COMPAÑIA MINERA ANTAMINA S.A.

PROGRAMA DE EXPANSION
INGENIERIA PROYECTOS
10/09
Plan de 3 Semanas
3WEEK SEMANA ANTERIOR SEMANA ACTUAL SIGUIENTE SEMANA
SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI

ITEM Actividades INICIO FINAL


INICIO FINAL
03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Documentos de
PREVISTO PREVISTO Seguridad
ACTIVIDADES PREVIAS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

AP1010 Instalación de oficina de contratista y supervisión, carteles 27-Jul 10-Sep 7-Aug 8-Sep W W W W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

AP1020 Construcción de pozas de sedimentación 10-Sep 24-Sep 17-Aug 31-Aug 0 0 0 0 0 0 0 W W W W W W W W W W W W W W W 0 0 0 0 0 0 OK

AP1030 Retiro de estructuras : cerco, caseta, postes de alumbrado 20-Sep 25-Sep 27-Aug 1-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W W W 0 0 0 0 0 OK

OD1010 Suministro de Tuberias HDPE Ø 24" y Ø28" por ANTAMINA 27-Jul 11-Sep 27-Jul W W W W W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB1040 Montaje de Valvula de Aire AV1 TRAMO: 0+024 - 0+160 9-Sep 10-Sep 29-Jul 31-Jul 0 0 0 0 0 0 W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TRAMO: 0+550 - 0+650 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2000 Termofusión de Tuberia HDPE TRAMO: 0+550 - 0+650 22-Aug 23-Aug 7-Aug 8-Aug 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2020 Montaje de Valvula de Aire AV TRAMO: 0+550 - 0+650 9-Sep 9-Sep 10-Aug 10-Aug 0 0 0 0 0 0 W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TRAMO: 0+650 - 0+760 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2030 Termofusión de Tuberia HDPE TRAMO: 0+650 - 0+760 1-Aug 4-Aug 10-Aug 13-Aug 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2050 Montaje de Valvula de Aire AV TRAMO: 0+650 - 0+760 9-Sep 9-Sep 15-Aug 16-Aug 0 0 0 0 0 0 W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TRAMO: 0+760 - 0+880 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2060 Termofusión de Tuberia HDPE TRAMO: 0+760 - 0+880 5-Aug 8-Aug 16-Aug 19-Aug 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2070 Montaje de Tuberia HDPE TRAMO: 0+760 - 0+880 9-Sep 10-Sep 19-Aug 21-Aug 0 0 0 0 0 0 W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2080 Montaje de Valvula de Aire AV TRAMO: 0+760 - 0+880 13-Sep 13-Sep 21-Aug 22-Aug 0 0 0 0 0 0 0 0 0 0 W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TRAMO: 0+880 - 1+1360 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2090 Termofusión de Tuberia HDPE TRAMO: 0+880 - 1+1360 31-Aug 13-Sep 22-Aug 1-Sep W W W W W W W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 NO

TB2100 Montaje de Tuberia HDPE TRAMO: 0+880 - 1+1360 10-Sep 18-Sep 27-Aug 6-Sep 0 0 0 0 0 0 0 W W W W W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 OK

TB2110 Montaje de Placas Orificio TRAMO: 0+880 - 1+1360 12-Sep 16-Sep 31-Aug 4-Sep 0 0 0 0 0 0 0 0 0 W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

ESTRUCTURA DE DESCARGA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

ED1000 Habilitado y armado de acero 8-Sep 12-Sep 3-Sep 7-Sep 0 0 0 0 0 W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

ED1010 Colocación de Encofrado 13-Sep 15-Sep 7-Sep 9-Sep 0 0 0 0 0 0 0 0 0 0 W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

ED1020 Colocación de Concreto para estructura 16-Sep 17-Sep 9-Sep 11-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 W W 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

ED1030 Montaje y ubicación de estructura de descarga 20-Sep 22-Sep 11-Sep 14-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W 0 0 0 0 0 0 0 0 OK

DESVIO DE AGUAS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 NO

DA1000 Fabricación de compuerta Metalica 10-Sep 25-Sep 10-Sep 25-Sep 0 0 0 0 0 0 0 W W W W W W W W W W W W W W W W 0 0 0 0 0 OK

DA1010 Montaje de compuerta en Decant Tunnel 25-Sep 28-Sep 25-Sep 28-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W 0 0 OK

OD1040 Desvio de Agua provenientes de los canales 28-Sep 1-Oct 18-Sep 22-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W OK

PROTECCION DE TUBERIA DE DESCARGA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

LINEA: 0+475 a 605 - PIPE 30" HDPE - M1POI-308 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

OBRAS CIVILES LINEA HDPE 30" - M1POI-308 14-Sep 28-Nov 20-Aug 9-Nov 0 0 0 0 0 0 0 0 0 0 0 W W W W W W W W W W W W W W W W W OK

