FICHA DE IDENTIFICACION DE OBRA

1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES


QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75 DIAS CALENDARIO
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72
13 AMPLIACION DE PLAZO 11 DIAS CALENDARIO 3 S/.214,817.62 S/.296,652.90
14 FECHA DE REINICIO DEOBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

PRESUPUESTO
ITEM DESCRIPCION COSTO(S/.)
1 COSTO DIRECTO S/.929,946.40
2 GASTOS GENERALES(10%) S/.46,497.32
3 UTILIDAD(5%) S/.46,497.32
SUB TOTAL S/.1,022,941.04

INDICES
INDICE SIMBOLO DESCRIPCION % COEFICIENTES
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE
21 CEMENTO 79.76 339.42 339.42 339.42 339.42 339.42 339.42 339.42 339.42
CM 0.115
49 MAQUINARIA 20.24 246.31 248.53 253.39 257.41 261.65 269.28 269.32 270.11
5 AGREGADO GRUESO 18.35 228.63 229.31 231.53 253.11 255.31 258.21 259.15 261.36
AM 0.136
43 MADERA NACIONAL 81.65 575.31 576.21 577.36 577.45 577.49 578.31 578.48 579.11
17 L LADRILLO 100 0.121 682.16 683.53 685.29 689.31 691.63 692.73 692.89 693.46
3 F ACERO CORRUGADO 100 0.221 433.19 433.22 434.16 434.16 434.25 435.31 453.36 454.67
47 J MANO DE OBRA 100 0.307 471.44 471.44 475.18 475.18 475.18 475.18 475.18 475.18
39 GU GAST.GEN Y UTILIDAD 100 0.100 381.32 381.32 383.25 383.25 383.25 383.25 383.42 383.42
.
CALCULO DE LOS COEFICIENTE DE REAJUSTE "K" MENSUAL DE 2017
FECHA DE VALOR REFERENCIAL: 12-Apr-17

MES: ABRIL

INDICES
INDICE SIMBOLO DESCRIPCION % COEFICIENTES
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE
CEMENTO 79.76 339.42 339.42 339.42 339.42 339.42 339.42 339.42 339.42
21 CM 0.115
MAQUINARIA 20.24 246.31 248.53 253.39 257.41 261.65 269.28 269.32 270.11
AGREGADO GRUESO 18.35 228.63 229.31 231.53 253.11 255.31 258.21 259.15 261.36
5 AM 0.136
MADERA NACIONAL 81.65 575.31 576.21 577.36 577.45 577.49 578.31 578.48 579.11
17 L LADRILLO 100 0.121 682.16 683.53 685.29 689.31 691.63 692.73 692.89 693.46
3 F ACERO CORRUGADO 100 0.221 433.19 433.22 434.16 434.16 434.25 435.31 453.36 454.67
47 J MANO DE OBRA 100 0.307 471.44 471.44 475.18 475.18 475.18 475.18 475.18 475.18
39 GU GAST.GEN Y UTILIDAD 100 0.100 381.32 381.32 383.25 383.25 383.25 383.25 383.42 383.42
1.000
K=0.115*(CMr/CMo)+0.136*(Amr/AMo)+0.121*(Lr/Lo)+0.221*(Fr/Fo)+0.307*(Jr/Jo)+0.100*(GUr/GRo)

FECHA DE INICIO DE PLAZO DE EJECUCION: 2-Aug-17

MES: AGOSTO

INDICE % DE Io Ir Ir*%Part. K
SIMBOLO DESCRIPCION COEF. DE INCID. Io*%Part. Ir*%Part.
UNIFIC. PARTICIPACION ABRIL JULIO Io*%Part. AGOSTO
CEMENTO 79.76 339.42 339.42
21 CM 0.115 32057.45 32282.12 1.007 0.116
MAQUINARIA 20.24 246.31 257.41
AGREGADO GRUESO 18.35 228.63 253.11
43 AM 0.136 51169.42 51793.36 1.012 0.138
MADERA NACIONAL 81.65 575.31 577.45
17 L LADRILLO 0.121 100 682.16 689.31 68216.00 68931.00 1.010 0.122
3 F ACERO CORRUGADO 0.221 100 433.19 434.16 43319.00 43416 1.002 0.221
47 J MANO DE OBRA 0.307 100 471.44 475.18 47144.00 47518 1.008 0.309
39 GU GAST.GEN Y UTILIDAD 0.100 100 381.32 383.25 38132.00 38325 1.005 0.101
1.00717
MES: SETIEMBRE

