%
01.15.09.02.02 ELIMINACION DE MATERIAL EXEDENTE
01.15.09.02.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 151.67 8.47 1,284.64 0.00 0% 0.00 0% 0.00 ### 0.00 0% 151.67 1,284.64 100%
01.15.09.02.03 REFINE Y NIVELACION
01.15.09.02.03.01 REFINE Y NIVELACION EN TERRENO m2 80.89 6.74 545.20 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 545.20 100%
01.15.09.03 OBRAS DE CONCRETO SIMPLE
01.15.09.03.01 SOLADO
01.15.09.03.01.01 SOLADO PARA ZAPATAS E=4" C-H 1:12 m2 80.89 36.45 2,948.44 0.00 0% 0.00 0% 0.00 ### 0.00 0% 80.89 2,948.44 100%
01.15.09.04 OBRAS DE CONCRETO ARMADO
01.15.09.04.01 CONCRETO F'C=175 KG/CM2 m3 58.29 413.40 24,097.09 0.00 0% 0.00 0% 0.00 ### 0.00 0% 58.29 24,097.09 100%
01.15.09.04.02 ACERO DE REFUERZO FY=4200 KG/CM2. MURO DE CONTENCION kg 4877.83 5.19 25,315.94 0.00 0% 0.00 0% 0.00 ### 0.00 0% 4,877.83 25,315.94 100%
01.15.09.04.03 ENCOFRADO Y DESENCOFRADO m2 180.22 62.00 11,173.64 0.00 0% 0.00 0% 0.00 ### 0.00 0% 180.22 11,173.64 100%
01.15.09.05 OTROS
01.15.09.05.01 TUBERIA PVC SAL Ø 4" PARA DRENAJE m 15.39 30.00 461.70 0.00 0% 0.00 0% 0.00 ### 0.00 0% 15.39 461.70 100%
01.15.09.05.02 JUNTA E=1" CON ESPUMA PLASTICA Y JEBE MICROPOROSO m 3.07 23.16 71.10 0.00 0% 0.00 0% 0.00 ### 0.00 0% 3.07 71.10 100%
COSTO DIRECTO 223,010.58 0.00 0.00% 0.00 0.00% ### 0.00 0.00% 223,010.73 100.00%
GASTOS GENERALES (11.33 %CD) 25,267.10 0.00 0.00 ### 0.00 25,267.10
GASTOS DE SUPERVISION (3.39 %CD) 7,560.06 0.00 0.00 - 7,560.06
SUB TOTAL 255,837.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 255,837.89 100.00%
VALORIZACION DEDUCTIVO N°02 APROBADOCON RESOLUCION N° 193-2020-MDP/LC.
( SETIEMBRE DEL 2020)
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y
ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.14 LOSA DEPORTIVO MULTIUSO+TRIBUNA DE CONCRETO ARMADO+COBERTURA
01.14.01 CONSTRUCCION DE TRIBUNA
01.14.01.01 TRABAJOS PRELIMINARES
01.14.01.01.01 LIMPIEZA DE TERRENO
01.14.01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 91 3.22 293.02 0.00 0% 0.00 0% 0.00 ### 0.00 0% 91.00 293.02 100%
01.14.01.01.02 TRAZO, NIVELES Y REPLANTEO
01.14.01.01.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 91 10.08 917.28 0.00 0% 0.00 0% 0.00 ### 0.00 0% 91.00 917.28 100%
01.14.01.02 MOVIMIENTO DE TIERRAS
01.14.01.02.01 EXCAVACIONES
01.14.01.02.01.01 EXCAVACION MANUAL P LOSA, TRIBUNA, /UÑA Y CUNETA m3 29.82456 42.46 1,266.35 0.00 0% 0.00 0% 0.00 ### 0.00 0% 29.82 1,266.35 100%
