Phase Prepared by
Area UCSM Date Prepared
Work that must and can be done before Planned Activities Complete
Ref Task Description Location
starting this task
On Time? Reasons for delay or disruption*
Snag Free? Hour
PEPELMA DE VIDRIO 60x60 VIDRIO H=2.40m Instalacion de pepelma en muros de SS.HH. Nivel 10 Tarrajeo primario 11:00
Liberación de puntos para grifería electrónica en SSHH Nivel 1 y Azotea Trazo topográfico 12:00
ADICIONAL - GRIFERÍA ELECTRÓNICA
Discapacitados
Material deliverd
Ref Material te be delivered Location to drop
Damage Reasons for wrong delivery
Time free On Time?
*reasons 1 Late materials • 2 Wrong materials • 3 Other trade in work area • 4 Prerequisite activity not completed • 5 Unplanned work• 6 Labour shortage • 7 Over estimation of what could be achieved • 8 Task required rework •
9 Late or incomplete information • 10 Weather • 11 Plant/tools unavailable • 12 Other, please state