Está en la página 1de 16

Página 1

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
01.00.00 ESTRUCTURAS

01.01.00 OBRAS PROVISIONALES


01.01.01 ALMACEN Y CASETA DE GUARDIANIA M mes 5.00 5.00
01.01.02 CARTEL DE OBRA (5.4X3.6)M UND 1.00 1.00
01.02.00 TRABAJOS PRELIMINARES

01.02.01 LIMPIEZA MANUAL DEL TERRENO m2 810.00


27.000 30.00 1.00 810.00

01.02.02 TRAZOS , NIVELES Y REPLANTEOS m2 810.00 810.00


(VER PLANO PG )

01.03.00 MOVIMIENTO DE TIERRAS

01.03.01 EXCAVACION PARA ZAPATAS DE 1.00 MT A 1.40 MT DE PROFUNDIDAD m3 34.93


z-1 1.100 1.10 1.20 10.00 14.52
z-2 1.200 1.20 1.20 4.00 6.91
z-3 1.250 1.25 1.20 4.00 7.50
z-4 2.000 2.50 1.20 1.00 6.00

01.03.02 EXCAVACION MASIVA m3 666.49


VER PLANO TOPOGRAFICO

01.03.03 EXCAVACION DE CIMIENTOS CORRIDOS m3 39.41


CIMENTACION
EJE 3-CORTE 1-1 (entre e y d) 0.500 4.48 0.80 1.00 1.79
EJE 3-CORTE 2-2 (entre d y c) 0.500 2.94 1.20 1.00 1.76
EJE 4-CORTE 2-2 (entre d y c) 0.500 2.98 1.20 1.00 1.79
EJE 5-CORTE 2-2 (entre e y d) 0.500 2.18 1.20 1.00 1.31
EJE 5-CORTE 3-3 (entre e y d) 0.500 2.35 0.80 1.00 0.94
EJE 5-CORTE 2-2 (entre d y c) 0.500 2.98 0.80 1.00 1.19
EJE 6-CORTE 2-2 (d y c) 0.500 2.98 1.20 1.00 1.79
EJE 7-CORTE 2-2(entre e y d) 0.500 2.03 1.20 1.00 1.22
EJE 7-CORTE1-1(entre e y d) 0.500 2.50 0.80 1.00 1.00
Página 2

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
EJE 7-CORTE 2-2(entre d y c) 0.500 2.98 1.20 1.00 1.79
EJE 8-CORTE 2-2(entre e y d) 0.500 1.98 1.20 1.00 1.19
EJE 8-CORTE 2-2(entre e y d) 0.500 2.50 1.20 1.00 1.50
EJE 8-CORTE 2-2(entre d y c) 0.500 2.93 1.20 1.00 1.76
entre 4 y 5 ;entre e y d corte 1-1 0.500 2.20 0.80 1.00 0.88
entre 6 Y 7 ;entre e y d corte 1-1 0.500 3.68 0.80 1.00 1.47
entre 6 Y 7 ;entre d y c corte 1-1 0.500 2.60 0.80 1.00 1.04
entre 7 y 8 ;entre d y c corte 1-1 0.500 2.93 0.80 1.00 1.17
EJE C CORTE 1-1
ENTRE 3 Y 4 0.500 2.88 0.80 1.00 1.15
ENTRE4 Y 5 0.500 3.55 0.80 1.00 1.42
ENTRE 5 Y 6 0.500 2.05 0.80 1.00 0.82
ENTRE 6 Y 7 0.500 1.90 0.80 1.00 0.76
ENTRE 7 Y 8 0.500 2.57 0.80 1.00 1.03
EJE D CORTE 1-1
ENTRE 3 Y 4 0.500 2.94 0.80 1.00 1.18
ENTRE4 Y 5 0.500 3.55 0.80 1.00 1.42
ENTRE 5 Y 6 0.500 2.05 0.80 1.00 0.82
ENTRE 6 Y 7 0.500 - 0.80 1.00 -
ENTRE 7 Y 8 0.500 - 0.80 1.00 -
EJE E CORTE 1-1
ENTRE 3 Y 4 0.500 - 0.80 1.00 -
ENTRE4 Y 5 0.500 3.35 0.80 1.00 1.34
ENTRE 5 Y 6 0.500 1.92 0.80 1.00 0.77
ENTRE 6 Y 7 0.500 1.93 0.80 1.00 0.77
ENTRE 7 Y 8 0.500 2.36 0.80 1.00 0.94
ENTRE E Y D ; 4 Y 5 CORTE 1-1 0.500 1.65 0.80 1.00 0.66
ENTRE E Y D ; 4 Y 6 CORTE 1-1 0.500 4.80 0.80 1.00 1.92
ENTRE C Y D ; 6 Y 7 CORTE 1-1 0.500 1.10 0.80 1.00 0.44
ENTRE E Y D ; 7 Y 8 CORTE 1-1 0.500 0.48 0.80 2.00 0.38
RELLENO CON MATERIAL PROPIO M3 110.21
z-1 0.063 1.100 1.10 0.60 10.00 6.89
z-2 0.063 1.200 1.20 0.60 4.00 3.31
z-3 0.063 1.250 1.25 0.60 4.00 3.60
z-4 0.250 2.000 2.50 0.60 1.00 2.85
EJE 3-CORTE 1-1 (entre e y d) 0.350 4.48 0.30 1.00 0.47
EJE 3-CORTE 2-2 (entre d y c) 0.350 2.94 0.30 1.00 0.31
EJE 4-CORTE 2-2 (entre d y c) 0.350 2.98 0.30 1.00 0.31
EJE 5-CORTE 2-2 (entre e y d) 0.350 2.18 0.30 1.00 0.23
EJE 5-CORTE 3-3 (entre e y d) 0.350 2.35 0.30 1.00 0.25
EJE 5-CORTE 2-2 (entre d y c) 0.350 2.98 0.30 1.00 0.31
EJE 6-CORTE 2-2 (d y c) 0.350 2.98 0.30 1.00 0.31
EJE 7-CORTE 2-2(entre e y d) 0.350 2.03 0.30 1.00 0.21
EJE 7-CORTE1-1(entre e y d) 0.350 2.50 0.30 1.00 0.26
Página 3

