CRONOGRAMA PROGRAMADO - CONTRACTUAL GORE

PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E. Nº 320 – CHAVIN,
DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

AGOSTO 2020 SETIEMBRE 2020 OCTUBRE 2020 NOCIEMBRE 2020 DICIEMBRE 2020
DESCRIPCIÓN AVANCE DE OBRA
01 31 01 30 01 31 01 30 01 15

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 536,858.52 S/. 133,281.84 S/. 759,322.64 S/. 823,571.89 S/. 682,243.08 S/. 189,494.26
% AVANCE DE MES 17.18% 4.27% 24.30% 26.36% 21.83% 6.06%
% AVANCE ACUMULADO MENSUAL 17.18% 21.45% 45.75% 72.10% 93.94% 100.00%
GASTOS GENERALES 9.21% S/. 49,421.34 S/. 12,269.47 S/. 69,900.62 S/. 75,815.18 S/. 62,804.94 S/. 17,444.19
UTILIDAD 9.00% S/. 48,317.27 S/. 11,995.37 S/. 68,339.04 S/. 74,121.47 S/. 61,401.88 S/. 17,054.48
SUBTOTAL S/. 634,597.13 S/. 157,546.67 S/. 897,562.29 S/. 973,508.54 S/. 806,449.90 S/. 223,992.93
IGV (18%) S/. 114,227.48 S/. 28,358.40 S/. 161,561.21 S/. 175,231.54 S/. 145,160.98 S/. 40,318.73
TOTAL MENSUAL S/. 748,824.61 S/. 185,905.07 S/. 1,059,123.50 S/. 1,148,740.08 S/. 951,610.88 S/. 264,311.66

GRÁFICO DE AVANCE DE OBRA


100%

90%

80%

70%
% DE AVANCE

60%

50%

40%

30%

20%

10%

0%
1 2 3 4 5 6 7
CURVA "S"
PROGRAMADO VS EJECUTADO
MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°
22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA
100.00% –
100.00% DEPARTAMENTO DE ICA
Avance Programado Avance Ejecutado

90.00%
83.42%

80.00%

70.00%

59.44%
60.00%

50.00%
42.02%
40.00%

30.00% 26.70%

20.00%

11.40%
10.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0.00% 0.00%
- del 01/02/19 al 28/02/19 del 01/03/19 al 31/03/19 del 01/04/19 al 30/04/19 del 01/05/19 al 31/05/19 del 01/06/19 al 30/06/19 del 01/07/19 al 30/07/19
CRONOGRAMA REPROGRAMADO - CONTRACTUAL GORE
PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E.
Nº 320 – CHAVIN, DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

FEBRERO 2019 MARZO 2019 ABRIL 2019 MAYO 2019 JUNIO 2019 JULIO 2019
DESCRIPCIÓN
01 28 01 31 01 30 01 31 01 30 01 30

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 81,114.73 S/. 108,864.51 S/. 109,006.81 S/. 123,949.00 S/. 170,625.55 S/. 117,972.13
% AVANCE DE MES 11.40% 15.30% 15.32% 17.42% 23.98% 16.58%
% AVANCE ACUMULADO MENSUAL 11.40% 26.70% 42.02% 59.44% 83.42% 100.00%
GASTOS GENERALES 22.00% S/. 17,845.24 S/. 23,950.19 S/. 23,981.50 S/. 27,268.78 S/. 37,537.62 S/. 25,953.87
UTILIDAD 10.00% S/. 8,111.47 S/. 10,886.45 S/. 10,900.68 S/. 12,394.90 S/. 17,062.55 S/. 11,797.21
SUBTOTAL S/. 107,071.44 S/. 143,701.15 S/. 143,888.99 S/. 163,612.68 S/. 225,225.72 S/. 155,723.21
IGV (18%) S/. 19,272.86 S/. 25,866.21 S/. 25,900.02 S/. 29,450.28 S/. 40,540.63 S/. 28,030.18
TOTAL MENSUAL S/. 126,344.30 S/. 169,567.35 S/. 169,789.01 S/. 193,062.96 S/. 265,766.35 S/. 183,753.38

GRÁFICO DE AVANCE DE OBRA


100% 100.00%

90%
83.42%
80%

70%

60%
% DE AVANCE

59.44%

50%

42.02%
40%

30%
26.70%
20%

10% 11.40%

0% 0.00%
1 2 3 4 5 6 7
20%

10% 11.40%

0% 0.00%
1 2 3 4 5 6 7
CRONOGRAMA EJECUTADO - CONTRACTUAL GORE
PROYECTO: "MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E.
Nº 320 – CHAVIN, DISTRITO CHAVIN – PROVINCIA CHINCHA – ICA"

FEBRERO 2019 MARZO 2019 ABRIL 2019 MAYO 2019 JUNIO 2019 JULIO 2019
DESCRIPCIÓN
01 28 01 31 01 30 01 31 01 30 01 30

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
% AVANCE DE MES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
% AVANCE ACUMULADO MENSUAL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
GASTOS GENERALES 22.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
UTILIDAD 10.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
SUBTOTAL S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
IGV (18%) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
TOTAL MENSUAL S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00

GRÁFICO DE AVANCE DE OBRA


100%

90%

80%

70%

60%
% DE AVANCE

50%

40%

30%

20%

10%

0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


1 2 3 4 5 6 7
RESUMEN DE AVANCE DE EJECUCIÓN

VALORIZACION PERIODO PROGRAMADO EJECUTADO


ACUMULADO ACUMULADO
INICIO - 0.00% 0.00%
VAL 01 del 01/02/19 al 28/02/19 11.40% 0.00%
VAL 02 del 01/03/19 al 31/03/19 26.70% 0.00%
VAL 03 del 01/04/19 al 30/04/19 42.02% 0.00%
VAL 04 del 01/05/19 al 31/05/19 59.44% 0.00%
VAL 05 del 01/06/19 al 30/06/19 83.42% 0.00%
VAL 06 del 01/07/19 al 30/07/19 100.00% 0.00%
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : PARADIZO S.R.L.
PLAZO : 180 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 06
01/10/2018 AL 31/10/2018

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

01 TRABAJOS GENERALES 114,563.43


01.01 OBRAS PROVISIONALES 6,950.00
01.01.01 CARTEL PARA LA OBRA 2.40 X 3.60 und 1.00 950.00 950.00 1.00 950.00 100.00% 0.00 0.00 0.00% 1.00 950.00 100.00% 0.00 0.00 0.00%
01.01.02 ALMACEN DE OBRA glb 1.00 6,000.00 6,000.00 0.80 4,800.00 80.00% 0.00 0.00 0.00% 0.80 4,800.00 80.00% 0.20 1,200.00 20.00%
01.02 OBRAS PRELIMINARES 107,613.43
01.02.01 TRANSPORTE DE MATERIALES A OBRA glb 1.00 58,980.01 58,980.01 0.40 23,592.00 40.00% 0.00 0.00 0.00% 0.40 23,592.00 40.00% 0.60 35,388.01 60.00%
01.02.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIE glb 1.00 22,199.02 22,199.02 0.90 19,979.12 90.00% 0.00 0.00 0.00% 0.90 19,979.12 90.00% 0.10 2,219.90 10.00%
01.02.03 IMPLEMENTOS DE SEGURIDAD PARA LOS TRABAJADORES glb 1.00 10,000.00 10,000.00 1.00 10,000.00 100.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00% 0.00 0.00 0.00%
01.02.04 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 80.00 189.58 15,166.40 80.00 15,166.40 100.00% 0.00 0.00 0.00% 80.00 15,166.40 100.00% 0.00 0.00 0.00%
01.02.05 ELIMINACION DE MATERIAL DEMOLIDO CARGUIO C/EQ 125HP m3 80.00 15.85 1,268.00 80.00 1,268.00 100.00% 0.00 0.00 0.00% 80.00 1,268.00 100.00% 0.00 0.00 0.00%
02 SECTOR INICIAL 225,861.54
02.01 ESTRUCTURAS 84,768.77
02.01.01 OBRAS PRELIMINARES 372.30
02.01.01.01 LIMPIEZA DE TERRENO m2 138.40 0.95 131.48 138.40 131.48 100.00% 0.00 0.00 0.00% 138.40 131.48 100.00% 0.00 0.00 0.00%
02.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 138.40 1.74 240.82 138.40 240.82 100.00% 0.00 0.00 0.00% 138.40 240.82 100.00% 0.00 0.00 0.00%
02.01.02 MOVIMIENTO DE TIERRAS 7,902.25
02.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 35.16 41.41 1,455.98 35.16 1,455.98 100.00% 0.00 0.00 0.00% 35.16 1,455.98 100.00% 0.00 0.00 0.00%
02.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 50.40 41.41 2,087.06 50.40 2,087.06 100.00% 0.00 0.00 0.00% 50.40 2,087.06 100.00% 0.00 0.00 0.00%
02.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 112.10 2.48 278.01 112.10 278.01 100.00% 0.00 0.00 0.00% 112.10 278.01 100.00% 0.00 0.00 0.00%
02.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 32.53 27.36 890.02 32.53 890.02 100.00% 0.00 0.00 0.00% 32.53 890.02 100.00% 0.00 0.00 0.00%
02.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 11.21 197.01 2,208.48 11.21 2,208.48 100.00% 0.00 0.00 0.00% 11.21 2,208.48 100.00% 0.00 0.00 0.00%
02.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 62.00 15.85 982.70 62.00 982.70 100.00% 0.00 0.00 0.00% 62.00 982.70 100.00% 0.00 0.00 0.00%
02.01.03 OBRAS DE CONCRETO SIMPLE 15,500.07
02.01.03.01 SOLADO PARA ZAPATAS m2 36.00 35.13 1,264.68 36.00 1,264.68 100.00% 0.00 0.00 0.00% 36.00 1,264.68 100.00% 0.00 0.00 0.00%
02.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 13.08 333.17 4,357.86 13.08 4,357.86 100.00% 0.00 0.00 0.00% 13.08 4,357.86 100.00% 0.00 0.00 0.00%
02.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.39 387.67 2,089.54 5.39 2,089.54 100.00% 0.00 0.00 0.00% 5.39 2,089.54 100.00% 0.00 0.00 0.00%
02.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 71.83 46.45 3,336.50 71.83 3,336.50 100.00% 0.00 0.00 0.00% 71.83 3,336.50 100.00% 0.00 0.00 0.00%
02.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 112.10 39.71 4,451.49 112.10 4,451.49 100.00% 0.00 0.00 0.00% 112.10 4,451.49 100.00% 0.00 0.00 0.00%
02.01.04 OBRAS DE CONCRETO ARMADO 60,994.15
02.01.04.01 ZAPATAS 10,006.67
02.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 18.00 449.81 8,096.58 18.00 8,096.58 100.00% 0.00 0.00 0.00% 18.00 8,096.58 100.00% 0.00 0.00 0.00%
02.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 456.96 4.18 1,910.09 456.96 1,910.09 100.00% 0.00 0.00 0.00% 456.96 1,910.09 100.00% 0.00 0.00 0.00%
02.01.04.02 VIGA DE CIMENTACION 13,214.46
02.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 9.50 449.81 4,273.20 9.50 4,273.20 100.00% 0.00 0.00 0.00% 9.50 4,273.20 100.00% 0.00 0.01 0.00%
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 76.00 51.41 3,907.16 76.00 3,907.16 100.00% 0.00 0.00 0.00% 76.00 3,907.16 100.00% 0.00 0.00 0.00%
02.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,204.33 4.18 5,034.10 1,204.33 5,034.10 100.00% 0.00 0.00 0.00% 1,204.33 5,034.10 100.00% 0.00 0.00 0.00%
02.01.04.03 COLUMNAS Y PLACAS 19,610.14
02.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 11.53 449.81 5,186.31 11.53 5,186.31 100.00% 0.00 0.00 0.00% 11.53 5,186.31 100.00% 0.00 0.00 0.00%
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 127.00 53.08 6,741.16 127.00 6,741.16 100.00% 0.00 0.00 0.00% 127.00 6,741.16 100.00% 0.00 0.00 0.00%
02.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,837.96 4.18 7,682.67 1,837.96 7,682.67 100.00% 0.00 0.00 0.00% 1,837.96 7,682.67 100.00% 0.00 0.00 0.00%
02.01.04.04 VIGAS 15,656.91
02.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 10.19 449.81 4,583.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.19 4,583.56 100.00%
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 98.14 62.13 6,097.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 6,097.44 100.00%
02.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,190.41 4.18 4,975.91 0.00 0.00 0.00% 1,190.41 4,975.91 100.00% 1,190.41 4,975.91 100.00% 0.00 0.00 0.00%

Página 7
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.01.04.05 COLUMNETAS 2,505.97


02.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.33 419.72 558.23 1.33 558.23 100.00% 0.00 0.00 0.00% 1.33 558.23 100.00% 0.00 0.00 0.00%
02.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 17.76 53.08 942.70 17.76 942.70 100.00% 0.00 0.00 0.00% 17.76 942.70 100.00% 0.00 0.00 0.00%
02.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 240.44 4.18 1,005.04 240.44 1,005.04 100.00% 0.00 0.00 0.00% 240.44 1,005.04 100.00% 0.00 0.00 0.00%
02.02 ARQUITECTURA 119,572.63
02.02.01 ALBAÑILERIA 6,173.76
02.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 111.48 55.38 6,173.76 111.48 6,173.76 100.00% 0.00 0.00 0.00% 111.48 6,173.76 100.00% 0.00 0.00 0.00%
02.02.02 REVOQUES 16,085.43
02.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 140.42 26.62 3,737.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.42 3,737.98 100.00%
02.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 93.80 26.62 2,496.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 93.80 2,496.96 100.00%
02.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 139.00 28.80 4,003.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 139.00 4,003.20 100.00%
02.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 245.20 3.45 845.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 245.20 845.94 100.00%
02.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 98.14 31.39 3,080.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 3,080.61 100.00%
02.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 99.44 3.45 343.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99.44 343.07 100.00%
02.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 64.80 13.60 881.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.80 881.28 100.00%
02.02.02.08 BRUÑAS DE 1.0 cm m 74.72 9.32 696.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.72 696.39 100.00%
02.02.03 PISOS Y PAVIMENTOS 10,893.71
02.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 118.50 35.38 4,192.53 118.50 4,192.53 100.00% 0.00 0.00 0.00% 118.50 4,192.53 100.00% 0.00 0.00 0.00%
02.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 118.50 56.55 6,701.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 118.50 6,701.18 100.00%
02.02.04 CONTRAZOCALOS 5,499.22
02.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 77.10 19.27 1,485.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.10 1,485.72 100.00%
02.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 96.80 15.40 1,490.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 96.80 1,490.72 100.00%
02.02.04.03 ZOCALO DE CERAMICA 20 X 30 CM m2 27.15 92.92 2,522.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.15 2,522.78 100.00%
02.02.05 CARPINTERIA MADERA 3,658.71
02.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.72 496.22 2,838.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 2,838.38 100.00%
02.02.05.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 2.34 350.57 820.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.34 820.33 100.00%
02.02.06 CARPINTERIA METALICA 7,302.36
02.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 37.84 192.98 7,302.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.84 7,302.36 100.00%
02.02.07 CERRAJERIA 245.96
02.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
02.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 10.00 9.01 90.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 90.10 100.00%
02.02.08 VIDRIOS, CRISTALES Y SIMILARES 5,262.45
02.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 407.31 12.92 5,262.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 407.31 5,262.45 100.00%
02.02.09 PINTURAS 4,843.26
02.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 222.96 10.57 2,356.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.96 2,356.69 100.00%
02.02.09.02 PINTURA EN CONTRAZOCALO m2 9.68 7.96 77.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.68 77.05 100.00%
02.02.09.03 PINTURA EN VIGAS m2 98.14 13.73 1,347.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 98.14 1,347.46 100.00%
02.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 80.52 13.19 1,062.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 80.52 1,062.06 100.00%
02.02.10 CUBIERTA METALICA Y CIELO RASO 59,607.77
02.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 190.30 122.00 23,216.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 190.30 23,216.60 100.00%
02.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 183.00 75.18 13,757.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 183.00 13,757.94 100.00%
02.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 194.11 116.60 22,633.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 194.11 22,633.23 100.00%
02.03 INSTALACIONES ELECTRICAS 14,806.77
02.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 25.00 145.99 3,649.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 3,649.75 100.00%
02.03.02 SALIDA TOMACORRIENTE pto 8.00 215.17 1,721.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,721.36 100.00%
02.03.03 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 2.00 219.38 438.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 438.76 100.00%
02.03.04 SALIDA PARA INTERRUPTOR SIMPLE pto 5.00 108.23 541.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 541.15 100.00%
02.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%
02.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 22.00 205.71 4,525.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 4,525.62 100.00%
02.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 3.00 68.59 205.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 205.77 100.00%
02.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 136.56 10.81 1,476.21 90.00 972.90 65.91% 0.00 0.00 0.00% 90.00 972.90 65.91% 46.56 503.31 34.09%
02.03.09 ALAMBRE THHN 2.5 mm2 m 264.68 1.67 442.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 264.68 442.02 100.00%
02.03.10 ALAMBRE THHN 4 mm2 m 106.00 2.19 232.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 106.00 232.14 100.00%
02.03.11 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
02.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
02.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
02.04 INSTALACIONES SANITARIAS 6,713.37
02.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88

Página 8
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
02.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
02.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
02.04.02 SISTEMA DE DESAGUE 2,066.22
02.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
02.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.08 100.00%
02.04.02.03 SALIDA VENTILACION DE 2" pto 2.00 58.08 116.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 116.16 100.00%
02.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
02.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
02.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.00 33.95 339.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 339.50 100.00%
02.04.02.07 YEE PVC SAL 4"X2" und 3.00 61.97 185.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 185.91 100.00%
02.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
02.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 10.00 14.89 148.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 148.90 100.00%
02.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.00 3.86 38.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 38.60 100.00%
02.04.02.11 CAMA DE APOYO m 10.00 9.44 94.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 94.40 100.00%
02.04.02.12 RELLENO COMPACTADO DE ZANJAS m 10.00 12.00 120.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 120.00 100.00%
02.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.03 SISTEMA DE AGUA FRIA 955.73
02.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 291.36 100.00%
02.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 8.05 17.01 136.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.05 136.93 100.00%
02.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.94 100.00%
02.04.03.04 TEE PVC 1/2" und 3.00 11.04 33.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 33.12 100.00%
02.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 7.05 14.89 104.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 104.97 100.00%
02.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 7.05 3.86 27.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 27.21 100.00%
02.04.03.07 CAMA DE APOYO m 7.05 9.44 66.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 66.55 100.00%
02.04.03.08 RELLENO COMPACTADO DE ZANJAS m 7.05 12.00 84.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 84.60 100.00%
02.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
02.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
02.04.04 SISTEMA DE AGUA PLUVIAL 2,497.54
02.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.60 58.77 2,150.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.60 2,150.98 100.00%
02.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
02.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
03 SECTOR SECUNDARIA 373,415.79
03.01 ESTRUCTURAS 157,033.01
03.01.01 OBRAS PRELIMINARES 311.88
03.01.01.01 LIMPIEZA DE TERRENO m2 115.94 0.95 110.14 115.94 110.14 100.00% 0.00 0.00 0.00% 115.94 110.14 100.00% 0.00 0.00 0.00%
03.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 115.94 1.74 201.74 115.94 201.74 100.00% 0.00 0.00 0.00% 115.94 201.74 100.00% 0.00 0.00 0.00%
03.01.02 MOVIMIENTO DE TIERRAS 11,127.55
03.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 20.92 41.41 866.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.92 866.30 100.00%
03.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 85.68 41.41 3,548.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 85.68 3,548.01 100.00%
03.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.00 2.48 260.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.00 260.40 100.00%
03.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 55.88 27.36 1,528.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.88 1,528.88 100.00%
03.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 19.69 197.01 3,879.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.69 3,879.13 100.00%
03.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 65.92 15.85 1,044.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.92 1,044.83 100.00%
03.01.03 OBRAS DE CONCRETO SIMPLE 12,111.33
03.01.03.01 SOLADO PARA ZAPATAS m2 65.83 35.13 2,312.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.83 2,312.61 100.00%
03.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.72 333.17 1,905.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 1,905.73 100.00%
03.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 3.70 387.67 1,434.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 1,434.38 100.00%
03.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 49.28 46.45 2,289.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.28 2,289.06 100.00%
03.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.00 39.71 4,169.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.00 4,169.55 100.00%
03.01.04 OBRAS DE CONCRETO ARMADO 133,482.25
03.01.04.01 ZAPATAS 20,484.56
03.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 35.51 449.81 15,972.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.51 15,972.75 100.00%
03.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,079.38 4.18 4,511.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,079.38 4,511.81 100.00%
03.01.04.02 VIGA DE CIMENTACION 12,509.61
03.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 8.59 449.81 3,863.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.59 3,863.87 100.00%
03.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 68.75 51.41 3,534.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 68.75 3,534.44 100.00%
03.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,222.80 4.18 5,111.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,222.80 5,111.30 100.00%

Página 9
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.01.04.03 COLUMNAS Y PLACAS 47,206.14


03.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 27.42 449.81 12,333.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.42 12,333.79 100.00%
03.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 281.66 53.08 14,950.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 281.66 14,950.51 100.00%
03.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 4,765.99 4.18 19,921.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,765.99 19,921.84 100.00%
03.01.04.04 VIGAS 27,967.41
03.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.99 449.81 7,642.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.99 7,642.27 100.00%
03.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 163.64 62.13 10,166.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 163.64 10,166.95 100.00%
03.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 2,430.19 4.18 10,158.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,430.19 10,158.19 100.00%
03.01.04.05 LOSAS ALIGERADAS 16,968.05
03.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 11.60 449.81 5,217.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.60 5,217.80 100.00%
03.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 132.54 51.12 6,775.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 6,775.44 100.00%
03.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 466.17 4.18 1,948.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 466.17 1,948.59 100.00%
03.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,104.46 2.74 3,026.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,104.46 3,026.22 100.00%
03.01.04.06 COLUMNETAS 7,805.24
03.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 4.39 419.72 1,842.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.39 1,842.57 100.00%
03.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 58.56 53.08 3,108.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.56 3,108.36 100.00%
03.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 682.85 4.18 2,854.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 682.85 2,854.31 100.00%
03.01.04.07 VIGAS COLLARIN 541.24
03.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.38 419.72 159.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 159.49 100.00%
03.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 5.12 53.08 271.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.12 271.77 100.00%
03.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.31 4.18 109.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.31 109.98 100.00%
03.02 ARQUITECTURA 161,830.49
03.02.01 ALBAÑILERIA 8,900.12
03.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 160.71 55.38 8,900.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.71 8,900.12 100.00%
03.02.02 REVOQUES 27,991.70
03.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 210.39 26.62 5,600.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.39 5,600.58 100.00%
03.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 111.03 26.62 2,955.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 111.03 2,955.62 100.00%
03.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 281.66 28.80 8,111.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 281.66 8,111.81 100.00%
03.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 439.60 3.45 1,516.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 439.60 1,516.62 100.00%
03.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 163.64 31.39 5,136.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 163.64 5,136.66 100.00%
03.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 398.80 3.45 1,375.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 398.80 1,375.86 100.00%
03.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 115.20 13.60 1,566.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 115.20 1,566.72 100.00%
03.02.02.08 BRUÑAS DE 1.0 cm m 185.39 9.32 1,727.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.39 1,727.83 100.00%
03.02.03 CIELO RASO 5,746.93
03.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 132.54 43.36 5,746.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 5,746.93 100.00%
03.02.04 PISOS Y PAVIMENTOS 20,912.44
03.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 210.00 35.38 7,429.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 7,429.80 100.00%
03.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 210.00 56.55 11,875.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 210.00 11,875.50 100.00%
03.02.04.03 PISO CEMENTO PULIDO E=2" m2 30.99 51.86 1,607.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.99 1,607.14 100.00%
03.02.05 CONTRAZOCALOS 3,920.57
03.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 140.40 19.27 2,705.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.40 2,705.51 100.00%
03.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 78.90 15.40 1,215.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.90 1,215.06 100.00%
03.02.06 CARPINTERIA MADERA 7,443.30
03.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 15.00 496.22 7,443.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 7,443.30 100.00%
03.02.07 CARPINTERIA METALICA 10,768.28
03.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 55.80 192.98 10,768.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.80 10,768.28 100.00%
03.02.08 CERRAJERIA 629.76
03.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 6.00 77.93 467.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 467.58 100.00%
03.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 18.00 9.01 162.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 162.18 100.00%
03.02.09 VIDRIOS, CRISTALES Y SIMILARES 7,760.14
03.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 600.63 12.92 7,760.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 600.63 7,760.14 100.00%
03.02.10 PINTURAS 9,374.13
03.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 331.68 10.57 3,505.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 331.68 3,505.86 100.00%
03.02.10.02 PINTURA EN CONTRAZOCALO m2 44.48 7.96 354.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.48 354.06 100.00%
03.02.10.03 PINTURA EN VIGAS m2 124.98 13.73 1,715.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.98 1,715.98 100.00%
03.02.10.04 PINTURA EN COLUMNAS m2 181.75 13.19 2,397.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 181.75 2,397.28 100.00%
03.02.10.05 PINTURA EN CIELO RASO m2 132.54 10.57 1,400.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 1,400.95 100.00%
03.02.11 CUBIERTA METALICA Y CIELO RASO 58,383.12

