CALENDARIO VALORIZADO - PROGRAMADO

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI DELL’ACQUA CC.PP LUJARAJA
DISTRITO DE SANTIAGO-ICA-ICA”
CONTRATISTA : CONSORCIO ESPINAR PLAZO DE EJECUCION: 180 DIAS CALENDARIOS

RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017

SUPERVISOR ING. LUIS ENRIQUE MINA APARICIO TERMINO CONTRACTUAL 10 DE ABRIL DE 2018

VALOR REFERENCIAL CON IGV S/. 2,537,294.19 MODALIDAD CONTRATACION: A SUMA ALZADA

EJECUCION DE OBRA: FACTOR DE RELACION: 98.50%

PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78


PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,117,995.57

13-Oct-17 01-Nov-17 01-Dec-17 01-Jan-18 01-Feb-18 01-Mar-18 01-Apr-18


VALOR
COD. DESCRIPCION 31-Oct-17 30-Nov-17 31-Dec-17 31-Jan-18 28-Feb-18 31-Mar-18 10-Apr-18
REFERENCIAL
19 30 31 31 28 31 10

01 I.E. N° 22353 ANTONIO RAIMONDI 1,869,782.01 17,762.93 127,706.11 390,036.53 433,228.49 308,140.08 401,442.20 191,465.68

COSTO PARCIAL 1,869,782.01 17,762.93 127,706.11 390,036.53 433,228.49 308,140.08 401,442.20 191,465.68
GASTOS GENERALES 10.00% 186,978.20 1,776.29 12,770.61 39,003.65 43,322.85 30,814.01 40,144.22 19,146.57
UTLIDAD 5.00% 93,489.10 888.15 6,385.31 19,501.83 21,661.42 15,407.00 20,072.11 9,573.28
SUBTOTAL 2,150,249.31 20,427.37 146,862.03 448,542.01 498,212.76 354,361.09 461,658.53 220,185.53
FACTOR DE RELACION (98.50%) 2,117,995.57 20,120.96 144,659.10 441,813.88 490,739.57 349,045.67 454,733.65 216,882.75
I.G.V. 18% 381,239.20 3,621.77 26,038.64 79,526.50 88,333.12 62,828.22 81,852.06 39,038.89

TOTAL MONTO CONTRACTUAL 2,499,234.78 23,742.73 170,697.74 521,340.38 579,072.69 411,873.89 536,585.71 255,921.64
Monto Contractual Acumulado 23,742.73 194,440.47 715,780.85 1,294,853.54 1,706,727.43 2,243,313.14 2,499,234.78
% Avance Mensual: 0.00% 0.95% 6.83% 20.86% 23.17% 16.48% 21.47% 10.24%
% Avance Mensual Acumulado: 0.00% 0.95% 7.78% 28.64% 51.81% 68.29% 89.76% 100.00%

1
CALENDARIO VALORIZADO - REAL DE EJECUCION DE OBRA

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI DELL’ACQUA CC.PP LUJARAJA
DISTRITO DE SANTIAGO-ICA-ICA”
CONTRATISTA : CONSORCIO ESPINAR PLAZO DE EJECUCION: 180 DIAS CALENDARIOS
RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017

SUPERVISOR ING. LUIS ENRIQUE MINA APARICIO TERMINO CONTRACTUAL 10 DE ABRIL DE 2018

VALOR REFERENCIAL CON IGV S/. 2,537,294.19 MODALIDAD CONTRATACION: A SUMA ALZADA

EJECUCION DE OBRA: FACTOR DE RELACION: 98.50%

PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78


PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,150,249.31

13-Oct-17 01-Nov-17 01-Dec-17 01-Jan-18 01-Feb-18 01-Mar-18 01-Apr-18


VALOR
COD. DESCRIPCION 31-Oct-17 30-Nov-17 31-Dec-17 31-Jan-18 28-Feb-18 31-Mar-18 10-Apr-18
REFERENCIAL
19 30 31 31 28 31 10

01 I.E. N° 22353 ANTONIO RAIMONDI 1,869,782.01 54,515.11 348,645.64 199,275.02 251,688.51

COSTO PARCIAL 1,869,782.01 54,515.11 348,645.64 199,275.02 251,688.51 - - -


GASTOS GENERALES 10.00% 186,978.20 5,451.51 34,864.56 19,927.50 25,168.85 - - -
UTLIDAD 5.00% 93,489.10 2,725.76 17,432.28 9,963.75 12,584.43 - - -
SUBTOTAL 2,150,249.31 62,692.38 400,942.48 229,166.27 289,441.79 - - -
FACTOR DE RELACION (98.50%) 2,117,995.57 61,752.00 394,928.35 225,728.78 285,100.16 - - -
I.G.V. 18% 381,239.20 11,115.35 71,087.10 40,631.18 51,318.03 - - -

TOTAL MONTO CONTRACTUAL 2,499,234.78 72,867.35 466,015.45 266,359.96 336,418.19 - - -


Monto Contractual Acumulado 72,867.35 466,015.45 732,375.41 1,068,793.60 1,068,793.60 1,068,793.60 1,068,793.60
% Avance Mensual: 0.00% 2.92% 18.65% 10.66% 13.46% 0.00% 0.00% 0.00%
% Avance Mensual Acumulado: 0.00% 2.92% 21.57% 32.23% 45.69% 45.69% 45.69% 45.69%
CALENDARIO VALORIZADO - PROGRAMADO
100.00%
PORCENTAJE DE AVANCE

100.00%

90.00% 89.76%

80.00%

70.00%
68.29%

60.00%

50.00%
51.81%

40.00%

30.00% 28.64%

20.00%

10.00%
7.78%

0.00% 0.00% 0.95%


1 2 3 4 5 6 7

NUMERO DE VALORIZACIONES
AVANCE ACUMULADO COMPARATIVO
REAL VS PROGRAMADO
25.00%
PORCENTAJE DE AVANCE

REAL
PROGRAMADO
21.57%
20.00%

15.00%

10.00%

7.78%

5.00%

2.92%
0.95%
0.00%
2
1
0
Meses
RESUMEN DE VALORIZACIONES DE OBRA
VALORIZACION N°04 (03-01-2018 AL 31-01-2018)

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI DELL’ACQUA CC.PP LUJARAJA
DISTRITO DE SANTIAGO-ICA-ICA”
CONTRATISTA : CONSORCIO ESPINAR PLAZO DE EJECUCION: 180 DIAS CALENDARIOS

RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017

SUPERVISOR ING. LUIS ENRIQUE MINA APARICIO TERMINO CONTRACTUAL 10 DE ABRIL DE 2018

VALOR REFERENCIAL CON IGV S/. 2,537,294.19 MODALIDAD CONTRATACION: A SUMA ALZADA

EJECUCION DE OBRA: FACTOR DE RELACION: 0.985


PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78
PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,150,249.31

13-Oct-17 01-Nov-17 01-Dec-17 01-Jan-18 01-Feb-18 01-Mar-18 01-Apr-18


VALOR
COD DESCRIPCION 31-Oct-17 30-Nov-17 31-Dec-17 31-Jan-18 28-Feb-18 31-Mar-18 10-Apr-18
REFERENCIAL
19 30 31 31 28 31 10

01 I.E. N° 22353 ANTONIO RAIMONDI 2,150,249.31 62,692.38 400,942.48 229,166.27 289,441.79

FACTOR DE RELACIO 98.50% 2,117,995.58 61,751.99 394,928.35 225,728.79 285,100.17 -


TOTAL Sin IGV 2,117,995.58 61,751.99 394,928.35 225,728.79 285,100.17 - - -
TOTAL ACUMULADO Sin IGV 2,117,995.58 61,751.99 456,680.33 682,409.12 967,509.29 - - -
TOTAL ACUMULADO Con IGV 2,499,234.78 72,867.35 538,882.79 805,242.77 1,141,660.96 0.00 0.00 0.00
AMORTIZACION DEL ADELANTO DIRECTO
VALORIZACION N°04 (03-01-2018 AL 31-01-2018)

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI


DELL’ACQUA CC.PP LUJARAJA DISTRITO DE SANTIAGO-ICA-ICA”

CONTRATISTA : CONSORCIO ESPINAR


RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES
JEFE DE SUPERVISION: ING. LUIS ENRIQUE MINA APARICIO
EJECUCION DE OBRA:
PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78
PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,117,995.57
PLAZO DE EJECUCION: 180 DIAS CALENDARIOS
INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017
TERMINO CONTRACTUAL 10 DE ABRIL DE 2018
MODALIDAD CONTRATACION: A SUMA ALZADA
FACTOR DE RELACION: 0.985
MONTO ADELANTO DIRECTO SIN (IGV): S/. 211,799.56
MONTO ADELANTO DIRECTO CON (IGV): S/. 249,923.48

VALORIZACION MONTO AMORTIZACION MONTO DEL SALDO POR


Nº MES VALORIZADO ADELANTO ADELANTO AMORTIZAR

1 13-Oct-17
61,751.99 61,751.99 S/. 211,799.56 150,047.57
31-Oct-17
2 1-Nov-17
394,942.48 39,492.83 110,554.74
30-Nov-17
3 1-Dec-17
225,728.79 110,554.74 -0.00
31-Dec-17
4 1-Jan-18
285,100.17 - -0.00
31-Jan-18
5 1-Feb-18
- -0.00
28-Feb-18
6 1-Mar-18
- -0.00
31-Mar-18
7 1-Apr-18
- -0.00
10-Apr-18
TOTAL 967,523.43 211,799.56

SALDO POR VALORIZAR S/. 1,150,472.14

AVANCE DE OBRA ACUMULADO 45.69%

AMORTIZACION ACUMULADA S/. 211,799.56

AMORTIZACION ACUMULADA ANTERIOR S/. 211,799.56

AMORTIZACION DEL MES S/. 0.00


AMORTIZACION DEL ADELANTO MATERIALES
VALORIZACION N°04 (03-01-2018 AL 31-01-2018)

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI


DELL’ACQUA CC.PP LUJARAJA DISTRITO DE SANTIAGO-ICA-ICA”

CONTRATISTA : CONSORCIO ESPINAR


RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES
JEFE DE SUPERVISION: ING. LUIS ENRIQUE MINA APARICIO
EJECUCION DE OBRA:
PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78
PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,117,995.57
PLAZO DE EJECUCION: 180 DIAS CALENDARIOS
INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017
TERMINO CONTRACTUAL 10 DE ABRIL DE 2018
MODALIDAD CONTRATACION: A SUMA ALZADA
FACTOR DE RELACION: 0.985
MONTO ADELANTO MATERIALES SIN (IGV): S/. 423,599.11
MONTO ADELANTO MATERIALES CON (IGV): S/. 499,846.96

VALORIZACION MONTO AMORTIZACION MONTO DEL SALDO POR


Nº MES VALORIZADO ADELANTO ADELANTO AMORTIZAR

1 13-Oct-17
61,751.99 - S/. 423,599.11 423,599.11
31-Oct-17
2 1-Nov-17
394,942.48 39,492.83 384,106.28
30-Nov-17
3 1-Dec-17
225,728.79 39,492.83 344,613.45
31-Dec-17
4 1-Jan-18
336,418.19 118,887.37 225,726.08
31-Jan-18
5 1-Feb-18
- 225,726.08
28-Feb-18
6 1-Mar-18
- 225,726.08
31-Mar-18
7 1-Apr-18
- 225,726.08
10-Apr-18
TOTAL 1,018,841.46 197,873.03

SALDO POR VALORIZAR S/. 1,099,154.11

AVANCE DE OBRA ACUMULADO 48.11%

AMORTIZACION ACUMULADA S/. 197,873.03

AMORTIZACION ACUMULADA ANTERIOR S/. 78,985.66

AMORTIZACION DEL MES S/. 118,887.37


RESUMEN DE VALORIZACION MENSUAL Nº 04
V A L O R I Z A C I O N N° 04 (03-01-2018 AL 31-01-2018)

OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI DELL’ACQUA CC.PP LUJARAJA
DISTRITO DE SANTIAGO-ICA-ICA”
CONTRATISTA : CONSORCIO ESPINAR
RESIDENTE DE OBRA: ING. JUAN RAUL LEON FLORES
JEFE DE SUPERVISION: ING. LUIS ENRIQUE MINA APARICIO
EJECUCION DE OBRA:
PRESUPUESTO CONTRATADO (CON IGV): S/. 2,499,234.78
PRESUPUESTO CONTRATADO (SIN IGV): S/. 2,117,995.57
PLAZO DE EJECUCION: 180 DIAS CALENDARIOS
INICIO PLAZO DE EJECUCION: 13 DE OCTUBRE DE 2017
TERMINO CONTRACTUAL 10 DE ABRIL DE 2018
MODALIDAD CONTRATACION: CONCURSO OFERTA
FACTOR DE RELACION: 1.00
DESCRIPCION MONTO VAL. ACUM. VALORIZACION VAL. ACUM. % AVANCE SALDO POR
CONTRATADO ANTERIOR ACTUAL ACTUAL ESPECIAL. VALORIZAR

VALORIZACION CONTRACTUAL (V)

I.E. N° 22353 ANTONIO RAIMONDI 2,150,249.31 62,692.38 400,942.48 463,634.82 21.57% 1,686,614.49

TOTAL CONTRACTUAL 2,150,249.31 62,692.38 400,942.48 463,634.82 1,686,614.49


AVANCES % ANTERIOR ACUM. % ACTUAL % ACUMULADO
% AVANCE REAL 2.93% 18.65% 21.58% 78.42%
% AVANCE PROGRAMADO 0.95% 0.95% 1.90%

FACTOR DE RELACION 0.985 S/. 61,751.99 S/. 394,928.34 S/. 456,680.30

REAJUSTE AUTORIZADO (S) ANTERIOR ACUM. ACTUAL ACUMULADO

I.E. N° 22353 ANTONIO RAIMONDI -

TOTAL CONTRACTUAL S/. - S/. - S/. -

VALORIZACION BRUTA (VB=V+S) S/. 61,751.99 S/. 394,928.34 S/. 456,680.30

DEDUCCIONES DE REAJUSTE QUE NO CORRESPONDEN ANTERIOR ACUM. ACTUAL ACUMULADO

DRNC del Adelanto Directo - - -


DRNC del Adelanto de Materiales - - -
TOTAL DE DEDUCCIONES S/. - S/. - S/. -

AMORTIZACION (A) ANTERIOR ACUM. ACTUAL ACUMULADO

ADELANTO DIRECTO S/IGV 10% S/. - 211,799.56 - 211,799.56


ADELANTO DE MATERIALES S/IGV 10% S/. - 78,985.66 118,887.37 197,873.03
TOTAL AMORTIZACIONES S/. 290,785.22 S/. 118,887.37 S/. 409,672.59

VALORIZACION NETA (VN=VB-D-A) S/. -229,033.2 S/. 276,040.97 S/. 47,007.70

MULTA POR ATRAZO DE OBRA (M) S/. - S/. - S/. -

MONTO A PAGAR AL CONTRATISTA ANTERIOR ACUM. ACTUAL ACUMULADO

- EN EFECTIVO (VN-M) S/. -229,033.2 S/. 276,040.97 S/. 47,007.70


- EN IGV (VNx18%) S/. -41,226.0 S/. 49,687.38 S/. 8,461.38
MONTO TOTAL CON I.G.V. S/. -270,259.2 S/. 325,728.35 S/. 55,469.08
TOTAL MONTO A FACTURAR S/. -270,259.2 S/. 325,728.35 S/. 55,469.08
VALORIZACION Nº 04 (del 03/01/2018 al 31/01/2018)
I.E. N° 22353 ANTONIO RAIMONDI
OBRA: “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I.E. N° 22353 ANTONIO RAIMONDI DELL’ACQUA CC.PP LUJARAJA DISTRITO DE SANTIAGO-ICA-ICA”
PISCO, CHINCHA - REGION ICA VALOR REFERENCIAL S/. 2,537,294.19
UBICACIÓN: LUJARAJA - SANTIAGO - ICA - ICA MONTO EJECUCION DE OBRA: S/. 2,499,234.78
SISTEMA DE CONTRATACION : A SUMA ALZADA INGENIERO RESIDENTE : ING. JUAN RAUL LEON FLORES
SUPERVISOR : ING. LUIS ENRIQUE MINA APARICIO
CONTRATISTA : CONSORCIO ESPINAR (GEOCONS CONSULTORIA Y CONSTRUCCION SAC - ROMA INVERSIONES GENERALES S.A.C.) INICIO PLAZO DE EJECUCION DE OBRA : 13 DE OCTUBRE DEL 2017

