FECHA BASE DEL PRESUPUESTO AGOSTO 2020

MES DE INICIO DE VALORIZACIONES OCTUBRE 2020

CONTROL DE VALORIZACIONES (DATOS SIN IGV) LEYENDA


SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL
Nº MES "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA” TOTAL
1 9/30/2020 8,410.29 8,410.29 COLOR DATOS AL INICIO
2 10/31/2020
3 11/30/2020 COLOR EN CADA VALORIZACION
4 12/31/2020
COLOR SON CONSECUENCIA

ACUMULADO ACTUAL 8,410.29 8,410.29 (verificar al inicio)


COLOR SON CONTROLES
CONTRATO 1,608,247.46 1,608,247.46
COLOR FALTA LLENAR
SALDO 1,599,837.18 1,599,837.18

RESUMEN
Monto del Mes Avance
OBRAS PROYECTADAS Contrato Anterior Acumulado % Saldo % Programado %
sin IGV Actual Acumulado
MANTENIMIENTO PERIÓDICO 1,608,247.46 0.00 8,410.29 8,410.29 0.52% 1,599,837.18 99.48% 16,820.56 1.05%
SUB-TOTAL 1,608,247.46 0.00 8,410.29 8,410.29 0.52% 1,599,837.18 99.48% 16,820.56 1.05%
IMPUESTO IGV 18% 289,484.54 0.00 1,513.85 1,513.85 0.52% 287,970.69 99.48% 3,027.70 1.05%
TOTAL 1,897,732.00 0.00 9,924.14 9,924.14 0.52% 1,887,807.87 99.48% 19,848.26 1.05%
I.- FICHA DE IDENTIFICACION DE LA OBRA
VALORIZACIÓN DE OBRA Nº 01 (Del 28 al 30 de Setiembre del 2020)
1 Servicio :
SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL
"EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”

2 Ubicación : EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA
Area Geográfica : 1
3 Metas :
REHABILITACION Y MEJORAMIENTO DEL TRAMO JEMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA
BUENA - CP. PIOBAMBA, KM 00+000 HASTA EL KM 33+530

4 Entidad Contratante : MUNICIPALIDAD PROVINCIAL DE CELENDÍN


5 Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.
6 Supervisión :
Inspector de Servicio : ING. LENIN ESPINOZA SILVA CIP Nº 178799
7 Residente : ING. LÁZARO ENCARNACIÓN TERRONES VÁSQUEZ CIP Nº 87965
8 Financiamiento : MINISTERIO DE TRANSPORTES Y COMUNICACIONES
9 Procedimiento de Selección : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
10 Modalidad : SUMA ALZADA
11 Presupuesto referencial, con IGV y fecha : S/. 1,897,732.00 ´Septiembre 2020
12 Presupuesto referencial, sin IGV y fecha : S/. 1,608,247.46 ´Septiembre 2020
13 Factor de Relación (FR) : 1.00
14 Monto del contrato, con IGV : S/. 1,897,732.00
15 Monto del contrato, sin IGV : S/. 1,608,247.46
16 Plazo de ejecución, en d. c. : 90
17 Adelanto directo con IGV y fecha de pago : S/. 0.00 no solicita 0.00%
18 Adelanto directo sin IGV y fecha de pago : S/. 0.00 no solicita 0.00%
19 Fecha inicio plazo contractual : 28-Sep-20
20 Fecha término plazo contractual : 26-Dec-20
21 Avance Real Acumulado : 0.52%
22 Avance Programado Acumulado : 1.05%
23 Situación de la obra respecto del avance : SERVICIO ATRASADO.