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
EJE 7-CORTE 2-2(entre d y c) 0.350 2.98 0.30 1.00 0.31
EJE 8-CORTE 2-2(entre e y d) 0.350 1.98 0.30 1.00 0.21
EJE 8-CORTE 2-2(entre e y d) 0.350 2.50 0.30 1.00 0.26
EJE 8-CORTE 2-2(entre d y c) 0.350 2.93 0.30 1.00 0.31
entre 4 y 5 ;entre e y d corte 1-1 0.350 2.20 0.30 1.00 0.23
entre 6 Y 7 ;entre e y d corte 1-1 0.350 3.68 0.30 1.00 0.39
entre 6 Y 7 ;entre d y c corte 1-1 0.350 2.60 0.30 1.00 0.27
entre 7 y 8 ;entre d y c corte 1-1 0.350 2.93 0.30 1.00 0.31
EJE C CORTE 1-1
ENTRE 3 Y 4 0.350 2.88 0.30 1.00 0.30
ENTRE4 Y 5 0.350 3.55 0.30 1.00 0.37
ENTRE 5 Y 6 0.350 2.05 0.30 1.00 0.22
ENTRE 6 Y 7 0.350 1.90 0.30 1.00 0.20
ENTRE 7 Y 8 0.350 2.57 0.30 1.00 0.27
EJE D CORTE 1-1
ENTRE 3 Y 4 0.350 2.94 0.30 1.00 0.31
ENTRE4 Y 5 0.350 3.55 0.30 1.00 0.37
ENTRE 5 Y 6 0.350 2.05 0.30 1.00 0.22
ENTRE 6 Y 7 0.350 - 0.30 1.00 -
ENTRE 7 Y 8 0.350 - 0.30 1.00 -
EJE E CORTE 1-1
ENTRE 3 Y 4 0.350 - 0.30 1.00 -
ENTRE4 Y 5 0.350 3.35 0.30 1.00 0.35
ENTRE 5 Y 6 0.350 1.92 0.30 1.00 0.20
ENTRE 6 Y 7 0.350 1.93 0.30 1.00 0.20
ENTRE 7 Y 8 0.350 2.36 0.30 1.00 0.25

ENTRE E Y D ; 4Y5 CORTE 1-1 0.350 1.65 0.30 1.00 0.17


ENTRE E Y D ; 4Y6 CORTE 1-1 0.350 4.80 0.30 1.00 0.50
ENTRE C Y D ; 6Y7 CORTE 1-1 0.350 1.10 0.30 1.00 0.12
ENTRE E Y D ; 7Y8 CORTE 1-1 0.350 0.48 0.30 2.00 0.10
84.46

