UNID. MET. P.UNIT. P.TOTAL S/. METRADO MONTO S/. METRADO MONTO S/. METRADO MONTO S/.
01 OBRAS PRELIMINARES 31,155.90
01.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y HERRAMIENTAS PARA LA OB glb 0.50 46,009.80 23,004.90 0.25 11,502.45 0.125 5,751.23 0.13 5,751.23
01.02 TRAZO YREPLANTEO km 14.14 576.45 8,151.00 14.14 8,151.00 0.00 0.00 0.00 0.00
02 PAVIMENTOS 371,784.47
02.01 REPOSICION DE AFIRMADO E=0.10 m m2 12,466.27 26.41 329,234.19 5,361.31 141,592.20 4,749.84 125,443.27 2,355.12 62,198.72
02.02 ESCARIFICADO, RECONFORMACION Y COMPACTADO DE LA RASANTE m2 25,788.05 1.65 42,550.28 25,788.05 42,550.28 0.00 0.00 0.00 0.00
03 TRANSPORTE 248,292.40
03.01 TRANSPORTE DE MATERIAL PARA AFIRMADO D<1 km m3k 16,779.39 12.24 205,379.73 7,883.65 96,495.88 6,435.66 78,772.48 2,460.08 30,111.37
03.02 TRANSPORTE DE MATERIAL PARA AFIRMADO D>1 km m3k 35,760.56 1.20 42,912.67 18,140.21 21,768.25 13,936.41 16,723.69 3,683.94 4,420.73
04 IMPACTO AMBIENTAL 3,136.00
04.01 RESTAURACION DE CANTERAS m2 2,000.00 1.04 2,080.00 500.00 520.00 1,000.00 1,040.00 500.00 520.00
04.02 RESTAURACION DE AREA AFECTADA POR PATIO DE MAQUINAS m2 1,200.00 0.88 1,056.00 300.00 264.00 600.00 528.00 300.00 264.00
COSTO DIRECTO 654,368.77 322,844.06 228,258.67 103,266.04
GASTOS GENERALES (3.18% CD) 13.179% 86,240.35 42,548.16 30,082.59 13,609.60
UTILIDAD (10% CD) 10.000% 65,436.88 32,284.41 22,825.87 10,326.60
SUB TOTAL 806,046.00 397,676.62 281,167.13 127,202.25
IMPUESTO (IGV 18%) 18.00% 145,088.28 71,581.79 50,610.08 22,896.41
MONTO REFERENCIAL DE OBRA (VR) 951,134.28 469,258.42 331,777.21 150,098.66
AVANCE PROGRAMADO DE EJECUCIÓN (%) 49.34% 34.88% 15.78%
AVANDE ACUMULADO PROGRAMADO (%) 49.34% 84.22% 100.00%