Tasa 10%

INVERSION INICIAL S/ 20,848.00

FLUJOS DE INGRESOS FLUJOS DE EGRESOS


A B
AÑO VALOR AÑO VALOR
1 S/ 60,352.50 1 S/ 43,085.00
2 S/ 63,906.25 2 S/ 43,808.26
3 S/ 68,257.50 3 S/ 46,278.59
4 S/ 72,608.75 4 S/ 48,778.11
5 S/ 76,956.25 5 S/ 51,306.50
TOTAL S/ 342,081.25 TOTAL S/ 233,256.46

FORMULACION

f1 S/ 17,267.50 VNA S/ 81,023.84


f2 S/ 20,097.99 VAN S/ 60,175.84
f3 S/ 21,978.91 TIR 89.45%
f4 S/ 23,830.64
f5 S/ 25,649.75
n 5 años
i 10 % de tasa = 0.1
IO 20848
FLUJO DE EFECTIVO NETO
A-B
AÑO VALOR
1 S/ 17,267.50 -20848
2 S/ 20,097.99 17267.5
3 S/ 21,978.91 20097.99
4 S/ 23,830.64 21978.91
5 S/ 25,649.75 23830.64
25649.75
ELABORAR LA RED CPM, UTILIZANDO EL METODO DE LAS
PRECEDENCIAS. IDENTIFICAR LA RUTA CRITICA Y EL TIEMPO
TOTAL DEL PROYECTO ES EF
LS LF
CODIGO ACTIVIDADES PRECEDENCIDURACION H
A OBRAS PRELIMINARES 10 DURACION
B MOV. TIERRAS A 15
C CIMENTACION B 12
D MUROS B 9
E COLUMNAS B 26
F TECHO C 7
G INST. SANITARIA C 4
H INST. ELECTRICAS D 18
I REVESTIMIENTO F 15
J TANQUE ELEVADO F,G 13
K ACABADOS H,I 10
L ENTREGA DE LA OBRA E,J,K 1

INICIO A

0 10
ES TIEMPO INICIAL MAS TEMPRANO
EF TIEMPO FINAL MAS TEMPRANO
LS TIEMPO INICIAL MAS TARDIO
LF TIEMPO FINAL MAS TARDIO
DURACION (DIAS,SEMANAS , MESES)
P PARTIDA , ACTIVIDAD QUE SE VA DESARROLLAR
H HOLGURA

12
B
D

15
9
J

13

F I

7 15

18

26
K L

10 1
FIN