Página 10
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.02.11.01 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 185.92 116.60 21,678.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 185.92 21,678.27 100.00%
03.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 180.50 75.18 13,569.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.50 13,569.99 100.00%
03.02.11.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 189.63 122.00 23,134.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 189.63 23,134.86 100.00%
03.03 INSTALACIONES ELECTRICAS 26,845.81
03.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 48.00 145.99 7,007.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 7,007.52 100.00%
03.03.02 SALIDA TOMACORRIENTE pto 18.00 215.17 3,873.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,873.06 100.00%
03.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
03.03.04 SALIDA PARA INTERRUPTOR DOBLE pto 6.00 112.89 677.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 677.34 100.00%
03.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%
03.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 48.00 205.71 9,874.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 9,874.08 100.00%
03.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
03.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 218.62 10.81 2,363.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 218.62 2,363.28 100.00%
03.03.09 ALAMBRE THHN 2.5 mm2 m 324.68 1.67 542.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 324.68 542.22 100.00%
03.03.10 ALAMBRE THHN 4 mm2 m 131.32 2.19 287.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 131.32 287.59 100.00%
03.03.11 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
03.03.12 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
03.03.13 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
03.03.14 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
03.04 INSTALACIONES SANITARIAS 2,809.47
03.04.01 SISTEMA DE AGUA PLUVIAL 2,809.47
03.04.01.01 CANALETA PARA AGUA FLUVIAL DE 4" m 36.50 58.77 2,145.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.50 2,145.11 100.00%
03.04.01.02 TUBERIA PVC SAL D=4" m 13.00 45.40 590.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 590.20 100.00%
03.04.01.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
03.05 CONSTRUCCION DE ESCALERAS 24,897.01
03.05.01 OBRAS PRELIMINARES 48.31
03.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 17.06 100.00%
03.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 31.25 100.00%
03.05.02 MOVIMIENTO DE TIERRAS 1,179.42
03.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.85 573.53 100.00%
03.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 35.04 100.00%
03.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.54 96.85 100.00%
03.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.41 277.78 100.00%
03.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.38 196.22 100.00%
03.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
03.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.33 1,775.80 100.00%
03.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.74 674.55 100.00%
03.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.08 839.82 100.00%
03.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 561.10 100.00%
03.05.04 OBRAS DE CONCRETO ARMADO 11,546.69
03.05.04.01 VIGA DE CIMENTACION 2,645.43
03.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 899.62 100.00%
03.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.02 1,029.23 100.00%
03.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 171.43 716.58 100.00%
03.05.04.02 COLUMNAS 2,896.60
03.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.67 751.18 100.00%
03.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 799.92 100.00%
03.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 321.89 1,345.50 100.00%
03.05.04.03 VIGAS 2,222.94
03.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.66 746.68 100.00%
03.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 801.48 100.00%
03.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.43 674.78 100.00%
03.05.04.04 ESCALERAS 2,484.68
03.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.89 850.14 100.00%
03.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.19 682.25 100.00%
03.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 227.82 952.29 100.00%
03.05.04.05 LOSA MACIZA 1,297.04
03.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.77 346.35 100.00%
03.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 279.59 100.00%

Página 11
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

03.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.55 671.10 100.00%
03.05.05 ALBAÑILERIA 1,616.54
03.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.19 1,616.54 100.00%
03.05.06 REVOQUES 4,512.97
03.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
03.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
03.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
03.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
03.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
03.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
03.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
03.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
03.05.07 PISOS 732.78
03.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
03.05.08 CONTRAZOCALOS 262.11
03.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
03.05.09 PINTURAS 1,146.92
03.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
03.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
03.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
03.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
03.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
04 ADMINISTRACION, SALA DE COMPUTO Y SALON DE USOS MULTIPLES 379,732.21
04.01 ESTRUCTURAS 139,933.65
04.01.01 OBRAS PRELIMINARES 350.61
04.01.01.01 LIMPIEZA DE TERRENO m2 130.34 0.95 123.82 130.34 123.82 100.00% 0.00 0.00 0.00% 130.34 123.82 100.00% 0.00 0.00 0.00%
04.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 130.34 1.74 226.79 130.34 226.79 100.00% 0.00 0.00 0.00% 130.34 226.79 100.00% 0.00 0.00 0.00%
04.01.02 MOVIMIENTO DE TIERRAS 8,554.41
04.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 16.51 41.41 683.68 0.00 0.00 0.00% 16.51 683.68 100.00% 16.51 683.68 100.00% 0.00 0.00 0.00%
04.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 83.01 41.41 3,437.44 0.00 0.00 0.00% 83.01 3,437.44 100.00% 83.01 3,437.44 100.00% 0.00 0.00 0.00%
04.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 105.58 2.48 261.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.58 261.84 100.00%
04.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 26.24 27.36 717.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.24 717.93 100.00%
04.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 10.56 197.01 2,080.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.56 2,080.43 100.00%
04.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 86.63 15.85 1,373.09 0.00 0.00 0.00% 86.63 1,373.09 100.00% 86.63 1,373.09 100.00% 0.00 0.00 0.00%
04.01.03 OBRAS DE CONCRETO SIMPLE 12,520.73
04.01.03.01 SOLADO PARA ZAPATAS m2 63.86 35.13 2,243.40 0.00 0.00 0.00% 63.86 2,243.40 100.00% 63.86 2,243.40 100.00% 0.00 0.00 0.00%
04.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 6.35 333.17 2,115.63 0.00 0.00 0.00% 6.35 2,115.63 100.00% 6.35 2,115.63 100.00% 0.00 0.00 0.00%
04.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 5.23 387.67 2,027.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.23 2,027.51 100.00%
04.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 41.80 46.45 1,941.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.80 1,941.61 100.00%
04.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 105.58 39.71 4,192.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.58 4,192.58 100.00%
04.01.04 OBRAS DE CONCRETO ARMADO 118,507.90
04.01.04.01 ZAPATAS 20,173.23
04.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 34.85 449.81 15,675.88 0.00 0.00 0.00% 34.85 15,675.88 100.00% 34.85 15,675.88 100.00% 0.00 0.00 0.00%
04.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,075.92 4.18 4,497.35 0.00 0.00 0.00% 1,075.92 4,497.35 100.00% 1,075.92 4,497.35 100.00% 0.00 0.00 0.00%
04.01.04.02 VIGA DE CIMENTACION 11,190.06
04.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 7.98 449.81 3,589.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00%
04.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 63.80 51.41 3,279.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.80 3,279.96 100.00%
04.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 1,033.64 4.18 4,320.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,033.64 4,320.62 100.00%
04.01.04.03 COLUMNAS Y PLACAS 35,879.80
04.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 21.44 449.81 9,643.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.44 9,643.93 100.00%
04.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 216.32 53.08 11,482.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 11,482.27 100.00%
04.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 3,529.57 4.18 14,753.60 0.00 0.00 0.00% 3,529.57 14,753.60 100.00% 3,529.57 14,753.60 100.00% 0.00 0.00 0.00%
04.01.04.04 VIGAS 23,771.80
04.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.27 449.81 7,318.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.27 7,318.41 100.00%
04.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 132.75 62.13 8,247.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 8,247.76 100.00%
04.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,963.07 4.18 8,205.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,963.07 8,205.63 100.00%
04.01.04.05 LOSAS ALIGERADAS 19,154.31
04.01.04.05.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 12.45 449.81 5,600.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.45 5,600.13 100.00%

Página 12
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.01.04.05.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 142.31 51.12 7,274.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 7,274.89 100.00%
04.01.04.05.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 724.91 4.18 3,030.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 724.91 3,030.12 100.00%
04.01.04.05.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,185.83 2.74 3,249.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,185.83 3,249.17 100.00%
04.01.04.06 COLUMNETAS 7,823.00
04.01.04.06.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 3.44 419.72 1,443.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.44 1,443.84 100.00%
04.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 77.48 53.08 4,112.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.48 4,112.64 100.00%
04.01.04.06.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 542.23 4.18 2,266.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 542.23 2,266.52 100.00%
04.01.04.07 VIGAS COLLARIN 515.70
04.01.04.07.01 CONCRETO VIGAS COLLARIN f'c=175 kg/cm2 m3 0.36 419.72 151.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.36 151.10 100.00%
04.01.04.07.02 ENCOFRADO Y DESENCOFRADO EN VIGAS COLLARIN m2 4.79 53.08 254.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.79 254.25 100.00%
04.01.04.07.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN VIGAS COLLARIN kg 26.40 4.18 110.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.40 110.35 100.00%
04.02 ARQUITECTURA 174,570.71
04.02.01 ALBAÑILERIA 8,721.24
04.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 157.48 55.38 8,721.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 157.48 8,721.24 100.00%
04.02.02 REVOQUES 24,798.60
04.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 208.54 26.62 5,551.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 208.54 5,551.33 100.00%
04.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 161.28 26.62 4,293.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.28 4,293.27 100.00%
04.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 216.32 28.80 6,230.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 6,230.02 100.00%
04.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 191.40 3.45 660.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 191.40 660.33 100.00%
04.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 132.75 31.39 4,167.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 4,167.02 100.00%
04.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 216.98 3.45 748.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.98 748.58 100.00%
04.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 138.00 13.60 1,876.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.00 1,876.80 100.00%
04.02.02.08 BRUÑAS DE 1.0 cm m 136.40 9.32 1,271.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.40 1,271.25 100.00%
04.02.03 CIELO RASO 6,170.56
04.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 142.31 43.36 6,170.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 6,170.56 100.00%
04.02.04 PISOS Y PAVIMENTOS 23,179.67
04.02.04.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 232.88 35.38 8,239.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.88 8,239.29 100.00%
04.02.04.02 PISO DE CERAMICO 45 X 45 CM m2 232.88 56.55 13,169.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.88 13,169.36 100.00%
04.02.04.03 PISO CEMENTO PULIDO E=2" m2 34.15 51.86 1,771.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 34.15 1,771.02 100.00%
04.02.05 CONTRAZOCALOS 5,606.04
04.02.05.01 CONTRAZOCALO CERAMICO H=0.10 m. m 138.18 19.27 2,662.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.18 2,662.73 100.00%
04.02.05.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 76.00 15.40 1,170.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.00 1,170.40 100.00%
04.02.05.03 ZOCALO DE CERAMICA 20 X 30 CM m2 19.08 92.92 1,772.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.08 1,772.91 100.00%
04.02.06 CARPINTERIA MADERA 9,607.44
04.02.06.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 16.50 496.22 8,187.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.50 8,187.63 100.00%
04.02.06.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 4.05 350.57 1,419.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.05 1,419.81 100.00%
04.02.07 CARPINTERIA METALICA 13,514.39
04.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 70.03 192.98 13,514.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.03 13,514.39 100.00%
04.02.08 CERRAJERIA 839.68
04.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
04.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 24.00 9.01 216.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 216.24 100.00%
04.02.09 VIDRIOS, CRISTALES Y SIMILARES 9,738.32
04.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 753.74 12.92 9,738.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 753.74 9,738.32 100.00%
04.02.10 PINTURAS 10,210.13
04.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 369.82 10.57 3,909.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 369.82 3,909.00 100.00%
04.02.10.02 PINTURA EN CONTRAZOCALO m2 15.20 7.96 120.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.20 120.99 100.00%
04.02.10.03 PINTURA EN VIGAS m2 132.75 13.73 1,822.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.75 1,822.66 100.00%
04.02.10.04 PINTURA EN COLUMNAS Y PLACAS m2 216.32 13.19 2,853.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.32 2,853.26 100.00%
04.02.10.05 PINTURA EN CIELO RASO m2 142.31 10.57 1,504.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 142.31 1,504.22 100.00%
04.02.11 CUBIERTA METALICA Y CIELO RASO 62,184.64
04.02.11.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 201.47 122.00 24,579.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 201.47 24,579.34 100.00%
04.02.11.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 181.50 75.18 13,645.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 181.50 13,645.17 100.00%
04.02.11.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 205.49 116.60 23,960.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 205.49 23,960.13 100.00%
04.03 INSTALACIONES ELECTRICAS 33,036.01
04.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 41.00 145.99 5,985.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 5,985.59 100.00%
04.03.02 SALIDA TOMACORRIENTE pto 54.00 215.17 11,619.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.00 11,619.18 100.00%
04.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 8.00 108.23 865.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 865.84 100.00%
04.03.04 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 114.38 228.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 228.76 100.00%

Página 13
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 38.00 205.71 7,816.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 7,816.98 100.00%
04.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
04.03.07 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 285.11 10.81 3,082.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 285.11 3,082.04 100.00%
04.03.08 ALAMBRE THHN 2.5 mm2 m 344.56 1.67 575.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 344.56 575.42 100.00%
04.03.09 ALAMBRE THHN 4 mm2 m 415.47 2.19 909.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 415.47 909.88 100.00%
04.03.10 TABLERO DE DISTRIBUCION und 1.00 469.91 469.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 469.91 100.00%
04.03.11 SUBTABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
04.03.12 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
04.03.13 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
04.04 INSTALACIONES SANITARIAS 7,294.83
04.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,193.88
04.04.01.01 INODORO TANQUE BAJO pza 2.00 361.79 723.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 723.58 100.00%
04.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 195.88 391.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 391.76 100.00%
04.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.27 78.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 78.54 100.00%
04.04.02 SISTEMA DE DESAGUE 2,175.09
04.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
04.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 145.54 291.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.08 100.00%
04.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
04.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
04.04.02.05 SUMIDERO DE 2" pza 2.00 77.41 154.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 154.82 100.00%
04.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.47 33.95 355.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 355.46 100.00%
04.04.02.07 YEE PVC SAL 4"X2" und 2.00 61.97 123.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 123.94 100.00%
04.04.02.08 YEE PVC SAL 2"X2" und 2.00 58.33 116.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 116.66 100.00%
04.04.02.09 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
04.04.02.10 EXCAVACION MANUAL PARA TUBERIA m 10.47 14.89 155.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 155.90 100.00%
04.04.02.11 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.47 3.86 40.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 40.41 100.00%
04.04.02.12 CAMA DE APOYO m 10.47 9.44 98.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 98.84 100.00%
04.04.02.13 RELLENO COMPACTADO DE ZANJAS m 10.47 12.00 125.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.47 125.64 100.00%
04.04.02.14 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.03 SISTEMA DE AGUA FRIA 1,193.38
04.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 72.84 291.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 291.36 100.00%
04.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 4.01 17.01 68.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.01 68.21 100.00%
04.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.00 18.07 126.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 126.49 100.00%
04.04.03.04 CODO PVC 1/2" und 2.00 9.94 19.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 19.88 100.00%
04.04.03.05 TEE PVC 1/2" und 3.00 11.04 33.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 33.12 100.00%
04.04.03.06 CODO PVC 3/4" und 1.00 10.78 10.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10.78 100.00%
04.04.03.07 EXCAVACION MANUAL PARA TUBERIA m 11.01 14.89 163.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 163.94 100.00%
04.04.03.08 REFINE NIVELACION Y COMPACTACION DE ZANJA m 11.01 3.86 42.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 42.50 100.00%
04.04.03.09 CAMA DE APOYO m 11.01 9.44 103.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 103.93 100.00%
04.04.03.10 RELLENO COMPACTADO DE ZANJAS m 11.01 12.00 132.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.01 132.12 100.00%
04.04.03.11 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
04.04.03.12 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
04.04.04 SISTEMA DE AGUA PLUVIAL 2,732.48
04.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 32.10 58.77 1,886.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.10 1,886.52 100.00%
04.04.04.02 TUBERIA PVC SAL D=4" m 17.00 45.40 771.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 771.80 100.00%
04.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
04.05 CONSTRUCCION DE ESCALERAS 24,897.01
04.05.01 OBRAS PRELIMINARES 48.31
04.05.01.01 LIMPIEZA DE TERRENO m2 17.96 0.95 17.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 17.06 100.00%
04.05.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 17.96 1.74 31.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.96 31.25 100.00%
04.05.02 MOVIMIENTO DE TIERRAS 1,179.42
04.05.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 13.85 41.41 573.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.85 573.53 100.00%
04.05.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 14.13 2.48 35.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 35.04 100.00%
04.05.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.54 27.36 96.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.54 96.85 100.00%
04.05.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 1.41 197.01 277.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.41 277.78 100.00%
04.05.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.38 15.85 196.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.38 196.22 100.00%
04.05.03 OBRAS DE CONCRETO SIMPLE 3,851.27
04.05.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.33 333.17 1,775.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.33 1,775.80 100.00%

Página 14
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

04.05.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 1.74 387.67 674.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.74 674.55 100.00%
04.05.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 18.08 46.45 839.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.08 839.82 100.00%
04.05.03.04 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 14.13 39.71 561.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 561.10 100.00%
04.05.04 OBRAS DE CONCRETO ARMADO 11,546.69 0.00
04.05.04.01 VIGA DE CIMENTACION 2,645.43
04.05.04.01.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 2.00 449.81 899.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 899.62 100.00%
04.05.04.01.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 20.02 51.41 1,029.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.02 1,029.23 100.00%
04.05.04.01.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 171.43 4.18 716.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 171.43 716.58 100.00%
04.05.04.02 COLUMNAS 2,896.60
04.05.04.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.67 449.81 751.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.67 751.18 100.00%
04.05.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 15.07 53.08 799.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 799.92 100.00%
04.05.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 321.89 4.18 1,345.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 321.89 1,345.50 100.00%
04.05.04.03 VIGAS 2,222.94
04.05.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 1.66 449.81 746.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.66 746.68 100.00%
04.05.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.90 62.13 801.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 801.48 100.00%
04.05.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 161.43 4.18 674.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 161.43 674.78 100.00%
04.05.04.04 ESCALERAS 2,484.68
04.05.04.04.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 1.89 449.81 850.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.89 850.14 100.00%
04.05.04.04.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 11.19 60.97 682.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.19 682.25 100.00%
04.05.04.04.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 227.82 4.18 952.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 227.82 952.29 100.00%
04.05.04.05 LOSA MACIZA 1,297.04
04.05.04.05.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 0.77 449.81 346.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.77 346.35 100.00%
04.05.04.05.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 5.15 54.29 279.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 279.59 100.00%
04.05.04.05.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 160.55 4.18 671.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.55 671.10 100.00%
04.05.05 ALBAÑILERIA 1,616.54
04.05.05.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 29.19 55.38 1,616.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.19 1,616.54 100.00%
04.05.06 REVOQUES 4,512.97
04.05.06.01 TARRAJEO EN EXTERIORES C:A-1:4 m2 58.38 26.62 1,554.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 1,554.08 100.00%
04.05.06.02 TARRAJEO DE COLUMNAS C:A-1:4 m2 15.07 28.80 434.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 434.02 100.00%
04.05.06.03 VESTIDURA DE ARISTAS EN COLUMNAS m 64.72 3.45 223.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.72 223.28 100.00%
04.05.06.04 TARRAJEO DE VIGAS C:A-1:4 m2 12.90 31.39 404.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 404.93 100.00%
04.05.06.05 VESTIDURA DE ARISTAS EN VIGAS m 51.73 3.45 178.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.73 178.47 100.00%
04.05.06.06 BRUÑAS DE 1.0 cm m 82.78 9.32 771.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.78 771.51 100.00%
04.05.06.07 REVESTIMIENTO DE GRADAS Y ESCALERA m2 15.39 36.85 567.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.39 567.12 100.00%
04.05.06.08 REVESTIMIENTO DE FONDO DE ESCALERAS CON CEMENTO m2 10.30 36.85 379.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.30 379.56 100.00%
04.05.07 PISOS 732.78
04.05.07.01 PISO CEMENTO PULIDO E=2" m2 14.13 51.86 732.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 732.78 100.00%
04.05.08 CONTRAZOCALOS 262.11
04.05.08.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.02 15.40 262.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.02 262.11 100.00%
04.05.09 PINTURAS 1,146.92
04.05.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 58.38 10.57 617.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.38 617.08 100.00%
04.05.09.02 PINTURA EN COLUMNAS m2 15.07 13.19 198.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.07 198.77 100.00%
04.05.09.03 PINTURA EN VIGAS m2 12.90 13.73 177.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.90 177.12 100.00%
04.05.09.04 PINTURA EN FONDO DE ESCALERA m2 8.39 11.37 95.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.39 95.39 100.00%
04.05.09.05 PINTURA EN LOSA MACIZA m2 5.15 11.37 58.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.15 58.56 100.00%
05 CONSTRUCCION DE COMEDOR 144,917.87
05.01 ESTRUCTURAS 52,611.09
05.01.01 OBRAS PRELIMINARES 188.04
05.01.01.01 LIMPIEZA DE TERRENO m2 69.90 0.95 66.41 69.90 66.41 100.00% 0.00 0.00 0.00% 69.90 66.41 100.00% 0.00 0.00 0.01%
05.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 69.90 1.74 121.63 69.90 121.63 100.00% 0.00 0.00 0.00% 69.90 121.63 100.00% 0.00 0.00 0.00%
05.01.02 MOVIMIENTO DE TIERRAS 4,303.76
05.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 18.27 41.41 756.56 18.27 756.56 100.00% 0.00 0.00 0.00% 18.27 756.56 100.00% 0.00 0.00 0.00%
05.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 25.91 41.41 1,072.93 25.91 1,072.93 100.00% 0.00 0.00 0.00% 25.91 1,072.93 100.00% 0.00 0.00 0.00%
05.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 63.56 2.48 157.63 63.56 157.63 100.00% 0.00 0.00 0.00% 63.56 157.63 100.00% 0.00 0.00 0.00%
05.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 29.59 27.36 809.58 29.59 809.58 100.00% 0.00 0.00 0.00% 29.59 809.58 100.00% 0.00 0.00 0.00%
05.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 6.36 197.01 1,252.98 6.36 1,252.98 100.00% 0.00 0.00 0.00% 6.36 1,252.98 100.00% 0.00 0.00 0.00%
05.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 16.03 15.85 254.08 16.03 254.08 100.00% 0.00 0.00 0.00% 16.03 254.08 100.00% 0.00 0.00 0.00%
05.01.03 OBRAS DE CONCRETO SIMPLE 7,695.11

