DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.01. MUROS Y TABIQUES DE ALBAÑILERIA
03.01.01.01. MURO DE LADRILLO KK 18 H APAREJO CABEZA M2
PRIMER PISO MEDIA AGUA
EJE A
ENTRE 02-03 2.00 0.83 2.40 3.98 2.91
ENTRE 02-03 1.00 0.80 2.40 1.92
ENTRE 02-03 2.00 0.90 1.20 2.16
EJE B
ENTRE 01-02 1.00 1.63 2.40 3.91
ENTRE 01-02 1.00 1.48 2.40 3.55 1.66
ENTRE 03-04 1.00 2.60 2.40 6.24
ENTRE 03-05 1.00 0.57 1.60 0.91
EJE C
ENTRE 02 - 04 1.00 7.28 2.40 17.47
ENTRE 01 - 02 1.00 3.10 2.40 7.44
EJE D
ENTRE 01 - 02 1.00 3.10 2.40 7.44 1.66
EJE 01
ENTRE B-D 2.00 0.55 2.40 2.64
ENTRE B-D 1.00 0.90 2.40 2.16
ENTRE B-D 2.00 0.90 1.20 2.16
EJE 02 3.08
ENTRE B-D 1.00 2.60 2.40 6.24 2.91
ENTRE B-A 1.00 2.50 2.40 6.00 5.14
EJE 03
ENTRE A-C 1.00 2.70 2.40 6.48
EJE 4
ENTRE A-B 1.00 1.39 2.40 3.34
TOTAL 84.05
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.02. REVOQUES Y REVESTIMIENTOS
03.01.02.01. TARRAJEO MUROS INTERILRES MEZ C:A 1:5,E=1.5CM M2
PRIMER PISO
EJE A
ENTRE 02-03 2.00 0.83 2.40 3.98
ENTRE 02-03 1.00 0.80 2.40 1.92
ENTRE 02-03 2.00 0.90 1.20 2.16
EJE B
ENTRE 01-02 1.00 1.63 2.40 3.91
ENTRE 01-02 1.00 1.48 2.40 3.55
ENTRE 03-04 1.00 2.60 2.40 6.24
ENTRE 03-05 1.00 0.57 1.60 0.91
EJE C
ENTRE 02 - 04 1.00 7.28 2.40 17.47
ENTRE 01 - 02 1.00 3.10 2.40 7.44
EJE D
ENTRE 01 - 02 1.00 3.10 2.40 7.44
EJE 01
ENTRE B-D 2.00 0.55 2.40 2.64
ENTRE B-D 1.00 0.90 2.40 2.16
ENTRE B-D 2.00 0.90 1.20 2.16
EJE 02 3.08
ENTRE B-D 1.00 2.60 2.40 6.24
ENTRE B-A 1.00 2.50 2.40 6.00
EJE 03
ENTRE A-C 1.00 2.70 2.40 6.48
EJE 4
ENTRE A-B 1.00 1.39 2.40 3.34
TOTAL 84.05
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
REVOQUES Y REVESTIMIENTOS
03.01.02.02. TARRAJEO MUROS EXTER. FROTACHADO MEZ C:A 1:5,E=1.5CM M2
PRIMER PISO
EJE A
ENTRE 02-03 2.00 0.83 2.40 3.98
ENTRE 02-03 1.00 0.80 2.40 1.92
ENTRE 02-03 2.00 0.90 1.20 2.16
EJE B
ENTRE 01-02 1.00 1.63 2.40 3.91
ENTRE 01-02 1.00 1.48 2.40 3.55
ENTRE 03-04 1.00 2.60 2.40 6.24
ENTRE 03-05 1.00 0.57 1.60 0.91
EJE C
GOBIERNO REGIONAL DE APURIMAC
ENTRE 02 - 04 1.00 0.00 2.40 0.00
ENTRE 01 - 02 1.00 3.10 2.40 7.44
EJE D
ENTRE 01 - 02 1.00 3.10 2.40 7.44
EJE 01
ENTRE B-D 2.00 0.55 2.40 2.64
ENTRE B-D 1.00 0.90 2.40 2.16
ENTRE B-D 2.00 0.90 1.20 2.16
EJE 02
ENTRE B-D 1.00 0.00 2.40 0.00
ENTRE B-A 1.00 2.50 2.40 6.00
EJE 03
ENTRE A-C 1.00 2.70 2.40 6.48
EJE 4
ENTRE A-B 1.00 1.69 2.40 4.06
TOTAL 61.06
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.02.03.TARRAJEO COLUMNAS, MEZCLA 1:5 cm M2
