*SERVICIOS AUXILIARES
MINA*
-CONSEM EIRL-
CAPACIDAD INSTALADA DE SERVICIOS AUXILIARES
MINA
6000.00 50%
9784.84
9784.84
9784.84
9784.84
9784.84
9784.84
9469.20
9469.20
9469.20
8837.92
40%
8370.16
8100.00
7880.15
7500.00
7287.60
4000.00
7002.60
6727.44
30%
6165.12
5700.00
5496.17
20%
2000.00
10%
0.00 0%
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE
45000.00
25000.00 60%
44548.36
44548.36
44548.36
44548.36
44548.36
44548.36
43111.32
43111.32
43111.32
42711.39
42050.50
40342.00
40237.23
39933.00
39591.30
20000.00
35781.35
34510.30
33707.60
30846.50
29343.30
40%
15000.00
10000.00
20%
5000.00
0.00 0%
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE
38567.43
38567.43
37323.32
20000.00
34835.10
40%
30853.95
30853.95
30853.95
29858.66
29858.66
29726.00
27380.00
25907.00
15000.00
25753.00
25338.00
24088.00
30%
21855.00
19561.00
19499.00
18930.00
10000.00
20%
5000.00 10%
0.00 0%
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE
RELLENO HIDRAULICO 320.00 m3 1160.00 m3 689.70 m3 890.10 m3 1480.00 m3 1579.80 m3 107% 72%
MANTENIMIENTO DE VIAS 2850.00 mts 3050.00 mts 2750.00 mts 2850.00 mts 5900.00 mts 5600.00 mts 95% 78%
EXTRACCION DE DESMONTE 5029.65 tns 5029.65 tns 4539.00 tns 5763.00 tns 10059.31 tns 10302.00 tns 102% 90%
PROGRAMA VS EJECUTADO – SEM42
PROGRAMA SEMANAL DE RELLENO HIDRAULICO - SEM: 42
3. PROGRAMA SEMANAL DE RELLENO HIDRAULICO
1 7 -Oc t 1 8 -Oc t 1 9 -Oc t 2 0 -Oc t 2 1 -Oc t 2 2 -Oc t 2 3 -Oc t
ITEM MINA LABOR M3 ESTADO DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE PROG EJEC
TJ2330 PROGRAMADO 120 120
1
EJECUTADO 0
TJ3033 PROGRAMADO 200 200
2
EJECUTADO 0
ENCANTO TJ2656 PROGRAMADO 500 500
3
EJECUTADO 54.6 200 100 354.6
ROSA TJ2027 PROGRAMADO 410 410
4
EJECUTADO 89.6 218.4 63.7 371.7
LOURDES TJ2822 PROGRAMADO 250 250
5
EJECUTADO 47 220 110 377
ENCANTO TJ2632 PROGRAMADO 0
6
EJECUTADO 24.2 24.2
ROSARITO GL2894 PROGRAMADO 0
7
EJECUTADO 62.7 147.8 210.5
RUMPUY TJ2462 PROGRAMADO 0
7
EJECUTADO 53.7 53.7
LOURDES TJ2817 PROGRAMADO 0
7
EJECUTADO 188.1 188.1
PROGRAMADO 0
8
EJECUTADO 0
PROG (M3) 320 0 0 0 0 0 0 910 0 250 0 0 0 0 1480.00 m3 1579.80 m3
EJEC. (M3) 0 0 0 0 0 24.2 89.6 218.4 126.4 147.8 53.7 289.7 420 210
LAB OR M 3*
INDICADORES
TJ2656 354.6
RESUMEN POR TJ2822 377
M3 PROGRAMADOS 1480 LABORES TJ2817 188.1
M3 EJECUTADOS 1579.8 TJ2027 371.7
TJ2462 53.7
CUMP. SEM 107%
TJ2632 24.2
CUMP. MES 72.0% GL2894 210.5
PROGRAMA VS EJECUTADO – SEM –
42
PROGRAMA DE MANTENIMIENTO DE VIAS 17 -Oct 1 8-Oct 1 9 -Oct 20 -Oct 2 1-Oct 22 -Oct 23 -Oct
EJEC.//PROG. OBSERVACION
REFERENCIA REFERENCIA
ITEM LABOR ACTIVIDAD METROS DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE
INICIAL FINAL
RASPADO YNIVELADO DE 850 PROGRAMADO 500 350
1 RP-940 BOCAMINA CM2022 100%
VIAS + CANTONEO 850 EJECUTADO 500 350
RASPADO YNIVELADO DE 900 PROGRAMADO 450 450
2 RP-940 CM2022 R2 94%
VIAS + CANTONEO 850 EJECUTADO 400 450
RASPADO YNIVELADO DE 750 PROGRAMADO 300 450
3 RP92440 R2 POKER 100%
VIAS + CANTONEO 750 EJECUTADO 300 450
RASPADO YNIVELADO DE 950 PROGRAMADO 450 500
4 RP-92440 R4 CM2705 89%
VIAS + CANTONEO 850 EJECUTADO 400 450
RASPADO YNIVELADO DE 850 PROGRAMADO 350 500
5 RP92440 CM2705 SANDVIK 88%
VIAS + CANTONEO 750 EJECUTADO 350 400
EX-CAMARADE RASPADO YNIVELADO DE 900 PROGRAMADO 450 450
6 RP690 DOBLEVIA 94%
CIMBRA VIAS + CANTONEO 850 EJECUTADO 450 400
EX-CAMARADE RASPADO YNIVELADO DE 700 PROGRAMADO 350 350
7 RP690 RP850 100%
CIMBRA VIAS + CANTONEO 700 EJECUTADO 350 350
PROG/GDIA 500 350 450 450 300 450 450 500 350 500 450 450 350 350 5900.00 mts
TOTAL PROG. SEMANAL 5 900 EJEC/GDIA 500 350 400 450 300 450 400 450 350 400 450 400 350 350 5600.00 mts
EJEC/DIA 850.00 mts 850.00 mts 750.00 mts 850.00 mts 750.00 mts 850.00 mts 700.00 mts
V°B°
GDIA DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE
PROG/ DIA 850.00 mts 900.00 mts 750.00 mts 950.00 mts 850.00 mts 900.00 mts 700.00 mts
MTS. EJECT.ACUM 850.00 mts 850.00 mts 750.00 mts 850.00 mts 750.00 mts 850.00 mts 700.00 mts % ACUM.SEM % ACUM.MES
%CUMPLIMIENTO 100.0% 94.4% 100.0% 89.5% 88.2% 94.4% 100.0% 9 5% 78 %
DIF. 0 -50 0 -100 -100 -50 0
PROGRAMA VS EJECUTADO – SEM - 42
SE IMPLEMENTO 02 SANGRILLAS EN R2 Y
01 05 03 72%
UNA SANGRILLA EN LA RP690
IMPLEMENTACIÓN DE 06 MANÓMETROS A
02 LAS 3 GUARDIAS PARA MEDIR LA PRESIÓN 06 06 100%
DE AIRE EN LAS PUNTERAS