Página 15
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.01.03.01 SOLADO PARA ZAPATAS m2 19.93 35.13 700.14 19.93 700.14 100.00% 0.00 0.00 0.00% 19.93 700.14 100.00% 0.00 0.00 0.00%
05.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.29 333.17 1,762.47 5.29 1,762.47 100.00% 0.00 0.00 0.00% 5.29 1,762.47 100.00% 0.00 0.00 0.00%
05.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 2.69 387.67 1,042.83 2.69 1,042.83 100.00% 0.00 0.00 0.00% 2.69 1,042.83 100.00% 0.00 0.00 0.00%
05.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 35.86 46.45 1,665.70 35.86 1,665.70 100.00% 0.00 0.00 0.00% 35.86 1,665.70 100.00% 0.00 0.00 0.00%
05.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 63.56 39.71 2,523.97 63.56 2,523.97 100.00% 0.00 0.00 0.00% 63.56 2,523.97 100.00% 0.00 0.00 0.00%
05.01.04 OBRAS DE CONCRETO ARMADO 40,424.18
05.01.04.01 ZAPATAS 5,545.41
05.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 9.97 449.81 4,484.61 9.97 4,484.61 100.00% 0.00 0.00 0.00% 9.97 4,484.61 100.00% 0.00 0.00 0.00%
05.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 253.78 4.18 1,060.80 253.78 1,060.80 100.00% 0.00 0.00 0.00% 253.78 1,060.80 100.00% 0.00 0.00 0.00%
05.01.04.02 VIGA DE CIMENTACION 8,818.36
05.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.35 449.81 2,856.29 6.35 2,856.29 100.00% 0.00 0.00 0.00% 6.35 2,856.29 100.00% 0.00 0.00 0.00%
05.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 50.80 51.41 2,611.63 50.80 2,611.63 100.00% 0.00 0.00 0.00% 50.80 2,611.63 100.00% 0.00 0.00 0.00%
05.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 801.54 4.18 3,350.44 801.54 3,350.44 100.00% 0.00 0.00 0.00% 801.54 3,350.44 100.00% 0.00 0.00 0.00%
05.01.04.03 COLUMNAS Y PLACAS 13,991.50
05.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.21 449.81 3,692.94 8.21 3,692.94 100.00% 0.00 0.00 0.00% 8.21 3,692.94 100.00% 0.00 0.00 0.00%
05.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 91.20 53.08 4,840.90 91.20 4,840.90 100.00% 0.00 0.00 0.00% 91.20 4,840.90 100.00% 0.00 0.00 0.00%
05.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,305.66 4.18 5,457.66 1,305.66 5,457.66 100.00% 0.00 0.00 0.00% 1,305.66 5,457.66 100.00% 0.00 0.00 0.00%
05.01.04.04 VIGAS 10,012.03
05.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 6.62 449.81 2,977.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.62 2,977.74 100.00%
05.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 63.32 62.13 3,934.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 3,934.07 100.00%
05.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 741.68 4.18 3,100.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 741.68 3,100.22 100.00%
05.01.04.05 COLUMNETAS 2,056.88
05.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 1.13 419.72 474.28 1.13 474.28 100.00% 0.00 0.00 0.00% 1.13 474.28 100.00% 0.00 0.00 0.00%
05.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 15.12 53.08 802.57 15.12 802.57 100.00% 0.00 0.00 0.00% 15.12 802.57 100.00% 0.00 0.00 0.00%
05.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 186.61 4.18 780.03 186.61 780.03 100.00% 0.00 0.00 0.00% 186.61 780.03 100.00% 0.00 0.00 0.00%
05.02 ARQUITECTURA 78,614.27
05.02.01 ALBAÑILERIA 3,063.62
05.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 55.32 55.38 3,063.62 55.32 3,063.62 100.00% 0.00 0.00 0.00% 55.32 3,063.62 100.00% 0.00 0.00 0.00%
05.02.02 REVOQUES 11,385.22
05.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 84.51 26.62 2,249.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.51 2,249.66 100.00%
05.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 53.01 26.62 1,411.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.01 1,411.13 100.00%
05.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 70.68 28.80 2,035.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.68 2,035.58 100.00%
05.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 92.00 3.45 317.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 92.00 317.40 100.00%
05.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 63.32 31.39 1,987.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 1,987.61 100.00%
05.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 61.60 3.45 212.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 61.60 212.52 100.00%
05.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 97.10 27.89 2,708.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 97.10 2,708.12 100.00%
05.02.02.08 BRUÑAS DE 1.0 cm m 49.70 9.32 463.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.70 463.20 100.00%
05.02.03 PISOS Y PAVIMENTOS 5,843.07
05.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 63.56 35.38 2,248.75 63.56 2,248.75 100.00% 0.00 0.00 0.00% 63.56 2,248.75 100.00% 0.00 0.00 0.00%
05.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 63.56 56.55 3,594.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.56 3,594.32 100.00%
05.02.04 CONTRAZOCALOS 1,272.03
05.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 37.80 19.27 728.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.80 728.41 100.00%
05.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 35.30 15.40 543.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.30 543.62 100.00%
05.02.05 CARPINTERIA MADERA 6,321.84
05.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 12.74 496.22 6,321.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.74 6,321.84 100.00%
05.02.06 CARPINTERIA METALICA 5,773.96
05.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 29.92 192.98 5,773.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.92 5,773.96 100.00%
05.02.07 CERRAJERIA 524.80
05.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 5.00 77.93 389.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 389.65 100.00%
05.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 15.00 9.01 135.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 135.15 100.00%
05.02.08 VIDRIOS, CRISTALES Y SIMILARES 4,182.85
05.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 323.75 12.92 4,182.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 323.75 4,182.85 100.00%
05.02.09 PINTURAS 3,306.15
05.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 137.02 10.57 1,448.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.02 1,448.30 100.00%
05.02.09.02 PINTURA EN CONTRAZOCALO m2 7.06 7.96 56.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.06 56.20 100.00%
05.02.09.03 PINTURA EN VIGAS m2 63.32 13.73 869.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.32 869.38 100.00%
05.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 70.68 13.19 932.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.68 932.27 100.00%
05.02.10 CUBIERTA METALICA Y CIELO RASO 36,940.73

Página 16
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

05.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 113.85 122.00 13,889.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 113.85 13,889.70 100.00%
05.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 126.50 75.18 9,510.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 126.50 9,510.27 100.00%
05.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 116.13 116.60 13,540.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 116.13 13,540.76 100.00%
05.03 INSTALACIONES ELECTRICAS 8,742.62
05.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 10.00 145.99 1,459.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,459.90 100.00%
05.03.02 SALIDA TOMACORRIENTE pto 9.00 215.17 1,936.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,936.53 100.00%
05.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 4.00 108.23 432.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 432.92 100.00%
05.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 10.00 205.71 2,057.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 2,057.10 100.00%
05.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 100.00 10.81 1,081.00 40.00 432.40 40.00% 0.00 0.00 0.00% 40.00 432.40 40.00% 60.00 648.60 60.00%
05.03.06 ALAMBRE THHN 2.5 mm2 m 125.00 1.67 208.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.00 208.75 100.00%
05.03.07 ALAMBRE THHN 4 mm2 m 101.00 2.19 221.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 101.00 221.19 100.00%
05.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
05.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
05.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
05.04 INSTALACIONES SANITARIAS 4,949.89
05.04.01 APARATOS Y ACCESORIOS SANITARIOS 1,433.36
05.04.01.01 LAVADERO DE ACERO INOXIDABLE DOS POZAS CON ESCU und 2.00 447.76 895.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 895.52 100.00%
05.04.01.02 GRIFO TIPO CUELLO DE CISNE CROMADO 1/2" und 4.00 134.46 537.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 537.84 100.00%
05.04.02 SISTEMA DE DESAGUE 1,071.20
05.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 4.00 93.15 372.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 372.60 100.00%
05.04.02.02 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
05.04.02.03 TUBERIA PVC SAL P/DESAGUE D=2" m 6.25 29.80 186.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 186.25 100.00%
05.04.02.04 YEE PVC SAL P/DESAGUE D=2" und 1.00 27.59 27.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 27.59 100.00%
05.04.02.05 CODO PVC SAL P/DESAGUE D=2" und 1.00 25.81 25.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 25.81 100.00%
05.04.02.06 EXCAVACION MANUAL PARA TUBERIA m 6.25 14.89 93.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 93.06 100.00%
05.04.02.07 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.25 3.86 24.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 24.13 100.00%
05.04.02.08 CAMA DE APOYO m 6.25 9.44 59.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 59.00 100.00%
05.04.02.09 RELLENO COMPACTADO DE ZANJAS m 6.25 12.00 75.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 75.00 100.00%
05.04.02.10 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.03 SISTEMA DE AGUA FRIA 729.43
05.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 145.68 100.00%
05.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 6.15 17.01 104.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 104.61 100.00%
05.04.03.03 CODO PVC 1/2" und 2.00 9.94 19.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 19.88 100.00%
05.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11.04 100.00%
05.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 6.15 14.89 91.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 91.57 100.00%
05.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 6.15 3.86 23.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 23.74 100.00%
05.04.03.07 CAMA DE APOYO m 6.15 9.44 58.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 58.06 100.00%
05.04.03.08 RELLENO COMPACTADO DE ZANJAS m 6.15 12.00 73.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.15 73.80 100.00%
05.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
05.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
05.04.04 SISTEMA DE AGUA PLUVIAL 1,715.90
05.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 23.30 58.77 1,369.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 1,369.34 100.00%
05.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
05.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%
06 CONSTRUCCIÓN DE SERVICIOS HIGIENICOS 232,892.65
06.01 ESTRUCTURAS 64,827.86
06.01.01 OBRAS PRELIMINARES 228.00
06.01.01.01 LIMPIEZA DE TERRENO m2 84.76 0.95 80.52 84.76 80.52 100.00% 0.00 0.00 0.00% 84.76 80.52 100.00% 0.00 0.00 0.00%
06.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 84.76 1.74 147.48 84.76 147.48 100.00% 0.00 0.00 0.00% 84.76 147.48 100.00% 0.00 0.00 0.00%
06.01.02 MOVIMIENTO DE TIERRAS 5,317.64
06.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 30.78 41.41 1,274.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.78 1,274.60 100.00%
06.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 26.68 41.41 1,104.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.68 1,104.82 100.00%
06.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 76.49 2.48 189.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 189.70 100.00%
06.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 19.68 27.36 538.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.68 538.44 100.00%
06.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 7.65 197.01 1,507.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.65 1,507.13 100.00%
06.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 44.35 15.85 702.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.35 702.95 100.00%
06.01.03 CONCRETO SIMPLE 12,987.55
06.01.03.01 SOLADO PARA ZAPATAS m2 20.52 35.13 720.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.52 720.87 100.00%

Página 17
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 12.74 333.17 4,244.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.74 4,244.59 100.00%
06.01.03.03 SOBRECIMIENTO 1:8 + 25% P.M m3 4.95 387.67 1,918.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.95 1,918.97 100.00%
06.01.03.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 66.00 46.45 3,065.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 66.00 3,065.70 100.00%
06.01.03.05 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 76.49 39.71 3,037.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 3,037.42 100.00%
06.01.04 CONCRETO ARMADO 46,294.67
06.01.04.01 ZAPATAS 5,692.90
06.01.04.01.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 10.26 449.81 4,615.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.26 4,615.05 100.00%
06.01.04.01.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 257.86 4.18 1,077.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 257.86 1,077.85 100.00%
06.01.04.02 VIGA DE CIMENTACION 8,838.96
06.01.04.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 6.23 449.81 2,802.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.23 2,802.32 100.00%
06.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 49.80 51.41 2,560.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.80 2,560.22 100.00%
06.01.04.02.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 831.68 4.18 3,476.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 831.68 3,476.42 100.00%
06.01.04.03 COLUMNAS Y PLACAS 13,863.72
06.01.04.03.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 8.04 449.81 3,616.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.04 3,616.47 100.00%
06.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 89.52 53.08 4,751.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 4,751.72 100.00%
06.01.04.03.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACA kg 1,314.72 4.18 5,495.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,314.72 5,495.53 100.00%
06.01.04.04 VIGAS 13,462.21
06.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 8.81 449.81 3,962.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.81 3,962.83 100.00%
06.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 84.20 62.13 5,231.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 5,231.35 100.00%
06.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 1,021.06 4.18 4,268.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,021.06 4,268.03 100.00%
06.01.04.05 COLUMNETAS 4,436.88
06.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 2.52 419.72 1,057.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.52 1,057.69 100.00%
06.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 33.64 53.08 1,785.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.64 1,785.61 100.00%
06.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 381.24 4.18 1,593.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 381.24 1,593.58 100.00%
06.02 ARQUITECTURA 122,519.44
06.02.01 MUROS Y TABIQUES 6,205.88
06.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 112.06 55.38 6,205.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.06 6,205.88 100.00%
06.02.02 REVOQUES 15,227.74
06.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 137.56 26.62 3,661.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.56 3,661.85 100.00%
06.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 86.56 26.62 2,304.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.56 2,304.23 100.00%
06.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 89.52 28.80 2,578.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 2,578.18 100.00%
06.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 169.60 3.45 585.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 169.60 585.12 100.00%
06.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 84.20 31.39 2,643.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 2,643.04 100.00%
06.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 109.88 3.45 379.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 109.88 379.09 100.00%
06.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A-1: m2 92.20 27.89 2,571.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 92.20 2,571.46 100.00%
06.02.02.08 BRUÑAS DE 1.0 cm m 54.16 9.32 504.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.16 504.77 100.00%
06.02.03 PISOS 7,031.73
06.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 76.49 35.38 2,706.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 2,706.22 100.00%
06.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 76.49 56.55 4,325.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.49 4,325.51 100.00%
06.02.04 ZOCALOS 16,988.89
06.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 32.00 15.40 492.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 492.80 100.00%
06.02.04.02 ZOCALO DE CERAMICA 20 X 30 CM m2 177.53 92.92 16,496.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.53 16,496.09 100.00%
06.02.05 CARPINTERIA DE MADERA 24,845.08
06.02.05.01 PUERTAS 14,785.70
06.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 17.08 496.22 8,475.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.08 8,475.44 100.00%
06.02.05.01.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 18.00 350.57 6,310.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 6,310.26 100.00%
06.02.05.02 TABIQUES DIVISORIOS 10,059.38
06.02.05.02.01 DIVISIONES CONTRAPLACADAS DE MADERA (SSHH) m2 37.44 268.68 10,059.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.44 10,059.38 100.00%
06.02.06 CARPINTERIA METALICA 2,223.13
06.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 11.52 192.98 2,223.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.52 2,223.13 100.00%
06.02.07 CERRAJERIA 1,475.26
06.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 77.93 623.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 623.44 100.00%
06.02.07.02 PICAPORTE DE ALUMINIO 2 PULGADAS pza 18.00 17.29 311.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 311.22 100.00%
06.02.07.03 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 60.00 9.01 540.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 60.00 540.60 100.00%
06.02.08 VIDRIOS, CRISTALES Y SIMILARES 1,602.08
06.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 124.00 12.92 1,602.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 124.00 1,602.08 100.00%
06.02.09 PINTURAS 4,756.73
06.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 224.12 10.57 2,368.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 224.12 2,368.95 100.00%

Página 18
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

06.02.09.02 PINTURA EN CONTRAZOCALO m2 6.40 7.96 50.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.40 50.94 100.00%
06.02.09.03 PINTURA EN VIGAS m2 84.20 13.73 1,156.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.20 1,156.07 100.00%
06.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 89.52 13.19 1,180.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.52 1,180.77 100.00%
06.02.10 CUBIERTA METALICA Y CIELO RASO 42,162.92
06.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
06.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPOR m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
06.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
06.03 INSTALACIONES ELECTRICAS 12,831.07
06.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 20.00 145.99 2,919.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,919.80 100.00%
06.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 8.00 219.38 1,755.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,755.04 100.00%
06.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 10.00 108.23 1,082.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,082.30 100.00%
06.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 20.00 205.71 4,114.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,114.20 100.00%
06.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 99.90 10.81 1,079.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99.90 1,079.92 100.00%
06.03.06 ALAMBRE THHN 2.5 mm2 m 206.80 1.67 345.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 206.80 345.36 100.00%
06.03.07 ALAMBRE THHN 4 mm2 m 86.40 2.19 189.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 86.40 189.22 100.00%
06.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
06.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
06.03.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
06.04 INSTALACIONES SANITARIAS 32,714.28
06.04.01 APARATOS Y ACCESORIOS SANITARIOS 11,468.50
06.04.01.01 INODORO TANQUE BAJO pza 20.00 361.79 7,235.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 7,235.80 100.00%
06.04.01.02 LAVATORIO DE LOZA BLANCA und 18.00 195.88 3,525.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 3,525.84 100.00%
06.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 18.00 39.27 706.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 706.86 100.00%
06.04.02 SISTEMA DE DESAGUE 11,848.24
06.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 18.00 93.15 1,676.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 1,676.70 100.00%
06.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 20.00 145.54 2,910.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,910.80 100.00%
06.04.02.03 SALIDA VENTILACION DE 2" pto 4.00 58.08 232.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 232.32 100.00%
06.04.02.04 REGISTRO DE BRONCE 4" und 8.00 285.99 2,287.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 2,287.92 100.00%
06.04.02.05 SUMIDERO DE 2" pza 10.00 77.41 774.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 774.10 100.00%
06.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 35.40 33.95 1,201.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 1,201.83 100.00%
06.04.02.07 YEE PVC SAL 4"X2" und 8.00 61.97 495.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 495.76 100.00%
06.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 6.00 25.81 154.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 154.86 100.00%
06.04.02.09 YEE PVC SAL 4" und 4.00 64.85 259.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 259.40 100.00%
06.04.02.10 CODO PVC SAL P/DESAGUE D=4" und 6.00 28.52 171.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 171.12 100.00%
06.04.02.11 EXCAVACION MANUAL PARA TUBERIA m 35.40 14.89 527.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 527.11 100.00%
06.04.02.12 REFINE NIVELACION Y COMPACTACION DE ZANJA m 35.40 3.86 136.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 136.64 100.00%
06.04.02.13 CAMA DE APOYO m 35.40 9.44 334.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 334.18 100.00%
06.04.02.14 RELLENO COMPACTADO DE ZANJAS m 35.40 12.00 424.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.40 424.80 100.00%
06.04.02.15 CAJA DE REGISTRO CON REJILLA METALICA und 2.00 130.35 260.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 260.70 100.00%
06.04.03 SISTEMA DE AGUA FRIA 7,446.56
06.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 42.00 72.84 3,059.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42.00 3,059.28 100.00%
06.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 41.40 17.01 704.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.40 704.21 100.00%
06.04.03.03 TUBERIA PVC SAP CLASE 10-3/4" m 7.74 18.07 139.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.74 139.86 100.00%
06.04.03.04 CODO PVC 1/2" und 10.00 9.94 99.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 99.40 100.00%
06.04.03.05 TEE PVC 1/2" und 12.00 11.04 132.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 132.48 100.00%
06.04.03.06 REDUCCION PVC 3/4" - 1/2" und 6.00 10.11 60.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 60.66 100.00%
06.04.03.07 CODO PVC 3/4" und 2.00 10.78 21.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 21.56 100.00%
06.04.03.08 TEE PVC 3/4" und 4.00 11.97 47.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 47.88 100.00%
06.04.03.09 EXCAVACION MANUAL PARA TUBERIA m 49.14 14.89 731.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 731.69 100.00%
06.04.03.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 49.14 3.86 189.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 189.68 100.00%
06.04.03.11 CAMA DE APOYO m 49.14 9.44 463.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 463.88 100.00%
06.04.03.12 RELLENO COMPACTADO DE ZANJAS m 49.14 12.00 589.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.14 589.68 100.00%
06.04.03.13 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 6.00 70.70 424.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 424.20 100.00%
06.04.03.14 CAJA PARA VALVULAS und 6.00 130.35 782.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 782.10 100.00%
06.04.04 SISTEMA DE AGUA PLUVIAL 1,950.98
06.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 58.77 1,604.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 1,604.42 100.00%
06.04.04.02 TUBERIA PVC SAL D=4" m 6.00 45.40 272.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 272.40 100.00%
06.04.04.03 CODO PVC SAL D=4" und 2.00 37.08 74.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 74.16 100.00%

Página 19
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07 TANQUE CISTERNA - TANQUE ELEVADO 49,283.11 0.00%


07.01 ESTRUCTURAS 26,769.78
07.01.01 OBRAS PRELIMINARES 23.54
07.01.01.01 LIMPIEZA DE TERRENO m2 8.75 0.95 8.31 8.75 8.31 100.00% 0.00 0.00 0.00% 8.75 8.31 100.00% 0.00 0.00 0.00%
07.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 8.75 1.74 15.23 8.75 15.23 100.00% 0.00 0.00 0.00% 8.75 15.23 100.00% 0.00 0.00 0.00%
07.01.02 MOVIMIENTO DE TIERRAS 1,079.23
07.01.02.01 EXCAVACION DE ZANJAS PARA CISTERNA m3 17.50 41.41 724.68 17.50 724.68 100.00% 0.00 0.00 0.00% 17.50 724.68 100.00% 0.00 0.01 0.00%
07.01.02.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 8.75 2.48 21.70 8.75 21.70 100.00% 0.00 0.00 0.00% 8.75 21.70 100.00% 0.00 0.00 0.00%
07.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 21.00 15.85 332.85 21.00 332.85 100.00% 0.00 0.00 0.00% 21.00 332.85 100.00% 0.00 0.00 0.00%
07.01.03 CONCRETO SIMPLE 586.88
07.01.03.01 SOLADO m2 8.75 35.13 307.39 8.75 307.39 100.00% 0.00 0.00 0.00% 8.75 307.39 100.00% 0.00 0.00 0.00%
07.01.03.02 SOBRECIMIENTO 1:8 + 25% P.M m3 0.28 387.67 108.55 0.28 108.55 100.00% 0.00 0.00 0.00% 0.28 108.55 100.00% 0.00 0.00 0.00%
07.01.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 3.68 46.45 170.94 3.68 170.94 100.00% 0.00 0.00 0.00% 3.68 170.94 100.00% 0.00 0.00 0.00%
07.01.04 CONCRETO ARMADO 25,080.13
07.01.04.01 COLUMNAS 7,138.87
07.01.04.01.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 3.98 449.81 1,790.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.98 1,790.24 100.00%
07.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 49.04 53.08 2,603.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 2,603.04 100.00%
07.01.04.01.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 656.84 4.18 2,745.59 656.84 2,745.59 100.00% 0.00 0.00 0.00% 656.84 2,745.59 100.00% 0.00 0.00 0.00%
07.01.04.02 VIGAS 4,141.00
07.01.04.02.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 2.16 449.81 971.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.16 971.59 100.00%
07.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 24.48 62.13 1,520.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 1,520.94 100.00%
07.01.04.02.03 VIGAS ACERO fy=4,200 kg/cm2 kg 394.37 4.18 1,648.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 394.37 1,648.47 100.00%
07.01.04.03 LOSA MACIZA 3,002.53
07.01.04.03.01 LOSA MACIZA CONCRETO FC=210 KG/CM2 m3 2.40 449.81 1,079.54 2.40 1,079.54 100.00% 0.00 0.00 0.00% 2.40 1,079.54 100.00% 0.00 0.00 0.00%
07.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA m2 12.00 54.29 651.48 12.00 651.48 100.00% 0.00 0.00 0.00% 12.00 651.48 100.00% 0.00 0.00 0.00%
07.01.04.03.03 LOSA MACIZA ACERO fy=4,200 kg/cm2 kg 304.19 4.18 1,271.51 304.19 1,271.51 100.00% 0.00 0.00 0.00% 304.19 1,271.51 100.00% 0.00 0.00 0.00%
07.01.04.04 CISTERNA 10,317.18
07.01.04.04.01 CONCRETO EN CISTERNA f'c=210 kg/cm2 m3 11.25 485.41 5,460.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.25 5,460.86 100.00%
07.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 18.22 51.41 936.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.22 936.69 100.00%
07.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN CISTERNA kg 937.71 4.18 3,919.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 937.71 3,919.63 100.00%
07.01.04.05 COLUMNETAS 480.55
07.01.04.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 0.28 419.72 117.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.28 117.52 100.00%
07.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 3.68 53.08 195.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.68 195.33 100.00%
07.01.04.05.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 40.12 4.18 167.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.12 167.70 100.00%
07.02 ARQUITECTURA 11,218.94
07.02.01 MUROS Y TABIQUES 835.13
07.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 15.08 55.38 835.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.08 835.13 100.00%
07.02.02 REVOQUES 4,950.63
07.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 15.84 26.62 421.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 421.66 100.00%
07.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 49.04 28.80 1,412.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 1,412.35 100.00%
07.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 152.00 3.45 524.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 152.00 524.40 100.00%
07.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 24.48 31.39 768.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 768.43 100.00%
07.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 57.60 3.45 198.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 57.60 198.72 100.00%
07.02.02.07 REVESTIMIENTO DE CIELO RASO EN LOSA MACIZA m2 12.00 36.85 442.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 442.20 100.00%
07.02.02.08 TARRAJEO CON IMPERMEABILIZANTE EN TANQUE CISTERN m2 18.22 38.42 700.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.22 700.01 100.00%
07.02.02.09 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 4.50 13.60 61.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.50 61.20 100.00%
07.02.03 PISOS 365.09
07.02.03.01 PISO CEMENTO PULIDO E=2" m2 7.04 51.86 365.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.04 365.09 100.00%
07.02.04 ZOCALOS 369.60 0.00
07.02.04.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 24.00 15.40 369.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 369.60 100.00%
07.02.05 CARPINTERIA DE MADERA 803.88
07.02.05.01 PUERTAS 803.88
07.02.05.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 1.62 496.22 803.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.62 803.88 100.00%
07.02.06 CARPINTERIA METALICA 2,119.02
07.02.06.01 VENTANAS 463.15
07.02.06.01.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.40 192.98 463.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 463.15 100.00%
07.02.06.02 ESCALERAS 1,655.87