INDICE % DE Io Ir Ir*%Part. K
SIMBOLO DESCRIPCION COEF. DE INCID. Io*%Part. Ir*%Part.
UNIFIC. PARTICIPACION ABRIL AGOSTO Io*%Part. SETIEMBRE
CEMENTO 79.76 339.42 339.42
21 CM 0.115 32057.45 32367.94 1.010 0.116
MAQUINARIA 20.24 246.31 261.65
AGREGADO GRUESO 18.35 228.63 255.31
43 AM 0.136 51169.42 51837.00 1.013 0.138
MADERA NACIONAL 81.65 575.31 577.49
17 L LADRILLO 0.121 100 682.16 691.63 68216.00 69163.00 1.014 0.123
3 F ACERO CORRUGADO 0.221 100 433.19 434.25 43319.00 43425 1.002 0.222
47 J MANO DE OBRA 0.307 100 471.44 475.18 47144.00 47518 1.008 0.309
39 GU GAST.GEN Y UTILIDAD 0.1 100 381.32 383.25 38132.00 38325 1.005 0.101
1.00805
MES: OCTUBRE

INDICE % DE Io Ir Ir*%Part. K
SIMBOLO DESCRIPCION COEF. DE INCID. Io*%Part. Ir*%Part.
UNIFIC. PARTICIPACION ABRIL SETIEMBRE Io*%Part. OCTUBRE
CEMENTO 79.76 339.42 339.42
21 CM 0.115 32057.45 32522.37 1.015 0.117
MAQUINARIA 20.24 246.31 269.28
AGREGADO GRUESO 18.35 228.63 258.21
43 AM 0.136 51169.42 51957.17 1.015 0.138
MADERA NACIONAL 81.65 575.31 578.31
17 L LADRILLO 0.121 100 682.16 692.73 68216.00 69273.00 1.015 0.123
3 F ACERO CORRUGADO 0.221 100 433.19 435.31 43319.00 43531 1.005 0.222
47 J MANO DE OBRA 0.307 100 471.44 475.18 47144.00 47518 1.008 0.309
39 GU GAST.GEN Y UTILIDAD 0.1 100 381.32 383.25 38132.00 38325 1.005 0.101
1.00966
MES: NOVIEMBRE

INDICE % DE Io Ir Ir*%Part. K
SIMBOLO DESCRIPCION COEF. DE INCID. Io*%Part. Ir*%Part.
UNIFIC. PARTICIPACION ABRIL OCTUBRE Io*%Part. NOVIEMBRE
CEMENTO 79.76 339.42 339.42
21 CM 0.115 32057.45 32523.18 1.015 0.117
MAQUINARIA 20.24 246.31 269.32
AGREGADO GRUESO 18.35 228.63 259.15
43 AM 0.136 51169.42 51988.29 1.016 0.138
MADERA NACIONAL 81.65 575.31 578.48
17 L LADRILLO 0.121 100 682.16 692.89 68216.00 69289.00 1.016 0.123
3 F ACERO CORRUGADO 0.221 100 433.19 453.36 43319.00 45336 1.047 0.231
47 J MANO DE OBRA 0.307 100 471.44 475.18 47144.00 47518 1.008 0.309
39 GU GAST.GEN Y UTILIDAD 0.1 100 381.32 383.42 38132.00 38342 1.006 0.101
1.01903
MES: JULIO

INDICE % DE Io Ir Ir*%Part. K
SIMBOLO DESCRIPCION COEF. DE INCID. Io*%Part. Ir*%Part.
UNIFIC. PARTICIPACION ABRIL JUNIO Io*%Part. JULIO
CEMENTO 79.76 339.42 339.42
21 CM 0.115 32057.45 32200.75 1.004 0.116
MAQUINARIA 20.24 246.31 253.39
AGREGADO GRUESO 18.35 228.63 231.53
43 AM 0.136 51169.42 51390.02 1.004 0.137
MADERA NACIONAL 81.65 575.31 577.36
17 L LADRILLO 0.121 100 682.16 685.29 68216.00 68529.00 1.005 0.122
3 F ACERO CORRUGADO 0.221 100 433.19 434.16 43319.00 43416 1.002 0.221
47 J MANO DE OBRA 0.307 100 471.44 475.18 47144.00 47518 1.008 0.309
39 GU GAST.GEN Y UTILIDAD 0.1 100 381.32 383.25 38132.00 38325 1.005 0.101
1.00509

