OBRA:
PROPIETARIO:
UBICACIÓN:
FECHA:
MEDIDAS
ITEM DESCRIPCION UND CANT. n veces PARCIAL TOTAL
LARGO ANCHO ALTO
PLANILLA DE METRADOS
OBRA:
PROPIETARIO:
UBICACIÓN:
FECHA:
FECHA:
VIGAS DE CIMENTACION
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE
m2 49.93
CIMENTACION
EJES YY
EJE G,F,D,C,B 2.00 5.00 6.40 0.30 19.20
EJE E´ 2.00 1.00 1.80 0.30 1.08
EJE E 2.00 1.00 4.35 0.30 2.61
EJE D´ 2.00 1.00 1.80 0.30 1.08
EJES XX
EJE 3, 2´, 2 2.00 3.00 14.09 0.30 25.36
EJE 2´ 2.00 1.00 1.00 0.30 0.60
VIGAS
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 29.12
EJES YY
EJE G,F,D,C,B 1.00 5.00 6.40 0.35 11.2
EJE E´ 1.00 1.00 1.80 0.35 0.63
EJE E 1.00 1.00 4.35 0.35 1.52
EJE D´ 1.00 1.00 1.80 0.35 0.63
EJES XX
EJE 3, 2´, 2 1.00 3.00 14.09 0.35 14.79
EJE 2´ 1.00 1.00 1.00 0.35 0.35
FECHA:
LOSA ALIGERADA
ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADA m2 134.44
PAÑOS
1 1.00 1.00 3.15 2.95 9.29
2 1.00 1.00 3.25 2.95 9.59
3 1.00 1.00 1.80 2.22 4.00
4 1.00 1.00 1.80 1.00 1.80
5 1.00 1.00 1.10 2.85 3.14
6 1.00 1.00 3.25 2.85 9.26
7 1.00 1.00 1.80 2.22 4.00
8 1.00 1.00 1.10 2.85 3.14
9 1.00 1.00 3.25 2.85 9.26
10 1.00 1.00 3.15 2.95 9.29
11 1.00 1.00 3.25 2.95 9.59
12 1.00 1.00 3.15 2.75 8.66
13 1.00 1.00 3.25 2.75 8.94
VOLADO FRONTAL/POSTERIOR 2.00 1.00 17.25 0.70 24.15
VOLADO LATERAL/DERECHO E IZQUIERDO 2.00 1.00 7.15 0.70 10.01
FRISOS 2.00 1.00 17.25 0.20 6.90
2.00 1.00 8.55 0.20 3.42
ALBAÑILERIA
MURO DE LADRILLO KK DE ARCILLA 9X14X24CM, DE SOGA m2 153.05
EJE 3 1.00 1.00 8.94 2.50 22.35
EJE 3´ 1.00 1.00 7.05 2.55 17.98
EJE 2´ 1.00 1.00 2.75 2.50 6.88
EJE 2 1.00 1.00 11.60 2.10 24.36
1.00 1.00 2.75 2.50 6.88
EJE G, C 1.00 2.00 3.57 2.50 17.83
EJE E 1.00 1.00 7.95 2.50 19.88
EJE F,D 1.00 2.00 5.35 2.50 26.75
EJE B 1.00 1.00 3.15 1.60 5.04
1.00 1.00 0.40 2.50 1.00
1.00 1.00 1.95 2.10 4.10
FECHA:
PISOS Y PAVIMENTOS
FALSO PISO E=2" (MEZCLA 1:10, CEMENTO:HORMIGON) m2 99.41
AREA DAMAS 1.00 40.04 40.04
AREA VARONES 1.00 40.04 40.04
OFICINA ADMINISTRATIVA 1.00 9.66 9.66
DEPOSITO 1.00 9.67 9.67
FECHA:
ZOCALOS
ZOCALO DE MAYOLICA DE COLOR 0.15x0.30M. DE 1RA. m2 100.71
CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA CEDRO m2 13.44
P3 2.00 1.00 2.1 4.20
P4 4.00 0.90 2.1 7.56
P5 1.00 0.80 2.1 1.68
COSTO DIRECTO
10.00 % UTILIDAD
SUB_TOTAL
IMPUESTO(IGV 18%)
TOTAL DE OBRA
7.50 % GASTOS DE SUPERVISION
PRESUPUESTO TOTAL
Precio S/ Parcial S/
463.18 0.00
471.08 0.00
57.68 0.00
544.03 0.00
56.72 0.00
463.18 0.00
66.03 0.00
505.27 0.00
3.48 0.00
50.81 0.00
81.06 0.00
80.68 0.00
27.34 0.00
39.28 0.00
15.56 0.00
21.32 0.00
92.53 0.00
229.54 0.00
90.88 0.00
323.36 0.00
189.11 0.00
126.09 0.00
11.24 0.00
18.78 0.00
18.77 0.00
77.95 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00