Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 2 de 41
Índice
1. Datos Generales .................................................................................................... 4
2. Alcance .................................................................................................................. 4
3. Objetivo ................................................................................................................. 4
4. Marco Normativo/ Documentos de Referencia ....................................................... 4
5. Términos y Definiciones......................................................................................... 5
6. Responsabilidad del Personal................................................................................ 6
7. Secuencia del Trabajo ........................................................................................... 9
7.1. Topografía ...................................................................................................... 9
7.2. Evaluación Geomecánica ............................................................................... 9
7.3. Excavación mediante la Ventana de Descarga ............................................. 10
7.4. Salida del Túnel de Descarga ....................................................................... 19
7.5. Servicios Auxiliares....................................................................................... 32
8. Documentos de Referencia ................................................................................. 35
9. Recursos ............................................................................................................. 36
9.1. Mano de Obra............................................................................................... 36
9.2. Equipos ........................................................................................................ 36
9.3. Herramientas ................................................................................................ 37
9.4. Materiales ..................................................................................................... 37
9.5. Cronograma de Ejecución ............................................................................ 38
10. Aseguramiento y control de calidad.................................................................. 38
11. Seguridad, Salud Ocupacional y Medio Ambiente ............................................ 39
11.1. Riesgos asociados .................................................................................... 39
11.2. Equipos de protección personal (EPP) ...................................................... 40
11.3. Sistema de protección colectivo ................................................................ 40
11.4. Equipos de Emergencia ............................................................................ 41
11.5. Material para Señalizaciones .................................................................... 41
11.6. Documentos .............................................................................................. 41
11.7. Restricciones ............................................................................................ 41
12. Anexos ............................................................................................................. 41
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 4 de 41
1. Datos Generales
Lugar donde se desarrollará la actividad: Proyecto: “Central Hidroeléctrica San Gabán
III” en el distrito de San Gabán, provincia Carabaya, departamento de Puno.
Ejecutante: CWE y empresas contratistas.
Horario de Trabajo: Se realizará en dos turnos, diurno (7:30 a 19:30) y nocturno (19:30
a 7:30). Con una hora de alimentos por cada turno.
2. Alcance
El presente procedimiento tiene aplicación para la construcción del “Túnel de Descarga”
que CWE ejecute, el cual debe ser cumplido con el contratista, sub contratistas,
proveedores y demás participantes de la construcción.
3. Objetivo
El objetivo principal del presente documento es otorgar los métodos de excavación y
sostenimiento para la construcción de la salida del túnel “Túnel de Descarga”.
5. Términos y Definiciones
Acarreo: Transporte de material excavado del lugar de la operación hasta su
disposición final o temporal.
Paraguas o micropilotes: De acuerdo con la forma y estilo de la sección, los
tubos de acero van a estar dispuestos en una dirección circunferencial en un
cierto intervalo para formar un cobertizo de tubos.
Método de perforación y voladura: Diseños de taladros con barrenos y
colocación de emulsiones para su explosión.
Eliminación: Es el material excedente, después de haber realizado el relleno
con material propio, estos serán transportados hasta los DMEs con maquinarias.
Sostenimiento con pernos de anclaje y mortero: Mantener las rocas estables
en el túnel, utilizando pernos y mortero.
Personal Autorizado: Son aquellas personas que efectúan trabajos de
voladura, manipulan, transportan explosivos y cuenta con la debida autorización
vigente expedida por la SUCAMEC.
Espaciamiento: Es la distancia entre taladro y taladro.
Altura del Taladro: Es la profundidad del Taladro perforado.
Taladro: Perforación de forma cilíndrica que se realiza en la roca para poder
cargar los explosivos.
Taco: Parte del taladro que no lleva carga y se tapa con cartón, sirviendo como
retenedor de la energía explosiva.
Prima: Es la unión de un detonador y un iniciador, sirve para iniciar la carga
explosiva.
DME: Deposito de Material Excedente donde se acopia los materiales
excavados (tierra y piedras) del túnel.
Ventilación: Transportar el aire fresco a los frentes de trabajo con ventiladores
axiales a través de las mangas de ventilación y evacuar el aire viciado fuera del
túnel.
Grado de Luminosidad: Es aquel que comprende la cantidad de iluminación
ya sea por medios mecánicos o medios naturales.
Lumen: Unidad de medida que se usa para describir la cantidad de luz que
emite una fuente sobre una superficie.
Lux: Es equivalente a un lumen por metro cuadrado.
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 6 de 41
Ingeniero de Calidad:
Revisar a diario los procesos de operación de acuerdo a las normas.
Identificar, comunicar y tomar medidas preventivas de los riesgos
encontrados en la zona de trabajo.
Coordinar y vigilar que las actividades descritas en el presente
procedimiento se realicen según lo descrito.
Verificar el análisis de riesgos para la actividad.
Proporcionar indicaciones oportunas, eficaces y aptas al residente de la obra
Verificar que los equipos y herramientas dispuestos para las actividades
cuenten con certificado de calibración vigente y su check list de inspección.
Garantizar que los trabajadores estén capacitados en el presente
procedimiento.
Documentar las actividades realizadas completando los protocolos de
calidad adecuadamente.
Realizar la recepción de los materiales utilizados: acero de refuerzo, pernos,
cable bolting, tubos para drenaje, mallas, cintas de aterramiento, shotcrete,
mortero y concreto, de acuerdo con las condiciones dispuestas para cada
material en los correspondientes informes de recepción y planos.
Efectuar y documentar las inspecciones que le corresponden de acuerdo con
el Programa de Puntos de Inspección y asegurar el correcto archivo de todos
los registros generados en relación con esta unidad de ejecución.
Ingeniero Geólogo:
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 9 de 41
Figura 02: Vista en planta del Túnel de Descarga (Ver plano 413E63-04-
06-03)
7.3.1. Sostenimiento
Sección tipo A:
Para el sostenimiento la sección tipo A del túnel de descarga, se tiene
como referencia el plano 413E63-04-06-07, el mismo que indica lo
siguiente:
Sección tipo B:
Para el sostenimiento de la sección tipo B del túnel de descarga, se tiene
como referencia el plano 413E63-04-06-07, el mismo que indica lo
siguiente:
Clase de Roca IV
Sección Tipo Baúl 5.50 x 5.55 m2
Pernos en Bóveda 07 Ø25mm@21°, L=4.5m, e=1m
Pernos en hastiales 06 Ø25mm@1m, L=4.5m, e=1m
Shotcrete con fibra de acero 15cm y luego 2cm de C20W6
Concreto en piso 30cm
Drenaje 04 Ø56mm@30°, L=0.5m, e=3m
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 13 de 41
Sección tipo C:
Para el sostenimiento de la sección tipo C del túnel de descarga, se tiene
como referencia el plano 413E63-04-06-07, el mismo que indica lo
siguiente:
Sección tipo D:
Para el sostenimiento de la sección tipo D del túnel de descarga, se
tiene como referencia el plano 413E63-04-06-07, el mismo que indica lo
siguiente:
Clase de Roca V
Sección Tipo Baúl 7.20 x 6.90 m2
Pernos en Bóveda 09 Ø25mm@16°, L=4.5m, e=1m
Pernos en hastiales 08 Ø25mm@1m, L=4.5m, e=1m
Shotcrete con fibra de acero 20cm y luego 2cm de C20W6
Concreto en piso y paredes 80cm
Arco de acero HEB 120 @ 0.8m
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 15 de 41
EXPLOSIVO (Kg)
Roca Tipo IV
ROCA IV
LONGITUD DE AVANCE POR DISPARO(m) 2.50
AREA 27.68
VOLUMEN 69.21
CARGA TOTAL (kg) 98.30
Nro. de Taladros 68.00
Nro. de Alivios 2.00
FACTOR DE CARGA (Kg/m3) 1.42
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 17 de 41
EXPLOSIVO (Kg)
NUMERO DE COLUMNA DE EMULEX 65% EMULEX 65% EMULEX 80%
DESCRIPCIÓN TACO TOTAL
TALADRO CARGA 1 1/2 x 12 1 1/4 x 12 1 1/4 x 12 EMUL. 65% EMUL. 80% EMUL. 65% EMUL. 80%
1 1/2 x 12 1 1/2 x 12 1 1/4 x 12 1 1/4 x 12
Roca Tipo V
ROCA IV
LONGITUD DE AVANCE POR DISPARO(m) 1.50
AREA 35.77
VOLUMEN 53.66
CARGA TOTAL (kg) 57.44
Nro. de Taladros 91.00
Nro. de Alivios 0.00
FACTOR DE CARGA (Kg/m3) 1.07
EXPLOSIVO (Kg)
NUMERO DE COLUMNA DE EMULEX 65% EMULEX 65%
DESCRIPCIÓN TACO TOTAL
TALADRO CARGA 1 1/2 x 12 1 1/4 x 12 EMUL. 65% EMUL. 80% EMUL. 65% EMUL. 80%
1 1/2 x 12 1 1/2 x 12 1 1/4 x 12 1 1/4 x 12
7.4.2. Afrontamiento
La medición de replanteo de los puntos de control debe tomarse antes de
la construcción, la pendiente se puede excavar cuando la medición de
replanteo sea correcta.
Para el afrontonamiento del túnel de descarga se tiene como referencia el
plano 413E63-04-06-01, tal y como se aprecia en la figura N° 13.
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 21 de 41
Alcantarillado
Reductor de Velocidad
Carretera interoceánica
talud en el rango del arco de concreto “perímetro del falso túnel” que se
muestra en la figura, debe protegerse solo con un shotcrete de 10 cm.