31 de October de 2020
RESUMEN DE VALORIZACIÓN Nº 01 - OCTUBRE 2020

PROYECTO: SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”

REGION : CAJAMARCA MONTO DE LA OBRA : S/. 1,897,732.00


PROVINCIA : CELENDIN FECHA DE INICIO DE OBRA : 9/28/2020
DISTRITO : SUCRE - OXAMARCA PLAZO DE EJECUCION : 90 dias calendarios
LOCALIDADES : EMP. PE 08 B (C.P VIGASPAMPA) - PERIODO DE EJECUCION : Del 28/09/2020 AL 30/09/2020
MINASCONGA – COCÁN- YERBA BUENA
- CP. PIOBAMBA. FECHA DE PRESENTACION : 9/30/2020

GASTOS AVANCE ACTUAL


SUB COSTO UTILIDADES SUB TOTAL
DESCRIPCION GENERALES IGV (18 %) TOTAL S/. COSTO SUB TOTAL % DE
PRESUP. DIRECTO S/. S/. S/. G.G. S/. U.T. S/. IGV (18%) TOTAL S/.
S/. DIRECTO S/. AVANCE

1 REHABILITACION Y MEJORAMIENT 1,443,772.86 92,285.96 72,188.64 1,608,247.46 289,484.54 1,897,732.01 7,550.17 482.61 377.51 8,410.29 1,513.85 9,924.15 0.52%

T O T A L GENERAL S/. 1,443,772.86 92,285.96 72,188.64 1,608,247.46 289,484.54 1,897,732.00 7,550.17 482.61 377.51 8,410.29 1,513.85 9,924.15 0.52%

PRESUPUESTO TOTAL DE OBRA : S/.1,897,732.00


AVANCE DE OBRA ANTERIOR : 0.00%
AVANCE DE OBRA ACTUAL : 0.52% (COSTO DIRECTO)
AVANCE ACUMULADO AL 30/09/17 : 0.52%

VALORIZACION ACTUAL DE OBRA : S/.9,924.15


CÁLCULO DEL REINTEGRO AUTORIZADO
Contrato Principal

SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL Procedimiento PROCEDIMIENTO ESPECIAL DE
OBRA: de Selección
CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – SELECCIÓN N° 007-2020-MPC/CS
YERBA BUENA - CP. PIOBAMBA” AMOVER CONTRATISTAS GENERALES
Contratista :
E.I.R.L.
Val. Fecha Valorización Valorización Reajuste Reajuste Deducciones por Adelantos Reintegro
No. Programada Real K-1 Program. Real Autorizado Directo Para Materi. Autorizado
Bruto Neto
A B C D E F=C*E G=D*E H I J L =H-I-J

REHABILITACION Y M 1,608,267.37 8,410.29 - - - - - -


1 31-oct-20 488,493.08 8,410.29 0.000 - -
2 30-nov-20 497,051.67 - - -
3 31-dic-20 622,722.62 - - -
TOTAL REINTEGRO REHABILIACIÓN Y MEJOAMIENTO -
REINTEGRO ACUMULADO VALORIZACION ANTERIOR -
REINTEGRO VALORIZACION PRESENTE -
VALORIZACIÓN DE OBRA N° 01 (Del 01/10/2020 al 31/10/2020)

