Está en la página 1de 1

PLANILLA DE METRADOS Nº 1

OBRA : CALCULO DE MATERIALES

DISTRITO : JUNIN ALUMNO: TERREL PAYANO, GUSTAVO


PROVINCIA : JUNIN
REGION : JUNIN

N° DIMENCIONES CEMENTO ARENA GRAVA AGUA


ITEM DESCRIPCION Und. CANT. PARCIAL TOTAL
VECES AREA LARGO ANCHO ALTO
04.00 CONCRETO SIMPLE
04.01 SOLADO PARA ZAPATAS M3 0.27 1.33 0.14 0.27 0.02
SOLADO 1 1 0.90 0.90 0.05 0.04
SOLADO 2 4 0.80 0.80 0.05 0.13
SOLADO 3 4 0.70 0.70 0.05 0.10

04.02 CIMIENTOS CORRIDOS 1:10 + 30% P.G. F¨y> 100kg/cm2 M3 2.86 14.28 1.46 2.86 0.26
VERTICAL
EJE A ENTRE EJE 1 Y 2 1 1.58 0.35 0.50 0.28
EJE A ENTRE EJE 2 Y 3 1 2.23 0.35 0.50 0.39
EJE A' ENTRE EJE 2 Y 3 1 2.25 0.35 0.50 0.39
EJE B ENTRE EJE 2 Y 3 1 1.60 0.35 0.50 0.28
EJE C ENTRE EJE 1 Y 2 1 1.58 0.35 0.50 0.28
EJE C ENTRE EJE 2 Y 3 1 2.23 0.35 0.50 0.39
HORIZONTAL
EJE 1 ENTRE EJE A Y B 1 1.40 0.35 0.50 0.25
EJE 1 ENTRE EJE B Y C 1 1.40 0.35 0.50 0.25
EJE 2 ENTRE EJE B Y C 1 1.25 0.35 0.50 0.22
EJE 3 ENTRE EJE A Y B 1 0.80 0.35 0.50 0.14
EJE 3 ENTRE EJE B Y C 1 1.40 0.35 0.50 0.25
ADICIONAL 1 0.80 0.35 0.50 0.14
05.00 OBRAS DE CONCRETO ARMADO
05.01 CONCRETO PARA ZAPATAS F'C=210 KG/CM2 M3 2.67 23.99 1.39 1.41 0.50
ZAPATA 1(Z-1) 1 0.90 0.90 0.50 0.41
ZAPATA 2(Z-2) 4 0.80 0.80 0.50 1.28
ZAPATA 3(Z-3) 4 0.70 0.70 0.50 0.98

05.03 COLUMNAS.- CONCRETO 210KG/CM2 M3 1.29 12.59 1.29 0.69 0.24


PRIMER PISO
C-01 9 0.25 0.25 2.30 1.29

sin desp.
05.09 LOSAS MACIZAS.- CONC. 210 KG/CM2 M3 fac: 2.18 218
24.86 0.09 2.18