Está en la página 1de 32

CONTROL FÍSICO - FINANCIERO - VALORIZACION Nº01

CORRESPONDIENTE AL MES DE MARZO DEL 2021

OBRA "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO MODALIDAD : ADMINISTRACION DIRECTA MONTO REFERENCIAL S/. 502,425.00

UBICACIÓN : CHONGOS BAJO, CHUPACA, JUNÍN RESIDENTE : ING. JHOSEF J. CASTRO ROSAS MONTO SEGÚN RESOLUCION S/. 1,444,331.84

FECHA : MARZO 2021 SUPERVISOR : ING. JUVENAL LUIS AQUINO CALDERON PLAZO DE EJECUCIÓN : 120 días calendario

RESUMEN FÍSICO
DESCRIPCION PRESUPUESTO VAL-01 (MARZO) VAL-02 (ABRIL) VAL-03 (MAYO) VAL-04 (JUNIO) VAL ACUMULADA SALDO

COSTO DIRECTO S/. 1,342,695.92 S/. 102,999.17 S/. 102,999.17 S/. 1,239,696.75

GASTOS GENERALES S/. 53,707.84 S/. 4,119.97 S/. 4,119.97 S/. 49,587.87

SUB-TOTAL S/. 1,396,403.76 S/. 107,119.14 S/. 107,119.14 S/. 1,289,284.62

SUPERVISION S/. 27,928.08 S/. 2,142.38 S/. 2,142.38 S/. 25,785.70

PRESUPUESTO DE OBRA S/. 1,424,331.83

EXPEDIENTE TECNICO S/. 20,000.00 S/. 20,000.00 S/. 20,000.00

VALORIZACIÓN BRUTA DE OBRA S/. 1,444,331.83 S/. 109,261.52 S/. 109,261.52 S/. 1,335,070.31

FACTOR DE RELACIÓN 1.00

VALORIZACION BRUTA DE OBRA S/. 1,444,331.83 S/. 109,261.52 S/. 0.00 S/. 0.00 S/. 0.00 S/. 109,261.52 S/. 1,335,070.31

PORCENTAJE DE AVANCE EJECUTADO (%) 100.00% 7.67% 7.67% 92.33%

PORCENTAJE DE AVANCE PROGRAMADO (%) 100.00% 18.10% 18.10% 81.90%

RESUMEN FINANCIERO

DESCRIPCION PRESUPUESTO GASTOS MES DE MARZO 2021 GASTOS MES DE ABRIL 2021 GASTOS MES DE MAYO 2021 GASTOS MES DE JUNIO 2021 TOTAL SALDO

PRESUPUESTO ETAPA I S/. 1,444,331.83 S/. 119,515.50

ASIGNACION PRESUPUESTAL DE LA MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO S/. 309,482.00 S/. 119,515.50 S/. 0.00 S/. 0.00 S/. 0.00 S/. 119,515.50 S/. 189,966.50

RUBRO 07 S/. 309,482.00 S/. 119,515.50 S/. 0.00 S/. 0.00 S/. 0.00 S/. 119,515.50 S/. 189,966.50

2.6.2.2.2.5 - BIENES S/. 125,232.00 S/. 32,515.50 S/. 32,515.50 S/. 92,716.50

2.6.2.2.2.6 - SERVICIOS S/. 184,250.00 S/. 67,000.00 S/. 67,000.00 S/. 117,250.00

ELABORACION DEL EXPEDIENTE TECNICO S/. 20,000.00 S/. 20,000.00 S/. 20,000.00

TOTAL FINANCIERO S/. 309,482.00 S/. 119,515.50 S/. 0.00 S/. 0.00 S/. 0.00 S/. 119,515.50 S/. 189,966.50
PORCENTAJE DE AVANCE FINANCIERO (%) 100.00% 8.27% 0.00% 0.00% 0.00% 8.27% 91.73%

PORCENTAJE DE AVANCE FINANCIERO ACUM. (%) 100.00% 8.27% 8.27% 8.27% 8.27% 8.27% 91.73%
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

01 TRABAJOS PRELIMINARES
01.01 CARTEL IDENTIFICACIÓN DE OBRA, INCL GIGANTOGRAFIA GLB 0.00 0.00%
01.02 ALMACÉN, OFICINAS Y GUARDIANÍA mes 0.23 5.75%
01.03 CERCO PERIMETRICO PROVISIONAL GLB 0.00 0.00%
01.04 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIAS, EQUIPOS Y HERRAMIENTAS GLB 0.06 6.00%
01.05 IMPLEMENTACIÓN DE SALUD, SEGURIDAD EN EL TRABAJO. GLB 0.04 4.00%
01.06 IMPLEMENTACIÓN DEL PLAN CONTRA COVID-19. GLB 0.04 4.00%
01.07 MITIGACION DE IMPACTO AMBIENTAL GLB 0.04 4.00%
01.08 FLETE PARA TRANSPORTE DE MATERIALES GLB 0.06 6.00%
01.09 DEMOLICIÓN DE PABELLÓN DE AULAS Y OTROS GLB 0.00 0.00%
01.10 ELIMINACIÓN DEL MATERIAL DE DEMOLICIÓN GLB 0.00 0.00%
02 ESTRUCTURAS
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 0.00 0.00%
02.01.02 TRAZO Y REPLANTEO m2 0.00 0.00%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIÓN CON MAQUINARIA P/CIMENTACIÓN m3 0.00 0.00%
02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO CAPAS CADA 0.20M m3 0.00 0.00%
02.02.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO CAPAS CADA 0.20M m3 0.00 0.00%
02.02.04 CAMA DE ARENA PARA VIGAS DE CIMENTACIÓN m3 0.00 0.00%
02.02.05 NIVELACIÓN Y COMPACTACIÓN EN TERRENO NORMAL m2 0.00 0.00%

02.02.06 AFIRMADO DE 4" PARA VEREDAS CON EQUIPO LIVIANO m2 0.00 0.00%
02.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA DIST./PROM = 5KM m3 0.00 0.00%
02.03 CONCRETO SIMPLE
02.03.01 SOLADO
02.03.01.01 SOLADO EN ZAPATA MEZCLA C:H 1:10 m2 0.00 0.00%
02.03.01.02 SOLADO EN VIGAS DE CIMENTACION MEZCLA C:H 1:10 m2 0.00 0.00%
02.03.02 CIMIENTOS CORRIDOS
02.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G m3 0.00 0.00%
02.03.03 SOBRECIMIENTOS
02.03.03.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 0.00 0.00%
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS m2 0.00 0.00%
02.03.04 FALSO PISO
02.03.04.01 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGÓN E=4" m2 0.00 0.00%
02.03.05 VEREDAS
02.03.05.01 VEREDAS f'c=175 Kg/cm2 m3 0.00 0.00%
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 0.00 0.00%
02.04 CONCRETO ARMADO
02.04.01 ZAPATAS
02.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 111.45 100.00%
02.04.01.02 ACERO PARA ZAPATAS GRADO 60 kg 0.00 0.00%
02.04.02 VIGAS DE CIMENTACION
02.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C=210 KG/CM2 m3 16.84 100.00%
02.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2 0.00 0.00%
02.04.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION kg 0.00 0.00%
02.04.03 SOBRECIMIENTOS ARMADOS
02.04.03.01 SOBRECIMIENTOS DE C.A. f'c=175 Kg/cm2 m3 22.61 100.00%
02.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS ARMADOS m2 347.84 100.00%
02.04.03.03 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 636.37 35.91%
02.04.04 COLUMNAS
02.04.04.01 CONCRETO EN COLUMNETAS f'c=175 kg/cm2. m3 2.85 24.72%
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

02.04.04.02 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 30.93 79.35%


02.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 0.00 0.00%
02.04.04.04 ACERO GRADO 60 EN COLUMNAS kg 0.00 0.00%
02.04.05 VIGAS
02.04.05.01 CONCRETO EN VIGUETAS f'c=175 kg/cm2. m3 0.00 0.00%
02.04.05.02 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 0.00 0.00%
02.04.05.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 0.00 0.00%
02.04.05.04 ACERO GRADO 60 EN VIGAS kg 0.00 0.00%
02.04.06 LOSAS ALIGERADAS
02.04.06.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 m3 0.00 0.00%
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 0.00 0.00%
02.04.06.03 BLOQUETA P/ TECHO DE 30X30X15 CM PARA TECHO ALIGERADO und 0.00 0.00%
02.04.06.04 ACERO GRADO 60 EN LOSAS ALIGERADAS kg 0.00 0.00%
02.04.07 ESCALERAS
02.04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 0.00 0.00%
02.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 0.00 0.00%
02.04.07.03 ACERO GRADO 60 EN ESCALERAS kg 0.00 0.00%
02.05 DISEÑO DE MEZCLAS
02.05.01 DISEÑO DE MEZCLA P/CONCRETO F'C=175 KG/CM² und 0.00 0.00%
02.05.02 DISEÑO DE MEZCLA P/CONCRETO F'C=210 KG/CM² und 0.00 0.00%
02.06 PRUEBA DE ROTURA

02.06.01 PRUEBA DE ROTURA DE PROBETA und 20.00 50.00%


03 ARQUITECTURA
03.01 MUROS Y TABIQUES
03.01.01 MURO DE LADRILLO KK TIPO IV SOGA MEZCLA: C:A 1:5 x 1:5 CM m2 0.00 0.00%
03.01.02 MURO DE LADRILLO KK TIPO IV CABEZA MEZCLA: C:A 1:5 x 1:5 CM m2 0.00 0.00%
03.02 REVOQUES ENLUCIDOS Y MOLDURAS
03.02.01 TARRAJEO PRIMARIO Y RAYADO C/MEZC. C: A 1:5, E=1.5CM. m2 0.00 0.00%
03.02.02 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:5 x 1:5 CM m 0.00 0.00%
03.02.03 TARRAJEO DE MUROS EXTERIORES, E=1.5CM, C: A 1:5 m2 0.00 0.00%
03.02.04 TARRAJEO DE MUROS INTERIORES, E=1.5CM, C: A 1:5 m2 0.00 0.00%
03.02.05 TARRAJEO DE COLUMNAS, E=1.5cm, C:A 1:5 m2 0.00 0.00%
03.02.06 TARRAJEO DE COLUMNETAS, E=1.5cm, C:A 1:5 m2 0.00 0.00%
03.02.07 TARRAJEO DE VIGAS, E=1.5 CM, C: A 1:5 m2 0.00 0.00%
03.02.08 VESTIDURA DE DERRAMES, E=1.5CM, C: A 1:5 m 0.00 0.00%
03.02.09 EJECUCIÓN DE BRUÑAS EN FACHADA m 0.00 0.00%
03.02.10 TARRAJEO DE COBERTURA CON IMPERMEABILIZANTE m2 0.00 0.00%
03.03 CIELORRASOS
03.03.01 TARRAJEO DE CIELORRASO E=1.5cm, C:A 1:5 m2 0.00 0.00%
03.04 PISOS Y PAVIMENTOS
03.04.01 PISOS
03.04.01.01 PISO CERÁMICO 30 X 30 CM ANTIDESLIZANTE m2 0.00 0.00%
03.04.01.02 PORCELANATO 60X60 CM ANTIDESLIZANTE DE ALTO TRANSITO m2 0.00 0.00%
03.04.01.03 PISO DE CEMENTO SEMI PULIDO FROTACHADO Y BRUÑADO m2 0.00 0.00%
03.05 ZÓCALOS Y CONTRAZÓCALOS
03.05.01 ZÓCALOS
03.05.01.01 ZÓCALO DE CERÁMICO DE 30 X 30 CM. m2 0.00 0.00%
03.05.01.02 PORCELANATO DE 60 X 60 CM PARA FACHADA COLOR NEGRO m2 0.00 0.00%
03.05.01.03 PORCELANATO DE 60 X 60 cm PARA FACHADA COLOR BLANCO m2 0.00 0.00%
03.05.02 CONTRAZOCALOS
03.05.02.01 CONTRAZÓCALO DE PORCELANATO DE H=010 M m2 0.00 0.00%
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

03.06 CARPINTERÍA DE FENÓLICO


03.06.01 SEPARADORES DE MELAMINE DE E= 15MM m2 0.00 0.00%
03.06.02 PUERTA DE MELAMINE E= 15MM und 0.00 0.00%
03.07 CARPINTERIA DE MADERA
03.07.01 PUERTA APANELADA, E=35MM /INCL. COLOCACIÓN m2 0.00 0.00%
03.07.02 PUERTA CONTRAPLACADA E=45MM /INCL. COLOCACIÓN und 0.00 0.00%
03.08 CARPINTERÍA DE ALUMINIO
03.08.01 VENTANA DE ALUMINIO SEGÚN DISEÑO m2 0.00 0.00%
03.09 MURO CORTINA
03.09.01 MURO CORTINA DE ALUMINIO EN INGRESO PRINCIPAL m2 0.00 0.00%
03.09.02 MURO CORTINA DE ALUMINIO EN INTERIOR DE MODULO m2 0.00 0.00%
03.10 CARPINTERÍA METÁLICA
03.10.01 PUERTA EN MURO CORTINA EN INTERIOR DE MODULO (1.2 X 2.4) und 0.00 0.00%
03.10.02 PORTÓN TIPO REJA CORREDIZO (3.5MX3.15M) / INCL. INSTALACIÓN und 0.00 0.00%
03.11 OTROS
03.11.01 BARRA DE APOYO ABATIBLE VERTICAL DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS und 0.00 0.00%
03.11.02 BARRA DE APOYO DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS - LAVATORIOS und 0.00 0.00%
03.11.03 BARRA DE APOYO DE ACERO INOXIDABLE DE Ø 1" X 36" EN BAÑO DE DISCAPACITADOS und 0.00 0.00%
03.12 VIDRIOS, CRISTALES Y SIMILARES
03.12.01 VIDRIOS
03.12.01.01 VIDRIO TEMPLADO COLOR AZUL REFLEJANTE DE 6 MM m2 0.00 0.00%

03.12.01.02 VIDRIO INSULADO ESMERILADO EN MURO CORTINA INTERIOR m2 0.00 0.00%


03.12.01.03 VIDRIO DE SEGURIDAD EN MURO CORTINA EXTERIOR m2 0.00 0.00%
03.12.01.04 ESPEJO RECLINABLE (0.60X0.70) und 0.00 0.00%
03.12.01.05 PUERTA DE VIDRIO DE 10MM EN INGRESO PRINCIPAL m2 0.00 0.00%
03.13 CERRAJERIA
03.13.01 CERRADURA DE ACERO INOXIDABLE und 0.00 0.00%
03.13.02 BISAGRAS ALUMINIZADA CAPUCHINA DE 3 1/2"x3 1/2" pza 0.00 0.00%
03.13.03 BISAGRAS DE ACERO ALUMINIZADO PESADO DE 3. 1/2" X 3. 1/2" 04 POR C/PUERTA und 0.00 0.00%
03.13.04 CERRADURA PESADA DE 2 GOLPES und 0.00 0.00%
03.13.05 MANIJA DE BRONCE PARA PUERTAS DE 4" und 0.00 0.00%
03.14 PINTURA
03.14.01 PINTURA LÁTEX SOBRECIMIENTOS m2 0.00 0.00%
03.14.02 PINTURA LÁTEX EN MUROS EXTERIORES m2 0.00 0.00%
03.14.03 PINTURA LÁTEX EN MUROS INTERIORES m2 0.00 0.00%
03.14.04 PINTURA LÁTEX COLUMNAS m2 0.00 0.00%
03.14.05 PINTURA LÁTEX COLUMNETAS m2 0.00 0.00%
03.14.06 PINTURA LÁTEX VIGAS m2 0.00 0.00%
03.14.07 PINTURA LÁTEX DERRAMES EN VANOS DE PUERTAS Y VENTANAS m 0.00 0.00%
03.14.08 PINTURA DE CIELORRASOS, LÁTEX 02 MANOS, INC. IMPRIMANTE m2 0.00 0.00%
03.14.09 PINTURA EN PUERTAS DE MADERA C/BARNIZ - 2 MANOS m2 0.00 0.00%
03.15 VARIOS
03.15.01 JUNTA DE CONSTRUCCIÓN TEKNOPORT 1" m2 0.00 0.00%
03.16 EQUIPAMIENTO
03.16.01 ESCRITORIO DE DOS GAVETAS und 0.00 0.00%
03.16.02 SILLA EJECUTIVA ERGONÓMICA und 0.00 0.00%
03.16.03 ESCRITORIO TIPO L (1.30 X 1.94) und 0.00 0.00%
03.16.04 SILLA VISITANTE und 0.00 0.00%
03.16.05 ESTANTE und 0.00 0.00%
03.16.06 COMPUTADORA I5 und 0.00 0.00%
03.16.07 IMPRESORA MULTIFUNCIONAL und 0.00 0.00%
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

04 INSTALACIONES SANITARIAS
04.01 INSTALACIONES SANITARIAS DE AGUA
04.01.01 MOVIMIENTO DE TIERRAS
04.01.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE AGUA SECCIÓN 0.30 M m3 0.00 0.00%
04.01.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 0.00 0.00%
04.01.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 0.00 0.00%
04.01.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 0.00 0.00%
04.01.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 0.00 0.00%
04.01.01.06 CAMA DE ARENA m2 0.00 0.00%
04.01.02 APARATOS Y ACCESORIOS SANITARIOS INCLUIDO COLOCACIÓN
04.01.02.01 INODORO TANQUE BAJO DE LOSA und 0.00 0.00%
04.01.02.02 URINARIO BAMBI und 0.00 0.00%
04.01.02.03 PAPELERA PARA EMPOTRAR DE LOSA pza 0.00 0.00%
04.01.02.04 LAVATORIO DE PARED C/GRIFE.CROMADA 20X17CM.(JAMAICA O SIMIL) und 0.00 0.00%
04.01.03 SISTEMA DE AGUA FRIA
04.01.03.01 SALIDA DE AGUA FRÍA (RIEGO) CON TUBERÍA DE PVC-SAP 1/2" pto 0.00 0.00%
04.01.04 REDES DE DISTRIBUCIÓN
04.01.04.01 RED DE DISTRIBUCIÓN TUBERÍA DE 3/4" PVC-SAP C10 m 0.00 0.00%
04.01.04.02 RED DE DISTRIBUCIÓN TUBERÍA DE 1/2" PVC-SAP C10 m 0.00 0.00%
04.01.05 ACCESORIOS DE REDES
04.01.05.01 CODO PVC-SAP 1/2" pza 0.00 0.00%

04.01.05.02 TEE PVC SAP DE 3/4" pza 0.00 0.00%


04.01.05.03 TEE PVC SAP DE 1/2" pza 0.00 0.00%
04.01.05.04 UNIÓN PVC SAP DE 3/4" pza 0.00 0.00%
04.01.05.05 UNIÓN PVC SAP DE 1/2" pza 0.00 0.00%
04.01.05.06 REDUCCIÓN PVC-SAP DE 3/4" A 1/2" pza 0.00 0.00%
04.01.05.07 VÁLVULA DE COMPUERTA DE BRONCE UNIÓN ROSCADA 1/2" pza 0.00 0.00%
04.01.06 INSTALACIÓN DE TANQUE ELEVADO Y CISTERNA
04.01.06.01 INSTALACIÓN DE CISTERNA GLB 0.00 0.00%
04.01.06.02 INSTALACIÓN DE TANQUE ELEVADO GLB 0.00 0.00%
04.01.07 VARIOS
04.01.07.01 CAJA CON TAPA METÁLICA PARA VÁLVULAS DE 12" X 12" und 0.00 0.00%
04.02 INSTALACIONES SANITARIAS DE DESAGÜE
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE DESAGÜE SECCIÓN 0.30 M m 0.00 0.00%
04.02.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 0.00 0.00%
04.02.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 0.00 0.00%
04.02.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 0.00 0.00%
04.02.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 0.00 0.00%
04.02.01.06 CAMA DE ARENA m2 0.00 0.00%
04.02.02 SALIDAS DE DESAGÜE Y VENTILACIÓN
04.02.02.01 SALIDA DE DESAGUE DE PVC 2" pto 0.00 0.00%
04.02.02.02 SALIDA DE DESAGÜE DE PVC 4" pto 0.00 0.00%
04.02.02.03 SALIDA DE VENTILACIÓN EN PVC SAL 4" pto 0.00 0.00%
04.02.02.04 SALIDA DE VENTILACIÓN EN PVC SAL 2" pto 0.00 0.00%
04.02.03 REDES DE DERIVACIÓN
04.02.03.01 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 4" m 0.00 0.00%
04.02.03.02 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 2" m 0.00 0.00%
04.02.04 ACCESORIOS PARA REDES DE DERIVACIÓN
04.02.04.01 CODO PVC-SAL 2" X 45º pza 0.00 0.00%
04.02.04.02 CODO PVC-SAL 4" X 45º pza 0.00 0.00%
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