Alcantarillado
Reductor de Velocidad
Carretera interoceánica
Figura 17: Vista lateral del tubo guía del falso túnel (Ver plano
413E63-04-08).
7.4.4. Construcción del cobertizo de Micropilotes
El techo o cubierta de la tubería del túnel debe ser construido por dos
segmentos. La longitud del arco de cobertura es de 2 m a lo largo del eje
del túnel, y la cantidad real debe contarse en el sitio. La longitud de las
juntas de la cubierta del primer y segundo segmento es de 3 m. Las
partes altas y bajas del túnel en el segmento del techo o cubierta de
tubería podrían excavarse por separado. El constructor puede ajustar el
método de excavación según la situación en el sitio, pero debe garantizar
la estabilidad de la roca circundante durante el período de construcción.
El plan de construcción debe ser informado y aprobado antes de que
entre en vigencia.
Figura 22: Vista de altura entre cota superior del túnel con la
carretera interoceánica
a) Ventilación
b) Instalación Eléctrica
Siempre en las instalaciones y equipos más usuales para dar servicio al
interior del túnel son:
Casa de fuerza.
Cuadros eléctricos.
Grupos electrógenos.
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 33 de 41
Luminarias.
riesgo eléctrico.
Que indiquen el lugar donde existan cables y equipos eléctricos
enterrados.
Las herramientas eléctricas manuales no deben ser operadas a
alto voltaje.
9. Recursos
9.2. Equipos
Excavadoras sobre Orugas CAT 329
Tractor sobre Orugas
Cargador frontal sobre llantas 3 m3
Volquetes 15 m3
Robot Shotcretero
Equipo de Iluminación
Compresora 750
Perforadora Jack Leg. YT-28
Cisterna
Estación Total Leyca
Jumbo hidráulico DT820
Código: POET-CWE-060-
Excavación y sostenimiento en 19
casa de máquinas Versión 00
Fecha: 16-12-2019
PROCEDIMIENTO OPERATIVO ESPECÍFICO DE TRABAJO
Proyecto: “Construcción Central Hidroeléctrica San Gabán III” N° Páginas: Página 37 de 41
9.3. Herramientas
Motosierra
Machete
Palas
Pico
Barretas
Comba de 6 Lbs.
Barrenos
Sacabarrenos
Wincha
Barretillas de desate
9.4. Materiales
Excavación y sostenimiento para afrontonamiento
ITEM CLASIFICACIÓN UNIDAD CANTIDAD
Excavación Suelo m3 2048
C25W6F100 m3 286
Concreto
C10W6 m3 11
e=8mm t 0.45
Acero de refuerzo e=16mm t 20.06
e=20mm t 2.03
Mampostería d=25 mm, L=3m m3 36
Shotcrete C20W6 m3 55
Taladros de drenaje d=25mm m 280
Drenaje de PVC d=56mm, L=0.5m m 316
Juntas de polietileno 200g/m2 m2 15
Desprendimiento
Caída de Personas a distinto nivel
Caídas a Nivel
Atrapamientos por partes móviles de las máquinas
Golpe por maquinarias
Atropellos
Volcadura.
Incendio
Electrocuciones
Polvo
Ruido
Explosiones
Colisiones
Tropiezos
Mordeduras y Picaduras
11.6. Documentos
Autorización del Operador.
PETAR
Análisis de Trabajo Seguro (ATS).
Check List – Equipos
Planos
11.7. Restricciones
Todo personal que realice trabajos en esta zona, no podrá ingresar si no cuenta con
lo siguiente:
Y
¯¯¸fi¿ · ø
Details for drainage hole
9
74 0
75 1:100
1
75
2 drainage hole
75
3 ¯¯¸fi¿ ƒ 56
4
75
75
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´
¿ 4.5m
concrete slope protection »¤ „ ¶˛ depth:4.5m
5
75
0
6
0
1
6
75
¡ª
5
1 ¯ 10cm”æC20» ˜ ˝`
bottom protection area C20 shotcrete
• ˝·ƒ ˙ł ƒ 50UPVC floral tube£‹mesh diameter:5mm
River San Gaban ` …ߡŒ˝… ƒ 50UPVC¯¯¸fi»¤„ £‹»¤„ ˝ł – ¶5mm£‹
1350
1100
†‰· ø
550 550 Details for joint rebar
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´
40cm thick concrete 1:50
550
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ 60cm”æ‚ ‰ » ˜ ˝` slope protection
40cm thick concrete ‚˜‰¤¯¯¸fi„ 150¡`100
60cm thick concrete floor 40cm”æ‚ ‰ » ˜ ˝`»⁄˘´
slope protection reconstruct drain
ˆ• ⁄` † ‰ 20 „ º»⁄˘´`‹‰ concrete slope protection
joint for joint rebar concrete connecting slab
80 50 40
60cm”æ‚ ‰ » ˜ ˝`
755.20~ 754.70
200
¯ 10cm”æC20» ˜ ˝`
5
60cm thick concrete floor 758
C20 shotcrete
50
40
W0
40cm thick concrete slope protection
5
110 880 110 40
˝` »⁄ ˘´
30cm”手˘ ˚fl † ‰ 20
1:0.6
1:0.6
excavation section for tailrace tunnel outlet 30cm thick masonry joint rebar
˝` »⁄ ˘´
˜
752.20~751.70 ˛†¸fi¸ ¶·‡ ¿ ¿“˝ ¶˛
700
751.70~ 751.20
‰ »
˜
747.60
40cm”æ ‚
‰ »
2 ‚ˆ˙ł †» Ł 2
40cm”æ ‚
150
1
75
1:50
75
„ •¶˛§†» Ł»⁄˘´ ¯ 40
3 1:0.6
75 no slope protection this area
16@ 6
1:0.6
1:0
20
4
.
75 16@20
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ 40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ ƒ 8@40¡`40 16@20
”›¶·
40cm thick concrete 40cm thick concrete culvert 40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ 748.20
slope protection slope protection
5 concrete slope protection
75 16@20
16@
1:0.6
60
16@20
20
756
759
6
70 Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
—£”¸ CHECKED
˛†¸fi¸ ¶·‡ ¿ ¿“˝ … §»⁄˝…£¤1/2£'
Ł…˘ DESIGNED
EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL OUTLET
˘˝… DRAWN
»Æ˙' ¤ SPECIALTY »Æ˙' COUNTERSIGNATURE ¨ ˘ DATE Ł…˘ ⁄”¯ D.C. No. A142000843 ˝…”¯ DRAWING NO. 413E63-04-06-01
¡¡¡¡ ˚ øˆ £”˛· ›˚ ¨¤£‹†» ˆ•› ¡£¤´…£'¡¢·«†¥» ¸ß ˆ£‹¶ ˙ ¨¤——˛“‰«–£` • ¿˘ •¤´ ¨˛ ˜¨¤ ß¡£
1-1 “„⁄‡ `¿– Bill of Quantities
1:200
¿ ˘ ª ł–Œ ˇ ˜¿ Item „ ‚æ Classification ¥˛» Unit ˚ `¿ Quantity –‚ ¢ Remarks
COORDINATES OF CONTROL POINTS ˝`•‰ˆ ˝ 3
m 2048
Earth excavation
› ˆˇ
– ”¯ No. X Y 3
C25W6F100£¤¶ £' m 286
original ground line » ˜ ˝` concrete
W0 8505952.605 346083.940 3 †ª» ˜ ˝`
C10W6 m 11 blinding concrete
40cm thick concrete W1 8505944.784 346087.270
slope protection ƒ8 t 0.45 „ ¸ª`¿
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ tailrace tower A 8505942.629 346082.210 ‚‰ estimate
˛†¸fi¸ 16 t 20.06
755.90
rebar
` …ߡŒ˝… B 8505946.939 346092.330 †‰
20 t 2.03 joint rebar
shown in other figure
1:
30cm”棋 ‰‹–Œ”¯M10 3 ‚˜‰¤¯¯¸fi„
0.