Página 20
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

07.02.06.02.01 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO m 8.50 135.43 1,151.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.50 1,151.16 100.00%
07.02.06.02.02 ESCALERA GATO ALUMINIO - CISTERNA und 1.00 309.90 309.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 309.90 100.00%
07.02.06.02.03 MARCO Y TAPA DE FIERRO 60x60 und 1.00 194.81 194.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 194.81 100.00%
07.02.07 CERRAJERIA 104.96 0.00
07.02.07.01 CERRADURA DE DOS GOLPES TIPO PESADO pza 1.00 77.93 77.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.93 100.00%
07.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 3.00 9.01 27.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 27.03 100.00%
07.02.08 VIDRIOS, CRISTALES Y SIMILARES 333.72
07.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 25.83 12.92 333.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.83 333.72 100.00%
07.02.09 PINTURAS 1,336.91
07.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 31.68 10.57 334.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.68 334.86 100.00%
07.02.09.02 PINTURA EN CONTRAZOCALO m2 2.40 7.96 19.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.40 19.10 100.00%
07.02.09.03 PINTURA EN VIGAS m2 24.48 13.73 336.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.48 336.11 100.00%
07.02.09.04 PINTURA EN COLUMNAS m2 49.04 13.19 646.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.04 646.84 100.00%
07.03 INSTALACIONES ELECTRICAS 3,766.59
07.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 1.00 145.99 145.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.99 100.00%
07.03.02 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 1.00 219.38 219.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 219.38 100.00%
07.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
07.03.04 SALIDA PARA ELECTROBOMBA pto 2.00 104.38 208.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 208.76 100.00%
07.03.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 1.00 68.59 68.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 68.59 100.00%
07.03.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 9.96 10.81 107.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.96 107.67 100.00%
07.03.07 ALAMBRE THHN 2.5 mm2 m 5.08 1.67 8.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.08 8.48 100.00%
07.03.08 ALAMBRE THHN 4 mm2 m 22.26 2.19 48.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.26 48.75 100.00%
07.03.09 EQUIPO DE BOMBEO, INC. 2 ELECTROBOMBAS 1 HP Y TABL und 1.00 1,505.51 1,505.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,505.51 100.00%
07.03.10 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
07.03.11 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
07.03.12 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
07.04 INSTALACIONES SANITARIAS 7,527.80
07.04.01 VALVULAS Y LLAVES 1,332.90
07.04.01.01 VALVULA COMPUERTA DE 3/4" und 1.00 100.51 100.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 100.51 100.00%
07.04.01.02 VALVULA COMPUERTA DE 1 1/2" und 3.00 189.35 568.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 568.05 100.00%
07.04.01.03 VALVULA CHECK DE BRONCE 1 1/2" und 2.00 98.74 197.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 197.48 100.00%
07.04.01.04 VALVULA FLOTADORA 3/4" und 1.00 101.28 101.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 101.28 100.00%
07.04.01.05 VALVULA PIE CON CANASTILLA DE BRONCE 2" und 2.00 182.79 365.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 365.58 100.00%
07.04.02 ALMACENAMIENTO DE AGUA 6,033.58
07.04.02.01 TUBERIA F°G° 3" m 1.00 51.83 51.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 51.83 100.00%
07.04.02.02 TUBERIA F°G° 2" m 15.70 33.60 527.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.70 527.52 100.00%
07.04.02.03 TUBERIA F°G° 1 1/2" m 22.35 27.70 619.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.35 619.10 100.00%
07.04.02.04 CODO F°G° 3" x 90 und 1.00 56.76 56.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 56.76 100.00%
07.04.02.05 CODO F°G° 2" x 90 und 7.00 31.93 223.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 223.51 100.00%
07.04.02.06 CODO F°G° 1 1/2" x 90 und 8.00 26.51 212.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 212.08 100.00%
07.04.02.07 TEE F°G° 2" und 1.00 35.32 35.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 35.32 100.00%
07.04.02.08 TEE F°G° 1 1/2" und 2.00 31.08 62.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 62.16 100.00%
07.04.02.09 UNION UNIVERSAL F°G° 2" und 6.00 79.25 475.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 475.50 100.00%
07.04.02.10 UNION UNIVERSAL F°G° 1 1/2" und 8.00 56.84 454.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 454.72 100.00%
07.04.02.11 BRIDA ROMPE AGUA und 3.00 38.94 116.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 116.82 100.00%
07.04.02.12 JUNTA WATER STOP 8" m 11.20 76.42 855.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.20 855.90 100.00%
07.04.02.13 CAJA DE REBOSE C/REJILLA DE FIERRO und 1.00 280.52 280.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 280.52 100.00%
07.04.02.14 TAPA METALICA SANITARIA und 1.00 326.48 326.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 326.48 100.00%
07.04.02.15 ABRAZADERAS DE F°G° und 23.00 10.67 245.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 245.41 100.00%
07.04.02.16 TANQUE DE POLIETILENO 2500 LT und 1.00 1,489.95 1,489.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,489.95 100.00%
07.04.03 DESAGUE Y VENTILACION 161.32
07.04.03.01 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
07.04.03.02 SOMBRERO DE VENTILACION 2" und 1.00 15.78 15.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 15.78 100.00%
08 PORTADA Y CASETA DE VIGILANCIA 22,918.40
08.01 ESTRUCTURAS 9,518.16
08.01.01 OBRAS PRELIMINARES 16.90
08.01.01.01 LIMPIEZA DE TERRENO m2 6.28 0.95 5.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 5.97 100.00%
08.01.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 6.28 1.74 10.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.28 10.93 100.00%

Página 21
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.01.02 MOVIMIENTO DE TIERRAS 743.23


08.01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 2.56 41.41 106.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.56 106.01 100.00%
08.01.02.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 7.96 41.41 329.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.96 329.62 100.00%
08.01.02.03 NIVELACION Y APISONADO MANUAL PARA PISOS m2 3.81 2.48 9.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 9.45 100.00%
08.01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 0.96 27.36 26.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.96 26.27 100.00%
08.01.02.05 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 0.38 197.01 74.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.38 74.86 100.00%
08.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 12 m3 12.43 15.85 197.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.43 197.02 100.00%
08.01.03 OBRAS DE CONCRETO SIMPLE 717.03
08.01.03.01 SOLADO PARA ZAPATAS m2 6.62 35.13 232.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.62 232.56 100.00%
08.01.03.02 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 1.00 333.17 333.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 333.17 100.00%
08.01.03.03 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 3.81 39.71 151.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 151.30 100.00%
08.01.04 OBRAS DE CONCRETO ARMADO 8,041.00
08.01.04.01 SOBRECIMIENTO ARMADO 1,094.65
08.01.04.01.01 SOBRECIMIENTO 1:8 + 25% P.M m3 0.88 387.67 341.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.88 341.15 100.00%
08.01.04.01.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 11.78 46.45 547.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.78 547.18 100.00%
08.01.04.01.03 SOBRECIMIENTO ACERO fy=4,200 kg/cm2 kg 49.36 4.18 206.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.36 206.32 100.00%
08.01.04.02 ZAPATAS 1,709.32
08.01.04.02.01 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 3.06 449.81 1,376.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.06 1,376.42 100.00%
08.01.04.02.02 ZAPATAS ACERO fy=4,200 kg/cm2 kg 79.64 4.18 332.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.64 332.90 100.00%
08.01.04.03 VIGA DE CIMENTACION 611.69
08.01.04.03.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 0.46 449.81 206.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.46 206.91 100.00%
08.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACI m2 3.70 51.41 190.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 190.22 100.00%
08.01.04.03.03 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 51.33 4.18 214.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.33 214.56 100.00%
08.01.04.04 COLUMNAS 2,534.69
08.01.04.04.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 1.21 449.81 544.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.21 544.27 100.00%
08.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 20.01 53.08 1,062.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.01 1,062.13 100.00%
08.01.04.04.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS kg 222.08 4.18 928.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.08 928.29 100.00%
08.01.04.05 VIGAS 1,500.04 0.00
08.01.04.05.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 0.84 449.81 377.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.84 377.84 100.00%
08.01.04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 9.61 62.13 597.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 597.07 100.00%
08.01.04.05.03 VIGAS ACERO fy=4,200 kg/cm2 kg 125.63 4.18 525.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 125.63 525.13 100.00%
08.01.04.06 PARAPETO 276.08
08.01.04.06.01 CONCRETO PARAPETO f'c=210 kg/cm2 m3 0.18 449.81 80.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.18 80.97 100.00%
08.01.04.06.02 ENCOFRADO Y DESENCOFRADO EN PARAPETO m2 2.45 62.13 152.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.45 152.22 100.00%
08.01.04.06.03 PARAPETO ACERO fy=4,200 kg/cm2 kg 10.26 4.18 42.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.26 42.89 100.00%
08.01.04.07 LOSAS ALIGERADAS 314.53
08.01.04.07.01 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 0.21 449.81 94.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.21 94.46 100.00%
08.01.04.07.02 LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO m2 2.41 51.12 123.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 123.20 100.00%
08.01.04.07.03 LOSAS ALIGERADAS ACERO fy=4,200 kg/cm2 kg 9.41 4.18 39.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.41 39.33 100.00%
08.01.04.07.04 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 21.00 2.74 57.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 57.54 100.00%
08.02 ARQUITECTURA 9,207.85
08.02.01 ALBAÑILERIA 798.58
08.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARE m2 14.42 55.38 798.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 798.58 100.00%
08.02.02 REVOQUES 1,810.03
08.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 14.42 26.62 383.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.42 383.86 100.00%
08.02.02.03 TARRAJEO DE COLUMNAS C:A-1:4 m2 12.72 28.80 366.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.72 366.34 100.00%
08.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS m 37.10 3.45 128.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.10 128.00 100.00%
08.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 9.61 31.39 301.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 301.66 100.00%
08.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 23.30 3.45 80.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.30 80.39 100.00%
08.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1 m 12.20 13.60 165.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 165.92 100.00%
08.02.03 CIELO RASO 104.50
08.02.03.01 TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-A m2 2.41 43.36 104.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 104.50 100.00%
08.02.04 PISOS Y PAVIMENTOS 197.59
08.02.04.01 PISO CEMENTO PULIDO E=2" m2 3.81 51.86 197.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.81 197.59 100.00%
08.02.05 CONTRAZOCALOS 267.96
08.02.05.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 17.40 15.40 267.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.40 267.96 100.00%
08.02.06 CARPINTERIA MADERA 1,276.07

Página 22
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

08.02.06.01 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 3.64 350.57 1,276.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.64 1,276.07 100.00%
08.02.07 CARPINTERIA METALICA 3,627.00
08.02.07.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 2.44 192.98 470.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.44 470.87 100.00%
08.02.07.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" m2 9.62 328.08 3,156.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.62 3,156.13 100.00%
08.02.08 CERRAJERIA 209.92
08.02.08.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
08.02.08.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
08.02.09 VIDRIOS, CRISTALES Y SIMILARES 339.28
08.02.09.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 26.26 12.92 339.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.26 339.28 100.00%
08.02.10 PINTURAS 576.92
08.02.10.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 23.84 10.57 251.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.84 251.99 100.00%
08.02.10.02 PINTURA EN CONTRAZOCALO m2 3.48 7.96 27.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.48 27.70 100.00%
08.02.10.03 PINTURA EN VIGAS m2 9.61 13.73 131.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.61 131.95 100.00%
08.02.10.04 PINTURA EN COLUMNAS m2 10.60 13.19 139.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.60 139.81 100.00%
08.02.10.05 PINTURA EN CIELO RASO m2 2.41 10.57 25.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 25.47 100.00%
08.03 INSTALACIONES ELECTRICAS 1,807.85
08.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 2.00 145.99 291.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 291.98 100.00%
08.03.02 SALIDA TOMACORRIENTE pto 2.00 215.17 430.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 430.34 100.00%
08.03.03 SALIDA PARA INTERRUPTOR SIMPLE pto 2.00 108.23 216.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 216.46 100.00%
08.03.04 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIR und 2.00 68.59 137.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 137.18 100.00%
08.03.05 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 12.00 10.81 129.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 129.72 100.00%
08.03.06 ALAMBRE THHN 2.5 mm2 m 36.00 1.67 60.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 60.12 100.00%
08.03.07 ALAMBRE THHN 4 mm2 m 24.00 2.19 52.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 52.56 100.00%
08.03.08 TABLERO DE DISTRIBUCION und 1.00 439.49 439.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.49 100.00%
08.03.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
08.04 INSTALACIONES SANITARIAS 2,384.54
08.04.01 APARATOS Y ACCESORIOS SANITARIOS 596.94
08.04.01.01 INODORO TANQUE BAJO pza 1.00 361.79 361.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 361.79 100.00%
08.04.01.02 LAVATORIO DE LOZA BLANCA und 1.00 195.88 195.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 195.88 100.00%
08.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 1.00 39.27 39.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 39.27 100.00%
08.04.02 SISTEMA DE DESAGUE 1,219.68
08.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 93.15 186.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 186.30 100.00%
08.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 1.00 145.54 145.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 145.54 100.00%
08.04.02.03 SALIDA VENTILACION DE 2" pto 1.00 58.08 58.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58.08 100.00%
08.04.02.04 REGISTRO DE BRONCE 4" und 1.00 285.99 285.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 285.99 100.00%
08.04.02.05 SUMIDERO DE 2" pza 1.00 77.41 77.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 77.41 100.00%
08.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 3.00 33.95 101.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 101.85 100.00%
08.04.02.07 YEE PVC SAL 4"X2" und 1.00 61.97 61.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 61.97 100.00%
08.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 25.81 51.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 51.62 100.00%
08.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 3.00 14.89 44.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 44.67 100.00%
08.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.00 3.86 11.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 11.58 100.00%
08.04.02.11 CAMA DE APOYO m 3.00 9.44 28.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 28.32 100.00%
08.04.02.12 RELLENO COMPACTADO DE ZANJAS m 3.00 12.00 36.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 36.00 100.00%
08.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
08.04.03 SISTEMA DE AGUA FRIA 567.92
08.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 2.00 72.84 145.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 145.68 100.00%
08.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 3.50 17.01 59.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 59.54 100.00%
08.04.03.03 CODO PVC 1/2" und 1.00 9.94 9.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.94 100.00%
08.04.03.04 TEE PVC 1/2" und 1.00 11.04 11.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11.04 100.00%
08.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 3.50 14.89 52.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 52.12 100.00%
08.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 3.50 3.86 13.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 13.51 100.00%
08.04.03.07 CAMA DE APOYO m 3.50 9.44 33.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 33.04 100.00%
08.04.03.08 RELLENO COMPACTADO DE ZANJAS m 3.50 12.00 42.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.50 42.00 100.00%
08.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1 und 1.00 70.70 70.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 70.70 100.00%
08.04.03.10 CAJA PARA VALVULAS und 1.00 130.35 130.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.35 100.00%
09 MITIGACIÓN AMBIENTAL 25,000.00
09.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 25,000.00 25,000.00 0.80 20,000.00 80.00% 0.00 0.00 0.00% 0.80 20,000.00 80.00% 0.20 5,000.00 20.00%
10 CAPACITACION Y SENSIBILIZACION 19,880.00

Página 23
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

10.01 CAPACITACION PARA MANTENIMIENTO glb 1.00 8,380.00 8,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,380.00 100.00%
10.02 SENSIBILIZACION DE BENEFICIARIOS glb 1.00 11,500.00 11,500.00 0.30 3,450.00 30.00% 0.00 0.00 0.00% 0.30 3,450.00 30.00% 0.70 8,050.00 70.00%
11 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
11.01 CARPINTERIA MADERA 2,580.34
11.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
11.02 CARPINTERIA METALICA 3,189.96
11.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
11.03 CERRAJERIA 209.92
11.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
11.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
11.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
11.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
11.05 PINTURAS 3,174.34
11.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
11.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
11.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
11.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
11.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 1.00 607.27 100.00% 0.00 0.00 0.00% 1.00 607.27 100.00% 0.00 0.00 0.00%
11.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
11.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
11.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
11.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
11.07 INSTALACIONES ELECTRICAS 8,783.50
11.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
11.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%
11.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
11.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
11.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
11.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
11.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
11.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
11.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
11.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
11.08 VARIOS 843.30 0.00
11.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
12 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
12.01 CARPINTERIA MADERA 2,580.34
12.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
12.02 CARPINTERIA METALICA 3,189.96
12.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
12.03 CERRAJERIA 209.92
12.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
12.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
12.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
12.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
12.05 PINTURAS 3,174.34
12.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
12.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
12.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
12.06 CUBIERTA METALICA Y CIELO RASO 44,352.34
12.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 607.27 100.00%
12.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
12.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
12.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
12.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
12.07 INSTALACIONES ELECTRICAS 8,783.50
12.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
12.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%

Página 24
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

12.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
12.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
12.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
12.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
12.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
12.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
12.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
12.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
12.08 VARIOS 843.30
12.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
13 REMODELACION Y CAMBIO DE CUBIERTA SECTOR PRIMARIA AULAS 1 Y 2 65,432.56
13.01 CARPINTERIA MADERA 2,580.34
13.01.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 5.20 496.22 2,580.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.20 2,580.34 100.00%
13.02 CARPINTERIA METALICA 3,189.96
13.02.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 16.53 192.98 3,189.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.53 3,189.96 100.00%
13.03 CERRAJERIA 209.92
13.03.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 2.00 77.93 155.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 155.86 100.00%
13.03.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 6.00 9.01 54.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 54.06 100.00%
13.04 VIDRIOS, CRISTALES Y SIMILARES 2,298.86
13.04.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 177.93 12.92 2,298.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 177.93 2,298.86 100.00%
13.05 PINTURAS 3,174.34
13.05.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 164.80 10.57 1,741.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.80 1,741.94 100.00%
13.05.02 PINTURA EN VIGAS m2 77.60 13.73 1,065.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.60 1,065.45 100.00%
13.05.03 PINTURA EN COLUMNAS m2 27.82 13.19 366.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.82 366.95 100.00%
13.06 CUBIERTA METALICA Y CIELO RASO 44,352.34 0.00
13.06.01 DESMONTAJE DE COBERTURA EXISTENTE glb 1.00 607.27 607.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 607.27 100.00%
13.06.02 RESANE PRODUCTO DE DESMONTAJE glb 1.00 1,582.15 1,582.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,582.15 100.00%
13.06.03 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS m2 132.41 122.00 16,154.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.41 16,154.02 100.00%
13.06.04 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORT m 136.50 75.18 10,262.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.50 10,262.07 100.00%
13.06.05 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 135.05 116.60 15,746.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 135.05 15,746.83 100.00%
13.07 INSTALACIONES ELECTRICAS 8,783.50
13.07.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 15.00 145.99 2,189.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 2,189.85 100.00%
13.07.02 SALIDA TOMACORRIENTE pto 5.00 215.17 1,075.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,075.85 100.00%
13.07.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 108.23 108.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 108.23 100.00%
13.07.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 112.89 225.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 225.78 100.00%
13.07.05 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/E und 15.00 205.71 3,085.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,085.65 100.00%
13.07.06 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 73.02 10.81 789.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.02 789.35 100.00%
13.07.07 ALAMBRE THHN 2.5 mm2 m 147.44 1.67 246.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 147.44 246.22 100.00%
13.07.08 ALAMBRE THHN 4 mm2 m 71.61 2.19 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.61 156.83 100.00%
13.07.09 PRUEBA ELECTRICA glb 1.00 50.00 50.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 50.00 100.00%
13.07.10 POZO DE CONEXION A TIERRA und 1.00 855.74 855.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 855.74 100.00%
13.08 VARIOS 843.30
13.08.01 CANALETA PARA AGUA FLUVIAL DE 4" m 27.30 30.89 843.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.30 843.30 100.00%
14 CONSTRUCCION DE VEREDAS 124,773.80
14.01 OBRAS PRELIMINARES 2,711.41
14.01.01 LIMPIEZA DE TERRENO m2 1,034.89 0.97 1,003.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 1,003.84 100.00%
14.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 1,034.89 1.65 1,707.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 1,707.57 100.00%
14.02 MOVIMIENTO DE TIERRAS 43,860.65
14.02.01 CORTE DE TERRENO CON MAQUINARIA m3 206.98 5.34 1,105.27 200.00 1,068.00 96.63% 0.00 0.00 0.00% 200.00 1,068.00 96.63% 6.98 37.27 3.37%
14.02.02 BASE PARA VEREDAS DE 0.15 M m2 1,034.89 37.51 38,818.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 38,818.72 100.00%
14.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 248.37 15.85 3,936.66 240.00 3,804.00 96.63% 0.00 0.00 0.00% 240.00 3,804.00 96.63% 8.37 132.66 3.37%
14.03 CONCRETO SIMPLE 78,201.74
14.03.01 VEREDA CONC. FC=175 KG/CM2 E=4" m2 1,034.89 43.57 45,090.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 45,090.16 100.00%
14.03.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 275.97 41.82 11,541.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 275.97 11,541.07 100.00%
14.03.03 JUNTA DE DILATACION m 1,379.85 13.78 19,014.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,379.85 19,014.33 100.00%
14.03.04 CURADO CON AGUA EN VEREDA m2 1,034.89 2.47 2,556.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,034.89 2,556.18 100.00%
15 RAMPAS 8,542.76
15.01 OBRAS PRELIMINARES 104.64

Página 25
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

15.01.01 LIMPIEZA DE TERRENO m2 39.94 0.97 38.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 38.74 100.00%
15.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 39.94 1.65 65.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 65.90 100.00%
15.02 MOVIMIENTO DE TIERRAS 255.14
15.02.01 CORTE DE TERRENO CON MAQUINARIA m3 1.25 5.34 6.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.25 6.68 100.00%
15.02.02 BASE PARA RAMPAS DE 0.15 M m2 5.99 37.51 224.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.99 224.68 100.00%
15.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 1.50 15.85 23.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.50 23.78 100.00%
15.03 CONCRETO SIMPLE 3,159.80
15.03.01 CONCRETO FROTACHADO EN LOSA FC=175 KG/CM2 E=4" m3 4.63 439.64 2,035.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.63 2,035.53 100.00%
15.03.02 ENCOFRADO Y DESENCOFRADO EN RAMPAS m2 19.17 41.82 801.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.17 801.69 100.00%
15.03.03 JUNTA DE DILATACION m 16.25 13.78 223.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.25 223.93 100.00%
15.03.04 CURADO CON AGUA EN RAMPAS m2 39.94 2.47 98.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.94 98.65 100.00%
15.04 CARPINTERIA METALICA 5,023.18
15.04.01 BARANDAS METALICAS DE TUBO 2" m 63.90 78.61 5,023.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.90 5,023.18 100.00%
16 GRADAS Y ESCALERAS 15,269.04
16.01 OBRAS PRELIMINARES 60.34
16.01.01 LIMPIEZA DE TERRENO m2 22.43 0.95 21.31 2.90 2.76 12.93% 0.00 0.00 0.00% 2.90 2.76 12.93% 19.53 18.56 87.07%
16.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 22.43 1.74 39.03 2.90 5.05 12.93% 0.00 0.00 0.00% 2.90 5.05 12.93% 19.53 33.98 87.07%
16.02 MOVIMIENTO DE TIERRAS 1,247.62
16.02.01 EXCAVACION DE ZANJAS MANUAL m3 5.25 41.41 217.40 1.00 41.41 19.05% 0.00 0.00 0.00% 1.00 41.41 19.05% 4.25 175.99 80.95%
16.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 13.46 27.36 368.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.46 368.27 100.00%
16.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 3.36 197.01 661.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.36 661.95 100.00%
16.03 OBRAS DE CONCRETO 6,737.15
16.03.01 CIMIENTOS 1,749.14
16.03.01.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 3 m3 5.25 333.17 1,749.14 1.00 333.17 19.05% 0.00 0.00 0.00% 1.00 333.17 19.05% 4.25 1,415.97 80.95%
16.03.02 ESCALERAS 4,988.01
16.03.02.01 ESCALERAS CONCRETO FC=210 KG/CM2 m3 7.98 449.81 3,589.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.98 3,589.48 100.00%
16.03.02.02 ESCALERA ENCOFRADO Y DESENCOFRADO m2 14.70 60.97 896.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.70 896.26 100.00%
16.03.02.03 ESCALERA ACERO fy=4,200 kg/cm2 kg 120.16 4.18 502.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 120.16 502.27 100.00%
16.04 REVOQUES 1,470.32
16.04.01 REVESTIMIENTO DE GRADAS Y ESCALERA m2 39.90 36.85 1,470.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.90 1,470.32 100.00%
16.05 CARPINTERIA METALICA 4,997.34
16.05.01 BARANDAS METALICAS DE TUBO 2" m 44.85 78.61 3,525.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 3,525.66 100.00%
16.05.02 CANTONERA DE ALUMINIO EN PASOS DE ESCALERA m 84.00 17.52 1,471.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.00 1,471.68 100.00%
16.06 PINTURAS 466.89
16.06.01 PINTURA ANTICORROSIVA EN BARANDAS m 44.85 10.41 466.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.85 466.89 100.00%
16.07 VARIOS 289.38
16.07.01 JUNTA DE DILATACION m 21.00 13.78 289.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 289.38 100.00%
17 PATIO DE HONOR 28,317.10
17.01 OBRAS PRELIMINARES 709.26
17.01.01 LIMPIEZA DE TERRENO m2 270.71 0.97 262.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 262.59 100.00%
17.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 270.71 1.65 446.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 446.67 100.00%
17.02 MOVIMIENTO DE TIERRAS 11,012.28
17.02.01 CORTE DE TERRENO CON MAQUINARIA m3 27.07 5.34 144.55 27.07 144.55 100.00% 0.00 0.00 0.00% 27.07 144.55 100.00% 0.00 0.00 0.00%
17.02.02 BASE GRANULAR DE 0.15 M m2 276.00 37.51 10,352.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 276.00 10,352.76 100.00%
17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 32.49 15.85 514.97 32.49 514.97 100.00% 0.00 0.00 0.00% 32.49 514.97 100.00% 0.00 0.00 0.00%
17.03 CONCRETO SIMPLE 16,595.56
17.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 27.07 439.64 11,901.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.07 11,901.05 100.00%
17.03.02 ENCOFRADO Y DESENCOFRADO EN PATIO m2 36.80 41.82 1,538.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.80 1,538.98 100.00%
17.03.03 JUNTA DE DILATACION m 180.47 13.78 2,486.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 180.47 2,486.88 100.00%
17.03.04 CURADO CON AGUA m2 270.71 2.47 668.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.71 668.65 100.00%
18 LOSAS DEPORTIVA 60,745.47
18.01 OBRAS PRELIMINARES 1,092.02
18.01.01 LIMPIEZA DE TERRENO m2 416.80 0.97 404.30 416.80 404.30 100.00% 0.00 0.00 0.00% 416.80 404.30 100.00% 0.00 0.00 0.00%
18.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 416.80 1.65 687.72 416.80 687.72 100.00% 0.00 0.00 0.00% 416.80 687.72 100.00% 0.00 0.00 0.00%
18.02 MOVIMIENTO DE TIERRAS 17,157.10
18.02.01 CORTE DE TERRENO CON MAQUINARIA m3 62.52 5.34 333.86 62.52 333.86 100.00% 0.00 0.00 0.00% 62.52 333.86 100.00% 0.00 0.00 0.00%
18.02.02 BASE GRANULAR DE 0.15 M m2 416.80 37.51 15,634.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 15,634.17 100.00%
18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 75.02 15.85 1,189.07 75.02 1,189.07 100.00% 0.00 0.00 0.00% 75.02 1,189.07 100.00% 0.00 0.00 0.00%