04.02.04.03 CODO PVC SAL 4" X 90° CON REDUCCIÓN A 2" pza 0.00 0.00%
04.02.04.04 YEE PVC-SAL DE 2" pza 0.00 0.00%
04.02.04.05 TEE PVC-SAL DE 4 pza 0.00 0.00%
04.02.04.06 REDUCCIÓN PVC-SAL 4"X 2" pza 0.00 0.00%
04.02.05 ADITAMENTOS VARIOS
04.02.05.01 SUMIDERO DE BRONCE 2" und 0.00 0.00%
04.02.05.02 REGISTRO ROSCADO DE BRONCE CROMADO 4" und 0.00 0.00%
04.02.05.03 SOMBRERO VENTILACIÓN PVC DE 2" und 0.00 0.00%
04.02.06 CAJAS DE REGISTRO
04.02.06.01 CAJA DE REGISTRO DE DESAGÜE 10" X 20" CON TAPA DE CONCRETO und 0.00 0.00%
04.03 SISTEMA DE AGUA DE LLUVIA
04.03.01 TUBERÍAS EN BAJANTES PLUVIALES
04.03.01.01 TUBERÍA PARA AGUAS PLUVIALES DE PVC SAL 3" m 0.00 0.00%
04.03.02 ACCESORIOS
04.03.02.01 CODO PVC-SAL 3" X 90° pza 0.00 0.00%
04.03.02.02 ABRAZADERA DE FIJACIÓN P/TUBERÍA PLUVIAL und 0.00 0.00%
05 INSTALACIONES ELÉCTRICAS Y COMUNICACIONES
05.01 INSTALACIONES ELÉCTRICAS
05.01.01 CANALIZACION Y/O TUBERIAS
05.01.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø20 MM m 0.00 0.00%
05.01.01.02 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø60 MM m 0.00 0.00%

05.01.01.03 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø43 MM m 0.00 0.00%


05.01.02 SALIDAS ELECTRICAS
05.01.02.01 SALIDA CON CAJA OCTOGONAL DE 100x100x50mm FG PESADA und 0.00 0.00%
05.01.02.02 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 0.00 0.00%
05.01.03 CAJAS DE INTERCONEXIÓN ELÉCTRICA F°G°
05.01.03.01 CAJA DE INTERCONEXION FG 200x200x150mm und 0.00 0.00%
05.01.04 CONDUCTORES ELÉCTRICOS
05.01.04.01 CABLE TIPO FPL-2x16AWG m 0.00 0.00%
05.01.04.02 CABLE TIPO NH-80 - 2.5 mm2 m 0.00 0.00%
05.01.04.03 CABLE TIPO NH-80 - 4.0 mm2 m 0.00 0.00%
05.01.04.04 CABLE TIPO NH-80 - 16.0 mm2 m 0.00 0.00%
05.01.04.05 CABLE TIPO N2XOH - 70.0 mm2 m 0.00 0.00%
05.01.05 CONDUCTOR ELÉCTRICO PARA PUESTA A TIERRA
05.01.05.01 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 2.5 mm2 m 0.00 0.00%
05.01.05.02 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 4.0 mm2 m 0.00 0.00%
05.01.05.03 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 10.0 mm2 m 0.00 0.00%
05.01.06 EQUIPOS LUMINARAS
05.01.06.01 PANEL LED RECTANGULAR PARA ADOSAR DE 40W, 220V. und 0.00 0.00%
05.01.06.02 LÁMPARA LED DE 10W,220V CON SOQUETE PARA ADOSAR und 0.00 0.00%
05.01.07 ARTEFACTOS ELECTRICOS
05.01.07.01 INTERRUPTOR SIMPLE und 0.00 0.00%
05.01.07.02 INTERRUPTOR DOBLE und 0.00 0.00%
05.01.07.03 INTERRUPTOR CONMUTADOR und 0.00 0.00%
05.01.07.04 TOMACORRIENTE SIMPLE (LUZ DE EMERGENCIA) 15A, 220V und 0.00 0.00%
05.01.07.05 TOMACORRIENTE DOBLE CON TOMA A TIERRA 15A, 220V und 0.00 0.00%
05.01.08 EQUIPOS DE SEGURIDAD
05.01.08.01 LUZ ESTROBOSCOPICA CON PARLANTE DEL SISTEMA DE ALARMA CONTRA INCENDIO. und 0.00 0.00%
05.01.08.02 ESTACIÓN MANUAL DE ALARMA CONTRA INCENDIO. und 0.00 0.00%
05.01.08.03 EQUIPO LUZ DE EMERGENCIA, 220V. und 0.00 0.00%
05.01.09 TABLEROS GENERALES Y DE DISTRIBUCIÓN
RESUMEN DE METRADOS EJECUTADOS

CORRESPONDIENTE AL MES DE MARZO DE 2021

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

DEPARTAMENTO JUNÍN
PROVINCIA CHUPACA
DISTRITO CHONGOS BAJO
RESIDENTE DE OBRA ING. JUVENAL LUIS AQUINO CALDERON
SUPERVISOR DE OBRA ING. JHOSEF J. CASTRO ROSAS

METRADO
ITEM DESCRIPCIÓN UND %
EJECUTADO

05.01.09.01 TABLERO GENERAL TG 380 TRIFASICO 24 POLOS und 0.00 0.00%


05.01.09.02 TABLERO DE DISTRIBUCIÓN TD 380V TRIFÁSICO 24 POLOS und 0.00 0.00%
05.01.10 EQUIPOS - INTERRUPTORES TÉRMICOS - INTERRUPTORES DIFERENCIALES
05.01.10.01 INTERRUPTOR TÉRMICO 2x15A und 0.00 0.00%
05.01.10.02 INTERRUPTOR TÉRMICO 2x20A und 0.00 0.00%
05.01.10.03 INTERRUPTOR TÉRMICO 3X63A und 0.00 0.00%
05.01.10.04 INTERRUPTOR TÉRMICO 3x70 und 0.00 0.00%
05.01.10.05 INTERRUPTOR TÉRMICO 3x80A und 0.00 0.00%
05.01.10.06 INTERRUPTOR DIFERENCIAL 2x25A-30mA und 0.00 0.00%
05.01.11 SISTEMA DE PUESTA A TIERRA
05.01.11.01 PUESTA A TIERRA und 0.00 0.00%
05.01.12 VARIOS
05.01.12.01 PRUEBAS DE PUESTAS A TIERRA GLB 0.00 0.00%
05.01.12.02 PRUEBAS DE AISLAMIENTO GLB 0.00 0.00%
05.01.12.03 PRUEBAS DE FUNCIONAMIENTO DE EQUIPOS ELÉCTRICOS GLB 0.00 0.00%
05.01.12.04 PRUEBAS DE CONTINUIDAD GLB 0.00 0.00%
05.01.12.05 PRUEBAS DE ILUMINACIÓN GLB 0.00 0.00%
05.01.12.06 PROTOCOLO DE PRUEBAS ELECTRICOS GLB 0.00 0.00%
05.01.13 INSTALACIÓN DE ELECTROBOMBA
05.01.13.01 INSTALACIÓN DE ELECTROBOMBA INCL. ACCESORIOS GLB 0.00 0.00%
05.02 INSTALACIONES DE COMUNICACIONES CCTV

05.02.01 CANALIZACIONES Y TUBERIA DE PVC - SAP


05.02.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø25MM m 0.00 0.00%
05.02.02 SALIDAS DE COMUNICACIONES
05.02.02.01 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 0.00 0.00%
05.02.03 CAJAS DE PASO E INTERCONEXIÓN ELÉCTRICA
05.02.03.01 SALIDA CON CAJA DE PASO DE 100x100x100mm FG PESADA und 0.00 0.00%
05.02.04 CABLEADO ESTRUCTURADO
05.02.04.01 CABLE F/UTP - CAT 6 A. m 0.00 0.00%
05.02.05 EQUIPOS DE SISTEMA VOZ Y DATA
05.02.05.01 CONECTOR TIPO BALUM und 0.00 0.00%
05.02.05.02 EQUIPO ACCESS POINT und 0.00 0.00%
05.02.05.03 EQUIPO DVR und 0.00 0.00%
05.02.06 EQUIPOS DE SISTEMA DE TELEFONÍA Y PROYECTOR MULTIMEDIA
05.02.06.01 EQUIPO PROYECTOR MULTIMEDIA, EN TECHO, UN CONECTOR RJ45, 1UTP CAT. 6A. und 0.00 0.00%
05.02.07 EQUIPOS DE SISTEMA DE CIRCUITO CERRADO DE TELEVISIÓN
05.02.07.01 EQUIPO CAMARA, FIJA, PARA INTERIOR, DOMO, 1.3MP, EN TECHO, UN CONECTOR BALUM, 1UTP CAT. 6A. und 0.00 0.00%
05.02.07.02 EQUIPO CÁMARA, FIJA, PARA INTERIOR, DOMO TIPO PTZ und 0.00 0.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %

01 TRABAJOS PRELIMINARES

01.01 CARTEL IDENTIFICACIÓN DE OBRA, INCL GIGANTOGRAFIA GLB 1 1350.08 1350.08 1.00 1350.08 100.00% 0.00 0.00 0.00% 1.00 1,350.08 100.00% - 0.00 0.00%
01.02 ALMACÉN, OFICINAS Y GUARDIANÍA mes 4 1250.00 5000.00 2.77 3462.50 69.25% 0.23 287.50 5.75% 3.00 3,750.00 75.00% 1.00 1,250.00 25.00%

01.03 CERCO PERIMETRICO PROVISIONAL GLB 1 7000.00 7000.00 1.00 7000.00 100.00% 0.00 0.00 0.00% 1.00 7,000.00 100.00% - 0.00 0.00%
01.04 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIAS, EQUIPOS Y HERRAMIENTAS GLB 1 8000.00 8000.00 0.69 5520.00 69.00% 0.06 480.00 6.00% 0.75 6,000.00 75.00% 0.25 2,000.00 25.00%

01.05 IMPLEMENTACIÓN DE SALUD, SEGURIDAD EN EL TRABAJO. GLB 1 17500.00 17500.00 0.80 14000.00 80.00% 0.04 700.00 4.00% 0.84 14,700.00 84.00% 0.16 2,800.00 16.00%
01.06 IMPLEMENTACIÓN DEL PLAN CONTRA COVID-19. GLB 1 20000.00 20000.00 0.80 16000.00 80.00% 0.04 800.00 4.00% 0.84 16,800.00 84.00% 0.16 3,200.00 16.00%
01.07 MITIGACION DE IMPACTO AMBIENTAL GLB 1 4000.00 4000.00 0.80 3200.00 80.00% 0.04 160.00 4.00% 0.84 3,360.00 84.00% 0.16 640.00 16.00%

01.08 FLETE PARA TRANSPORTE DE MATERIALES GLB 1 7500.00 7500.00 0.69 5175.00 69.00% 0.06 450.00 6.00% 0.75 5,625.00 75.00% 0.25 1,875.00 25.00%
01.09 DEMOLICIÓN DE PABELLÓN DE AULAS Y OTROS GLB 1 59000.00 59000.00 1.00 59000.00 100.00% 0.00 0.00 0.00% 1.00 59,000.00 100.00% - 0.00 0.00%
01.10 ELIMINACIÓN DEL MATERIAL DE DEMOLICIÓN GLB 1 29000.00 29000.00 1.00 29000.00 100.00% 0.00 0.00 0.00% 1.00 29,000.00 100.00% - 0.00 0.00%
02 ESTRUCTURAS 0.00
02.01 TRABAJOS PRELIMINARES 0.00
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 510.18 3.81 1943.79 510.18 1943.79 100.00% 0.00 0.00 0.00% 510.18 1,943.79 100.00% - 0.00 0.00%

02.01.02 TRAZO Y REPLANTEO m2 510.18 5.69 2902.92 510.18 2902.92 100.00% 0.00 0.00 0.00% 510.18 2,902.92 100.00% - 0.00 0.00%
02.02 MOVIMIENTO DE TIERRAS 0.00 0.00

02.02.01 EXCAVACIÓN CON MAQUINARIA P/CIMENTACIÓN m3 589.36 61.22 36080.62 589.36 36080.62 100.00% 0.00 0.00 0.00% 589.36 36,080.62 100.00% - 0.00 0.00%
02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO CAPAS CADA 0.20M m3 51.94 73.89 3837.85 51.94 3837.85 100.00% 0.00 0.00 0.00% 51.94 3,837.85 100.00% - 0.00 0.00%
02.02.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO CAPAS CADA 0.20M m3 171.36 73.89 12661.79 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 171.36 12,661.79 100.00%

02.02.04 CAMA DE ARENA PARA VIGAS DE CIMENTACIÓN m3 3.09 69.70 215.37 3.09 215.37 100.00% 0.00 0.00 0.00% 3.09 215.37 100.00% - 0.00 0.00%
02.02.05 NIVELACIÓN Y COMPACTACIÓN EN TERRENO NORMAL m2 527.51 25.55 13477.88 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 527.51 13,477.88 100.00%

02.02.06 AFIRMADO DE 4" PARA VEREDAS CON EQUIPO LIVIANO m2 527.54 17.88 9432.42 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 527.54 9,432.42 100.00%
02.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA DIST./PROM = 5KM m3 668.53 20.07 13417.40 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 668.53 13,417.40 100.00%
02.03 CONCRETO SIMPLE 0.00
02.03.01 SOLADO 0.00
02.03.01.01 SOLADO EN ZAPATA MEZCLA C:H 1:10 m2 18.72 33.52 627.49 18.72 627.49 100.00% 0.00 0.00 0.00% 18.72 627.49 100.00% - 0.00 0.00%

02.03.01.02 SOLADO EN VIGAS DE CIMENTACION MEZCLA C:H 1:10 m2 10.24 32.87 336.59 10.24 336.59 100.00% 0.00 0.00 0.00% 10.24 336.59 100.00% - 0.00 0.00%
02.03.02 CIMIENTOS CORRIDOS 0.00
02.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G m3 4.84 239.45 1158.94 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.84 1,158.94 100.00%
02.03.03 SOBRECIMIENTOS 0.00
02.03.03.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 1.39 307.69 427.69 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.39 427.69 100.00%
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS m2 20.52 39.98 820.39 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 20.52 820.39 100.00%

02.03.04 FALSO PISO 0.00


02.03.04.01 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGÓN E=4" m2 468.99 32.25 15124.93 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 468.99 15,124.93 100.00%

02.03.05 VEREDAS 0.00


02.03.05.01 VEREDAS f'c=175 Kg/cm2 m3 6.92 385.50 2667.66 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.92 2,667.66 100.00%
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 16.73 53.21 890.20 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 16.73 890.20 100.00%

02.04 CONCRETO ARMADO 0.00


02.04.01 ZAPATAS 0.00

02.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 111.45 395.74 44105.22 - 0.00 0.00% 111.45 44105.22 100.00% 111.45 44,105.22 100.00% - 0.00 0.00%
02.04.01.02 ACERO PARA ZAPATAS GRADO 60 kg 4896.33 10.82 52978.29 4,896.33 52978.29 100.00% 0.00 0.00 0.00% 4,896.33 52,978.29 100.00% - 0.00 0.00%
02.04.02 VIGAS DE CIMENTACION 0.00
02.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C=210 KG/CM2 m3 16.84 407.56 6863.31 - 0.00 0.00% 16.84 6863.31 100.00% 16.84 6,863.31 100.00% - 0.00 0.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
02.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2 123.2 53.21 6555.47 123.20 6555.47 100.00% 0.00 0.00 0.00% 123.20 6,555.47 100.00% - 0.00 0.00%
02.04.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION kg 4352.96 10.82 47099.03 4,352.96 47099.03 100.00% 0.00 0.00 0.00% 4,352.96 47,099.03 100.00% - 0.00 0.00%

02.04.03 SOBRECIMIENTOS ARMADOS 0.00


02.04.03.01 SOBRECIMIENTOS DE C.A. f'c=175 Kg/cm2 m3 22.61 385.50 8716.16 - 0.00 0.00% 22.61 8716.16 100.00% 22.61 8,716.16 100.00% - 0.00 0.00%

02.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS ARMADOS m2 347.84 53.21 18508.57 - 0.00 0.00% 347.84 18508.57 100.00% 347.84 18,508.57 100.00% - 0.00 0.00%
02.04.03.03 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 1772.05 10.82 19173.58 1,135.68 12288.06 64.09% 636.37 6885.52 35.91% 1,772.05 19,173.58 100.00% - 0.00 0.00%

02.04.04 COLUMNAS 0.00


02.04.04.01 CONCRETO EN COLUMNETAS f'c=175 kg/cm2. m3 11.53 385.50 4444.82 - 0.00 0.00% 2.85 1098.68 24.72% 2.85 1,098.68 24.72% 8.68 3,346.14 75.28%
02.04.04.02 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 38.98 418.50 16313.13 - 0.00 0.00% 30.93 12944.21 79.35% 30.93 12,944.21 79.35% 8.05 3,368.92 20.65%

02.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 606.12 27.58 16716.79 376.01 10370.36 62.04% 0.00 0.00 0.00% 376.01 10,370.36 62.04% 230.11 6,346.43 37.96%
02.04.04.04 ACERO GRADO 60 EN COLUMNAS kg 8646.29 10.82 93552.86 8,567.22 92697.32 99.09% 0.00 0.00 0.00% 8,567.22 92,697.32 99.09% 79.07 855.54 0.91%
02.04.05 VIGAS 0.00
02.04.05.01 CONCRETO EN VIGUETAS f'c=175 kg/cm2. m3 2.99 385.50 1152.65 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.99 1,152.65 100.00%
02.04.05.02 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 33.49 460.03 15406.40 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 33.49 15,406.40 100.00%
02.04.05.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 289.38 72.68 21032.14 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 289.38 21,032.14 100.00%

02.04.05.04 ACERO GRADO 60 EN VIGAS kg 5508.09 10.82 59597.53 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 5,508.09 59,597.53 100.00%
02.04.06 LOSAS ALIGERADAS 0.00

02.04.06.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 m3 34.77 421.60 14659.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 34.77 14,659.03 100.00%
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 397.38 51.06 20290.22 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 397.38 20,290.22 100.00%
02.04.06.03 BLOQUETA P/ TECHO DE 30X30X15 CM PARA TECHO ALIGERADO und 3312 3.12 10333.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3,312.00 10,333.44 100.00%

02.04.06.04 ACERO GRADO 60 EN LOSAS ALIGERADAS kg 1963.76 10.82 21247.88 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1,963.76 21,247.88 100.00%
02.04.07 ESCALERAS 0.00

02.04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 12.22 477.70 5837.49 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.22 5,837.49 100.00%
02.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 62.67 81.92 5133.93 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 62.67 5,133.93 100.00%
02.04.07.03 ACERO GRADO 60 EN ESCALERAS kg 984.81 10.70 10537.47 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 984.81 10,537.47 100.00%
02.05 DISEÑO DE MEZCLAS 0.00
02.05.01 DISEÑO DE MEZCLA P/CONCRETO F'C=175 KG/CM² und 1 380.00 380.00 1.00 380.00 100.00% 0.00 0.00 0.00% 1.00 380.00 100.00% - 0.00 0.00%

02.05.02 DISEÑO DE MEZCLA P/CONCRETO F'C=210 KG/CM² und 1 380.00 380.00 1.00 380.00 100.00% 0.00 0.00 0.00% 1.00 380.00 100.00% - 0.00 0.00%
02.06 PRUEBA DE ROTURA 0.00
02.06.01 PRUEBA DE ROTURA DE PROBETA und 40 50.00 2000.00 - 0.00 0.00% 20.00 1000.00 50.00% 20.00 1,000.00 50.00% 20.00 1,000.00 50.00%
03 ARQUITECTURA 0.00
03.01 MUROS Y TABIQUES 0.00
03.01.01 MURO DE LADRILLO KK TIPO IV SOGA MEZCLA: C:A 1:5 x 1:5 CM m2 426.2 102.83 43826.15 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 426.20 43,826.15 100.00%