01.03.04 Eliminaciones (e=1.2) m3 756.74


630.621 1.20 756.74
Página 4

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
01.03.05 RELLENO CON MATERIAL DE PRESTAMO-AFIRMADO m3 33.98
(AFIRMADO e=10cm) 4.35 0.10 1.00 0.44
335.42 0.10 1.00 33.54
01.03.06 RELLENO CON MATERIAL PRESTAMO -ARENA FINA m3 33.98
(ARENA FINA e=10cm) 335.42 0.10 1.00 33.54
4.35 0.10 1.00 0.44
01.04.00 OBRAS DE CONCRETO SIMPLE
01.04.01 CIMIENTOS CORRIDOS m3 25.10
EJE 3-CORTE 1-1 (entre e y d) 0.500 4.88 0.50 1.00 1.22
EJE 3-CORTE 2-2 (entre d y c) 0.500 3.53 0.50 1.00 0.88
EJE 4-CORTE 2-2 (entre d y c) 0.500 3.83 0.50 1.00 0.96
EJE 5-CORTE 2-2 (entre e y d) 0.500 5.38 0.50 1.00 1.35
EJE 5-CORTE 3-3 (entre e y d) 0.500 - 0.50 1.00 -
EJE 5-CORTE 2-2 (entre d y c) 0.500 3.83 0.50 1.00 0.96
EJE 6-CORTE 2-2 (d y c) 0.500 3.83 0.50 1.00 0.96
EJE 7-CORTE 2-2(entre e y d) 0.500 5.43 0.50 1.00 1.36
EJE 7-CORTE1-1(entre e y d) 0.500 - 0.50 1.00 -
EJE 7-CORTE 2-2(entre d y c) 0.500 3.83 0.50 1.00 0.96
EJE 8-CORTE 2-2(entre e y d) 0.500 5.18 0.50 1.00 1.30
EJE 8-CORTE 2-2(entre e y d) 0.500 - 0.50 1.00 -
EJE 8-CORTE 2-2(entre d y c) 0.500 3.28 0.50 1.00 0.82
entre 4 y 5 ;entre e y d corte 1-1 0.500 2.20 0.50 1.00 0.55
entre 6 Y 7 ;entre e y d corte 1-1 0.500 3.68 0.50 1.00 0.92
entre 6 Y 7 ;entre d y c corte 1-1 0.500 2.60 0.50 1.00 0.65
entre 7 y 8 ;entre d y c corte 1-1 0.500 2.93 0.50 1.00 0.73
EJE C CORTE 1-1
ENTRE 3 Y 4 0.500 3.50 0.50 1.00 0.88
ENTRE4 Y 5 0.500 4.10 0.50 1.00 1.03
ENTRE 5 Y 6 0.500 2.30 0.50 1.00 0.58
ENTRE 6 Y 7 0.500 2.15 0.50 1.00 0.54
ENTRE 7 Y 8 0.500 2.57 0.50 1.00 0.64
EJE D CORTE 1-1
ENTRE 3 Y 4 0.500 3.79 0.50 1.00 0.95
ENTRE4 Y 5 0.500 4.40 0.50 1.00 1.10
ENTRE 5 Y 6 0.500 2.90 0.50 1.00 0.73
ENTRE 6 Y 7 0.500 - 0.50 1.00 -
ENTRE 7 Y 8 0.500 - 0.50 1.00 -
EJE E CORTE 1-1
ENTRE 3 Y 4 0.500 - 0.50 1.00 -
ENTRE4 Y 5 0.500 4.10 0.50 1.00 1.03
ENTRE 5 Y 6 0.500 2.30 0.50 1.00 0.58
ENTRE 6 Y 7 0.500 2.45 0.50 1.00 0.61
Página 5

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
ENTRE 7 Y 8 0.500 2.90 0.50 1.00 0.73
ENTRE E Y D ; 4 Y 5 CORTE 1-1 0.500 1.65 0.50 1.00 0.41
ENTRE E Y D ; 4 Y 6 CORTE 1-1 0.500 4.80 0.50 1.00 1.20
ENTRE C Y D ; 6 Y 7 CORTE 1-1 0.500 1.10 0.50 1.00 0.28
ENTRE E Y D ; 7 Y 8 CORTE 1-1 0.500 0.48 0.50 2.00 0.24
01.04.02 FALSA ZAPATA 1:12 C:H +30%PG m3 8.71

EJE 3-CORTE 2-2 (entre d y c) 0.500 3.53 0.50 1.00 0.88


EJE 4-CORTE 2-2 (entre d y c) 0.500 3.83 0.50 1.00 0.96
EJE 5-CORTE 2-2 (entre e y d) 0.500 5.38 0.50 1.00 1.35

EJE 5-CORTE 2-2 (entre d y c) 0.500 3.83 0.50 1.00 0.96


EJE 6-CORTE 2-2 (d y c) 0.500 3.83 0.50 1.00 0.96
EJE 7-CORTE 2-2(entre e y d) 0.500 5.43 0.50 1.00 1.36

EJE 7-CORTE 2-2(entre d y c) 0.500 3.83 0.50 1.00 0.96


EJE 8-CORTE 2-2(entre e y d) 0.500 5.18 0.50 1.00 1.30

01.04.03 SOLADO m3 3.27


z-1 1.100 1.10 0.10 10.00 1.21
z-2 1.200 1.20 0.10 4.00 0.58
z-3 1.250 1.25 0.10 4.00 0.63
z-4 2.000 2.50 0.10 1.00 0.50
CISTERNA 1.800 2.00 0.10 1.00 0.36
01.04.04 SOBRECIMIENTOS
01.04.04.01 CONCRETO 1:8 C:H+25 % PM m3 10.22
EJE 3-CORTE 1-1 (entre e y d) 0.150 4.88 0.65 1.00 0.48
EJE 3-CORTE 2-2 (entre d y c) 0.150 3.53 0.65 1.00 0.34
EJE 4-CORTE 2-2 (entre d y c) 0.150 3.83 0.65 1.00 0.37
EJE 5-CORTE 2-2 (entre e y d) 0.150 5.38 0.65 1.00 0.52
EJE 5-CORTE 3-3 (entre e y d) 0.150 - 0.65 1.00 -
EJE 5-CORTE 2-2 (entre d y c) 0.150 3.83 0.65 1.00 0.37
EJE 6-CORTE 2-2 (d y c) 0.150 3.83 0.65 1.00 0.37
EJE 7-CORTE 2-2(entre e y d) 0.150 5.43 0.65 1.00 0.53
EJE 7-CORTE1-1(entre e y d) 0.150 - 0.65 1.00 -
EJE 7-CORTE 2-2(entre d y c) 0.150 3.83 0.65 1.00 0.37
EJE 8-CORTE 2-2(entre e y d) 0.150 5.18 0.65 1.00 0.51
EJE 8-CORTE 2-2(entre e y d) 0.150 - 0.65 1.00 -
EJE 8-CORTE 2-2(entre d y c) 0.150 3.28 0.65 1.00 0.32
entre 4 y 5 ;entre e y d corte 1-1 0.150 2.20 0.65 1.00 0.21
entre 6 Y 7 ;entre e y d corte 1-1 0.150 3.68 0.65 1.00 0.36
entre 6 Y 7 ;entre d y c corte 1-1 0.150 2.60 0.65 1.00 0.25
entre 7 y 8 ;entre d y c corte 1-1 0.150 2.93 0.65 1.00 0.29
EJE C CORTE 1-1
Página 6