01.14.01.02.01.02 REFINE Y NIVELACION EN TERRENO m2 64.8364 6.74 437.00 0.00 0% 0.00 0% 0.00 ### 0.00 0% 64.84 437.00 100%
01.14.01.02.01.04 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 37.2782 17.69 659.45 0.00 0% 0.00 0% 0.00 ### 0.00 0% 37.28 659.45 100%
01.14.01.02.01.05 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 37.2782 8.47 315.75 0.00 0% 0.00 0% 0.00 ### 0.00 0% 37.28 315.75 100%
01.14.01.04 CANALETA PLUVIAL DE LOSA DEPORTIVA
01.14.01.04.01 CONCRETO EN CANALETA F'C=175 KG/CM2 m3 14.1 413.40 5,828.94 0.00 0% 0.00 0% 0.00 ### 0.00 0% 14.10 5,828.94 100%
01.14.01.04.02 ENCOFRADO Y DESENCOFRADO EN CANALETA m2 146.86 62.00 9,105.32 0.00 0% 0.00 0% 0.00 ### 0.00 0% 146.86 9,105.32 100%
01.14.01.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 EN CANALETAS kg 206.19 5.19 1,070.13 0.00 0% 0.00 0% 0.00 ### 0.00 0% 206.19 1,070.13 100%
COSTO DIRECTO 19,893.19 0.00 0.00% 0.00 0.00% ### 0.00 0.00% 19,893.42 100.00%
GASTOS GENERALES (11.13 %CD) 2,214.11 0.00 0.00 ### 0.00 2,214.11
GASTOS DE SUPERVISION (3.39 %CD) 674.38 0.00 0.00 - 674.38
SUB TOTAL 22,781.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 22,781.91 100.00%
VALORIZACION DEDUCTIVO S/N RESOLUCION
( SETIEMBRE DEL 2020)
MEJORAMIENTO Y AMPLIACIÓN DE LAS I.E. SECUNDARIA BARTOLOME HERRERA,QUISTO CENTRAL Y
ACTIVIDAD: FECHA DE INICIO DE OBRA : ´01/07/2019
CATARATA EN EL DISTRITO DE PICHARI-LA CONVENCIÓN-CUSCO(QUISTO CENTRAL)"
MOD. DE EJECUCION : ADM. DIRECTA FECHA DE PARALIZACION DE OBRA 12/20/2019
PLAZO DE EJECUCION EXP. : 06 MESES (180 DIAS) AMPLIACION DE PLAZO N°01 2 MESES + 15 DIAS
AMP.PLAZO N° 01 : 75 DIAS CALENDARIOS FECHA DE REINICIO DE OBRA 2/10/2020
AMP.PLAZO N° 02 : 30 DIAS CALENDARIOS FECHA DE PARALIZACION DE OBRA 3/16/2020
SUPERVISOR : ING. ALEXANDER REMUZGO GUEVARA FECHA DE REINICIO DE OBRA 6/22/2020
RESIDENTE : ING. MARIO JOSEPH HUAYHUA BERROCAL FECHA DE TERMINACION DE OBRA 9/30/2020
PRESUPUESTO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR
MONTO MONTO MONTO MONTO
ÍTEM PARTIDA COSTO COSTO
METR. UNITARIO PARCIAL METR. VALORIZAC. % METR. VALORIZAC. % METR. VALORIZAC. % METR. %
UND (S/.) (S/.) VALORIZ. TOTAL
TOTAL TOTAL TOTAL
01 EXISTENCIA DE IFRAESTRCUTURA EDUCATIVA SECUNDARIA QUISTO CENTRAL
01.08 MEJORAMIENTO DE 04 AULAS Y ESCALERA
01.08.03 REPOSICION DE CANALETA PLUVIAL
01.08.03.01 CANAL SEMICIRCULAR PLANCHA DE ALUMINIO m 94 97.96 9,208.24 0.00 0% 0.00 0% 0.00 ### 0.00 0% 94.00 9,208.24 100%