03.01.02 MURO DE LADRILLO KK TIPO IV CABEZA MEZCLA: C:A 1:5 x 1:5 CM m2 5.87 151.22 887.66 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 5.87 887.66 100.00%
03.02 REVOQUES ENLUCIDOS Y MOLDURAS 0.00

03.02.01 TARRAJEO PRIMARIO Y RAYADO C/MEZC. C: A 1:5, E=1.5CM. m2 57.03 20.45 1166.26 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 57.03 1,166.26 100.00%
03.02.02 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:5 x 1:5 CM m 72.11 29.31 2113.54 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 72.11 2,113.54 100.00%
03.02.03 TARRAJEO DE MUROS EXTERIORES, E=1.5CM, C: A 1:5 m2 28.32 24.28 687.61 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 28.32 687.61 100.00%

03.02.04 TARRAJEO DE MUROS INTERIORES, E=1.5CM, C: A 1:5 m2 583.68 16.64 9712.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 583.68 9,712.44 100.00%
03.02.05 TARRAJEO DE COLUMNAS, E=1.5cm, C:A 1:5 m2 151.1 31.25 4721.88 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 151.10 4,721.88 100.00%

03.02.06 TARRAJEO DE COLUMNETAS, E=1.5cm, C:A 1:5 m2 111.79 31.25 3493.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 111.79 3,493.44 100.00%
03.02.07 TARRAJEO DE VIGAS, E=1.5 CM, C: A 1:5 m2 206.69 37.93 7839.75 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 206.69 7,839.75 100.00%
03.02.08 VESTIDURA DE DERRAMES, E=1.5CM, C: A 1:5 m 137.4 12.62 1733.99 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 137.40 1,733.99 100.00%
03.02.09 EJECUCIÓN DE BRUÑAS EN FACHADA m 216.67 8.34 1807.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 216.67 1,807.03 100.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
03.02.10 TARRAJEO DE COBERTURA CON IMPERMEABILIZANTE m2 634.79 32.16 20414.85 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 634.79 20,414.85 100.00%
03.03 CIELORRASOS 0.00

03.03.01 TARRAJEO DE CIELORRASO E=1.5cm, C:A 1:5 m2 443.77 28.77 12767.26 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 443.77 12,767.26 100.00%
03.04 PISOS Y PAVIMENTOS 0.00

03.04.01 PISOS 0.00


03.04.01.01 PISO CERÁMICO 30 X 30 CM ANTIDESLIZANTE m2 38.71 80.97 3134.35 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 38.71 3,134.35 100.00%

03.04.01.02 PORCELANATO 60X60 CM ANTIDESLIZANTE DE ALTO TRANSITO m2 445.42 78.87 35130.28 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 445.42 35,130.28 100.00%
03.04.01.03 PISO DE CEMENTO SEMI PULIDO FROTACHADO Y BRUÑADO m2 63.93 25.00 1598.25 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 63.93 1,598.25 100.00%
03.05 ZÓCALOS Y CONTRAZÓCALOS 0.00

03.05.01 ZÓCALOS 0.00


03.05.01.01 ZÓCALO DE CERÁMICO DE 30 X 30 CM. m2 50.45 71.59 3611.72 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 50.45 3,611.72 100.00%
03.05.01.02 PORCELANATO DE 60 X 60 CM PARA FACHADA COLOR NEGRO m2 48.81 91.47 4464.65 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 48.81 4,464.65 100.00%
03.05.01.03 PORCELANATO DE 60 X 60 cm PARA FACHADA COLOR BLANCO m2 13.93 91.47 1274.18 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 13.93 1,274.18 100.00%
03.05.02 CONTRAZOCALOS 0.00
03.05.02.01 CONTRAZÓCALO DE PORCELANATO DE H=010 M m2 224.45 29.98 6729.01 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 224.45 6,729.01 100.00%

03.06 CARPINTERÍA DE FENÓLICO 0.00


03.06.01 SEPARADORES DE MELAMINE DE E= 15MM m2 16.6 175.82 2918.61 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 16.60 2,918.61 100.00%

03.06.02 PUERTA DE MELAMINE E= 15MM und 15.84 469.27 7433.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 15.84 7,433.24 100.00%
03.07 CARPINTERIA DE MADERA 0.00
03.07.01 PUERTA APANELADA, E=35MM /INCL. COLOCACIÓN m2 3 382.00 1146.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.00 1,146.00 100.00%

03.07.02 PUERTA CONTRAPLACADA E=45MM /INCL. COLOCACIÓN und 2 350.00 700.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 700.00 100.00%
03.08 CARPINTERÍA DE ALUMINIO 0.00

03.08.01 VENTANA DE ALUMINIO SEGÚN DISEÑO m2 13.06 240.00 3134.40 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 13.06 3,134.40 100.00%
03.09 MURO CORTINA 0.00
03.09.01 MURO CORTINA DE ALUMINIO EN INGRESO PRINCIPAL m2 159.16 299.30 47636.59 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 159.16 47,636.59 100.00%
03.09.02 MURO CORTINA DE ALUMINIO EN INTERIOR DE MODULO m2 86.75 296.30 25704.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 86.75 25,704.03 100.00%
03.10 CARPINTERÍA METÁLICA 0.00

03.10.01 PUERTA EN MURO CORTINA EN INTERIOR DE MODULO (1.2 X 2.4) und 6 320.00 1920.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.00 1,920.00 100.00%
03.10.02 PORTÓN TIPO REJA CORREDIZO (3.5MX3.15M) / INCL. INSTALACIÓN und 1 360.00 360.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 360.00 100.00%
03.11 OTROS 0.00
03.11.01 BARRA DE APOYO ABATIBLE VERTICAL DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS und 1 544.30 544.30 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 544.30 100.00%
03.11.02 BARRA DE APOYO DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS - LAVATORIOS und 1 544.30 544.30 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 544.30 100.00%
03.11.03 BARRA DE APOYO DE ACERO INOXIDABLE DE Ø 1" X 36" EN BAÑO DE DISCAPACITADOS und 1 628.59 628.59 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 628.59 100.00%

03.12 VIDRIOS, CRISTALES Y SIMILARES 0.00


03.12.01 VIDRIOS 0.00

03.12.01.01 VIDRIO TEMPLADO COLOR AZUL REFLEJANTE DE 6 MM m2 13.06 94.60 1235.48 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 13.06 1,235.48 100.00%
03.12.01.02 VIDRIO INSULADO ESMERILADO EN MURO CORTINA INTERIOR m2 101.17 92.59 9367.33 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 101.17 9,367.33 100.00%
03.12.01.03 VIDRIO DE SEGURIDAD EN MURO CORTINA EXTERIOR m2 86.75 117.74 10213.95 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 86.75 10,213.95 100.00%

03.12.01.04 ESPEJO RECLINABLE (0.60X0.70) und 3 52.54 157.62 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.00 157.62 100.00%
03.12.01.05 PUERTA DE VIDRIO DE 10MM EN INGRESO PRINCIPAL m2 6.71 365.00 2449.15 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.71 2,449.15 100.00%

03.13 CERRAJERIA 0.00


03.13.01 CERRADURA DE ACERO INOXIDABLE und 17 101.07 1718.19 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 17.00 1,718.19 100.00%
03.13.02 BISAGRAS ALUMINIZADA CAPUCHINA DE 3 1/2"x3 1/2" pza 12 18.55 222.60 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.00 222.60 100.00%
03.13.03 BISAGRAS DE ACERO ALUMINIZADO PESADO DE 3. 1/2" X 3. 1/2" 04 POR C/PUERTA und 36 25.57 920.52 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 36.00 920.52 100.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
03.13.04 CERRADURA PESADA DE 2 GOLPES und 3 81.07 243.21 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.00 243.21 100.00%
03.13.05 MANIJA DE BRONCE PARA PUERTAS DE 4" und 17 41.14 699.38 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 17.00 699.38 100.00%

03.14 PINTURA 0.00


03.14.01 PINTURA LÁTEX SOBRECIMIENTOS m2 72.11 11.39 821.33 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 72.11 821.33 100.00%

03.14.02 PINTURA LÁTEX EN MUROS EXTERIORES m2 28.32 13.78 390.25 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 28.32 390.25 100.00%
03.14.03 PINTURA LÁTEX EN MUROS INTERIORES m2 583.68 11.39 6648.12 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 583.68 6,648.12 100.00%

03.14.04 PINTURA LÁTEX COLUMNAS m2 151.1 11.39 1721.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 151.10 1,721.03 100.00%
03.14.05 PINTURA LÁTEX COLUMNETAS m2 111.79 11.39 1273.29 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 111.79 1,273.29 100.00%
03.14.06 PINTURA LÁTEX VIGAS m2 206.69 13.78 2848.19 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 206.69 2,848.19 100.00%

03.14.07 PINTURA LÁTEX DERRAMES EN VANOS DE PUERTAS Y VENTANAS m 137.4 2.66 365.48 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 137.40 365.48 100.00%
03.14.08 PINTURA DE CIELORRASOS, LÁTEX 02 MANOS, INC. IMPRIMANTE m2 443.77 13.78 6115.15 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 443.77 6,115.15 100.00%
03.14.09 PINTURA EN PUERTAS DE MADERA C/BARNIZ - 2 MANOS m2 24.56 14.02 344.33 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 24.56 344.33 100.00%
03.15 VARIOS 0.00
03.15.01 JUNTA DE CONSTRUCCIÓN TEKNOPORT 1" m2 1096.47 14.95 16392.23 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1,096.47 16,392.23 100.00%
03.16 EQUIPAMIENTO 0.00

03.16.01 ESCRITORIO DE DOS GAVETAS und 11 190.00 2090.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 11.00 2,090.00 100.00%
03.16.02 SILLA EJECUTIVA ERGONÓMICA und 17 150.00 2550.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 17.00 2,550.00 100.00%

03.16.03 ESCRITORIO TIPO L (1.30 X 1.94) und 7 150.00 1050.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 1,050.00 100.00%
03.16.04 SILLA VISITANTE und 25 100.00 2500.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 25.00 2,500.00 100.00%
03.16.05 ESTANTE und 12 260.00 3120.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.00 3,120.00 100.00%

03.16.06 COMPUTADORA I5 und 16 2200.00 35200.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 16.00 35,200.00 100.00%
03.16.07 IMPRESORA MULTIFUNCIONAL und 11 670.00 7370.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 11.00 7,370.00 100.00%

04 INSTALACIONES SANITARIAS 0.00


04.01 INSTALACIONES SANITARIAS DE AGUA 0.00
04.01.01 MOVIMIENTO DE TIERRAS 0.00
04.01.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE AGUA SECCIÓN 0.30 M m3 4.35 45.84 199.40 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.35 199.40 100.00%
04.01.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 21.77 4.58 99.71 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 21.77 99.71 100.00%

04.01.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 5.81 36.78 213.69 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 5.81 213.69 100.00%
04.01.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 2.91 22.92 66.70 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.91 66.70 100.00%
04.01.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 14.52 5.65 82.04 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 14.52 82.04 100.00%
04.01.01.06 CAMA DE ARENA m2 12.72 44.85 570.49 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.72 570.49 100.00%
04.01.02 APARATOS Y ACCESORIOS SANITARIOS INCLUIDO COLOCACIÓN 0.00
04.01.02.01 INODORO TANQUE BAJO DE LOSA und 7 408.21 2857.47 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 2,857.47 100.00%

04.01.02.02 URINARIO BAMBI und 2 388.21 776.42 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 776.42 100.00%
04.01.02.03 PAPELERA PARA EMPOTRAR DE LOSA pza 7 59.16 414.12 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 414.12 100.00%

04.01.02.04 LAVATORIO DE PARED C/GRIFE.CROMADA 20X17CM.(JAMAICA O SIMIL) und 7 348.61 2440.27 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 2,440.27 100.00%
04.01.03 SISTEMA DE AGUA FRIA 0.00
04.01.03.01 SALIDA DE AGUA FRÍA (RIEGO) CON TUBERÍA DE PVC-SAP 1/2" pto 22 78.27 1721.94 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 22.00 1,721.94 100.00%

04.01.04 REDES DE DISTRIBUCIÓN 0.00


04.01.04.01 RED DE DISTRIBUCIÓN TUBERÍA DE 3/4" PVC-SAP C10 m 29.05 7.78 226.01 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 29.05 226.01 100.00%

04.01.04.02 RED DE DISTRIBUCIÓN TUBERÍA DE 1/2" PVC-SAP C10 m 45.53 7.78 354.22 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 45.53 354.22 100.00%
04.01.05 ACCESORIOS DE REDES 0.00
04.01.05.01 CODO PVC-SAP 1/2" pza 26 9.01 234.26 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 26.00 234.26 100.00%
04.01.05.02 TEE PVC SAP DE 3/4" pza 3 8.51 25.53 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.00 25.53 100.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
04.01.05.03 TEE PVC SAP DE 1/2" pza 20 8.51 170.20 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 20.00 170.20 100.00%
04.01.05.04 UNIÓN PVC SAP DE 3/4" pza 27 8.81 237.87 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 27.00 237.87 100.00%

04.01.05.05 UNIÓN PVC SAP DE 1/2" pza 25 8.41 210.25 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 25.00 210.25 100.00%
04.01.05.06 REDUCCIÓN PVC-SAP DE 3/4" A 1/2" pza 2 8.91 17.82 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 17.82 100.00%

04.01.05.07 VÁLVULA DE COMPUERTA DE BRONCE UNIÓN ROSCADA 1/2" pza 4 97.24 388.96 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 388.96 100.00%
04.01.06 INSTALACIÓN DE TANQUE ELEVADO Y CISTERNA 0.00

04.01.06.01 INSTALACIÓN DE CISTERNA GLB 1 15000.00 15000.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 15,000.00 100.00%
04.01.06.02 INSTALACIÓN DE TANQUE ELEVADO GLB 1 6800.00 6800.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 6,800.00 100.00%
04.01.07 VARIOS 0.00

04.01.07.01 CAJA CON TAPA METÁLICA PARA VÁLVULAS DE 12" X 12" und 4 316.20 1264.80 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 1,264.80 100.00%
04.02 INSTALACIONES SANITARIAS DE DESAGÜE 0.00
04.02.01 MOVIMIENTO DE TIERRAS 0.00
04.02.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE DESAGÜE SECCIÓN 0.30 M m 63.33 45.84 2903.05 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 63.33 2,903.05 100.00%
04.02.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 12.67 4.58 58.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.67 58.03 100.00%
04.02.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 3.8 36.78 139.76 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.80 139.76 100.00%

04.02.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 6.33 22.92 145.08 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.33 145.08 100.00%
04.02.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 1.9 5.65 10.74 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.90 10.74 100.00%

04.02.01.06 CAMA DE ARENA m2 12.67 44.85 568.25 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.67 568.25 100.00%
04.02.02 SALIDAS DE DESAGÜE Y VENTILACIÓN 0.00
04.02.02.01 SALIDA DE DESAGUE DE PVC 2" pto 18 76.96 1385.28 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 18.00 1,385.28 100.00%

04.02.02.02 SALIDA DE DESAGÜE DE PVC 4" pto 16 84.84 1357.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 16.00 1,357.44 100.00%
04.02.02.03 SALIDA DE VENTILACIÓN EN PVC SAL 4" pto 2 82.73 165.46 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 165.46 100.00%

04.02.02.04 SALIDA DE VENTILACIÓN EN PVC SAL 2" pto 9 76.96 692.64 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 9.00 692.64 100.00%
04.02.03 REDES DE DERIVACIÓN 0.00
04.02.03.01 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 4" m 34.26 14.67 502.59 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 34.26 502.59 100.00%
04.02.03.02 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 2" m 29.07 10.39 302.04 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 29.07 302.04 100.00%
04.02.04 ACCESORIOS PARA REDES DE DERIVACIÓN 0.00

04.02.04.01 CODO PVC-SAL 2" X 45º pza 19 14.34 272.46 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 19.00 272.46 100.00%
04.02.04.02 CODO PVC-SAL 4" X 45º pza 7 22.81 159.67 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 159.67 100.00%
04.02.04.03 CODO PVC SAL 4" X 90° CON REDUCCIÓN A 2" pza 6 46.65 279.90 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.00 279.90 100.00%
04.02.04.04 YEE PVC-SAL DE 2" pza 15 14.74 221.10 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 15.00 221.10 100.00%
04.02.04.05 TEE PVC-SAL DE 4 pza 3 19.94 59.82 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 3.00 59.82 100.00%
04.02.04.06 REDUCCIÓN PVC-SAL 4"X 2" pza 7 16.79 117.53 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.00 117.53 100.00%

04.02.05 ADITAMENTOS VARIOS 0.00


04.02.05.01 SUMIDERO DE BRONCE 2" und 4 49.06 196.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 196.24 100.00%

04.02.05.02 REGISTRO ROSCADO DE BRONCE CROMADO 4" und 8 73.03 584.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 8.00 584.24 100.00%
04.02.05.03 SOMBRERO VENTILACIÓN PVC DE 2" und 6 18.51 111.06 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.00 111.06 100.00%
04.02.06 CAJAS DE REGISTRO 0.00

04.02.06.01 CAJA DE REGISTRO DE DESAGÜE 10" X 20" CON TAPA DE CONCRETO und 5 196.89 984.45 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 5.00 984.45 100.00%
04.03 SISTEMA DE AGUA DE LLUVIA 0.00

04.03.01 TUBERÍAS EN BAJANTES PLUVIALES 0.00


04.03.01.01 TUBERÍA PARA AGUAS PLUVIALES DE PVC SAL 3" m 38.64 10.49 405.33 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 38.64 405.33 100.00%
04.03.02 ACCESORIOS 0.00
04.03.02.01 CODO PVC-SAL 3" X 90° pza 6 18.91 113.46 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 6.00 113.46 100.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
04.03.02.02 ABRAZADERA DE FIJACIÓN P/TUBERÍA PLUVIAL und 36 29.70 1069.20 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 36.00 1,069.20 100.00%
05 INSTALACIONES ELÉCTRICAS Y COMUNICACIONES 0.00

05.01 INSTALACIONES ELÉCTRICAS 0.00


05.01.01 CANALIZACION Y/O TUBERIAS 0.00

05.01.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø20 MM m 542.83 13.31 7225.07 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 542.83 7,225.07 100.00%
05.01.01.02 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø60 MM m 11.86 14.44 171.26 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 11.86 171.26 100.00%

05.01.01.03 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø43 MM m 2.64 14.07 37.14 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.64 37.14 100.00%
05.01.02 SALIDAS ELECTRICAS 0.00
05.01.02.01 SALIDA CON CAJA OCTOGONAL DE 100x100x50mm FG PESADA und 194 70.86 13746.84 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 194.00 13,746.84 100.00%

05.01.02.02 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 60 72.06 4323.60 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 60.00 4,323.60 100.00%
05.01.03 CAJAS DE INTERCONEXIÓN ELÉCTRICA F°G° 0.00
05.01.03.01 CAJA DE INTERCONEXION FG 200x200x150mm und 2 288.26 576.52 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 576.52 100.00%
05.01.04 CONDUCTORES ELÉCTRICOS 0.00
05.01.04.01 CABLE TIPO FPL-2x16AWG m 91.89 35.36 3249.23 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 91.89 3,249.23 100.00%
05.01.04.02 CABLE TIPO NH-80 - 2.5 mm2 m 521.93 4.64 2421.76 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 521.93 2,421.76 100.00%

05.01.04.03 CABLE TIPO NH-80 - 4.0 mm2 m 304.79 5.51 1679.39 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 304.79 1,679.39 100.00%
05.01.04.04 CABLE TIPO NH-80 - 16.0 mm2 m 7.26 28.01 203.35 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 7.26 203.35 100.00%

05.01.04.05 CABLE TIPO N2XOH - 70.0 mm2 m 10.87 36.13 392.73 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 10.87 392.73 100.00%
05.01.05 CONDUCTOR ELÉCTRICO PARA PUESTA A TIERRA 0.00
05.01.05.01 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 2.5 mm2 m 284.69 11.69 3328.03 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 284.69 3,328.03 100.00%