Página 26
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

18.03 CONCRETO SIMPLE 31,783.50


18.03.01 CONCRETO SEMIPULIDO EN LOSA FC=175 KG/CM2 m3 62.52 439.64 27,486.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 62.52 27,486.29 100.00%
18.03.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPORTIVA m2 83.36 51.55 4,297.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.36 4,297.21 100.00%
18.04 PINTURAS 1,837.47
18.04.01 PINTURA DE MARCA EN LOSA DEPORTIVA m 266.30 6.90 1,837.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 266.30 1,837.47 100.00%
18.05 VARIOS 8,875.38
18.05.01 JUNTA DE DILATACION m 277.87 13.78 3,829.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 277.87 3,829.05 100.00%
18.05.02 CURADO CON ADITIVO ANTISOL m2 416.80 3.71 1,546.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 416.80 1,546.33 100.00%
18.05.03 ARCOS DE FUTBOL CON TABLERO DE BASQUET pza 2.00 1,500.00 3,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,000.00 100.00%
18.05.04 POSTE DE TUBO PARA VOLEY pza 2.00 250.00 500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 500.00 100.00%
19 CONSTRUCCION DE MURO DE CONTENCION 647,548.41
19.01 OBRAS PRELIMINARES 2,466.94
19.01.01 LIMPIEZA DE TERRENO m2 941.58 0.97 913.33 800.00 776.00 84.96% 0.00 0.00 0.00% 800.00 776.00 84.96% 141.58 137.33 15.04%
19.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 941.58 1.65 1,553.61 800.00 1,320.00 84.96% 0.00 0.00 0.00% 800.00 1,320.00 84.96% 141.58 233.61 15.04%
19.02 MOVIMIENTO DE TIERRAS 123,308.74
19.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 685.44 41.41 28,384.07 120.40 4,985.76 17.57% 0.00 0.00 0.00% 120.40 4,985.76 17.57% 565.04 23,398.31 82.43%
19.02.02 NIVELACION Y APISONADO MANUAL m2 763.37 2.48 1,893.16 50.00 124.00 6.55% 0.00 0.00 0.00% 50.00 124.00 6.55% 713.37 1,769.16 93.45%
19.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO (AFI m3 381.63 197.01 75,184.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 381.63 75,184.93 100.00%
19.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 637.26 27.36 17,435.43 10.00 273.60 1.57% 0.00 0.00 0.00% 10.00 273.60 1.57% 627.26 17,161.83 98.43%
19.02.05 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 25.94 15.85 411.15 8.00 126.80 30.84% 0.00 0.00 0.00% 8.00 126.80 30.84% 17.94 284.35 69.16%
19.03 OBRAS DE CONCRETO 520,704.96
19.03.01 CONCRETO CICLOPEO MURO DE CONTENCION FC=140 KG/CM m3 1,108.26 372.14 412,427.88 215.00 80,010.10 19.40% 0.00 0.00 0.00% 215.00 80,010.10 19.40% 893.26 332,417.78 80.60%
19.03.02 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION m2 2,120.17 51.07 108,277.08 296.00 15,116.72 13.96% 0.00 0.00 0.00% 296.00 15,116.72 13.96% 1,824.17 93,160.36 86.04%
19.04 VARIOS 1,067.77
19.04.01 TUBERIA PVC SAL D=3" DRENAJE MUROS m 83.16 12.84 1,067.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 83.16 1,067.77 100.00%
20 CONSTRUCCION DE CERCO 53,726.28
20.01 OBRAS PRELIMINARES 127.62
20.01.01 LIMPIEZA DE TERRENO m2 48.71 0.97 47.25 48.71 47.25 100.00% 0.00 0.00 0.00% 48.71 47.25 100.00% 0.00 0.00 0.00%
20.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 48.71 1.65 80.37 48.71 80.37 100.00% 0.00 0.00 0.00% 48.71 80.37 100.00% 0.00 0.00 0.00%
20.02 MOVIMIENTO DE TIERRAS 49.07 0.00
20.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 0.81 41.41 33.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 33.54 100.00%
20.02.02 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 0.98 15.85 15.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.98 15.53 100.00%
20.03 OBRAS DE CONCRETO SIMPLE 269.87
20.03.01 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 30 m3 0.81 333.17 269.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 269.87 100.00%
20.04 CARPINTERIA METALICA 53,279.72
20.04.01 CERCO MALLA METALICA COCADA DE 2" m 173.51 307.07 53,279.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 173.51 53,279.72 100.00%
21 ADQUISICION E INSTALACION DE POSTES ORNAMENTALES 30,322.97
21.01 ADQUISICION DE POSTES ORNAMENTALES und 26.00 350.00 9,100.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 9,100.00 100.00%
21.02 TRAZO NIVELADO Y REPLANTEO m2 13.00 1.67 21.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 21.71 100.00%
21.03 CIMENTACION PARA POSTES m3 6.50 333.17 2,165.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.50 2,165.61 100.00%
21.04 EXCAVACION DE ZANJAS PARA CABLE SUBTERRANEO m3 76.53 41.41 3,169.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.53 3,169.11 100.00%
21.05 INSTALACION DE POSTES ORNAMENTALES und 26.00 6.34 164.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 164.84 100.00%
21.06 INSTALACION DE FAROLAS ORNAMENTALES und 26.00 209.37 5,443.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 5,443.62 100.00%
21.07 INSTALACION DE CABLE SUBTERRANEO NYY 3X10MM2 m 306.12 33.51 10,258.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 306.12 10,258.08 100.00%
22 CORTES GENERALES 145,915.73
22.01 EXCAVACION CON MAQUINARIA m3 5,516.20 6.96 38,392.75 5,516.20 38,392.75 100.00% 0.00 0.00 0.00% 5,516.20 38,392.75 100.00% 0.00 0.00 0.00%
22.02 RELLENO CON MATERIAL PROPIO, COMPACTADO m3 345.58 27.36 9,455.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 345.58 9,455.07 100.00%
22.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP m3 6,187.25 15.85 98,067.91 6,187.25 98,067.91 100.00% 0.00 0.00 0.00% 6,187.25 98,067.91 100.00% 0.00 0.00 0.00%
23 INSTALACION DE SISTEMA DE AGUA Y DESAGUE 28,190.61
23.01 SISTEMA DE DESAGUE 8,307.53
23.01.01 TRAZO NIVELADO Y REPLANTEO m 91.31 1.65 150.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 150.66 100.00%
23.01.02 EXCAVACION MANUAL PARA TUBERIA m 91.31 14.89 1,359.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 1,359.61 100.00%
23.01.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 91.31 3.86 352.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 352.46 100.00%
23.01.04 CAMA DE APOYO m 91.31 9.44 861.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 861.97 100.00%
23.01.05 RELLENO COMPACTADO DE ZANJAS m 91.31 12.00 1,095.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 1,095.72 100.00%
23.01.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 3.65 15.85 57.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.65 57.85 100.00%
23.01.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 14.03 21.56 302.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.03 302.49 100.00%
23.01.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 77.28 41.51 3,207.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.28 3,207.89 100.00%

Página 27
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

23.01.09 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 577.38 100.00%
23.01.10 PRUEBA HIDRAULICA m 91.31 3.74 341.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.31 341.50 100.00%
23.02 SISTEMA DE AGUA 6,827.77
23.02.01 TRAZO NIVELADO Y REPLANTEO m 112.03 1.65 184.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 184.85 100.00%
23.02.02 EXCAVACION MANUAL PARA TUBERIA m 112.03 14.89 1,668.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,668.13 100.00%
23.02.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 112.03 3.86 432.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 432.44 100.00%
23.02.04 CAMA DE APOYO m 112.03 9.44 1,057.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,057.56 100.00%
23.02.05 RELLENO COMPACTADO DE ZANJAS m 112.03 12.00 1,344.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 1,344.36 100.00%
23.02.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.38 15.85 85.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.38 85.27 100.00%
23.02.07 SUMINISTRO E INSTALACION DE TUBERIA 1 1/2" AGUA m 75.48 15.65 1,181.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 75.48 1,181.26 100.00%
23.02.08 SUMINISTRO E INSTALACION DE TUBERIA 3/4" AGUA m 36.55 10.07 368.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.55 368.06 100.00%
23.02.09 SUMINISTRO E INSTALACION DE ACCESORIOS glb 1.00 86.85 86.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 86.85 100.00%
23.02.10 PRUEBA HIDRAULICA m 112.03 3.74 418.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.03 418.99 100.00%
23.03 SISTEMA DE DRENAJE 13,055.31
23.03.01 TRAZO NIVELADO Y REPLANTEO m 133.95 1.65 221.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 221.02 100.00%
23.03.02 EXCAVACION MANUAL PARA TUBERIA m 133.95 14.89 1,994.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,994.52 100.00%
23.03.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 133.95 3.86 517.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 517.05 100.00%
23.03.04 CAMA DE APOYO m 133.95 9.44 1,264.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,264.49 100.00%
23.03.05 RELLENO COMPACTADO DE ZANJAS m 133.95 12.00 1,607.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 1,607.40 100.00%
23.03.06 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 5.36 15.85 84.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.36 84.96 100.00%
23.03.07 SUMINISTRO E INSTALACION DE TUBERIA 4" DE DESAGUE m 55.02 21.56 1,186.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 55.02 1,186.23 100.00%
23.03.08 SUMINISTRO E INSTALACION DE TUBERIA 6" DE DESAGUE m 41.00 41.51 1,701.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 1,701.91 100.00%
23.03.09 SUMINISTRO E INSTALACION DE TUBERIA 8" DE DESAGUE m 37.93 51.82 1,965.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.93 1,965.53 100.00%
23.03.10 CAJA DE REGISTRO 30X60 CM CON REJILLA METALICA und 11.00 130.35 1,433.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,433.85 100.00%
23.03.11 CAJAS DE REGISTRO DE DESAGUE 60 x 60 cm und 3.00 192.46 577.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 577.38 100.00%
23.03.12 PRUEBA HIDRAULICA m 133.95 3.74 500.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 133.95 500.97 100.00%
24 INSTALACIONES ELECTRICAS GENERALES 22,569.52
24.01 TRAZO NIVELADO Y REPLANTEO m 140.00 1.65 231.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 231.00 100.00%
24.02 EXCAVACION MANUAL PARA TUBERIA m 140.00 14.89 2,084.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 2,084.60 100.00%
24.03 REFINE NIVELACION Y COMPACTACION DE ZANJA m 140.00 3.86 540.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 540.40 100.00%
24.04 CAMA DE APOYO m 140.00 9.44 1,321.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 1,321.60 100.00%
24.05 RELLENO COMPACTADO DE ZANJAS m 140.00 12.00 1,680.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 1,680.00 100.00%
24.06 CABLE NYY 6MM2 m 657.93 7.04 4,631.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 657.93 4,631.83 100.00%
24.07 CABLE NYY 10MM2 m 347.04 10.57 3,668.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 347.04 3,668.21 100.00%
24.08 CABLE NYY 16MM2 m 255.00 15.18 3,870.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 255.00 3,870.90 100.00%
24.09 SUMINISTRO E INSTALACION DE TUBERIA ELECTRICA 1" m 419.99 8.79 3,691.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 419.99 3,691.71 100.00%
24.10 TABLERO DE DISTRIBUCION und 1.00 543.57 543.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 543.57 100.00%
24.11 CAJA DE REGISTRO 40X40 CM und 3.00 101.90 305.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 305.70 100.00%
25 AREAS VERDES 42,366.85
25.01 OBRAS PRELIMINARES 1,990.31
25.01.01 LIMPIEZA DE TERRENO m2 759.66 0.97 736.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 736.87 100.00%
25.01.02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 759.66 1.65 1,253.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 1,253.44 100.00%
25.02 MOVIMIENTO DE TIERRAS 15,402.98
25.02.01 CORTE MANUAL DE TERRENO m3 75.97 24.14 1,833.92 50.00 1,207.00 65.82% 0.00 0.00 0.00% 50.00 1,207.00 65.82% 25.97 626.92 34.18%
25.02.02 PREPARACION DE TIERRA DE CHACRA m2 759.66 6.53 4,960.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 4,960.58 100.00%
25.02.03 EXT. Y NIV. DE TIERRA DE CHACRA PARA SEMBRADO DE GRA m2 759.66 9.43 7,163.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 7,163.59 100.00%
25.02.04 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125H m3 91.16 15.85 1,444.89 70.00 1,109.50 76.79% 0.00 0.00 0.00% 70.00 1,109.50 76.79% 21.16 335.39 23.21%
25.03 SEMBRADO DE GRASS 17,973.56
25.03.01 SEMBRADO DE GRASS m2 759.66 23.66 17,973.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 17,973.56 100.00%
25.04 VARIOS 7,000.00
25.04.01 ADQUISICION E INSTALACION DE JUEGO RECREATIVOS und 2.00 3,500.00 7,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,000.00 100.00%
26 ADQUISICION DE EQUIPAMIENTO 63,256.00
26.01 ADQUISICION DE EQUIPAMIENTO COCINA glb 1.00 4,980.00 4,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,980.00 100.00%
26.02 ADQUISICION DE EQUIPAMIENTO SALA DE COMPUTO glb 1.00 58,276.00 58,276.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58,276.00 100.00%
27 ADQUISICION DE MOBILIARIO ESCOLAR 64,465.00
27.01 ADQUISICION DE MOBILIARIO ESCOLAR INICIAL glb 4.00 240.00 960.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 960.00 100.00%
27.02 ADQUISICION DE MOBILIARIO ESCOLAR PRIMARIO glb 74.00 270.00 19,980.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.00 19,980.00 100.00%
27.03 ADQUISICION DE MOBILIARIO ESCOLAR SECUNDARIO glb 53.00 270.00 14,310.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.00 14,310.00 100.00%

Página 28
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

27.04 ADQUISICION DE MOBILIARIO PARA AULAS glb 1.00 10,380.00 10,380.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,380.00 100.00%
27.05 ADQUISICION DE MOBILIARIO PARA SALA DE USOS MULTIPLES glb 1.00 3,615.00 3,615.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,615.00 100.00%
27.06 ADQUISICION DE MOBILIARIO PARA SALA DE COMPUTO glb 1.00 6,865.00 6,865.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,865.00 100.00%
27.07 ADQUISICION DE MOBILIARIO PARA DIRECCION glb 1.00 715.00 715.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 715.00 100.00%
27.08 ADQUISICION DE MOBILIARIO PARA SECRETARIA Y ESPERA glb 1.00 970.00 970.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 970.00 100.00%
27.09 ADQUISICION DE MOBILIARIO PARA SALA DE PROFESORES glb 1.00 2,295.00 2,295.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,295.00 100.00%
27.10 ADQUISICION DE MOBILIARIO PARA CENTRO DE RECURSOS E glb 1.00 2,855.00 2,855.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,855.00 100.00%
27.11 ADQUISICION DE MOBILIARIO PARA COCINA glb 1.00 1,520.00 1,520.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,520.00 100.00%
28 FLETE TERRESTRE 4,000.00
28.01 TRANSPORTE DE EQUIPAMIENTO Y MOBILIARIO A OBRA glb 1.00 4,000.00 4,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,000.00 100.00%

COSTO DIRECTO 3,124,772.22 487,102.54 49,755.98 536,858.52 2,587,913.70


GASTOS GENERALES 9.21% 287,655.74 44,840.98 4,580.36 49,421.34 238,234.40
UTILIDAD 9.00% 281,229.50 43,839.23 4,478.04 48,317.27 232,912.23
SUB - TOTAL 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33
FACTOR DE RELACION 1.00000 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33

MONTO BRUTO VALORIZADO 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33


SUB-TOTAL 3,693,657.46 575,782.75 58,814.38 634,597.13 3,059,060.33

IGV (18%) 18% 103,640.90 10,586.59 114,227.48 550,630.86

VALOR REFERENCIAL 4,358,515.80 679,423.65 15.59% 69,400.97 1.59% 748,824.61 17.18% 3,609,691.19 82.82%
EXPEDIENTE TECNICO 110,263.07

EJECUCION DE OBRA+EXPEDIENTE TECNICO 4,468,778.87


SUPERVISION 110,263.07

TOTAL DE INVERSION 4,579,041.94

Página 29
VALORIZACION DE OBRA N° 01
PROPIETARIO : GOBIERNO REGIONAL DE ICA
"MEJORAMIENTO Y AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. Nº 22273 Y DE LA I.E. Nº 320 – CHAVIN, DISTRITO CHAVIN –
EJECUCIÓN DE LA OBRA
PROVINCIA CHINCHA – ICA"
UBICACIÓN : ICA - ICA - REGION DE ICA
CONTRATISTA EJECUTOR :
SISTEMA DE CONTRATACIÓN : SUMA ALZADA INICIO DE PLAZO CONTRACTUAL : 2/1/2019
SUPERVISOR DE OBRA :
VALOR REFERENCIAL DE OBRA S/. 15,265,415.14 Incluído IGV PLAZO DE EJECUCION : 180 DIAS CALENDARIOS

FECHA DE PRESUPUESTO BASE : ABRIL DE 2016


PRESUPUESTO OFERTADO S/. 15,265,415.14 Incluído IGV TERMINO DE PLAZO CONTRACTUAL : 7/30/2019
S/. 12,936,792.49 Sin IGV

MONTO DEL VALORIZACIÓN SALDO


DESCRIPCION CONTRATO
SIN IGV
ANTERIOR ACTUAL ACUMULADO % MONTO %

VALORIZACIÓN N° 11 - (VB)

ESTRUCTURAS 420,892.87 0.00 0.00 0.00 0.00% 420,892.87 100.00%

ARQUITECTURA 447,101.97 0.00 0.00 0.00 0.00% 447,101.97 100.00%


INSTALACIONES ELECTRICAS 58,053.82 0.00 0.00 0.00 0.00% 58,053.82 100.00%
INSTALACIONES SANITARIAS 13,174.52 0.00 0.00 0.00 0.00% 13,174.52 100.00%

VALORIZACIÓN N° 11 BRUTA - (VB) 939,223.19 0.00 0.00 0.00 0.00% 939,223.19 100.00%

% AVANCE DE LA OBRA A LA FECHA 0.00% 0.00% 0.00%


% AVANCE DE LA OBRA PROGRAMADO 0.00% 11.40% 11.40%

REAJUSTES (S)

REAJUSTE RECONOCIDO 0.00 0.00 0.00

TOTAL REAJUSTES - (S) 0.00 0.00 0.00

VALORIZACIÓN N° 11 (V = VB + S) 939,223.19 0.00 0.00 0.00

AMORTIZACIONES (A)
0
AMORTIZACION ADELANTO DIRECTO

AMORTIZACION ADELANTO DIRECTO 10% 93,922.32 0.00 0.00 0.00 0.00% 93,922.32 100.00%

AMORTIZACION ADELANTO DE MATERIALES

AMORTIZACION ADELANTO DE MATERIALES (NO SOLICITADO) 0.00 0.00 0.00 0.00 0.00% 0.00 0.00%

TOTAL AMORTIZACIONES 93,922.32 0.00 0.00 0.00 0.00% 93,922.32 100.00%

VALORIZACIÓN NETA ( VN = VB - A ) 939,223.19 0.00 0.00 0.00

MONTOS A PAGAR AL CONTRATISTA

EN EFECTIVO (VN ) 939,223.19 0.00 0.00 0.00


I.G.V. 169,060.17 0.00 0.00 0.00
MONTO TOTAL CON IGV 1,108,283.37 0.00 0.00 0.00

TOTAL A SOLICITAR A FAVOR DEL CONTRATISTA 1,108,283.37 0.00 0.00 0.00


OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : ICONSER SAC
PLAZO : 120 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 01 - ESTRUCTURAS

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

01 OBRAS PROVISIONALES
01.01 CARTEL PARA LA OBRA 2.40 X 3.60 und 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,000.00 100.00%
01.01.01 ALMACEN DE OBRA glb 1.00 6,000.00 6,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,000.00 100.00%
01.01.02 OBRAS PRELIMINARES
01.02 TRANSPORTE DE MATERIALES A OBRA glb 1.00 10,000.00 10,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00%
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS PARAglb 1.00 8,000.00 8,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,000.00 100.00%
01.02.02 IMPLEMENTOS DE SEGURIDAD PARA LOS TRABAJADORES glb 1.00 12,000.00 12,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 12,000.00 100.00%
01.02.03 LIMPIEZA DE TERRENO m2 272.30 1.03 280.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 272.30 280.47 100.00%
02 TRAZO NIVELADO Y REPLANTEO INICIAL m2 272.30 1.83 498.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 272.30 498.31 100.00%
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 69.93 38.73 2,708.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.93 2,708.39 100.00%
02.01.01.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3 136.08 38.73 5,270.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 136.08 5,270.38 100.00%
02.01.01.02 NIVELACION Y APISONADO MANUAL PARA PISOS m2 231.23 2.50 578.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 231.23 578.08 100.00%
02.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 91.95 27.97 2,571.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.95 2,571.84 100.00%
02.01.02.01 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 32.31 197.62 6,385.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.31 6,385.10 100.00%
02.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP/VOLQ 15 m3 140.30 15.86 2,225.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.30 2,225.16 100.00%
02.01.02.03 OBRAS DE CONCRETO SIMPLE
02.01.02.04 SOLADO PARA ZAPATAS m2 101.83 22.74 2,315.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 101.83 2,315.61 100.00%
02.01.02.05 CONCRETO PARA CIMIENTOS CORRIDOS FC=100 KG/CM2 + 30% PG (6" Mm3 24.13 225.96 5,452.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.13 5,452.41 100.00%
02.01.02.06 SOBRECIMIENTO 1:8 + 25% P.M m3 10.83 281.44 3,048.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.83 3,048.00 100.00%
02.01.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 139.19 46.99 6,540.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 139.19 6,540.54 100.00%
02.01.03.01 CONCRETO EN FALSO PISO FC=140 KG/CM2 E=10CM m2 231.23 37.83 8,747.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 231.23 8,747.43 100.00%
02.01.03.02 OBRAS DE CONCRETO ARMADO
02.01.03.03 ZAPATAS
02.01.03.04 ZAPATAS CONCRETO f'c=210 kg/cm2 m3 53.51 435.54 23,305.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.51 23,305.75 100.00%
02.01.03.05 ZAPATAS ACERO fy=4,200 kg/cm2 kg 1,536.34 4.80 7,374.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,536.34 7,374.43 100.00%
02.01.04 VIGA DE CIMENTACION
02.01.04.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 m3 20.09 435.54 8,750.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.09 8,750.00 100.00%
02.01.04.01.01 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION m2 164.77 52.11 8,586.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164.77 8,586.16 100.00%
02.01.04.01.02 ACERO fy=4,200 kg/cm2 PARA VIGAS DE CIMENTACION kg 2,598.56 4.80 12,473.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,598.56 12,473.09 100.00%
02.01.04.02 COLUMNAS Y PLACAS
02.01.04.02.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 40.62 435.54 17,691.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 40.62 17,691.63 100.00%
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 423.73 53.72 22,762.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 423.73 22,762.78 100.00%
02.01.04.02.03 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACAS kg 6,925.84 4.80 33,244.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6,925.84 33,244.03 100.00%
02.01.04.03 VIGAS
02.01.04.03.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 28.84 435.54 12,560.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28.84 12,560.97 100.00%
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 274.68 62.83 17,258.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 274.68 17,258.14 100.00%
02.01.04.03.03 VIGAS ACERO fy=4,200 kg/cm2 kg 3,782.03 4.80 18,153.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,782.03 18,153.74 100.00%
02.01.04.04 LOSA ALIGERADA
02.01.04.04.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 11.60 435.54 5,052.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.60 5,052.26 100.00%
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 132.54 62.83 8,327.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 8,327.49 100.00%
02.01.04.04.03 VIGAS ACERO fy=4,200 kg/cm2 kg 466.17 4.80 2,237.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 466.17 2,237.62 100.00%
02.01.04.05 LOSA ALIGERADA LADRILLO HUECO 15X30X30 und 1,104.46 3.07 3,390.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,104.46 3,390.69 100.00%
02.01.04.05.01 COLUMNETAS