PROYECTO: SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”
MONTO
1,897,732.00 OBRA CP. PIOBAMBA, :KM 00+000 HASTA EL KM 33+530
PROY. :
REGION : CAJAMARCA MONTO OBRA : 1,897,732.00 (INC. IGV) F.R. = 1.00
PROVINCIA : CELENDIN FECHA INICIO DE OBRA : 9/28/2020
DISTRITO : SUCRE - OXAMARCA PLAZO DE EJECUCION : 90.00 dias calendarios
CASERIO : EMP. PE 08 B (C.P VIGASPAMPA) - MINASCONGA – COCÁN- YERBA BUENA - C FECHA
Presu TÉRMINO OBRA : 12/26/2020
Item Descripción puest AVANCES Saldo
o
Anterior Actual Acumulado Metrado Valorizado S/.
Precio
Und Metrado Presupuesto Metrado Valorizado S/. Metrado Valorizado S/. Metrado Valorizado S/. %
Unitario
01 EJECUCION DEL MANTENIMIENTO PERIODICO 1,443,772.86
01.01 OBRAS PRELIMINARES 32,982.55
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 15,100.33 15,100.33 0.00 0.00 0.50 7,550.17 0.50 7,550.17 50.00% 0.50 7550.17
01.01.02 TRAZO Y REPLANTEO km 33.53 533.32 17,882.22 0.00 0.00 0.00 0.00 0.00 0.00% 33.53 17882.22
01.02 PAVIMENTOS 852,624.40
01.02.01 CAPA NIVELANTE E=0.05m m3 7,002.50 30.44 213,156.10 0.00 0.00 0.00 0.00 0.00 0.00% 7,002.50 213156.10
01.02.02 MATERIAL GRANULAR DE CANTERA E=0.15m m3 21,007.50 30.44 639,468.30 0.00 0.00 0.00 0.00 0.00 0.00% 21,007.50 639468.30
01.03 TRANSPORTE 320,449.63
01.03.01 TRANSPORTE DE MATERIAL GRANULAR D<=1 km m3k 19,934.11 7.46 148,708.46 0.00 0.00 0.00 0.00 0.00 0.00% 19,934.11 148708.46
01.03.02 TRANSPORTE DE MATERIAL GRANULAR D>1 km m3k 66,677.65 2.43 162,026.69 0.00 0.00 0.00 0.00 0.00 0.00% 66,677.65 162026.69
01.03.03 TRANSPORTE DE MATERIAL EXCEDENTE D<=1 km m3k 1,121.11 7.34 8,228.95 0.00 0.00 0.00 0.00 0.00 0.00% 1,121.11 8228.95
01.03.04 TRANSPORTE DE MATERIAL EXCEDENTE D>1 km m3k 544.15 2.73 1,485.53 0.00 0.00 0.00 0.00 0.00 0.00% 544.15 1485.53
01.04 OBRAS DE ARTE Y DRENAJE 177,709.00
01.04.01 RECONFORMACIÓN DE CUNETAS m 33,530.00 5.30 177,709.00 0.00 0.00 0.00 0.00 0.00 0.00% 33,530.00 177709.00
01.05 SEÑALIZACION 38,521.32
01.05.01 INSTALACION DE POSTES KILOMÉTRICOS und 34.00 257.82 8,765.88 0.00 0.00 0.00 0.00 0.00 0.00% 34.00 8765.88
01.05.02 SEÑALES PREVENTIVAS und 40.00 465.39 18,615.60 0.00 0.00 0.00 0.00 0.00 0.00% 40.00 18615.60
01.05.03 SEÑALES REGLAMENTARIAS und 7.00 862.56 6,037.92 0.00 0.00 0.00 0.00 0.00 0.00% 7.00 6037.92
01.05.04 SEÑALES INFORMATIVAS und 6.00 850.32 5,101.92 0.00 0.00 0.00 0.00 0.00 0.00% 6.00 5101.92
01.06 IMPACTO AMBIENTAL 20,283.19
01.06.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS ha 2.31 8,780.60 20,283.19 0.00 0.00 0.00 0.00 0.00 0.00% 2.31 20283.19
01.07 EMERGENCIA SANITARIA 1,202.77
01.07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 1,202.77 1,202.77 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 1202.77

COSTO DIRECTO S/. 1,443,772.86 0.00 7550.17 7550.17 1436222.70


GASTOS GENERALES (6.392%) 92,285.96 0.00 482.61 482.61 91,803.35
UTILIDAD ( 5%) 72,188.64 0.00 377.51 377.51 71,811.13
SUB TOTAL 1,608,247.46 0.00 8,410.29 8,410.29 1,599,837.18
IMPUESTO IGV = 18% 289,484.54 0.00 1,513.85 1,513.85 287,970.69
VALOR REFERENCIAL 1,897,732.00 0.00 9,924.14 9,924.14 1,887,807.86
% DE AVANCE PARCIAL 0.00% 0.52% 0.52% 99.48%
Procedimiento de Selección : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
:
PROYECTO SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) -
MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”