05.01.05.02 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 4.0 mm2 m 166.25 14.32 2380.70 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 166.25 2,380.70 100.00%
05.01.05.03 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 10.0 mm2 m 2.64 17.47 46.12 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.64 46.12 100.00%

05.01.06 EQUIPOS LUMINARAS 0.00


05.01.06.01 PANEL LED RECTANGULAR PARA ADOSAR DE 40W, 220V. und 72 65.54 4718.88 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 72.00 4,718.88 100.00%
05.01.06.02 LÁMPARA LED DE 10W,220V CON SOQUETE PARA ADOSAR und 17 35.54 604.18 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 17.00 604.18 100.00%
05.01.07 ARTEFACTOS ELECTRICOS 0.00
05.01.07.01 INTERRUPTOR SIMPLE und 11 17.84 196.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 11.00 196.24 100.00%

05.01.07.02 INTERRUPTOR DOBLE und 2 25.76 51.52 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 51.52 100.00%
05.01.07.03 INTERRUPTOR CONMUTADOR und 12 26.02 312.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.00 312.24 100.00%
05.01.07.04 TOMACORRIENTE SIMPLE (LUZ DE EMERGENCIA) 15A, 220V und 4 25.52 102.08 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 102.08 100.00%
05.01.07.05 TOMACORRIENTE DOBLE CON TOMA A TIERRA 15A, 220V und 35 30.02 1050.70 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 35.00 1,050.70 100.00%
05.01.08 EQUIPOS DE SEGURIDAD 0.00
05.01.08.01 LUZ ESTROBOSCOPICA CON PARLANTE DEL SISTEMA DE ALARMA CONTRA INCENDIO. und 15 966.86 14502.90 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 15.00 14,502.90 100.00%

05.01.08.02 ESTACIÓN MANUAL DE ALARMA CONTRA INCENDIO. und 2 94.86 189.72 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 189.72 100.00%
05.01.08.03 EQUIPO LUZ DE EMERGENCIA, 220V. und 4 221.86 887.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 887.44 100.00%

05.01.09 TABLEROS GENERALES Y DE DISTRIBUCIÓN 0.00


05.01.09.01 TABLERO GENERAL TG 380 TRIFASICO 24 POLOS und 1 1276.52 1276.52 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 1,276.52 100.00%
05.01.09.02 TABLERO DE DISTRIBUCIÓN TD 380V TRIFÁSICO 24 POLOS und 1 1024.89 1024.89 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 1,024.89 100.00%

05.01.10 EQUIPOS - INTERRUPTORES TÉRMICOS - INTERRUPTORES DIFERENCIALES 0.00


05.01.10.01 INTERRUPTOR TÉRMICO 2x15A und 1 128.56 128.56 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 128.56 100.00%

05.01.10.02 INTERRUPTOR TÉRMICO 2x20A und 15 148.56 2228.40 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 15.00 2,228.40 100.00%
05.01.10.03 INTERRUPTOR TÉRMICO 3X63A und 1 153.56 153.56 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 153.56 100.00%
05.01.10.04 INTERRUPTOR TÉRMICO 3x70 und 2 150.56 301.12 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 301.12 100.00%
05.01.10.05 INTERRUPTOR TÉRMICO 3x80A und 2 150.56 301.12 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 2.00 301.12 100.00%
VALORIZACIÓN DE AVANCE DE OBRA N°05
RESIDENCIA DE OBRA
CORRESPONDIENTE AL MES DE JULIO DEL 2021 (01/07/21 - 07/07/21)

FICHA TÉCNICA RESUMEN TOTAL


Monto Asignado Ref. S/502,425.00 Monto Valorizado Anterior S/ 457,474.71 30.71%
OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Monto según resolución S/1,444,331.84 Monto Valorizado del mes S/ 109,261.52 7.67%
Costo Directo Total S/1,342,695.92 Monto Valorizado Acumulado S/ 546,736.23 38.39%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO Factor de Relación 1.0000 Saldo por Valorizar S/ 877,595.61 61.61%
MODALIDAD : ADMINISTRACION DIRECTA Fecha de Inicio de Obra 03 de March de 2021
INSPECTOR : ING. JUVENAL LUIS AQUINO CALDERON Plazo Contractual 120 días calendario
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS Fecha Paralización de Obra 07 de May de 2021
Fecha Reinicio de Obra 08 de June de 2021
Fecha Termino de Obra
Periodo Valorizado 01/07/21 - 07/07/21
Días Valorizados 7 días calendario

PRESUPUESTO AVANCES
SALDO
ITEM DESCRIPCION UNID PRECIO UNITARIO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
METRADO SUBTOTAL (S/)
(S/) METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO SUBTOTAL (S/) % METRADO TOTAL (S/) %
05.01.10.06 INTERRUPTOR DIFERENCIAL 2x25A-30mA und 12 115.71 1388.52 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 12.00 1,388.52 100.00%
05.01.11 SISTEMA DE PUESTA A TIERRA 0.00

05.01.11.01 PUESTA A TIERRA und 4 6500.00 26000.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 26,000.00 100.00%
05.01.12 VARIOS 0.00

05.01.12.01 PRUEBAS DE PUESTAS A TIERRA GLB 1 4500.00 4500.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 4,500.00 100.00%
05.01.12.02 PRUEBAS DE AISLAMIENTO GLB 1 2200.00 2200.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 2,200.00 100.00%

05.01.12.03 PRUEBAS DE FUNCIONAMIENTO DE EQUIPOS ELÉCTRICOS GLB 1 3600.00 3600.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 3,600.00 100.00%
05.01.12.04 PRUEBAS DE CONTINUIDAD GLB 1 2600.00 2600.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 2,600.00 100.00%
05.01.12.05 PRUEBAS DE ILUMINACIÓN GLB 1 2400.00 2400.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 2,400.00 100.00%

05.01.12.06 PROTOCOLO DE PRUEBAS ELECTRICOS GLB 1 2400.00 2400.00 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 2,400.00 100.00%
05.01.13 INSTALACIÓN DE ELECTROBOMBA 0.00
05.01.13.01 INSTALACIÓN DE ELECTROBOMBA INCL. ACCESORIOS GLB 1 1187.83 1187.83 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 1,187.83 100.00%
05.02 INSTALACIONES DE COMUNICACIONES CCTV 0.00
05.02.01 CANALIZACIONES Y TUBERIA DE PVC - SAP 0.00
05.02.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø25MM m 43.99 12.49 549.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 43.99 549.44 100.00%

05.02.02 SALIDAS DE COMUNICACIONES 0.00


05.02.02.01 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 4 47.86 191.44 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 191.44 100.00%

05.02.03 CAJAS DE PASO E INTERCONEXIÓN ELÉCTRICA 0.00


05.02.03.01 SALIDA CON CAJA DE PASO DE 100x100x100mm FG PESADA und 1 50.86 50.86 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 50.86 100.00%
05.02.04 CABLEADO ESTRUCTURADO 0.00

05.02.04.01 CABLE F/UTP - CAT 6 A. m 43.99 15.39 677.01 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 43.99 677.01 100.00%
05.02.05 EQUIPOS DE SISTEMA VOZ Y DATA 0.00

05.02.05.01 CONECTOR TIPO BALUM und 8 28.48 227.84 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 8.00 227.84 100.00%
05.02.05.02 EQUIPO ACCESS POINT und 1 379.65 379.65 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 379.65 100.00%
05.02.05.03 EQUIPO DVR und 1 1222.56 1222.56 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 1,222.56 100.00%
05.02.06 EQUIPOS DE SISTEMA DE TELEFONÍA Y PROYECTOR MULTIMEDIA 0.00
05.02.06.01 EQUIPO PROYECTOR MULTIMEDIA, EN TECHO, UN CONECTOR RJ45, 1UTP CAT. 6A. und 1 2338.56 2338.56 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 2,338.56 100.00%

05.02.07 EQUIPOS DE SISTEMA DE CIRCUITO CERRADO DE TELEVISIÓN 0.00


05.02.07.01 EQUIPO CAMARA, FIJA, PARA INTERIOR, DOMO, 1.3MP, EN TECHO, UN CONECTOR BALUM, 1UTP CAT. 6A. und 4 118.56 474.24 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 4.00 474.24 100.00%
05.02.07.02 EQUIPO CÁMARA, FIJA, PARA INTERIOR, DOMO TIPO PTZ und 1 118.56 118.56 - 0.00 0.00% 0.00 0.00 0.00% - 0.00 0.00% 1.00 118.56 100.00%
COSTO DIRECTO 1,342,695.92 412,400.74 102,999.17 515,399.91 827,296.01
GASTOS GENERALES (4.0%) 53,707.84 16,496.03 4,119.97 20,616.00 33,091.84
SUB-TOTAL 1,396,403.76 428,896.77 107,119.14 536,015.91 860,387.85

SUPERVISION (2.0%) 27,928.08 8,577.94 2,142.38 10,720.32 17,207.76


PRESUPUESTO DE OBRA 1,424,331.83

EXPEDIENTE TECNICO 20,000.00 20,000.00


VALORIZACION BRUTA DE OBRA 1,444,331.83 457,474.71 109,261.52 546,736.23 877,595.61
PORCENTAJE DE AVANCE EJECUTADO (%) 30.71% 7.67% 38.39% 61.61%
Página 16

CRONOGRAMA DE EJECUCIÓN FÍSICA

"MEJORAMIENTO DE PISTAS Y VEREDAS JR. SAN MARTÍN CUADRA I Y II, PROLOGACIÓN 13 DE NOVIEMBRE CUADRA I Y II, PSJE. INGENIERÍA, JR. SUCRE CUADRA I, II
PROYECTO
y III, DISTRITO DE EL TAMBO, PROVINCIA DE HUANCAYO – JUNÍN".

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE EL TAMBO


DISTRITO : EL TAMBO
FECHA : JULIO DEL 2020

ITEM DESCRIPCION UND PARCIAL MES 01 (DEL MES 02 (DEL MES 03 (DEL MES 04 (DEL MES 05 (DEL TOTAL
24 AL 29 DE 01 AL 15 DE 16 AL 30 DE 01 AL 31 DE 01 AL 23 DE
FEBRERO) MARZO) JUNIO) JULIO) AGOSTO)

01 PAVIMENTO RIGIDO
01.01 OBRAS PROVISIONALES
01.01.01 GUARDIANIA Y ALMACEN mes 12,480.00 2,080.00 2,080.00 2,080.00 3,120.00 3,120.00 12,480.00
01.01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1,250.00 1,250.00 1,250.00
01.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1,198.94 299.74 299.74 299.74 299.74 1,198.94
01.02 TRABAJOS PRELIMINARES
01.02.01 TRAZO DE NIVELES Y REPLANTEO INICIAL m2 1,102.88 1,102.88 1,102.88
01.02.02 TRAZO DE NIVELES Y REPLANTEO DURANTE LA OBRA m2 1,121.27 224.25 224.25 224.25 224.25 224.25 1,121.27
01.02.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 1,000.00 1,000.00 1,000.00
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE TERRENO CON MAQ. A NIVEL DE MEJOR. DE SUBRASANTE m3 20,652.68 5,163.17 12,047.40 3,442.11 20,652.68
01.03.02 EXCAVACION MANUAL m3 215.58 215.58 215.58
01.03.03 PERFILADO Y COMPACTADO A NIVEL DE SUB RASANTE m2 6,304.82 3,152.41 3,152.41 6,304.82
01.03.04 ACARREO MANUAL DE MATERIAL EXCEDENTE PARA ELIMINACION m3 6,501.23 3,250.62 3,250.62 6,501.23
01.03.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 54,337.12 27,168.56 27,168.56 54,337.12
01.04 MEJORAMIENTO DE SUB RASANTE
01.04.01 MATERIAL PARA SUB RASANTE PUESTO EN OBRA m3 29,943.30 14,971.65 14,971.65 29,943.30
01.04.02 EXTENDIDO RIEGO NIVELACION Y COMPACTACION SUB-RASANTE E=0.50m. m2 6,176.15 2,058.72 4,117.43 6,176.15
01.05 SUB BASE GRANULAR
01.05.01 MATERIAL PARA SUB BASE PUESTO EN OBRA m3 13,447.91 13,447.91 13,447.91
01.05.02 EXTENDIDO RIEGO NIVELACION Y COMPACTACION SUB-BASE E=0.20m. m2 8,767.93 8,767.93 8,767.93
01.06 PAVIMENTO RIGIDO
01.06.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO m2 8,460.80 4,230.40 4,230.40 8,460.80
01.06.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO INC. ACABADO m3 130,993.37 65,496.69 65,496.69 130,993.37
01.06.03 JUNTAS ASFALTICAS m 4,846.60 2,423.30 2,423.30 4,846.60
01.06.04 CURADO DEL PAVIMENTO m2 7,807.82 3,903.91 3,903.91 7,807.82
01.07 DOWELLS (JUNTA TRANSVERSAL) -
01.07.01 JUNTA TRANSVERSAL kg 11,658.48 11,658.48 11,658.48
01.08 OBRAS DE CONCRETO -
01.08.01 BOCACALLES -
01.08.01.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 97.36 97.36 97.36
01.08.01.02 CONCRETO FC=210 KG/CM2 MAS ACABADO m3 1,800.90 1,800.90 1,800.90
01.08.01.03 CURADO DE ELEMENTOS DE CONCRETO m2 158.68 158.68 158.68
01.08.01.04 JUNTAS ASFALTICAS m 120.07 120.07 120.07
01.08.02 CUNETAS -
01.08.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 2,645.79 1,322.90 1,322.90 2,645.79
01.08.02.02 CONCRETO FC=210 KG/CM2 MAS ACABADO m3 10,500.67 5,250.34 5,250.34 10,500.67
01.08.02.03 CURADO DE ELEMENTOS DE CONCRETO m2 925.88 462.94 462.94 925.88
01.08.02.04 JUNTAS ASFALTICAS m 173.50 86.75 86.75 173.50
01.08.03 BADENES -
01.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 82.07 82.07 82.07
01.08.03.02 CONCRETO FC=210 KG/CM2 MAS ACABADO m3 570.35 570.35 570.35
01.08.03.03 CURADO DE ELEMENTOS DE CONCRETO m2 60.70 60.70 60.70
01.08.03.04 JUNTAS ASFALTICAS m 103.14 103.14 103.14
01.09 SEÑALIZACION HORIZONTAL -
01.09.01 PINTURA LINEAL CENTRAL AL EJE DE VIA (DISCONTINUA) m 1,785.06 1,785.06 1,785.06
01.09.02 PINTURA LINEAL DE PARE m2 102.55 102.55 102.55
01.09.03 PINTURA ZONAL CRUCE PEATONAL m2 2,122.85 2,122.85 2,122.85
01.09.04 PINTURA DE SIMBOLOS - FLECHAS m2 142.38 142.38 142.38
Página 17

CRONOGRAMA DE EJECUCIÓN FÍSICA


01.10 VARIOS -
01.10.01 REPOSICION DE TUBERIA MATRIZ DE AGUA POTABLE und 497.37 248.69 248.69 497.37
01.10.02 REPOSICION DE TUBERIA COLECTOR DE ALCANTARILLADO SANITARIO und 2,895.07 1,447.54 1,447.54 2,895.07
01.10.03 NIVELACION DE BUZONES und 1,303.50 651.75 651.75 1,303.50
01.10.04 CURADO DE TECHO DE BUZON m2 24.39 24.39 24.39
01.10.05 LIMPIEZA FINAL DE OBRA m2 661.73 661.73 661.73
01.10.06 MITIGACION DE IMPACTO AMBIENTAL GLB 1,800.00 1,800.00 1,800.00
01.10.07 SEGURIDAD Y SALUD EN OBRA GLB 16,519.75 2,753.29 2,753.29 2,753.29 4,955.93 3,303.95 16,519.75
01.10.08 INSTALACION DE PLACA RECORDATORIA GLB 573.58 573.58 573.58
01.11 MURO DE CONTENCION H=1.30 -
01.11.01 TRABAJOS PRELIMINARES -
01.11.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 11.67 11.67 11.67
01.11.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA m2 8.70 8.70 8.70
01.11.02 MOVIMIENTO DE TIERRAS -
01.11.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS m3 901.81 450.91 450.91 901.81
01.11.02.02 PERFILADO Y NIVELACION DE TERRENO MANUAL m2 31.18 15.59 15.59 31.18
01.11.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 116.34 58.17 58.17 116.34
01.11.02.04 ACARREO MANUAL DE MATERIAL EXCEDENTE PARA ELIMINACION m3 273.40 136.70 136.70 273.40
01.11.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 296.64 148.32 148.32 296.64
01.11.03 OBRAS DE CONCRETO SIMPLE -
01.11.03.01 SOLADO C:H 1:10 e=4" m2 1,453.73 1,453.73 1,453.73
01.11.04 OBRAS DE CONCRETO ARMADO -
01.11.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,438.62 1,438.62 1,438.62
01.11.04.02 ACERO DE REFUERZO FY=4200 KG/CM2 EN MURO kg 3,436.17 3,436.17 3,436.17
01.11.04.03 CONCRETO FC=210 KG/CM2 MAS ACABADO m3 4,023.70 4,023.70 4,023.70
01.11.05 OTROS -
01.11.05.01 JUNTAS DE CONTRACCION CADA 3m m 59.59 59.59 59.59
01.12 MURO DE CONTENCION H=2.20 -
01.12.01 TRABAJOS PRELIMINARES -
01.12.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 13.20 13.20 13.20
01.12.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA m2 9.84 9.84 9.84
01.12.02 MOVIMIENTO DE TIERRAS -
01.12.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS m3 1,727.09 863.55 863.55 1,727.09
01.12.02.02 PERFILADO Y NIVELACION DE TERRENO MANUAL m2 35.28 17.64 17.64 35.28
01.12.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 138.21 69.11 69.11 138.21
01.12.02.04 ACARREO MANUAL DE MATERIAL EXCEDENTE PARA ELIMINACION m3 377.98 188.99 188.99 377.98
01.12.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 275.30 137.65 137.65 275.30
01.12.03 OBRAS DE CONCRETO SIMPLE -
01.12.03.01 SOLADO C:H 1:10 e=4" m2 1,644.96 1,644.96 1,644.96
01.12.04 OBRAS DE CONCRETO ARMADO -
01.12.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,810.08 1,810.08 1,810.08
01.12.04.02 ACERO DE REFUERZO FY=4200 KG/CM2 EN MURO kg 4,762.28 4,762.28 4,762.28
01.12.04.03 CONCRETO FC=210 KG/CM2 MAS ACABADO m3 8,203.65 8,203.65 8,203.65
01.12.05 OTROS -
01.12.05.01 JUNTAS DE CONTRACCION CADA 3m m 74.91 74.91 74.91
02 ACERA PEATONAL -
02.01 TRABAJOS PRELIMINARES -
02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 404.77 404.77 404.77
02.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA m2 301.74 150.87 150.87 301.74
02.01.03 DEMOLICION DE VEREDAS EXISTENTES m3 382.55 382.55 382.55
02.02 MOVIMIENTO DE TIERRAS -
02.02.01 CORTE MANUAL DE TERRENO EN VEREDAS Y MARTILLOS m3 4,274.34 1,068.59 1,068.59 1,068.59 1,068.59 4,274.34
02.02.02 EXCAVACION MANUAL PARA SARDINEL EXPUESTO m3 1,245.67 311.42 311.42 311.42 311.42 1,245.67
02.02.03 PERFILADO Y NIVELACION EN SUBRASANTE DE VEREDAS m2 2,575.79 643.95 643.95 643.95 643.95 2,575.79
02.02.04 RELLENO Y COMPACTADO DE BASE DE VEREDA C/MATERIAL PRESTAMO, E=0.10 M m3 11,500.14 2,875.04 2,875.04 2,875.04 2,875.04 11,500.14
02.02.05 ACARREO MANUAL DE MATERIAL EXCEDENTE PARA ELIMINACION m3 901.36 225.34 225.34 225.34 225.34 901.36
02.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1,145.44 286.36 286.36 286.36 286.36 1,145.44
02.03 OBRAS DE CONCRETO -
02.03.01 SARDINEL EXPUESTO -
02.03.01.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 5,183.77 3,455.85 1,727.92 5,183.77
02.03.01.02 CONCRETO FC=175 KG/CM2 MAS ACABADO m3 9,281.38 4,640.69 4,640.69 9,281.38
02.03.01.03 JUNTAS ASFALTICAS m 134.24 134.24 134.24
Página 18