PRIMER PISO
COLUMNAS EXTERIOR
Eje A 2.00 0.50 2.80 2.80
Eje B 2.00 0.50 2.80 2.80
Eje C 1.00 0.25 2.80 0.70
Eje D 2.00 0.50 2.80 2.80
Eje 01 1.00 0.50 2.80 1.40
COLUMNAS INTERIORES
Eje A 2.00 0.25 2.80 1.40
Eje B 2.00 0.25 2.80 1.40
Eje C 1.00 0.25 2.80 0.70
Eje D 2.00 0.25 2.80 1.40
Eje 01 1.00 0.25 2.80 0.70
TOTAL 16.10
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.02.04.TARRAJEO VIGAS, MEZCLA 1:5,E=1.5cm M2
PRIMER PISO
VIGAS EXTERIOR
Eje A 1.00 4.00 0.30 1.20
Eje B 1.00 11.00 0.30 3.30
Eje C 1.00 7.33 0.30 2.20
Eje D 1.00 4.15 0.30 1.25
Eje 01 1.00 4.00 0.30 1.20
Eje 02 1.00 6.50 0.30 1.95
Eje 03 1.00 4.30 0.30 1.29
Eje 04 1.00 1.69 0.30 0.51
VIGAS INTERIORES
Eje A 1.00 4.00 0.20 0.80
Eje B 1.00 11.00 0.20 2.20
Eje C 1.00 7.33 0.20 1.47
Eje D 1.00 4.15 0.20 0.83
Eje 01 1.00 4.00 0.20 0.80
Eje 02 1.00 6.50 0.20 1.30
Eje 03 1.00 4.30 0.20 0.86
Eje 04 1.00 1.69 0.20 0.34
TOTAL 21.49
N DE
DESCRIPCION UND PERIMETRO PARCIAL TOTAL
VECES
03.01.02.05. VESTIDURA DE DERRAMES.e=1.5cm ML
PRIMER PISO
VENTANA
Vertical EJE A 2.00 2.10 4.20
horizontal EJE B 1.00 7.44 7.44
Vertical EJE D 1.00 5.10 5.10
horizontal EJE 01 2.00 2.10 4.20
Vertical EJE 02 1.00 5.10 5.10
Vertical EJE 03 1.00 4.90 4.90
TOTAL 30.94
N DE
DESCRIPCION UND AREA ANCHO ALTO PARCIAL TOTAL
VECES
03.01.04. PISOS Y PAVIMENTOS
03.01.04.01. CONTRAPISOS
03.01.04.01.01. CONTRAPISO DE 40 mm BASE M2
PRIMER PISO
GOBIERNO REGIONAL DE APURIMAC
DORMITORIO 01 1.00 13.46 1.00 13.46
COCINA 1.00 14.05 1.00 14.05
SERVICIO HIGIENICO 1.00 4.19 1.00 4.19
TOTAL 31.70
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.04.02. PISOS
03.01.04.02.01. PISO DE MADERA MACHIHEMBRADO M2
PRIMER PISO
DORMITORIO 01 1.00 13.46 1.00 13.46
COCINA 1.00 14.05 1.00 14.05
SERVICIO HIGIENICO 1.00 4.19 1.00 4.19
TOTAL 31.70
N DE
DESCRIPCION UND AREA ANCHO LARGO PARCIAL TOTAL
VECES
03.01.04.02.02. PISO DE CONCRETO PULIDO, BRUÑADO Y COLOREADO, E=2" M2
Pazadiso
PRIMER PISO
TERRAZA 1.00 10.00 1 10.00
TOTAL 10.00
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.05. ZOCALOS Y CONTRAZOCALOS
03.01.05.01. ZOCALO CON CEMENTO PULIDO H= 0.30
PRIMER PISO
Eje A/1-5 1.00 16.95 0.3 5.09
Eje 1/A-C 1.00 7.65 0.3 2.30
Eje 5/A-B 1.00 3.60 0.3 1.08
TOTAL 8.46
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.05.02. CONTRAZOCALO CEMENTO PULIDO H= 0.10 ML
PRIMER PISO
Eje C/1-5 1.00 13.75 13.75
SEGUNDO PISO
Eje C/1-5 1.00 13.75 13.75
TERCER PISO