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.00509 1.00717 1.00805 1.00966 1.01903
VALORIZACION N° 01
( DEL 02 DE AGOSTO AL 15 AGOSTO DEL 2017)
1) DATOS:
1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES
QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72
13 AMPLIACION DE PLAZO 11 3 S/.214,817.62 S/.296,652.90
14 FECHA DE REINICIO DE OBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.005 1.007 1.008 1.010 1.019

2) AVANCES (S/IGV): AGOSTO


VAL. N° 01
PROGRAMADO REAL
VALORIZACION PARCIAL S/.143,211.75 S/.184,129.39
VALORIZACION PARCIAL
VAL. PARCIAL x FR S/.136,336.15 S/.175,289.34

VALORIZACION VALORIZACION ACUMULADA S/.136,336.15 S/.175,289.34


ACUMULADA

SITUACION DE LA OBRA ADELANTADA

3) ADELANTO DIRECTO

6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00


7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17

4) CALCULO DEL REINTEGRO


R = V(K - 1) K (AGOSTO)= 1.00717

CALCULO DE REINTEGRO
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA

5) CALCULO DE LA DEDUCCION AD K Ka (JULIO)= 1.00509


D *V * (  1)
C Ka AD= S/.90,000.00
C= S/.973,829.64
CALCULO DE LA DEDUCCION
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48

6) CALCULO DE LA AMORTIZACION

AMORTIZACION
SALDO
N° MES VAL REAL*FR AD (%) AMORTIZACION ADELANTO
ADELANTO
01 AGOSTO 175,289.34 9.24% 16,200.00 90,000.00 73,800.00
RESUMEN DE VALORIZACION N°01 - AGOSTO
Valor Referencial (VR): ###
Monto contratado (MC): 973,829.64
Factor de Relacion (FR): 0.95199

ACUMULADO % AVANCE
DESCRIPCION ANTERIOR S/. ACTUAL S/. SALDO
S/. ACUMULADO
A) VALORIZACION (S/IGV) x FR 175,289.34 175,289.34
B) REINTEGRO RECONOCIDO (S/IGV) 1,256.65 1,256.65
VAL. BRUTA 176,545.98 176,545.98
C) AMORTIZACIONES
Amortizacion de Adelanto Directo 16,200.00 16,200.00
Amortizacion de Adelanto Materiales 0.00 0.00
16,200.00 16,200.00
VAL. NETA 160,345.98 160,345.98
D) RETENCIONES (DEDUCCIONES) 18.00% 798,540.30
Deducción Adelanto Directo 33.48 33.48
Deducción Adelanto Materiales 0.00 0.00
TOTAL RETENCIONES 33.48 33.48

E) MONTO A PAGAR AL CONTRATISTA


En efectivo 160,312.51 160,312.51
IGV (18%) 28,856.25 28,856.25
TOTAL A PAGAR 189,168.76 189,168.76
VALORIZACION N° 02
( DEL 16 DE AGOSTO AL 31 AGOSTO DEL 2017)
1) DATOS:
1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES
QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39 02-15
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72 16-31
13 AMPLIACION DE PLAZO 11 3 S/.214,817.62 S/.296,652.90 01-15
14 FECHA DE REINICIO DE OBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03 16-30
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00 01-15
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.005 1.007 1.008 1.010 1.019

2) AVANCES (S/IGV): AGOSTO AGOSTO


VAL. N° 01 VAL. N° 02
PROGRAMADO REAL PROGRAMADO REAL
VALORIZACION PARCIAL S/.143,211.75 S/.184,129.39 S/.265,964.67 S/.317,111.72
VALORIZACION PARCIAL
VAL. PARCIAL x FR S/.136,336.15 S/.175,289.34 S/.253,195.71 S/.301,887.19