Ubicación : EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA
Area Geográfica : 1
Valor Referencial : S/. 1,897,732.00 (inc. IGV) S/.1,608,247.46 (sin IGV)
Monto Contratado : S/. 1,897,732.00 (inc. IGV) S/.1,608,247.46 (sin IGV)
Factor de relación : 1.00000
Inspector de Servicio : ING. LENIN ESPINOZA SILVA
Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.
Plazo de Ejecución de Obra : 90 dias calendarios
Fecha de inicio de Obra : 28-Sep-20
Fecha de término de Obra : 26-Dec-20
Ampliaciones de Plazo : 0

RESUMEN DE VALORIZACIÓN N° 01
(DEL 28 AL 30 DE SETIEMBRE DE 2020)

MONTO VAL ACUM % DE


DESCRIPCIÓN VAL ACTUAL VAL ACUM ACTUAL SALDO POR VALORIZAR
CONTRATO ANTERIOR AVANCE

REHABILITACION Y MEJORAMIENTO DEL TRAMO


1,608,247.46 0.00 8,410.29 8,410.29 0.52% 1,599,837.18
TOTAL CONTRACTUAL (S/IGV) 1,608,247.46 0.00 8,410.29 8,410.29 0.52% 1,599,837.18
% DE AVANCE DE OBRA A LA FECHA 0.00% 0.52% 0.52% 99.48%
% DE AVANCE DE OBRA PROGRAMADO 1.05%
SITUACIÓN ACTUAL OBRA ATRASADA

REAJUSTES (S)
REHABILITACION Y MEJORAMIENTO DEL TRAMO JEMP. PE 08 0.00 0.00 0.00
TOTAL REAJUSTES (R) 0.00 0.00 0.00

AMORTIZACIONES (A)
Amortización del Adelanto Directo 0.00 0.00 0.00 0.00 0.00
Amortización del Adelanto para Materiales 0.00 0.00 0.00 0.00 0.00

Amortización por retención por fiel cumplimiento 0.00 0.00 0.00 0.00 0.00% 0.00
TOTAL AMORTIZACIONES (A) 0.00 0.00 0.00 0.00 0.00

VALORIZACION NETA (VN=VA+R-A) 0.00 8,410.29 8,410.29

MULTA POR ATRASO DE OBRA (M) 0.00 0.00 0.00

MONTO A PAGAR AL CONTRATISTA


En efectivo (VN-M) 0.00 8,410.29 8,410.29
En IGV (VN x 18%) 0.00 1,513.85 1,513.85

MONTO TOTAL CON IGV S/. 0.00 9,924.14 9,924.14


TOTAL A PAGAR S/. 9,924.14

NOTA:

0
VALORIZACION TOTAL N° 01 DEL ADICIONAL N° 02 - SEPTIEMBRE 2020

OBRA: SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”

REGION : CAJAMARCA MONTO DE LA OBRA : S/. 1,897,732.00

PROVINCIA : CELENDIN FECHA DE INICIO DE OBRA : 9/28/2020

DISTRITO : SUCRE - OXAMARCA PLAZO DE EJECUCION : 90


PERIODO DE EJECUCION : Del 28/09/2020 AL 30/09/2020 FECHA DE PRESENTACION : 9/30/2020

Monto Contractual
VALORIZACION (SIN IGV) SALDO POR
Item Descripción sin IGV
ANTERIOR ACTUAL ACUMULADO VALORIZAR