Eje C/1-5 1.00 13.75 13.75
TOTAL 41.25
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.06. CARPINTERIA DE MADERA
PUERTAS UND
PRIMER PISO
PUERTA (2.5X1) 2 2.8 1 5.60
PUERTA (2.5X1) 2 2.8 1 5.60
PUERTA (2.5X1) 2 2.8 1 5.60
TOTAL 16.80
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.05.03. VENTANA DE MADERA AGUANO M2
PRIMER PISO
Eje A-A 1.00 12.84 1.70 21.83
Eje C-C 1.00 10.42 1.30 13.55
Eje A-A 1.00 12.84 1.70 21.83
Eje C-C 1.00 10.42 1.30 13.55
Eje A-A 1.00 12.84 1.70 21.83
Eje C-C 1.00 10.42 1.30 13.55
TOTAL 106.12
03.01.10. PINTURA
03.01.10.01. PINTURA LATEX EN MUROS INTERIORES (2 MANOS) M2
PRIMER PISO
EJE A
ENTRE 01-02 1.00 3.22 1.10 3.54
ENTRE 02-03 1.00 3.20 1.10 3.52
ENTRE 03-04 1.00 3.20 1.10 3.52
ENTRE 04-05 1.00 3.22 1.10 3.54
EJE C
ENTRE 01-02 1.00 2.23 1.50 3.35
ENTRE 02-03 1.00 3.20 1.50 4.80
ENTRE 03-04 1.00 2.20 1.50 3.30
ENTRE 04-05 1.00 3.23 1.50 4.85
EJE 01
GOBIERNO REGIONAL DE APURIMAC
ENTRE A-B 1.00 3.08 2.50 7.70
ENTRE B-C 1.00 3.08 2.50 7.70
EJE 03
ENTRE A-B 2.00 3.08 2.50 15.40
ENTRE B-C 2.00 3.08 2.50 15.40
EJE 05
ENTRE A-B 1.00 3.08 2.50 7.70
ENTRE B-C 1.00 3.08 2.50 7.70
SEGUNDO PISO
EJE A
ENTRE 01-02 1.00 3.22 1.10 3.54
ENTRE 02-03 1.00 3.20 1.10 3.52
ENTRE 03-04 1.00 3.20 1.10 3.52
ENTRE 04-05 1.00 3.22 1.10 3.54
EJE C
ENTRE 01-02 1.00 2.22 1.50 3.33
ENTRE 02-03 1.00 3.22 1.50 4.83
ENTRE 03-04 1.00 2.20 1.50 3.30
ENTRE 04-05 1.00 3.22 1.50 4.83
EJE 01
ENTRE A-B 1.00 3.08 2.60 8.01
ENTRE B-C 1.00 3.08 2.60 8.01
EJE 03
ENTRE A-B 2.00 3.08 2.60 16.02
ENTRE B-C 2.00 3.08 2.60 16.02
EJE 05
ENTRE A-B 1.00 3.08 2.60 8.01
ENTRE B-C 1.00 3.08 2.60 8.01
TOTAL 186.49
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.10.02. PINTURA LATEX EN MUROS EXTERIORES (2 MANOS) M2
PRIMER PISO
EJE A
ENTRE 01-02 1.00 3.22 0.80 2.58
ENTRE 02-03 1.00 3.20 0.80 2.56
ENTRE 03-04 1.00 3.20 0.80 2.56
ENTRE 04-05 1.00 3.22 0.80 2.58
EJE C
ENTRE 01-02 1.00 2.22 1.20 2.66
ENTRE 02-03 1.00 3.20 1.20 3.84
ENTRE 03-04 1.00 2.20 1.20 2.64
ENTRE 04-05 1.00 3.23 1.20 3.88
EJE 01
ENTRE A-B 1.00 3.08 2.80 8.62
ENTRE B-C 1.00 3.08 2.80 8.62
EJE 05
ENTRE A-B 1.00 3.08 2.80 8.62
SEGUNDO PISO
EJE A
ENTRE 01-02 1.00 3.22 0.80 2.58
ENTRE 02-03 1.00 3.20 0.80 2.56
ENTRE 03-04 1.00 3.20 0.80 2.56
ENTRE 04-05 1.00 3.22 0.80 2.58
EJE C
ENTRE 01-02 1.00 2.22 1.20 2.66
ENTRE 02-03 1.00 3.22 1.20 3.86
ENTRE 03-04 1.00 2.20 1.20 2.64
ENTRE 04-05 1.00 3.22 1.20 3.86
EJE D (INTERIOR)
ENTRE 02-03 1.00 1.60 1.50 2.40
