3 DEPARTAMENTO HUANCAVELICA
4 PROVINCIA ACOBAMBA
5 DISTRITO ANTA
VALORIZACION REAJUSTE DE VALORIZACIONES POR FORMULA POLINOMICA TOTAL A CANCELAR PAGADO PENDIENTE
CALENDARIO AL CONTRATISTA DE PAGO
MESES P. BASE VALORIZACION ESCALAMIENTO DEDUCCION DE REINTEGRO VALORIZACION AMORTIZACION AMORTIZACION VALORIZACION IGV DEL V.N. + IGV EFECTIVO = EFECTIVO EFECTIVO
Nº FECHA CONTRATADO DEL MES K MONTO QUE NO CORRESPONDE BRUTA DEL ADELANTO DE ADELANTO NETA I.G.V. ADELANTOS ADELANTO +ADELANTO (VN - Fg) + S/. S/.
MES POR ADELANTO DIRECTO REAJUSTADA DIRECTO PARA MATERIALES (19%) (19%) IGV
Err:509
MES DE SETIEMBRE 2022
2 MES DE SETIEMBRE 2022 Err:509 1-Jun-05 #REF! #REF! 0.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 0.00 Err:509
TOTAL Err:509 Err:509 #REF! 0.00 Err:509 Err:509 Err:509 Err:509 Err:509 38,428.50 7,301.41 Err:509 Err:509 88,975.93 Err:509
SALDO POR
VALORIZAR Err:509
SALDO POR
AMORTIZAR Err:509 Err:509
SALDO MCO.
PPTAL 2005 Err:509 Err:509 Err:509
PLAZO DE EJECUCION : 90 días calendarios FECHA DE INICIO DE OBRA : 16-Febrero-2006 FECHA DE TERMINO DE OBRA: 16-Mayo-2006
(Fecha de entrega de terreno : 26-Enero-2006)
ELABORADO POR : REVISADO POR APROBADO POR :
SUPERVISOR : Ingº ALAVARO G. AMAYA ALVAREZ JEFE DE PROYECTO: DIRECTOR DE ADMINISTRACION :
FICHA TECNICA MES DE SETIEMBRE
DATOS GENERALES DEL PROYECTO
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA
OBRA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
PRESUPUESTOS
PRESUPUESTO BASE S/. 575,173.81
PRESUPUESTO OFERTADO S/. 517,656.43
FACTOR DE RELACION S/. 0.90
PLAZOS:
PLAZO DE EJECUCION 90 DIAS CALENDARIOS
FECHA DE ENTREGA DE TERRENO 6/29/2022
FECHA DE INICIO DE OBRA 7/1/2022
FECHA DE TERMINO DE OBRA 10/19/2022
FECHA REAL DE TERMINO DE OBRA 10/19/2022
RECEPCION DE OBRA
PLAZO REAL DE EJECUCION 110 DIAS CALENDARIOS
ADELANTOS SOLICITADOS
ADELANTO DIRECTO S/. - 0.00%
FECHA DEL ADELANTO DIRECTO
ADELANTO POR MATERIALES S/. - 0.00%
ADELANTO POR MATERIALES S/. - 0.00%
VALORIZACIONES PAGADAS
VALORIZACION Nº 01 S/. 159,800.25 30.87%
VALORIZACION Nº 02 S/. 68,504.78 30.87%
VALORIZACION ACUMULADA S/. 228,305.02 44.10%
ADELANTO DIRECTO 10% S/. - 0.00%
ADELANTO PARA METERIALES 25% S/. - 0.00%
TOTAL PAGADO S/. S/. 228,305.02 44.10%
CERTIFICADO DE PAGO
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA -
OBRA
PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
CONTRATO VALORIZACION %
DESCRIPCION
(S/IGV) ANTERIOR ACTUAL ACUMULADA ACUM. SALDO
VALORIZACION Nº 01
B: REAJUSTES
VALORIZACION BRUTA ( VB : A + B ) 193,478.83 133,281.50 326,760.32
MONTO TOTAL (Con I.G.V.) S/. 517,656.43 S/. 228,305.02 S/. 157,272.17 S/. 385,577.18 132,079.25
MONTO FACTURABLE (Con I.G.V.) CON FACTOR S/. 517,656.43 S/. 228,305.02 S/. 157,272.17 S/. 385,577.18 132,079.25