A VALORIZACION CONTRACTUAL
1,608,247.46 0.00 8,410.29 8,410.29 1,599,837.16
SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO
VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP.
PIOBAMBA”
TOTAL (A) 1,608,247.46 0.00 8,410.29 8,410.29 1,599,837.16
CONTROL DE AVANCE DE OBRA AVANCE FISICO EJECUTADO 0.00% 0.52% 0.52% 99.48%
AVANCE FISICO PROGRAMADO 0.00% 1.05% 1.05% 98.95%
% DE AVANCE REAL DE OBRA 0.00% 0.52% 0.52% 99.48%
B REAJUSTES ACUMULADOS
Reintegro por fórmula polinómica 0.00 0.00 0.00
Reajuste que no corresponde por Adelanto Directo - Valorización No. 01 0.00 0.00 0.00
Deductivo por adelanto Materiales 0.00 0.00 0.00
TOTAL (B) 0.00 0.00 0.00
C AMORTIZACION
C1 POR ADELANTO DIRECTO (0.00 %) 0.00 0.00 0.00 0.00 0.00
C2 POR ADELANTO DE MATERIALES 0.00 0.00 0.00 0.00 0.00
C3 POR FIEL CUMPLIMIENTO (0.00%) 0.00 0.00 0.00 0.00
TOTAL (C ) 0.00 0.00 0.00 0.00 0.00
Valorización Neta (A+B-C) 0.00 8,410.29 8,410.29

MONTO DE LA VALORIZACION (SIN IGV) S/. - 8,410.29 8,410.29 1,599,837.16

IMPUESTO GENERAL A LAS VENTAS (I.G.V) ( 18% ) S/. 0.00 1,513.85 1,513.85 287,970.69
MONTO TOTAL DE LA VALORIZACION POR FACTURAR S/. 9,924.14 1,887,807.85
MONTO NETO A PAGAR AL CONTRATISTA VALORIZACION ACTUAL S/. - 9,924.14

SON:

NOTA:
*

*
RESUMEN DE CONTROL DE VALORIZACIONES - MES SEPTIEMBRE 2020

SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN –
Proyecto: YERBA BUENA - CP. PIOBAMBA”

Contratista: AMOVER CONTRATISTAS GENERALES E.I.R.L.


Inspector de Servicio ING. LENIN ESPINOZA SILVA

Total Reajuste Valorización Retención por Amortización Valorización I.G.V. Total


Monto (S/.) Bruta fiel cumlimiento por Adelanto Neta Valorización
Neta
PROCEDIMIENTO DE SELECCION. Nº DISTRITO Valoriz. Valoriz (+) (S/.) y adelanto Materiales (S/.) (S/.) (+) (S/.)
Acumulada
(S/.) directo (S/.) (-) (S/.)
(S/.) (-)
SUCRE -
PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
OXAMARCA
01 8,410.29 0.00 8,410.29 0.00 0.00 8,410.29 8,410.29 1,513.85 9,924.15
SUCRE -
PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
OXAMARCA
02 0.00 0.00 0.00 0.00 0.00 0.00
SUCRE -
PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
OXAMARCA
03 0.00 0.00 0.00 0.00 0.00 0.00
SUCRE -
PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS
OXAMARCA
04 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL 8,410.29 0.00 8,410.29 0.00 0.00 8,410.29 1,513.85 9,924.14


CRONOGRAMA VALORIZADO DE SERVICIO

MANTENIMIENTO PERIODICO Y RUTINARIO DEL CAMINO VECINAL TRAMO: EMP. PE 08 B (CP. VIGASPAMPA) - MINASCONGA - COCÁN - YERBA BUENA - CP. PIOBAM

MES 1(SET) MES 2 (OCT) MES 3 (NOV)


Item Descripción Und. Metrado Precio S/. Parcial S/.
S/ % S/ % S/
01 OBRAS PRELIMINARES 32,982.55
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1 15100.33 15,100.33 15,100.33 100.00%