VALORIZACION VALORIZACION ACUMULADA S/.136,336.15 S/.175,289.34 S/.389,531.86 S/.477,176.52


ACUMULADA

SITUACION DE LA OBRA ADELANTADA ADELANTADA

3) ADELANTO DIRECTO

6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00


7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17

4) CALCULO DEL REINTEGRO


R = V(K - 1) K (AGOSTO)= 1.00717

CALCULO DE REINTEGRO 01
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65

CALCULO DE REINTEGRO 02
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
3,420.88
1,256.65
2,164.23

5) CALCULO DE LA DEDUCCION AD K Ka (JULIO)= 1.00509


D *V * (  1)
C Ka AD= S/.90,000.00
C= S/.973,829.64
CALCULO DE LA DEDUCCION
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
91.13
33.48
57.65
6) CALCULO DE LA AMORTIZACION

AMORTIZACION
SALDO
N° MES VAL REAL*FR AD (%) AMORTIZACION ADELANTO
ADELANTO
01 AGOSTO 175,289.34 9.24% 16,200.00 90,000.00 73,800.00
02 AGOSTO 301,887.19 9.24% 27,900.00 73,800.00 45,900.00
RESUMEN DE VALORIZACION N°02 - AGOSTO
Valor Referencial (VR): ###
Monto contratado (MC): 973,829.64
Factor de Relacion (FR): 0.95199

ACUMULADO % AVANCE
DESCRIPCION ANTERIOR S/. ACTUAL S/. SALDO
S/. ACUMULADO
A) VALORIZACION (S/IGV) x FR 175,289.34 301,887.19 477,176.52
B) REINTEGRO RECONOCIDO (S/IGV) 1,256.65 2,164.23 3,420.88
VAL. BRUTA 176,545.98 304,051.42 480,597.40
C) AMORTIZACIONES
Amortizacion de Adelanto Directo 16,200.00 27,900.00 44,100.00
Amortizacion de Adelanto Materiales 0.00 0.00 0.00
16,200.00 27,900.00 44,100.00
VAL. NETA 160,345.98 276,151.42 436,497.40
D) RETENCIONES (DEDUCCIONES) 49.00% 496,653.12
Deducción Adelanto Directo 33.48 57.65 91.13
Deducción Adelanto Materiales 0.00 0.00 0.00
TOTAL RETENCIONES 33.48 57.65 91.13

E) MONTO A PAGAR AL CONTRATISTA


En efectivo 160,312.51 276,093.76 436,406.27
IGV (18%) 28,856.25 49,696.88 78,553.13
TOTAL A PAGAR 189,168.76 325,790.64 514,959.40
VALORIZACION N° 03
( DEL 12 DE SETIEMBRE AL 26 SETIEMBRE DEL 2017)
1) DATOS:
1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES
QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39 02-15
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72 16-31
13 AMPLIACION DE PLAZO 11 3 S/.214,817.62 S/.296,652.90 01-15
14 FECHA DE REINICIO DE OBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03 16-30
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00 01-15
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.005 1.007 1.008 1.010 1.019

2) AVANCES (S/IGV): AGOSTO AGOSTO SETIEMBRE


VAL. N° 01 VAL. N° 02 VAL. N° 03
PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL
VALORIZACION PARCIAL S/.143,211.75 S/.184,129.39 S/.265,964.67 S/.317,111.72 S/.214,817.62 S/.296,652.90
VALORIZACION PARCIAL
VAL. PARCIAL x FR S/.136,336.15 S/.175,289.34 S/.253,195.71 S/.301,887.19 S/.204,504.22 S/.282,410.60

VALORIZACION VALORIZACION ACUMULADA S/.136,336.15 S/.175,289.34 S/.389,531.86 S/.477,176.52 S/.594,036.08 S/.759,587.12


ACUMULADA

SITUACION DE LA OBRA ADELANTADA ADELANTADA ADELANTADA

3) ADELANTO DIRECTO

6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00


7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17

4) CALCULO DEL REINTEGRO


R = V(K - 1) K (AGOSTO)= 1.007
K (SETIEMBRE)= 1.008
CALCULO DE REINTEGRO 01
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65

CALCULO DE REINTEGRO 02
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
3,420.88
1,256.65
2,164.23
CALCULO DE REINTEGRO 03
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
03 SETIEMBRE 204,504.22 282,410.60 0.008 1,646.31 2,273.48 2,273.48 ADELANTADA
4,438.86 4,438.86 5,694.35
2,164.23
2,274.64