ADJUDICACION ADJUDICACION SIMPLIFICADA NRO. 004-2022-CS%MDA
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA -
PROYECTO DEPARTAMENTO DE HUANCAVELICA”
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANTA
UBICACIÓN : CHONGOS BAJO-CHUPACA-JUNIN
CONTRATISTA CONSORCIO VISTA ALEGRE DE ANTA
SUPERVISION ARQ. BICILINO ANTEZANA ARECHE
VAL. MONTO GASTOS GEN. UTILIDAD VALORIZ. IGV PAGO SUPER NETO A
PERIODO VALORIZADO REAJUSTES
Nº BRUTO 8.00% 5.00% NETA 19.00% 5.00% PAGAR
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
METRADO
MONTO P.U. MATERIAL Ima Imo TOTAL AMORTIZACION
MATERIALES IU F.R. UTILIZADO SALDO POR AMORTIZAR
OTORGADO (Pmu) (Nov 2019) (abril 2019) AMORTIZADO ACUMULADA
( Mmu )
MANO DE OBRA INC. LEYES SOCIALES 47 0.00 0.90000 0.04 0.00 619.76 619.79 0.00 0.00 0.00
ACERO DE CONSTRUCCION CORRUGADO 3 0.00 0.90000 0.03 0.00 538.09 538.89 0.00 0.00 0.00
CEMENTO PORTLAND TIPO I 21 0.00 0.90000 0.10 0.00 449.56 449.56 0.00 0.00 0.00
MAQUINARIA Y EQUIPO IMPORTADO 49 0.00 0.90000 0.10 0.00 315.38 316.07 0.00 0.00 0.00
AGREGADO GRUESO 5 0.00 0.90000 0.10 0.00 438.49 434.66 0.00 0.00 0.00
INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 0.00 0.90000 0.04 0.00 460.59 459.10 0.00 0.00 0.00
SUB TOTAL S/. 0.00 S/. 0.00 S/. 0.00 0.00
IGV 18% S/. 0.00 S/. 0.00 S/. 0.00 0.00
TOTALES S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
RESUMEN DE VALORIZACION DE OBRA
VALORIZACION DE OBRA Nª 03 AL 30 DE SETIEMBRE DEL 2022
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE MODALIDAD : A SUMA ALZADA PLAZO DE EJECUCION 110 DIAS CALENDARIOS PROVINCIA ACOBAMBA
VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA -
OBRA: DEPARTAMENTO DE HUANCAVELICA” AMPLIACION DE PLAZO Nº 01 FECHA DE INICIO DEL SERVICIO 7/1/2022
DISTRITO ANTA
CONTRATISTA CONSORCIO VISTA ALEGRE DE ANTA PRESUPUESTO REFERENCIAL S/. PROG. TERMINO DEL SERVICIO 10/19/2022
INSPECTOR ARQ. BICILINO ANTEZANA ARECHE 517,656.43 TERMINO OBRA AMPLIACION LOCALIZACION COMUNIDAD DE VISTA
ALEGRE
RESIDENTE ING. CESAR JULIAN LANDEO TITO FECHA PRESENTACION PERIODO
30 DE SETIEMBRE 2022 DEL 01-09-2022 AL 30-09-2022
AVANCE
SALDOS
PARTIDA DESCRIPCION UND METRADO PARCIAL ANTERIOR ACTUAL ACUMULADO
(S/.) PARCIAL % PARCIAL % PARCIAL % PARCIAL %
SUB - TOTAL 1 438,691.88 193,478.83 44.10% 133,281.50 30.38% 326,760.32 74.49% 111,931.57 25.51%
Adelanto Otorgado: S/. 150,847.46 Sin IGV Material: Cemento Portland Tipo I
NOTA: A solicitud del Contratista se está amortizando el 100% del adelanto de materiales para el cemento.
Adelanto Otorgado: S/. 150,847.46 Sin IGV Material: Cemento Portland Tipo I
ADELANTO Nº 01 DESCRIPCION DEL MATERIAL : CEMENTO TIPO I PORTLAND F.P. N°02
MES ADELANTO OTORGADO COEF. INCIDENC ADELANTO SALD.ADEL. DEDUCCION DEDUCC. ACUM.