drainage hole ‰‹˘ ˚fl masonry m 36
6
30cm thick,mortar grade M10 reconstruct drain
¯¯¸fi¿ ƒ 56@3m¡`3m „ •¶˛§†» Ł»⁄˘´ concrete arch
C25£‹10cm”æ 3
L=4.5m no slope protection ‚ ‰ » ˜ ˝` „ ¯ » ˜ ˝` shotcrete C25£‹10cm thickness
m 55
this area ` …ߡŒ˝… ¿ ¶ƒ 56£‹L=4.5m
tailrace tunnel ¯¯¸fi¿ ¨º 4.5m
shown in other figure drainage hole hole diameter ƒ 56£‹L=4.5m
m 280 entering-rock 4.5m
˛†¸fi¸ ¶·
bottom protection area ƒ 50UPVC»¤„ ˝ „ ˝`„⁄†…£¤200g/m £'
2
100
748.20
60cm thick concrete floor
748.20 Note£”
747.60 ¡¡¡¡1¡¢These drawings are about excavation and supporting for tailrace tunnel outlet of the PERU San Gab¤¢n ¢
60cm”æ‚ ‰ » ˜ ˝` ˆ•
60cm thick concrete floor 5cm”æC10 †ª» ˜ ˝` 5cm thick blinding concrete hydropower project,2 drawing in total and drawing numbers is 413E63-04-06-01¡«02;
joint
150 700 200 950 ¡¡¡¡2¡¢The repetition measurement of control points should be taken before construction,the slope can be excavated when
2000 repetition measurement is right;
¡¡¡¡3¡¢The slope should be protected with 10cm thick shotcrete,ƒ 56 drainage holes@3m¡`3m should be drilled along
.6
40cm thick concrete excavation contour line for tunnel
1:0
40cm thick concrete
slope protection ˛†¸fi¸ ¶·¿“˝ ´ “ˇ ¡¡¡¡9¡¢The water should be pumped out of foundation pit during construction period,to avoid water collecting or going
slope protection
` …ߡŒ˝… shown in other figure
into the tunnel,to ensure safety and quality of construction;
88 440 440 88
100
100
¯¯¸fi¿ ƒ 56@3m¡`3m drainage hole ¡¡¡¡10¡¢The bottom protection should be set in the end of tailrece tunnel outlet,and replacement should be done with
748.20
L=4.5m
10cm thick shotcrete ¯ 10cm”æ¸ » ˜ ˝` 747.60 ¯ 10cm”æ¸ » ˜ ˝` 10cm thick shotcrete the foundation of tailrece tower,which is shown detailedly in other figure;
¡¡¡¡11¡¢The excavation and supporting for tailrace tunnel,concrete arch and pipe roof is shown in other figure;
60cm”æ‚ ‰ » ˜ ˝` 5cm”æC10 †ª» ˜ ˝` ‚ˆ˙ł †» Ł 60cm”æ‚ ‰ » ˜ ˝`
60cm thick concrete floor 5cm thick blinding concrete no concrete floor 60cm thick concrete floor ¡¡¡¡12¡¢Safety monitoring and inspection tour of slope and highway should be strengthened to ensure safety of staff and
110 880 110 equipments during construction;
1100 ¡¡¡¡13¡¢The others unnoted refer to technical clause in bidding document and standards;
¡¡¡¡14¡¢The unit in drawing of elevation is meter,of structure dimension is centimeter,of hole diameter is millimeter;
¡¡¡¡15¡¢Legend: Gravel and boulder including sand Boulder and gravel including clay
»ø·¡»» ˙ł foundation replacement area
¸ ˆ £” ` …ߡŒ˝… shown in other figure
¡¡¡¡2¡¢˚'„⁄˙ ƒ¶ ¿ ˘ ª‰ł——•¯ ø¶¤˛»£‹‚·”¸˛ ˛ ” †¯˜ ‰ł——¿“˝ ˚'„⁄£» ¡¡¡¡9¡¢‡ ¿ ¿“˝ ¶˛ ƒ ”ˆ˚'„⁄˘ ‡Ø¯¯¸fi£‹‚ ‰ » ˜ ˝` – ˆ ˚ „ £‹• „¶·¿ » ¸fi» „„ ‰ł¶·˜ £‹ –£ ⁄˚'„⁄ †¨«”˝ ˚`¿£» EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
¡¡¡¡3¡¢˛†¸fi¸ ¶·‡ ¿ ¿“˝ – ˘´ ø¯ 10cm”æC25» ˜ ˝`£‹˘´ˆ †… Łƒ 56¯¯¸fi¿ @3m¡`3m£¤ ˘´ˆ º£'£‹ 4.5m£‹†¢ Ł40cm”æ‚ ‰ » ˜ ˝`»⁄˘´£‹ ¡¡¡¡10¡¢˛†¸fi‡ ¿ ˜'¶¸” »¶¤•¶˛§˜ —Ł‰ł——• ˝»⁄ ·ƒ £‹˛†¸fi¸ »ø·¡˜ † ˆ»» ·ƒ £‹– ˝… ø‰ ˚ £‹ ` …ߡŒ˝…£» EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
¡¡¡¡¡¡ ˆ• † ˆ– ¿ ¯ ˜› ‡ £‹˘´ Ł60cm”æ‚ ‰ » ˜ ˝` ,˝… —¸ø˚ 8.8m¡`7m•¶˛§ ” ˘ ˛†¸fi¸ »ø·¡¿“˝ —Ł “†» Ł £» ¡¡¡¡11¡¢˛†¸fi¸ ¶·¶· ¶˛¿“˝ … §»⁄¡¢» ˜ ˝` „ ¡¢„ ¯ ¨` …ߡŒ˝…£‹– ˝…‰ ˚ £»
Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
¡¡¡¡4¡¢˝… —¸ø˚ ˛†¸fi¸ ¶·¶·¿ ‚ ‰ » ˜ ˝` „ •¶˛§˜ ˘´ˆ ” ˘ ‰ł¶·¿“˝ —Ł “£‹‰ ¯ 10cm”æC20» ˜ ˝`• – £‹†» Ł‚ ‰ » ˜ ˝`»⁄˘´£» ¡¡¡¡12¡¢˛†¸fi¸ ¶·‡ ¿ … ¶· ¶˛˚'„⁄˘ … ƒ… ˙¿– ˘´”˝`“ „«´• †¨«… † … †˚ £‹¨•–£¨¸ –”˝ Ł–‚ †¨«£» DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
¡¡¡¡5¡¢‚ ‰ » ˜ ˝`»⁄˘´… †ª ø¯ ˆ¸«†ª 16@20cm¡`20cm‚ ‰ ˝ł£‹»⁄˘´ Ł ˆƒ 8@40cm¡`40cm ›‰ £‹„⁄‡ `¿– —‚ ‰ `¿˛“„ ¸ª`¿£‹ ¡¡¡¡13¡¢˘ ¸ß˛· ¡˚´ ¸ˇŒ…ß —–Œ˛˜… ……˚ı ı¿ … ˇ „ „ ‡ „ •¶£» ”¸ … APPROVED ˚'„⁄ˇŒ˝… Ł…˘
ˆ ´‡˚¥… ˝œ¢ ¸fi
CONSTRUCTION DESIGN
¡¡¡¡¡¡ ˚ …˚•¢ œ˛“ …£‹˝… —‚ ‰ –£»⁄†ª5cm£‹ —¡ˆ“„ ‡⁄¶¨42d£»»⁄˘´… » ˜ ˝`‰‰ ¿ ·10m • ˚'„⁄• £‹ ‰‰ ˙ ƒ „˚ ·ƒ £‹ ¡¡¡¡14¡¢˝… —‚ ‡ ˆ …˘£‹‡ · ˆ …˘£‹¿ ¶ ”`ˆ …˘£» ”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
¸fi „⁄ †¿•
†Ø EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION
¡¡¡¡¡¡ „˚ ˇ ˚ ˛“0.92£‹†¢˘ 5cm”æ †ª» ˜ ˝`£» ¡¡¡¡15¡¢˝… £” ´ ø˚fl¡¢˘fl˚fl…— ˘fl˚fl¡¢¿Ø˚fl¡¢´ ø˚fl…—˝`
—£”¸ CHECKED
¡¡¡¡6¡¢˘‰ˆ ˝… ——Øˇ ı ¸ø˚ •¶˛§˜ »⁄˘´– ˆ ⁄` 20@20cm† ‰ £‹† ‰ ˇˇ´¯¯‡⁄¶ … ‚ †… ˆ£‹ –ª º» ˜ ˝` „ ‰Æ„„ˇ `‹£» ¡¡¡¡¡¡ ˛†¸fi¸ ¶·‡ ¿ ¿“˝ … §»⁄˝…£¤2/2£'
Ł…˘ DESIGNED
EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL OUTLET
¡¡¡¡7¡¢˛“– ˆ ”›¶·¸fi` ¯¯¨º˛†¸fi‡ ¿ £‹”›¶·ˇ´ ˛ ƒ‰ł——¯¯¸fi„ ‚˜‰¤£‹‰«”›¶·¸fi` ¯¯ `ˇ´ ˛” £‹˝… —¸ø˚ ¯¯¸fi„ ˇ ´•‰ „'†˛¿…£‹˚'„⁄ —¿ ‚ø ˇ ‡¡ ˘˝… DRAWN
¡¡¡¡¡¡ ˙Ø¿ ‰ł—— ߣ‹ ƒ ¡`¿ ¶ º˛†¸fi‡ ¿ £‹ —˛˚˚ – Ł ˘´£‹¯¯¸fi„ ¶ˇˆ ‡ · ˛“1.5m¡`1m£¤¿ ¡`‚ £'£‹ … `‰† Ł30cm”手˘ ˚fl£‹„ ˜ ‰‹˜¤˘‰£» ¨ ˘ DATE 2018.04 –¨ SCALE ¨ ˝… AS NOTED
X
N
EXCAVATION PLANE OF TAILRACE TUNNEL
Y
—¡ …„ §»⁄ —˝¶ˇˆ ˝…
950
access tunnel 1:100
‰ł‡§‰»˝¤¶· CROSS SECTION OF ADVANCING SMALL PIPE
` …ߡŒ˝…
small pipe
ƒ 42 ¢‰‹—¡ …„ £‹L=3.5m£‹»•ˇ … 40cm
‰˙6¡ª~
10¡ª£‹· ‰ 1m
cable tunnel
950
boundary line of this drawing ´˝¤• ¶·
– ·˛‡ ˝…‰ ˇ ` …ߡŒ˝…
¯ ‚ ˇ¸˛‹» ˜ ˝`
W0+949.61
steel fiber reinforced shotcrete
– ¶·
main transformer cavern
1
.9
78 W4 ˛†¸fi¸ ¶· 120¡ª
tailrace tunnel
9
W5
+
W0
540
main powerhouse • – ˚‰‚ „ … HEB120£‹… 0.8m
‡§•¿ W6 closed type steel arch HEB120£‹@0.8m
2930 32853
‚ ‰ » ˜ ˝`‡˜˘
R5
96 7¡ª
33.5
W0+621.08
23 000 reinforced concrete lining
50
R1
0
R0
1
O2
00
10
1100
headrace tunnel lateral steel support
1
150
87
2.