CRONOGRAMA DE EJECUCIÓN FÍSICA


02.03.02 MARTILLOS Y VEREDAS -
02.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,230.50 615.25 615.25 1,230.50
02.03.02.02 CONCRETO F'C=175 KG/CM2 DE 4" (INCLUYE ACABADO + BRUÑADO) m3 21,127.43 10,563.72 10,563.72 21,127.43
02.03.02.03 JUNTAS ASFALTICAS m 1,757.01 1,757.01 1,757.01
02.03.03 GRADERIAS -
02.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,171.23 1,171.23 1,171.23
02.03.03.02 CONCRETO F'C=175 KG/CM2 DE 4" (INCLUYE ACABADO + BRUÑADO) m3 4,583.58 4,583.58 4,583.58
02.03.04 RAMPAS -
02.03.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 20.38 20.38 20.38
02.03.04.02 CONCRETO F'C=175 KG/CM2 (INC. ACABADO + BRUÑADO) m3 855.49 855.49 855.49
02.04 SEÑALIZACION -
02.04.01 SEÑALIZACION HORIZONTAL -
02.04.01.01 PINTURA LINEAL EN SARDINEL m 4,397.23 4,397.23 4,397.23
02.04.02 SEÑALIZACION VERTICAL -
02.04.02.01 SEÑALES INFORMATIVAS und 804.42 804.42 804.42
02.04.02.02 SEÑALES REGLAMENTARIA und 644.70 644.70 644.70
02.05 TACHOS DE DESECHOS -
02.05.01 TACHOS DE DESECHOS ORGANICOS E INORGANICOS und 1,073.56 1,073.56 1,073.56
02.06 VARIOS -
02.06.01 RECONEXION DE PUNTOS DE AGUA pto 2,794.48 931.49 931.49 931.49 2,794.48
02.06.02 RECONEXION DE INSTALACION DE PUNTOS DE DESAGUE pto 5,047.64 1,682.55 1,682.55 1,682.55 5,047.64
-
COSTO DIRECTO 487,897.39 21,302.83 78,731.54 107,134.74 156,928.41 123,799.87 487,897.39
GASTOS GENERALES 6.10% 29,761.74 1,299.47 4,802.62 6,535.22 9,572.63 7,551.79 29,761.74

SUB TOTAL 517,659.13 22,602.30 83,534.16 113,669.96 166,501.05 131,351.66 517,659.13


SUPERVISION 2.6% 13,459.14 587.66 2,171.89 2,955.42 4,329.03 3,415.14 13,459.14

PRESUPUESTO TOTAL 531,118.27 23,189.96 85,706.05 116,625.38 170,830.07 134,766.80 531,118.27

% DE AVANZE 4.37% 16.14% 21.96% 32.16% 25.37%


% ACUMULADO 4.37% 20.50% 42.46% 74.63% 100.00%
Página 19

CRONOGRAMA DE AVANCE FISICO


(SUSTENTADO EN EL PROGRAMA DE EJECUCION DE OBRA CPM)

: “REMODELACION DE PISTAS; EN EL(LA) JR. LOS BOSQUES, TRAMO: AV. JOSE CARLOS MARIATEGUI - JR. SEBASTIAN LORENTE, SECTOR NC-06, DISTRITO DE EL TAMBO, PROVINCIA HUANCAYO,
OBRA
DEPARTAMENTO JUNIN”
MODALIDAD : ADMINISTRACION DIRECTA
LUGAR : JUNIN, PROVINCIA DE HUANCAYO, DISTRITO DE EL TAMBO
UBICACION : LOS BOSQUES
FECHA : NOVIEMBRE DE 2019
SUPERVISOR : ING. JUVENAL LUIS AQUINO CALDERON
RESIDENTE : ING. JHOSEF J. CASTRO ROSAS

AVANCE VALORIZADO
ITEM DESCRIPCION UND METRADO PRECIO PARCIAL
MES 01 MES 02 MES 03 MES 04

01 OBRAS PROVISIONALES
01.01 GUARDIANIA Y ALMACEN mes 4.00 500.00 2,000.00 500.00 500.00 500.00 500.00
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1.00 1,200.00 1,200.00 1200.00
01.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 8.00 250.00 2,000.00 2000.00
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 1,000.00 1,000.00 500.00 500.00
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2 5,570.24 0.41 2,283.80 2283.80
02.02 TRAZO Y REPLANTEO PRELIMINAR m2 5,570.24 0.32 1,782.48 891.24 891.24
02.03 TRAZO Y REPLANTEO DURANTE EJECUCION DE OBRA m2 5,570.24 0.76 4,233.38 2116.69 2116.69
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO HASTA LA SUBRASANTE m3 819.11 5.74 4,701.69 4701.69
03.02 EXCAVACION MANUAL m3 94.53 24.06 2,274.39 2274.39
03.03 ACARREO MANUAL DE MATERIAL DE CORTE m3 94.53 9.02 852.66 852.66
03.04 CARGUIO DE MATERIAL EXCEDENTE m3 1,096.37 3.90 4,275.84 4275.84
03.05 TRANSPORTE DE MATERIAL EXCEDENTE m3 1,096.37 9.75 10,689.61 10689.61
04 PAVIMENTO RIGIDO
04.01 MEJORAMIENTO DE BASE GRANULAR
04.01.01 ESCARIF. Y PERFIL. DE SUB BASE m2 3,839.32 1.58 6,066.13 3033.06 3033.06
04.01.02 MATERIAL GRANULAR P/SUB BASE PUESTO EN OBRA m3 345.54 35.00 12,093.90 12093.90
304.01.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE GRANULAR m2 3,839.32 2.96 11,364.39 11364.39
04.02 PAVIMENTO RIGIDO (e = 0.20 m)
04.02.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO m2 580.27 37.67 21,858.77 10929.39 10929.39
04.02.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO + ACABADO m3 745.72 397.40 296,349.13 148174.56 148174.56
04.02.03 CURADO CON ARROCERAS m2 3,728.58 0.60 2,237.15 1118.57 1118.57
04.03 DOWELLS
04.03.01 INSTALACION DE DOWELLS und 1,778.00 11.77 20,927.06 10463.53 10463.53
05 CUNETA
05.01 ENCOFRADO Y DESENCOFRADO EN CUNETA m2 185.73 29.62 5,501.32 2750.66 2750.66
05.02 CONCRETO FC=210 KG/CM2 EN CUNETAS m3 61.14 384.03 23,479.59 11739.80 11739.80
05.03 ACABADO EN CUNETAS m2 185.73 5.96 1,106.95 553.48 553.48
06 BADEN DE CONCRETO
06.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 31.44 29.62 931.25 465.63 465.63
06.02 CONCRETO FC=210 KG/CM2 EN BADEN m3 38.97 384.03 14,965.65 7482.82 7482.82
06.03 ACABADO EN BADEN m2 194.83 5.96 1,161.19 580.59 580.59
07 BOCA CALLES
07.01 ENCOFRADO Y DESENCOFRADO EN BOCA CALLE m2 8.76 29.62 259.47 129.74 129.74
07.02 CONCRETO FC=210 KG/CM2 EN BOCA CALLE + ACABADO m3 22.16 384.03 8,510.10 4255.05 4255.05
07.03 CURADO CON ARROCERAS m2 110.82 0.60 66.49 33.25 33.25
08 JUNTAS
08.01 RELLENO DE JUNTAS CON ASFALTO m 2,074.92 2.51 5,208.05 2604.02 2604.02
09 SEÑALIZACION
09.01 PINTURA LINEAL EN SARDINEL m 1,091.90 9.79 10,689.70 10689.70
09.02 PINTURA ZONAL CRUCE PEATONAL m2 295.70 24.01 7,099.76 7099.76
09.03 PINTURA INTERM. DISCONT. - CENTRO DE VIA m 272.98 4.66 1,272.09 1272.09
09.04 PINTURA DE SIMBOLOS - FLECHAS m2 19.80 24.82 491.44 491.44
10 ENSAYOS Y PRUEBAS DE LABORATORIO
10.01 PRUEBA DE CONTROL DE DENSIDAD DE CAMPO und 15.00 35.00 525.00 262.50 262.50
10.02 ENSAYO PROCTOR MODIFICADO DE CAMPO und 1.00 150.00 150.00 75.00 75.00
10.03 ENSAYO DE RELACIÓN DE SOPORTE DE CALIFORNIA - CBR DE SUELO und 1.00 250.00 250.00 125.00 125.00
10.04 PRUEBA DE ROTURA DE PROBETAS DE CONCRETO und 30.00 20.00 600.00 300.00 300.00
10.05 DISEÑO DE MEZCLA DE CONCRETO und 1.00 220.00 220.00 220.00
11 MITIGACION AMBIENTAL
11.01 MITIGACION DE IMPACTO AMBIENTAL GLB 1.00 1,500.00 1,500.00 1500.00
12 VARIOS
12.01 LIMPIEZA DE TERRENO MANUAL m2 5,570.24 0.41 2,283.80 2283.80
12.02 PLACA RECORDATORIA GLB 1.00 550.00 550.00 550.00
12.03 TAPA DE BUZONES und 10.00 370.00 3,700.00 3700.00
12.03 SEGURIDAD Y SALUD EN OBRA GLB 1.00 13,699.64 13,699.64 3424.91 3424.91 3424.91 3424.91

COSTO DIRECTO 512,411.86 38,963.90 220,416.68 205,968.50 47062.79

GASTOS GENERALES 11.90% 60,977.01 4636.70 26229.58 24510.25 5600.47

SUBTOTAL 573,388.88 43600.60 246646.26 230478.75 52663.26

PORCENTAJE MENSUAL % 7.60% 43.02% 40.20% 9.18%


PORCENTAJE ACUMULADO % 7.60% 50.62% 90.82% 100.00%
Página 20

CRONOGRAMA VALORIZADO DE OBRA - I ETAPA


Presupuesto CREACIÓN DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO, PROVINCIA DE CHUPACA, DEPARTAMENTO JUNÍN - I ETAPA.
Cliente S10 S.A.
Lugar JUNIN - CHUPACA - CHONGOS BAJO
MES 1 MES 2 MES 3 MES 4
Item Descripción Und. Metrado Precio S/. Parcial S/.
01 TRABAJOS PRELIMINARES
01.01 CARTEL IDENTIFICACIÓN DE OBRA, INCL GIGANTOGRAFIA GLB 1.00 1,118.23 1,118.23 S/.1,118.23
01.02 ALMACÉN, OFICINAS Y GUARDIANÍA mes 5.00 1,000.00 5,000.00 S/.5,000.00
01.03 CERCO PERIMETRICO PROVISIONAL GLB 1.00 7,000.00 7,000.00 S/.7,000.00
01.04 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIAS, EQUIPOS Y HERRAMIENTAS GLB 1.00 8,000.00 8,000.00 S/.8,000.00
01.05 IMPLEMENTACIÓN DE SALUD, SEGURIDAD EN EL TRABAJO. GLB 0.50 35,000.00 17,500.00 S/.17,500.00
01.06 IMPLEMENTACIÓN DEL PLAN CONTRA COVID-19. GLB 0.50 40,000.00 20,000.00 S/.20,000.00
01.07 MITIGACION DE IMPACTO AMBIENTAL GLB 0.50 8,000.00 4,000.00 S/.4,000.00
01.08 FLETE PARA TRANSPORTE DE MATERIALES GLB 0.50 15,000.00 7,500.00 S/.7,500.00
01.09 DEMOLICIÓN DE PABELLÓN DE AULAS Y OTROS GLB 1.00 59,000.00 59,000.00 S/.59,000.00
01.10 ELIMINACIÓN DEL MATERIAL DE DEMOLICIÓN GLB 1.00 29,000.00 29,000.00 S/.29,000.00
02 ESTRUCTURAS
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 510.18 3.81 1,943.79 S/.1,943.79
02.01.02 TRAZO Y REPLANTEO m2 510.18 5.65 2,882.52 S/.2,882.52
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIÓN CON MAQUINARIA P/CIMENTACIÓN m3 589.36 55.22 32,544.46 S/.32,544.46
02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO CAPAS CADA 0.20M m3 51.94 73.89 3,837.85 S/.3,837.85
02.02.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO CAPAS CADA 0.20M m3 171.36 73.89 12,661.79 S/.12,661.79
02.02.04 CAMA DE ARENA PARA VIGAS DE CIMENTACIÓN m3 3.09 62.70 193.74 S/.193.74
02.02.05 NIVELACIÓN Y COMPACTACIÓN EN TERRENO NORMAL m2 527.51 19.00 10,022.69 S/.10,022.69
02.02.06 AFIRMADO DE 4" PARA VEREDAS CON EQUIPO LIVIANO m2 527.54 23.25 12,265.31 S/.12,265.31
02.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA DIST./PROM = 5KM m3 668.53 11.65 7,788.37 S/.7,788.37
02.03 CONCRETO SIMPLE
02.03.01 SOLADO
02.03.01.01 SOLADO EN ZAPATA MEZCLA C:H 1:10 m2 18.72 30.40 569.09 S/.569.09
02.03.01.02 SOLADO EN VIGAS DE CIMENTACION MEZCLA C:H 1:10 m2 10.24 29.75 304.64 S/.304.64
02.03.02 CIMIENTOS CORRIDOS
02.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G m3 4.84 227.75 1,102.31 S/.1,102.31
02.03.03 SOBRECIMIENTOS
02.03.03.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 1.39 307.69 427.69 S/.427.69
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS m2 20.52 39.51 810.75 S/.810.75
02.03.04 FALSO PISO
02.03.04.01 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGÓN E=4" m2 468.99 30.22 14,172.88 S/.14,172.88
02.03.05 VEREDAS
02.03.05.01 VEREDAS f'c=175 Kg/cm2 m3 6.92 385.50 2,667.66 S/.2,667.66
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 16.73 52.70 881.67 S/.881.67
02.04 CONCRETO ARMADO
02.04.01 ZAPATAS
02.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 111.45 395.74 44,105.22 S/.44,105.22
02.04.01.02 ACERO PARA ZAPATAS GRADO 60 kg 4,896.33 10.61 51,950.06 S/.51,950.06
02.04.02 VIGAS DE CIMENTACION
02.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C=210 KG/CM2 m3 16.84 407.56 6,863.31 S/.6,863.31
02.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2 123.20 52.70 6,492.64 S/.6,492.64
02.04.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION kg 4,352.96 10.61 46,184.91 S/.46,184.91
02.04.03 SOBRECIMIENTOS ARMADOS
02.04.03.01 SOBRECIMIENTOS DE C.A. f'c=175 Kg/cm2 m3 22.61 385.50 8,716.16 S/.8,716.16
02.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS ARMADOS m2 347.84 52.70 18,331.17 S/.18,331.17
02.04.03.03 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 1,772.05 10.61 18,801.45 S/.18,801.45
02.04.04 COLUMNAS
02.04.04.01 CONCRETO EN COLUMNETAS f'c=175 kg/cm2. m3 11.53 385.50 4,444.82 S/.4,444.82
02.04.04.02 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 38.98 418.50 16,313.13 S/.16,313.13
02.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 606.12 27.07 16,407.67 S/.16,407.67
02.04.04.04 ACERO GRADO 60 EN COLUMNAS kg 8,646.29 10.61 91,737.14 S/.91,737.14
02.04.05 VIGAS
02.04.05.01 CONCRETO EN VIGUETAS f'c=175 kg/cm2. m3 2.99 385.50 1,152.65 S/.1,152.65
02.04.05.02 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 38.98 460.03 17,931.97 S/.17,931.97
02.04.05.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 289.38 72.19 20,890.34 S/.20,890.34
02.04.05.04 ACERO GRADO 60 EN VIGAS kg 5,508.09 10.61 58,440.83 S/.58,440.83
02.04.06 LOSAS ALIGERADAS
Página 21

02.04.06.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 m3 34.77 421.60 14,659.03 S/.14,659.03
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 397.38 50.94 20,242.54 S/.20,242.54
02.04.06.03 BLOQUE HUECO/CONCRETO 15X30X25 CM PARA TECHO ALIGERADO und 3,312.00 3.12 10,333.44 S/.10,333.44
02.04.06.04 ACERO GRADO 60 EN LOSAS ALIGERADAS kg 1,963.76 10.61 20,835.49 S/.20,835.49
02.04.07 ESCALERAS
02.04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 12.22 477.70 5,837.49 S/.5,837.49
02.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 62.67 81.76 5,123.90 S/.5,123.90
02.04.07.03 ACERO GRADO 60 EN ESCALERAS kg 984.81 10.70 10,537.47 S/.10,537.47
02.05 DISEÑO DE MEZCLAS
02.05.01 DISEÑO DE MEZCLA P/CONCRETO F'C=175 KG/CM² und 1.00 380.00 380.00 S/.380.00
02.05.02 DISEÑO DE MEZCLA P/CONCRETO F'C=210 KG/CM² und 1.00 380.00 380.00 S/.380.00
02.06 PRUEBA DE ROTURA
02.06.01 PRUEBA DE ROTURA DE PROBETA und 20.00 50.00 1,000.00 S/.1,000.00
03 ARQUITECTURA
03.01 MUROS Y TABIQUES
03.01.01 MURO DE LADRILLO KK TIPO IV SOGA MEZCLA: C:A 1:5 x 1:5 CM m2 426.20 102.81 43,817.62 S/.43,817.62
03.01.02 MURO DE LADRILLO KK TIPO IV CABEZA MEZCLA: C:A 1:5 x 1:5 CM m2 5.87 151.20 887.54 S/.887.54
03.02 REVOQUES ENLUCIDOS Y MOLDURAS
03.02.01 TARRAJEO PRIMARIO Y RAYADO C/MEZC. C: A 1:5, E=1.5CM. m2 57.03 20.43 1,165.12 S/.1,165.12
03.02.02 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:5 x 1:5 CM m 72.11 29.31 2,113.54 S/.2,113.54
03.02.03 TARRAJEO DE MUROS EXTERIORES, E=1.5CM, C: A 1:5 m2 28.32 24.26 687.04 S/.687.04
03.02.04 TARRAJEO DE MUROS INTERIORES, E=1.5CM, C: A 1:5 m2 583.68 16.62 9,700.76 S/.9,700.76
03.02.05 TARRAJEO DE COLUMNAS, E=1.5cm, C:A 1:5 m2 151.10 31.23 4,718.85 S/.4,718.85
03.02.06 TARRAJEO DE COLUMNETAS, E=1.5cm, C:A 1:5 m2 111.79 31.23 3,491.20 S/.3,491.20
03.02.07 TARRAJEO DE VIGAS, E=1.5 CM, C: A 1:5 m2 206.69 37.82 7,817.02 S/.7,817.02
03.02.08 VESTIDURA DE DERRAMES, E=1.5CM, C: A 1:5 m 137.40 12.62 1,733.99 S/.1,733.99
03.02.09 EJECUCIÓN DE BRUÑAS EN FACHADA m 216.67 8.34 1,807.03 S/.1,807.03
03.02.10 TARRAJEO DE COBERTURA CON IMPERMEABILIZANTE m2 634.79 32.16 20,414.85 S/.20,414.85
03.03 CIELORRASOS
03.03.01 TARRAJEO DE CIELORRASO E=1.5cm, C:A 1:5 m2 443.77 28.66 12,718.45 S/.12,718.45
03.04 PISOS Y PAVIMENTOS
03.04.01 PISOS
03.04.01.01 PISO CERÁMICO 30 X 30 CM ANTIDESLIZANTE m2 38.71 80.97 3,134.35 S/.3,134.35
03.04.01.02 PORCELANATO 60X60 CM ANTIDESLIZANTE DE ALTO TRANSITO m2 445.42 78.87 35,130.28 S/.35,130.28
03.04.01.03 PISO DE CEMENTO SEMI PULIDO FROTACHADO Y BRUÑADO m2 63.93 25.00 1,598.25 S/.1,598.25
03.05 ZÓCALOS Y CONTRAZÓCALOS
03.05.01 ZÓCALOS
03.05.01.01 ZÓCALO DE CERÁMICO DE 30 X 30 CM. m2 50.45 71.59 3,611.72 S/.3,611.72
03.05.01.02 PORCELANATO DE 60 X 60 CM PARA FACHADA COLOR NEGRO m2 48.81 91.47 4,464.65 S/.4,464.65
03.05.01.03 PORCELANATO DE 60 X 60 cm PARA FACHADA COLOR BLANCO m2 13.93 91.47 1,274.18 S/.1,274.18
03.05.02 CONTRAZOCALOS
03.05.02.01 CONTRAZÓCALO DE PORCELANATO DE H=010 M m2 224.45 29.98 6,729.01 S/.6,729.01
03.06 CARPINTERÍA DE FENÓLICO S/.0.00
03.06.01 SEPARADORES DE MELAMINE DE E= 15MM m2 16.60 175.82 2,918.61 S/.2,918.61
03.06.02 PUERTA DE MELAMINE E= 15MM und 15.84 469.27 7,433.24 S/.7,433.24
03.07 CARPINTERIA DE MADERA
03.07.01 PUERTA APANELADA, E=35MM /INCL. COLOCACIÓN m2 3.00 382.00 1,146.00 S/.1,146.00
03.07.02 PUERTA CONTRAPLACADA E=45MM /INCL. COLOCACIÓN und 2.00 350.00 700.00 S/.700.00
03.08 CARPINTERÍA DE ALUMINIO
03.08.01 VENTANA DE ALUMINIO SEGÚN DISEÑO m2 13.06 240.00 3,134.40 S/.3,134.40
03.09 MURO CORTINA
03.09.01 MURO CORTINA DE ALUMINIO EN INGRESO PRINCIPAL m2 159.16 299.30 47,636.59 S/.47,636.59
03.09.02 MURO CORTINA DE ALUMINIO EN INTERIOR DE MODULO m2 86.75 296.30 25,704.03 S/.25,704.03
03.10 CARPINTERÍA METÁLICA
03.10.01 PUERTA EN MURO CORTINA EN INTERIOR DE MODULO (1.2 X 2.4) und 6.00 320.00 1,920.00 S/.1,920.00
03.10.02 PORTÓN TIPO REJA CORREDIZO (3.5MX3.15M) / INCL. INSTALACIÓN und 1.00 360.00 360.00 S/.360.00
03.11 OTROS