VAL. PERIODO DE MES MONTO MONTO Vº UTILIZ.( A) Imr Ima Imo POR UTILIZ. MENSUAL MENSUAL
Nº REGULARIZ. OTORG. (1) DEFRACTADO (2) (3) (4) (5)=(2)*(3)*(4) (6) (7) (8) (10)=(1)-(5) (11)=(5)*(8)/(7)*(((6)-(7))/(8))
OCT'00 350.55 350.55 350.55 93,208.44 0.00 0.00
1 19-OCT AL 20-NOV 339,089.97 0.299 0.5685 57,639.02
NOV'00 350.55 350.55 350.55 0.00 0.00
NOV'00 350.55 350.55 350.55 #REF! #REF! #REF!
2 21-NOV AL 20-DIC OCT./00 150,847.46 150,847.46 #REF! 0.299 0.5685 #REF!
DIC'00 350.55 350.55 350.55 #REF! #REF!
DIC'00 350.55 350.55 350.55 #REF! #REF! #REF!
3 21-DIC AL 20-ENE #REF! 0.299 0.5685 #REF!
ENE'01 350.55 350.55 350.55 #REF! #REF!
ENE'01 350.55 350.55 350.55 #REF! #REF! #REF!
4 21-ENE AL 20-FEB #REF! 0.299 0.5685 #REF!
FEB'01 350.55 350.55 350.55 #REF! #REF!
1 19-OCT AL 20-NOV NOV'00 339,089.97 0.299 0.0870 8,820.75 232.87 232.87 223.87 20,028.10 0.00 0.00
#REF!
ADJUDICACION ADJUDICACION SIMPLIFICADA NRO. 004-2022-CS%MDA
PROYECTO “MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
ENTIDAD MUNICIPALIDAD DISTRITAL DE ANTA
UBICACIÓN #REF!
CONTRATISTA CONSORCIO VISTA ALEGRE DE ANTA
SUPERVISION ARQ. BICILINO ANTEZANA ARECHE
FORMULA DEDUCCION QUE NO CORRESPONDE : D = Deducción del adelanto por cada elemento
Imo = Indice del elemento a la fecha base
Ima = Indice del elemento a la fecha del adelanto
D = Valoriz. x Coef.Incid. x (Imr - Ima) / Imo Imr = Indice del elemento a la fecha del reajuste
PRIMER PAGO
01 Feb-06 Err:509 0.424 100.00% Err:509 361.79 361.79 361.79 Err:509 Err:509 Err:509 Err:509 0.00 Err:509
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
MUNICIPALIDAD DISTRITAL DE ANTA RESIDENTE DE OBRA: ING. CESAR JULIAN LANDEO TITO
COMUNIDAD DE VISTA ALEGRE PLAZO DE EJECUCIÓN: 110 DIAS CALENDARIOS
S/. 517,656.43 FECHA DE INICIO DE OBRA: 7/1/2022 90.00
COMUNIDAD DE VISTA ALEGRE FECHA DE CULMINACION 9/29/2022 240.00
ARQ. BICILINO ANTEZANA ARECHE 150.00
ING. CESAR JULIAN LANDEO TITO
VALORIZACION DE OBRA Nª 03 AL 30 DE SETIEMBRE DEL 2022
AVANCE ANTERIOR AVANCE ACTUAL EJECUTADO SALDO A EJECUTAR
UND METRADO PRECIO TOTAL METRADO MONTO % METRADO MONTO % METRADO MONTO % METRADO MONTO %
OBRAS PROVISIONALES 3,249.45
ALQUILER DE LOCAL PARA LA OBRA
CARTEL DE IDENTIFICACION DE LA OBRA, 3.60mX2.40m mes 3.00 450.00 1,350.00 2.00 900.00 66.67% 1.00 450.00 33.33% 3.00 1,350.00 100.00% 0.00 0.00 0.00%
und 1.00 374.91 374.91 1.00 374.91 100.00% - 0.00% 1.00 374.91 100.00% 0.00 0.00 0.00%
SEÑALIZACION EN OBRA DURANTE LA EJECUCION glb 1.00 1,524.54 1,524.54 1.00 1,524.54 100.00% - 0.00% 1.00 1,524.54 100.00% 0.00 0.00 0.00%
TRABAJOS PRELIMINARES
11,270.89
TRAZO, NIVELACION Y REPLANTEO
m2 14,637.52 0.77 11,270.89 14,637.52 11,270.89 100.00% - 0.00% 14,637.52 11,270.89 100.00% 0.00 0.00 0.00%