Página 31
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.01.04.05.02 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 5.72 403.68 2,309.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.72 2,309.05 100.00%
02.01.04.05.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 76.32 53.72 4,099.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 76.32 4,099.91 100.00%
02.02 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNETAS kg 923.29 4.80 4,431.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 923.29 4,431.79 100.00%
02.02.01 ESCALERAS
02.02.01.01 CONCRETO COLUMNAS Y PLACAS f'c=210 kg/cm2 m3 2.54 435.54 1,106.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.54 1,106.27 100.00%
02.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS Y PLACAS m2 16.76 53.72 900.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.76 900.35 100.00%
02.02.02.01 ACERO fy=4,200 kg/cm2 GRADO 60 EN COLUMNAS Y PLACAS kg 391.21 4.80 1,877.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 391.21 1,877.81 100.00%
02.02.02.02 CONSTRUCCION DE VEREDAS
02.02.02.03 OBRAS PRELIMINARES
02.02.02.04 LIMPIEZA DE TERRENO m2 182.20 1.05 191.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.20 191.31 100.00%
02.02.02.05 TRAZO NIVELADO Y REPLANTEO INICIAL m2 182.20 1.74 317.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.20 317.03 100.00%
02.02.02.06 MOVIMIENTO DE TIERRAS
02.02.02.07 CORTE DE TERRENO CON MAQUINARIA m3 12.20 5.38 65.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 65.64 100.00%
02.02.02.08 BASE PARA VEREDAS DE 0.15 M m2 182.20 37.92 6,909.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.20 6,909.02 100.00%
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP/VOLQ m3 12.20 15.86 193.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 193.49 100.00%
02.02.03.01 CONCRETO SIMPLE
02.02.03.02 VEREDA CONC. FC=175 KG/CM2 E=4" m2 182.20 46.86 8,537.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.20 8,537.89 100.00%
02.02.04 JUNTA DE DILATACION m 122.00 13.80 1,683.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 122.00 1,683.60 100.00%
02.02.04.01 CURADO CON AGUA EN VEREDA m2 182.20 2.44 444.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.20 444.57 100.00%

COSTO DIRECTO 318,858.24 0.00 0.00 0.00 318,858.24


GASTOS GENERALES 22.00% 70,148.81 0.00 0.00 0.00 70,148.81
UTILIDAD 10.00% 31,885.82 0.00 0.00 0.00 31,885.82
SUB - TOTAL 420,892.87 0.00 0.00 0.00 420,892.87
FACTOR DE RELACION 1.00000 420,892.87 0.00 0.00 0.00 420,892.87

MONTO BRUTO VALORIZADO 420,892.87 0.00 0.00 0.00 420,892.87


SUB-TOTAL 420,892.87 0.00 0.00 0.00 420,892.87

IGV (18%) 18% 0.00 0.00 0.00 75,760.72

VALOR REFERENCIAL 496,653.59 - 0.00% - 0.00% 0.00 0.00% 496,653.59 100.00%

TOTAL DE INVERSION 496,653.59

Página 32
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : ICONSER SAC
PLAZO : 120 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 01 -ARQUITECTURA

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.02 ARQUITECTURA
02.02.01 ALBAÑILERIA
02.02.01.01 MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-ARENA m2 301.38 55.45 16,711.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 301.38 16,711.52 100.00%
02.02.02 REVOQUES
02.02.02.01 TARRAJEO EN INTERIORES C:A-1:4 m2 409.19 26.68 10,917.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 409.19 10,917.19 100.00%
02.02.02.02 TARRAJEO EN EXTERIORES C:A-1:4 m2 219.90 26.68 5,866.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 219.90 5,866.93 100.00%
02.02.02.03 TARRAJEO DE COLUMNAS Y PLACAS C:A-1:4 m2 485.38 28.73 13,944.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 485.38 13,944.97 100.00%
02.02.02.04 VESTIDURA DE ARISTAS EN COLUMNAS Y PLACAS m 697.70 3.75 2,616.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 697.70 2,616.38 100.00%
02.02.02.05 TARRAJEO DE VIGAS C:A-1:4 m2 313.51 31.30 9,812.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 313.51 9,812.86 100.00%
02.02.02.06 VESTIDURA DE ARISTAS EN VIGAS m 581.02 3.75 2,178.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 581.02 2,178.83 100.00%
02.02.02.07 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS C:A (1:4) m 195.39 13.56 2,649.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 195.39 2,649.49 100.00%
02.02.02.08 BRUÑAS DE 1.0 cm m 270.41 9.30 2,514.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.41 2,514.81 100.00%
TARRAJEO DE CIELO RASO - SUPERFICIE CON CEMENTO-ARENA m2 132.54 64.95 8,608.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 8,608.47 100.00%
02.02.03 PISOS Y PAVIMENTOS
02.02.03.01 CONTRAPISO DE 48 mm, MEZCLA 1:5 m2 328.50 36.52 11,996.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 328.50 11,996.82 100.00%
02.02.03.02 PISO DE CERAMICO 45 X 45 CM m2 328.50 56.47 18,550.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 328.50 18,550.40 100.00%
PISO DE CEMENTO PULIDO m2 14.13 31.66 447.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.13 447.36 100.00%
02.02.04 CONTRAZOCALOS
02.02.04.01 CONTRAZOCALO CERAMICO H=0.10 m. m 217.50 19.23 4,182.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 217.50 4,182.53 100.00%
02.02.04.02 CONTRAZOCALO DE CEMENTO PULIDO h=0.20 m m 192.72 16.53 3,185.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 192.72 3,185.66 100.00%
02.02.04.03 ZOCALO DE CERAMICA 20 X 30 CM m2 27.15 92.72 2,517.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.15 2,517.35 100.00%
02.02.05 CARPINTERIA MADERA
02.02.05.01 PUERTA DE CEDRO MACHIMBRADA SEGUN DISEÑO m2 20.72 507.16 10,508.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.72 10,508.36 100.00%
02.02.05.02 PUERTA CONTRAPLACADA SEGUN DISEÑO m2 2.34 357.88 837.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.34 837.44 100.00%
02.02.06 CARPINTERIA METALICA
02.02.06.01 VENTANA C/PERFILES DE ALUMINIO - SISTEMA DIRECTO m2 93.64 195.14 18,272.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 93.64 18,272.91 100.00%
02.02.07 CERRAJERIA
02.02.07.01 CERRADURA DE TRES GOLPES TIPO PESADO pza 8.00 76.93 615.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 615.44 100.00%
02.02.07.02 BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½" und 28.00 9.62 269.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28.00 269.36 100.00%
02.02.08 VIDRIOS, CRISTALES Y SIMILARES
02.02.08.01 SUM. E INST. DE VIDRIO CRUDO SEMIDOBLE p2 1,007.94 12.88 12,982.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,007.94 12,982.27 100.00%
02.02.09 PINTURAS
02.02.09.01 PINTURA LATEX EN EXTERIORES E INTERIORES 2 MANOS m2 626.56 10.45 6,547.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 626.56 6,547.55 100.00%
02.02.09.02 PINTURA EN CONTRAZOCALO m2 54.16 7.90 427.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.16 427.86 100.00%
02.02.09.03 PINTURA EN VIGAS m2 236.02 13.63 3,216.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 236.02 3,216.95 100.00%
02.02.09.04 PINTURA EN COLUMNAS Y PLACAS m2 277.34 13.11 3,635.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 277.34 3,635.93 100.00%
PINTURA EN CIELO RASO m2 132.54 11.22 1,487.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.54 1,487.10 100.00%
02.02.10 CUBIERTA METALICA Y CIELO RASO
02.02.10.01 SUM. E INST. DE CIELO RASO SUSPENDIDO CON BALDOSAS DE SUPE m2 376.22 125.79 47,324.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 376.22 47,324.71 100.00%
02.02.10.02 SUM. E INST. DE CORREAS METALICAS INCL. BASE, SOPORTE, PINTU m 363.50 75.95 27,607.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 363.50 27,607.83 100.00%
02.02.10.03 SUM. E INST. DE COBERTURA TR4 Y CUMBRERA m2 383.74 119.63 45,906.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 383.74 45,906.82 100.00%
AREAS VERDES
LIMPIEZA DE TERRENO m2 759.66 1.05 797.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 797.64 100.00%
TRAZO NIVELADO Y REPLANTEO INICIAL m2 759.66 1.74 1,321.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 1,321.81 100.00%

Página 33
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

MOVIMIENTO DE TIERRAS
CORTE MANUAL DE TERRENO m3 75.97 22.59 1,716.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 75.97 1,716.16 100.00%
PREPARACION DE TIERRA DE CHACRA m2 759.66 6.56 4,983.37 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 4,983.37 100.00%
EXT. Y NIV. DE TIERRA DE CHACRA PARA SEMBRADO DE GRASS m2 759.66 9.35 7,102.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 7,102.82 100.00%
ELIMINACION DE MATERIAL EXCEDENTE CARGUIO C/EQ 125HP/VOL m3 91.16 15.86 1,445.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.16 1,445.80 100.00%
SEMBRADO DE GRASS
SEMBRADO DE GRASS m2 759.66 23.70 18,003.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 759.66 18,003.94 100.00%
VARIOS
ADQUISICION E INSTALACION DE JUEGO RECREATIVOS und 2.00 3,500.00 7,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,000.00 100.00%

COSTO DIRECTO 338,713.62 0.00 0.00 0.00 338,713.62


GASTOS GENERALES 22.00% 74,517.00 0.00 0.00 0.00 74,517.00
UTILIDAD 10.00% 33,871.36 0.00 0.00 0.00 33,871.36
SUB - TOTAL 447,101.97 0.00 0.00 0.00 447,101.97
FACTOR DE RELACION 1.00000 447,101.97 0.00 0.00 0.00 447,101.97

MONTO BRUTO VALORIZADO 447,101.97 0.00 0.00 0.00 447,101.97


SUB-TOTAL 447,101.97 0.00 0.00 0.00 447,101.97

IGV (18%) 18% 0.00 0.00 0.00 80,478.36

VALOR REFERENCIAL 527,580.33 - 0.00% - 0.00% 0.00 0.00% 527,580.33 100.00%

TOTAL DE INVERSION 527,580.33

Página 34
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : ICONSER SAC
PLAZO : 120 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 01 - INSTALACIONES ELECTRICAS

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.03 INSTALACIONES ELECTRICAS


02.03.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 73.00 154.03 11,244.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.00 11,244.19 100.00%
02.03.02 SALIDA TOMACORRIENTE pto 26.00 219.97 5,719.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 5,719.22 100.00%
02.03.03 SALIDA TOMACORRIENTE A PRUEBA DE AGUA pto 3.00 224.97 674.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 674.91 100.00%
02.03.04 SALIDA PARA INTERRUPTOR SIMPLE pto 11.00 110.64 1,217.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,217.04 100.00%
02.03.05 SALIDA PARA INTERRUPTOR TRIPLE pto 4.00 116.04 464.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 464.16 100.00%
02.03.06 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR P/EMPOTRAR 4 und 70.00 214.40 15,008.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.00 15,008.00 100.00%
02.03.07 SUM. E INST. DE ARTEFACTO DE ALUMBRADO INTERIOR CIRCULAR 22W und 4.00 69.40 277.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 277.60 100.00%
02.03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm m 355.18 13.37 4,748.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 355.18 4,748.76 100.00%
02.03.09 ALAMBRE THHN 2.5 mm2 m 589.36 1.83 1,078.53 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 589.36 1,078.53 100.00%
02.03.10 ALAMBRE THHN 4 mm2 m 237.32 2.32 550.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 237.32 550.58 100.00%
02.03.11 TABLERO DE DISTRIBUCION und 2.00 500.18 1,000.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,000.36 100.00%
02.03.12 PRUEBA ELECTRICA glb 2.00 120.00 240.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 240.00 100.00%
02.03.13 POZO DE CONEXION A TIERRA und 2.00 878.41 1,756.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,756.82 100.00%

COSTO DIRECTO 43,980.17 0.00 0.00 0.00 43,980.17


GASTOS GENERALES 22.00% 9,675.64 0.00 0.00 0.00 9,675.64
UTILIDAD 10.00% 4,398.02 0.00 0.00 0.00 4,398.02
SUB - TOTAL 58,053.82 0.00 0.00 0.00 58,053.82
FACTOR DE RELACION 1.00000 58,053.82 0.00 0.00 0.00 58,053.82

MONTO BRUTO VALORIZADO 58,053.82 0.00 0.00 0.00 58,053.82


SUB-TOTAL 58,053.82 0.00 0.00 0.00 58,053.82

IGV (18%) 18% 0.00 0.00 0.00 10,449.69

VALOR REFERENCIAL 68,503.51 - 0.00% - 0.00% 0.00 0.00% 68,503.51 100.00%

TOTAL DE INVERSION 68,503.51

Página 35
OBRA : MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA
ENTIDAD : GOBIERNO REGIONAL DE ICA
SUPERVISIÓN : CONSORCIO SUPERVISION CHINCHA
CONTRATISTA : ICONSER SAC
PLAZO : 120 DIAS CALENDARIOS
MODALIDAD : A SUMA ALZADA

PLANILLA DE VALORIZACION N° 01 - INSTALACIONES SANITARIAS

PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

02.04 INSTALACIONES SANITARIAS


02.04.01 APARATOS Y ACCESORIOS SANITARIOS
02.04.01.01 INODORO TANQUE BAJO pza 2.00 371.99 743.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 743.98 100.00%
02.04.01.02 LAVATORIO DE LOZA BLANCA und 2.00 202.65 405.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 405.30 100.00%
02.04.01.03 CAÑO DE BRONCE - LLAVE DE 1/2" und 2.00 39.77 79.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 79.54 100.00%
02.04.02 SISTEMA DE DESAGUE
02.04.02.01 SALIDA DE DESAGUE PVC D=2" pto 2.00 96.37 192.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 192.74 100.00%
02.04.02.02 SALIDA DE DESAGUE PVC D=4" pto 2.00 150.79 301.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 301.58 100.00%
02.04.02.03 SALIDA VENTILACION DE 2" pto 2.00 60.47 120.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 120.94 100.00%
02.04.02.04 REGISTRO DE BRONCE 4" und 1.00 312.37 312.37 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 312.37 100.00%
02.04.02.05 SUMIDERO DE 2" pza 1.00 79.38 79.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 79.38 100.00%
02.04.02.06 TUBERIA PVC SAL P/DESAGUE D=4" m 10.00 35.74 357.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 357.40 100.00%
02.04.02.07 YEE PVC SAL 4"X2" und 3.00 63.06 189.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 189.18 100.00%
02.04.02.08 CODO PVC SAL P/DESAGUE D=2" und 2.00 26.84 53.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 53.68 100.00%
02.04.02.09 EXCAVACION MANUAL PARA TUBERIA m 10.00 14.91 149.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 149.10 100.00%
02.04.02.10 REFINE NIVELACION Y COMPACTACION DE ZANJA m 10.00 3.87 38.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 38.70 100.00%
02.04.02.11 CAMA DE APOYO m 10.00 9.36 93.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 93.60 100.00%
02.04.02.12 RELLENO COMPACTADO DE ZANJAS m 10.00 12.20 122.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 122.00 100.00%
02.04.02.13 CAJA DE REGISTRO CON REJILLA METALICA und 1.00 136.46 136.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 136.46 100.00%
02.04.03 SISTEMA DE AGUA FRIA
02.04.03.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" pto 4.00 73.55 294.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 294.20 100.00%
02.04.03.02 TUBERIA PVC SAP CLASE 10-1/2" m 8.05 17.52 141.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.05 141.04 100.00%
02.04.03.03 CODO PVC 1/2" und 1.00 9.89 9.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9.89 100.00%
02.04.03.04 TEE PVC 1/2" und 3.00 11.09 33.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 33.27 100.00%
02.04.03.05 EXCAVACION MANUAL PARA TUBERIA m 7.05 14.91 105.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 105.12 100.00%
02.04.03.06 REFINE NIVELACION Y COMPACTACION DE ZANJA m 7.05 3.87 27.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 27.28 100.00%
02.04.03.07 CAMA DE APOYO m 7.05 9.36 65.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 65.99 100.00%
02.04.03.08 RELLENO COMPACTADO DE ZANJAS m 7.05 12.20 86.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.05 86.01 100.00%
02.04.03.09 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1/2" und 1.00 130.40 130.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 130.40 100.00%
02.04.03.10 CAJA PARA VALVULAS und 1.00 136.46 136.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 136.46 100.00%
02.04.04 SISTEMA DE AGUA PLUVIAL
02.04.04.01 CANALETA PARA AGUA FLUVIAL DE 4" m 73.10 61.85 4,521.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.10 4,521.24 100.00%
02.04.04.02 TUBERIA PVC SAL D=4" m 19.00 47.54 903.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.00 903.26 100.00%
02.04.04.03 CODO PVC SAL D=4" und 4.00 37.65 150.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 150.60 100.00%

COSTO DIRECTO 9,980.70 0.00 0.00 0.00 9,980.70


GASTOS GENERALES 22.00% 2,195.75 0.00 0.00 0.00 2,195.75
UTILIDAD 10.00% 998.07 0.00 0.00 0.00 998.07
SUB - TOTAL 13,174.52 0.00 0.00 0.00 13,174.52
FACTOR DE RELACION 1.00000 13,174.52 0.00 0.00 0.00 13,174.52

MONTO BRUTO VALORIZADO 13,174.52 0.00 0.00 0.00 13,174.52


SUB-TOTAL 13,174.52 0.00 0.00 0.00 13,174.52

Página 36
PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO ACTUAL
ITEM DESCRIPCION DE LA PARTIDA
UNIDAD METRADO P. UNIT MONTO S/. METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. % METRADO MONTO S/. %

IGV (18%) 18% 0.00 0.00 0.00 2,371.41

VALOR REFERENCIAL 15,545.94 - 0.00% - 0.00% 0.00 0.00% 15,545.94 100.00%

TOTAL DE INVERSION 15,545.94

Página 37
38

FORMULA POLINOMICA ESTRUCTURAS -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018

Io Ir FEBRERO-
MONOMIO SIMB. IND. DESCRIPCION COEF. % Kr
AGOSTO-18 2019
1 MO 47 MANO DE OBRA 0.293 100.00% 602.11 -

2 CE 21 CEMENTO PORTLAND TIPO I 0.126 100.00% 423.68 -

3 AC 03 ACERO DE CONSTRUCCION CORRUGADO 0.187 100.00% 525.48 -

4 AG 05 AGREGADO GRUESO 0.144 100.00% 216.30 -

5 M 43 MADERA NACIONAL 0.121 100.00% 677.88 -

6 MQ 100.00% 302.20 -
49 MAQUINARIA Y EQUIPO IMPORTADO 0.129

K= 0.000
39

FORMULA POLINOMICA ARQUITECTURA -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018

Io Ir FEBRERO-
MONOMIO SIMB. IND. DESCRIPCION COEF. % Kr
AGOSTO-18 2019
1 MO 47 MANO DE OBRA 0.551 100.00% 602.11 -

2 M 43 MADERA NACIONAL 0.051 100.00% 677.88 -

3 AC 24 CERAMICA ESMALTADA 0.083 100.00% 243.29 -

4 PAC 56 PLANCHA DE ACERO LAC 0.115 100.00% 542.19 -

5 CE 21 CEMENTO PORTLAND TIPO I 0.125 100.00% 423.68 -

6 D 100.00% 483.02 -
30 DÓLAR 0.075

K= 0.000
40

FORMULA POLINOMICA INSTALACIONES ELECTRICAS -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018

Io Ir FEBRERO-
MONOMIO SIMB. IND. DESCRIPCION COEF. % Kr
AGOSTO-18 2019
1 MO 47 MANO DE OBRA 0.477 100.00% 602.11 -

2 AAI 12 ARTEFACTO DE ALUMBRADO INTERIOR 0.324 100.00% 320.72 -

3 CE 21 CEMENTO PORTLAND TIPO I 0.056 100.00% 423.68 -

4 PVC 72 TUBERIA DE PVC 0.060 100.00% 435.02 -

5 ATW 07 ALAMBRE Y CABLE TIPO TW 0.083 100.00% 672.83 -

K= 0.000
41

FORMULA POLINOMICA INSTALACIONES ELECTRICAS -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018
42

FORMULA POLINOMICA INSTALACIONES SANITARIAS -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018

Io Ir FEBRERO-
MONOMIO SIMB. IND. DESCRIPCION COEF. % Kr
AGOSTO-18 2019
1 MO 47 MANO DE OBRA 0.401 100.00% 602.11 -

2 CE 21 CEMENTO PORTLAND TIPO I 0.087 100.00% 423.68 -

3 PVC 72 TUBERIA DE PVC 0.292 100.00% 435.02 -

4 TFE 71 TUBERIA DE FIERRO 0.133 100.00% 652.95 -

5 SAN 10 APARATO SANITARIO CON GRIFERIA 0.087 100.00% 414.57 -

K= 0.000
43

FORMULA POLINOMICA INSTALACIONES SANITARIAS -CALCULO DEL FACTOR DE REAJUSTE

Obra: MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N°


22273 Y DE LA I.E. N° 320 – CHAVIN, DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA –
DEPARTAMENTO DE ICA
Propietario: GOBIERNO REGIONAL DE ICA-NEXA
Fecha: PRECIOS VIGENTES AGOSTO 2018
44

CALCULO DE REAJUSTES - RESUMEN

Obra:
MEJORAMIENTO, AMPLIACION DE LA CALIDAD DEL SERVICIO EDUCATIVO INTEGRAL DE LA I.E. N° 22273 Y DE LA I.E. N° 320 – CHAVIN,
DISTRITO DE CHAVIN – PROVINCIA DE CHINCHA – DEPARTAMENTO DE ICA