5) CALCULO DE LA DEDUCCION AD K Ka (JULIO)= 1.00509


D *V * (  1)
C Ka AD= S/.90,000.00
C= S/.973,829.64
CALCULO DE LA DEDUCCION 01
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48

CALCULO DE LA DEDUCCION 02
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
91.13
33.48
57.65
CALCULO DE LA DEDUCCION 03
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
03 SETIEMBRE 204,504.22 282,410.60 9.24% 1.008 1.005 55.63 76.82 76.82
130.02 130.02
57.65
72.37

6) CALCULO DE LA AMORTIZACION

AMORTIZACION
SALDO
N° MES VAL REAL*FR AD (%) AMORTIZACION ADELANTO
ADELANTO
01 AGOSTO 175,289.34 9.24% 16,200.00 90,000.00 73,800.00
02 AGOSTO 301,887.19 9.24% 27,900.00 73,800.00 45,900.00
03 SETIEMBRE 282,410.60 9.24% 26,100.00 45,900.00 19,800.00
RESUMEN DE VALORIZACION N°03 - SETIEMBRE
Valor Referencial (VR): ###
Monto contratado (MC): 973,829.64
Factor de Relacion (FR): 0.95199

ACUMULADO % AVANCE
DESCRIPCION ANTERIOR S/. ACTUAL S/. SALDO
S/. ACUMULADO
A) VALORIZACION (S/IGV) x FR 477,176.52 282,410.60 759,587.12
B) REINTEGRO RECONOCIDO (S/IGV) 3,420.88 2,274.64 5,695.51
VAL. BRUTA 480,597.40 284,685.23 765,282.63
C) AMORTIZACIONES
Amortizacion de Adelanto Directo 44,100.00 26,100.00 70,200.00
Amortizacion de Adelanto Materiales 0.00 0.00 0.00
44,100.00 26,100.00 70,200.00
VAL. NETA 436,497.40 258,585.23 695,082.63
D) RETENCIONES (DEDUCCIONES) 78.00% 214,242.52
Deducción Adelanto Directo 91.13 72.37 163.49
Deducción Adelanto Materiales 0.00 0.00 0.00
TOTAL RETENCIONES 91.13 72.37 163.49

E) MONTO A PAGAR AL CONTRATISTA


En efectivo 436,406.27 258,512.87 694,919.14
IGV (18%) 78,553.13 46,532.32 125,085.44
TOTAL A PAGAR 514,959.40 305,045.18 820,004.58
VALORIZACION N° 04
( DEL 27 DE SETIEMBRE AL 11 DE OCTUBRE DEL 2017)
1) DATOS:
1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES
QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39 02-15 AGO
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72 16-31 AGO
13 AMPLIACION DE PLAZO 11 3 S/.214,817.62 S/.296,652.90 01-15 SET
14 FECHA DE REINICIO DE OBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03 16-30 SET
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00 01-15 OCT
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.005 1.007 1.008 1.010 1.019

2) AVANCES (S/IGV): AGOSTO AGOSTO SETIEMBRE OCTUBRE


VAL. N° 01 VAL. N° 02 VAL. N° 03 VAL. N° 04
PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL
VALORIZACION PARCIAL S/.143,211.75 S/.184,129.39 S/.265,964.67 S/.317,111.72 S/.214,817.62 S/.296,652.90 S/.245,505.85 S/.225,047.03
VALORIZACION PARCIAL
VAL. PARCIAL x FR S/.136,336.15 S/.175,289.34 S/.253,195.71 S/.301,887.19 S/.204,504.22 S/.282,410.60 S/.233,719.11 S/.214,242.52

VALORIZACION VALORIZACION ACUMULADA S/.136,336.15 S/.175,289.34 S/.389,531.86 S/.477,176.52 S/.594,036.08 S/.759,587.12 S/.827,755.19 S/.973,829.64
ACUMULADA

SITUACION DE LA OBRA ADELANTADA ADELANTADA ADELANTADA ADELANTADA

3) ADELANTO DIRECTO

6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00


7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17

4) CALCULO DEL REINTEGRO


R = V(K - 1) K (AGOSTO)= 1.007
K (SETIEMBRE)= 1.008
CALCULO DE REINTEGRO 01 K (OCTUBRE)= 1.010
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65