ESTRUCTURA
90,074.50
MOVIMIENTO
EXCAVACIONDEPARA
TIERRAS
DADOS DE CIMENTACION 56,623.87
m3 12.48 20.41 254.72 12.48 254.72 100.00% - 0.00% 12.48 254.72 100.00% 0.00 0.00 0.00%
m3 68.19 20.41 1,391.76 - - 0.00% 68.19 1,391.76 100.00% 68.19 1,391.76 100.00% 0.00 0.00 0.00%
m3 6.76 20.41 137.97 6.76 137.97 100.00% - 0.00% 6.76 137.97 100.00% 0.00 0.00 0.00%
m3 8,101.84 2.00 16,203.68 8,101.84 16,203.68 100.00% - 0.00% 8,101.84 16,203.68 100.00% 0.00 0.00 0.00%
m3 9,008.73 1.58 14,233.79 9,008.73 14,233.79 100.00% - 0.00% 9,008.73 14,233.79 100.00% 0.00 0.00 0.00%
m3 383.92 63.56 24,401.96 - - 0.00% 383.92 24,401.96 100.00% 383.92 24,401.96 100.00% 0.00 0.00 0.00%
CONCRETO SIMPLE 33,450.62
CONCRETO EN DADOS DE CIMENTACION MEZCLA 1:8 + 25% PM
3,884.28
CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 12.48 311.24 3,884.28 12.48 3,884.28 100.00% - 0.00% 12.48 3,884.28 100.00% 0.00 0.00 0.00%
22,983.44
SOLADO PARA ZAPATAS MEZCLA E=4" 1:10 m3 68.19 337.05 22,983.44 - - 0.00% 68.19 22,983.44 100.00% 68.19 22,983.44 100.00% 0.00 0.00 0.00%
264.47
m3 0.97 272.65 264.47 0.97 264.47 100.00% - 0.00% 0.97 264.47 100.00% 0.00 0.00 0.00%
59.98
m3 0.22 272.65 59.98 0.22 59.98 99.99% - 0.00% 0.22 59.98 99.99% 0.00 0.00 0.00%
6,258.45
m3 213.09 29.37 6,258.45 213.09 6,258.45 100.00% - 0.00% 213.09 6,258.45 100.00% 0.00 0.00 0.00%
CONCRETO ARMADO 8,580.54
ZAPATAS INGRESO PRINCIPAL
1,890.88
ZAPATAS - CONCRETO F'C=210 KG/CM2
1,347.64
m3 3.86 349.13 1,347.64 - - 0.00% 3.86 1,347.64 100.00% 3.86 1,347.64 100.00% 0.00 0.00 0.00%
ZAPATAS - ACERO F'Y=4,200 KG/CM2
543.24
kg 108.00 5.03 543.24 - - 0.00% 108.00 543.24 100.00% 108.00 543.24 100.00% 0.00 0.00 0.00%
COLUMNAS INGRESO PRINCIPAL
1,650.03
m3 1.37 349.13 478.31 - - 0.00% 1.37 478.31 100.00% 1.37 478.31 100.00% 0.00 0.00 0.00%
m2 5.49 29.37 161.24 - 5.49 161.24 161.24 5.49 0.00 0.00%
kg 200.89 5.03 1,010.48 - - 0.00% 200.89 1,010.48 100.00% 200.89 1,010.48 100.00% 0.00 0.00 0.00%
PLACAS INGRESO PRINCIPAL
5,039.64
m3 5.85 349.13 2,042.41 - - 0.00% 5.85 2,042.41 100.00% 5.85 2,042.41 100.00% 0.00 0.00 0.00%
m2 45.27 29.37 1,329.58 - 45.27 1,329.58 1,329.58 45.27 0.00 0.00%
kg 331.54 5.03 1,667.65 - - 0.00% 331.54 1,667.65 100.00% 331.54 1,667.65 100.00% 0.00 0.00 0.00%
ARQUITECTURA
MUROS Y TABIQUERIA DE ALBAÑILERIA 134,612.67
146.54
146.54
m2 3.52 41.63 146.54 - - 0.00% 3.52 146.54 100.00% 3.52 146.54 100.00% 0.00 0.00 0.00%
3,934.64
m2 22.86 8.71 199.11 - - 0.00% 11.43 99.56 50.00% 11.43 99.56 50.00% 11.43 99.55 50.00%
m2 426.18 7.67 3,268.80 - - 0.00% 213.09 1,634.40 213.09 1,634.40 50.00% 213.09 1,634.40 50.00%
m2 45.27 10.31 466.73 - - 0.00% 22.64 233.37 50.00% 22.64 233.37 50.00% 22.64 233.36 50.00%