UND. DIMENSIONES (m)


N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
ENTRE 3 Y 4 0.150 3.50 0.65 1.00 0.34
ENTRE4 Y 5 0.150 4.10 0.65 1.00 0.40
ENTRE 5 Y 6 0.150 2.30 0.65 1.00 0.22
ENTRE 6 Y 7 0.150 2.15 0.65 1.00 0.21
ENTRE 7 Y 8 0.150 2.57 0.65 1.00 0.25
EJE D CORTE 1-1
ENTRE 3 Y 4 0.150 3.79 0.65 1.00 0.37
ENTRE4 Y 5 0.150 4.40 0.65 1.00 0.43
ENTRE 5 Y 6 0.150 2.90 0.65 1.00 0.28
ENTRE 6 Y 7 0.150 - 0.65 1.00 -
ENTRE 7 Y 8 0.150 - 0.65 1.00 -
EJE E CORTE 1-1
ENTRE 3 Y 4 0.150 - 0.65 1.00 -
ENTRE4 Y 5 0.150 4.10 0.65 1.00 0.40
ENTRE 5 Y 6 0.150 2.30 0.65 1.00 0.22
ENTRE 6 Y 7 0.150 2.45 0.65 1.00 0.24
ENTRE 7 Y 8 0.150 2.90 0.65 1.00 0.28
ENTRE E Y D ; 4 Y 5 CORTE 1-1 0.150 1.65 0.65 1.00 0.16
ENTRE E Y D ; 4 Y 6 CORTE 1-1 0.150 4.80 0.65 1.00 0.47
ENTRE C Y D ; 6 Y 7 CORTE 1-1 0.150 1.10 0.65 1.00 0.11
ENTRE E Y D ; 7 Y 8 CORTE 1-1 0.150 0.48 0.65 2.00 0.09
torre tanque elevado 0.150 5.20 0.55 1.00 0.43
01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 136.21
EJE 3-CORTE 1-1 (entre e y d) 4.88 0.65 2.00 6.34
EJE 3-CORTE 2-2 (entre d y c) 3.53 0.65 2.00 4.59
EJE 4-CORTE 2-2 (entre d y c) 3.83 0.65 2.00 4.98
EJE 5-CORTE 2-2 (entre e y d) 5.38 0.65 2.00 6.99
EJE 5-CORTE 3-3 (entre e y d) - 0.65 2.00 -
EJE 5-CORTE 2-2 (entre d y c) 3.83 0.65 2.00 4.98
EJE 6-CORTE 2-2 (d y c) 3.83 0.65 2.00 4.98
EJE 7-CORTE 2-2(entre e y d) 5.43 0.65 2.00 7.06
EJE 7-CORTE1-1(entre e y d) - 0.65 2.00 -
EJE 7-CORTE 2-2(entre d y c) 3.83 0.65 2.00 4.98
EJE 8-CORTE 2-2(entre e y d) 5.18 0.65 2.00 6.73
EJE 8-CORTE 2-2(entre e y d) - 0.65 2.00 -
EJE 8-CORTE 2-2(entre d y c) 3.28 0.65 2.00 4.26
entre 4 y 5 ;entre e y d corte 1-1 2.20 0.65 2.00 2.86
entre 6 Y 7 ;entre e y d corte 1-1 3.68 0.65 2.00 4.78
entre 6 Y 7 ;entre d y c corte 1-1 2.60 0.65 2.00 3.38
entre 7 y 8 ;entre d y c corte 1-1 2.93 0.65 2.00 3.81
EJE C CORTE 1-1
ENTRE 3 Y 4 3.50 0.65 2.00 4.55
ENTRE4 Y 5 4.10 0.65 2.00 5.33
ENTRE 5 Y 6 2.30 0.65 2.00 2.99
ENTRE 6 Y 7 2.15 0.65 2.00 2.80
ENTRE 7 Y 8 2.57 0.65 2.00 3.34
EJE D CORTE 1-1
Página 7