1.00 2.10 0.60 1.26
ENTRE 03-04 2.00 1.60 1.50 4.80
1.00 2.10 0.60 1.26
ENTRE 04-05 1.00 1.60 1.50 2.40
1.00 2.87 0.60 1.72
EJE D (EXTERIOR)
ENTRE 02-03 1.00 1.60 1.70 2.72
1.00 2.10 0.80 1.68
ENTRE 03-04 2.00 1.60 1.70 5.44
1.00 2.10 0.80 1.68
ENTRE 04-05 1.00 1.60 1.70 2.72
1.00 2.87 0.80 2.30
EJE 01
ENTRE A-B 1.00 3.08 2.60 8.01
ENTRE B-C 1.00 3.08 2.60 8.01
EJE 05
ENTRE A-B 1.00 3.08 2.60 8.01
1.00 16.25 0.60 9.75
TOTAL 136.62
GOBIERNO REGIONAL DE APURIMAC
N DE
DESCRIPCION UND LARGO ANCHO ALTO PARCIAL TOTAL
VECES
03.01.10.03. PINTURA LATEX CIELO RASO M2
PRIMER PISO
Eje A-C/ 1-2 1.00 7.15 3.67 26.24
Eje C-D/ 1-2 1.00 1.80 3.67 6.61
Eje A-C/ 2-3 1.00 7.15 3.70 26.46
Eje C-D/ 2-3 1.00 1.80 3.70 6.66
Eje A-C/ 3-4 1.00 7.15 3.70 26.46
Eje C-D/ 3-4 1.00 1.80 3.70 6.66
Eje A-C/ 4-5 1.00 7.15 3.67 26.24
Eje C-D/ 4-5 1.00 1.80 3.67 6.61
TOTAL 131.92
ARQUITECTURA - AULAS / BLOQUE - 01
Obra :
Mejoramiento de los Servicios de Educacion Secundaria de la Institucion Educativa Manuel Eufracio Alvarez Duran,
Distrito de Cotabambas, Provincia Cotabambas, Region Apurimac
Propietario: Gobierno Regional de Apurimac
Departamento : Apurimac Provincia : Cotabambas Distrito : Cotabambas
03.01.03 CIELORRASOS
03.01.03.01 CIELORRASOS EMPASTADO CON MORTERO DE CEMENTO m2 #REF!
03.01.03.02 CIELORASO CON PANEL FIBROCEMENTO DE e=6mm m2 #REF!
03.01.08 CERRAJERIA
03.01.08.01 BISAGRA CAPUCHINA ACERO ALUMINIZADA DE 4"X4" pza #REF!
03.01.08.02 CERRADURA DE SOBREPONER pza #REF!
03.01.10 PINTURA
03.01.10.01 PINTURA LATEX EN MUROS INTERIORES (2 MANOS) INCLUYE IMPRIMANTE m2 186.49
03.01.10.02 PINTURA LATEX EN MUROS EXTERIORES CON ACABADO SATINADO (2 MANOS) m2 136.62
03.01.10.03 PINTURA LATEX EN CIELO RASO (2 MANOS) INCLUYE IMPRIMANTE m2 131.92
03.01.10.04 PINTURA LATEX EN VIGAS (2 MANOS) INCLUYE IMPRIMANTE m2 #REF!
03.01.10.05 PINTURA LATEX EN COLUMNAS (2 MANOS) INCLUYE IMPRIMANTE m2 #REF!
03.01.10.06 PINTURA CON BARNIZ EN CARPINTERIA DE MADERA m2 #REF!
03.01.10.07 PINTURA ESMALTE EN ZOCALOS H=0.30 m2 #REF!
Página 6
ARQUITECTURA - AULAS / BLOQUE - 01
Obra :
Mejoramiento de los Servicios de Educacion Secundaria de la Institucion Educativa Manuel Eufracio Alvarez Duran,
Distrito de Cotabambas, Provincia Cotabambas, Region Apurimac
Propietario: Gobierno Regional de Apurimac
Departamento : Apurimac Provincia : Cotabambas Distrito : Cotabambas
03.01.11 SEÑALETICA
03.01.11.01 LETREROS DE SEÑALIZACIÒN u 5.00
Página 7