CALCULO DE REINTEGRO 02
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
3,420.88
1,256.65
2,164.23
CALCULO DE REINTEGRO 03
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
03 SETIEMBRE 204,504.22 282,410.60 0.008 1,646.31 2,273.48 2,273.48 ADELANTADA
4,438.86 4,438.86
2,164.23
2,274.64
CALCULO DE REINTEGRO 04
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
03 SETIEMBRE 204,504.22 282,410.60 0.008 1,646.31 2,273.48 2,273.48 ADELANTADA
04 OCTUBRE 233,719.11 214,242.52 0.010 2,257.62 2,069.48 2,069.48 ADELANTADA
6,696.48 6,696.48
2,274.64
4,421.84

5) CALCULO DE LA DEDUCCION AD K Ka (JULIO)= 1.00509


D *V * (  1)
C Ka AD= S/.90,000.00
C= S/.973,829.64
CALCULO DE LA DEDUCCION 01
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48

CALCULO DE LA DEDUCCION 02
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
91.13
33.48
57.65
CALCULO DE LA DEDUCCION 03
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
03 SETIEMBRE 204,504.22 282,410.60 9.24% 1.008 1.005 55.63 76.82 76.82
130.02 130.02 167.95
57.65
72.37
CALCULO DE LA DEDUCCION 04
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
03 SETIEMBRE 204,504.22 282,410.60 9.24% 1.008 1.005 55.63 76.82 76.82
04 OCTUBRE 233,719.11 214,242.52 9.24% 1.010 1.005 98.16 89.98 89.98
228.18 228.18 257.93
72.37
155.81
6) CALCULO DE LA AMORTIZACION

AMORTIZACION
SALDO
N° MES VAL REAL*FR AD (%) AMORTIZACION ADELANTO
ADELANTO
01 AGOSTO 175,289.34 9.24% 16,200.00 90,000.00 73,800.00
02 AGOSTO 301,887.19 9.24% 27,900.00 73,800.00 45,900.00
03 SETIEMBRE 282,410.60 9.24% 26,100.00 45,900.00 19,800.00
04 OCTUBRE 214,242.52 9.24% 19,800.00 19,800.00 0.00
RESUMEN DE VALORIZACION N°04 - OCTUBRE
Valor Referencial (VR): ###
Monto contratado (MC): 973,829.64
Factor de Relacion (FR): 0.95199

ACUMULADO % AVANCE
DESCRIPCION ANTERIOR S/. ACTUAL S/. SALDO
S/. ACUMULADO
A) VALORIZACION (S/IGV) x FR 759,587.12 214,242.52 973,829.64
B) REINTEGRO RECONOCIDO (S/IGV) 5,695.51 4,421.84 10,117.35
VAL. BRUTA 765,282.63 218,664.36 983,947.00
C) AMORTIZACIONES
Amortizacion de Adelanto Directo 70,200.00 19,800.00 90,000.00
Amortizacion de Adelanto Materiales 0.00 0.00 0.00
70,200.00 19,800.00 90,000.00
VAL. NETA 695,082.63 198,864.36 893,947.00
D) RETENCIONES (DEDUCCIONES) 100.00% 0.00
Deducción Adelanto Directo 163.49 155.81 319.31
Deducción Adelanto Materiales 0.00 0.00 0.00
TOTAL RETENCIONES 163.49 155.81 319.31

E) MONTO A PAGAR AL CONTRATISTA


En efectivo 694,919.14 198,708.55 893,627.69
IGV (18%) 125,085.44 35,767.54 160,852.98
TOTAL A PAGAR 820,004.58 234,476.09 1,054,480.67
VALORIZACION N° 05
( DEL 12 DE OCTUBRE AL 26 DE OCTUBRE DEL 2017)
1) DATOS:
1 VALOR REFERENCIAL S/.1,022,941.04 AVANCES
QUINCENA
2 FECHA DE VALOR REFERENCIAL 12-Apr-17 PROGRAMADO REAL
3 MONTO CONTRATADO S/.973,829.64 1 14% 18%
4 FECHA DE CONTRATO 6-Jul-17 2 26% 31%
5 FACTOR DE RELACION 0.95199 3 21% 29%
6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00 4 24% 22%
7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17 5 15%
8 PLAZO DE EJECUCION 75
9 ENTREGA DE TERRENO 1-Aug-17 VALORIZACION
10 FECHA DE INICIO DE PLAZO DE EJECUCION 2-Aug-17 N° PROGRAMADO REAL
11 FECHA PROGRAMADA DE FIN DE PLAZO DE EJECUCION 15-Oct-17 1 S/.143,211.75 S/.184,129.39 02-15 AGO 02-15 AGO
12 PARALIZACION DE OBRA 1-Sep-17 2 S/.265,964.67 S/.317,111.72 16-31 AGO 16-31 AGO
13 AMPLIACION DE PLAZO 11 3 S/.214,817.62 S/.296,652.90 01-15 SET 12-26 SET
14 FECHA DE REINICIO DE OBRA 12-Sep-17 4 S/.245,505.85 S/.225,047.03 16-30 SET 27-11 OCT
15 NUEVA FECHA DE TERMINO 26-Oct-17 5 S/.153,441.16 S/.0.00 01-15 OCT 12-26 OCT
16 FECHA DETERMINO REAL DE LA OBRA 22-Oct-17 S/.1,022,941.04 S/.1,022,941.04