01.02 TRAZO Y REPLANTEO km 33.53 533.32 17,882.22 17882.22 100.00%


02 PAVIMENTOS 852,624.40
02.01 CAPA NIVELANTE E=0.05m m3 7002.5 30.44 213,156.10 112351.03 52.71% 100805.07
3
2.02 MATERIAL GRANULAR DE CANTERA E=0.15m m 21007.5 30.44 639,468.30 150178.16
03 TRANSPORTE 320,449.63
03.01 TRANSPORTE DE MATERIAL GRANULAR D<=1 km m3km 19934.11 7.46 148,708.46 148708.46 100.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR D>1 km m3km 66677.65 2.43 162,026.69 143798.69 88.75% 18228
03.03 TRANSPORTE DE MATERIAL EXCEDENTE D<=1 km m3km 1121.11 7.34 8,228.95
03.04 TRANSPORTE DE MATERIAL EXCEDENTE D>1 km m3km 544.15 2.73 1,485.53
04 OBRAS DE ARTE Y DRENAJE 177,709.00
04.01 RECONFORMACIÓN DE CUNETAS m 33530 5.3 177,709.00 153027.19
05 SEÑALIZACION 38,521.32
05.01 INSTALACIÓN DE POSTES KILOMETRICO und 34 257.82 8,765.88 7548.4
6.01 SEÑALES PREVENTIVAS und 40 465.39 18,615.60 4809.03
6.02 SEÑALES REGLAMENTARIAS und 7 862.56 6,037.92 6037.92
6.03 SEÑALES INFORMATIVAS und 6 850.32 5,101.92 5101.92
06 IMPACTO AMBIENTAL 20,283.19
6.01 RECUPERACIÓN AMBIENTAL DE AREAS OCUPADAS ha 2.31 8780.6 20,283.19
07 EMERGENCIA SANITARIA 1,202.77
7.01 EMERGENCIA SANITARIA COVID 19 glb 1 1202.77 1,202.77 676.55 56.25% 482.77
COSTO DIRECTO 1,443,772.86 15,100.33 423,416.95 446,218.46
6.39200% GASTOS GENERALES (6.392%) 92,285.96 965.21 27,064.81 28,522.28
5.00000% UTILIDAD (5%) 72,188.64 755.02 21,170.85 22,310.92
---------------- ----------------- ----------------- ---------
SUB TOTAL 1,608,247.47 16,820.56 471,652.61 497,051.67
18.00000% IMPUESTO GENERAL A LAS VENTAS(18%) 289,484.54 3,027.70 84,897.47 89,469.30
========
TOTAL PRESUPUESTO 1,897,732.01 19,848.26 556,550.08 586,520.97
AVANCE PROGRAMADO VALORIZADO 1.05% 29.33% 30.91%
AVANCE PROGRAMADO VALORIZADO ACUMULADO 1.05% 30.37% 61.28%
GRAMA VALORIZADO DE SERVICIO

MO: EMP. PE 08 B (CP. VIGASPAMPA) - MINASCONGA - COCÁN - YERBA BUENA - CP. PIOBAMBA

MES 3 (NOV) MES 4 (DIC)

% S/ %

47.29%

23.48% 489,290.14 76.52%

11.25%
8228.95 100.00%
1485.53 100.00%

86.11% 24,681.81 13.89%

86.11% 1,217.48 13.89%


25.83% 13806.57 74.17%
100.00%
100.00%

20,283.19 100.00%

40.14% 43.43 3.61%


559,037.11
35,733.65
27,951.86
---------
622,722.62
112,090.07

734,812.69
38.72%
100.00%
CURVA "S"

SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) -
OBRA: MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA”

CONTRATISTA : AMOVER CONTRATISTAS GENERALES E.I.R.L.