0
+0
W1
0
120
1250
NOTES:
¡¡¡¡1¡¢This set of drawings are the excavation and supporting for tailrace tunnel,totally 5 pieces with drawing NO.413E63-04-06-03¡«07. They should be connected with drawings of excavation and support for
tailrace tunnel outlet. The control points of W0¡¢W1 should be the same with that drawing.
¡¡¡¡2¡¢The repetition measurement of control points should be taken before construction,the slope can be excavated when repetition measurement is right;during the construction of tunnel rock excavation£‹
excavation should follor the principe of£”short footage¡¢weaken blasting and very close to tunnel face.Blasting parameters should be controled strictly so as to avoid the interrupt to surrounding rock.
Pay attention to drainage and ensure the excavation quality. The excavation of tunnel from stakes W0+000.00¡«W0+060.00 shown in the drawing is for the long pipe roof way. It can be divided into 2 sections.
Area of W0+030.00 should be constructed according to the requirements of 2nd section of pipe roof, side wall and roof can be properly can be expanding excavated to satisfy the follow-up construction.
Construction details for pipe roof is in the other drawings.
¡¡¡¡3¡¢Stakes in the drawings are along the tunnel axis. The scale of this set of drawings are from stake W0+000.00 to W1+002.87.See other drawings about the structure of tailrace tunnel.
¡¡¡¡4¡¢The material quantities are calculated according to the existed geological data.The record and forcast of geological should be enhanced.The actual rock type should be confirmed by the geological engineer on construction site and adjust the support ways.
¡¡¡¡5¡¢Fault named Fcm and its control area across the tailrace tunnel, it should be constructed according to type C .
¡¡¡¡6¡¢Construction of steel fiber should satisfy the bidding documents requirements to qualify the quality of shotcrete.
EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
¡¡¡¡7¡¢Construction of bolt and drainage hole should satisfy the requirements of bidding documents. EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
¡¡¡¡8¡¢Drainage pipe should be packaged with geotechnical cloth (also the pipe orifice),and then be inserted into drainage holes.The gap of pipe and hole surface should be filled with cement motar to prevent cutting reinforcements.
Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
The drainage holes should be constructed by locating imbedded pipes.
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
¡¡¡¡9¡¢The drilling diameter of anchor bolt hole should be no smaller than the designed ones. the position deviation should be smaller than ¡ 10cm¡£The holes should be cleared before construction£»All the motar of motar anchor bolts in this drawings are M25£»
”¸ … APPROVED ˆ ´‡˚¥… ˝œ¢ ¸fi ˚'„⁄ˇŒ˝… Ł…˘
The anchor bolts in the lining section should be welded with the reinforcements in the lining concrete. CONSTRUCTION DESIGN
”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
¡¡¡¡10¡¢Construction of steel arch should satisfy the requirements of bidding documents. ƒ 25@50cm reinforcements should be used for connection between every two steel archs and be arranged staggered;the steel archs in pipe roof section is closed type. ¸fi „⁄ †¿•
†Ø EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION
¡¡¡¡11¡¢Satety supervision and monitoring should be enhanced during construction of tunnel excavation to make people and equipments safe.
—£”¸ CHECKED
¡¡¡¡12¡¢During excavation of pipe roof section pass through the Lianyang road,the footage should be strictly controlled,and only after construction of concrete lining,the tunnelling can be continue,safety warning signs should be set up on the road.
Ł…˘ DESIGNED
˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£¤1/5£'
¡¡¡¡13¡¢After finishing the excavation of Class ¢ and ¢ı rock type including the pipe roof section£‹the initial stage supporting should be constructed in time for the safety. EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL
˘˝… DRAWN
¡¡¡¡14¡¢Stakes, elevations are in meter, dimensiongs are in cm, diameters of holes and anchor bolts are in mm.
¨ ˘ DATE 2018.08 –¨ SCALE ¨ ˝… AS NOTED
¡¡¡¡15¡¢Else not mentioned should follow the bidding documents and related standars.
»Æ˙' ¤ SPECIALTY »Æ˙' COUNTERSIGNATURE ¨ ˘ DATE Ł…˘ ⁄”¯ D.C. No. A142000843 ˝…”¯ DRAWING NO. 413E63-04-06-03
¡¡¡¡16¡¢legends£” gravel and boulder including sand boulder and gravel including clay ballast and rubble including clay quartz sericite slate
¡¡¡¡ ˚ øˆ £”˛· ›˚ ¨¤£‹†» ˆ•› ¡£¤´…£'¡¢·«†¥» ¸ß ˆ£‹¶ ˙ ¨¤——˛“‰«–£` • ¿˘ •¤´ ¨˛ ˜¨¤ ß¡£
˛†¸fi¸ ¶·¿“˝ ˘‰ˆ ˝…2
1:2000
X
N
EXCAVATION PLANE OF TAILRACE TUNNEL
Y
0
85
0
80
900
`“ „«´•
road
O1
R 5000
outlet section
‡ ¶·¿ ¿“˝
W1 ` …ߡŒ˝…
˛†¸fi¸ ¶· .4¡ª
6
W3 3 W2
tailrace tunnel
7
6
540
550
2
4
0
0
W0
0 6
3
0
60
31262 18921 0
1863 32 7
360
of
t
o
n
0
˛† ¸fi ¸ ¶· ˘ ª
er
i
0
o
0
.
950
„ ¯ ‰ „ ·ƒ
tp
0
0
8
p
6
0
0
i
.
0
.
fp
r
7
+
1
a
9
0
2
t
0
W
6
do
s
+
0
+
W
0
W
W
n
e
00
10
¸ ˆ £”
¡¡¡¡1¡¢– ˝…˛“˚¥… ˝œ¢ ¸fi ˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£‹„†5 ¯£‹˝…”¯413E63-04-06-03¡«07£‹—Ł º˛†¸fi¸ ¶·¶·¿ ¿“˝ … §»⁄˝…¯ ”ˇ˚„ ˆ£‹˝… —¿ ˘ ªW0¡¢W1 º˛†¸fi¸ ¶·¶·¿ ¿“˝ §»⁄˝… » ´£»
¡¡¡¡2¡¢˚'„⁄˙ ƒ¶ ¿ ˘ ª‰ł——•¯ ø¶¤˛»£‹†¢ º˛†¸fi¸ ¶·¶·¿ ¿“˝ ¿ ˘ ªˇ »¥†˛ £‹‚·”¸˛ ˛ ” †¯˜ ‰ł——¿“˝ ˚'„⁄£» ˚fl¶·˝ ¶˛˚'„⁄˚– ƒ† ˆ¶ ‰ł‡ ¡¢¨ı–‹˘˘… ‰ ‚œ ˘ ˆ ˙¿ §»⁄•‰˚‰‰ł——˚'„⁄£‹ ˇ‚æ¿ ˘¿“˝ –‹˘˘†˛˚ £‹– ˆ ¶ ˛§ ‡ ¨¯¶fl£» ”ˆ¶·˜