PRESUPUESTO AVANCES SALDO


COD. DESCRIPCIÓN UND MET. P.U. PARCIAL ANTERIOR ACTUAL ACUMULADO (PRESUPUESTO REMANENTE)
MET. PARCIAL % MET. PARCIAL % MET. % MET. PARCIAL %
35,692.29 21104.79 7004.29 19.62% 28,109.08 0.79 7583.21
01 OBRAS PROVISIONALES 15,949.79 12,039.05 2,410.74 0.15 14,449.79 0.91 - 1,500.00 9.40%
01.01. CASETA DE OFICINA, ALMACEN Y GUARDIANIA M2 80.00 63.82 5,105.60 80.00 5,105.60 - - - 80.00 5,105.60 1.00 - 0.00 0.00%
01.02. SERIVIOS HIGIENICOS GLB 2.00 1200.00 2,400.00 2.00 2,400.00 0.00 - - 2.00 2,400.00 1.00 - 0.00 0.00%
01.03. CERCO PROVISIONAL DE ESTERAS DURANTE LA OBRA M 249.76 9.42 2,352.74 100.00 942.00 149.76 1,410.74 0.60 249.76 2,352.74 1.00 - 0.00 0.00%
01.04. CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 x 2.40m UND 1.00 1091.45 1,091.45 1.00 1,091.45 0.00 - - 1.00 1,091.45 1.00 - 0.00 0.00%
01.05. MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 5000.00 5,000.00 0.50 2,500.00 0.20 1,000.00 0.20 0.70 3,500.00 0.70 0.30 1,500.00 30.00%
02 OBRAS PRELIMINARES 19,820.77 - 8,528.11 4,962.94 0.25 - 13,491.05 0.68 - 6,329.73 31.93%
02.01 LIMPIEZA DE TERRENO MANUAL M2 3483.44 1.57 5,469.00 1,498.79 2,353.10 872.22 1,369.39 0.25 2,371.01 3,722.49 0.68 1,112.43 1,746.52 31.93%
02.02 TRAZO Y REPLANTEO PREILIMINAR M2 3483.44 4.12 14,351.77 1,498.79 6,175.01 872.22 3,593.55 0.25 2,371.01 9,768.56 0.68 1,112.43 4,583.21 31.93%
03 DEMOLICIONES Y DESMONTAJES 27,529.54 - 25,782.55 1,747.00 0.06 - 27,529.54 1.00 - 0.00 0.00%
03.01 DEMOLICION DE CIMIENTOS DE CONCRETO M3 132.14 43.89 5,799.62 120.92 5,307.18 11.22 492.45 0.08 132.14 5,799.62 1.00 - 0.00 0.00%
03.02 DEMOLICION DE SOBRECIMIENTOS M3 19.23 26.08 501.52 17.72 462.14 1.51 39.38 0.08 19.23 501.52 1.00 - 0.00 0.00%
03.03 DEMOLICION DE COLUMNAS Y VIGAS DE CONCRETO M3 19.24 62.99 1,211.93 17.40 1,096.03 1.84 115.90 0.10 19.24 1,211.93 1.00 - 0.00 0.00%
03.04 DEMOLICION DE PISOS DE CONCRETO INCLUYENDO FALSO PISO M2 442.31 4.25 1,879.82 442.31 1,879.82 0.00 - - 442.31 1,879.82 1.00 - 0.00 0.00%
03.05 DEMOLICION DE LOSA ALIGERADA e= 20 cm M2 28.90 13.52 390.73 28.90 390.73 0.00 - - 28.90 390.73 1.00 - 0.00 0.00%
03.06 DEMOLICION DE MUROS DE ALBAÑILERIA M2 768.94 14.95 11,495.65 695.41 10,396.38 73.53 1,099.27 0.10 768.94 11,495.65 1.00 - 0.00 0.00%
03.07 DESMONTAJE DE ESTRUCTURA METALICA M2 125.16 14.27 1,786.03 125.16 1,786.03 0.00 - - 125.16 1,786.03 1.00 - 0.00 0.00%
03.08 DESMONTAJE DE MONTURA LIVIANA M2 323.70 11.90 3,852.03 323.70 3,852.03 0.00 - - 323.70 3,852.03 1.00 - 0.00 0.00%
03.09 DESMONTAJE DE PUERTAS M2 28.79 15.56 447.97 28.79 447.97 0.00 - - 28.79 447.97 1.00 - 0.00 0.00%
03.10 DESMONTAJE DE VENTANAS M2 52.81 3.11 164.24 52.81 164.24 0.00 - - 52.81 164.24 1.00 - 0.00 0.00%
04 MOVIMIENTO DE TIERRAS 196,603.51 - 109,488.23 43,908.22 0.22 - 153,396.46 0.78 - 43,207.05 21.98%
04.01 EXCAVACIONES 38,433.05 - 33,420.12 3,149.85 0.08 - 36,569.97 0.95 - 1,863.07 4.85%
04.01.01 EXCAVACION DE ZANJAS DE ZAPATAS M3 331.00 40.02 13,246.62 308.60 12,350.17 - - - 308.60 12,350.17 0.93 22.40 896.45 6.77%
04.01.02 EXCAVACION DE ZANJAS PARA CIMIENTO M3 325.74 35.01 11,404.16 218.36 7,644.78 89.97 3,149.85 0.28 308.33 10,794.63 0.95 17.41 609.52 5.34%
04.01.03 EXCAVACION DE ZANJAS PARA CISTERNA h>=2m M3 143.80 93.36 13,425.17 143.80 13,425.17 - - - 143.80 13,425.17 1.00 - 0.00 0.00%
04.01.04 EXCAVACION DE ZANJA P/SARDINELES T.N. M3 10.20 35.01 357.10 - - - - - - - - 10.20 357.10 100.00%
04.02 CORTES 7,849.00 - - 2,207.96 0.28 - 2,207.96 0.28 - 5,641.04 71.87%
04.02.01 CORTE DE TERRENO C/EQUIPO T.N. M3 539.45 14.55 7,849.00 - - 151.75 2,207.96 0.28 151.75 2,207.96 0.28 387.70 5,641.04 71.87%
04.03 RELLENOS 15,688.33 - 8,008.47 214.54 0.01 - 8,223.01 0.52 - 7,465.32 47.59%
04.03.01 RELLENO MANUAL COMPACTADO C/PLANCHA VIB. MATERIAL PROPIM3 179.96 14.36 2,584.23 160.94 2,311.10 14.94 214.54 0.08 175.88 2,525.64 0.98 4.08 58.59 2.27%
04.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO M3 213.62 13.06 2,789.88 160.84 2,100.57 - - - 160.84 2,100.57 0.75 52.78 689.31 24.71%
04.03.03 RELLENO MANUAL CON MATERIAL DE PRESTAMO (AFIRMADO) M3 58.00 110.50 6,409.00 - - - - - - - - 58.00 6,409.00 100.00%
04.03.04 RELLENO MANUAL MATERIAL DE PRESTAMO GRAVA M3 27.73 140.83 3,905.22 25.54 3,596.80 - - - 25.54 3,596.80 0.92 2.19 308.42 7.90%
04.04 NIVELACION DE TERRENOS 30,980.32 - 6,944.25 22,360.38 0.72 - 29,304.63 0.95 - 1,675.69 5.41%
04.04.01 ESCARIFICADO-NIVELACION INTERIOR Y COMPACTACION CON EQU M2 366.56 0.72 263.92 332.77 239.59 - - - 332.77 239.59 0.91 33.79 24.33 9.22%
04.04.02 AFIRMADO DE 4" EN INTERIORES (AREAS TACHADAS) M2 417.84 17.49 7,308.02 359.84 6,293.60 - - - 359.84 6,293.60 0.86 58.00 1,014.42 13.88%
04.04.03 AFIRMADO DE 6" PARA LOSA Y VEREDAS M2 658.39 18.85 12,410.65 17.60 331.76 607.00 11,441.95 0.92 624.60 11,773.71 0.95 33.79 636.94 5.13%
04.04.04 BASE COMPACTADA DE H= 0.10m, CON EQUIPO M2 1294.83 6.98 9,037.91 - - 1,294.83 9,037.91 1.00 1,294.83 9,037.91 1.00 - 0.00 0.00%
04.04.05 CONFORMACION DE TERRENO HASTA NIVEL DE SUBRASANTE C/M M2 1389.94 1.41 1,959.82 56.24 79.30 1,333.70 1,880.52 0.96 1,389.94 1,959.82 1.00 - 0.00 0.00%
04.05 ELIMINACION DE MATERIAL EXCEDENTE 103,652.81 - 61,115.39 15,975.49 0.15 - 77,090.89 0.74 - 26,561.93 25.63%
04.05.01 ACARREO INTERNO DE MATERIAL PROCEDENTE DE EXCAVACIONE M3 816.48 14.00 11,430.72 708.92 9,924.88 92.94 1,301.16 0.11 801.86 11,226.04 0.98 14.62 204.68 1.79%
04.05.02 ACARREO INTERNO MATERIAL PROCEDENTE DE DEMOLICIONES M3 866.90 23.79 20,623.55 367.74 8,748.53 28.78 684.68 0.03 396.52 9,433.21 0.46 470.38 11,190.34 54.26%
04.05.03 ELIMINACION DE MATERIAL EXCEDENTE ACUMULADO ACARREAD M3 1412.20 50.70 71,598.54 837.12 42,441.98 275.93 13,989.65 0.20 1,113.05 56,431.64 0.79 299.15 15,166.91 21.18%
05 CONCRETO SIMPLE 100,512.80 - 27,868.25 20,131.39 0.20 - 47,999.64 0.48 - 52,513.16 52.25%
05.01 SOLADOS 3,181.70 - 2,846.37 - - - 2,846.37 0.89 - 335.33 10.54%
05.01.01 SOLADOS CONCRETO f´c= 140kg/cm2 M2 142.04 22.40 3,181.70 127.07 2,846.37 0.00 - - 127.07 2,846.37 0.89 14.97 335.33 10.54%
05.02 SUB CIMIENTOS 14,426.22 - 13,274.34 1,151.88 0.08 - 14,426.22 1.00 - 0.00 0.00%
05.02.01 SUBCIEMIENTO, SUBZAPATAS; MEZCLA 1:12 + 30% P.G. M3 56.49 168.65 9,527.04 49.66 8,375.16 6.83 1,151.88 0.12 56.49 9,527.04 1.00 - 0.00 0.00%
05.02.02 SUBCIMIENTO, SUBZAPATAS, ENCOFRADO Y DESENCOFRADO M2 85.74 57.14 4,899.18 85.74 4,899.18 0.00 - - 85.74 4,899.18 1.00 - 0.00 0.00%
05.03 CIMIENTOS CORRIDOS 21,545.93 - 7,741.61 10,394.53 0.48 - 18,136.14 0.84 - 3,409.79 15.83%
05.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO - HORMIGON 30% PI M3 122.47 175.11 21,445.72 44.21 7,741.61 59.36 10,394.53 0.48 103.57 18,136.14 0.85 18.90 3,309.58 15.43%
05.03.02 CIMIENTOS CORRIDOS, ENCOFRADO Y DESENCOFRADO M2 2.30 43.57 100.21 - - 0.00 - - - - - 2.30 100.21 100.00%
05.04 SOBRECIMIENTO 9,965.01 - 4,005.93 5,131.83 0.51 - 9,137.76 0.92 - 827.25 8.30%
05.04.01 SOBRECIMIENTO, CONCRETO f´c= 175 kg/cm2 M3 7.71 289.62 2,232.97 6.37 1,844.88 1.14 330.17 0.15 7.51 2,175.05 0.97 0.20 57.92 2.59%
05.04.02 SOBRECIMIENTO, MEZCLA 1:8 CEMENTO - HORMIGON + 25% PIEDRA M3 5.70 339.44 1,934.81 - - 4.86 1,649.68 0.85 4.86 1,649.68 0.85 0.84 285.13 14.74%
05.04.03 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 167.26 34.66 5,797.23 62.35 2,161.05 90.94 3,151.98 0.54 153.29 5,313.03 0.92 13.97 484.20 8.35%
05.05 SARDINEL 9,250.63 - - - - - - - - 9,250.63 100.00%
05.05.01 SARDINELES, CONCRETO F´C= 175 KG/CM2. INCLUYE ACABADO M 126.40 60.28 7,619.39 - - 0.00 - - - - - 126.40 7,619.39 100.00%
05.05.02 SARDINELES, ENCOFRADO Y DESENCOFRADO M2 63.82 25.56 1,631.24 - - 0.00 - - - - - 63.82 1,631.24 100.00%
05.06 FALSO PISO 8,867.88 - - 3,453.15 0.39 - 3,453.15 0.39 - 5,414.73 61.06%
05.06.01 ENSANCHE EN FALSO PISO P/TABIQUERIA M3 1.00 197.06 197.06 - - 0.00 - - - - - 1.00 197.06 100.00%
05.06.02 FALSO PISO MEZCLA 1:8 e=4" M2 285.60 30.36 8,670.82 - - 113.74 3,453.15 0.40 113.74 3,453.15 0.40 171.86 5,217.67 60.18%
05.07 POZO PERCOLADOR 96.62 - - - - - - - - 96.62 100.00%
05.07.01 POZO PERCOLADOR, CONCRETO F´C= 175 KG/CM2 M3 0.25 386.49 96.62 - - 0.00 - - - - - 0.25 96.62 100.00%
05.08 LOSA DE CONCRETO MULTIFUNCIONAL 33,178.81 - - - - - - - - 33,178.81 100.00%
05.08.01 LOSA DE CONCRETO F´C= 175 KG/CM2 INCLUYE ENCOFRADO E= 0.15 M2 604.46 54.89 33,178.81 - - 0.00 - - - - - 604.46 33,178.81 100.00%