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
ENTRE 3 Y 4 3.79 0.65 2.00 4.93
ENTRE4 Y 5 4.40 0.65 2.00 5.72
ENTRE 5 Y 6 2.90 0.65 2.00 3.77
ENTRE 6 Y 7 - 0.65 2.00 -
ENTRE 7 Y 8 - 0.65 2.00 -
EJE E CORTE 1-1
ENTRE 3 Y 4 - 0.65 2.00 -
ENTRE4 Y 5 4.10 0.65 2.00 5.33
ENTRE 5 Y 6 2.30 0.65 2.00 2.99
ENTRE 6 Y 7 2.45 0.65 2.00 3.19
ENTRE 7 Y 8 2.90 0.65 2.00 3.77
ENTRE E Y D ; 4 Y 5 CORTE 1-1 1.65 0.65 2.00 2.15
ENTRE E Y D ; 4 Y 6 CORTE 1-1 4.80 0.65 2.00 6.24
ENTRE C Y D ; 6 Y 7 CORTE 1-1 1.10 0.65 2.00 1.43
ENTRE E Y D ; 7 Y 8 CORTE 1-1 0.48 0.65 4.00 1.25
torre tanque elevado 5.20 0.55 2.00 5.72

01.05.00 OBRAS DE CONCRETO ARMADO


01.05.01 ZAPATAS
01.05.01.01 CONCRETO(210 KG/CM2)ZAPATAS m3 14.56
z-1 1.100 1.10 0.50 10.00 6.05
z-2 1.200 1.20 0.50 4.00 2.88
z-3 1.250 1.25 0.50 4.00 3.13
z-4 2.000 2.50 0.50 1.00 2.50
01.05.01.02 ACERO f`Y=4200 Kg/cm2 kg 359.25
01.05.02 VIGAS DE CONEXIÓN
01.05.02.01 CONCRETO f`c=210 Kg/cm2 m3 3.00
EJE 3-CORTE 2-2 (entre d y c) 0.150 3.53 0.50 1.00 0.26
EJE 4-CORTE 2-2 (entre d y c) 0.150 3.83 0.50 1.00 0.29
EJE 5-CORTE 2-2 (entre e y d) 0.150 5.38 0.50 1.00 0.40

EJE 5-CORTE 2-2 (entre d y c) 0.150 3.83 0.50 1.00 0.29


EJE 6-CORTE 2-2 (d y c) 0.150 3.83 0.50 1.00 0.29
EJE 7-CORTE 2-2(entre e y d) 0.150 5.43 0.50 1.00 0.41

EJE 7-CORTE 2-2(entre d y c) 0.150 3.83 0.50 1.00 0.29


EJE 8-CORTE 2-2(entre e y d) 0.150 5.18 0.50 1.00 0.39

vc A-1 torre -tanque elevado 0.250 5.20 0.30 1.00 0.39

01.05.02.02 ENCOFRADO Y DESENCOFRADO m2 36.40


EJE 3-CORTE 2-2 (entre d y c) 3.53 0.50 2.00 3.53
EJE 4-CORTE 2-2 (entre d y c) 3.83 0.50 2.00 3.83
EJE 5-CORTE 2-2 (entre e y d) 5.38 0.50 2.00 5.38

EJE 5-CORTE 2-2 (entre d y c) 3.83 0.50 2.00 3.83


Página 8

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
EJE 6-CORTE 2-2 (d y c) 3.83 0.50 2.00 3.83
EJE 7-CORTE 2-2(entre e y d) 5.43 0.50 2.00 5.43

EJE 7-CORTE 2-2(entre d y c) 3.83 0.50 2.00 3.83


EJE 8-CORTE 2-2(entre e y d) 5.18 0.50 2.00 5.18
vc A-1 torre -tanque elevado 5.20 0.30 1.00 1.56
01.05.02.03 ACERO Kg 406.27
01.05.03 VOLADOS

01.05.03.01 CONCRETO f`c=210 Kg/cm2 m3 7.25


EJE E'
0.150 19.65 0.76 1.00 2.24
EJE C '
0.150 19.65 0.76 1.00 2.24
EJE3'
0.150 12.15 0.76 1.00 1.39
EJE8 '
0.150 12.15 0.76 1.00 1.39

01.05.03.02 ENCOFRADO Y DESENCOFRADO m2 106.21


EJE E'
0.150 19.65 0.76 1.00 32.82
EJE C '
0.150 19.65 0.76 1.00 32.82
EJE3'
0.150 12.15 0.76 1.00 20.29
EJE8 '
0.150 12.15 0.76 1.00 20.29
01.05.03.03 ACERO f`Y=4200 Kg/cm2 Kg 372.82
01.05.04.00 COLUMNAS
01.05.04.01 CONCRETO f`c=210 Kg/cm2 m3 22.35
eje E area perimetro
C-1 0.15 2.200 - 5.40 1.00 0.82
0.35 2.930 4.70 1.00 1.65
C-2 0.10 1.505 - 5.40 - -
C.3 0.15 2.200 - 5.40 - - VER PLANO E-01-E-02
4.70 - -
C.4 0.15 1.902 - 5.40 1.00 0.79
C-5 0.06 1.000 - 5.40 - -
C-6 0.16 2.189 - 5.40 2.00 1.69
C-7 0.14 2.075 - 5.40 - -
C-8 0.11 1.600 - 5.40 1.00 0.58
C-9 0.11 1.600 - 5.40 1.00 0.58
0.35 2.930 4.70 1.00 1.65
eje D -
C-1 0.15 2.200 - 4.46 - - VER PLANO E-01-E-02
Página 9