Propietario: GOBIERNO REGIONAL DE ICA-NEXA


Fecha: PRECIOS VIGENTES ENERO 2019

PROGRAMADO
VAL.
MES ESPECIALIDAD REAJUSTE REAJUSTE
N° VALORIZACION K
V x ( k-1 ) ACUMULADO

ESTRUCTURAS - - - -
ARQUITECTURA - - - -
SET. 2019 ELECTRICAS 01 - - - -
SANITARIAS - - - -
TOTAL - -
- -
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XV) VOL 3b - PABELLON DE 11 AULAS + SSHH (B2b) - INST. SANITARIAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 RED DE AGUA FRIA 12,413.98 METRADO S/. % METRADOS/. % METRADOS/. % METRADOS/. %
01.01 TRABAJOS PRELIMINARES 144.33
01.01.01 TRAZO Y REPLANTEO DE REDES DE AGUA m 51.00 2.83 144.33 51.00 144.33 100.00% - 0.00% 51.00 144.33 100.00% - - 0.00%
01.02 MOVIMIENTO DE TIERRAS 3,231.13
01.02.01 EXCAVACION DE ZANJAS MANUAL TN, HASTA 1.0 M m 51.00 28.58 1,457.58 51.00 1,457.58 100.00% - 0.00% 51.00 1,457.58 100.00% - - 0.00%
01.02.02 REFINE Y NIVELACION ZANJA T.N. m 51.00 1.61 82.11 51.00 82.11 100.00% - 0.00% 51.00 82.11 100.00% - - 0.00%
01.02.03 PREPARACION DE CAMA DE APOYO CON MATERIAL PROPIO ZARANDEADO E=10CM. m 51.00 1.98 100.98 51.00 100.98 100.00% - 0.00% 51.00 100.98 100.00% - - 0.00%
01.02.04 RELLENO Y COMPACTADO DE ZANJA, HASTA 1.00 m CON MATERIAL PROPIO m 51.00 29.51 1,505.01 51.00 1,505.01 100.00% - 0.00% 51.00 1,505.01 100.00% -
01.02.05 ACARREO MATERIAL EXCEDENTE HASTA UN DISTANCIA PROMEDIO DE 30 M m3 2.99 28.58 85.45 2.99 85.45 100.00% - 0.00% 2.99 85.45 100.00% -
01.03 TUBERIAS Y ACCESORIOS 278.49
01.03.01 TUBERIA PVC SAP DE 3/4" C- 10 C/R m 1.00 5.15 5.15 1.00 5.15 100.00% - 0.00% 1.00 5.15 100.00% - - 0.00%
01.03.02 TUBERIA PVC SAP DE 1/2" C- 10 C/R m 50.00 4.10 205.00 50.00 205.00 100.00% - 0.00% 50.00 205.00 100.00% - - 0.00%
01.03.03 PRUEBA HIDRAULICA Y DESINFECCIÓN m 51.00 1.34 68.34 51.00 68.34 100.00% - 0.00% 51.00 68.34 100.00% - - 0.00%
01.04 VALVULAS 769.18
01.04.01 VALVULA COMPUERTA DE 3/4". und 2.00 91.92 183.84 0.00 0.00 0.00% - 0.00% - - 0.00% 2.00 183.84 100.00%
01.04.02 VALVULA COMPUERTA DE 1/2" und 7.00 83.62 585.34 0.00 0.00 0.00% - 0.00% - - 0.00% 7.00 585.34 100.00%
01.05 SALIDAS DE AGUA FRIA 1,657.22
01.05.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - INODORO pto 6.00 69.27 415.62 6.00 415.62 100.00% - 0.00% 6.00 415.62 100.00% - - 0.00%
01.05.02 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - LAVATORIO pto 2.00 69.27 138.54 2.00 138.54 100.00% - 0.00% 2.00 138.54 100.00% - - 0.00%
01.05.03 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - LAVADERO CORRIDO pto 1.00 68.28 68.28 1.00 68.28 100.00% - 0.00% 1.00 68.28 100.00% - - 0.00%
01.05.04 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - URINARIO CORRIDO pto 7.00 107.78 754.46 7.00 754.46 100.00% - 0.00% 7.00 754.46 100.00% - - 0.00%
01.05.05 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" - DUCHA pto 4.00 70.08 280.32 4.00 280.32 100.00% - 0.00% 4.00 280.32 100.00% - - 0.00%
01.06 ACCESORIOS VARIOS 964.28
01.06.01 REDUCCION PVC SAP 3/4" - 1/2" und 2.00 21.77 43.54 2.00 43.54 100.00% - 0.00% 2.00 43.54 100.00% - - 0.00%
01.06.02 CODO PVC U.R. SAP 1/2"X90° und 19.00 14.65 278.35 19.00 278.35 100.00% - 0.00% 19.00 278.35 100.00% - - 0.00%
01.06.03 TEE PVC U.R. SAP 1/2" und 19.00 33.81 642.39 19.00 642.39 100.00% - 0.00% 19.00 642.39 100.00% - - 0.00%
01.07 SUMINISTRO E INSTALACION DE APARATOS Y ACCESORIOS SANITARIOS 5,369.35
01.07.01 INODORO TIPO SIFON JET COLOR BLANCO (SIN COLOCACION) pza 7.00 215.05 1,505.35 0.00 0.00 0.00% - 0.00% - - 0.00% 7.00 1,505.35 100.00%
01.07.02 LAVATORIO DE LOSA TIPO OVALIN BLANCO COMERCIAL (SIN COLOCACION pza 6.00 287.00 1,722.00 0.00 0.00 0.00% - 0.00% - - 0.00% 6.00 1,722.00 100.00%
01.07.03 DUCHA CROMADA 1 LLAVE INCLUYE ACCESORIOS und 4.00 175.12 700.48 0.00 0.00 0.00% - 0.00% - - 0.00% 4.00 700.48 100.00%
01.07.04 CAÑO DE BRONCE STANDARD - LLAVE DE 1/2" und 2.00 55.00 110.00 0.00 0.00 0.00% - 0.00% - - 0.00% 2.00 110.00 100.00%
01.01.07.07 COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS pza 19.00 70.08 1,331.52 0.00 0.00 0.00% - 0.00% - - 0.00% 19.00 1,331.52 100.00%
.02 RED DE DESAGUES 12,938.85
02.01 TRABAJOS PRELIMINARES 183.95
02.01.01 TRAZO Y REPLANTEO RED DE DESAGUES m 65.00 2.83 183.95 65.00 183.95 100.00% - 0.00% 65.00 183.95 100.00% - - 0.00%
02.02 MOVIMIENTO DE TIERRAS 5,511.69
02.02.01 EXCAVACION DE ZANJAS MANUAL TN Ø 2"-6", HASTA 1.0 M m 65.00 50.02 3,251.30 65.00 3,251.30 100.00% - 0.00% 65.00 3,251.30 100.00% - - 0.00%
02.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 2"-6" m 65.00 1.61 104.65 65.00 104.65 100.00% - 0.00% 65.00 104.65 100.00% - - 0.00%
02.02.03 PREPARACION DE CAMA DE APOYO CON MATERIAL PROPIO ZARANDEADO E=10CM. m 65.00 1.98 128.70 65.00 128.70 100.00% - 0.00% 65.00 128.70 100.00% - - 0.00%
02.02.04 RELLENO Y COMPACTADO DE ZANJA, HASTA 1.00 m CON MATERIAL PROPIO m 65.00 29.51 1,918.15 65.00 1,918.15 100.00% - 0.00% 65.00 1,918.15 100.00% - - 0.00%
02.02.05 ACARREO MATERIAL EXCEDENTE HASTA UN DISTANCIA PROMEDIO DE 30 M m3 3.81 28.58 108.89 3.81 108.89 100.00% - 0.00% 3.81 108.89 100.00% - 0.00 0.00%
02.03 TUBERIAS 876.11
02.03.01 TUBERIA PVC SAL Ø2" m 42.50 10.69 454.33 42.50 454.33 100.00% - 0.00% 42.50 454.33 100.00% - 0.00 0.00%
02.03.02 TUBERIA PVC SAL Ø 4" m 22.50 9.79 220.28 22.50 220.28 100.00% - 0.00% 22.50 220.28 100.00% - 0.01 0.00%
02.03.03 PRUEBA HIDRAULICA+ESCORRENTIA DE TUB. P/DESAGUE m 130.00 1.55 201.50 130.00 201.50 100.00% - 0.00% 130.00 201.50 100.00% - - 0.00%
02.04 SALIDAS DE DESAGUES 5,302.76
02.04.01 SALIDA DE DESAGUE TUB PVC 4" - INODORO pto 7.00 92.73 649.11 7.00 649.11 100.00% - 0.00% 7.00 649.11 100.00% - - 0.00%
02.04.02 SALIDA DE DESAGUE TUB PVC 2" - LAVATORIO pto 6.00 58.85 353.10 6.00 353.10 100.00% - 0.00% 6.00 353.10 100.00% - - 0.00%
02.04.03 SALIDA DE DESAGUE TUB PVC 2" - LAVADERO CORRIDO pto 2.00 58.85 117.70 2.00 117.70 100.00% - 0.00% 2.00 117.70 100.00% - - 0.00%
02.04.04 SALIDA DE DESAGUE TUB PVC 2" - URINARIO CORRIDO pto 1.00 66.85 66.85 1.00 66.85 100.00% - 0.00% 1.00 66.85 100.00% - - 0.00%
02.04.05 SALIDA DE DESAGUE TUB PVC 2" - DUCHA pto 4.00 81.85 327.40 4.00 327.40 100.00% - 0.00% 4.00 327.40 100.00% - - 0.00%
02.04.06 SALIDA DE TUBERIA DE VENTILACION PVC 2 pto 25.92 115.63 2,997.13 25.92 2,997.13 100.00% - 0.00% 25.92 2,997.13 100.00% - 0.00 0.00%
02.04.07 REGISTRO DE BRONCE ROSCADO DE 2" pto 2.00 53.43 106.86 2.00 106.86 100.00% - 0.00% 2.00 106.86 100.00% - - 0.00%
02.04.08 REGISTRO DE BRONCE ROSCADO DE 4" pto 5.00 65.93 329.65 5.00 329.65 100.00% - 0.00% 5.00 329.65 100.00% - - 0.00%
02.04.09 SUMIDERO DE BRONCE 2" pto 6.00 59.16 354.96 6.00 354.96 100.00% - 0.00% 6.00 354.96 100.00% - - 0.00%
02.05 ACCESORIOS VARIOS 1,064.34
02.05.01 YEE DE 4"X4" pza 7.00 26.55 185.85 7.00 185.85 100.00% - 0.00% 7.00 185.85 100.00% - - 0.00%
02.05.02 YEE DE 4"X2" pza 5.00 28.05 140.25 5.00 140.25 100.00% - 0.00% 5.00 140.25 100.00% - - 0.00%
02.05.03 YEE DE 2"X2" pza 17.00 14.22 241.74 17.00 241.74 100.00% - 0.00% 17.00 241.74 100.00% - - 0.00%
02.05.04 TEE PVC DE 4"* 4" und 2.00 38.72 77.44 2.00 77.44 100.00% - 0.00% 2.00 77.44 100.00% - - 0.00%
02.05.05 TEE PVC DE 4"* 2" und 9.00 35.72 321.48 9.00 321.48 100.00% - 0.00% 9.00 321.48 100.00% - - 0.00%
02.05.06 CODO DE 90° "X2" pza 5.00 12.94 64.70 5.00 64.70 100.00% - 0.00% 5.00 64.70 100.00% - - 0.00%
02.05.07 CODO DE 45°X2" pza 2.00 16.44 32.88 2.00 32.88 100.00% - 0.00% 2.00 32.88 100.00% - - 0.00%
03 SISTEMA DE AGUA DE LLUVIA 7,666.85
03.01 TUBERIA PVC-SAP 4" DE DESCARGA PLUVIAL DE TECHO m 90.14 72.70 6,553.18 45.00 3,271.50 49.92% - 0.00% 45.00 3,271.50 49.92% 45.14 3,281.68 50.08%
03.02 CODO PVC-SAP 4" * 90 und 16.00 24.22 387.52 16.00 387.52 100.00% - 0.00% 16.00 387.52 100.00% - - 0.00%
03.03 CAJA DE REGISTRO DE DESAGUE 12" X 24" C/TAPA DE CONCRETO pza 3.00 242.05 726.15 0.00 0.00 0.00% - - - - 0.00% 3.00 726.15 100.00%

33,019.68 22,873.31 69.27% 0.00 0.00% 22,873.31 69.27% 10,146.37 30.73%


VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXI) VOL 5 - TALLER 1: ELECTRICIDAD Y ELECTRONICA (B4) - ESTRUCTURAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 2,486.76 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 LIMPIEZA DE TERRENO MANUAL m2 469.20 1.12 525.50 469.20 525.50 100.00% 0.00 0.00% 469.20 525.50 100.00% 0.00 0.00 0.00%
01.02 TRAZO, NIVELES Y REPLANTEO INICIAL m2 469.20 4.18 1,961.26 469.20 1,961.26 100.00% 0.00 0.00% 469.20 1,961.26 100.00% 0.00 0.00 0.00%
02 MOVIMIENTO DE TIERRAS 23,133.44
02.01 NIVELACION DE TERRENO M2 469.20 2.49 1,168.31 469.20 1,168.31 100.00% 0.00 0.00% 469.20 1,168.31 100.00% 0.00 0.00 0.00%
02.02 EXCAVACION DE ZANJAS m3 277.39 33.34 9,248.18 277.39 9,248.18 100.00% 0.00 0.00% 277.39 9,248.18 100.00% 0.00 0.00 0.00%
02.03 RELLENO Y COMPACTADO C/ MATERIAL PROPIO m3 190.67 23.67 4,513.16 190.67 4,513.16 100.00% 0.00 0.00% 190.67 4,513.16 100.00% 0.00 0.00 0.00%
02.04 ACARREO INTERNO MAT. PROCED. DE EXCAVACIONES Dprom= m3 169.94 17.00 2,888.98 335.09 5,696.45 197.18% 0.00 0.00% 335.09 5,696.45 197.18% -165.15 -2,807.47 -97.18%
02.05 ELIMINACION MATERIAL EXCEDENTE CON MAQUINARIA VOLQUm3 169.94 7.91 1,344.23 169.94 1,344.23 100.00% 0.00 0.00% 169.94 1,344.23 100.00% 0.00 0.00 0.00%
02.06 NIVELACION Y APISONADO PARA FALSO PISO O PISO m2 399.39 2.18 870.67 399.39 870.67 100.00% 0.00 0.00% 399.39 870.67 100.00% 0.00 0.00 0.00%
02.07 RELLENO CON AFIRMADO DE e=4" (100% COMPACTACION) m3 40.58 76.39 3,099.91 40.58 3,099.91 100.00% 0.00 0.00% 40.58 3,099.91 100.00% 0.00 0.00 0.00%
03 OBRAS DE CONCRETO SIMPLE 36,975.49
03.01 CONCRETO EN FALSA ZAPATAS F'C= 100 KG/CM2 m3 56.97 257.89 14,691.99 62.89 16,218.70 110.39% 0.00 0.00% 62.89 16,218.70 110.39% -5.92 -1,526.71 -10.39%
03.02 CIMIENTO CORRIDO F'c=140 kg/cm2 m3 9.38 303.68 2,848.52 9.38 2,848.52 100.00% 0.00 0.00% 9.38 2,848.52 100.00% 0.00 0.00 0.00%
03.03 CONCRETO EN SOBRECIMIENTO F'C= 175 KG/CM2 m3 3.75 411.54 1,543.28 3.75 1,543.28 100.00% 0.00 0.00% 3.75 1,543.28 100.00% 0.00 0.00 0.00%
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 50.13 31.61 1,584.61 50.13 1,584.61 100.00% 0.00 0.00% 50.13 1,584.61 100.00% 0.00 0.00 0.00%
03.05 FALSO PISO e= 4" (10CM.) 1:6 C:H m2 399.39 40.83 16,307.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 399.39 16,307.09 100.00%
04 OBRAS DE CONCRETO ARMADO 192,998.43
04.01 ZAPATAS 31,979.03
04.01.01 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 65.80 349.47 22,995.13 65.80 22,995.13 100.00% 0.00 0.00% 65.80 22,995.13 100.00% 0.00 0.00 0.00%
04.01.02 ZAPATAS, ACERO FY=4200KG/CM2 kg 1,860.02 4.83 8,983.90 1,860.02 8,983.90 100.00% 0.00 0.00% 1,860.02 8,983.90 100.00% 0.00 0.00 0.00%
04.02 VIGAS DE CIMENTACION 9,867.55
04.02.01 VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 6.27 371.88 2,331.69 6.27 2,331.69 100.00% 0.00 0.00% 6.27 2,331.69 100.00% 0.00 0.00 0.00%
04.02.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 60.25 54.27 3,269.77 60.25 3,269.77 100.00% 0.00 0.00% 60.25 3,269.77 100.00% 0.00 0.00 0.00%
04.02.03 VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2. kg 828.88 4.96 4,111.24 828.88 4,111.24 100.00% 0.00 0.00% 828.88 4,111.24 100.00% 0.00 0.00 0.00%
04.02.04 VIGAS DE CIMENTACION, BASE CON POLIESTILENO EXPANDIDO m2 9.19 16.85 154.85 9.19 154.85 100.00% 0.00 0.00% 9.19 154.85 100.00% 0.00 0.00 0.00%
04.03 SOBRECIMIENTOS REFORZADOS 13,392.28
04.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO F'C= 175 KG/CM2 m3 12.14 401.74 4,877.12 12.14 4,877.12 100.00% 0.00 0.00% 12.14 4,877.12 100.00% 0.00 0.00 0.00%
04.03.02 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 140.24 31.61 4,432.99 140.24 4,432.99 100.00% 0.00 0.00% 140.24 4,432.99 100.00% 0.00 0.00 0.00%
04.03.03 SOBRECIMIENTO, ACERO FY=4200 KG/CM2 . kg 779.04 5.24 4,082.17 779.04 4,082.17 100.00% 0.00 0.00% 779.04 4,082.17 100.00% 0.00 0.00 0.00%
04.04 COLUMNETAS 8,449.56
04.04.01 COLUMNETAS, CONCRETO F'C= 175 KG/CM2 m3 4.33 381.44 1,651.64 4.33 1,651.64 100.00% 0.00 0.00% 4.33 1,651.64 100.00% 0.00 0.00 0.00%
04.04.02 COLUMNETAS, ENCOFRADO Y DESENCOFRADO m2 42.41 46.14 1,956.80 42.41 1,956.80 100.00% 0.00 0.00% 42.41 1,956.80 100.00% 0.00 0.00 0.00%
04.04.03 COLUMNETAS, ACERO FY=4200 KG/CM2 kg 1,014.91 4.77 4,841.12 1,014.91 4,841.12 100.00% 0.00 0.00% 1,014.91 4,841.12 100.00% 0.00 0.00 0.00%
04.05 COLUMNAS 73,972.99
04.05.01 COLUMNAS, CONCRETO F'C= 210 KG/CM2 m3 41.00 507.07 20,789.87 41.00 20,789.87 100.00% 0.00 0.00% 41.00 20,789.87 100.00% 0.00 0.00 0.00%
04.05.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 416.20 56.37 23,461.19 416.20 23,461.19 100.00% 0.00 0.00% 416.20 23,461.19 100.00% 0.00 0.00 0.00%
04.05.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 5,885.53 5.05 29,721.93 5,885.53 29,721.93 100.00% 0.00 0.00% 5,885.53 29,721.93 100.00% 0.00 0.00 0.00%
04.06 VIGUETAS DE ARRIOSTRE 2,797.25
04.06.01 VIGUETAS DE ARRIOSTRE, CONCRETO F'c= 175KG/CM2 m3 1.80 329.85 593.73 1.80 593.73 100.00% 0.00 0.00% 1.80 593.73 100.00% 0.00 0.00 0.00%
04.06.02 VIGUETAS DE ARRIOSTRE, ENCOFRADO Y DESENCOFRADO m2 23.47 53.91 1,265.27 23.47 1,265.27 100.00% 0.00 0.00% 23.47 1,265.27 100.00% 0.00 0.00 0.00%
04.06.03 VIGA DE ARRIOSTRE, ACERO FY=4200 KG/CM2. kg 191.48 4.90 938.25 191.48 938.25 100.00% 0.00 0.00% 191.48 938.25 100.00% 0.00 0.00 0.00%
04.07 VIGAS 23,310.95
04.07.01 VIGAS, CONCRETO F'C=210 KG/CM2 m3 15.91 391.02 6,221.13 15.91 6,221.13 100.00% 0.00 0.00% 15.91 6,221.13 100.00% 0.00 0.00 0.00%
04.07.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 155.95 59.62 9,297.74 155.95 9,297.74 100.00% 0.00 0.00% 155.95 9,297.74 100.00% 0.00 0.00 0.00%
04.07.03 VIGAS, ACERO FY=4200 KG/CM2. kg 1,590.22 4.90 7,792.08 1,590.22 7,792.08 100.00% 0.00 0.00% 1,590.22 7,792.08 100.00% 0.00 0.00 0.00%
04.08 CANALETA DE CONCRETO EN TECHO 29,228.82
04.08.01 CANALETA DE CONCRETO EN TECHO, CONCRETO F'C=210 KG/CMm3 12.60 412.67 5,199.64 12.60 5,199.64 100.00% 0.00 0.00% 12.60 5,199.64 100.00% 0.00 0.00 0.00%
04.08.02 CANALETA DE CONCRETO EN TECHO, ENCOFRADO Y DESENCOFRm2 267.12 72.87 19,465.03 267.12 19,465.03 100.00% 0.00 0.00% 267.12 19,465.03 100.00% 0.00 0.00 0.00%
04.08.03 CANALETA DE CONCRETO EN TECHO, ACERO FY=4200 KG/CM2. kg 931.46 4.90 4,564.15 931.46 4,564.15 100.00% 0.00 0.00% 931.46 4,564.15 100.00% 0.00 0.00 0.00%
05 ESTRUCTURA METALICA Y COBERTURA 110,699.04
05.01 TIJERAL METÁLICO DE SECCIÓN RECTANGULAR T-1 und 5.00 6,670.74 33,353.70 5.00 33,353.70 100.00% 0.00 0.00% 5.00 33,353.70 100.00% 0.00 0.00 0.00%
05.02 SOPORTES METALICOS PARA CERCHAS und 10.00 580.16 5,801.60 10.00 5,801.60 100.00% 0.00 0.00% 10.00 5,801.60 100.00% 0.00 0.00 0.00%
05.03 VIGUETA TIPO "Z" DE 100mm x 51mm x 4.5mmm x 6.00m m 453.60 80.82 36,659.95 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 453.60 36,659.95 100.00%
05.04 TENSORES METALICOS DE ACERO LISO DE 3/8" m 100.80 28.32 2,854.66 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 100.80 2,854.66 100.00%
05.05 TEMPLADORES METALICOS DE ACERO LISO DE 1/2" (ENTRE TIJERm 170.56 23.45 3,999.63 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 170.56 3,999.63 100.00%
05.06 COBERTURA CON PLANCHA METALICA TIPO TECNOTECHO MOD.m2 359.86 77.89 28,029.50 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 359.86 28,029.50 100.00%
06 MUROS Y TABIQUES DE ALBAÑILERIA 5,153.01
06.01 MURO DE SOGA CON LADRILLO DE ARCILLA 9x13x24 CM (CON ALm2 44.63 91.18 4,069.36 44.63 4,069.36 100.00% 0.00 0.00% 44.63 4,069.36 100.00% 0.00 0.00 0.00%
06.02 MURO DE CABEZA CON LADRILLO DE ARCILLA 9X13X24 (CON ALAm2 7.32 148.04 1,083.65 7.32 1,083.65 100.00% 0.00 0.00% 7.32 1,083.65 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 371,446.17 287,929.50 66.70% 0.00 0.00% 287,929.50 77.52% 83,516.67 22.48%
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

0801064 +MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA "CARLOS FERMÍN FITZCARRALD"


