MODULO

PROYECTO : Total
LABORATORIO CALIFICADO KG de
ACERO
FECHA : ENERO 2022
LA UNIÓN - PIURA - PIURA
UBICACIÓN:
DESCRIPCIÓN VOLUMEN (m3) AREAS (m2) METRO LINEAL (m) PTO UND
ITEM CALCULO
a l h n vol a l n área l n Lt GLB DE ACERO
01.00.00 ESTRUCTURAS
01.01.00 MOVIMIENTO DE TIERRAS
01.01.01 EXCAVACIONES
01.01.01.01 Excavación manual de zanjas para cimientos y/o zapatas
EXCAVACIÓN DE CIMIENTO 1
EJE 1, ENTRE EJE A Y C 1.00 6.00 1.05 1.00 6.30

EJE A, ENTRE EJE 1 Y 4 1.00 8.00 1.05 1.00 8.40

EJE C, ENTRE EJE 1 Y 4 1.00 8.00 1.05 1.00 8.40

EJE 4, ENTRE EJE A Y C 1.00 6.00 1.05 1.00 6.30

EXCAVACIÓN DE CIMIENTO 2
EJE 2, ENTRE EJE A Y B 0.85 2.47 1.05 1.00 2.20

EJE 2', ENTRE EJE A Y B 0.85 2.47 1.05 1.00 2.20

EJE B, ENTRE EJE 2 Y 2' 0.85 1.05 1.05 1.00 0.94

EJE B, ENTRE EJE 3 Y 2' 0.85 0.40 1.05 1.00 0.36

EJE 3, ENTRE EJES A Y C 0.85 4.00 1.05 1.00 3.57

EJE B, ENTRE EJE 3 Y 4 0.85 2.00 1.05 1.00 1.79

40.46

01.01.02 RELLENOS
01.01.02.01 Relleno y compactado con material propio manual.
RELLENO EN CIMIENTO 1
EJE 1, ENTRE EJE A Y C 0.75 5.50 0.50 1.00 2.06
0.25 0.80 0.50 1.00 0.10

EJE A, ENTRE EJE 1 Y 4 0.75 7.55 0.50 1.00 2.83

EJE C, ENTRE EJE 1 Y 4 0.75 7.85 0.50 1.00 2.94

EJE 4, ENTRE EJE A Y C 0.75 5.35 0.50 1.00 2.01

RELLENO EN CIMIENTO 2
EJE 2, ENTRE EJE A Y B 0.70 2.47 0.50 1.00 0.86
0.15 0.75 0.50 1.00 0.06
DESCUENTO DE COLUMNA 0.10 0.25 0.50 -1.00 -0.01

EJE 2', ENTRE EJE A Y B 0.70 2.47 0.50 1.00 0.86


DESCUENTO DE COLUMNA 0.10 0.25 0.50 -1.00 -0.01

EJE B, ENTRE EJE 2 Y 2' 0.70 1.05 0.50 1.00 0.37

EJE B, ENTRE EJE 3 Y 2' 0.85 0.40 0.50 1.00 0.17

EJE 3, ENTRE EJES A Y C 0.70 4.00 0.50 1.00 1.40


0.15 0.90 0.50 1.00 0.07
DESCUENTO DE COLUMNA 0.10 0.25 0.50 -1.00 -0.01

EJE B, ENTRE EJE 3 Y 4 0.70 2.00 0.50 1.00 0.70

14.40

01.02.00 OBRAS DE CONCRETO ARMADO


01.02.01 CIMIENTOS CORRIDOS
01.02.01.01 CONCRETO F'c=210 KG/CM2 PARA ZAPATAS
CONCRETO EN CIMIENTO 1
EJE 1, ENTRE EJE A Y C 1.00 6.00 0.50 1.00 3.00