¡¡¡¡¡¡ ˚'„⁄˘ ¯¯¸fi£‹¨•–£¿“˝ ˚`¿£»˝… —¸ø˚ fi”¯W0+000.00¡«W0+060.00¶·¶˛† ˆ‡⁄„ ¯ ˚'„⁄ ˜•‰˚‰¿“˝ £‹¿ • `‰¶˛˚'„⁄£‹ fi”¯W0+030.00 »¶¤•¶˛§˜ ƒ‚ø ¶ ¶˛„ ¯ … „ ˚'„⁄—Ł “£‹– ˙‰… ¶¥„ ˚˚ – '˝ £‹ ´œ ª” —ł˚'„⁄—Ł “£‹„ ¯ ‰Æ„„` …ߡŒ˝…¡£
¡¡¡¡¡¡ „ ¯ ¶˛” ‚†‚˙†ª¶·¶˛ … ˘ ¸ß ˚ ı… ‰ˇ† ¡¢˜ ‡ ¶· ˜¶·¶˛£‹ ›‚ •‰¨•¨ˇ” £‹¿ † ˆ‡‹˙ —¡ …„ ˜•‰˚‰‰ł——¿“˝ ˚'„⁄£‹ˇŒ…ß —˝¶ˇˆ ˝…£‹„⁄‡ `¿ ˚ …˚•¢ œ˛“ …£»
¡¡¡¡3¡¢˝… — fi”¯˛“ ¶· Æˇ ‡⁄¶¨£‹– ˝…‡ ˝…•¶˛§˛“ fi”¯W0+000.00¡«W1+002.87£‹˛†¸fi¸ ¶·‡˜˘ ‰Æ„„` …ߡŒ˝…£»
¡¡¡¡4¡¢– ˝…‚ø ˇ — ˚ ˚`ˇ‰ł——¿“˝ §»⁄ Ł…˘”˝…˘¸ª„⁄‡ `¿¡£˚'„⁄˘ … ƒ… ˙¿ ˚ ⁄–¤”˝– ´…£‹˚ …˚˚'„⁄ —¶·˚ ˛§ – ˚„⁄‡ ˚ƒˇ ‡¡˙'¶¤˛“ …£‹ §»⁄—˝˚‰‚ø ˛§ – ˇ ƒ ߣ»
¡¡¡¡5¡¢¨ ¶ˇ†ª… ˘˘¸Ø·ł·' ‰˛†¸fi¸ ¶·˚–£‹¿ ·C—˝¶ˇˆ ‰ł——¿“˝ §»⁄£»
¡¡¡¡6¡¢¯ ‚ ˇ¸˛‹» ˜ ˝`˚'„⁄ ƒ´œ ª —–Œ˛˜… … ˇ „ „ ‡ „ •¶ “˙ £‹ ¨•–£¯ » ˜ ˝`˚'„⁄ ˚`¿£»
EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
¡¡¡¡7¡¢ˆ“¯ … ¯¯¸fi¿ ˚'„⁄ ƒ´œ ª —–Œ˛˜… “˙ £‹˝… —¸ø ¢ˆ“‚¸¡¢¯¯¸fi¿ … ø˛“¿“˝ ´ “ˆ … £»
EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
¡¡¡¡8¡¢¯¯¸fi„ ƒ ˆ˝`„⁄†… „ £¤„ ¿ »˘ „ £'” † ¨º¯¯¸fi¿ —£»„ º¿ ˆ … ˇ¶ ƒ ˆ¸fi˜ ‰‹ ˚ £‹˛“• „ ¿ ‰ ¶ˇ‚ ‰ £‹¯¯¸fi¿ ƒ† ˆ´æ„ ¶¤˛» ˜•‰˚‰£»
¡¡¡¡9¡¢ˆ“‚¸ Œ¿ ¿ ¶†» ˆ—¡ Ł…˘ £‹¿ ˛»˘«† —¡ ¡ 10cm¡£† ‚¸˙ ¿ ˜ – —º˙ ‡ ‚ »£»– ˝…¸ø — ‰‹ˆ“‚¸ ˜ ‰‹–Œ”¯˛“M25£»‡˜˘ ¶˛ˆ“‚¸ “˙ ˝ ´¶… –„‡˝ £‹ˇŒ…ß˝… —¸ø˚ £» Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
¡¡¡¡10¡¢‚ „ … ˚'„⁄ ƒ´œ ª —–Œ˛˜… “˙ £‹Øfl… ƒ† ˆ 25@50cm‚ ‰ ¿ ¿¿`‹‰ £‹`‹‰ ‚ ‰ Øfl… · ¿“†… ˆ;„ ¯ ¶˛‚ „ … ˛“• – ˚‰£‹ †¿ ˝† ” † ˆ”Æˇ —˝‚ ”‚‰ §‡¯£‹†» ˆ˙ … ‰Æ„„‡ · £»
”¸ … APPROVED ˆ ´‡˚¥… ˝œ¢ ¸fi ˚'„⁄ˇŒ˝… Ł…˘
¡¡¡¡11¡¢¶·˝ ˚'„⁄˘ … ƒ… ˙¿ †¨«… † £‹¨•–£¨¸ –”˝ Ł–‚ †¨«£» CONSTRUCTION DESIGN
”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
¸fi „⁄ †¿•
¡¡¡¡12¡¢„ ¯ ¶˛·' ‰`“ „«´•˚–£‹ ƒ ˇ‚æ¿ ˘‰ł‡ £‹… ˚–˝Œ‡ ·'´•¶˛» ˜ ˝`‡˜˘ ” … —ł ‰ł£‹†¢ ˚'„⁄ … ´•¶˛ Ł ˆ †¨« fl˚ –Œ £‹… ˙¿ †¨« †˚ £‹•¢ˇ ˛˚ ƒ… ˚––¤‚ ˇ ˜¿†¿£‹† ¨¡·ƒ ·º˚'£»¡¡¡¡ †Ø EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION
¡¡¡¡13¡¢¢ ¡¢¢ı ˛§ ¶·¶˛£¤”‹„ ¯ ¶˛£'¿“˝ ˝Œ‡ ” £‹ ƒ… ˚–˝Œ‡ ‡ı˘ §»⁄£¤ˆ“¯ ¡¢¯¯¸fi¿ … ‚ „ … £'£‹ ߲§ ˛¨¶¤”˝˚'„⁄ †¨«£» —£”¸ CHECKED
Ł…˘ DESIGNED
˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£¤2/5£'
¡¡¡¡14¡¢˝… —‚ ‡ ¡¢ fi”¯ ˆ …˘£‹‡ · ˆ …˘£‹¿ ¶¡¢ˆ“‚¸ – ¶ ”`ˆ …˘£» EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL
˘˝… DRAWN
¡¡¡¡15¡¢˘ ¸ß˛· ¡˚´ ¸ˇŒ…ß —–Œ˛˜… ……˚ı ı¿ … ˇ „ „ ‡ „ •¶£»
¨ ˘ DATE 2018.08 –¨ SCALE ¨ ˝… AS NOTED
¡¡¡¡16¡¢˝… £” ´ ø˚fl¡¢˘fl˚fl…— ˘fl˚fl¡¢¿Ø˚fl¡¢´ ø˚fl…—˝` ¿Ø˚fl¡¢¸Ø˚fl…—˝` ˚fl ¢ ˘˜‚ ¡¢ ˘˜‚ Ł…˘ ⁄”¯ D.C. No. A142000843 ˝…”¯ DRAWING NO. 413E63-04-06-04
øˆ £”˛· ›˚ ¨¤£‹†» ˆ•› ¡£¤´…£'¡¢·«†¥» ¸ß ˆ£‹¶ ˙ ¨¤——˛“‰«–£` • ¿˘ •¤´ ¨˛ ˜¨¤ ß¡£
˛†¸fi¸ ¶· ˘˚ˆ ˝…1
1:2000
LONGITUDINAL SECTION OF TAILRACE TUNNEL
CONTROL POINTS COORDINATES
¿ ˘ ª ł–Œ
– ”¯ NO. X Y
—‰ˇ
separatrix of lithology
W0 8505952.605 346083.940
lower limit of intense weathering
˙¿• »flˇ´ˇ
W1 8505944.784 346087.270
W2 8505854.652 346125.647
W3 8505851.841 346126.744
960 lower limit of moderate weathering
960
¨ı• »flˇ´ˇ W4 8505052.066 346411.597
W5 8505028.818 346428.730
W6 8505014.455 346447.913
O1 8505835.065 346079.643
O2 8505068.842 346458.699
underground water line
˝˘† ˇ´¸fi˛»
880 880
5
50
750.11 i=0.1% 749.73 rock bolt
25£‹‚¸‡⁄L=4.5m ‚ø 4407
‚„…
steel arch
HEB120 t 138.20
‚‰ ‚ „ … `‹‰ ‰
2396 2930 32853 25 t 37.45
reinforcement connect the steel arch
720 720
˘‰ˆ “˝ ¶˛ ¯¯¸fi¿ ¿ ¶ƒ 56£‹L=0.5m
38179 drainage hole hole diameter ƒ 56£‹L=0.5m
m 724
2
ƒ 50UPVC»¤„ ˝ „ ˝`„⁄†…£¤200g/m £'
2
ƒ 50UPVC floral tube geotechnical cloth£¤200g/m£'
m 724
W1+002.87
W0+978.91
W0+949.61
W0+621.08
Æˇ ¿ ˘ ª
W6 W5 W4
control points of axis
W1+002.87
W0+978.91
W0+949.61
W0+621.08
fi”¯stakes£¤m£' EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
£¤ ¶· Æˇ £' EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
through tunnel axis
Æˇ ‡⁄¶¨£¤m£'
23.96 29.30 328.53
Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
length
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
˛§ –
¢ ”¸ … APPROVED ˆ ´‡˚¥… ˝œ¢ ¸fi ˚'„⁄ˇŒ˝… Ł…˘
rock type CONSTRUCTION DESIGN
”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
¶ˇˆ —˝˚‰ ¸fi „⁄ †¿•
A †Ø EXAMINED HYDROPOWER PROJECT
tunnel section type HYDRAULIC SECTION
—£”¸ CHECKED
¸ˆ
Ł…˘ DESIGNED
˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£¤3/5£'
notes
EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL
˘˝… DRAWN
880 880
lower limit of intense weathering
˙¿• »flˇ´ˇ
—‰ˇ
separatrix of lithology
0
5
9
5
6
749.73 i=0.1% 748.96 748.60
‡ ¶· ª
outlet point
start point
W0+621.08
W0+100.62
W0+097.60
W0+060.00
W0+000.00
ª
‰ „ ·ƒ
¶· ˘
˛† ¸fi ¸
„ ¯
Æˇ ¿ ˘ ª W3
W1 W0
control points of axis W2
W0+621.08
W0+308.46
W0+300.46
W0+119.25
W0+111.25
W0+100.62
W0+097.60
W0+060.00
W0+030.00
W0+000.00
W0-000.36
W0-008.86
fi”¯stakes£¤m£'
£¤ ¶· Æˇ £'
through tunnel axis
Æˇ ‡⁄¶¨£¤m£'
312.62 8 181.21 8 10.63 37.60 60
length
3.02
˛§ –
¢ ¢ ¢ı
rock type
¶ˇˆ —˝˚‰
A B C D
tunnel section type
· ø1
˛ –¨ EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
DETAIL 1 EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
50
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
ƒ 50UPVC drainage floral tube ˚'„⁄ˇŒ˝… Ł…˘
”¸ … APPROVED ˆ ´‡˚¥… ˝œ¢ ¸fi
ƒ 50UPVC¯¯¸fi»¤„ £‹»¤„ ˝ł – ¶5mm CONSTRUCTION DESIGN
… 5cm¡`5cm£‹˝ „ ˝`„⁄†…£¤200g/m £'2 ”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
¸fi „⁄ †¿•
@5cmx5cm with geotechnical cloth outside †Ø EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION
—£”¸ CHECKED
¯ ‚ ˇ¸˛‹» ˜ ˝`
Ł…˘ DESIGNED
˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£¤4/5£'
steel fiber reinforced shotcrete EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL
˘˝… DRAWN
20
20
224
264
0
R 32
0 34 R
R 36 0
R1 220 220 00
38 0 R1
¡ª
0
6
R
2
5
R1 0
3
0
.