MES JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE


K 1.005 1.007 1.008 1.010 1.019

2) AVANCES (S/IGV): AGOSTO AGOSTO SETIEMBRE OCTUBRE OCTUBRE


VAL. N° 01 VAL. N° 02 VAL. N° 03 VAL. N° 04 VAL. N° 05
PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL PROGRAMADO REAL
VALORIZACION PARCIAL S/.143,211.75 S/.184,129.39 S/.265,964.67 S/.317,111.72 S/.214,817.62 S/.296,652.90 S/.245,505.85 S/.225,047.03 S/.153,441.16 S/.0.00
VALORIZACION PARCIAL
VAL. PARCIAL x FR S/.136,336.15 S/.175,289.34 S/.253,195.71 S/.301,887.19 S/.204,504.22 S/.282,410.60 S/.233,719.11 S/.214,242.52 S/.146,074.45 S/.0.00

VALORIZACION VALORIZACION ACUMULADA S/.136,336.15 S/.175,289.34 S/.389,531.86 S/.477,176.52 S/.594,036.08 S/.759,587.12 S/.827,755.19 S/.973,829.64 S/.973,829.64 S/.973,829.64
ACUMULADA

SITUACION DE LA OBRA ADELANTADA ADELANTADA ADELANTADA ADELANTADA ADELANTADA

3) ADELANTO DIRECTO

6 MONTO DE ADELANTO DIRECTO(SIN IGV) S/.90,000.00


7 FECHA DE PAGO DE ADELANTO DIRECTO 27-Jul-17

4) CALCULO DEL REINTEGRO


R = V(K - 1) K (AGOSTO)= 1.007
K (SETIEMBRE)= 1.008
CALCULO DE REINTEGRO 01 K (OCTUBRE)= 1.010
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65

CALCULO DE REINTEGRO 02
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
3,420.88
1,256.65
2,164.23
CALCULO DE REINTEGRO 03
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
03 SETIEMBRE 204,504.22 282,410.60 0.008 1,646.31 2,273.48 2,273.48 ADELANTADA
4,438.86 4,438.86
2,164.23
2,274.64
CALCULO DE REINTEGRO 04
VAL.
VAL. N° MES VAL. REAL (K-1) R prog R real R reconocido
PROGRAMADA
01 AGOSTO 136,336.15 175,289.34 0.007 977.39 1,256.65 1,256.65 ADELANTADA
02 AGOSTO 253,195.71 301,887.19 0.007 1,815.16 2,164.23 2,164.23 ADELANTADA
03 SETIEMBRE 204,504.22 282,410.60 0.008 1,646.31 2,273.48 2,273.48 ADELANTADA
04 OCTUBRE 233,719.11 214,242.52 0.010 2,257.62 2,069.48 2,069.48 ADELANTADA
6,696.48 6,696.48 7,763.83
2,274.64
4,421.84

5) CALCULO DE LA DEDUCCION AD K Ka (JULIO)= 1.00509


D *V * (  1)
C Ka AD= S/.90,000.00
C= S/.973,829.64
CALCULO DE LA DEDUCCION 01
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48