06 CONCRETO ARMADO 647,857.61 - 388,916.59 107,090.18 0.17 - 496,006.76 0.77 - 151,850.87 23.44%
06.01 CIMIENTO ARMADO 33,524.63 - 33,524.63 - - - 33,524.63 1.00 - 0.00 0.00%
06.01.01 CIMIENTOS ARMADOS, CONCRETO F´C= 210 KG/CM2 M3 60.40 295.91 17,872.96 60.40 17,872.96 0.00 - - 60.40 17,872.96 1.00 - 0.00 0.00%
06.01.02 CIMIENTOS ARMADOS, ENCOFRADO Y DESENCOFRADO M2 111.24 26.95 2,997.92 111.24 2,997.92 0.00 - - 111.24 2,997.92 1.00 - 0.00 0.00%
06.01.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 2387.50 5.30 12,653.75 2,387.50 12,653.75 0.00 - - 2,387.50 12,653.75 1.00 - 0.00 0.00%
06.02 ZAPATAS 18,055.37 - 17,456.36 - - - 17,456.36 0.97 - 599.01 3.32%
06.02.01 ZAPATAS, CONCRETO F´C= 210 KG/CM2 M3 24.86 295.02 7,334.20 23.46 6,921.17 0.00 - - 23.46 6,921.17 0.94 1.40 413.03 5.63%
06.02.02 ZAPATAS, ENCOFRADO Y DESENCOFRADO M2 106.32 65.11 6,922.50 106.32 6,922.50 0.00 - - 106.32 6,922.50 1.00 - 0.00 0.00%
06.02.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 716.73 5.30 3,798.67 681.64 3,612.69 0.00 - - 681.64 3,612.69 0.95 35.09 185.98 4.90%
06.03 VIGAS DE CIMENTACION 13,817.66 - 13,817.66 - - - 13,817.66 1.00 - 0.00 0.00%
06.03.01 VIGAS DE CIMENTACION, CONCRETO F´C= 210 KG/CM2 M3 6.81 337.99 2,301.71 6.81 2,301.71 0.00 - - 6.81 2,301.71 1.00 - 0.00 0.00%
06.03.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO M2 45.44 61.23 2,782.29 45.44 2,782.29 0.00 - - 45.44 2,782.29 1.00 - 0.00 0.00%
06.03.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 1647.86 5.30 8,733.66 1,647.86 8,733.66 0.00 - - 1,647.86 8,733.66 1.00 - 0.00 0.00%
06.04 POZO PERCOLADOR 252.26 - - - - - - - - 252.26 100.00%
06.04.01 POZO PERCOLADOR, CONCRETO F´C= 210 KG/CM2 M3 0.20 365.65 73.13 - - 0.00 - - - - - 0.20 73.13 100.00%
06.04.02 POZO PERCOLADOR, ENCOFRADO Y DESENCOFRADO M2 2.05 60.31 123.64 - - 0.00 - - - - - 2.05 123.64 100.00%
06.04.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 10.47 5.30 55.49 - - 0.00 - - - - - 10.47 55.49 100.00%
06.05 TANQUE SEPTICO 3,400.99 - - - - - - - - 3,400.99 100.00%
06.05.01 TANQUE SEPTICO, CONCRETO F´C= 210 KG/CM2 M3 3.80 365.65 1,389.47 - - 0.00 - - - - - 3.80 1,389.47 100.00%
06.05.02 TANQUE SEPTICO, ENCOFRADO Y DESENCOFRADO M2 22.03 54.10 1,191.82 - - 0.00 - - - - - 22.03 1,191.82 100.00%
06.05.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 154.66 5.30 819.70 - - 0.00 - - - - - 154.66 819.70 100.00%
06.06 SOBRECIMIENTO ARMADO 74,698.70 - 64,750.89 - - - 64,750.89 0.87 - 9,947.81 13.32%
06.06.01 SOBRECIMIENTO ARMADO, CONCRETO F´C= 210 KG/CM2 M3 47.44 405.08 19,217.00 41.62 16,859.43 0.00 - - 41.62 16,859.43 0.88 5.82 2,357.57 12.27%
06.06.02 SOBRECIMIENTO ARMADO, ENCOFRADO Y DESENCOFRADO M2 496.26 57.14 28,356.30 393.28 22,472.02 0.00 - - 393.28 22,472.02 0.79 102.98 5,884.28 20.75%
06.06.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 5118.00 5.30 27,125.40 4,796.12 25,419.44 0.00 - - 4,796.12 25,419.44 0.94 321.88 1,705.96 6.29%
06.07 PLACAS 31,091.71 - 23,758.49 - - - 23,758.49 0.76 - 7,333.22 23.59%
06.07.01 PLACAS, CONCRETO F´C= 210 KG/CM2 C/ADITIVO PLASTIFICANTE ( M3 20.76 458.05 9,509.12 16.44 7,530.34 0.00 - - 16.44 7,530.34 0.79 4.32 1,978.78 20.81%
06.07.02 PLACAS, ENCOFRADO Y DESENCOFRADO CARAVISTA C/ADITIVO M2 207.81 71.89 14,939.46 164.45 11,822.31 0.00 - - 164.45 11,822.31 0.79 43.36 3,117.15 20.87%
06.07.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 1253.42 5.30 6,643.13 831.29 4,405.84 0.00 - - 831.29 4,405.84 0.66 422.13 2,237.29 33.68%
06.08 MURO DE CONTENCION 48,825.52 - 48,825.52 - - - 48,825.52 1.00 - 0.00 0.00%
06.08.01 MURO DE CONTENCION, CONCRETO F´C= 210 KG/CM2 M3 45.07 405.08 18,256.96 45.07 18,256.96 0.00 - - 45.07 18,256.96 1.00 - 0.00 0.00%
06.08.02 MURO DE CONTENCION, ENCOFRADO Y DESENCOFRADO M2 245.07 57.14 14,003.30 245.07 14,003.30 0.00 - - 245.07 14,003.30 1.00 - 0.00 0.00%
06.08.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 3125.52 5.30 16,565.26 3,125.52 16,565.26 0.00 - - 3,125.52 16,565.26 1.00 - 0.00 0.00%
06.09 COLUMNAS 156,426.83 - 95,263.41 38,695.33 0.25 - 133,958.74 0.86 - 22,468.11 14.36%
06.09.01 COLUMNAS, CONCRETO F´C= 210 KG/CM2 C/ADITIVO PLASTIFICANT M3 40.42 452.88 18,305.41 19.60 8,876.45 20.82 9,428.96 0.52 40.42 18,305.41 1.00 - 0.00 0.00%
06.09.02 COLUMNAS, CONCRETO F´C= 210 KG/CM2 M3 39.51 426.76 16,861.29 7.54 3,217.77 11.21 4,783.98 0.28 18.75 8,001.75 0.47 20.76 8,859.54 52.54%
06.09.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA C/ADITIV M2 372.48 72.58 27,034.60 180.88 13,128.27 191.60 13,906.33 0.51 372.48 27,034.60 1.00 - 0.00 0.00%
06.09.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 438.68 56.55 24,807.35 87.20 4,931.16 129.92 7,346.98 0.30 217.12 12,278.14 0.49 221.56 12,529.22 50.51%
06.09.05 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 13097.77 5.30 69,418.18 12,284.86 65,109.76 609.26 3,229.08 0.05 12,894.12 68,338.84 0.98 203.65 1,079.35 1.55%
06.10 VIGAS 124,061.56 - 32,562.28 39,486.67 0.32 - 72,048.94 0.58 - 52,012.61 41.92%
06.10.01 VIGAS, CONCRETO F´C= 210 KG/CM2 C/ADITIVO PLASTIFICANTE (CA M3 46.62 485.92 22,653.59 12.09 5,874.77 23.31 11,326.80 0.50 35.40 17,201.57 0.76 11.22 5,452.02 24.07%
06.10.02 VIGAS, CONCRETO F´C= 210 KG/CM2 M3 21.52 472.77 10,174.01 1.02 482.23 2.76 1,304.85 0.13 3.78 1,787.07 0.18 17.74 8,386.94 82.43%
06.10.03 VIGAS, ENCOFRADO Y DESENCOFRADO CARAVISTA C/ADITIVO M2 291.72 93.15 27,173.72 75.25 7,009.54 145.86 13,586.86 0.50 221.11 20,596.40 0.76 70.61 6,577.32 24.20%
06.10.04 VIGAS, ENCOFRADO Y DESENCOFRADO M2 259.59 65.20 16,925.27 10.86 708.07 32.88 2,143.78 0.13 43.74 2,851.85 0.17 215.85 14,073.42 83.15%
06.10.05 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 8893.39 5.30 47,134.97 3,488.24 18,487.67 2098.94 11,124.38 0.24 5,587.18 29,612.05 0.63 3,306.21 17,522.91 37.18%
06.11 LOSA MACIZA 1,144.79 - - - - - - - - 1,144.79 100.00%
06.11.01 LOSA MACIZA, CONCRETO F´C= 210 KG/CM2 M3 1.20 349.22 419.06 - - 0.00 - - - - - 1.20 419.06 100.00%
06.11.02 LOSA MACIZA, ENCOFRADO Y DESENCOFRADO M2 5.90 56.53 333.53 - - 0.00 - - - - - 5.90 333.53 100.00%
06.11.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 74.00 5.30 392.20 - - 0.00 - - - - - 74.00 392.20 100.00%
06.12 LOSAS ALIGERADAS 70,904.20 - 21,935.66 26,838.09 0.38 - 48,773.75 0.69 - 22,130.46 31.21%
06.12.01 LOSA ALIGERADA, CONCRETO F´C= 210 KG/CM2 M3 39.17 332.74 13,033.43 11.74 3,906.37 16.43 5,466.92 0.42 28.17 9,373.29 0.72 11.00 3,660.14 28.08%
06.12.02 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 554.49 44.21 24,514.00 134.13 5,929.89 241.43 10,673.62 0.44 375.56 16,603.51 0.68 178.93 7,910.50 32.27%
06.12.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 3493.90 5.30 18,517.67 1,608.31 8,524.04 804.15 4,262.00 0.23 2,412.46 12,786.04 0.69 1,081.44 5,731.63 30.95%
06.12.04 LOSA ALIGERADA, LADRILLO HUECO DE ARCILLA 0.30 X 0.30 X 0.15 U 4637.22 3.20 14,839.10 1,117.30 3,575.36 2011.11 6,435.55 0.43 3,128.41 10,010.91 0.67 1,508.81 4,828.19 32.54%
06.13 ESCALERAS 3,445.33 - - - - - - - - 3,445.33 100.00%
06.13.01 ESCALERAS, CONCRETO F´C= 210 KG/CM2 M3 2.85 464.02 1,322.46 - - 0.00 - - - - - 2.85 1,322.46 100.00%
06.13.02 ESCALERAS, ENCOFRADO Y DESENCOFRADO M2 19.65 86.57 1,701.10 - - 0.00 - - - - - 19.65 1,701.10 100.00%
06.13.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 79.58 5.30 421.77 - - 0.00 - - - - - 79.58 421.77 100.00%
06.14 TANQUE CISTERNA 39,091.78 - 37,021.69 2,070.09 0.05 - 39,091.78 1.00 - 0.00 0.00%
06.14.01 TANQUE CISTERNA, CONCRETO F´C= 280 KG/CM2 M3 32.80 494.78 16,228.78 30.30 14,991.83 2.50 1,236.95 0.08 32.80 16,228.78 1.00 - 0.00 0.00%
06.14.02 TANQUE CISTERNA, ENCOFRADO Y DESENCOFRADO M2 129.00 54.10 6,978.90 113.60 6,145.76 15.40 833.14 0.12 129.00 6,978.90 1.00 - 0.00 0.00%
06.14.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 2997.00 5.30 15,884.10 2,997.00 15,884.10 0.00 - - 2,997.00 15,884.10 1.00 - 0.00 0.00%
06.15 TANQUE ELEVADO 11,060.80 - - - - - - - - 11,060.80 100.00%
06.15.01 TANQUE ELEVADO, CONCRETO F´C= 280 KG/CM2 M3 7.80 494.78 3,859.28 - - 0.00 - - - - - 7.80 3,859.28 100.00%
06.15.02 TANQUE ELEVADO, ENCOFRADO Y DESENCOFRADO M2 40.20 75.12 3,019.82 - - 0.00 - - - - - 40.20 3,019.82 100.00%
06.15.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 789.00 5.30 4,181.70 - - 0.00 - - - - - 789.00 4,181.70 100.00%