Inspector de Servicio ING. LENIN ESPINOZA SILVA

CURVA PROGRAMADO VS. EJECUTADO


120.00%

98.95%
100.00%

80.00%

60.23%
60.00% Row 39
Row 35

40.00%
29.33%

20.00%

1.05%
0.52%
0.00%
SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

-20.00%

ENE.2016 FEB.2016 MAR.2016

COSTO DIRECTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE TOTAL


TOTAL PROGRAMADO S/IGV (CD) 16820.56 471652.61 497051.67 622722.62 1,608,247.45
AVAN. MENS. PROGRAMADO (%)-CD 1.05% 29.33% 30.91% 38.72% 100.00%
AVAN. ACUM. PROGRAMADO (CD) 16,820.56 488,473.17 985,524.84 1,608,247.45
AVAN. ACUM. PROGRAMADO (%) -CD 1.05% 29.33% 60.23% 98.95%
TOTAL VALORIZADO S/IGV - CD 8,410.29 8,410.29
AVANCE MENSUAL VALORIZ. -CD 0.52%
AVAN. ACUM. VALORIZADO - CD 8,410.29
AVANCE ACUM. VALORIZADO - CD 0.52%
GRAFICOS SOBRE EL AVANCE DE OBRA

AVANCES MENSUALES
SEPT. 2020 OCT.2020 NOV.2020 DIC. 2021 Total

REAL 0.52% 0.52%

PROGRAMADO 1.05% 29.33% 30.91% 38.72% 100.00%

AVANCES ACUMULADOS
SEPT. 2020 OCT.2020 NOV.2020 DIC. 2021

ACUMULADO REAL 0.52%


ACUM. PROGRAMADO 1.05% 30.37% 61.28% 100.00%

GRAFICO DE AVANCES FISICOS ACUMULADOS

120.00%

100.00%
100.00%

80.00%

61.28%
60.00%

40.00%

30.37%

20.00%

1.05%
0.00522947128467
0.00%
SEPT. 2020

OCT.2020

NOV.2020

DIC. 2021

REAL PROGRAMADO
CONTROL DEL AVANCE FINANCIERO

CONTROL DEL ADELANTO DIRECTO

Monto del adelanto directo con IGV = S/. 0.00


Monto del adelanto directo sin IGV = S/. 0.00 (A)
Fecha de pago del adel. Directo = No se solicito

A continuación se presenta en el siguiente cuadro, las amortizaciones que se vienen realizando:


ADELANTO AMORTIZADO
VALORIZACION Nº MES-AÑO S/.
(SIN IGV)
01 30-Sep-20 0.00
02 31-Oct-20
03 30-Nov-20
04 31-Dec-20
04 30-Dec-99
05 30-Dec-99
TOTAL AMORTIZADO (B) 0.00
SALDO POR AMORTIZAR (A-B) 0.00

CONTROL DE VALORIZACIONES

Monto del Mes


ESPECIALIDAD Contrato Anterior Acumulado Saldo
sin IGV Actual
MANTENIMIENTO PERIÓDICO 1,608,247.46 0.00 8,410.29 8,410.29 1,599,837.18
SUB-TOTAL 1,608,247.46 0.00 8,410.29 8,410.29 1,599,837.18
IMPUESTO IGV 18% 289,484.54 0.00 1,513.85 1,513.85 287,970.69
TOTAL S/. 1,897,732.01 0.00 9,924.14 9,924.14 1,887,807.87

CONTROL DEL ADELANTO PARA MATERIALES


Monto del adelanto materiales con IGV = S/. 0.00
Monto del adelanto materiales sin IGV = S/. 0.00 (A)
Fecha de pago del adel. Materiales = No se Solicito

A continuación se presenta en el siguiente cuadro, las amortizaciones que se vienen realizando:


ADELANTO AMORTIZADO
VALORIZACION Nº MES-AÑO S/.
(SIN IGV)
01 30-Sep-20 0.00
02 31-Oct-20 0.00
03 30-Nov-20
04 31-Dec-20
04 30-Dec-99
05 30-Dec-99
TOTAL AMORTIZADO (B) 0.00
SALDO POR AMORTIZAR (A-B) 0.00
REPORTE DE PAGOS EFECTUADOS AL CONTRATISTA