40 220 220 4
R1
.
¡ª
3
6
5
2
5
6
.
¡ª
3
O3 O4
5
2
6
132.89¡ª
¡ª
620
O3 O4
132.89¡ª
690
376
80cm”æ‚ ‰ » ˜ ˝`‡˜˘ steel fiber shotcrete ` …ߡŒ˝…
¯ 20cm”æ‚ ˇ¸˛‹» ˜ ˝`
` …ߡŒ˝… ¯ 20cm”æ‚ ˇ¸˛‹» ˜ ˝`
406
– ˆ ¯ 2cm”æ¸ C20» ˜ ˝`
– ˆ ¯ 2cm”æ¸ C20» ˜ ˝` reinforced concrete lining
• – ˚‰‚ „ … HEB120£‹… 0.8m
reinforced concrete lining ‚ „ … HEB120£‹… 1m 50cm”æ » ˜ ˝`
closed type steel arch HEB120£‹@0.8m
120
80cm”æ » ˜ ˝` steel arch HEB120£‹@1m ` …ߡŒ˝…
` …ߡŒ˝… anchor bolt anchor bolt
‰‹ˆ“‚¸3 25@1m£‹L=4.5m£‹¯¯ 1m ‰‹ˆ“‚¸3 25@1m£‹L=4.5m£‹¯¯ 1m
100
anchor bolt anchor bolt ´¶‡ ¯ » ˜ ˝`ˆ 50cm£‹”‹ –„‡20cm ´¶‡ ¯ » ˜ ˝`ˆ 50cm£‹”‹ –„‡20cm
‰‹ˆ“‚¸4 25@1m£‹L=4.5m£‹¯¯ 1m ‰‹ˆ“‚¸4 25@1m£‹L=4.5m£‹¯¯ 1m
´¶‡ ¯ » ˜ ˝`ˆ 50cm£‹”‹ –„‡20cm ´¶‡ ¯ » ˜ ˝`ˆ 50cm£‹”‹ –„‡20cm 20 300 300 20
640
20 340 340 20
drainage hole
¯¯¸fi¿ 4ƒ 56@30¡ª£‹¯¯ 3m ‰‹ˆ“‚¸5 25@30¡ª£‹L=3m£‹¯¯ 1.5m
…ß· ø1
184
detail 1 0
…ß· ø1
R 28
29 R
5
184
R5 220 220
¡ª
5
6
detail 1 0 5 R5
2
5
28
3
R
.
3
29 R
5
2
0
6¡ª
R5 220 220 0
¡ª
R5
6
0
2
O3 O4
5
3
.
132.89¡ª
3
5
2
555
¡ª
O3 O4
132.89¡ª EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
O
550
steel fiber shotcrete – ˆ ¯ 2cm”æ¸ C20» ˜ ˝` reinforced concrete lining DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
¯ 10cm”æ‚ ˇ¸˛‹» ˜ ˝` ‚ „ … HEB120£‹… 1.2m 30cm”æ » ˜ ˝`
”¸ … APPROVED ˚'„⁄ˇŒ˝… Ł…˘
100
– ˆ ¯ 2cm”æ¸ C20» ˜ ˝` reinforced concrete lining steel arch HEB120£‹@1.2m ` …ߡŒ˝… ˆ ´‡˚¥… ˝œ¢ ¸fi
CONSTRUCTION DESIGN
30cm”æ » ˜ ˝` ”¸¶¤ VERIFIED PERU San Gab¤¢n ¢
120
¸fi „⁄ †¿•
` …ߡŒ˝… ‰‹ˆ“‚¸3 25@1m£‹L=4.5m£‹¯¯ 1m ‰‹ˆ“‚¸3 25@1m£‹L=4.5m£‹¯¯ 1m †Ø EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION
‰‹ˆ“‚¸2 25@1.5m£‹L=3m£‹¯¯ 1.5m ‰‹ˆ“‚¸2 25@1.5m£‹L=3m£‹¯¯ 1.5m anchor bolt anchor bolt
—£”¸ CHECKED
anchor bolt anchor bolt 15 260 260 15
Ł…˘ DESIGNED
˛†¸fi¸ ¶·¿“˝ … §»⁄˝…£¤5/5£'
550 EXCAVATION AND SUPPORTING FOR TAILRACE TUNNEL
10 260 260 10 ˘˝… DRAWN
‚ ‰ » ˜ ˝` „ £¤†»”‹ ¶ ¶˛„ ¯ „ ‡⁄¶¨£'£»„ ¯ ¶·¶˛‰¤ Ø• ˇˇ´`‰†¿• † ˆ ¤‰ •¤¿“˝ £‹ ¤‰ ‡⁄¶¨3¡«4m£‹˚'„⁄‰ł‡ 1¡«1.5m£‹ˆ¿‚ ‰ł‡ ¿“˝ ˝Œ‡ ” £‹ ƒ… ˚–˚'„⁄
1:0
reinforced concrete cover arch
.6
752.60 ˇ ˝‡¯ ˆ“ §»⁄£‹•‰¿ ‰ł——ˇ´ »‰ł‡ ¿“˝ £‹˚'„⁄ ¥˛»¿ ‚ø ˚ …˚˙Ø¿ ˚˚ – ß¿“˝ •‰˚‰£‹ «– —º–£ ⁄˚'„⁄˘ ¶·˜ ˛§ ˛¨¶¤… †¨«£‹˚'„⁄•‰ ‚—º ˇ–¤¯œ …£»
¡¡¡¡12¡¢˝… —‚ ‡ ¡¢ fi”¯ ˆ …˘£‹‡ · ˆ …˘£‹¿ ¶¡¢‚ „ – ¶… – ”æ ”`ˆ …˘£» fi”¯ º˛†¸fi¸ ¶·¿“˝ … §»⁄˝… » ´£»
» ˜ ˝`
¡¡¡¡13¡¢„ ¯ ˚'„⁄˘ … ƒ… ˙¿ †¨«… † £‹•¢ˇ ‡`‰ ¡¢– —˛ ‡£ ƒ… ˚–•· ¡£‹†¢† ¨¡·º˚'£‹¨•–£¨¸ –¡¢ Ł–‚”˝„⁄‡ †¨«£»
concrete baseboard 60cm”æ‚ ‰ » ˜ ˝`
174 60cm thick concrete baseboard
¡¡¡¡14¡¢˘ ¸ß˛· ¡˚´ ¸ˇŒ…ß —–Œ˛˜… ……˚ı ı¿ … ˇ „ „ ‡ „ •¶¡£
748.60
„⁄‡ `¿– quantity list
748.00
ˇ ˜¿ „ ‚æ ¥˛» ˚ `¿ –‚ ¢
W1 5cm”æ» ˜ ˝` †ª item specifications unit quantity comment
5 reinforcement
25 t 0.55 „ ¯ „ ¶¤‚ ‰
fastening rebar
636
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´ „⁄ ‚ I18 t 3.48
profile steel
40cm thick concrete slope protection 756.30
22@20 ¿¿„
ƒ 127¡`4mm m 180
orifice pipe
755.60 755.50
ƒ 108¡`6mm‚ »¤„ m »¡¢¶ ¶˛
1240
1:0
22@20
1:0
22
¢£”– —‚ »¤„ „⁄‡ `¿˛“ »¡¢¶ ¶˛„ ¯ ˚'„⁄¶·¶˛ ‚ »¤„ `¿£‹˘ ¸ß ø˛“¶·¿ » ˜ ˝` „ „⁄‡ `¿¡£
22@20
note: quantity of side-holes steel pipe in the list is total quantity of first and second segment pipe roof,
and the rest is the quantity of cover arch.
¯ 10cm”æ¸ » ˜ ˝` reinforced concrete cover arch
1:0
25„ ¶¤‚ ‰ 756.30
.6
fastening rebar ƒ 127¡`4¿ ¿ „ orifice pipes 752.10 EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
755.90 751.60 EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
shotcret ƒ 108¡`6„ ¯
I18—˝‚ „ …
¯ » ˜ ˝`†ª pipe roof
I18 profile steel arch frame
Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
22@20
755.50 DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
reinforced concrete cover arch 174 PIPE ROOF AND SUPPORTING FOR TAILRACE TUNNEL OUTLET
.6
˘˝… DRAWN
50
755.60
4. Drilling method should be adopted in pipe roof construction and XY-28-300 electrical drilling machine could be equipped. When
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´
joint rebar drilling and putting in long pipe roof steel pipes, axis direction of drilling bar must be controlled ristrictly. Scaffolds
40cm thick concrete slope protection
20† ‰ 22@20 should be built reliablely, and drilling machine should be fixed formly. During drilling the angle of deflection should be
` …ߡŒ˝…
22@20 measured. If the angle of deflection exceeds limits of design, correction measures should be taken in time.
shown in other figure
5. C25 concrete cover arch is the guide wall for pipe roof. Before pipe roof construction, cover arch should be built and ƒ 127x4mm
guide pipe should be fixed in it. To make sure of direction of hole is right, lifting space should be reserved and upward angle
ƒ 8@40¡`40
22@20 should be controlled when guide pipe be erected.
22@20
6. Steel pipe should connected by screw clasps, which length is 15cm. The length of threaded ƒ 108¡`6mm steel pipe is 30cm. To
22@20
22@20 752.60 stagger joints of steel pipes, length of first segment steel pipe of odd number holes is 3m, and length of first segment of
50
50
steel pipe of even number holes is 6m. The length of following segments is 6m.