06.16 GRADERIAS DE CONCRETO 11,949.33 - - - - - - - - 11,949.33 100.00%
06.16.01 GRADERIAS DE CONCRETO, CONCRETO F´C= 210 KG/CM2 M3 7.64 464.76 3,550.77 - - 0.00 - - - - - 7.64 3,550.77 100.00%
06.16.02 GRADERIAS DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 81.37 75.12 6,112.51 - - 0.00 - - - - - 81.37 6,112.51 100.00%
06.16.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 431.33 5.30 2,286.05 - - 0.00 - - - - - 431.33 2,286.05 100.00%
06.17 GRADAS 672.26 - - - - - - - - 672.26 100.00%
06.17.01 GRADAS, CONCRETO F´C= 175 KG/CM2 M3 1.56 286.38 446.75 - - 0.00 - - - - - 1.56 446.75 100.00%
06.17.02 GRADAS, ENCOFRADO Y DESENCOFRADO M2 2.00 34.05 68.10 - - 0.00 - - - - - 2.00 68.10 100.00%
06.17.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 29.70 5.30 157.41 - - 0.00 - - - - - 29.70 157.41 100.00%
06.18 ASTA DE BANDERA 685.52 - - - - - - - - 685.52 100.00%
06.18.01 ASTA DE BANDERA, CONCRETO F´C= 175 KG/CM2 C/ADITIVO PLAST M3 0.80 328.58 262.86 - - 0.00 - - - - - 0.80 262.86 100.00%
06.18.02 ASTA DE BANDERA, ENCOFRADO Y DESENCOFRADO CARAVISTA CO M2 4.10 72.58 297.58 - - 0.00 - - - - - 4.10 297.58 100.00%
06.18.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 23.60 5.30 125.08 - - 0.00 - - - - - 23.60 125.08 100.00%
06.12 SARDINEL SUMERGIDO Y PERALTADO 4,748.37 - - - - - - - - 4,748.37 100.00%
06.12.01 SARDINEL PERALTADO, CONCRETO F´C= 175 KG/CM2 C/ADITIVO PL M3 3.91 328.58 1,284.75 - - 0.00 - - - - - 3.91 1,284.75 100.00%
06.12.02 SARDINEL PERALTADO, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 41.37 72.58 3,002.63 - - 0.00 - - - - - 41.37 3,002.63 100.00%
06.12.03 ACERO CORRUGADO Fy= 4200 KG/CM2 GRADO 60 KG 86.98 5.30 460.99 - - 0.00 - - - - - 86.98 460.99 100.00%
07 ALBAÑILERIA 71,204.10 - 29,813.00 27,644.99 0.39 - 57,457.98 0.81 - 13,746.12 19.31%
07.01 MUROS DE LADRILLO KK-CABEZA-30%VACIO-18 HUECOS-MEZCLA 1:4M2 314.33 108.53 34,114.23 163.85 17,782.64 150.48 16,331.59 0.48 314.33 34,114.23 1.00 - 0.00 0.00%
07.02 MUROS DE LADRILLO KK-SOGA-30%VACIO-18 HUECOS-MEZCLA 1:4 XM2 534.13 65.60 35,038.93 178.76 11,726.66 162.32 10,648.19 0.30 341.08 22,374.85 0.64 193.05 12,664.08 36.14%
07.03 MURO DE LADRILLO DE CANTO C/A 1:4 X 1.5cm M2 3.73 49.64 185.16 - - 0.00 - - - - - 3.73 185.16 100.00%
07.04 ALAMBRE #8 REFUERZO HORIZONTAL KG 363.70 5.13 1,865.78 59.20 303.70 129.67 665.21 0.36 188.87 968.90 0.52 174.83 896.88 48.07%
08 REVOQUES Y REVESTIMIENTOS 93,823.87 - - 14,791.35 0.16 - 14,791.35 0.16 - 79,032.52 84.23%
08.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO, MORTERO C:A 1:5 M2 140.26 21.05 2,952.47 - - 0.00 - - - - - 140.26 2,952.47 100.00%
08.02 TARRAJEO EN MURO INTERIOR Y EXTERIOR. MORTERO C/A 1:4 M2 2188.96 23.48 51,396.78 - - 411.64 9,665.31 0.19 411.64 9,665.31 0.19 1,777.32 41,731.47 81.19%
08.03 TARRAJEO DE COLUMNAS, MORTERO C/A 1:4 M2 262.52 34.22 8,983.43 - - 12.87 440.41 0.05 12.87 440.41 0.05 249.65 8,543.02 95.10%
08.04 TARRAJEO DE VIGAS, MORTERO C/A 1:4 M2 145.55 40.98 5,964.64 - - 9.15 374.97 0.06 9.15 374.97 0.06 136.40 5,589.67 93.71%
08.05 TARRAJEO EN ESTRUCTURAS ALTAS ALT. PROM.=10M M2 29.70 34.32 1,019.30 - - 0.00 - - - - - 29.70 1,019.30 100.00%
08.06 TARRAJEO CON IMPERMEABILIZANTE, MORTERO C/A 1:3 M2 184.62 30.37 5,606.91 - - 123.10 3,738.55 0.67 123.10 3,738.55 0.67 61.52 1,868.36 33.32%
08.07 VESTIDURA DE DERRAMES (1:5) M 218.66 12.33 2,696.08 - - 46.40 572.11 0.21 46.40 572.11 0.21 172.26 2,123.97 78.78%
08.08 VESTIDURA DE DERRAMES CON BORDES BOLEADOS M 3.86 19.93 76.93 - - 0.00 - - - - - 3.86 76.93 100.00%
08.09 VESTIDURA DE FONDO DE ESCALERA M2 12.32 37.57 462.86 - - 0.00 - - - - - 12.32 462.86 100.00%
08.10 REVESTIMIENTO CON CEMENTO PULIDO DE PASO Y CONTRAPASO M2 94.19 33.94 3,196.81 - - 0.00 - - - - - 94.19 3,196.81 100.00%
08.11 REVESTIMIENTO EN PIEDRA LAJA M2 26.83 54.39 1,459.28 - - 0.00 - - - - - 26.83 1,459.28 100.00%
08.12 PIZARRA CEMENTO 5.00 X 1.20 SIN TIZERO U 5.00 174.60 873.00 - - 0.00 - - - - - 5.00 873.00 100.00%
08.13 BRUÑAS SEGÚN DETALLE (1 X 1) M 1246.30 7.33 9,135.38 - - 0.00 - - - - - 1,246.30 9,135.38 100.00%
09 CIELORRASOS 20,628.10 - - 5,024.51 0.24 - 5,024.51 0.24 - 15,603.59 75.64%
09.01 CIELO RASO CON MEZCLA C:A 1:5 M2 550.67 37.46 20,628.10 - - 134.13 5,024.51 0.24 134.13 5,024.51 0.24 416.54 15,603.59 75.64%
10 PISOS Y PAVIMENTOS 143,735.51 - - 3,041.41 0.02 - 3,041.41 0.02 - 140,694.10 97.88%
10.01 CONTRAPISOS 13,045.38 - - 3,041.41 0.23 - 3,041.41 0.23 - 10,003.97 76.69%
10.01.01 CONTRAPISO DE 48 mm M2 487.86 26.74 13,045.38 - - 113.74 3,041.41 0.23 113.74 3,041.41 0.23 374.12 10,003.97 76.69%
10.02 PISOS 47,108.30 - - - - - - - - 47,108.30 100.00%
10.02.01 PISO DE CERAMICA DE 0.30X0.30 m - COLOR CLARO M2 32.90 59.06 1,943.07 - - 0.00 - - - - - 32.90 1,943.07 100.00%
10.02.02 PISO DE CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR M2 191.76 31.19 5,980.99 - - 0.00 - - - - - 191.76 5,980.99 100.00%
10.02.03 PISO DE CERAMKICA 0.40X0.40 m - CRETA GRIS - ALTO TRANSITO M2 454.96 59.06 26,869.94 - - 0.00 - - - - - 454.96 26,869.94 100.00%
10.02.04 PISO DE ADOQUINES DE CONCRETO 10X20X8 cm (COLOCACION Y C M2 124.50 98.91 12,314.30 - - 0.00 - - - - - 124.50 12,314.30 100.00%
10.03 SARDINEL 2,446.66 - - - - - - - - 2,446.66 100.00%
10.03.01 SARDINEL h=0.50, CONCRETO DE F'C=175 KG/CM2 M 20.60 90.20 1,858.12 - - 0.00 - - - - - 20.60 1,858.12 100.00%
10.03.02 SARDINEL, ENCOFRADO Y DESENCOFRADO M2 10.30 57.14 588.54 - - 0.00 - - - - - 10.30 588.54 100.00%
10.04 VEREDAS 80,021.35 - - - - - - - - 80,021.35 100.00%
10.04.01 VEREDA, CONCRETO DE F'C=175 KG/CM2 E=4" MAS ACABADO FRO M2 1319.43 58.42 77,081.10 - - 0.00 - - - - - 1,319.43 77,081.10 100.00%
10.04.02 VEREDA, ENCOFRADO Y DESENCOFRADO M2 159.97 18.38 2,940.25 - - 0.00 - - - - - 159.97 2,940.25 100.00%
10.05 VARIOS 1,113.82 - - - - - - - - 1,113.82 100.00%
10.05.01 CANALETAS 1/2" CAÑA EN CIRCULACION M 31.70 15.59 494.20 - - 0.00 - - - - - 31.70 494.20 100.00%
10.05.02 CANALETA MEDIA CAÑA 2" EN COBERTURA M 13.40 18.93 253.66 - - 0.00 - - - - - 13.40 253.66 100.00%
10.05.03 ANCLAJE DE CONCRETO F'C=175 KG/CM2 PARA POSTES Y ARCOS M3 1.22 299.97 365.96 - - 0.00 - - - - - 1.22 365.96 100.00%
11 CONTRAZOCLAOS 8,132.31 - - - - - - - - 8,132.31 100.00%
11.01 CONTRAZOCALO DE CERAMICA GRIS DE 10X40 cm M 245.80 12.85 3,158.53 - - 0.00 - - - - - 245.80 3,158.53 100.00%
11.02 CONTRAZOCALO SIN COLOREAR H=20 cm MZ 1:2 = 1.5cm M 247.23 12.03 2,974.18 - - 0.00 - - - - - 247.23 2,974.18 100.00%
11.03 CONTRAZOCALO SIN COLOREAR H=30 cm MZ 1:2 = 1.5cm M 113.92 14.50 1,651.84 - - 0.00 - - - - - 113.92 1,651.84 100.00%
11.04 CONTRAZOCALO RECTOS EN ESCALERA H= 20 cm E= 1.5cm M 18.40 18.90 347.76 - - 0.00 - - - - - 18.40 347.76 100.00%
12 ZOCALOS 10,122.13 - - - - - - - - 10,122.13 100.00%
12.01 ZOCALO DE MAYOLICA DE 20X30(1a.) M2 124.98 80.99 10,122.13 - - 0.00 - - - - - 124.98 10,122.13 100.00%
13 CUBIERTAS 25,919.25 - - - - - - - - 25,919.25 100.00%
13.01 CUBIERTA LADRILLO PASTELERO ASENTADO CON BARRO E=2" C/F M2 317.96 40.50 12,877.38 - - 0.00 - - - - - 317.96 12,877.38 100.00%
13.02 IMPERMEABILIZACION DE TECHOS CON PINTURA ASFALTICA M2 309.16 6.75 2,086.83 - - 0.00 - - - - - 309.16 2,086.83 100.00%
13.03 PROVISION E INSTALACON DE CUBIERTA PARA TRIBUNAS M 48.00 228.23 10,955.04 - - 0.00 - - - - - 48.00 10,955.04 100.00%
14 CARPINTERIA DE MADERA 17,632.29 - - - - - - - - 17,632.29 100.00%
14.01 PUERTAS C.N. CON TABLEROS DE MADERA, 01 HOJA M2 21.35 364.37 7,779.30 - - 0.00 - - - - - 21.35 7,779.30 100.00%
14.02 PUERTA DE MADERA MACHIHEMBRADA SIMPLE S/ DETALLE M2 7.77 293.26 2,278.63 - - 0.00 - - - - - 7.77 2,278.63 100.00%
14.03 PUERTA C.N. C/TRIPLAY 9mm M2 7.11 236.43 1,681.02 - - 0.00 - - - - - 7.11 1,681.02 100.00%
14.04 PUERTA DE MADERA CEDRO + TRIPLAY CONTRAPLACADA SEGÚN M2 7.68 209.29 1,607.35 - - 0.00 - - - - - 7.68 1,607.35 100.00%
14.05 REJILLA DE MADERA + TRIPLAY CONTRAPLACADA SEGÚN DETALL M2 2.24 108.04 242.01 - - 0.00 - - - - - 2.24 242.01 100.00%
14.06 TICERO DE MADERA CEDRO, BARNIZADA I=5.00 m U 5.00 144.10 720.50 - - 0.00 - - - - - 5.00 720.50 100.00%
14.07 TABIQUERIA DRYWALL E=13CM C/RELLENO ACUSTICO C/PLANCHA 5 M2 34.83 95.42 3,323.48 - - 0.00 - - - - - 34.83 3,323.48 100.00%
15 CARPINTERIA METALICA 44,457.47 - - - - - - - - 44,457.47 100.00%
15.01 PROV. E INSTALACION DE PORTONES DE FIERRO SEGÚN DETALLE(L= U 1.00 3200.00 3,200.00 - - 0.00 - - - - - 1.00 3,200.00 100.00%