UND. N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL
0.35 2.930 4.46 -
C-2 0.10 1.505 - 4.46 1.00 0.45
C.3 0.15 2.200 - 4.46 - -
-
C.4 0.15 1.902 - 4.46 - -
C-5 0.06 1.000 - 4.46 4.00 1.12
C-6 0.16 2.189 - 4.46 - -
C-7 0.14 2.075 - 4.46 1.00 0.64
C-8 0.11 1.600 - 4.46 - -
C-9 0.11 1.600 - 4.46 - -
0.35 2.930 -
EJE C -
C-1 0.15 2.200 - 3.84 - -
0.35 2.930 3.14 - -
C-2 0.10 1.505 - 3.84 - -
C.3 0.15 2.200 - 3.84 2.00 1.17 VER PLANO E-01-E-02
0.22 3.017 3.14 2.00 1.38
C.4 0.15 1.902 - 3.84 - -
C-5 0.06 1.000 - 3.84 1.00 0.24
C-6 0.16 2.189 - 3.84 - -
C-7 0.14 2.075 - 3.84 3.00 1.64
C-8 0.11 1.600 - 3.84 - -
C-9 0.11 1.600 - 3.84 - -
0.35 2.930 3.14 -
-
C-10 0.06 1.000 - 7.60 2.00 0.95
C-11 0.04 0.800 - 4.60 23.00 3.97
C-12 0.02 0.600 - 4.60 6.00 0.62
C-13 0.07 1.200 - - - -
C-14 0.16 2.300 - 7.60 2.00 2.43
C-15 0.03 0.700 - - - -
C-16 0.05 1.015 - - - -
C-17 0.04 0.800 - - - -
COLUMNETAS DE INDEPENDIZACION DE ALFEIZER 0.13 - 0.15 15.700 4.00 1.22

01.05.04.02 ENCOFRADO Y DESENCOFRADO m2 350.42


eje E area perimetro
C-1 0.15 2.200 - 5.40 1.00 11.88
0.35 2.930 4.70 1.00 13.77
C-2 0.10 1.505 - 5.40 - -
C.3 0.15 2.200 - 5.40 - - VER PLANO E-01-E-02
4.70 - -
C.4 0.15 1.902 - 5.40 1.00 10.27
C-5 0.06 1.000 - 5.40 - -
Página 10

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL
C-6 0.16 2.189 - 5.40 2.00 23.64
C-7 0.14 2.075 - 5.40 - -
C-8 0.11 1.600 - 5.40 1.00 8.64
C-9 0.11 1.600 - 5.40 1.00 8.64
0.35 2.930 4.70 1.00 13.77
eje D -
C-1 0.15 2.200 - 4.46 - -
0.35 2.930 4.46 -
C-2 0.10 1.505 - 4.46 1.00 6.71
C.3 0.15 2.200 - 4.46 - - VER PLANO E-01-E-02
-
C.4 0.15 1.902 - 4.46 - -
C-5 0.06 1.000 - 4.46 4.00 17.84
C-6 0.16 2.189 - 4.46 - -
C-7 0.14 2.075 - 4.46 1.00 9.25
C-8 0.11 1.600 - 4.46 - -
C-9 0.11 1.600 - 4.46 - -
0.35 2.930 -
EJE C -
C-1 0.15 2.200 - 3.84 - -
0.35 2.930 3.14 - -
C-2 0.10 1.505 - 3.84 - -
C.3 0.15 2.200 - 3.84 2.00 16.90 VER PLANO E-01-E-02
0.22 3.017 3.14 2.00 18.95
C.4 0.15 1.902 - 3.84 - -
C-5 0.06 1.000 - 3.84 1.00 3.84
C-6 0.16 2.189 - 3.84 - -
C-7 0.14 2.075 - 3.84 3.00 23.90
C-8 0.11 1.600 - 3.84 - -
C-9 0.11 1.600 - 3.84 - -
0.35 2.930 3.14 -
C-10 0.06 1.000 - 7.60 2.00 15.20
C-11 0.04 0.800 - 4.60 23.00 84.64
C-12 0.02 0.600 - 4.60 6.00 0.62
C-13 0.07 1.200 - - - -
C-14 0.16 2.300 - 7.60 2.00 34.96
C-15 0.03 0.700 - - - -
C-16 0.05 1.015 - - - -
C-17 0.04 0.800 - - - -
COLUMNETAS DE INDEPENDIZACION DE ALFEIZER 0.430 15.700 4.00 27.00
Página 11

