Documentos de Académico
Documentos de Profesional
Documentos de Cultura
0
Fecha: XXXXX
CONTROL DE PROYECTOS
Proyecto "xxxxx"
<<<NOMBRE DEL SERVICIO>>>
Aprobado por:
Coordinador de Proyecto
: xxxxx
: xxxxx
Cliente
: xxxxx
REV
POR
REVISADO
EMITIDO PARA
FECHA
CHKD
PROYECTO
Contrato No:
Constructora:
Descripcion:
Inicio :
15-Jul-10
Fin :
23-Oct-10
Fecha Corte :
21-Aug-10
SEMANAS
HH
Contrato
Item de
Pago
No.
Plan
Actual
20
60
CIMENTACION
31-Jul
7-Aug
14-Aug
21-Aug
28-Aug
4-Sep
11-Sep
18-Sep
25-Sep
2-Oct
9-Oct
16-Oct
23-Oct
Sem.No.
10
11
12
13
14
15
30.0%
60.0%
100.0%
15.0%
65.0%
1.0%
5.0%
15.0%
30.0%
45.0%
50.0%
60.0%
70.0%
80.0%
100.0%
2.0%
4.0%
60.0%
90.0%
100.0%
1.7%
100.0%
65.0%
1.1% Plan
5.2%
45.0%
4.0%
0.2% Plan
1,070
3.00
100
OCTUBRE
24-Jul
Actual
SEPTIEMBRE
17-Jul
Actual
2.00
AGOSTO
Fecha de
Corte
80
MOVILIZACION Y TRAZOS
1.00
JULIO
% Trabajo
Completado
del Total
Peso
DESCRIPCION
PRELIMINARES
2010
% Avance
Acumulado
ITEM DE TRABAJO
10.0%
8.7%
0.0%
0.0%
0.0% Plan
15.0%
Actual
1
CHIMENEA
4.00
200
17.4%
60.0%
40.0%
7.0% Plan
Actual
10.0%
15.0%
20.0%
30.0%
60.0%
5.0%
20.0%
25.0%
20.0%
40.0%
80.0%
100.0%
10.0%
20.0%
Programado - Acumulado
Actual - Acumulado
DUCTO DE HUMOS
5.00
200
17.4%
0.0%
0.0%
0.0% Plan
50.0%
100.0%
Actual
6.00
200
17.4%
0.0%
0.0%
0.0% Plan
30.0%
100.0%
Actual
7.00
60
5.2%
0.0%
0.0%
0.0% Plan
100.0%
Actual
MESA DE CARGA
8.00
50
4.3%
0.0%
0.0%
0.0% Plan
Actual
HORNO
9.00
200
17.4%
70.0%
20.0%
3.5% Plan
Actual
ANCLAJES METALICOS
10.00
60
5.2%
0.0%
0.0%
15.0%
30.0%
60.0%
70.0%
80.0%
100.0%
35.0%
50.0%
70.0%
80.0%
85.0%
95.0%
15.0%
0
30.0%
52.0%
70.0%
5.0%
10.0%
20.0%
90.0%
100.0%
0.0% Plan
100.0%
Actual
0
TOTAL
1,150
17-J ul
24-Jul
31-J ul
7-Aug
14-Aug
21-Aug
28-Aug
4-Sep
40
35
20
15
10
B
C
D
E
F
G
H
I
J
K
L
M
N
Notas:
61901242.xls / Curva S
FUERZA LABORAL
Programado - Mano de Obra Indirecta
Programado - Mano de Obra Directa
Total - Programado (A+B)
Actual - Mano de Obra Indirecta
Actual - Mano de Obra Directa
Total - Actual (D+E)
HORAS TRABAJADAS - LABOR DIRECTA
Programado Parcial
Programado Acumulado
Actual Parcial
Actual Acumulado
% COMPLETADO
Programado - Periodo
Programado - Acumulado
Actual - Periodo
Actual - Acumulado
25-Sep
25
10
10
17-Jul
10
10
18-Sep
30
Fuerza Laboral
(Cantidad)
11-Sep
Row 67
Row 71
10 9
10 9
14-Aug
21-Aug
10
10
10
10
10
10
10
10
2-Oct
9-Oct
10
2
24-Jul
31-Jul
7-Aug
28-Aug
4-Sep
11-Sep
18-Sep
25-Sep
16-Oct
23-Oct
17-Jul
24-Jul
31-Jul
7-Aug
14-Aug
21-Aug
28-Aug
4-Sep
11-Sep
18-Sep
25-Sep
2-Oct
9-Oct
16-Oct
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
12
13
13
13
13
13
13
13
13
13
13
13
13
13
13
11
12
12
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
200
300
400
500
600
700
800
900
1,000
1,100
1,200
1,300
1,400
1,500
50
20
60
80
90
90
50
70
130
210
300
390
0.57%
2.47%
4.43%
3.74%
6.35%
9.13%
8.96%
7.48%
8.22%
15.87%
16.87%
10.09%
3.30%
2.26%
0.26%
0.57%
3.04%
7.48%
11.22%
17.57%
26.70%
35.65%
43.13%
51.35%
67.22%
84.09%
94.17%
97.48%
0.37%
1.84%
2.61%
1.74%
0.87%
4.35%
0.37%
2.21%
4.82%
6.56%
7.43%
11.77%
23-Oct
99.74% 100.00%
Rev. D.G.B
EN FUERZA LABORAL :
EN PROGRAMADO: LA
INFORMACION SALE DE LA
PROGRAMACION DEL
CONTRATISTA
EN ACTUAL:
SE CONSIDERA EL PICO SEMANAL
DE PERSONAS DE LA SEMANA
REPORTADA (INFORMACION DE
LOS REPORTES DIARIOS)
EN HORAS TRABAJADAS:
EN PROGRAMADO: LA
INFORMACION SALE DE LA
PROGRAMACION DEL
CONTRATISTA
EN ACTUAL:
SE CONSIDERA LA SUMA DE LAS
HORAS LABORADAS DE
PERSONAS EN LA SEMANA
REPORTADA (INFORMACION DE
LOS REPORTES DIARIOS