752.10 joint rebar
20† ‰ 7. Pipe roof should be laid accroding to design position. Side-holes steel pipes should be built firstly, then no hole pipes should
22@20
joint rebar …ß˝…413E63-04-06-01¡«02 be built after grouting. No hole pipes are used for inspection of grouting quality.
20† ‰ 22@20 22@20 22@20
22@20 shown in other figure 8. Vertical view of concrete cover arch in the drawing shows projection dimensions. It should be built by lofting on the slope. Two
…ß˝…413E63-04-06-01¡«02
22@20 layers and two way ƒ 22@20 reinforcement and ƒ 8@40x40 dragging reinforcement should be laid in it. Sections in the drawing
shown in other figure ƒ 8@40¡`40
are reinforcement sketch. Lofting must be done during reinforcement erction according to structure outline. Reinforcement quantity
22@20 22@20
should be counted on site. Thickness of protection layer is 5cm, and minimum anchor length is 42d.
9. Pipe roof of headrace tunnel should be built by two segments. Dimension of concrete cover arch between two segments is shown
40cm”æ‚ ‰ » ˜ ˝`»⁄˘´
in the drawing. Length of cover arch is 2m along tunnel axis, and actual quantity should be counted on site. The length of
40cm thick concrete slope protection
first and second segment cover roof lapping joints is 3m. High and low parts of tunnel in pipe roof segment could be
excavated seperately. The length of steps is 3¡«4m, and excavation footage is 1¡«1.5m. When one footage is finished, system
15
15
shotcret and anchor bar must be done in time. And that should be done before next footage begin. Constructor can adjust
excavation method according to situation on site, but they must ensure stability of surrounding rock during construction
period. Construction plan must be reported and approved before it put into effect.
80 720 80
10. Grouting requiements for pipe roof:
(1)grouting slurry: pure cement slurry;
3 (2)grouting parameters: water cement ratio 1:1, innitial grouting pressure 0.5¡«1.0MPa£‹final grouting pressure 2.0MPa.
(3)cement slurry in pipes should be cleaned in time after grouting, the pipes should be filled with 30# cement sand slurry
1 and deformation occurs, it must be reported in time. So that constructors can take measures to ensure staff, equipment
and project safety.
14. For matters not mensioned, refer to technical items of bidding document and relevant criteria.
755.10
608 side-holes steel pipe
ƒ 108¡`6mm‚ »¤„
156
42
328
R4
¡ª
R
.
60
R 140
3
752.66 0 100cm long with no hole, d8mm grouting hole, spacing of 30cm, quincunx distributed 10cm cone head
38
2
752.60
grout stop segment reserved
770
R
56
140
96
I18—˝‚ „ …
751.60 ƒ 127¿ ¿ „ orifice pipes concrete connecting slab
„ º»⁄˘´`‹‰ steel arch frame
268 »•ˇ … 40cm EPC ‡— : —„œ¸fi ß `ƒ¶ ˝ „«¸
concrete connecting slab circumferential spacing 40cm
˛†¸fi¸ ¶·¿“˝ ´ “ˇ EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
40
40
excavation outline
of tailrace tunnel Ł…˘•‰:
‡⁄‰›¿–† „ »fi Ł…˘ — ¿ —ˇ ¨˛„«¸
300
200
EXCAVACIONES
TIPO DE
ESTRUCTURA/CATEGORÍA
OBRA
分部工程:
单位工程:
PUNTO DE INSPECCIÓN Y SU CÓDIGO COTA/ PROGRESIVA
单元工程及编码: 工程部位桩号、高程:
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
无松动岩块、陡坎、尖角,周边无不稳定块体,无植被,无积水 £ 合格 Cumple
开挖岩面或壁面
1 No hay bloques de roca sueltos, puntas afiladas, bloques £ 不合格 No Cumple
Superficie de la excavación
inestables alrededor, libre de árbols , libre de agua
资料齐全且合格 £ 合格 Cumple
测 记录齐全且合格
2 Registros completos y conformes £ 不合格 No Cumple
Registro topográfico
(CWE-RC-F-002,CWE-RC-F-003)
开挖联合验收签证记录是否齐全且
合格 资料齐全且合格 £ 合格 Cumple
3 Registro de Inspeccion Conjunta Registros completos y conformes £ 不合格 No Cumple
de Excavacion (CWE-RC-F-004)
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-002
秘鲁圣加旺水电站项目 REVISIÓN: 1
施测内容 施测说明
项次 施测单位
Contenido del levantamiento Descripción del
ÍTEM Área de realización
topográfico levantamiento topográfico
施工部自评 测 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
质 部评定 测 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-003
秘鲁圣加旺水电站项目 REVISIÓN: 1
测 验收记录表 N° DE PAGINAS: 1 de 1
REGISTRO DE LEVANTAMIENTO TOPOGRÁFICO ESPECIALIDAD: CIVIL
ESTRUCTURA/CATEGORÍ
TIPO DE OBRA
A
单位工程:
分部工程:
PUNTO DE INSPECCIÓN Y SU CÓDIGO COTA/ PROGRESIVA
所属单元工程及编码: 工程部位 桩号、高程:
PLANO DE REFERENCIA FECHA
施工依据: 施工时段:
10
11
12
13
14
15
姓名及签名:
Nombre y Firma:
现场测
TOPÓGRAFO DE CAMPO
日期 Fecha:
姓名及签名:
Nombre y Firma:
现场记录
REGISTRADOR DE CAMPO
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-004
秘鲁圣加旺水电站项目 REVISIÓN: 1
开挖工程联合验收签证表 N° DE PAGINAS: 1 de 1
ESPECIALIDAD: CIVIL
PROTOCOLO DE INSPECCION COJUNTA DE OBRA DE EXCAVACION
边坡 Talud 隧洞 Túnel
该验收部位共测 开挖断面 Número de sección de medición ( )个
unidads
NOTAS / COMENTARIOS /
OBSERVACIONES :
备注 / 意见
质 工程师(姓名及签名)Nombre y Firma:
施工部
Área de construcción
日期 Fecha:
该验收部位围岩等级为:
El tipo de roca es:
Ⅰ类 Ⅱ类 Ⅲ类 Ⅳ类 Ⅴ类(强风化基岩土体)
其他说明 Observacione :
地质验收意见
GEOLOGÍA
日期 Fecha:
边坡 Talud 隧洞 Túnel
日期 Fecha:
合格,同意进入后续工程项目施工;
Aceptado, se puede iniciar el siguiente proceso
质 部验收意见
ÁREA DE CALIDAD 按设计要求进行处理,重新申请验收。
No aceptado, se require el tratamiento de acuerdo a las observaciones de área de
ingeniería.
日期 Fecha:
备注: 本表后附测 资料
Nota: Se adjunta la información de levantamiento topográfico
Central Hidroeléctrica San Gabán III CWE-RC-F-006
秘鲁圣加旺水电站项目 REVISIÓN: 1
喷混凝土 合格 Cumple
按照规范正确养护
4 Shotcrete 混凝土养护 不合格 No Cumple
Se realizó el curado
Curado
合格 Cumple
喷混凝土外观质 符合规范要求
5 不合格 No Cumple
Calidad superficial Cumple con las especificaciones
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-007
秘鲁圣加旺水电站项目 REVISIÓN: 1
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
锚杆材质性能 符合设计要求 ( ) 合格 Cumple
1
规格性能 Característica Cumple con el diseño 不合格 No Cumple
Especificación y 锚杆长度 符合设计要求 ( ) 合格 Cumple
2
característica Longitud Cumple con el diseño 不合格 No Cumple
锚杆直径 符合设计要求 ( ) 合格 Cumple
3
Diámetro Cumple con el diseño 不合格 No Cumple
孔深 符合设计要求 ( ) 合格 Cumple
4
Profundidad Cumple con el diseño 不合格 No Cumple
孔径 符合设计要求 ( ) 合格 Cumple
5
Diámetro Cumple con el diseño 不合格 No Cumple
自检合格,同意报验 Resultado :
合格 Cumple
不合格 No Cumple
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-008
秘鲁圣加旺水电站项目 REVISIÓN: 1
喷射混凝土开仓申请单 N° DE PAGINAS: 1 de 1
PROTOCOLO DE LIBERACIÓN PARA LA APLICACIÓN DE SHOTCRETE ESPECIALIDAD: CIVIL
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
£ 合格 Cumple
混凝土配合比 已完成并报 批准
1 £ 不合格 No Cumple
Diseño de mezcla Cumple con el diseño y aprobado
£ 合格 Cumple
喷射面清理和冲洗 已按要求对受喷面清扫和冲洗并验收合格
2 £ 不合格 No Cumple
Lavado de la superficie Con agua a presión y aire
£ 合格 Cumple
受喷面滴水、淋水部位 已处理合格
3 £ 不合格 No Cumple
Tratamiento de drenaje Se realizó el tratamiento
£ 合格 Cumple
作业区通风、照明 已到位
4 £ 不合格 No Cumple
Ventilación y iluminación Adecuado