Subpresupuesto 027 (XXVI) V OL 6 - TALLER 2: MECÁNICA DE PRODUCCIÓN ( B5) - ARQUITECTURA
Item Descripciòn Und Metrado P.Unit P.Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 REVOQUES Y ENLUCIDOS 26,011.68 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 TARRAJEO EXTERIOR EN MUROS C:A 1:5 e=1.50 cm. m2 108.44 21.18 2,296.76 108.44 2,296.76 100.00% - 0.00% 108.44 2,296.76 100.00% -
01.02 TARRAJEO INTERIOR EN MUROS C:A 1:5 e=1.50 cm. m2 261.78 18.14 4,748.69 261.78 4,748.69 100.00% - 0.00% 261.78 4,748.69 100.00% -
01.03 TARRAJEO EN COLUMNAS - PLACAS C:A 1:5 e=1.50 cm m2 321.03 26.37 8,465.56 321.03 8,465.56 100.00% - 0.00% 321.03 8,465.56 100.00% -
01.04 TARRAJEO EN VIGAS C:A 1/5, e=1.50 cm m2 116.31 32.75 3,809.15 116.31 3,809.15 100.00% - 0.00% 116.31 3,809.15 100.00% -
01.05 TARRAJEO EN TAPASOL Y CANALETA C:A 1:5 e=1.50 cm. m2 148.68 29.52 4,389.03 148.68 4,389.03 100.00% - 0.00% 148.68 4,389.03 100.00% -
01.06 VESTIDURA DE DERRAMES a=0.15 C:A 1:5 e=1.50cm. m 29.20 12.28 358.58 29.20 358.58 100.00% - 0.00% 29.20 358.58 100.00% -
01.07 BRUÑAS VERTICALES DE 1" m 153.60 6.71 1,030.66 153.60 1,030.66 100.00% - 0.00% 153.60 1,030.66 100.00% -
01.08 JUNTAS DE DILATACIÓN VERTICAL DE 25 CM CON TEKNOPm 35.20 9.47 333.34 35.20 333.34 100.00% - 0.00% 35.20 333.34 100.00% -
01.09 JUNTA DE DILATACION VERTICAL DE 15 C.M. CON TECNORm 19.80 7.34 145.33 19.80 145.33 100.00% - 0.00% 19.80 145.33 100.00% -
01.10 TARRAJEO PRIMARIO RAYADO CON CEMENTO-ARENA PARm2 4.06 17.52 71.13 4.06 71.13 100.00% - 0.00% 4.06 71.13 100.00% -
01.11 REVESTIMIENTO DE MUEBLE DE CONCRETO CON CERÁMIm2 4.38 82.98 363.45 4.38 363.45 100.00% - 0.00% 4.38 363.45 100.00% -
02 PISOS Y PAVIMENTOS 15,478.97 - 0.00%
02.01 PISOS INTERIORES DE CONCRETO - ACABADOS C:A 1:4 DE m2 322.94 27.36 8,835.64 - - 0.00% - 0.00% - - 0.00% 322.94 8,835.64 100.00%
02.02 VEREDA DE CONCRETO F'C=175 KG/CM2 h=0.10m, ACABAm2 91.25 57.62 5,257.83 - - 0.00% - 0.00% - - 0.00% 91.25 5,257.83 100.00%
02.03 JUNTAS DE DILATACIÓN HORIZONTAL + SELLO ASFALTICOm 101.80 13.61 1,385.50 - - 0.00% - 0.00% - - 0.00% 101.80 1,385.50 100.00%
03 ZOCALOS Y CONTRAZOCALOS 2,589.38
03.01 CONTRAZOCALO CEMENTO PULIDO S/COLOREAR H=40cmm 90.60 13.95 1,263.87 - - 0.00% - 0.00% - - 0.00% 90.60 1,263.87 100.00%
03.02 CONTRAZOCALO CEMENTO PULIDO S/COLOREAR H=10 cmm 122.55 7.76 950.99 - - 0.00% - 0.00% - - 0.00% 122.55 950.99 100.00%
03.03 ZOCALO DE CERÁMICO DE 20X30 COLOR CLARO m2 6.03 62.11 374.52 - - 0.00% - 0.00% - - 0.00% 6.03 374.52 100.00%
04 CARPINTERIA DE MADERA 1,403.50
04.01 PUERTA DE MADERA QUINILLA MACHIHEMBRADA + MARCO m2 4.01 350.00 1,403.50 - - 0.00% - 0.00% - - 0.00% 4.01 1,403.50 100.00%
05 CARPINTERIA METALICA Y ALUMINIO 47,081.30
05.01 VENTANA METALICA CON MALLA OLIMPICA 2" + MARCO DE m2 109.76 220.00 24,147.20 - - 0.00% - 0.00% - - 0.00% 109.76 24,147.20 100.00%
05.02 PUERTA METALICA ENROLLABLE CON PLANCHA GALVANIZm2 18.28 260.00 4,752.80 - - 0.00% - 0.00% - - 0.00% 18.28 4,752.80 100.00%
05.03 PUERTA METALICA CORREDIZA DE TUBO CUADRADO CONm2 14.90 400.00 5,960.00 - - 0.00% - 0.00% - - 0.00% 14.90 5,960.00 100.00%
05.04 PARASOL DE POLICARBONATO CON MARCO DE ALUMINIOm2 94.01 130.00 12,221.30 - - 0.00% - 0.00% - - 0.00% 94.01 12,221.30 100.00%
06 CERRAJERIA 350.68
06.01 BISAGRA DE BRONCE ALUMINIZADAS DE 4" und 8.00 13.52 108.16 - - 0.00% - 0.00% - - 0.00% 8.00 108.16 100.00%
06.02 CERRADURA NACIONAL DE 3 GOLPES PARA PUERTA und 2.00 90.97 181.94 - - 0.00% - 0.00% - - 0.00% 2.00 181.94 100.00%
06.03 MANIJA DE BRONCE PARA PUERTAS und 2.00 30.29 60.58 - - 0.00% - 0.00% - - 0.00% 2.00 60.58 100.00%
07 PINTURA 8,347.09
07.01 PINTURA EN MUROS EXTERIORES AL LATEX SATINADO 2 m2 108.44 8.65 938.01 - - 0.00% - 0.00% - - 0.00% 108.44 938.01 100.00%
07.02 PINTURA EN MUROS INTERIORES AL LATEX SATINADO 2 m2 261.78 7.96 2,083.77 - - 0.00% - 0.00% - - 0.00% 261.78 2,083.77 100.00%
07.03 PINTURA EN COLUMNAS Y PLACAS AL LATEX SATINADO m2 321.03 9.25 2,969.53 - - 0.00% - 0.00% - - 0.00% 321.03 2,969.53 100.00%
07.04 PINTURA EN VIGAS AL LATEX SATINADO 2 MANOS m2 116.31 9.24 1,074.70 - - 0.00% - 0.00% - - 0.00% 116.31 1,074.70 100.00%
07.05 PINTURA EN TAPASOL Y CANALETA AL LATEX SATINADO m2 148.68 8.50 1,263.78 - - 0.00% - 0.00% - - 0.00% 148.68 1,263.78 100.00%
07.06 PINTURA EN DERRAMES AL LATEX SATINADO 2 MANOS m 4.38 3.95 17.30 - - 0.00% - 0.00% - - 0.00% 4.38 17.30 100.00%

COSTO DIRECTO 101,262.60


26,011.69 17.16% - 0.00% 26,011.69 25.69% 75,250.92 74.31%
VALORIZACION DE OBRA N° 04
CORRESPONDIENTE AL MES DE NOVIEMBRE DEL 2012

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.
Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012
Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXXII) VOL 8 - TALLER 4: MECÁNICA Y MOTORES (B7) - INST. ELECTRICAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 1,761.40 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 TRAZO Y REPLANTEO glb 1.00 511.57 511.57 1 511.57 100.00% 0.00 0.00% 0.00 511.57 100.00%
01.02 INGENIERIA DE DETALLE Exp 1.00 475.04 475.04 1 475.04 100.00% 0.00 0.00% 0.00 475.04 100.00%
01.03 ACABADO Y SEÑALIZACION m2 1.00 247.06 247.06 1 247.06 1.00 0.00 0.00% 0.00 247.06 100.00%
01.04 PRUEBAS Y PUESTA EN SERVICIO glb 1.00 527.73 527.73 1 527.73 100.00% 0.00 0.00% 0.00 527.73 100.00%
02 TABLEROS 5,631.78
02.01 MURO DE CONCRETO ARMADO DE 0.8X1.6X0.3 MTS M2 1.00 275.21 275.21 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 275.21 100.00%
02.02 SUMINISTRO E INSTALAC. DE TD 07/SEG ESPECIF. EN EL PLANO JGO 1.00 3,446.38 3,446.38 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 3,446.38 100.00%
02.03 SUMINISTRO E INSTALAC. DE TD 071/SEG ESPECIF. EN EL PLANO JGO 1.00 1,910.19 1,910.19 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 1,910.19 100.00%
03 ALIMENTADORES 907.12
03.01 CONDUCTOR NYY TRIPOLAR 1-3X10+T10 mm2, 1 KV ml 23.00 39.44 907.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 23.00 907.12 100.00%
04 SISTEMA DE PROTECCION A TIERRA 1,569.63
04.01 SISTEMA DE PUESTA TIERRA TIPO 01 JGO 1.00 971.13 971.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 971.13 100.00%
04.02 TENDIDO DE CONDUCTOR DE CU DESNUDO 35 MM2 ml 38.00 15.75 598.50 0.00 0.00% 0.00 0.00% 0.00 0.00% 38.00 598.50 100.00%
05 TUBERIAS Y CAJAS DE PASO 2,155.96
05.01 TUBERIA PVC-P DIAM 20 mm (3/4"x3m) EMPOTRADO m 132.00 4.38 578.16 132.00 578.16 100.00% 0.00 0.00% 0.00 578.16 100.00%
05.02 TUBERIA PVC-P DIAM 20 mm (3/4"x3m) ADOSADO m 148.00 6.87 1,016.76 148.00 1,016.76 100.00% 0.00 0.00% 0.00 1,016.76 100.00%
05.03 TUBERIA PVC-P DIAM 25 mm (1"x3m) EMPOTRADO m 49.30 4.91 242.06 49.30 242.06 100.00% 0.00 0.00% 0.00 242.06 100.00%
05.04 TUBERIA PVC-P DIAM 50 mm (2") EMPOTRADO m 23.00 5.56 127.88 23.00 127.88 100.00% 0.00 0.00% 0.00 127.88 100.00%
05.05 CAJA DE PASE -DERIVACION CIRCUITO DE FUERZA und 14.00 13.65 191.10 14.00 191.10 100.00% 0.00 0.00% 0.00 191.10 100.00%
06 CONDUCTORES Y CABLES 2,662.34
06.01 CONDUCTOR THW 3-1X10+T10mm2 m 20.00 23.14 462.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 462.80 100.00%
06.02 CONDUCTOR THW 4-1X4 mm2 m 29.30 9.40 275.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 29.30 275.42 100.00%
06.03 CONDUCTOR THW 3-1X4 mm2 m 69.30 7.69 532.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 69.30 532.92 100.00%
06.04 CONDUCTOR THW 3-1X2.5 mm2 m 100.36 5.22 523.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 100.36 523.88 100.00%
06.05 CONDUCTOR THW 2-1X2.5 mm2 m 230.67 3.76 867.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 230.67 867.32 100.00%
07 SALIDAS PARA ALUMBRADO 1,797.56
07.01 SALIDA PARA CENTRO DE LUZ EN TECHO und 20.00 63.04 1,260.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 1,260.80 100.00%
07.02 SALIDA PARA CENTRO DE LUZ EN PARED und 8.00 29.59 236.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 236.72 100.00%
07.03 SALIDA PARA LUZ DE EMERGENCIA und 4.00 30.05 120.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 120.20 100.00%
07.04 SALIDA PARA INTERRUPTORES EN PARED und 8.00 22.48 179.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 179.84 100.00%
08 ILUMINACION 5,757.92
08.01 SALIDA PARA LUMINARIA TIPO A und 20.00 219.18 4,383.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 4,383.60 100.00%
08.02 SALIDA PARA LUMINARIA TIPO B und 8.00 53.03 424.24 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.00 424.24 100.00%
08.03 SALIDA PARA LUMINARIA TIPO K und 4.00 179.92 719.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 719.68 100.00%
08.04 INSTALACION DE INTERRUPTOR SIMPLE und 7.00 28.14 196.98 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.00 196.98 100.00%
08.05 INSTALACION DE INTERRUPTOR DOBLE und 1.00 33.42 33.42 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 33.42 100.00%
09 FUERZA Y TOMACORRIENTES 2,122.51
09.01 SALIDA PARA TOMACORRIENTE DOBLE CON P/TIERRA 1.8 Mts und 1.00 74.31 74.31 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 74.31 100.00%
09.02 SALIDA PARA TOMACORRIENTE DOBLE CON P/TIERRA 0.40 Mts und 22.00 49.12 1,080.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 22.00 1,080.64 100.00%
09.03 SALIDA PARA TOMACORRIENTE P/CARGA ESPECIAL MONOFASICA und 1.00 99.07 99.07 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 99.07 100.00%
09.04 SALIDA PARA TOMACORRIENTE P/CARGA ESPECIAL TRIFASICA und 7.00 124.07 868.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.00 868.49 100.00%

24,366.22 3,917.36 16.08% 0.00 0.00% 3,917.36 16.08% 20,448.86 83.92%


#REF!
#REF!

Obra : MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA INSTITUCIÓN EDUCATIVA CARLOS FERMIN FITZCARRALD N° DE CONTRATO : 036-2012/GOREMAD/GGR.

Form. : 01 PRESUPUESTO GENERAL CONTRATISTA: CONSORCIO CARLOS F. FITZCARRALD FECHA : 03/07/2012


Cliente : GOBIERNO REGIONAL DE MADRE DE DIOS INSPECTOR: ING. EDUARDO DONAIRES CASTILLO MONTO DE CONTRATO : S/. 23,508,980.65 (INC. IGV.)
Ubicac. : TAMBOPATA - TAMBOPATA - MADRE DE DIOS. FACTOR DE RELACION: 1.0000000000 PLAZO EJECUCION : 548 DIAS CALENDARIOS

(XXXIII) VOL 9 - TALLER 5-6: HOSTELERÍA - CONFECCIONES (B8) - ESTRUCTURAS


Item Descripcion und Metrado P.unit Parcial ACUMULADO ANTERIOR MES ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
01 TRABAJOS PRELIMINARES 2,486.76 METRADO S/. % METRADO S/. % METRADO S/. % METRADO S/. %
01.01 LIMPIEZA DE TERRENO MANUAL m2 469.20 1.12 525.50 469.2 525.50 100.00% 0.00 0.00% 469.20 525.50 100.00% 0.00 0.00 100.00%
01.02 TRAZO, NIVELES Y REPLANTEO INICIAL m2 469.20 4.18 1,961.26 469.2 1,961.26 100.00% 0.00 0.00% 469.20 1,961.26 100.00% 0.00 0.00 100.00%
02 MOVIMIENTO DE TIERRAS 25,520.77
02.01 NIVELACION DE TERRENO m2 469.20 2.49 1,168.31 469.2 1,168.31 100.00% 0.00 0.00% 469.20 1,168.31 100.00% 0.00 0.00 100.00%
02.02 EXCAVACION DE ZANJAS m3 305.65 33.34 10,190.37 305.65 10,190.37 100.00% 0.00 0.00% 305.65 10,190.37 100.00% 0.00 0.00 100.00%
02.03 RELLENO Y COMPACTADO C/ MATERIAL PROPIO m3 202.88 23.67 4,802.17 202.88 4,802.17 100.00% 0.00 0.00% 202.88 4,802.17 100.00% 0.00 0.00 100.00%
02.04 ACARREO INTERNO MAT. PROCED. DE EXCAVACIONES Dprom=30M m3 194.47 17.00 3,305.99 367.26 6,243.42 188.85% 0.00 0.00% 367.26 6,243.42 188.85% -172.79 -2,937.43 100.00%
02.05 ELIMINACION MATERIAL EXCEDENTE CON MAQUINARIA VOLQUETE 15M3m3 194.47 7.91 1,538.26 194.47 1,538.26 100.00% 0.00 0.00% 194.47 1,538.26 100.00% 0.00 0.00 100.00%
02.06 NIVELACION Y APISONADO PARA FALSO PISO O PISO m2 454.25 2.18 990.27 454.25 990.27 100.00% 0.00 0.00% 454.25 990.27 100.00% 0.00 0.00 100.00%
02.07 RELLENO CON AFIRMADO DE e=4" (100% COMPACTACION) m3 46.15 76.39 3,525.40 46.15 3,525.40 100.00% 0.00 0.00% 46.15 3,525.40 100.00% 0.00 0.00 100.00%
03 OBRAS DE CONCRETO SIMPLE 45,816.78
03.01 CONCRETO EN FALSA ZAPATAS F'C= 100 KG/CM2 m3 56.97 257.89 14,691.99 62.89 16,218.70 110.39% 0.00 0.00% 62.89 16,218.70 110.39% -5.92 -1,526.71 100.00%
03.02 CIMIENTO CORRIDO F'c=140 kg/cm2 m3 26.05 303.68 7,910.86 26.05 7,910.86 100.00% 0.00 0.00% 26.05 7,910.86 100.00% 0.00 0.00 100.00%
03.03 CONCRETO EN SOBRECIMIENTO F'C= 175 KG/CM2 m3 5.70 411.54 2,345.78 5.70 2,345.78 100.00% 0.00 0.00% 5.70 2,345.78 100.00% 0.00 0.00 100.00%
03.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 73.43 31.61 2,321.12 73.43 2,321.12 100.00% 0.00 0.00% 73.43 2,321.12 100.00% 0.00 0.00 100.00%
03.05 FALSO PISO e= 4" (10CM.) 1:6 C:H m2 454.25 40.83 18,547.03 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 454.25 18,547.03 100.00%
04 OBRAS DE CONCRETO ARMADO 208,647.99
04.01 ZAPATAS 31,968.40
04.01.01 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 65.80 349.47 22,995.13 65.80 22,995.13 100.00% 0.00 0.00% 65.80 22,995.13 100.00% 0.00 0.00 100.00%
04.01.02 ZAPATAS, ACERO FY=4200KG/CM2 kg 1,857.82 4.83 8,973.27 1,857.82 8,973.27 100.00% 0.00 0.00% 1,857.82 8,973.27 100.00% 0.00 0.00 100.00%
04.02 VIGAS DE CIMENTACION 9,867.55
04.02.01 VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2 m3 6.27 371.88 2,331.69 6.27 2,331.69 100.00% 0.00 0.00% 6.27 2,331.69 100.00% 0.00 0.00 100.00%
04.02.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 60.25 54.27 3,269.77 60.25 3,269.77 100.00% 0.00 0.00% 60.25 3,269.77 100.00% 0.00 0.00 100.00%
04.02.03 VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2. kg 828.88 4.96 4,111.24 828.88 4,111.24 100.00% 0.00 0.00% 828.88 4,111.24 100.00% 0.00 0.00 100.00%
04.02.04 VIGAS DE CIMENTACION, BASE CON POLIESTILENO EXPANDIDO (TECNOPOR
m2 9.19 16.85 154.85 9.19 154.85 100.00% 0.00 0.00% 9.19 154.85 100.00% 0.00 0.00 100.00%
04.03 SOBRECIMIENTOS REFORZADOS 20,419.12
04.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO F'C= 175 KG/CM2 m3 17.88 401.74 7,183.11 17.88 7,183.11 100.00% 0.00 0.00% 17.88 7,183.11 100.00% 0.00 0.00 100.00%
04.03.02 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 223.64 31.61 7,069.26 223.64 7,069.26 100.00% 0.00 0.00% 223.64 7,069.26 100.00% 0.00 0.00 100.00%
04.03.03 SOBRECIMIENTO, ACERO FY=4200 KG/CM2 . kg 1,176.86 5.24 6,166.75 1,176.86 6,166.75 100.00% 0.00 0.00% 1,176.86 6,166.75 100.00% 0.00 0.00 100.00%
04.04 COLUMNETAS 12,773.96
04.04.01 COLUMNETAS, CONCRETO F'C= 175 KG/CM2 m3 6.70 381.44 2,555.65 6.70 2,555.65 100.00% 0.00 0.00% 6.70 2,555.65 100.00% 0.00 0.00 100.00%
04.04.02 COLUMNETAS, ENCOFRADO Y DESENCOFRADO m2 67.69 46.14 3,123.22 67.69 3,123.22 100.00% 0.00 0.00% 67.69 3,123.22 100.00% 0.00 0.00 100.00%
04.04.03 COLUMNETAS, ACERO FY=4200 KG/CM2 kg 1,487.44 4.77 7,095.09 1,487.44 7,095.09 100.00% 0.00 0.00% 1,487.44 7,095.09 100.00% 0.00 0.00 100.00%
04.05 COLUMNAS 73,972.99
04.05.01 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 41.00 507.07 20,789.87 41.00 20,789.87 100.00% 0.00 0.00% 41.00 20,789.87 100.00% 0.00 0.00 100.00%
04.05.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 416.20 56.37 23,461.19 416.20 23,461.19 100.00% 0.00 0.00% 416.20 23,461.19 100.00% 0.00 0.00 100.00%
04.05.03 COLUMNAS, ACERO FY=4200 KG/CM2. kg 5,885.53 5.05 29,721.93 5,885.53 29,721.93 100.00% 0.00 0.00% 5,885.53 29,721.93 100.00% 0.00 0.00 100.00%
04.06 VIGUETAS DE ARRIOSTRE 7,106.20
04.06.01 VIGUETAS DE ARRIOSTRE, CONCRETO F'c= 175KG/CM2 m3 3.99 329.85 1,316.10 3.99 1,316.10 100.00% 0.00 0.00% 3.99 1,316.10 100.00% 0.00 0.00 100.00%
04.06.02 VIGUETAS DE ARRIOSTRE, ENCOFRADO Y DESENCOFRADO m2 60.35 53.91 3,253.47 60.35 3,253.47 100.00% 0.00 0.00% 60.35 3,253.47 100.00% 0.00 0.00 100.00%
04.06.03 VIGA DE ARRIOSTRE, ACERO FY=4200 KG/CM2. kg 517.68 4.90 2,536.63 517.68 2,536.63 100.00% 0.00 0.00% 517.68 2,536.63 100.00% 0.00 0.00 100.00%
04.07 VIGAS 23,310.95
04.07.01 VIGAS, CONCRETO F'C=210 KG/CM2 m3 15.91 391.02 6,221.13 0.00 0.00 0.00% 15.91 6,221.13 100.00% 15.91 6,221.13 100.00% 0.00 0.00 100.00%
04.07.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 155.95 59.62 9,297.74 155.95 9,297.74 100.00% 0.00 0.00% 155.95 9,297.74 100.00% 0.00 0.00 100.00%
04.07.03 VIGAS, ACERO FY=4200 KG/CM2. kg 1,590.22 4.90 7,792.08 1,590.22 7,792.08 100.00% 0.00 0.00% 1,590.22 7,792.08 100.00% 0.00 0.00 100.00%
04.08 CANALETA DE CONCRETO EN TECHO 29,228.82
04.08.01 CANALETA DE CONCRETO EN TECHO, CONCRETO F'C=210 KG/CM2 CON ADm3 12.60 412.67 5,199.64 0.00 0.00 0.00% 12.60 5,199.64 100.00% 12.60 5,199.64 100.00% 0.00 0.00 100.00%
04.08.02 CANALETA DE CONCRETO EN TECHO, ENCOFRADO Y DESENCOFRADO m2 267.12 72.87 19,465.03 267.12 19,465.03 100.00% 0.00 0.00% 267.12 19,465.03 100.00% 0.00 0.00 100.00%
04.08.03 CANALETA DE CONCRETO EN TECHO, ACERO FY=4200 KG/CM2. kg 931.46 4.90 4,564.15 931.46 4,564.15 100.00% 0.00 0.00% 931.46 4,564.15 100.00% 0.00 0.00 100.00%
05 ESTRUCTURA METALICA Y COBERTURA 110,699.04
05.01 TIJERAL METÁLICO DE SECCIÓN RECTANGULAR T-1 und 5.00 6,670.74 33,353.70 5.00 33,353.70 100.00% 0.00 0.00% 5.00 33,353.70 100.00% 0.00 0.00 100.00%
05.02 SOPORTES METALICOS PARA CERCHAS und 10.00 580.16 5,801.60 10.00 5,801.60 100.00% 0.00 0.00% 10.00 5,801.60 100.00% 0.00 0.00 100.00%
05.03 VIGUETA TIPO "Z" DE 100mm x 51mm x 4.5mmm x 6.00m m 453.60 80.82 36,659.95 0.00 0.00 0.00% 453.60 36,659.95 100.00% 453.60 36,659.95 100.00% 0.00 0.00 100.00%
05.04 TENSORES METALICOS DE ACERO LISO DE 3/8" m 100.80 28.32 2,854.66 0.00 0.00 0.00% 100.80 2,854.66 100.00% 100.80 2,854.66 100.00% 0.00 0.00 100.00%
05.05 TEMPLADORES METALICOS DE ACERO LISO DE 1/2" (ENTRE TIJERALES) m 170.56 23.45 3,999.63 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 170.56 3,999.63 100.00%
05.06 COBERTURA CON PLANCHA METALICA TIPO TECNOTECHO MOD. TR4 950xm2 359.86 77.89 28,029.50 0 0 0.00% 0.00 0.00% 0.00 0.00 0.00% 359.86 28,029.50 100.00%
06 MUROS Y TABIQUES DE ALBAÑILERIA 24,826.96
06.01 MURO DE SOGA CON LADRILLO DE ARCILLA 9x13x24 CM. (CON ALAMBRE m
N2 72.16 91.18 6,579.55 72.16 6579.5488 100.00% 0.00 0.00% 72.16 6,579.55 100.00% 0.00 0.00 100.00%
06.02 MURO DE CABEZA CON LADRILLO DE ARCILLA 9X13X24 (CON ALAMBRE N°m2 123.26 148.04 18,247.41 123.26 18247.4104 100.00% 0.00 0.00% 123.26 18,247.41 100.00% 0.00 0.00 100.00%

COSTO DIRECTO 417,998.30 320,950.89 76.78% 50,935.38 12.19% 371,886.27 88.97% 46,112.03 11.03%