PINTURAS 45,408.59
m2 639.25 5.67 3,624.55 - - 0.00% 319.63 1,812.27 50.00% 319.63 1,812.27 50.00% 319.63 1,812.28 50.00%
m2 1,215.00 33.38 40,556.70 - - 0.00% 607.50 20,278.35 50.00% 607.50 20,278.35 50.00% 607.50 20,278.35 50.00%
m2 60.49 20.29 1,227.34 - - 0.00% 30.25 613.67 50.00% 30.25 613.67 50.00% 30.25 613.67 50.00%
JUNTAS DE DILATACION
1,362.95
RELLENO DE JUNTAS DE DILATACION CON ASFALTO RC-250
m 211.31 6.45 1,362.95 - - 0.00% 150.00 967.50 70.99% 150.00 967.50 70.99% 61.31 395.45 29.01%
CARPINTERIA METALICA
MALLA OLIMPICA 83,759.95
SUMINISTRO E INSTALACION DE COLUMNAS DE TUBERIA DE F°G° DE 2" 79,190.39
m 510.30 24.10 12,298.23 - - 0.00% 350.00 8,435.00 68.59% 350.00 8,435.00 68.59% 160.30 3,863.23 31.41%
m 156.00 176.36 27,512.16 156.00 27,512.16 100.00% - 0.00% 156.00 27,512.16 100.00% 0.00 0.00 0.00%
VALORIZACION DE OBRA Nª 03 AL 30 DE SETIEMBRE DEL 2022
DEL RESIDENTE DE OBRA
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
MUNICIPALIDAD DISTRITAL DE ANTA RESIDENTE DE OBRA: ING. CESAR JULIAN LANDEO TITO
COMUNIDAD DE VISTA ALEGRE PLAZO DE EJECUCIÓN: 110 DIAS CALENDARIOS
S/. 517,656.43 FECHA DE INICIO DE OBRA: 7/1/2022 90.00
COMUNIDAD DE VISTA ALEGRE FECHA DE CULMINACION 9/29/2022 240.00
ARQ. BICILINO ANTEZANA ARECHE 150.00
ING. CESAR JULIAN LANDEO TITO
VALORIZACION DE OBRA Nª 03 AL 30 DE SETIEMBRE DEL 2022
AVANCE ANTERIOR AVANCE ACTUAL EJECUTADO SALDO A EJECUTAR
UND METRADO PRECIO TOTAL METRADO MONTO % METRADO MONTO % METRADO MONTO % METRADO MONTO %
PUERTA METALICA m 1,375.00 28.64 39,380.00 - - 0.00% 800.00 22,912.00 58.18% 800.00 22,912.00 58.18% 575.00 16,468.00 41.82%
4,569.56
PRUEBAS DE LABORATORIO m 1.00 4,569.56 4,569.56 - - 0.00% - 0.00% 0.00 0.00 0.00% 1.00 4,569.56 100.00%
585.41
und 1.00 315.41 315.41 - - 0.00% 1.00 315.41 100.00% 1.00 315.41 100.00% 0.00 0.00 0.00%
und 10.00 27.00 270.00 - - 0.00% 10.00 270.00 100.00% 10.00 270.00 100.00% 0.00 0.00 0.00%
50,538.00
m3 295.06 20.41 6,022.17 295.06 6,022.17 100.00% - 0.00% 295.06 6,022.17 100.00% 0.00 0.00 0.00%
m 738.80 5.78 4,270.26 738.80 4,270.26 100.00% - 0.00% 738.80 4,270.26 100.00% 0.00 0.00 0.00%
m3 245.88 75.92 18,667.21 245.88 18,667.21 100.00% - 0.00% 245.88 18,667.21 100.00% 0.00 0.00 0.00%
m3 292.57 16.68 4,880.07 292.57 4,880.07 100.00% - 0.00% 292.57 4,880.07 100.00% 0.00 0.00 0.00%
m 631.98 20.77 13,126.22 631.98 13,126.22 100.00% - 0.00% 631.98 13,126.22 100.00% 0.00 0.00 0.00%
m 106.82 33.44 3,572.06 106.82 3,572.06 100.00% - 0.00% 106.82 3,572.06 100.00% 0.00 0.00 0.00%
VARIOS 20,533.34
m3 639.86 13.29 8,503.74 - - 0.00% - 0.00% 0.00 0.00 0.00% 639.86 8,503.74 100.00%