FECHA DE MONTO TOTAL


CONCEPTO CANCELACION SIN IGV

ADELANTO DIRECTO 30-Dec-99 S/. 0.00


ADELANTO MATERIALES AÚN NO SOLICITA S/. 0.00
VALORIZACION Nº 01 LA PRESENTE S/. 8,410.29

TOTAL CANCELADO S/. 8,410.29


EN LOS MONTOS PAGADOS PARA VALORIZACIONES, SE CONSIDERA PARA EL PRESENTE CUADRO:
VALORIZACION NETA = VALORIZACION BRUTA + REAJUSTES - AMORTIZACION DE ADELANTOS

DETERMINACION DEL AVANCE FINANCIERO


TOTAL DE PAGOS EFECTUADOS SIN IGV S/. 8,410.29 (A)
MONTO DEL CONTRATO SIN IGV S/. 1,608,247.46 (B)

% AVANCE FINANCIERO = (A/B) x 100 = 0.52%

COMPARACION ENTRE EL AVANCE FISICO Y EL FINANCIERO

AVANCE FISICO = 0.52%


AVANCE FINANCIERO = 0.52%

0.52%

0.52%

AVANCE FISICO AVANCE FINANCIERO


MUNICIPALIDAD PROVINCIAL DE CELENDIN

GERENCIA MUNICIPAL
GERENCIA DE INFRAESTRUCTURA

Procedimiento de Selecció : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS


Proyecto :
SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO
VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP.
PIOBAMBA”

EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA -


Ubicación
: CP. PIOBAMBA

Inspector de Servicio : ING. LENIN ESPINOZA SILVA


Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.

VALORIZACIÓN DE OBRA N° 01
(del 28 al 30 de setiembre del 2020)
MUNICIPALIDAD DISTRITAL DE HUASMÍN

GERENCIA MUNICIPAL
SUB GERENCIA DE INFRAESTRUCTURA

Procedimiento de Selección : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS


Proyecto :
SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO
VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP.
PIOBAMBA”

Ubicación : EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA BUENA - CP. PIOBAMBA
Supervisor : ING. LENIN ESPINOZA SILVA
Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.

INFORME Y VALORIZACIÓN DE SUPERVISIÓN N° 01


(del 28 al 30 de setiembre del 2020)
MUNICIPALIDAD PROVINCIAL DE CELENDIN

GERENCIA MUNICIPAL
GERENCIA DE INFRAESTRUCTURA

L.P. N° : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS


Proyecto :

SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL


CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA
BUENA - CP. PIOBAMBA”

Ubicación : HUASMIN - CELENDIN - CAJAMARCA


Supervisor de Obra : ING. LENIN ESPINOZA SILVA
Residente : ING. LÁZARO ENCARNACIÓN TERRONES VÁSQUEZ
Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.

VALORIZACIÓN DE OBRA N° 01
(del 28 al 30 de setiembre del 2020)

MUNICIPALIDAD PROVINCIAL DE CELENDIN

GERENCIA MUNICIPAL
GERENCIA DE INFRAESTRUCTURA

L.P. N° : PROCEDIMIENTO ESPECIAL DE SELECCIÓN N° 007-2020-MPC/CS


Proyecto :

SERVICIO PARA LA EJECUCIÓN DE MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL


CAMINO VECINAL "EMP. PE 08 B (CP VIGASPAMPA) - MINASCONGA – COCÁN – YERBA
BUENA - CP. PIOBAMBA”

Ubicación : HUASMIN - CELENDIN - CAJAMARCA


Supervisor de Obra : ING. LENIN ESPINOZA SILVA
Residente : ING. LÁZARO ENCARNACIÓN TERRONES VÁSQUEZ
Contratista : AMOVER CONTRATISTAS GENERALES E.I.R.L.

INFORME Y VALORIZACIÓN DE SUPERVISIÓN N° 01


(del 28 al 30 de setiembre del 2020)