Work that must and can be done before Planned Activities Complete
Ref Task Description Location
starting this task
On Time? Reasons for delay or disruption*
Snag Free? Hour
ENCHAPE PAC ALPLYC COLOR BLANCO e=4mm Liberacion de estructura metalica Nivel 5 Trazo topográfico 14:00
(AR-11) ESTRUCTURA METALICA
Material deliverd
Ref Material te be delivered Location to drop
Damage Reasons for wrong delivery
Time free On Time?
*reasons 1 Late materials • 2 Wrong materials • 3 Other trade in work area • 4 Prerequisite activity not completed • 5 Unplanned work• 6 Labour shortage • 7 Over estimation of what could be achieved • 8 Task required rework •