m2 14,693.00 0.51 7,493.43 - - 0.00% - 0.00% 0.00 0.00 0.00% 14,693.00 7,493.43 100.00%
und 1.00 586.24 586.24 - - 0.00% - 0.00% 0.00 0.00 0.00% 1.00 586.24 100.00%
und 1.00 2,357.64 2,357.64 1.00 2,357.64 100.00% - 0.00% 1.00 2,357.64 100.00% 0.00 0.00 0.00%
und 1.00 1,592.29 1,592.29 1.00 1,592.29 100.00% - 0.00% 1.00 1,592.29 100.00% 0.00 0.00 0.00%
FLETE TERRESTRE
30,345.86
glb 1.00 30,345.86 30,345.87 1.00 30,244.70 99.67% 101.17 0.33% 1.00 30,345.87 100.00% 0.00 0.00 0.00%
ALCANTARILLA DE CONCRETO ARMADO
28,980.55
m3 5.10 20.41 104.09 - - 0.00% - 0.00% 0.00 0.00 0.00% 5.10 104.09 100.00%
m3 1.02 272.65 278.10 - - 0.00 1.02 278.10 100.00%
m3 98.88 269.96 26,693.64 - - 0.00 98.88 26,693.64 100.00%
ENCOFRADO Y DESENCOFRADO EN COLUMNA m3 19.18 29.42 564.28 - - 0.00% - 0.00% 0.00 0.00 0.00% 19.18 564.28 100.00%
kg 273.56 4.90 1,340.43 - - 0.00% - 0.00% 0.00 0.00 0.00% 273.56 1,340.43 100.00%
EQUIPAMIENTO
1,800.00
glb 1.00 1,800.00 1,800.00 - - 0.00% - 0.00% 0.00 0.00 0.00% 1.00 1,800.00 100.00%
CAPACITACION Y SENSIBILIZACION
900.00
glb 1.00 900.00 900.00 0.70 630.00 70.00% 0.30 270.00 30.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA -
OBRA: PLAZO DE EJECUCION 110 DIAS CALENDARIOS
PROVINCIA DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
CONTRATISTA CONSORCIO VISTA ALEGRE DE ANTA FECHA DE INICIO DEL SERVICIO 01/07/2022
INSPECTOR ARQ. BICILINO ANTEZANA ARECHE PROG. TERMINO DEL SERVICIO 10/19/2022
RESIDENTE ING. CESAR JULIAN LANDEO TITO FECHA PRESENTACION 30 DE SETIEMBRE 2022
90%
80%
74.49%
70%
AVANCE MENSUAL ACUMULADO (%)
70.26%
60%
50% PROGRAMADO
44.10%
Column L
40%
30% 30.87%
28.64%
20%
10%
0% 0
01/09/21 jul-22 ago-22 sep-22
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA DE
OBRA:
ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
PLAZO DE EJECUCION 110 DIAS CALENDARIOS
CONTRATISTA CONSORCIO VISTA ALEGRE DE ANTA FECHA DE INICIO DEL SERVICIO 01/07/2022
INSPECTOR ARQ. BICILINO ANTEZANA ARECHE PROG. TERMINO DEL SERVICIO 19/10/2022
RESIDENTE ING. CESAR JULIAN LANDEO TITO FECHA PRESENTACION 30 DE SETIEMBRE 2022
450,000
400,000
385,577.18
350,000 363,730.69
300,000
250,000 228,305.02
200,000
159,800.25
150,000
148,243.31
100,000
50,000
0
0 0
01/09/21 44772 44804 44834
P ROGRA MA DO
“MEJORAMIENTO DEL ESTADIO VISTA ALEGRE DE LA LOCALIDAD DE VISTA ALEGRE DEL DISTRITO DE ANTA - PROVINCIA
PROYECTO
DE ACOBAMBA - DEPARTAMENTO DE HUANCAVELICA”
UBICACIÓN COMUNIDAD DE VISTA ALEGRE
TOTAL PRESUPUESTO (TP = ST + IGV) ACUMULADO CON EL FACTOR 517,656.43 148,243.40 215,487.52 153,925.52
TOTAL PRESUPUESTO (TP = ST + IGV) ACUMULADO MENSUAL 148,243.40 363,730.92 517,656.41
PORCENTAJE MENSUAL 28.64% 41.63% 29.74% 100.00%
PORCENTAJE ACUMULADO MENSUAL 28.64% 70.26% 100.00%