15.02 PROV. E INSTALACION DE PORTONES DE FIERRO SEGÚN DETALLE(L= U 1.00 1100.00 1,100.00 - - 0.00 - - - - - 1.00 1,100.00 100.00%
15.03 PUERTA METALICA CUARTO DE MAQUINAS(2.05X0.70) U 1.00 261.14 261.14 - - 0.00 - - - - - 1.00 261.14 100.00%
15.04 VENTANA DE FIERRO TIPO REJA M2 1.10 95.19 104.71 - - 0.00 - - - - - 1.10 104.71 100.00%
15.05 ASTA DE BANDERA SEGÚN DETALLE EN PLANOS U 1.00 560.00 560.00 - - 0.00 - - - - - 1.00 560.00 100.00%
15.06 CERCO METALICO SEGÚN DETALLE EN PLANOS M 56.96 250.00 14,240.00 - - 0.00 - - - - - 56.96 14,240.00 100.00%
15.07 PASAMANO DE TUBO DE F.G D=2", EN ESCALERA M 13.28 95.30 1,265.58 - - 0.00 - - - - - 13.28 1,265.58 100.00%
15.08 BARANDA METALICA D =2" F.G. M 21.00 246.64 5,179.44 - - 0.00 - - - - - 21.00 5,179.44 100.00%
15.09 ESCALERA DE GATO DE F.G. D=1-1/2" Y D=1" M 10.60 146.75 1,555.55 - - 0.00 - - - - - 10.60 1,555.55 100.00%
15.10 ESCALERA DE GATO EMPOTRADA DE ALUMINIO PARA T. CISTERNA U 1.00 294.13 294.13 - - 0.00 - - - - - 1.00 294.13 100.00%
15.11 CANTONERA DE FIERRO ESTRIADO EN ESCALERA M 38.00 43.00 1,634.00 - - 0.00 - - - - - 38.00 1,634.00 100.00%
15.12 SUMINISTRO E INSTALACION DE ANCLAJE PARA POSTE DE VOLEY U 2.00 51.14 102.28 - - 0.00 - - - - - 2.00 102.28 100.00%
15.13 SUMINISTRO E INSTALACION DE ANCLAJE PARA ARCO U 8.00 29.84 238.72 - - 0.00 - - - - - 8.00 238.72 100.00%
15.14 SUMINISTRO E INSTALACION DE ARCO CON TABLERO DE BASQUET U 2.00 1538.41 3,076.82 - - 0.00 - - - - - 2.00 3,076.82 100.00%
15.15 SUMINISTRO E INSTALACION DE POSTES DE VOLEY U 2.00 275.05 550.10 - - 0.00 - - - - - 2.00 550.10 100.00%
15.16 ESTRUCTURA METALICA CON PLANCHA DE POLICARBONATO M 31.70 350.00 11,095.00 - - 0.00 - - - - - 31.70 11,095.00 100.00%
16 CERRAJERIA 4,360.30 - - - - - - - - 4,360.30 100.00%
16.01 BISAGRA DE ALUMINIO DE 4" PESADA EN PUERTA PZA 52.00 33.10 1,721.20 - - 0.00 - - - - - 52.00 1,721.20 100.00%
16.02 BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2" PZA 4.00 20.39 81.56 - - 0.00 - - - - - 4.00 81.56 100.00%
16.03 BISAGRA CAPUCHINA DE 3" X 3" PZA 12.00 16.15 193.80 - - 0.00 - - - - - 12.00 193.80 100.00%
16.04 BISAGRA CAPUCHINA DE 2 1/2" X 2 1/2" PZA 24.00 25.53 612.72 - - 0.00 - - - - - 24.00 612.72 100.00%
16.05 CERRADURA DOS GOLPES EN PUERTA CON TIRADOR PZA 15.00 86.40 1,296.00 - - 0.00 - - - - - 15.00 1,296.00 100.00%
16.06 CERROJO DE FIERRO 2" U 8.00 17.01 136.08 - - 0.00 - - - - - 8.00 136.08 100.00%
16.07 CANDADO TIPO FORTE DE 60 mm INCLUYENDO ALDABAS PZA 2.00 61.19 122.38 - - 0.00 - - - - - 2.00 122.38 100.00%
16.08 MANIJA DE BRONCE 4" PARA PUERTAS U 18.00 10.92 196.56 - - 0.00 - - - - - 18.00 196.56 100.00%
17 VIDRIOS, CRISTALES Y SIMILARES 24,186.84 - - - - - - - - 24,186.84 100.00%
17.01 SISTEMA PIVOT VIDRIO TEMPLADO INCOLORO 6MM INC. ACCESORI M2 127.68 149.38 19,072.84 - - 0.00 - - - - - 127.68 19,072.84 100.00%
17.02 VIDRIOS SEMIDOBLES, TRANSPARENTES, INCLUYE SUMINISTRO Y P2 1276.86 3.31 4,226.41 - - 0.00 - - - - - 1,276.86 4,226.41 100.00%
17.03 VIDRIOS SEMIDOBLES, COLOR GRIS, INCLUYE SUMINISTRO Y COLO P2 259.53 3.42 887.59 - - 0.00 - - - - - 259.53 887.59 100.00%
18 PINTURA 51,421.41 - - - - - - - - 51,421.41 100.00%
18.01 PINTURA LATEX 2 MANOS EN CIELO RASO Y VIGAS M2 661.72 10.28 6,802.48 - - 0.00 - - - - - 661.72 6,802.48 100.00%
18.02 PINTURA LATEX 2 MANOS EN MUROS Y COLUMNAS M2 2342.61 9.15 21,434.88 - - 0.00 - - - - - 2,342.61 21,434.88 100.00%
18.03 PINTURA LATEX 2 MANOS + IMPRIM. RN RDTRUCT. ALTAS ALT. PRO M2 236.70 13.92 3,294.86 - - 0.00 - - - - - 236.70 3,294.86 100.00%
18.04 PINTURA C/BASE ZINCROMATO Y ESMALTE EPOXICO EN CARPINTER M2 6.78 24.72 167.60 - - 0.00 - - - - - 6.78 167.60 100.00%
18.05 PINTURA ESMALTE EN CARPINTERIA METALICA M 217.11 10.86 2,357.81 - - 0.00 - - - - - 217.11 2,357.81 100.00%
18.06 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CONCRETO H= M 374.89 9.52 3,568.95 - - 0.00 - - - - - 374.89 3,568.95 100.00%
18.07 SELLADO DE CONCRETO EXPUESTO M2 664.20 6.07 4,031.69 - - 0.00 - - - - - 664.20 4,031.69 100.00%
18.08 PINTURA PARA PIZARRA CON 2 MANOS M2 30.00 40.34 1,210.20 - - 0.00 - - - - - 30.00 1,210.20 100.00%
18.09 PINTURA BARNIZ EN CARPINTERIA DE MADERA M2 58.43 18.81 1,099.07 - - 0.00 - - - - - 58.43 1,099.07 100.00%
18.10 PINTURA DEMARCATORIA EN LOSA DEPORTIVA M 336.81 2.43 818.45 - - 0.00 - - - - - 336.81 818.45 100.00%
18.11 PINTURA DE AREAS CERRADAS M2 582.56 10.45 6,087.75 - - 0.00 - - - - - 582.56 6,087.75 100.00%
18.12 PINTURA EN TRIBUNAS M2 67.53 8.11 547.67 - - 0.00 - - - - - 67.53 547.67 100.00%
19 VARIOS, LIMPIEZA Y JARDINERIA 29,414.93 - - - - - - - - 29,414.93 100.00%
19.01 LIMPIEZA PERMANENTE DE LA OBRA M2 384.52 2.68 1,030.51 - - 0.00 - - - - - 384.52 1,030.51 100.00%
19.02 JUNTA DE DILATACION CON ESPUMA PLASTICA + JEBE MICROPORO M 126.49 16.93 2,141.48 - - 0.00 - - - - - 126.49 2,141.48 100.00%
19.03 JUNTA DE DILATACION EN COBERTURA PASTELERO CON MORTERO M 143.58 3.61 518.32 - - 0.00 - - - - - 143.58 518.32 100.00%
19.04 JUNTAS CON MORTERO ASFALTICO E=1" M 283.20 6.61 1,871.95 - - 0.00 - - - - - 283.20 1,871.95 100.00%
19.05 JUNTA DE DILATACION CON TECNOPORT E=1" M 2.80 8.29 23.21 - - 0.00 - - - - - 2.80 23.21 100.00%
19.06 JUNTAS TIPO J1 M 380.00 8.52 3,237.60 - - 0.00 - - - - - 380.00 3,237.60 100.00%
19.07 JUNTAS TIPO J2 M 57.00 6.80 387.60 - - 0.00 - - - - - 57.00 387.60 100.00%
19.08 SELLADO DE JUNTA CON SILICONA E=1.5 cm EN VENTANAS M 282.82 9.52 2,692.45 - - 0.00 - - - - - 282.82 2,692.45 100.00%
19.09 SUMINISTRO DE PELOTAS DE FULBITO, BASQUET Y VOLEY, NET Y GLB 1.00 1047.47 1,047.47 - - 0.00 - - - - - 1.00 1,047.47 100.00%
19.10 GARGOLA DE CONCRETO TERMINADA S/DISEÑO U 5.00 85.79 428.95 - - 0.00 - - - - - 5.00 428.95 100.00%
19.11 SEMBRADO DE GRASS Y FLORESTACION M2 544.20 22.93 12,478.51 - - 0.00 - - - - - 544.20 12,478.51 100.00%
19.12 ARBORIZACION U 22.00 48.04 1,056.88 - - 0.00 - - - - - 22.00 1,056.88 100.00%
19.13 REUBICACION DE CERCO METALICO EN TANQUE SEPTICO GLB 1.00 2500.00 2,500.00 - - 0.00 - - - - - 1.00 2,500.00 100.00%
20 MOBILIARIO URBANO 15,957.00 - - - - - - - - 15,957.00 100.00%
20.01 BANCAS DE MADERA CON RESPALDAR Y APOYO TIPO COLONIAL U 8.00 724.05 5,792.40 - - 0.00 - - - - - 8.00 5,792.40 100.00%
20.02 BOTADERO DE BASURA METALICO U 10.00 191.46 1,914.60 - - 0.00 - - - - - 10.00 1,914.60 100.00%
20.03 PERGOLA DE MADERA SEGÚN DETALLE EN PLANOS U 1.00 8250.00 8,250.00 - - 0.00 - - - - - 1.00 8,250.00 100.00%
21 APARATOS Y ACCESORIOS SANITARIOS 8,977.59 - - - - - - - - 8,977.59 100.00%
21.01 INODORO TANQUE BAJO BLANCO/BABY PZA 2.00 264.75 529.50 - - 0.00 - - - - - 2.00 529.50 100.00%
21.02 INODORO TANQUE BAJO ADULTO (NACIONAL BLANCO) PZA 7.00 323.73 2,266.11 - - 0.00 - - - - - 7.00 2,266.11 100.00%
21.03 LAVATORIO DE LOSA BLANCA DE PRIMERA, INCLUYE ACCESORIOS PZA 2.00 196.06 392.12 - - 0.00 - - - - - 2.00 392.12 100.00%
21.04 URINARIO PICO DE LORO DE LOSA VITRIFICADA PZA 3.00 236.78 710.34 - - 0.00 - - - - - 3.00 710.34 100.00%
21.05 BEBEDERO CORRIDO DE CONCRETO REVESTIDO C/CERAMICA 1.90 X M 1.90 382.09 725.97 - - 0.00 - - - - - 1.90 725.97 100.00%
21.06 BEBEDERO CORRIDO DE CONCRETO REVESTIDO C/CERAMICA 3.60 X M 3.60 747.93 2,692.55 - - 0.00 - - - - - 3.60 2,692.55 100.00%
21.07 CONFORMACION DE DUCHA SARDINEL ALT.= 0.40m U 1.00 1255.13 1,255.13 - - 0.00 - - - - - 1.00 1,255.13 100.00%
21.08 DUCHAS CROMADAS DE CABEZA GIRATORIA Y LLAVE PZA 1.00 47.98 47.98 - - 0.00 - - - - - 1.00 47.98 100.00%
21.09 JABONERA DE CERAMICA U 1.00 36.41 36.41 - - 0.00 - - - - - 1.00 36.41 100.00%
21.10 TOALLERA C/SOPORTE DE LOSA Y BARRA PLASTICA, COLOR BLAN U 1.00 25.11 25.11 - - 0.00 - - - - - 1.00 25.11 100.00%
21.11 PAPELERA DE LOSA Y BARRA PLASTICA COLOR BLANCO U 9.00 32.93 296.37 - - 0.00 - - - - - 9.00 296.37 100.00%
22 SISTEMA DE DESAGUE 20,114.27 - - 12,505.50 0.62 - 12,505.50 0.62 - 7,608.76 37.83%
22.01 SALIDAS DE DESAGUE 1,924.01 - - - - - - - - 1,924.01 100.00%
22.01.01 SALIDAS DE PVC SAL PARA DESAGUE DE 2" PTO 14.00 66.68 933.52 - - 0.00 - - - - - 14.00 933.52 100.00%
22.01.02 SALIDAS DE PVC SAL PARA DESAGUE DE 4" PTO 9.00 80.67 726.03 - - 0.00 - - - - - 9.00 726.03 100.00%
22.01.03 SALIDAS PARA VENTILACION PVC SAL DE 4" PTO 2.00 132.23 264.46 - - 0.00 - - - - - 2.00 264.46 100.00%
22.02 REDES DE DERIVACION Y COLECTORAS 14,895.14 - - 12,505.50 0.84 - 12,505.50 0.84 - 2,389.63 16.04%