03.11.01 BARRA DE APOYO ABATIBLE VERTICAL DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS und 1.00 544.30 544.30 S/.544.30

03.11.02 BARRA DE APOYO DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS - LAVATORIOS und 1.00 544.30 544.30 S/.544.30

03.11.03 BARRA DE APOYO DE ACERO INOXIDABLE DE Ø 1" X 36" EN BAÑO DE DISCAPACITADOS und 1.00 628.59 628.59 S/.628.59
03.12 VIDRIOS, CRISTALES Y SIMILARES
03.12.01 VIDRIOS
03.12.01.01 VIDRIO TEMPLADO COLOR AZUL REFLEJANTE DE 6 MM m2 13.06 94.60 1,235.48 S/.1,235.48
03.12.01.02 VIDRIO INSULADO ESMERILADO EN MURO CORTINA INTERIOR m2 101.17 92.59 9,367.33 S/.9,367.33
03.12.01.03 VIDRIO DE SEGURIDAD EN MURO CORTINA EXTERIOR m2 86.75 117.74 10,213.95 S/.10,213.95
Página 22

03.12.01.04 ESPEJO RECLINABLE (0.60X0.70) und 3.00 52.54 157.62 S/.157.62


03.12.01.05 PUERTA DE VIDRIO DE 10MM EN INGRESO PRINCIPAL m2 6.71 365.00 2,449.15 S/.2,449.15
03.13 CERRAJERIA
03.13.01 CERRADURA DE ACERO INOXIDABLE und 17.00 101.07 1,718.19 S/.1,718.19
03.13.02 BISAGRAS ALUMINIZADA CAPUCHINA DE 3 1/2"x3 1/2" pza 12.00 18.55 222.60 S/.222.60
03.13.03 BISAGRAS DE ACERO ALUMINIZADO PESADO DE 3. 1/2" X 3. 1/2" 04 POR C/PUERTA und 36.00 25.57 920.52 S/.920.52
03.13.04 CERRADURA PESADA DE 2 GOLPES und 3.00 81.07 243.21 S/.243.21
03.13.05 MANIJA DE BRONCE PARA PUERTAS DE 4" und 17.00 41.14 699.38 S/.699.38
03.14 PINTURA
03.14.01 PINTURA LÁTEX SOBRECIMIENTOS m2 72.11 11.39 821.33 S/.821.33
03.14.02 PINTURA LÁTEX EN MUROS EXTERIORES m2 28.32 13.78 390.25 S/.390.25
03.14.03 PINTURA LÁTEX EN MUROS INTERIORES m2 583.68 11.39 6,648.12 S/.6,648.12
03.14.04 PINTURA LÁTEX COLUMNAS m2 151.10 11.39 1,721.03 S/.1,721.03
03.14.05 PINTURA LÁTEX COLUMNETAS m2 111.79 11.39 1,273.29 S/.1,273.29
03.14.06 PINTURA LÁTEX VIGAS m2 206.69 13.78 2,848.19 S/.2,848.19
03.14.07 PINTURA LÁTEX DERRAMES EN VANOS DE PUERTAS Y VENTANAS m 137.40 2.66 365.48 S/.365.48
03.14.08 PINTURA DE CIELORRASOS, LÁTEX 02 MANOS, INC. IMPRIMANTE m2 443.77 13.78 6,115.15 S/.6,115.15
03.14.09 PINTURA EN PUERTAS DE MADERA C/BARNIZ - 2 MANOS m2 24.56 14.02 344.33 S/.344.33
03.15 VARIOS
03.15.01 JUNTA DE CONSTRUCCIÓN TEKNOPORT 1" m2 1,096.47 14.95 16,392.23 S/.16,392.23
03.16 EQUIPAMIENTO
03.16.01 ESCRITORIO DE DOS GAVETAS und 11.00 190.00 2,090.00 S/.2,090.00
03.16.02 SILLA EJECUTIVA ERGONÓMICA und 17.00 150.00 2,550.00 S/.2,550.00
03.16.03 ESCRITORIO TIPO L (1.30 X 1.94) und 7.00 150.00 1,050.00 S/.1,050.00
03.16.04 SILLA VISITANTE und 25.00 100.00 2,500.00 S/.2,500.00
03.16.05 ESTANTE und 12.00 260.00 3,120.00 S/.3,120.00
03.16.06 COMPUTADORA I5 und 16.00 2,200.00 35,200.00 S/.35,200.00
03.16.07 IMPRESORA MULTIFUNCIONAL und 11.00 670.00 7,370.00 S/.7,370.00
04 INSTALACIONES SANITARIAS
04.01 INSTALACIONES SANITARIAS DE AGUA
04.01.01 MOVIMIENTO DE TIERRAS
04.01.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE AGUA SECCIÓN 0.30 M m3 4.35 45.84 199.40 S/.199.40
04.01.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 21.77 4.58 99.71 S/.99.71
04.01.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 5.81 36.78 213.69 S/.213.69
04.01.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 2.91 22.92 66.70 S/.66.70
04.01.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 14.52 5.65 82.04 S/.82.04
04.01.01.06 CAMA DE ARENA m2 12.72 44.85 570.49 S/.570.49
04.01.02 APARATOS Y ACCESORIOS SANITARIOS INCLUIDO COLOCACIÓN
04.01.02.01 INODORO TANQUE BAJO DE LOSA und 7.00 408.21 2,857.47 S/.2,857.47
04.01.02.02 URINARIO BAMBI und 2.00 388.21 776.42 S/.776.42
04.01.02.03 PAPELERA PARA EMPOTRAR DE LOSA pza 7.00 59.16 414.12 S/.414.12
04.01.02.04 LAVATORIO DE PARED C/GRIFE.CROMADA 20X17CM.(JAMAICA O SIMIL) und 7.00 348.61 2,440.27 S/.2,440.27
04.01.03 SISTEMA DE AGUA FRIA
04.01.03.01 SALIDA DE AGUA FRÍA (RIEGO) CON TUBERÍA DE PVC-SAP 1/2" pto 22.00 78.27 1,721.94 S/.1,721.94
04.01.04 REDES DE DISTRIBUCIÓN
04.01.04.01 RED DE DISTRIBUCIÓN TUBERÍA DE 3/4" PVC-SAP C10 m 29.05 7.78 226.01 S/.226.01
04.01.04.02 RED DE DISTRIBUCIÓN TUBERÍA DE 1/2" PVC-SAP C10 m 45.53 7.78 354.22 S/.354.22
04.01.05 ACCESORIOS DE REDES
04.01.05.01 CODO PVC-SAP 1/2" pza 26.00 9.01 234.26 S/.234.26
04.01.05.02 TEE PVC SAP DE 3/4" pza 3.00 8.51 25.53 S/.25.53
04.01.05.03 TEE PVC SAP DE 1/2" pza 20.00 8.51 170.20 S/.170.20
04.01.05.04 UNIÓN PVC SAP DE 3/4" pza 27.00 8.81 237.87 S/.237.87
04.01.05.05 UNIÓN PVC SAP DE 1/2" pza 25.00 8.41 210.25 S/.210.25
04.01.05.06 REDUCCIÓN PVC-SAP DE 3/4" A 1/2" pza 2.00 8.91 17.82 S/.17.82
04.01.05.07 VÁLVULA DE COMPUERTA DE BRONCE UNIÓN ROSCADA 1/2" pza 4.00 97.24 388.96 S/.388.96
04.01.06 INSTALACIÓN DE TANQUE ELEVADO Y CISTERNA
04.01.06.01 INSTALACIÓN DE CISTERNA GLB 1.00 20,000.00 20,000.00 S/.20,000.00
04.01.06.02 INSTALACIÓN DE TANQUE ELEVADO GLB 1.00 18,000.00 18,000.00 S/.18,000.00
04.01.07 VARIOS
04.01.07.01 CAJA CON TAPA METÁLICA PARA VÁLVULAS DE 12" X 12" und 4.00 316.20 1,264.80 S/.1,264.80
04.02 INSTALACIONES SANITARIAS DE DESAGÜE
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE DESAGÜE SECCIÓN 0.30 M m 63.33 45.84 2,903.05 S/.2,903.05
04.02.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 12.67 4.58 58.03 S/.58.03
04.02.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 3.80 36.78 139.76 S/.139.76
04.02.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 6.33 22.92 145.08 S/.145.08
04.02.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 1.90 5.65 10.74 S/.10.74
Página 23

04.02.01.06 CAMA DE ARENA m2 12.67 44.85 568.25 S/.568.25


04.02.02 SALIDAS DE DESAGÜE Y VENTILACIÓN
04.02.02.01 SALIDA DE DESAGUE DE PVC 2" pto 18.00 76.96 1,385.28 S/.1,385.28
04.02.02.02 SALIDA DE DESAGÜE DE PVC 4" pto 16.00 84.84 1,357.44 S/.1,357.44
04.02.02.03 SALIDA DE VENTILACIÓN EN PVC SAL 4" pto 2.00 82.73 165.46 S/.165.46
04.02.02.04 SALIDA DE VENTILACIÓN EN PVC SAL 2" pto 9.00 76.96 692.64 S/.692.64
04.02.03 REDES DE DERIVACIÓN
04.02.03.01 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 4" m 34.26 14.67 502.59 S/.502.59
04.02.03.02 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 2" m 29.07 10.39 302.04 S/.302.04
04.02.04 ACCESORIOS PARA REDES DE DERIVACIÓN
04.02.04.01 CODO PVC-SAL 2" X 45º pza 19.00 14.34 272.46 S/.272.46
04.02.04.02 CODO PVC-SAL 4" X 45º pza 7.00 22.81 159.67 S/.159.67
04.02.04.03 CODO PVC SAL 4" X 90° CON REDUCCIÓN A 2" pza 6.00 46.65 279.90 S/.279.90
04.02.04.04 YEE PVC-SAL DE 2" pza 15.00 14.74 221.10 S/.221.10
04.02.04.05 TEE PVC-SAL DE 4 pza 3.00 19.94 59.82 S/.59.82
04.02.04.06 REDUCCIÓN PVC-SAL 4"X 2" pza 7.00 16.79 117.53 S/.117.53
04.02.05 ADITAMENTOS VARIOS S/.0.00
04.02.05.01 SUMIDERO DE BRONCE 2" und 4.00 49.06 196.24 S/.196.24
04.02.05.02 REGISTRO ROSCADO DE BRONCE CROMADO 4" und 8.00 73.03 584.24 S/.584.24
04.02.05.03 SOMBRERO VENTILACIÓN PVC DE 2" und 6.00 18.51 111.06 S/.111.06
04.02.06 CAJAS DE REGISTRO
04.02.06.01 CAJA DE REGISTRO DE DESAGÜE 10" X 20" CON TAPA DE CONCRETO und 5.00 196.89 984.45 S/.984.45
04.03 SISTEMA DE AGUA DE LLUVIA
04.03.01 TUBERÍAS EN BAJANTES PLUVIALES
04.03.01.01 TUBERÍA PARA AGUAS PLUVIALES DE PVC SAL 3" m 38.64 10.49 405.33 S/.405.33
04.03.02 ACCESORIOS
04.03.02.01 CODO PVC-SAL 3" X 90° pza 6.00 18.91 113.46 S/.113.46
04.03.02.02 ABRAZADERA DE FIJACIÓN P/TUBERÍA PLUVIAL und 36.00 29.70 1,069.20 S/.1,069.20
05 INSTALACIONES ELÉCTRICAS Y COMUNICACIONES
05.01 INSTALACIONES ELÉCTRICAS
05.01.01 CANALIZACION Y/O TUBERIAS
05.01.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø20 MM m 542.83 13.31 7,225.07 S/.7,225.07
05.01.01.02 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø60 MM m 11.86 14.44 171.26 S/.171.26
05.01.01.03 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø43 MM m 2.64 14.07 37.14 S/.37.14
05.01.02 SALIDAS ELECTRICAS
05.01.02.01 SALIDA CON CAJA OCTOGONAL DE 100x100x50mm FG PESADA und 194.00 70.86 13,746.84 S/.13,746.84
05.01.02.02 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 60.00 72.06 4,323.60 S/.4,323.60
05.01.03 CAJAS DE INTERCONEXIÓN ELÉCTRICA F°G°
05.01.03.01 CAJA DE INTERCONEXION FG 200x200x150mm und 2.00 288.26 576.52 S/.576.52
05.01.04 CONDUCTORES ELÉCTRICOS
05.01.04.01 CABLE TIPO FPL-2x16AWG m 91.89 35.36 3,249.23 S/.3,249.23
05.01.04.02 CABLE TIPO NH-80 - 2.5 mm2 m 521.93 4.64 2,421.76 S/.2,421.76
05.01.04.03 CABLE TIPO NH-80 - 4.0 mm2 m 304.79 5.51 1,679.39 S/.1,679.39
05.01.04.04 CABLE TIPO NH-80 - 16.0 mm2 m 7.26 28.01 203.35 S/.203.35
05.01.04.05 CABLE TIPO N2XOH - 70.0 mm2 m 10.87 36.13 392.73 S/.392.73
05.01.05 CONDUCTOR ELÉCTRICO PARA PUESTA A TIERRA
05.01.05.01 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 2.5 mm2 m 284.69 11.69 3,328.03 S/.3,328.03
05.01.05.02 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 4.0 mm2 m 166.25 14.32 2,380.70 S/.2,380.70
05.01.05.03 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 10.0 mm2 m 2.64 17.47 46.12 S/.46.12
05.01.06 EQUIPOS LUMINARAS_x000D_
05.01.06.01 PANEL LED RECTANGULAR PARA ADOSAR DE 40W, 220V. und 72.00 65.54 4,718.88 S/.4,718.88
05.01.06.02 LÁMPARA LED DE 10W,220V CON SOQUETE PARA ADOSAR und 17.00 35.54 604.18 S/.604.18
05.01.07 ARTEFACTOS ELECTRICOS
05.01.07.01 INTERRUPTOR SIMPLE und 11.00 17.84 196.24 S/.196.24
05.01.07.02 INTERRUPTOR DOBLE und 2.00 25.76 51.52 S/.51.52
05.01.07.03 INTERRUPTOR CONMUTADOR und 12.00 26.02 312.24 S/.312.24
05.01.07.04 TOMACORRIENTE SIMPLE (LUZ DE EMERGENCIA) 15A, 220V und 4.00 25.52 102.08 S/.102.08
05.01.07.05 TOMACORRIENTE DOBLE CON TOMA A TIERRA 15A, 220V und 35.00 30.02 1,050.70 S/.1,050.70
05.01.08 EQUIPOS DE SEGURIDAD_x000D_
05.01.08.01 LUZ ESTROBOSCOPICA CON PARLANTE DEL SISTEMA DE ALARMA CONTRA INCENDIO. und 15.00 966.86 14,502.90 S/.14,502.90
05.01.08.02 ESTACIÓN MANUAL DE ALARMA CONTRA INCENDIO. und 2.00 94.86 189.72 S/.189.72
05.01.08.03 EQUIPO LUZ DE EMERGENCIA, 220V. und 4.00 221.86 887.44 S/.887.44
05.01.09 TABLEROS GENERALES Y DE DISTRIBUCIÓN
05.01.09.01 TABLERO GENERAL TG 380 TRIFASICO 24 POLOS und 1.00 1,276.52 1,276.52 S/.1,276.52
05.01.09.02 TABLERO DE DISTRIBUCIÓN TD 380V TRIFÁSICO 24 POLOS und 1.00 1,024.89 1,024.89 S/.1,024.89
05.01.10 EQUIPOS - INTERRUPTORES TÉRMICOS - INTERRUPTORES DIFERENCIALES
05.01.10.01 INTERRUPTOR TÉRMICO 2x15A und 1.00 128.56 128.56 S/.128.56
Página 24

05.01.10.02 INTERRUPTOR TÉRMICO 2x20A und 15.00 148.56 2,228.40 S/.2,228.40


05.01.10.03 INTERRUPTOR TÉRMICO 3X63A und 1.00 153.56 153.56 S/.153.56
05.01.10.04 INTERRUPTOR TÉRMICO 3x70 und 2.00 150.56 301.12 S/.301.12
05.01.10.05 INTERRUPTOR TÉRMICO 3x80A und 2.00 150.56 301.12 S/.301.12
05.01.10.06 INTERRUPTOR DIFERENCIAL 2x25A-30mA und 12.00 115.71 1,388.52 S/.1,388.52
05.01.11 SISTEMA DE PUESTA A TIERRA
05.01.11.01 PUESTA A TIERRA und 4.00 6,500.00 26,000.00 S/.26,000.00
05.01.12 VARIOS
05.01.12.01 PRUEBAS DE PUESTAS A TIERRA GLB 1.00 4,500.00 4,500.00 S/.4,500.00
05.01.12.02 PRUEBAS DE AISLAMIENTO GLB 1.00 2,200.00 2,200.00 S/.2,200.00
05.01.12.03 PRUEBAS DE FUNCIONAMIENTO DE EQUIPOS ELÉCTRICOS GLB 1.00 3,600.00 3,600.00 S/.3,600.00
05.01.12.04 PRUEBAS DE CONTINUIDAD GLB 1.00 2,600.00 2,600.00 S/.2,600.00
05.01.12.05 PRUEBAS DE ILUMINACIÓN GLB 1.00 2,400.00 2,400.00 S/.2,400.00
05.01.12.06 PROTOCOLO DE PRUEBAS ELECTRICOS GLB 1.00 2,400.00 2,400.00 S/.2,400.00
05.01.13 INSTALACIÓN DE ELECTROBOMBA
05.01.13.01 INSTALACIÓN DE ELECTROBOMBA INCL. ACCESORIOS GLB 1.00 1,187.83 1,187.83 S/.1,187.83
05.02 INSTALACIONES DE COMUNICACIONES CCTV
05.02.01 CANALIZACIONES Y TUBERIA DE PVC - SAP
05.02.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø25MM m 43.99 12.49 549.44 S/.549.44
05.02.02 SALIDAS DE COMUNICACIONES
05.02.02.01 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 4.00 47.86 191.44 S/.191.44
05.02.03 CAJAS DE PASO E INTERCONEXIÓN ELÉCTRICA
05.02.03.01 SALIDA CON CAJA DE PASO DE 100x100x100mm FG PESADA und 1.00 50.86 50.86 S/.50.86
05.02.04 CABLEADO ESTRUCTURADO
05.02.04.01 CABLE F/UTP - CAT 6 A. m 43.99 15.39 677.01 S/.677.01
05.02.05 EQUIPOS DE SISTEMA VOZ Y DATA
05.02.05.01 CONECTOR TIPO BALUM und 8.00 28.48 227.84 S/.227.84
05.02.05.02 EQUIPO ACCESS POINT und 1.00 379.65 379.65 S/.379.65
05.02.05.03 EQUIPO DVR und 1.00 1,222.56 1,222.56 S/.1,222.56
05.02.06 EQUIPOS DE SISTEMA DE TELEFONÍA Y PROYECTOR MULTIMEDIA
05.02.06.01 EQUIPO PROYECTOR MULTIMEDIA, EN TECHO, UN CONECTOR RJ45, 1UTP CAT. 6A. und 1.00 2,338.56 2,338.56 S/.2,338.56
05.02.07 EQUIPOS DE SISTEMA DE CIRCUITO CERRADO DE TELEVISIÓN