CALCULO DE LA DEDUCCION 02
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
91.13
33.48
57.65
CALCULO DE LA DEDUCCION 03
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
03 SETIEMBRE 204,504.22 282,410.60 9.24% 1.008 1.005 55.63 76.82 76.82
130.02 130.02
57.65
72.37
CALCULO DE LA DEDUCCION 04
Ka (fecha del
N° MES VAL PROG*FR VAL REAL*FR AD (%) K D prog D real D reconocido
adelanto)
01 AGOSTO 136,336.15 175,289.34 9.24% 1.007 1.005 26.04 33.48 33.48
02 AGOSTO 253,195.71 301,887.19 9.24% 1.007 1.005 48.35 57.65 57.65
03 SETIEMBRE 204,504.22 282,410.60 9.24% 1.008 1.005 55.63 76.82 76.82
04 OCTUBRE 233,719.11 214,242.52 9.24% 1.010 1.005 98.16 89.98 89.98
228.18 228.18
72.37
155.81
6) CALCULO DE LA AMORTIZACION

AMORTIZACION
SALDO
N° MES VAL REAL*FR AD (%) AMORTIZACION ADELANTO
ADELANTO
01 AGOSTO 175,289.34 9.24% 16,200.00 90,000.00 73,800.00
02 AGOSTO 301,887.19 9.24% 27,900.00 73,800.00 45,900.00
03 SETIEMBRE 282,410.60 9.24% 26,100.00 45,900.00 19,800.00
04 OCTUBRE 214,242.52 9.24% 19,800.00 19,800.00 0.00
05 OCTUBRE 0.00 9.24% 0.00 0.00 0.00
RESUMEN DE VALORIZACION N°05 - OCTUBRE
Valor Referencial (VR): ###
Monto contratado (MC): 973,829.64
Factor de Relacion (FR): 0.95199

ACUMULADO % AVANCE
DESCRIPCION ANTERIOR S/. ACTUAL S/. SALDO
S/. ACUMULADO
A) VALORIZACION (S/IGV) x FR 973,829.64 0.00 973,829.64
B) REINTEGRO RECONOCIDO (S/IGV) 10,117.35 0.00 10,117.35
VAL. BRUTA 983,947.00 0.00 983,947.00
C) AMORTIZACIONES
Amortizacion de Adelanto Directo 90,000.00 0.00 90,000.00
Amortizacion de Adelanto Materiales 0.00 0.00 0.00
90,000.00 0.00 90,000.00
VAL. NETA 893,947.00 0.00 893,947.00
D) RETENCIONES (DEDUCCIONES) 100.00% 0.00
Deducción Adelanto Directo 319.31 0.00 319.31
Deducción Adelanto Materiales 0.00 0.00 0.00
TOTAL RETENCIONES 319.31 0.00 319.31

E) MONTO A PAGAR AL CONTRATISTA


En efectivo 893,627.69 0.00 893,627.69
IGV (18%) 160,852.98 0.00 160,852.98
TOTAL A PAGAR 1,054,480.67 0.00 1,054,480.67
CALCULO Y VALORIZACION DE MAYORES GASTOS GENERALES

Modalidad: SUMA ALZADA


Valor Referencial (S / IGV): S/. 1,022,941.04
Factor de Relacion: S/. 0.95199
Costo Directo: S/. 929,946.40
Gastos Generales (5 %): 5.00% S/. 46,497.32
Utilidad (5%) S/. 46,497.32
Sub - Total S/. 1,022,941.04

Plazo de Contrato: 75 DIAS CALENDARIO


Termino de Plazo de Contrato: 15-Oct-17
Ampliación de Plazo: 11 DIAS CALENDARIO
Nueva Fecha de Termino: 26-Oct-17
Indices:
Io= ABRIL DEL 2017 381.32
Ip= SETIEMBRE DEL 2017 383.25

Calculando el valor de los MGG, para la modalidad de SUMA ALZADA

MGG = S/. 7,177.56


CUADRO RESUMEN DE LA LIQUIDACION
VALOR REFERENCIAL : S/. 1,022,941.04
FECHA DE VALOR REFERENCIAL : 4/12/2017
MONTO DE CONTRATO CON IGV : S/. 973,829.64
FACTOR DE RELACION (F.R.) : 0.95199

Monto a Pagar al Contratista de las


valorizaciones: S/. 1,054,480.67

Pago de Mayores Gastos Generales: S/. 7,177.56

Penalidad por Mora: S/. 0.00

Monto Total a Pagar al Contratista: S/. 1,061,658.24