22.02.01 EXCAVACION DE ZANJA MANUAL H=0.80m A=0.60m M2 38.30 17.51 670.63 - - 25.30 443.00 0.66 25.30 443.00 0.66 13.00 227.63 33.94%
22.02.02 EXCAVACION DE ZANJA MANUAL H=0.65m A=0.40m M2 155.77 14.00 2,180.78 - - 155.77 2,180.78 1.00 155.77 2,180.78 1.00 - 0.00 0.00%
22.02.03 REFINE Y NIVELACION EN TERRENO NORMAL M2 194.07 4.67 906.31 - - 181.07 845.60 0.93 181.07 845.60 0.93 13.00 60.71 6.70%
22.02.04 CAMA DE ARENA PARA APOYO DE TUBERIA M2 194.07 6.35 1,232.34 - - 181.07 1,149.79 0.93 181.07 1,149.79 0.93 13.00 82.55 6.70%
22.02.05 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO M2 194.07 17.20 3,338.00 - - 181.07 3,114.40 0.93 181.07 3,114.40 0.93 13.00 223.60 6.70%
22.02.06 ELIMINACION DE MATERIAL EXCEDENTE MANUAL M3 37.66 25.55 962.21 - - 36.68 937.17 0.97 36.68 937.17 0.97 0.98 25.04 2.60%
22.02.07 TUBERIA PVC-SAL 2" M 33.30 26.85 894.11 - - 5.60 150.36 0.17 5.60 150.36 0.17 27.70 743.75 83.18%
22.02.08 TUBERIA PVC- SAL 4" M 134.94 34.91 4,710.76 - - 105.54 3,684.40 0.78 105.54 3,684.40 0.78 29.40 1,026.35 21.79%
22.03 ACCESORIOS DE REDES 1,340.96 - - - - - - - - 1,340.96 100.00%
22.03.01 YEE PVC SAP 2" UND 6.00 5.28 31.68 - - 0.00 - - - - - 6.00 31.68 100.00%
22.03.02 YEE PVC SAP 4" X 2" UND 5.00 9.53 47.65 - - 0.00 - - - - - 5.00 47.65 100.00%
22.03.03 TEE PVC SAP 2" UND 2.00 5.28 10.56 - - 0.00 - - - - - 2.00 10.56 100.00%
22.03.04 TEE PVC SAP 4" UND 11.00 7.80 85.80 - - 0.00 - - - - - 11.00 85.80 100.00%
22.03.05 CODO PVC SAL 2" X 45° UND 3.00 4.28 12.84 - - 0.00 - - - - - 3.00 12.84 100.00%
22.03.06 CODO PVC SAL 4" X 45° UND 1.00 5.78 5.78 - - 0.00 - - - - - 1.00 5.78 100.00%
22.03.07 CODO PVC SAL 4" X 90° UND 3.00 4.41 13.23 - - 0.00 - - - - - 3.00 13.23 100.00%
22.03.08 CODO PVC SAL 2" X 90° UND 16.00 3.20 51.20 - - 0.00 - - - - - 16.00 51.20 100.00%
22.03.09 TRAMPA "P" DE PVC SAL PARA DESAGUE DE 2" UND 3.00 6.58 19.74 - - 0.00 - - - - - 3.00 19.74 100.00%
22.03.10 SUMINISTRO Y COLOCACION REGISTRO DE BRONCE 2" UND 4.00 46.87 187.48 - - 0.00 - - - - - 4.00 187.48 100.00%
22.03.11 SOMBRERO DE VENTILACION DE 4" UND 2.00 4.00 8.00 - - 0.00 - - - - - 2.00 8.00 100.00%
22.03.12 INSTALACION DE ACCESORIOS DE PVC SAL UND 49.00 16.28 797.72 - - 0.00 - - - - - 49.00 797.72 100.00%
22.03.13 INSTALACION DE ACCESORIOS DE BRONCE UND 4.00 17.32 69.28 - - 0.00 - - - - - 4.00 69.28 100.00%
22.04 CAMARAS DE INSPECCION 1,954.16 - - - - - - - - 1,954.16 100.00%
22.04.01 SUMINISTRO E INSTLACION DE REJILLA MOVIBLE PARA SUMIDERO UND 2.00 61.87 123.74 - - 0.00 - - - - - 2.00 123.74 100.00%
22.04.02 CAJA DE REGISTRO DE ALB. DE 10" X 20" CON TAPA DE CONCRETO PZA 1.00 97.28 97.28 - - 0.00 - - - - - 1.00 97.28 100.00%
22.04.03 CAJA DE REBOSE, CON REJILLA DE FIERRO UND 4.00 138.05 552.20 - - 0.00 - - - - - 4.00 552.20 100.00%
22.04.04 TAPA SANITARIA PARA CISTERNA Y TANQUE ELEVADO UND 2.00 127.74 255.48 - - 0.00 - - - - - 2.00 255.48 100.00%
22.04.05 REBOSE DE CISTERNA DE FIERRO GALV. DE D=3" UND 1.00 93.59 93.59 - - 0.00 - - - - - 1.00 93.59 100.00%
22.04.06 REBOSE DE TANQUE ALTO DE FIERRO GALV. DE D=2" UND 1.00 124.39 124.39 - - 0.00 - - - - - 1.00 124.39 100.00%
22.04.07 ABRAZADERA DE FIJACION DE TUBOS HASTA 2" DE F. GALV. UND 15.00 22.20 333.00 - - 0.00 - - - - - 15.00 333.00 100.00%
22.04.08 ROMPE AGUA UND 8.00 46.81 374.48 - - 0.00 - - - - - 8.00 374.48 100.00%
23 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 7,808.47 - - - - - - - - 7,808.47 100.00%
23.01 SALIDAS DE AGUA FRIA 747.65 - - - - - - - - 747.65 100.00%
23.01.01 SALIDA DE AGUA FRIA - PVC - SAP 1/2" GLB 19.00 39.35 747.65 - - 0.00 - - - - - 19.00 747.65 100.00%
23.02 REDES DE DISTRIBUCION Y ALIMENTACION 7,060.82 - - - - - - - - 7,060.82 100.00%
23.02.01 TUVERIA PVC CLASE 10 - 1/2" M 27.00 4.71 127.17 - - 0.00 - - - - - 27.00 127.17 100.00%
23.02.02 TUVERIA PVC CLASE 10 - 3/4" M 110.51 5.39 595.65 - - 0.00 - - - - - 110.51 595.65 100.00%
23.02.03 TUBERIA PVC CLASE 10 - 1" M 67.19 6.07 407.84 - - 0.00 - - - - - 67.19 407.84 100.00%
23.02.04 TUBERIA PVC CLASE 10 - 2" M 11.36 10.64 120.87 - - 0.00 - - - - - 11.36 120.87 100.00%
23.02.05 CODO PVC SAP 1/2" X 90° UND 36.00 0.67 24.12 - - 0.00 - - - - - 36.00 24.12 100.00%
23.02.06 CODO PVC SAP 3/4" X 90° UND 58.00 1.25 72.50 - - 0.00 - - - - - 58.00 72.50 100.00%
23.02.07 CODO PVC SAP 1" X 90° UND 6.00 3.20 19.20 - - 0.00 - - - - - 6.00 19.20 100.00%
23.02.08 TEE PVC - SAP 3/4" UND 20.00 1.93 38.60 - - 0.00 - - - - - 20.00 38.60 100.00%
23.02.09 TEE PVC - SAP 1" UND 6.00 4.60 27.60 - - 0.00 - - - - - 6.00 27.60 100.00%
23.02.10 REDUCCION PVC - SAP 3/4" A 1/2" UND 23.00 1.26 28.98 - - 0.00 - - - - - 23.00 28.98 100.00%
23.02.11 REDUCCION PVC - SAP 1" A 3/4" UND 8.00 3.50 28.00 - - 0.00 - - - - - 8.00 28.00 100.00%
23.02.12 REDUCCION PVC - SAP 2" A 1 1/2" UND 2.00 5.60 11.20 - - 0.00 - - - - - 2.00 11.20 100.00%
23.02.13 UNION UNIVERSAL PVC 3/4" UND 10.00 6.65 66.50 - - 0.00 - - - - - 10.00 66.50 100.00%
23.02.14 VALVULA DE COMPUERTA DE BRONCE 3/4" PZA 11.00 39.44 433.84 - - 0.00 - - - - - 11.00 433.84 100.00%
23.02.15 VALVULA DE COMPUERTA DE BRONCE 2" PZA 3.00 87.18 261.54 - - 0.00 - - - - - 3.00 261.54 100.00%
23.02.16 VALVULA DE COMPUERTA DE BRONCE 4" PZA 1.00 111.18 111.18 - - 0.00 - - - - - 1.00 111.18 100.00%
23.02.17 VALVULA DE CHECK DE BRONCE D= 2" UND 2.00 92.84 185.68 - - 0.00 - - - - - 2.00 185.68 100.00%
23.02.18 VALVULA DE CHECK DE BRONCE D= 2 1/2" UND 2.00 108.06 216.12 - - 0.00 - - - - - 2.00 216.12 100.00%
23.02.19 VALVULA FLOTADORA D= 2" UND 1.00 116.03 116.03 - - 0.00 - - - - - 1.00 116.03 100.00%
23.02.20 TUBERIA DE FIERRO GALVANIZADO 2" M 18.40 29.58 544.27 - - 0.00 - - - - - 18.40 544.27 100.00%
23.02.21 TUBERIA DE FIERRO GALVANIZADO 2 1/2" M 3.40 39.28 133.55 - - 0.00 - - - - - 3.40 133.55 100.00%
23.02.22 TUBERIA DE FIERRO GALVANIZADO 4" M 15.70 49.75 781.08 - - 0.00 - - - - - 15.70 781.08 100.00%
23.02.23 INSTALACION DE ACCESORIOS DE PVC SAL UND 138.00 13.85 1,911.30 - - 0.00 - - - - - 138.00 1,911.30 100.00%
23.02.24 INSTALACION DE ACCESORIOS DE BRONCE UND 5.00 22.93 114.65 - - 0.00 - - - - - 5.00 114.65 100.00%
23.02.25 SUMINIST./ INSTALAC./ MURETE GRIFO DE RIEGO JARDIN D= 3/4" UND 5.00 136.67 683.35 - - 0.00 - - - - - 5.00 683.35 100.00%
24 SALIDAS 20,167.25 - - 7,961.56 0.39 - 7,961.56 0.39 - 12,205.69 60.52%
24.01 SALIDA PARA BRAQUETE PTO 13.00 99.54 1,294.02 - - 3.00 298.62 0.23 3.00 298.62 0.23 10.00 995.40 76.92%
24.02 SALIDA PARA FLUORESCENTE ADOSADO PTO 41.00 102.82 4,215.62 - - 16.00 1,645.12 0.39 16.00 1,645.12 0.39 25.00 2,570.50 60.98%
24.03 SALIDA PARA FLUORESCENTE EMPOTRADO PTO 10.00 117.38 1,173.80 - - 4.00 469.52 0.40 4.00 469.52 0.40 6.00 704.28 60.00%
24.04 SALIDA PARA LUCES DE EMERGENCIA PTO 9.00 161.76 1,455.84 - - 4.00 647.04 0.44 4.00 647.04 0.44 5.00 808.80 55.56%
24.05 SALIDA DE TECHO (VENTILADORES) PTO 16.00 124.35 1,989.60 - - 8.00 994.80 0.50 8.00 994.80 0.50 8.00 994.80 50.00%
24.06 SALIDA PARA INTERRUPTOR SIMPLE CON PVC PTO 14.00 98.51 1,379.14 - - 6.00 591.06 0.43 6.00 591.06 0.43 8.00 788.08 57.14%
24.07 SALIDA PARA INTERRUPTOR DOBLE CON PVC PTO 8.00 114.11 912.88 - - 3.00 342.33 0.38 3.00 342.33 0.38 5.00 570.55 62.50%
24.08 SALIDA PARA INTERRUPTOR DE CONMUTACION (PARA FLUORESCE PTO 6.00 115.69 694.14 - - 2.00 231.38 0.33 2.00 231.38 0.33 4.00 462.76 66.67%
24.09 SALIDA PARA INTERRUPTOR DE TIMBRE (PULSADOR) PTO 1.00 89.02 89.02 - - 0.00 - - - - - 1.00 89.02 100.00%
24.10 SALIDA PARA TOMACORRIENTE MONOFASICO DOBLE EMPOTRADO, PTO 27.00 138.10 3,728.70 - - 0.00 - - - - - 27.00 3,728.70 100.00%
24.11 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PUESTO A TI PTO 1.00 142.09 142.09 - - 1.00 142.09 1.00 1.00 142.09 1.00 - 0.00 0.00%
24.12 SALIDA PARA TOMACORRIENTE BIPOLAR EMPOTRADO EN PISO PTO 20.00 129.98 2,599.60 - - 20.00 2,599.60 1.00 20.00 2,599.60 1.00 - 0.00 0.00%
24.13 SALIDA PARA TIMBRE PTO 1.00 86.76 86.76 - - 0.00 - - - - - 1.00 86.76 100.00%
24.14 SALIDA PARA SPOT - LIGHT CON PVC PTO 4.00 101.51 406.04 - - 0.00 - - - - - 4.00 406.04 100.00%
25 CAJAS DE PASE 677.21 - - - - - - - - 677.21 100.00%
25.01 SUMINISTRO E INSTLACION DE CAJA DE PASE DE 100 X 100 X 55 MM UND 5.00 36.89 184.45 - - 0.00 - - - - - 5.00 184.45 100.00%
25.02 SUMINISTRO E INSTALACION DE CAJA DE PASE DE 150 X 150 X 100 UND 4.00 46.87 187.48 - - 0.00 - - - - - 4.00 187.48 100.00%