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL

01.05.04.03 ACERO f`Y=4200 Kg/cm2 Kg 2,911.42

01.05.05.00 VIGAS
01.05.05.01 CONCRETO f`c=210 Kg/cm2 m3 13.34

eje 1a
VIGA 2 0.250 1.30 0.20 2.00 1.69
eje 2
VIGA 2 0.250 1.30 0.20 2.00 0.13
eje 2 '
VIGA 7 0.150 11.40 0.20 1.00 0.34
eje 3 -
V-3 0.400 1.05 0.20 1.00 0.08
V-2 0.250 3.85 0.20 1.00 0.19
V-1 0.250 5.45 0.20 1.00 0.27
V-3 0.400 1.05 0.20 1.00 0.08
eje 4
V-5 0.300 1.05 0.20 1.00 0.06
V-2 0.250 3.85 0.20 1.00 0.19
V-4 0.300 5.45 0.20 1.00 0.33
V-5 0.300 1.05 0.20 1.00 0.06
eje 5
V-5 0.300 1.05 0.20 1.00 0.06
V-2 0.250 3.85 0.20 1.00 0.19
V-2 0.250 5.45 0.20 1.00 0.27
V-5 0.300 1.05 0.20 1.00 0.06
eje6
V-5 0.300 1.05 0.20 1.00 0.06
V-2 0.250 3.85 0.20 1.00 0.19
V-4 0.300 5.45 0.20 1.00 0.33
V-5 0.300 1.05 0.20 1.00 0.06
eje 7
V-5 0.300 1.05 0.20 1.00 0.06
V-2 0.250 3.85 0.20 1.00 0.19
V-2 0.250 5.45 0.20 1.00 0.27
V-5 0.300 1.05 0.20 1.00 0.06
eje 8
V-3 0.400 1.05 0.20 1.00 0.08
V-2 0.250 3.85 0.20 1.00 0.19
V-1 0.250 5.45 0.20 1.00 0.27
V-3 0.400 1.05 0.20 1.00 0.08
Página 12

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL

eje 8'
VIGA 7 0.150 11.40 0.20 1.00 0.34
eje A -
V-2 0.250 1.80 0.20 2.00 0.18
eje B
V-2 0.250 1.80 0.20 2.00 0.18
eje C'
V-6 0.200 19.65 0.20 1.00 0.79
eje C
V-1 0.250 19.65 0.20 1.00 0.98
eje D
V-1 0.250 19.65 0.20 1.00 0.98
eje E
V-1 0.250 19.65 0.20 1.00 0.98
eje E'
V-6 0.200 19.65 0.20 1.00 0.79
DINTELES

0.25 3.20 0.20 3.00 0.48


0.25 1.20 0.20 3.00 0.18
0.25 0.80 0.20 3.00 0.12
0.25 1.20 0.20 3.00 0.18
0.25 1.00 0.20 3.00 0.15
0.25 1.00 0.20 3.00 0.15
0.25 2.40 0.20 3.00 0.36
0.25 0.80 0.20 3.00 0.12
0.25 1.20 0.20 3.00 0.18
0.25 1.00 0.20 3.00 0.15
0.25 1.00 0.20 3.00 0.15
V-ALFEIZAR 0.13 10.40 0.10 2.00 0.27

01.05.05.02 ENCOFRADO Y DESENCOFRADO m2 164.28


eje 1a
VIGA 2 0.250 1.30 0.20 2.00 1.69
eje 2
VIGA 2 0.250 1.30 0.20 2.00 1.69
eje 2 '
Página 13

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
VIGA 7 0.150 11.40 0.20 1.00 6.27
eje 3
V-3 0.400 1.05 0.20 1.00 0.84
V-2 0.250 3.85 0.20 1.00 2.50
V-1 0.250 5.45 0.20 1.00 3.54
V-3 0.400 1.05 0.20 1.00 0.84
eje 4
V-5 0.300 1.05 0.20 1.00 0.74
V-2 0.250 3.85 0.20 1.00 2.50
V-4 0.300 5.45 0.20 1.00 3.82
V-5 0.300 1.05 0.20 1.00 0.74
eje 5
V-5 0.300 1.05 0.20 1.00 0.74
V-2 0.250 3.85 0.20 1.00 2.50
V-2 0.250 5.45 0.20 1.00 3.54
V-5 0.300 1.05 0.20 1.00 0.74
eje6
V-5 0.300 1.05 0.20 1.00 0.74
V-2 0.250 3.85 0.20 1.00 2.50
V-4 0.300 5.45 0.20 1.00 3.82
V-5 0.300 1.05 0.20 1.00 0.74
eje 7
V-5 0.300 1.05 0.20 1.00 0.74
V-2 0.250 3.85 0.20 1.00 2.50
V-2 0.250 5.45 0.20 1.00 3.54
V-5 0.300 1.05 0.20 1.00 0.74
eje 8
V-3 0.400 1.05 0.20 1.00 0.84
V-2 0.250 3.85 0.20 1.00 2.50
V-1 0.250 5.45 0.20 1.00 3.54
V-3 0.400 1.05 0.20 1.00 0.84
eje 8'
VIGA 7 0.150 11.40 0.20 1.00 6.27
eje A -
V-2 0.250 1.80 0.20 2.00 2.34
eje B
V-2 0.250 1.80 0.20 2.00 2.34
eje C'
V-6 0.200 19.65 0.20 1.00 11.79
eje C
V-1 0.250 19.65 0.20 1.00 12.77
eje D
V-1 0.250 19.65 0.20 1.00 12.77
eje E
V-1 0.250 19.65 0.20 1.00 12.77
eje E'
V-6 0.200 19.65 0.20 1.00 11.79
DINTELES
0.25 3.20 0.20 3.00 6.24
Página 14

