FACTOR DE PRESTACIONES

Factor para auxiliares por dia

Periodo constructivo: 150 dias, del 7 enero de 2019 al 7 de junio de 2019

Salario de Auxiliar: $10.61

Dia Calendario 150 dias


No. de Domingos 21 dias
No. de sábados 11 dias
No. de días festivos 8 dias
No. de permisos 2 dias
No. de incapacidades 2 dias
Total 44 dias pagados y no trabajados

𝐷𝑖𝑎𝑠 𝑡𝑟𝑎𝑏𝑎𝑗𝑎𝑑𝑜𝑠 = 106 𝑑𝑖𝑎𝑠 × $10.61 = $1124.66


𝐷𝑖𝑎𝑠 𝑛𝑜 𝑡𝑟𝑎𝑏𝑎𝑗𝑎𝑑𝑜𝑠 = 44 𝑑𝑖𝑎𝑠 × $10.61 = $466.84
𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $1124.66 + $466.84 = $1591.50

Prestacion por vacaciones y aguinaldo


𝑉𝑎𝑐𝑎𝑐𝑖𝑜𝑛𝑒𝑠 𝑦 𝑎𝑔𝑢𝑖𝑛𝑎𝑙𝑑𝑜 = $1591.50 × 14% = $222.81

𝐼𝑆𝑆𝑆, 𝐴𝐹𝑃 𝑒 𝐼𝑁𝑆𝐴𝐹𝑂𝑅𝑃 = $1814.31 × 15.25% = $276.68


$10
𝑆𝑒𝑔𝑢𝑟𝑜 𝑑𝑒 𝑣𝑖𝑑𝑎 = × 5 𝑚𝑒𝑠𝑒𝑠 = $50.00
1 𝑚𝑒𝑠
𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $1591.50 + $222.81 + $276.68 + $50.00 = $2140.99

Factor de prestaciones
$2140.99
𝐹𝑎𝑐𝑡𝑜𝑟 𝑑𝑒 𝑝𝑟𝑒𝑠𝑡𝑎𝑐𝑖𝑜𝑛𝑒𝑠 = = 1.90
$1124.66
Factor para obreros por unidad de obra

Periodo constructivo: 150 dias, del 7 enero de 2019 al 7 de junio de 2019

Salario de Obrero: $13.03

Dias trabajados:

 Meses que dura el proyecto: 5 meses


 Meses que permanecerá en la obra: 3.5 meses
 No. de Domingos: 14 dias
 No. de Sabados: 7 dias
 Dias trabajados: 105 – 14 – 7 = 84 dias
 Dias festivos: 6 dias

Calculando el factor de prestaciones sobre un salario de $100 se tiene:

Salario devengado

𝑃𝑟𝑒𝑠𝑡𝑎𝑐𝑖𝑜𝑛𝑒𝑠 𝑝𝑜𝑟 𝑓𝑖𝑛 𝑑𝑒 𝑠𝑒𝑚𝑎𝑛𝑎 = $100 × 27% = $ 27


𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $100 + $27 = $127

𝑃𝑟𝑒𝑠𝑡𝑎𝑐𝑖𝑜𝑛𝑒𝑠 𝑝𝑜𝑟 𝑣𝑎𝑐𝑎𝑐𝑖𝑜𝑛𝑒𝑠 𝑦 𝑎𝑔𝑢𝑖𝑛𝑎𝑙𝑑𝑜 = $127 × 14% = $ 17.78


𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $127 + $17.78 = $144.78

𝐼𝑆𝑆𝑆, 𝐴𝐹𝑃 𝑒 𝐼𝑁𝑆𝐴𝐹𝑂𝑅𝑃 = $144.78 × 15.25% = $ 22.08


𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $144.78 + $22.08 = $𝟏𝟔𝟔. 𝟖𝟔

Salario por días festivos remunerados

𝐷𝑖𝑎𝑠 𝑓𝑒𝑠𝑡𝑖𝑣𝑜𝑠 𝑟𝑒𝑚𝑢𝑛𝑒𝑟𝑎𝑑𝑜𝑠 = 6 𝑑𝑖𝑎𝑠 × $13.03 = $78.18


𝑉𝑎𝑐𝑎𝑐𝑖𝑜𝑛𝑒𝑠 𝑦 𝑎𝑔𝑢𝑖𝑛𝑎𝑙𝑑𝑜 = $78.18 × 14% = $10.95
𝐼𝑆𝑆𝑆, 𝐴𝐹𝑃 𝑒 𝐼𝑁𝑆𝐴𝐹𝑂𝑅𝑃 = $89.13 × 15.25% = $13.59
𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $78.18 + $10.95 + $13.59 = $𝟏𝟎𝟐. 𝟕𝟐

$102.72
𝐷𝑖𝑠𝑡𝑟𝑖𝑏𝑢𝑦𝑒𝑛𝑑𝑜 𝑒𝑛𝑡𝑟𝑒 𝑑𝑖𝑎𝑠 𝑡𝑟𝑎𝑏𝑎𝑗𝑎𝑑𝑜𝑠 = = $1.22
84 𝑑𝑖𝑎𝑠
$12 $48
𝑆𝑒𝑔𝑢𝑟𝑜 𝑑𝑒 𝑣𝑖𝑑𝑎 = × 4 𝑚𝑒𝑠𝑒𝑠 = = $0.57
1 𝑚𝑒𝑠 84 𝑑𝑖𝑎𝑠
$26.06
𝑃𝑒𝑟𝑚𝑖𝑠𝑜𝑠 𝑦 𝑜𝑡𝑟𝑜𝑠 = $13.03 × 2 𝑑𝑖𝑎𝑠 = = $0.31
84 𝑑𝑖𝑎𝑠
$26.06
𝐼𝑛𝑐𝑎𝑝𝑎𝑐𝑖𝑑𝑎𝑑 = $13.03 × 2 𝑑𝑖𝑎𝑠 = = $0.31
84 𝑑𝑖𝑎𝑠

𝑆𝑢𝑏𝑡𝑜𝑡𝑎𝑙 = $166.86 + $1.22 + $0.57 + $0.31 + $0.31 = $𝟏𝟔𝟗. 𝟐𝟕


Factor de prestaciones
$169.27
𝐹𝑎𝑐𝑡𝑜𝑟 𝑑𝑒 𝑝𝑟𝑒𝑠𝑡𝑎𝑐𝑖𝑜𝑛𝑒𝑠 = = 1.69