EJE A, ENTRE EJE 1 Y 4 1.00 8.00 0.50 1.00 4.00

EJE C, ENTRE EJE 1 Y 4 1.00 8.00 0.50 1.00 4.00

EJE 4, ENTRE EJE A Y C 1.00 6.00 0.50 1.00 3.00

CONCRETO EN CIMIENTO 2
EJE 2, ENTRE EJE A Y B 0.85 2.47 0.50 1.00 1.05

EJE 2', ENTRE EJE A Y B 0.85 2.47 0.50 1.00 1.05

EJE B, ENTRE EJE 2 Y 2' 0.85 1.05 0.50 1.00 0.45

EJE B, ENTRE EJE 3 Y 2' 0.85 0.40 0.50 1.00 0.17

EJE 3, ENTRE EJES A Y C 0.85 4.00 0.50 1.00 1.70

EJE B, ENTRE EJE 3 Y 4 0.85 2.00 0.50 1.00 0.85

19.27

01.02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL


ENCOFRADO EN CIMIENTO
EXTERIORMENTE, EJE A Y C, EN EJES 1 Y 4 0.50 32.00 1.00 16.00

EJE 1 Y 3, ENTRE EJE A Y C 0.50 18.30 1.00 9.15


0.50 5.36 1.00 2.68
0.50 4.06 1.00 2.03

EJE A Y B, EN EJES 3 Y 4 0.50 7.26 1.00 3.63

EJE C Y B, EN EJES 3 Y 4 0.50 7.06 1.00 3.53

37.02

01.02.02 SOBRECIMIENTOS
01.02.02.01 CONCRETO F'c=175 KG/CM2
EJE 1, EN EJE A Y C 0.25 4.46 1.00 1.00 1.12

EJE 4, EN EJE A Y C 0.25 2.63 1.00 2.00 1.32

EJE A, EN EJE 1 Y 4 0.25 8.75 1.00 1.00 2.19

EJE C, EN EJE 1 Y 4 0.25 9.00 1.00 1.00 2.25

EJE 2, EN EJE A Y B 0.15 1.88 1.00 1.00 0.28

EJE B, EN EJE 2 Y 2' 0.15 1.75 1.00 1.00 0.26


EJE 2', EN EJE A Y B 0.15 2.62 1.00 1.00 0.39

EJE 3, EN EJE A Y B 0.15 2.23 1.00 1.00 0.33

EJE 3, EN EJE C Y B 0.15 1.88 1.00 1.00 0.28

EJE B, EN EJE 3 Y 4 0.15 3.00 1.00 1.00 0.45

8.87

01.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL


EJE 1, EN EJE A Y C 1.00 4.46 2.00 8.92
0.25 1.00 1.00 0.25

EJE 4, EN EJE A Y C 1.00 2.63 4.00 10.52

EJE A, EN EJE 1 Y 4 1.00 8.75 2.00 17.50

EJE C, EN EJE 1 Y 4 1.00 9.00 2.00 18.00

EJE 2, EN EJE A Y B 1.00 1.88 2.00 3.76


0.15 1.00 1.00 0.15

EJE B, EN EJE 2 Y 2' 1.00 1.75 2.00 3.50

EJE 2', EN EJE A Y B 1.00 2.62 2.00 5.24

EJE 3, EN EJE A Y B 1.00 1.88 2.00 3.76


1.00 0.85 1.00 0.85

EJE 3, EN EJE C Y B 1.00 1.88 2.00 3.76


0.15 1.00 1.00 0.15

EJE B, EN EJE 3 Y 4 1.00 3.00 2.00 6.00

82.36

02.00.00 ARQUITECTURA
02.01.00 MUROS Y TABIQUES DE ALBAÑILERIA
03.01.01 Muro de ladrillo KK maq. De Soga 1:5
EJE 2, EN EJE A Y B 2.05 1.88 1.00 3.85

EJE B, EN EJE 2 Y 2' 2.05 0.75 1.00 1.54


1.00 1.00 1.00 1.00

EJE 2', EN EJE A Y B 2.05 2.12 1.00 4.35


1.00 0.50 1.00 0.50

EJE 3, EN EJE A Y B 2.05 2.23 1.00 4.57

EJE 3, EN EJE C Y B 2.05 1.88 1.00 3.85

EJE B, EN EJE 3 Y 4 2.05 3.00 1.00 6.15

25.81

03.01.02 Muro de ladrillo KK maq. De Cabeza 1:5


EJE 1, EN EJE A Y C 2.05 2.05 1.00 4.20
1.00 1.20 2.00 2.40

EJE 4, EN EJE A Y C 2.05 1.43 2.00 5.86


1.00 1.20 2.00 2.40

EJE A, EN EJE 1 Y 4 2.05 8.75 1.00 17.94

EJE C, EN EJE 1 Y 4 2.05 9.00 1.00 18.45

51.25
CONSOLIDADO DE METRADOS
MÓDULOS
PROYECTADOS
"EDIFICACIÓN UNIFAMILIAR"

TOTAL METRADO

VIVIENDA

UBICACIÓN: PIURA

ITEM DESCRIPCION UND TOTAL METRADO METRADO

01.00.00 ESTRUCTURAS
01.01.00 MOVIMIENTO DE TIERRAS
01.01.01 EXCAVACIONES
01.01.01.01 Excavación manual de zanjas para cimientos y/o zapatas M3 40.46 40.46
01.01.02 RELLENOS
01.01.02.01 Relleno y compactado con material propio manual. M3 14.40 14.40
01.02.00 OBRAS DE CONCRETO ARMADO
01.02.01 CIMIENTOS CORRIDOS
01.02.01.01 CONCRETO F'c=210 KG/CM2 PARA ZAPATAS m3 19.27 19.27
01.02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL KG 37.02 37.02
01.02.02 SOBRECIMIENTOS
01.02.02.01 CONCRETO F'c=175 KG/CM2 m3 8.87 8.87
01.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 82.36 82.36
02.00.00 ARQUITECTURA
02.01.00 MUROS Y TABIQUES DE ALBAÑILERIA
03.01.01 Muro de ladrillo KK maq. De Soga 1:5 M2 25.81 25.81
03.01.02 Muro de ladrillo KK maq. De Cabeza 1:5 M2 51.25 51.25
03.01.03 Acero de anclaje en Muros De Soga KG -
03.01.04 Acero de anclaje en Muros De Cabeza KG -
LADRILLOS DE CABEZA

AREA DE MUROS 51.253

L 0.23
A 0.13
H 0.09

CL 65.68 Por M2

CANTIDAD DE LADRILLOS TOTAL

CLT = 3366.4
EN TOTAL 3367
LADRILLOS EN MUROS DE SOGA

AREA DE MUROS 25.813

L 0.23
A 0.13
H 0.09

CL 38.87 Por M2

CANTIDAD DE LADRILLOS TOTAL

CLT = 1003.4
EN TOTAL 1004