01.10 MEJORAMIENTO DE CERCO PERIMÉTRICO
01.10.01 TARRAJEO EN GENERAL
01.10.01.01 TARRAJEO EN INTERIORES Y EXTERIORES E=1.5 CM MEZCLA 1:5 m2 50.625 25.87 1,309.67 0.00 0% 0.00 0% 0.00 ### 0.00 0% 50.63 1,309.67 100%
01.10.01.02 TARRAJEO DE SUPERFICIES DE COLUMNAS m2 8.1 32.01 259.28 0.00 0% 0.00 0% 0.00 ### 0.00 0% 8.10 259.28 100%
01.10.01.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 19.88 34.26 681.09 0.00 0% 0.00 0% 0.00 ### 0.00 0% 19.88 681.09 100%
01.10.01.04 EJECUCION DE BRUÑAS m 51.6 8.22 424.15 0.00 0% 0.00 0% 0.00 ### 0.00 0% 51.60 424.15 100%
01.10.02 PINTURAS
01.10.02.01 PINTURA AL LATEX DOS MANOS EN MUROS INTERIORES y EXT. m2 50.625 12.41 628.26 0.00 0% 0.00 0% 0.00 ### 0.00 0% 50.63 628.26 100%
01.10.02.02 PINTURA AL LATEX DOS MANOS EN COLUMNAS m2 8.1 14.34 116.15 0.00 0% 0.00 0% 0.00 ### 0.00 0% 8.10 116.15 100%
01.10.02.03 PINTURA AL LATEX DOS MANOS EN VIGAS m2 5.63 14.34 80.73 0.00 0% 0.00 0% 0.00 ### 0.00 0% 5.63 80.73 100%
01.10.02.04 PINTURA EN ZOCALOS m 76 9.31 707.56 0.00 0% 0.00 0% 0.00 ### 0.00 0% 76.00 707.56 100%
01.15 CONSTRUCCIÓN DE OBRAS EXTERIORES
01.15.06 INSTALACIONES SANITARIAS EXTERIORES
01.15.06.02 SISTEMA DE DESAGUE
01.15.06.02.04 CAJA DE REGISTRO
01.15.06.02.04.01 MOVIMIENTO DE TIERRAS
01.15.06.02.04.01.01 EXCAVACION DE PARA ESTRUTURAS m3 1.1 42.46 46.71 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.10 46.71 100%
01.15.06.02.04.01.02 ACARREO DE MATERIAL EXCEDENTE FUERA DE OBRA m3 1.44 17.69 25.47 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.44 25.47 100%
01.15.06.02.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE m3 1.44 8.47 12.20 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.44 12.20 100%
01.15.06.02.04.02 CONCRETO ARMADO
01.15.06.02.04.02.01 ACERO DE REFUERZO FY = 4200 KG/CM2 EN CAJA DE REGISTRO kg 38.03 5.19 197.38 0.00 0% 0.00 0% 0.00 ### 0.00 0% 38.03 197.38 100%
01.15.06.02.04.02.02 ENCOFRADO Y DESENCOFRADO PARA CAJA DE REGISTRO m2 7.13 62.00 442.06 0.00 0% 0.00 0% 0.00 ### 0.00 0% 7.13 442.06 100%
01.15.06.02.04.02.03 CONCRETO F'C=175 KG/CM2 PARA ESTRUCTURA m3 1.32 413.67 546.04 0.00 0% 0.00 0% 0.00 ### 0.00 0% 1.32 546.04 100%
COSTO DIRECTO 14,685.19 0.00 0.00% 0.00 0.00% ### 0.00 0.00% 14,685.18 100.00%
GASTOS GENERALES (11.13 %CD) 1,195.82 0.00 0.00 ### 0.00 1,195.82
GASTOS DE SUPERVISION (3.39 %CD) 506.57 0.00 0.00 - 506.57
SUB TOTAL 16,387.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,387.57 100.00%