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
0.25 1.20 0.20 3.00 2.34
0.25 0.80 0.20 3.00 1.56
0.25 1.20 0.20 3.00 2.34
0.25 1.00 0.20 3.00 1.95
0.25 1.00 0.20 3.00 1.95
0.25 2.40 0.20 3.00 4.68
0.25 0.80 0.20 3.00 1.56
0.25 1.20 0.20 3.00 2.34
0.25 1.00 0.20 3.00 1.95
0.25 1.00 0.20 3.00 1.95
V-ALFEIZAR 0.13 10.40 0.10 2.00 6.86

01.05.05.03 ACERO f`Y=4200 Kg/cm2 Kg 2,065.15

01.05.06.00 LOSA ALIGERADA


01.05.06.01 CONCRETO f`c=210 Kg/cm2 M3 21.29
POSTA 0.100 19.65 0.15 31.00 9.14
12.150 19.65 0.05 1.00 11.94
TORRE 0.100 1.30 0.15 5.00 0.10
1.800 1.30 0.05 1.00 0.12
01.05.06.02 ENCOFRADO Y DESENCOFRADO M2 241.09
12.150 19.65 1.00 238.75
1.800 1.300 1.00 2.34
01.05.06.03 ACERO f`Y=4200 Kg/cm2 KG 1,317.86
01.05.06.04 LADRILLO HUECO PARA TECHO (30 X30 X15 CM ) UND 12.150 19.65 8.33 1,989.48 2,008.98
1.800 1.300 8.33 19.50
Página 15

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
01.06.00 CERCO PERIMETRICO 0.150 0.60 0.20 1.00 0.33
01.06.01 MOVIMIENTO DE TIERRAS

01.06.01.01 EXCAVACION DE ZAPATAS DE CERCO PERIMETRICO m3 0.86

C-13 SIN REFUERZO 0.60 0.60 1.20 2.00 0.86

01.06.01.02 EXCAVACION DE CIMIENTOS CORRIDOS m3 38.38


0.45 106.60 0.80 1.00 38.38
CERCO

01.06.01.03 RELLENO CON MATERIAL PROPIO m3 8.00


0.30 106.60 0.25 1.00 8.00

01.06.01.04 Eliminaciones (e=1.2) m3 37.49 37.49

01.06.02 OBRAS DE CONCRETO SIMPLE

01.06.02.01 CIMIENTOS CORRIDOS m3 26.38


0.45 106.60 0.55 1.00 26.38

01.06.02.01 SOLADO PARA ZAPATAS M3 0.07


0.60 0.60 0.10 2.00 0.07
Página 16

UND.
N° DE
PARTIDA DESCRIPCION AREA(M2) ANCHO LARGO ALTURA ELEM. PARCIAL TOTAL OBSERV.
01.06.03 OBRAS DE CONCRETO ARMADO
01.06.03.01 ZAPATAS DE PORTICO PRINCIPAL m3 0.36
01.06.03.01.01 CONCRETO 0.60 0.60 0.50 2.00 0.36

01.06.03.02 SOBRECIMIENTO ARMADO


01.06.03.02.01 CONCRETO f`c=210 Kg/cm2 m3 8.79
0.15 106.60 0.55 1.00 8.79

01.06.03.02.02 ENCOFRADO Y DESENCOFRADO m2 117.26


106.60 0.55 2.00 117.26

01.06.03.02.03 ACERO Kg 334.69

01.06.03.03 COLUMNAS

01.06.03.03.01 CONCRETO f`c=210 Kg/cm2 m3 4.72


C-13 0.15 0.45 4.55 2.00 0.61
C-15 0.15 0.20 2.75 5.00 0.41
C-16 0.05 1.00 2.75 2.00 0.29
C-17 0.15 0.25 2.75 33.00 3.40

01.06.03.03.02 ENCOFRADO Y DESENCOFRADO m2 98.65


C-13 0.15 0.45 4.55 2.00 10.92
C-15 0.15 0.20 2.75 5.00 9.63
C-16 1.00 2.75 2.00 5.50
C-17 0.15 0.25 2.75 33.00 72.60

ACERO f`Y=4200 Kg/cm2


01.06.03.03.03 Kg 586.27

01.06.03.04 VIGAS

01.06.03.04.01 CONCRETO f`c=210 Kg/cm2 m3 0.20


V-04 0.20 3.40 0.30 1.00 0.20

01.06.03.04.02 ENCOFRADO Y DESENCOFRADO m2 2.38

V-04 0.20 3.40 0.30 1.00 2.38

01.06.03.04.03 ACERO f`Y=4200 Kg/cm2 Kg


15.54