PT1190 Excavación de zanjas 14-Sep 26-Sep 20-Aug 1-Sep 0 0 0 0 0 0 0 0 0 0 0 W W W W W W W W W W W W W 0 0 0 0 OK

PT1200 Colocación de solado (Concreto f'c=10 Mpa, e=0.05m) 28-Sep 9-Oct 3-Sep 14-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W OK

LINEA: 0+605 a 0+650 - PIPE 30" HDPE - MDPOI-309 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

OBRAS CIVILES LINEA HDPE 30" - MDPOI-309 9-Sep 20-Oct 15-Aug 12-Oct 0 0 0 0 0 0 W W W W W W W W W W W W W W W W W W W W W W OK

PT2040 Excavación de zanjas 9-Sep 13-Sep 15-Aug 19-Aug 0 0 0 0 0 0 W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

PT2050 Colocación de solado (Concreto f'c=10 Mpa, e=0.05m) 14-Sep 18-Sep 20-Aug 24-Aug 0 0 0 0 0 0 0 0 0 0 0 W W W W W 0 0 0 0 0 0 0 0 0 0 0 0 OK

PT2060 Colocación de acero de Refuerzo fy=4200 kg/cm2 28-Sep 3-Oct 20-Sep 25-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W OK

OBRAS MECANICAS HDPE 30" - MDPOI-309 19-Sep 30-Sep 11-Sep 22-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W W W W W W W W W OK

PT2090 Montaje de Pipe 30" HDPE y accesorios 19-Sep 30-Sep 11-Sep 22-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W W W W W W W W W OK

LINEA: 0+650 a Est. Booster - PIPE 30" AC. CARBONO - C1E2B-310 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 OK

OBRAS MECANICAS 24-Sep 6-Oct 3-Sep 17-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W W W W OK

PT2300 Montaje de Pipe 30" Carbon Steel y accesorios 24-Sep 29-Sep 3-Sep 8-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W W W 0 OK

PT2320 Montaje de valvulas y accesorios 27-Sep 6-Oct 8-Sep 17-Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W W W W OK


Proyecto:
Socio
Estrategico:
N° de
Contrato:

ITEM
Nuevo Dique y Variante de Carretera de Acceso

HV Contratistas

MOB-1411

ACTIVIDAD

Nuevo Dique de Agua Fresca y Variante de la Carretera de Acceso

Instalacion de Planta de Chancado

Puesta en Operación

Variante de Acceso

Progresiva 0+000 HASTA 1+006.7

Topografía y georeferenciación

Desbroce y Limpieza

Corte en Material Suelto

Nuevo Dique de Agua Fresca

Movilizacion Equipos/Personal/Instalacion Faena Nuevo Dique de Agua Fresca

Trazo y replanteo

Topsoil removal ( excavate,and stockoile)


COMPAÑÍA MINERA ANTAM
Programa de Expansi
EVALUACIÓN DEL PLAN SEM
DEL 11 A 17 de Setiem

METRADO METRADO
METRADO
UNIDAD SEMANAL SEMANAL Responsable
PRESUPUESTO
META CUMPLIDO

glb 1.00 1.00 A. Córdova

Km 1.01 0.10 0.10 J. Electo

ha 2.22 0.33 0.39 A. Córdova

m3 64,593.70 20,462.99 7,161.02 A. Córdova

glb 1.00 0.15 0.08 M. Manchego

glb 1.00 0.20 0.20 J. Electo

m3 2,721.73 720.00 750.00 A. Córdova


MPAÑÍA MINERA ANTAMINA S.A
Programa de Expansión
ACIÓN DEL PLAN SEMANAL N°09
DEL 11 A 17 de Setiembre

Semana 36
D L M M J V S

11 12 13 14 15 16 17 SI

X X X

X X X X X X X 1

X X X X 1

X X X X X X X

X X X X X X X

X X X X X X X 1

X X X X 1

4
57%
Fecha de inicio de semana:

Fecha de corte de semana:

Fecha de presentación:

NO TIPO CAUSA DE INCUMPLIMIENTO

1 ACT-PRE Se encuentra en mantenimiento

- Fallas mecanicas de los equipos y no llegada de equipos adicionales, por


1 ACT-PRE mayor metrado.

1 EXT Gestion de Ingreso de Equipos por temas documentarios

3 CLI-MAT CLIENTE - MATERIALES


CLI-ING CLIENTE - INGENIERÍA
57% CLI-PRI CLIENTE - PRIORIDADES
CLI-CAM CLIENTE - CAMBIO
MAT MATERIALES
DOC DOCUMENTACION TECNICA
ACT-PRE ACTIVIDADES PREVIAS
EXT EXTERNO
SC SUBCONTRATAS
EJEC ERRORES DE EJECUCION
QA/QC CONTROL DE CALIDAD
03/09/11

09/09/11

12/09/11

MEDIDA CORRECTIVA

0
0
0
0
0
0
2
1
0
0
0