05.02.07.01 EQUIPO CAMARA, FIJA, PARA INTERIOR, DOMO, 1.3MP, EN TECHO, UN CONECTOR BALUM, 1UTP CAT. 6A. und 4.00 118.56 474.24 S/.474.24

05.02.07.02 EQUIPO CÁMARA, FIJA, PARA INTERIOR, DOMO TIPO PTZ und 1.00 118.56 118.56 S/.118.56
COSTO DIRECTO S/.1,342,695.92 S/.243,018.75 S/.351,284.37 S/.740,974.81 S/.7,417.99
PORCENTAJE DE AVANCE VALORIZADO % 18.10% 26.16% 55.19% 0.55%
PORCENTAJE DE AVANCE VALORIZADO ACUMULADO % 18.10% 44.26% 99.45% 100.00%
GRÁFICO DEL AVANCE PROGRAMADO VS. AVANCE EJECUTADO ACUMULADO
CORRESPONDIENTE AL MES DE MARZO DEL 2021

OBRA "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I

ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO MODALIDAD : ADMINISTRACION DIRECTA MONTO ASIGNADO REF.
S/. 502,425.00
UBICACIÓN : CHONGOS BAJO, CHUPACA, JUNIN RESIDENTE : ING. JHOSEF J. CASTRO ROSAS MONTO SEGÚN RESOLUCION
S/. 1,444,331.84
FECHA : MARZO 2021 SUPERVISOR : ING. JUVENAL LUIS AQUINO CALDERON PLAZO DE EJECUCIÓN :120 días calendario

GRAFICO DEL PORCENTAJE DE AVANCE 99.45% 100.00%


1
PROGRAMADO VS EJECUTADO ACUMULADO
0.9

0.8

0.7

0.6

0.5
44.26%

0.4

0.3

0.2 18.10%

0.1 7.67%

0.00%
0
INICIO MARZO 2021 ABRIL 2021 MAYO 2021 JUNIO 2021

PROGRAMADO EJECUTADO

MONTOS VALORIZADOS PROGRAMADOS ACTUALIZADOS MONTOS VALORIZADOS EJECUTADOS

MONTOS TOTAL (Inc/ IGV) PORCENTAJES MONTOS TOTAL (Inc/ IGV) PORCENTAJES

MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.

S/. S/. % % S/. S/. % %

INICIO 0.00 0.00 0.00% 0.00% INICIO 0.00 0.00 0.00% 0.00%

MARZO 2021 261,414.15 261,414.15 18.10% 18.10% MARZO 2021 109,261.52 109,261.52 7.67% 7.67%

ABRIL 2021 377,874.98 639,289.13 26.16% 44.26% ABRIL 2021

MAYO 2021 797,063.20 1,436,352.33 55.19% 99.45% MAYO 2021

JUNIO 2021 7,979.50 1,444,331.83 0.55% 100.00% JUNIO 2021

TOTAL 1,444,331.83 TOTAL 109,261.52


NUMERO ITEM ESTADO
Caratula OK
Índice OK
###
ficha técnica de obra OK
###
Resumen ejecutivo OK
###
Informe del residente OK
###
Descripcion de las partidas ejecutadas del mes OK
###
Sustento de metrados ejecutados OK
###
Valorizacion de obra OK
###
Curva “s” OK
###
Cronograma de avance fisico OK
###
Cronograma de avanca valorizado OK
###
Copias del cuaderno de obra (fedateado) RESIDENTE
###
Panel fotofrafico (descripcion de cada fotografia)
###
Resumen De Estado Financiero
###
Cuadro De Resumen Fisico Y Financiero OK
###
Movimiento De Almacen JULIA
###
Cuadro De Control De Maquinas JULIA
###
Certificados De Calidad De Obra RESIDENTE
###
Anexos (PLANILLA) JULIA
Página 27

CRONOGRAMA VALORIZADO DE OBRA - VALORIZACIÓN 01 - ETAPA I


CORRESPONDIENTE AL MES DE MARZO DE 2021

Presupuesto "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
Entidad MUNICIPALIDAD DISTRITAL DE CHONGOS BAJO
Lugar JUNIN - CHUPACA - CHONGOS BAJO
Fecha MARZO 2021
Plazo 120 DÍAS CALENDARIOS
MES 1 MES 2 MES 3 MES 4
Item Descripción Und. Metrado Precio S/. Parcial S/.
01 TRABAJOS PRELIMINARES
01.01 CARTEL IDENTIFICACIÓN DE OBRA, INCL GIGANTOGRAFIA GLB 1.00 1,000.00 1,000.00 S/.0.00
01.02 ALMACÉN, OFICINAS Y GUARDIANÍA mes 5.00 800.00 4,000.00 S/.287.50
01.03 CERCO PERIMETRICO PROVISIONAL GLB 1.00 5,000.00 5,000.00 S/.0.00
01.04 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIAS, EQUIPOS Y HERRAMIENTAS GLB 1.00 5,000.00 5,000.00 S/.480.00
01.05 IMPLEMENTACIÓN DE SALUD, SEGURIDAD EN EL TRABAJO. GLB 0.50 35,000.00 17,500.00 S/.700.00
01.06 IMPLEMENTACIÓN DEL PLAN CONTRA COVID-19. GLB 0.50 40,000.00 20,000.00 S/.800.00
01.07 MITIGACION DE IMPACTO AMBIENTAL GLB 0.50 7,000.00 3,500.00 S/.160.00
01.08 FLETE PARA TRANSPORTE DE MATERIALES GLB 0.50 15,000.00 7,500.00 S/.450.00
01.09 DEMOLICIÓN DE PABELLÓN DE AULAS Y OTROS GLB 1.00 40,000.00 40,000.00 S/.0.00
01.10 ELIMINACIÓN DEL MATERIAL DE DEMOLICIÓN GLB 1.00 29,000.00 29,000.00 S/.0.00
02 ESTRUCTURAS
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 529.87 3.51 1,859.84 S/.1,943.79
02.01.02 TRAZO Y REPLANTEO m2 529.87 5.46 2,893.09 S/.2,882.52
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIÓN CON MAQUINARIA P/CIMENTACIÓN m3 530.07 39.37 20,868.86 S/.32,544.46
02.02.02 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO CAPAS CADA 0.20M m3 296.77 45.09 13,381.36 S/.3,837.85
02.02.03 CAMA DE ARENA PARA VIGAS DE CIMENTACIÓN m3 3.20 43.85 140.32 S/.12,661.79
02.02.04 NIVELACIÓN Y COMPACTACIÓN EN TERRENO NORMAL m2 497.47 14.25 7,088.95 S/.193.74
02.02.05 AFIRMADO DE 4" PARA VEREDAS CON EQUIPO LIVIANO m2 497.47 22.65 11,267.70 S/.10,022.69
02.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA DIST./PROM = 5KM m3 198.89 9.99 1,986.91 S/.12,265.31
02.03 CONCRETO SIMPLE
02.03.01 SOLADO
02.03.01.01 SOLADO EN ZAPATA MEZCLA C:H 1:10 m2 17.94 25.18 451.73 S/.451.73
02.03.02 CIMIENTOS CORRIDOS
02.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G m3 6.41 225.64 1,446.35 S/.1,446.35
02.03.03 SOBRECIMIENTOS
02.03.03.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 1.35 273.59 369.35 S/.369.35
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS m2 20.82 39.51 822.60 S/.822.60
02.03.04 FALSO PISO
02.03.04.01 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGÓN E=4" m2 497.47 28.92 14,386.83 S/.14,386.83
02.04 CONCRETO ARMADO
02.04.01 ZAPATAS
02.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 107.65 371.59 40,001.66 S/.40,001.66
02.04.01.02 ACERO PARA ZAPATAS GRADO 60 kg 4,584.60 9.56 43,828.78 S/.43,828.78
02.04.02 VIGAS DE CIMENTACION
02.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C=210 KG/CM2 m3 23.60 382.71 9,031.96 S/.9,031.96
02.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2 188.78 52.70 9,948.71 S/.9,948.71
02.04.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION kg 4,359.58 9.56 41,677.58 S/.41,677.58
02.04.03 SOBRECIMIENTOS ARMADOS
02.04.03.01 SOBRECIMIENTOS DE C.A. f'c=175 Kg/cm2 m3 26.16 365.75 9,568.02 S/.9,568.02
02.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS ARMADOS m2 431.60 52.70 22,745.32 S/.22,745.32
02.04.03.03 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 1,757.65 9.56 16,803.13 S/.16,803.13
02.04.04 COLUMNAS
02.04.04.01 CONCRETO EN COLUMNETAS f'c=175 kg/cm2. m3 10.35 365.75 3,785.51 S/.3,785.51
02.04.04.02 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 35.06 394.35 13,825.91 S/.13,825.91
02.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 544.51 27.07 14,739.89 S/.14,739.89
02.04.04.04 ACERO GRADO 60 EN COLUMNAS kg 12,262.82 9.56 117,232.56 S/.117,232.56
02.04.05 VIGAS
02.04.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 34.20 435.88 14,907.10 S/.14,907.10
02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 256.20 72.19 18,495.08 S/.18,495.08
02.04.05.03 ACERO GRADO 60 EN VIGAS kg 13,263.24 9.56 126,796.57 S/.126,796.57
02.04.06 LOSAS ALIGERADAS
02.04.06.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 m3 36.44 397.45 14,483.08 S/.14,483.08
Página 28

02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2 83.24 50.94 4,240.25 S/.4,240.25
02.04.06.03 BLOQUE HUECO/CONCRETO 15X30X25 CM PARA TECHO ALIGERADO und 2,971.38 3.12 9,270.71 S/.9,270.71
02.04.06.04 ACERO GRADO 60 EN LOSAS ALIGERADAS kg 3,467.00 9.56 33,144.52 S/.33,144.52
02.04.07 ESCALERAS
02.04.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 m3 17.11 453.55 7,760.24 S/.7,760.24
02.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2 115.48 81.76 9,441.64 S/.9,441.64
02.04.07.03 ACERO GRADO 60 EN ESCALERAS kg 654.00 9.63 6,298.02 S/.6,298.02
02.05 DISEÑO DE MEZCLAS
02.05.01 DISEÑO DE MEZCLA P/CONCRETO F'C=175 KG/CM² und 1.00 320.00 320.00 S/.0.00
02.05.02 DISEÑO DE MEZCLA P/CONCRETO F'C=210 KG/CM² und 1.00 320.00 320.00 S/.0.00
02.06 PRUEBA DE ROTURA
02.06.01 PRUEBA DE ROTURA DE PROBETA und 10.00 25.00 250.00 S/.250.00
03 ARQUITECTURA
03.01 MUROS Y TABIQUES
03.01.01 MURO DE LADRILLO KK TIPO IV SOGA MEZCLA: C:A 1:5 x 1:5 CM m2 495.27 70.86 35,094.83 S/.0.00
03.02 REVOQUES ENLUCIDOS Y MOLDURAS
03.02.01 TARRAJEO PRIMARIO Y RAYADO C/MEZC. C: A 1:5, E=1.5CM. m2 49.19 20.43 1,004.95 S/.1,004.95
03.02.02 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:5 x 1:5 CM m 194.06 29.31 5,687.90 S/.5,687.90
03.02.03 TARRAJEO DE MUROS EXTERIORES, E=1.5CM, C: A 1:5 m2 391.46 24.26 9,496.82 S/.9,496.82
03.02.04 TARRAJEO DE MUROS INTERIORES, E=1.5CM, C: A 1:5 m2 737.15 16.62 12,251.43 S/.12,251.43
03.02.05 TARRAJEO DE COLUMNAS, E=1.5cm, C:A 1:5 m2 242.33 31.23 7,567.97 S/.7,567.97
03.02.06 TARRAJEO DE COLUMNETAS, E=1.5cm, C:A 1:5 m2 172.97 31.23 5,401.85 S/.5,401.85
03.02.07 TARRAJEO DE VIGAS, E=1.5 CM, C: A 1:5 m2 808.46 37.82 30,575.96 S/.30,575.96
03.02.08 VESTIDURA DE DERRAMES, E=1.5CM, C: A 1:5 m 16.49 12.62 208.10 S/.208.10
03.02.09 EJECUCIÓN DE BRUÑAS EN FACHADA m 216.67 8.34 1,807.03 S/.1,807.03
03.02.10 TARRAJEO DE COBERTURA CON IMPERMEABILIZANTE m2 634.79 32.16 20,414.85 S/.20,414.85
03.03 CIELORRASOS
03.03.01 TARRAJEO DE CIELORRASO E=1.5cm, C:A 1:5 m2 436.48 28.66 12,509.52 S/.12,509.52
03.04 PISOS Y PAVIMENTOS
03.04.01 PISOS
03.04.01.01 PISO CERÁMICO 30 X 30 CM ANTIDESLIZANTE m2 37.94 78.48 2,977.53 S/.2,977.53
03.04.01.02 PORCELANATO 60X60 CM ANTIDESLIZANTE DE ALTO TRANSITO m2 402.24 76.38 30,723.09 S/.30,723.09
03.04.01.03 PISO DE CEMENTO SEMI PULIDO FROTACHADO Y BRUÑADO m2 63.94 25.00 1,598.50 S/.1,598.50
03.05 ZÓCALOS Y CONTRAZÓCALOS
03.05.01 ZÓCALOS
03.05.01.01 ZÓCALO DE CERÁMICO DE 30 X 30 CM. m2 50.45 69.10 3,486.10 S/.3,486.10
03.05.01.02 PORCELANATO DE 60 X 60 CM PARA FACHADA COLOR NEGRO m2 48.81 81.63 3,984.36 S/.3,984.36
03.05.01.03 PORCELANATO DE 60 X 60 cm PARA FACHADA COLOR BLANCO m2 13.93 81.63 1,137.11 S/.1,137.11
03.05.02 CONTRAZOCALOS
03.05.02.01 CONTRAZÓCALO DE PORCELANATO DE H=010 M m2 224.45 29.94 6,720.03 S/.6,720.03
03.06 CARPINTERÍA DE FENÓLICO
03.06.01 SEPARADORES DE MELAMINE DE E= 15MM m2 16.60 175.82 2,918.61 S/.2,918.61
03.06.02 PUERTA DE MELAMINE E= 15MM und 15.84 469.27 7,433.24 S/.7,433.24
03.07 CARPINTERIA DE MADERA
03.07.01 PUERTA APANELADA, E=35MM /INCL. COLOCACIÓN m2 3.00 382.00 1,146.00 S/.1,146.00
03.07.02 PUERTA CONTRAPLACADA E=45MM /INCL. COLOCACIÓN und 2.00 350.00 700.00 S/.700.00
03.08 CARPINTERÍA DE ALUMINIO
03.08.01 VENTANA DE ALUMINIO SEGÚN DISEÑO m2 13.06 240.00 3,134.40 S/.3,134.40
03.09 MURO CORTINA
03.09.01 MURO CORTINA DE ALUMINIO EN INGRESO PRINCIPAL m2 159.16 299.30 47,636.59 S/.47,636.59
03.09.02 MURO CORTINA DE ALUMINIO EN INTERIOR DE MODULO m2 86.75 296.30 25,704.03 S/.25,704.03
03.10 CARPINTERÍA METÁLICA
03.10.01 PUERTA EN MURO CORTINA EN INTERIOR DE MODULO (1.2 X 2.4) und 6.00 320.00 1,920.00 S/.1,920.00
03.10.02 PORTÓN TIPO REJA CORREDIZO (3.5MX3.15M) / INCL. INSTALACIÓN und 1.00 360.00 360.00 S/.360.00
03.11 OTROS
03.11.01 BARRA DE APOYO ABATIBLE VERTICAL DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS und 1.00 544.30 544.30 S/.544.30
03.11.02 BARRA DE APOYO DE ACERO INOXIDABLE CALIDAD 304 EN BAÑOS DE DISCAPACITADOS - LAVATORIOS und 1.00 544.30 544.30 S/.544.30
03.11.03 BARRA DE APOYO DE ACERO INOXIDABLE DE Ø 1" X 36" EN BAÑO DE DISCAPACITADOS und 1.00 628.59 628.59 S/.628.59
03.12 VIDRIOS, CRISTALES Y SIMILARES
03.12.01 VIDRIOS
03.12.01.01 VIDRIO TEMPLADO COLOR AZUL REFLEJANTE DE 6 MM m2 13.06 94.60 1,235.48 S/.1,235.48
03.12.01.02 VIDRIO INSULADO ESMERILADO EN MURO CORTINA INTERIOR m2 101.17 92.59 9,367.33 S/.9,367.33
03.12.01.03 VIDRIO DE SEGURIDAD EN MURO CORTINA EXTERIOR m2 86.75 117.74 10,213.95 S/.10,213.95
03.12.01.04 ESPEJO RECLINABLE (0.60X0.70) und 3.00 52.54 157.62 S/.157.62
03.12.01.05 PUERTA DE VIDRIO DE 10MM EN INGRESO PRINCIPAL m2 6.71 365.00 2,449.15 S/.2,449.15
03.13 CERRAJERIA
03.13.01 CERRADURA DE ACERO INOXIDABLE und 17.00 101.07 1,718.19 S/.1,718.19
Página 29