喷射混凝土连续供料能力 £ 合格 Cumple
已具备
5 Capacidad de producción continua del £ 不合格 No Cumple
Adecuado
concreto
£ 合格 Cumple
劳动组织完成,交通、临时设施 已就绪
6 £ 不合格 No Cumple
Instalaciones temporales Adecuado
£ 合格 Cumple
风、水、电等必须的辅助生产设施 已就绪
7 £ 不合格 No Cumple
Agua y energía Adecuado
£ 合格 Cumple
喷射混凝土厚度标志设置 控制喷射混凝土厚度的标志已埋设 ,厚度( )
8 £ 不合格 No Cumple
Calibrador de espesor Colocó, espesor( )
自检合格,同意报验 Resultado :
£ 合格 Cumple
£ 不合格 No Cumple
施工部自检 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
验收Resultado Final:
£ 合格 Cumple
£ 不合格 No Cumple
质 部验收 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
备注:质 部质 工程师签字同意后,8小时内若不进行喷混凝土施工,本表作废。
Nota:Se debe aplicar shotcrete dentro de 8 horas después de firmar el protocolo, caso contrario se requiere otra liberación
Central Hidroeléctrica San Gabán III CWE-RC-F-009
秘鲁圣加旺水电站项目 REVISIÓN: 1
喷层厚度检测
(单位:cm)
Ensayo del espesor de
shotcrete (cm)
施工部 质 部
Área de construcción Área de construcción
£ 合格 £ 不合格 £ 合格 £ 不合格
£ Aprobado £ No aprobado £ Aprobado £ No aprobado
喷层厚度检验结果
Resultado del ensayo del
espesor 质 工程师(姓名及签名): 质 工程师(姓名及签名):
Ingeniero de calidad: Ingeniero de calidad:
日期Fecha:
施工部 日期Fecha:
质 部
Área de construcción Área de construcción
£ 合格 £ 不合格 £ 合格 £ 不合格
£ Aprobado £ No aprobado £ Aprobado £ No aprobado
强度检验结果
Resultado de la prueba de
resistencia 质 工程师(姓名及签名): 质 工程师(姓名及签名):
Ingeniero de calidad: Ingeniero de calidad:
日期Fecha: 日期Fecha:
备注:附喷射混凝土试验检测记录。
Nota:Se adjunta el registro de ensayo de shotcrete
Central Hidroeléctrica San Gabán III CWE-RC-F-011
秘鲁圣加旺水电站项目 REVISIÓN: 1
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
钢支撑安装前质 检查 £ 合格 Cumple
质 检验记录齐全
1 Verificación de la calidad de cimbra £ 不合格 No Cumple
Registros completos y conformes
antes de la instalación
纵向连接筋设置符合图纸要求,间距( ) £ 合格 Cumple
钢支撑联接
2 Espaciadores entre cimbras cumplen con el plano, £ 不合格 No Cumple
Espaciadores
despaciamiento( )
钢支撑拱脚安装 £ 合格 Cumple
拱脚牢固稳定
3 Fijada del pie de la cimbra o dado de £ 不合格 No Cumple
Bien fijada a la roca
concreto
钢支撑靠近围岩或超挖较大部位采用喷混凝土填实 £ 合格 Cumple
钢支撑与围岩的间隙
4 Si se presenta la sobreexcavación, se debe rellenar £ 不合格 No Cumple
Espaciamiento con la roca
con shotcrete
£ 合格 Cumple
螺栓连接 符合规范和图纸要求 ( )
5 £ 不合格 No Cumple
Conexión atornillada Cumple con el plano y la norma
拼装结合紧密,偏差满足要求(≦5mm),或采取加固 £ 合格 Cumple
拼装连接部位
7 处理措施满足要求。( ) £ 不合格 No Cumple
Emplame de las piezas
emplame de piezas(Error≦5mm)
安装间距及位置 £ 合格 Cumple
与前后钢支撑安装间距满足设计要求,间距( )
8 Espaciamiento entre cimbras y £ 不合格 No Cumple
Cumple con la ingeniería,espaciamiento( )
levantamiento topográficos
NOTAS / COMENTARIOS / OBSERVACIONES :
备注 / 意见
自检合格,同意报验 Resultado :
£ 合格 Cumple
£ 不合格 No Cumple
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
工序质 验收Resultado Final:
£ 合格 Cumple
£ 不合格 No Cumple
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
备注:附相应批次钢支撑加工质 检验记录表
Nota: Se adjunta el protocolo del proceso de fabricación de las cimbras
Central Hidroeléctrica San Gabán III CWE-RC-F-012
秘鲁圣加旺水电站项目 REVISIÓN: 1
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
£ 合格 Cumple
钢筋网材质、规格、尺寸 符合设计要求,钢筋网类型( )
1 £ 不合格 No Cumple
Característica y dimención Cumple con el diseño, tipo de malla ( )
符合设计要求
£ 合格 Cumple
钢筋网格尺寸 尺寸( )间排距( )
2 £ 不合格 No Cumple
Dimención de la malla Cumple con el diseño, dimencion de malla y
cuadrantes ( )
£ 合格 Cumple
钢筋网与岩面距离 符合规范要求
3 £ 不合格 No Cumple
Distancia entre la malla y la roca Cumple con las especificaciones
£ 合格 Cumple
钢筋绑(焊)扎 绑扎(焊接)牢固,满足要求
4 £ 不合格 No Cumple
Amarre (Soldadura) de la malla Bien fijada, cumple con el requisito
自检合格,同意报验 Resultado :
£ 合格 Cumple
£ 不合格 No Cumple
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
工序质 验收Resultado Final:
£ 合格 Cumple
£ 不合格 No Cumple
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-013
秘鲁圣加旺水电站项目 REVISIÓN: 1
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
孔深 符合设计要求 ( ) 合格 Cumple
1
Profundidad Cumple con el diseño 不合格 No Cumple
孔径 符合设计要求 ( ) 合格 Cumple
2
Diámetro Cumple con el diseño 不合格 No Cumple
孔位偏差 合格 Cumple
3 ≤15cm
Desviación 不合格 No Cumple
排水孔 合格 Cumple
孔倾斜度 符合设计要求
4 Perforación 不合格 No Cumple
Inclinación Cumple con el diseño
孔数 符合设计要求 ( ) 合格 Cumple
5
Cantidad Cumple con el diseño 不合格 No Cumple
合格 Cumple
钻孔冲洗 孔壁清洁,孔底残留厚度不大于20cm
6 不合格 No Cumple
Lavado Limpio, el espesor del material remanente ≤20cm
管接头,管与岩石接触 合格 Cumple
密合不漏水,管内干净
7 Conexión entre tubos y el 不合格 No Cumple
No hay fuga de agua
排水管 contacto con la roca
Tubo de drenaje 合格 Cumple
排水管安装 材质符合设计要求,排水管直径( )
8 不合格 No Cumple
Instalación del tubo Cumple con el diseño, tipo de tubo( )
自检合格,同意报验 Resultado :
合格 Cumple
不合格 No Cumple
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
工序质 验收Resultado Final:
合格 Cumple
不合格 No Cumple
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-039
秘鲁圣加旺水电站项目 REVISIÓN: 1
排水孔孔深检测记录表
N° DE PAGINAS: 1 de 1
ESPECIALIDAD: CIVIL
PROTOCOLO DEL REGISTRO DE PROFUNDIDAD DE LLORONAS
述
ESQUEMA DE REFERENCIA con descripción específica del elemento(s)简图或相关规格 PROFUNDIDAD DE DISEÑO 设计孔深: m
现场检测记录
REGISTRO DE CAMPO
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
孔深检测
REGISTRO DE
PROFUNDIDAD
39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
质 部质 工程师(姓名及签名):
施工部质 工程师(姓名及签名):
Nombre y Firma de Área de Calidad:
Nombre y Firma de Área de Construcción:
日期 Fecha:
日期 Fecha:
Central Hidroeléctrica San Gabán III CWE-RC-F-010
秘鲁圣加旺水电站项目 REVISIÓN: 1
FECHA DE
SITIO A UTILIZAR
FABRICACIÓN
使用部位:
加工时间:
CÓDIGO DE FABRICACIÓN CANTIDAD
加工批次: 榀数:
项次 检验项目 质 标准 检验结果
ÍTEM DESCRIPCIÓN STÁNDAR DE CALIDAD RESULTADO
表观质 表观质 满足要求 合格 Cumple
1
Calidad superficial Cumplir con los requisitos 不合格 No Cumple
规格型号 符合图纸要求 ( ) 合格 Cumple
2
Tipo de cimbra Cumplir con el plano 不合格 No Cumple
外观质 长度及弧度符合图纸要求(偏差≤10mm)
Calidad 顶构件 合格 Cumple
3 Cumplir con el plano la longitud y radian
superficial piezas de arco 不合格 No Cumple
(error ≤10mm)
长度符合图纸要求(偏差≤10mm)
边构件 合格 Cumple
4 Cumplir con el plano la longitud
piezas hastiales 不合格 No Cumple
(error ≤10mm)
合格 Cumple
焊缝无裂缝、砂眼、焊瘤等明显缺陷
5 不合格 No Cumple
No presenta grieta, quemadura,overip
焊缝外观 夹渣、咬边、表面气孔满足规范要求
合格 Cumple
Superficial de la soldadura Cumplir con la norma la inclusión de escoria,
6 焊接质 不合格 No Cumple
undercut/ socavada y
Calidad de
porosidad superficia
soldadura
焊缝高度 合格 Cumple
7 6~8mm
Altura de soldadura 不合格 No Cumple
焊缝高度 合格 Cumple
8 6~8mm
Altura de soldadura 不合格 No Cumple
NOTAS / COMENTARIOS / OBSERVACIONES :
备注 / 意见
自检合格,同意报验 Resultado :
合格 Cumple
不合格 No Cumple
施工部自评 质 工程师(姓名及签名):
ÁREA DE CONSTRUCCIÓN Nombre y Firma:
日期 Fecha:
工序质 验收Resultado Final:
合格 Cumple
不合格 No Cumple
质 部评定 质 工程师(姓名及签名):
ÁREA DE CALIDAD Nombre y Firma:
日期 Fecha:
备注:附钢支撑加工详图
Nota: Se adjunta el plano de fabricación de cimbra