25.03 SUMINISTRO E INSTALACION DE CAJA DE PASE DE OCTOGONAL 100 UND 3.00 34.86 104.58 - - 0.00 - - - - - 3.00 104.58 100.00%
25.04 SUMINISTRO E INSTALACION DE CAJA DE PASE DE F.G. LIVIANA 150 UND 5.00 40.14 200.70 - - 0.00 - - - - - 5.00 200.70 100.00%
26 SALIDAS PARA COMUNICACIONES 637.36 - - 468.72 0.74 - 468.72 0.74 - 168.64 26.46%
26.01 SALIDA PARA TELEFONO PTO 3.00 64.12 192.36 - - 3.00 192.36 1.00 3.00 192.36 1.00 - 0.00 0.00%
26.02 SALIDA PARA INTERNET PTO 3.00 92.12 276.36 - - 3.00 276.36 1.00 3.00 276.36 1.00 - 0.00 0.00%
26.03 SUMINISTRO E INSTALACION DE CAMPANILLA DE TIMBRE 6" 220V/1 PTO 1.00 79.87 79.87 - - 0.00 - - - - - 1.00 79.87 100.00%
26.04 SUMINISTRO E INSTALACION DE CAMPANILLA DE TIMBRE 8" 220V/1 PTO 1.00 88.77 88.77 - - 0.00 - - - - - 1.00 88.77 100.00%
27 CANALIZACION Y/O TUBERIAS 8,607.58 - - - - - - - - 8,607.58 100.00%
27.01 SUMINISTRO E INSTALACION DE TUBERIA DE PVC SAP 25 MM M 415.00 11.87 4,926.05 - - 0.00 - - - - - 415.00 4,926.05 100.00%
27.02 SUMINISTRO E INSTALACION DE TUBERIA DE PVC SAP 35 MM M 172.50 14.40 2,484.00 - - 0.00 - - - - - 172.50 2,484.00 100.00%
27.03 SUMINISTRO E INSTALACION DE TUBERIA DE PVC SAP 40 MM M 35.70 16.25 580.13 - - 0.00 - - - - - 35.70 580.13 100.00%
27.04 SUMINISTRO E INSTALACION DE TUBERIA DE PVC SAP 55 MM M 35.00 17.64 617.40 - - 0.00 - - - - - 35.00 617.40 100.00%
28 CONDUCTORES Y CABLES 15,920.32 - - - - - - - - 15,920.32 100.00%
28.01 SUMINISTRO E INSTALACION CABLE NYY 3-1 X 4 mm2 M 345.00 14.52 5,009.40 - - 0.00 - - - - - 345.00 5,009.40 100.00%
28.02 SUMINISTRO E INSTALACION CABLE NYY 3-1 X 4 mm2 + 1 X 4 mm2 M 70.00 22.04 1,542.80 - - 0.00 - - - - - 70.00 1,542.80 100.00%
28.03 SUMINISTRO E INSTALACION CABLE NYY 3-1 X 6 mm2 + 1 X 6 mm2 M 172.50 24.60 4,243.50 - - 0.00 - - - - - 172.50 4,243.50 100.00%
28.04 SUMINISTRO E INSTALACION CABLE NYY 3-1 X 16 mm2 + 1 X 10 mm2 M 35.70 50.39 1,798.92 - - 0.00 - - - - - 35.70 1,798.92 100.00%
28.05 SUMINISTRO E INSTALACION CABLE NYY 3-1 X 50 mm2 + 1 X 35 mm2 M 35.00 95.02 3,325.70 - - 0.00 - - - - - 35.00 3,325.70 100.00%
29 TABLEROS ELECTRICOS 6,754.07 - - - - - - - - 6,754.07 100.00%
29.01 TABLERO DE DISTRIBUCION, EQUIPADO C/INTERRUP. TERMIMAGNETIC
UND 1.00 937.09 937.09 - - 0.00 - - - - - 1.00 937.09 100.00%
29.02 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERR. TERMOMAGNEUND 1.00 1498.35 1,498.35 - - 0.00 - - - - - 1.00 1,498.35 100.00%
29.03 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERRUP. TERMOMA UND 1.00 755.48 755.48 - - 0.00 - - - - - 1.00 755.48 100.00%
29.04 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERRUP. TERMOMA UND 1.00 848.03 848.03 - - 0.00 - - - - - 1.00 848.03 100.00%
29.05 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERRUP. TERMOMA UND 1.00 735.03 735.03 - - 0.00 - - - - - 1.00 735.03 100.00%
29.06 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERRUP. TERMOMA UND 1.00 735.03 735.03 - - 0.00 - - - - - 1.00 735.03 100.00%
29.07 SUMIN. E INST. TABLERO ELECTRICO CON INTERRUPTORES TERMO UND 1.00 618.03 618.03 - - 0.00 - - - - - 1.00 618.03 100.00%
29.08 SUMIN. E INST. DE TABLERO ELECTRICO CON INTERRUPTORES TER UND 1.00 627.03 627.03 - - 0.00 - - - - - 1.00 627.03 100.00%
30 CONEXIÓN A RED EXTERNA Y MEDIDOR 74,453.39 - - - - - - - - 74,453.39 100.00%
30.01 EXCAVACION DE ZANJA MANUAL H=0.65m A=0.50m M 658.20 28.01 18,436.18 - - 0.00 - - - - - 658.20 18,436.18 100.00%
30.02 EXCAVACION DE HOYOS PARA POSTE UND 16.00 28.01 448.16 - - 0.00 - - - - - 16.00 448.16 100.00%
30.03 EXCAVACION DE HOYOS PARA PUESTA A TIERRA UND 2.00 138.32 276.64 - - 0.00 - - - - - 2.00 276.64 100.00%
30.04 REFINE Y NIVELACION DE ZANJA M 658.20 3.82 2,514.32 - - 0.00 - - - - - 658.20 2,514.32 100.00%
30.05 CAMA DE ARENA 0.50 X 0.10 TN M 658.20 5.22 3,435.80 - - 0.00 - - - - - 658.20 3,435.80 100.00%
30.06 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO M 658.20 17.20 11,321.04 - - 0.00 - - - - - 658.20 11,321.04 100.00%
30.07 ELIMINACION DE MATERIAL EXCEDENTE MANUAL M3 658.20 25.55 16,817.01 - - 0.00 - - - - - 658.20 16,817.01 100.00%
30.08 SUMINISTRO E INSTALACION DE POSZO A TIERRA (<5 Ohms) UND 1.00 1409.49 1,409.49 - - 0.00 - - - - - 1.00 1,409.49 100.00%
30.09 SUMINISTRO E INSTALACION DE POSZO A TIERRA (<15 Ohms) UND 1.00 1082.41 1,082.41 - - 0.00 - - - - - 1.00 1,082.41 100.00%
30.10 SUMINISTRO E INSTALACION DE INTERRUPTOR HORARIO UND 3.00 193.33 579.99 - - 0.00 - - - - - 3.00 579.99 100.00%
30.11 TRANSPORTE DE POSTE DE CONCRETO DE ALMACEN A PUNTO DE IZUND 16.00 62.43 998.88 - - 0.00 - - - - - 16.00 998.88 100.00%
30.12 SUMINISTRO E INSTALACION DE POSTE C.A.C. 100/120/225 7METROS UND 4.00 492.84 1,971.36 - - 0.00 - - - - - 4.00 1,971.36 100.00%
30.13 SUMINISTRO E INSTALACION DE POSTE C.A.C. 200/120/240 8METROS UND 6.00 542.84 3,257.04 - - 0.00 - - - - - 6.00 3,257.04 100.00%
30.14 SUMINISTRO E INSTALACION DE POSTE C.A.C. 200/120/255 9METROS UND 6.00 592.84 3,557.04 - - 0.00 - - - - - 6.00 3,557.04 100.00%
30.15 SUMINISTRO E INSTALACION DE CRUCETA SIMETRICA DE C.A.V. UND 6.00 260.87 1,565.22 - - 0.00 - - - - - 6.00 1,565.22 100.00%
30.16 SUMINISTRO E INSTALACION DE PASTORAL SUCRE DE C.A.V. UND 6.00 259.08 1,554.48 - - 0.00 - - - - - 6.00 1,554.48 100.00%
30.17 SUBIDA A POSTE INC. CORTOCIRCUITO UND 16.00 88.93 1,422.88 - - 0.00 - - - - - 16.00 1,422.88 100.00%
30.18 SUMINISTRO E INSTALACION DE EMPALME SUBTERRANEO MONOFAUND 16.00 74.51 1,192.16 - - 0.00 - - - - - 16.00 1,192.16 100.00%
30.19 SUMINISTRO E INSTALACION DE EMPALME SUBTERRANEO TRIFASI UND 16.00 84.51 1,352.16 - - 0.00 - - - - - 16.00 1,352.16 100.00%
30.20 INSTALACION DEL SISTEMA DE MEDICION INC. MURETE UND 1.00 1261.13 1,261.13 - - 0.00 - - - - - 1.00 1,261.13 100.00%
31 ARTEFACTOS ELECTRICOS 25,056.12 - - - - - - - - 25,056.12 100.00%
31.01 SUMIN. E INST. DE ARTEFACTO FLUORESCENTE 2 x 18W MARCO DE UND 10.00 62.79 627.90 - - 0.00 - - - - - 10.00 627.90 100.00%
31.02 SUMIN. E INST. DE ARTEFACTO FLUORESCENTE 2 x 36W UND 3.00 91.53 274.59 - - 0.00 - - - - - 3.00 274.59 100.00%
31.03 SUMIN. E INST. DE ARTEFACTO FLUORESCENTE 3 x 36W UND 32.00 99.19 3,174.08 - - 0.00 - - - - - 32.00 3,174.08 100.00%
31.04 SUMIN. E INST. BRAQUETE REFLECTOR CON LAMPARAS AHORRADO UND 9.00 256.74 2,310.66 - - 0.00 - - - - - 9.00 2,310.66 100.00%
31.05 SUMINISTRO E INSTALACION DE ARTEFACTO FLUORESCENTE LAM UND 5.00 56.23 281.15 - - 0.00 - - - - - 5.00 281.15 100.00%
31.06 SUMINISTRO E INSTALACION LUMINARIA ASTRO+LAMPARA VAPOR UND 4.00 188.15 752.60 - - 0.00 - - - - - 4.00 752.60 100.00%
31.07 SUMINISTRO E INSTALACION REFLECTOR + LAMPARA HM - 250W UND 12.00 793.82 9,525.84 - - 0.00 - - - - - 12.00 9,525.84 100.00%
31.08 SUMINISTRO E INSTALACION DE BRAQUETE REFLECTOR + LAMPAR UND 4.00 302.64 1,210.56 - - 0.00 - - - - - 4.00 1,210.56 100.00%
31.09 SUMINISTRO E INSTALACION LUMINARIA TIPO FAROLA CONICA + UND 4.00 380.99 1,523.96 - - 0.00 - - - - - 4.00 1,523.96 100.00%
31.10 ARTEFACTO VENTILADOR DE TECHO UND 16.00 239.85 3,837.60 - - 0.00 - - - - - 16.00 3,837.60 100.00%
31.11 SUMINISTRO E INSTALACION LUMINARIA SPOTH LITGH LED DE 7W UND 4.00 193.80 775.20 - - 0.00 - - - - - 4.00 775.20 100.00%
31.12 SUMINISTRO E INSTALACION LUMINARIA TIPO FAROLA ESPEFERICAUND 2.00 380.99 761.98 - - 0.00 - - - - - 2.00 761.98 100.00%
32 EQUIPOS ELECTRICOS Y MECANICOS 6,905.91 - - - - - - - - 6,905.91 100.00%
32.01 SUMINISTRO E INSTALACION DE CONTROL DE NIVEL ELECTRICO UND 1.00 485.80 485.80 - - 0.00 - - - - - 1.00 485.80 100.00%
32.02 EQUIPO DE BOMBEO CON 2 ELECTROBOMBAS DE 1.4 HP UND 1.00 3615.81 3,615.81 - - 0.00 - - - - - 1.00 3,615.81 100.00%
32.03 PRUEBAS Y PUESTA EN SERVICIO UND 1.00 2804.30 2,804.30 - - 0.00 - - - - - 1.00 2,804.30 100.00%
33 MOBILIARIO Y EQUIPAMENTO 104,432.94 - - - - - - - - 104,432.94 100.00%
33.01 MOBILIARIOS Y EQUIPAMIENTO GLB 1.00 ### 104,432.94 - - 0.00 - - - - - 1.00 104,432.94 100.00%

COSTO DIRECTO TOTAL 1,869,782.01 602,435.78 32.23% 251,688.51 13.46% 854,124.26 45.69% 1,015,657.75 54.31%
GASTOS GENERALES (10%) 186,978.20 60,243.58 25,168.85 85,412.43 101,565.78
UTILIDAD (5.0%) 93,489.10 30,121.79 12,584.43 42,706.21 50,782.89
SUB TOTAL 2,150,249.31 692,801.15 289,441.79 982,242.90 1,168,006.42
FACTOR DE RELACION (98.50%) 2,117,995.57 682,409.13 285,100.16 967,509.26 1,150,486.32
I.G.V (18%) 381,239.20 122,833.64 51,318.03 174,151.67 207,087.54
TOTAL PRESUPUESTO 2,499,234.78 805,242.77 336,418.19 1,141,660.92 1,357,573.86