03.13.02 BISAGRAS ALUMINIZADA CAPUCHINA DE 3 1/2"x3 1/2" pza 12.00 18.55 222.60 S/.222.60
03.13.03 BISAGRAS DE ACERO ALUMINIZADO PESADO DE 3. 1/2" X 3. 1/2" 04 POR C/PUERTA und 36.00 25.57 920.52 S/.920.52
03.13.04 CERRADURA PESADA DE 2 GOLPES und 3.00 81.07 243.21 S/.243.21
03.13.05 MANIJA DE BRONCE PARA PUERTAS DE 4" und 17.00 41.14 699.38 S/.699.38
03.14 PINTURA
03.14.01 PINTURA LÁTEX SOBRECIMIENTOS m2 194.06 11.39 2,210.34 S/.2,210.34
03.14.02 PINTURA LÁTEX EN MUROS EXTERIORES m2 391.46 13.78 5,394.32 S/.5,394.32
03.14.03 PINTURA LÁTEX EN MUROS INTERIORES m2 737.15 11.39 8,396.14 S/.8,396.14
03.14.04 PINTURA LÁTEX COLUMNAS m2 242.33 11.39 2,760.14 S/.2,760.14
03.14.05 PINTURA LÁTEX COLUMNETAS m2 172.97 11.39 1,970.13 S/.1,970.13
03.14.06 PINTURA LÁTEX VIGAS m2 808.46 13.78 11,140.58 S/.11,140.58
03.14.07 PINTURA LÁTEX DERRAMES EN VANOS DE PUERTAS Y VENTANAS m 16.49 2.66 43.86 S/.43.86
03.14.08 PINTURA DE CIELORRASOS, LÁTEX 02 MANOS, INC. IMPRIMANTE m2 436.48 13.78 6,014.69 S/.6,014.69
03.14.09 PINTURA EN PUERTAS DE MADERA C/BARNIZ - 2 MANOS m2 24.56 14.02 344.33 S/.344.33
03.15 VARIOS
03.15.01 JUNTA DE CONSTRUCCIÓN TEKNOPORT 1" m2 1,096.47 14.95 16,392.23 S/.16,392.23
03.16 EQUIPAMIENTO
03.16.01 ESCRITORIO DE DOS GAVETAS und 11.00 190.00 2,090.00 S/.2,090.00
03.16.02 SILLA EJECUTIVA ERGONÓMICA und 17.00 150.00 2,550.00 S/.2,550.00
03.16.03 ESCRITORIO TIPO L (1.30 X 1.94) und 7.00 150.00 1,050.00 S/.1,050.00
03.16.04 SILLA VISITANTE und 25.00 100.00 2,500.00 S/.2,500.00
03.16.05 ESTANTE und 12.00 260.00 3,120.00 S/.3,120.00
03.16.14 COMPUTADORA I5 und 16.00 2,200.00 35,200.00 S/.35,200.00
03.16.15 IMPRESORA MULTIFUNCIONAL und 11.00 670.00 7,370.00 S/.7,370.00
04 INSTALACIONES SANITARIAS
04.01 INSTALACIONES SANITARIAS DE AGUA
04.01.01 MOVIMIENTO DE TIERRAS
04.01.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE AGUA SECCIÓN 0.30 M m3 3.81 45.84 174.65 S/.0.00
04.01.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 12.72 4.58 58.26 S/.0.00
04.01.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 31.79 36.78 1,169.24 S/.0.00
04.01.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 6.36 22.92 145.77 S/.0.00
04.01.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 8.27 5.65 46.73 S/.0.00
04.01.01.06 CAMA DE ARENA m2 12.72 43.85 557.77 S/.0.00
04.01.02 APARATOS Y ACCESORIOS SANITARIOS INCLUIDO COLOCACIÓN
04.01.02.01 INODORO TANQUE BAJO DE LOSA und 7.00 408.21 2,857.47 S/.2,857.47
04.01.02.02 URINARIO BAMBI und 1.00 388.21 388.21 S/.388.21
04.01.02.03 PAPELERA PARA EMPOTRAR DE LOSA pza 7.00 59.16 414.12 S/.414.12
04.01.02.04 LAVATORIO DE PARED C/GRIFE.CROMADA 20X17CM.(JAMAICA O SIMIL) und 7.00 348.61 2,440.27 S/.2,440.27
04.01.03 SISTEMA DE AGUA FRIA
04.01.03.01 SALIDA DE AGUA FRÍA (RIEGO) CON TUBERÍA DE PVC-SAP 1/2" pto 16.00 77.17 1,234.72 S/.1,234.72
04.01.04 REDES DE DISTRIBUCIÓN
04.01.04.01 RED DE DISTRIBUCIÓN TUBERÍA DE 3/4" PVC-SAP C10 m 57.33 7.78 446.03 S/.446.03
04.01.04.02 RED DE DISTRIBUCIÓN TUBERÍA DE 1/2" PVC-SAP C10 m 91.13 7.78 708.99 S/.708.99
04.01.05 ACCESORIOS DE REDES
04.01.05.01 CODO PVC-SAP 1/2" pza 4.00 9.01 36.04 S/.36.04
04.01.05.02 TEE PVC SAP DE 3/4" pza 55.00 8.51 468.05 S/.468.05
04.01.05.03 TEE PVC SAP DE 1/2" pza 2.00 8.51 17.02 S/.17.02
04.01.05.04 UNIÓN PVC SAP DE 3/4" pza 9.00 8.81 79.29 S/.79.29
04.01.05.05 UNIÓN PVC SAP DE 1/2" pza 6.00 8.41 50.46 S/.50.46
04.01.05.06 REDUCCIÓN PVC-SAP DE 3/4" A 1/2" pza 5.00 8.91 44.55 S/.44.55
04.01.05.07 VÁLVULA DE COMPUERTA DE BRONCE UNIÓN ROSCADA 1/2" pza 9.00 97.24 875.16 S/.875.16
04.01.06 INSTALACIÓN DE TANQUE ELEVADO Y CISTERNA
04.01.06.01 INSTALACIÓN DE CISTERNA GLB 1.00 4,500.00 4,500.00 S/.4,500.00
04.01.06.02 INSTALACIÓN DE TANQUE ELEVADO GLB 1.00 3,500.00 3,500.00 S/.3,500.00
04.01.07 VARIOS
04.01.07.01 CAJA CON TAPA METÁLICA PARA VÁLVULAS DE 12" X 12" und 3.00 316.20 948.60 S/.948.60
04.02 INSTALACIONES SANITARIAS DE DESAGÜE
04.02.01 MOVIMIENTO DE TIERRAS
04.02.01.01 EXCAVACIÓN DE ZANJAS PARA TUBERÍAS DE DESAGÜE SECCIÓN 0.30 M m 3.97 45.84 181.98 S/.0.00
04.02.01.02 REFINE Y NIVELACIÓN DE FONDO DE ZANJA PARA TUBERÍA m2 13.23 4.58 60.59 S/.0.00
04.02.01.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO A MANO m3 0.06 36.78 2.21 S/.0.00
04.02.01.04 ACARREO MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30.00 ML m3 6.62 22.92 151.73 S/.0.00
04.02.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE CON EQUIPO DIST. = 1.5 KM m3 1.98 5.65 11.19 S/.0.00
04.02.01.06 CAMA DE ARENA m2 13.23 43.85 580.14 S/.0.00
04.02.02 SALIDAS DE DESAGÜE Y VENTILACIÓN
04.02.02.01 SALIDA DE DESAGUE DE PVC 2" pto 7.00 76.96 538.72 S/.538.72
04.02.02.02 SALIDA DE DESAGÜE DE PVC 4" pto 4.00 84.84 339.36 S/.339.36
Página 30

04.02.02.03 SALIDA DE VENTILACIÓN EN PVC SAL 2" pto 3.00 76.96 230.88 S/.230.88
04.02.03 REDES DE DERIVACIÓN
04.02.03.01 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 4" m 34.65 14.67 508.32 S/.508.32
04.02.03.02 RED DE RECOLECCIÓN PVC SAL PARA DESAGÜE 2" m 48.20 10.39 500.80 S/.500.80
04.02.04 ACCESORIOS PARA REDES DE DERIVACIÓN
04.02.04.01 CODO PVC-SAL 2" X 45º pza 4.00 14.34 57.36 S/.57.36
04.02.04.02 CODO PVC-SAL 4" X 45º pza 2.00 22.81 45.62 S/.45.62
04.02.04.03 CODO PVC SAL 4" X 90° CON REDUCCIÓN A 2" pza 2.00 46.65 93.30 S/.93.30
04.02.04.04 YEE PVC-SAL DE 2" pza 3.00 14.74 44.22 S/.44.22
04.02.04.05 TEE PVC-SAL DE 4 pza 4.00 19.94 79.76 S/.79.76
04.02.04.06 REDUCCIÓN PVC-SAL 4"X 2" pza 16.00 16.79 268.64 S/.268.64
04.02.05 ADITAMENTOS VARIOS
04.02.05.01 SUMIDERO DE BRONCE 2" und 3.00 49.06 147.18 S/.147.18
04.02.05.02 REGISTRO ROSCADO DE BRONCE CROMADO 4" und 3.00 73.03 219.09 S/.219.09
04.02.05.03 SOMBRERO VENTILACIÓN PVC DE 2" und 3.00 18.51 55.53 S/.55.53
04.02.06 CAJAS DE REGISTRO
04.02.06.01 CAJA DE REGISTRO DE DESAGÜE 10" X 20" CON TAPA DE CONCRETO und 2.00 196.89 393.78 S/.393.78
04.03 SISTEMA DE AGUA DE LLUVIA
04.03.01 TUBERÍAS EN BAJANTES PLUVIALES
04.03.01.01 TUBERÍA PARA AGUAS PLUVIALES DE PVC SAL 3" m 9.60 10.49 100.70 S/.100.70
04.03.02 ACCESORIOS
04.03.02.01 CODO PVC-SAL 3" X 90° pza 6.00 18.91 113.46 S/.113.46
04.03.02.02 ABRAZADERA DE FIJACIÓN P/TUBERÍA PLUVIAL und 9.60 29.70 285.12 S/.285.12
05 INSTALACIONES ELÉCTRICAS Y COMUNICACIONES
05.01 INSTALACIONES ELÉCTRICAS
05.01.01 CANALIZACION Y/O TUBERIAS
05.01.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø20 MM m 645.11 13.31 8,586.41 S/.8,586.41
05.01.01.02 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø60 MM m 16.40 14.44 236.82 S/.236.82
05.01.01.03 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø43 MM m 5.28 14.07 74.29 S/.74.29
05.01.02 SALIDAS ELECTRICAS
05.01.02.01 SALIDA CON CAJA OCTOGONAL DE 100x100x50mm FG PESADA und 104.00 70.86 7,369.44 S/.7,369.44
05.01.02.02 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 60.00 72.06 4,323.60 S/.4,323.60
05.01.03 CAJAS DE INTERCONEXIÓN ELÉCTRICA F°G°
05.01.03.01 CAJA DE INTERCONEXION FG 200x200x150mm und 2.00 288.26 576.52 S/.576.52
05.01.04 CONDUCTORES ELÉCTRICOS
05.01.04.01 CABLE TIPO FPL-2x16AWG m 108.54 32.21 3,496.07 S/.3,496.07
05.01.04.02 CABLE TIPO NH-80 - 2.5 mm2 m 652.45 3.57 2,329.25 S/.2,329.25
05.01.04.03 CABLE TIPO NH-80 - 4.0 mm2 m 331.25 4.77 1,580.06 S/.1,580.06
05.01.04.04 CABLE TIPO NH-80 - 16.0 mm2 m 14.52 28.01 406.71 S/.406.71
05.01.04.05 CABLE TIPO N2XOH - 70.0 mm2 m 15.04 36.13 543.40 S/.543.40
05.01.05 CONDUCTOR ELÉCTRICO PARA PUESTA A TIERRA
05.01.05.01 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 2.5 mm2 m 355.88 11.69 4,160.24 S/.4,160.24
05.01.05.02 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 4.0 mm2 m 180.68 14.32 2,587.34 S/.2,587.34
05.01.05.03 CONDUCTOR TIPO CPT AMARILLO/VERDE DE 10.0 mm2 m 5.28 17.47 92.24 S/.92.24
05.01.06 EQUIPOS LUMINARAS
05.01.06.01 PANEL LED RECTANGULAR PARA ADOSAR DE 40W, 220V. und 72.00 65.54 4,718.88 S/.4,718.88
05.01.06.02 LÁMPARA LED DE 10W,220V CON SOQUETE PARA ADOSAR und 17.00 35.54 604.18 S/.604.18
05.01.07 ARTEFACTOS ELECTRICOS
05.01.07.01 INTERRUPTOR SIMPLE und 11.00 17.84 196.24 S/.196.24
05.01.07.02 INTERRUPTOR DOBLE und 2.00 25.76 51.52 S/.51.52
05.01.07.03 INTERRUPTOR CONMUTADOR und 12.00 26.02 312.24 S/.312.24
05.01.07.04 TOMACORRIENTE SIMPLE (LUZ DE EMERGENCIA) 15A, 220V und 4.00 25.52 102.08 S/.102.08
05.01.07.05 TOMACORRIENTE DOBLE CON TOMA A TIERRA 15A, 220V und 35.00 30.02 1,050.70 S/.1,050.70
05.01.08 EQUIPOS DE SEGURIDAD
05.01.08.01 LUZ ESTROBOSCOPICA CON PARLANTE DEL SISTEMA DE ALARMA CONTRA INCENDIO. und 15.00 966.86 14,502.90 S/.14,502.90
05.01.08.02 ESTACIÓN MANUAL DE ALARMA CONTRA INCENDIO. und 2.00 94.86 189.72 S/.189.72
05.01.08.03 EQUIPO LUZ DE EMERGENCIA, 220V. und 4.00 221.86 887.44 S/.887.44
05.01.09 TABLEROS GENERALES Y DE DISTRIBUCIÓN
05.01.09.01 TABLERO GENERAL TG 380 TRIFASICO 24 POLOS und 1.00 1,276.52 1,276.52 S/.1,276.52
05.01.09.02 TABLERO DE DISTRIBUCIÓN TD 380V TRIFÁSICO 24 POLOS und 1.00 1,024.89 1,024.89 S/.1,024.89
05.01.10 EQUIPOS - INTERRUPTORES TÉRMICOS - INTERRUPTORES DIFERENCIALES
05.01.10.01 INTERRUPTOR TÉRMICO 2x15A und 1.00 128.56 128.56 S/.128.56
05.01.10.02 INTERRUPTOR TÉRMICO 2x20A und 15.00 148.56 2,228.40 S/.2,228.40
05.01.10.03 INTERRUPTOR TÉRMICO 3X63A und 2.00 153.56 307.12 S/.307.12
05.01.10.04 INTERRUPTOR TÉRMICO 3x70 und 2.00 150.56 301.12 S/.301.12
05.01.10.05 INTERRUPTOR TÉRMICO 3x80A und 2.00 150.56 301.12 S/.301.12
05.01.10.06 INTERRUPTOR DIFERENCIAL 2x25A-30mA und 12.00 115.71 1,388.52 S/.1,388.52
Página 31

05.01.11 SISTEMA DE PUESTA A TIERRA


05.01.11.01 PUESTA A TIERRA und 1.00 6,500.00 6,500.00 S/.6,500.00
05.01.12 VARIOS
05.01.12.01 PRUEBAS DE PUESTAS A TIERRA GLB 1.00 4,200.00 4,200.00 S/.4,200.00
05.01.12.02 PRUEBAS DE AISLAMIENTO GLB 1.00 2,200.00 2,200.00 S/.2,200.00
05.01.12.03 PRUEBAS DE FUNCIONAMIENTO DE EQUIPOS ELÉCTRICOS GLB 1.00 3,600.00 3,600.00 S/.3,600.00
05.01.12.04 PRUEBAS DE CONTINUIDAD GLB 1.00 2,600.00 2,600.00 S/.2,600.00
05.01.12.05 PRUEBAS DE ILUMINACIÓN GLB 1.00 2,400.00 2,400.00 S/.2,400.00
05.01.12.06 PROTOCOLO DE PRUEBAS ELECTRICOS GLB 1.00 2,400.00 2,400.00 S/.2,400.00
05.01.14 INSTALACIÓN DE ELECTROBOMBA
05.01.14.01 INSTALACIÓN DE ELECTROBOMBA INCL. ACCESORIOS GLB 1.00 987.83 987.83 S/.987.83
05.02 INSTALACIONES DE COMUNICACIONES CCTV
05.02.01 CANALIZACIONES Y TUBERIA DE PVC - SAP
05.02.01.01 TUBERÍA PVC-SAP ELÉCTRICAS DE Ø25MM m 43.99 12.49 549.44 S/.549.44
05.02.02 SALIDAS DE COMUNICACIONES
05.02.02.01 SALIDA CON CAJA RECTAGULAR DE 100x55x50mm FG PESADA und 4.00 47.86 191.44 S/.191.44
05.02.03 CAJAS DE PASO E INTERCONEXIÓN ELÉCTRICA
05.02.03.01 SALIDA CON CAJA DE PASO DE 100x100x100mm FG PESADA und 1.00 50.86 50.86 S/.50.86
05.02.04 CABLEADO ESTRUCTURADO
05.02.04.01 CABLE F/UTP - CAT 6 A. m 43.99 15.39 677.01 S/.677.01
05.02.05 EQUIPOS DE SISTEMA VOZ Y DATA
05.02.05.01 CONECTOR TIPO BALUM und 8.00 28.48 227.84 S/.227.84
05.02.05.02 EQUIPO ACCESS POINT und 1.00 379.65 379.65 S/.379.65
05.02.05.03 EQUIPO DVR und 1.00 1,222.56 1,222.56 S/.1,222.56
05.02.06 EQUIPOS DE SISTEMA DE TELEFONÍA Y PROYECTOR MULTIMEDIA
05.02.06.01 EQUIPO PROYECTOR MULTIMEDIA, EN TECHO, UN CONECTOR RJ45, 1UTP CAT. 6A. und 1.00 2,338.56 2,338.56 S/.2,338.56
05.02.07 EQUIPOS DE SISTEMA DE CIRCUITO CERRADO DE TELEVISIÓN
05.02.07.01 EQUIPO CAMARA, FIJA, PARA INTERIOR, DOMO, 1.3MP, EN TECHO, UN CONECTOR BALUM, 1UTP CAT. 6A. und 4.00 118.56 474.24 S/.474.24
05.02.07.02 EQUIPO CÁMARA, FIJA, PARA INTERIOR, DOMO TIPO PTZ und 1.00 118.56 118.56 S/.118.56
COSTO DIRECTO S/.1,342,695.92 S/.2,877.50 S/.597,216.79 S/.334,861.62 S/.256,107.54
PORCENTAJE DE AVANCE EJECUTADO % 0.21% 44.48% 24.94% 19.07%
PORCENTAJE DE AVANCE EJECUTADO ACUMULADO % 0.21% 44.69% 69.63% 88.71%
PORCENTAJE DE AVANCE PROGRAMADO % 0.00% 0.00% 0.00% 37965.00%
PORCENTAJE DE AVANCE PROGRAMADO ACUMULADO % 0.00% 0.00% 0.00% 122256.00%
CALENDARIO VALORIZADO DE AVANCE DE OBRA

OBRA : "CREACION DEL PALACIO MUNICIPAL DEL DISTRITO DE CHONGOS BAJO - PROVINCIA DE CHUPACA - DEPARTAMENTO DE JUNIN" - ETAPA I
0 0

MES 1, ABRIL MES 2, MAYO MES 3, JUNIO MES 4, JULIO MES 5, AGOSTO MES 6, SETIEMBRE
PRECIO (DEL 20 AL 30) (DEL 01 AL 31) (DEL 01 AL 30) (DEL 01 AL 31) (DEL 01 AL 31) (DEL 01 AL 16)
PARCIAL
ITEM PARTIDAS UNIDAD METRADO UNITARIO
(S/) Resumen mensual Resumen mensual Resumen mensual Resumen mensual Resumen mensual Resumen mensual
(S/)
S/ % S/ % S/ % S/ % S/ % S/ %
I. CONSTRUCCIÓN MODULO SUM Y ADMINISTRACIÓN 285,259.38 30,585.96 10.72% 82,789.77 29.02% 34,579.84 12.12% 52,293.63 18.33% 80,533.37 28.23% 4,476.83 1.57%

II. CONSTRUCCIÓN MODULO AULA 233,330.46 26,754.29 11.47% 73,447.40 31.48% 28,034.28 12.01% 42,085.60 18.04% 58,455.30 25.05% 4,553.60 1.95%

III. MITIGACIÓN AMBIENTAL 33,452.41 2,454.71 7.34% 7,136.08 21.33% 7,136.08 21.33% 7,136.08 21.33% 7,136.08 21.33% 2,453.40 7.33%

IV. CONSTRUCCIÓN DE CERCO PERIMÉTRICO, PUERTA DE INGRESO Y PLANTEA 389,574.20 30,099.32 7.73% 47,292.72 12.14% 121,228.22 31.12% 116,870.75 30.00% 69,085.94 17.73% 4,997.26 1.28%

V. EQUIPAMIENTO 62,285.00 12,250.00 19.67% 37,526.25 60.25% 12,508.75 20.08%

VI. CAPACITACIÓN 12,633.71 12,633.72 100.00%

VII. TANQUE CISTERNA, ELEVADO, SEPTICO Y POZO PERCOLADOR 40,369.28 11,025.15 27.31% 11,385.90 28.20% 17,958.24 44.48%

COSTO DIRECTO 1,056,904.44 89,894.27 8.51% 221,691.11 20.98% 214,614.29 20.31% 218,386.06 20.66% 270,695.16 25.61% 41,623.55 3.94%
GASTOS GENERALES (10.00%) 105,690.44 8,989.43 22,169.11 21,461.43 21,838.61 27,069.52 4,162.35
UTILIDAD (10.00%) 105,690.44 8,989.43 22,169.11 21,461.43 21,838.61 27,069.52 4,162.35
SUBTOTAL 1,268,285.32 107,873.13 266,029.33 257,537.15 262,063.28 324,834.20 49,948.25
I.G.V. (18.00%) 228,291.36 19,417.16 47,885.28 46,356.69 47,171.39 58,470.16 8,990.68
MONTO TOTAL 1,496,576.68 127,290.29 313,914.61 303,893.84 309,234.67 383,304.36 58,938.93
FACTOR DE RELACIÓN 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000
VALORIZACIÓN NETA CONTRACTUAL 1,496,576.68 127,290.29 313,914.61 303,893.84 309,234.67 383,304.34 58,938.93 ###

También podría gustarte