Cliente: TORRE SUR Obra: Remodelación departamentos Torre Sur:

Concurso No. LICITACIÓN Departamento #1051, 117 M2

GASCA & NAVARRO, S.A. DE R.L. Departamento #1052, 120 M2

Departamento #2052, 93 M2

Departamento #4253, 113 M2


Lugar: Av. bra: ###IX RLOPySRM

CRONOGRAMA DE OBRA
DEPARTAMENTOS
MARZO ABRIL MAYO JUNIO JULIO AGOSTO
Semana 1 Semana 2 Semana 3 Semana 4 Semana 1 Semana 2 Semana 3 Semana 4 Semana 1 Semana 2 Semana 3 Semana 4 Semana 1 Semana 2 Semana 3 Semana 4 Semana 1 Semana 2 Semana 3 Semana 4 Semana 1 Semana 2 Semana 3 Semana 4
Concepto L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L MM J V S L M M J V S

PROGRAMA DE PROYECTO
DEPTO 1
DEPTO 2
DEPTO 3
DEPTO 4
DEPTO 4
DEPTO 5
DEPTO 6
DEPTO 7
DEPTO 8
DEPTO 9
DEPTO 10
DEPTO 11
DEPTO 12
DEPTO 13
DEPTO 14
DEPTO 15
DEPTO 16
DEPTO 17
DEPTO 18
DEPTO 19
DEPTO 20
DEPTO 21
DEPTO 22
DEPTO 23
DEPTO 24
DEPTO 25
DEPTO 26
DEPTO 28
DEPTO 29
DEPTO 30
DEPTO 31
DEPTO 32
DEPTO 33
DEPTO 34
DEPTO 35
DEPTO 36
DEPTO 37
DEPTO 38
DEPTO 39
DEPTO 40
DEPTO 41
DEPTO 42
DEPTO 43
DEPTO 44
DEPTO 45
DEPTO 46
DEPTO 47
DEPTO 48
DEPTO 49
DEPTO 50
DEPTO 51
DEPTO 52
DEPTO 53
DEPTO 54
DEPTO 55
PROGRAMA DE OBRA
DEPTO 1
DEPTO 2
DEPTO 3
DEPTO 4
DEPTO 4
DEPTO 5
DEPTO 6
DEPTO 7
DEPTO 8
DEPTO 9
DEPTO 10
DEPTO 11
DEPTO 12
DEPTO 13
DEPTO 14
DEPTO 15
DEPTO 16
DEPTO 17
DEPTO 18
DEPTO 19
DEPTO 20
DEPTO 21
DEPTO 22
DEPTO 23
DEPTO 24
DEPTO 25
DEPTO 26
DEPTO 28
DEPTO 29
DEPTO 30
DEPTO 31
DEPTO 32
DEPTO 33
DEPTO 34
DEPTO 35
DEPTO 36
DEPTO 37
DEPTO 38
DEPTO 39
DEPTO 40
DEPTO 41
DEPTO 42
DEPTO 43
DEPTO 44
DEPTO 45
DEPTO 46
DEPTO 47
DEPTO 48
DEPTO 49
DEPTO 50
DEPTO 51
DEPTO 52
DEPTO 53
DEPTO 54
DEPTO 55

CONSIDERACIONES:
SE TRABAJARA DE LUNES A SABADO EN UN HORARIO DE LUN A VIE DE 8:00 AM A 6:00 PM, SABADOS DE 8:AM A 1:00 PM
NO SE CONSIDERAN DIAS FESTIVOS DENTRO DEL CALENDARIO DE TRABAJO
EL TIEMPO DE DURACION DE LA OBRA SERA DE 6 MESES
INICIO DE OBRA: MARZO DEL 2024
TERMINO DE OBRA: AGOSTO DEL 2024
CRONOGRAMA DE OBRA
DEPARTAMENTOS
MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE
Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8 Semana 9 Semana 10 Semana 11 Semana 12 Semana 13 Semana 14 Semana 15 Semana 16 Semana 17 Semana 18 Semana 19 Semana 20 Semana 21 Semana 22 Semana 23 Semana 24 Semana 25 Semana 26 Semana 27 Semana 28
Concepto L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L MM J V S L M M J V S L M M J V S L M M J V S L M M J V S L MM J V S L M M J V S L M M J V S L M M J V S L M M J V S
27 28 29 30 31 1 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19 20 21 22 24 25 26 27 28 29 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27 29 30 31 1 2 3 5 6 7 8 9 10 12 13 14 15 16 17 19 20 21 22 23 24 26 27 28 29 30 1 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19 20 21 22 24 25 26 27 28 29 31 1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 ### 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6 7
CD1.2 Proyecto
CD1.21 MemoriaEjecutivo.
descriptiva.

CD1.211 Descripción de terreno.


CD1.212 Estudios de ALTA Survey
CD1.213 Especificaciones técnicas de la construcción
CD1.214 Descripción arquitectónica de proyecto.
CD1.22 Planos (arquitectónicos, ingenierías).
CD1.221 Arquitectónicos
CD1.222 Estructurales.
CD1.223 Eléctricos
CD1.224 Sanitarios.
CD1.225 Acabados
CD1.226 CCTV Internet, voz y datos.
CD1.23 Presupuesto
CD1.231 Catalogo de conceptos.
CD1.232 Matrices de precios unitarios.
CD1.234 Otros costos
CD1.235 FASAR.
CD1.236 Explosión de insumos ( materiales, mano de
obra y equipo y herramienta).
CD1.24Información adicional
CD1.241 Fichas técnicas
CD1.242Guías mecánicas.
CD1.243 Acabados
CD1.25 Programa de obra.
CD1.3 Construcción
CD1.31 Preliminares
CD1.312 Limpieza.
CD1.313 Trazo y nivelación.
CD1.32 Cimentación.
CD1.321 Excavación.
CD1.322 Acero
CD1.323 Cimbra
CD1.324 Concreto
CD1.33 Estructura planta baja y alta
CD1.331 Muros PLANTA BAJA PLANTA ALTA
CD1.332 Castillos PLANTA BAJA PLANTA ALTA
CD1.334 Cadenas PLANTA BAJA PLANTA ALTA
CD1.34 Losas planta alta y baja.
CD1.341 Cimbra PLANTA BAJA PLANTA ALTA
CD1.342 Acero PLANTA BAJA PLANTA ALTA
CD1.343 Concreto PLANTA BAJA PLANTA ALTA
CD1.35 Instalaciones planta alta y baja.
CD1.351 Eléctricas PLANTA BAJA PLANTA ALTA
CD1.352 Hidráulicas PLANTA BAJA PLANTA ALTA
CD1.353 Sanitarias PLANTA BAJA PLANTA ALTA
CD1.354 Especiales PLANTA BAJA PLANTA ALTA
CD1.36 Acabados interiores y exteriores.
CD1.361 Pintura
CD1.362 Puertas
CD1.363 Pisos
CD1.364 Yeso
CD1.365 Apagadores
CD1.37 Mobiliario.
CD1.38 Obras exteriores
CD1.381 Jardinería
CD1.382 Guarniciones
CD1.383 Alberca
CD1.384 Estacionamiento
CD1.385 Barda perimetral

CONSIDERACIONES:
SE TRABAJARA DE LUNES A SABADO EN UN HORARIO DE LUN A VIE DE 8:00 AM A 6:00 PM, SABADOS DE 8:AM A 1:00 PM
NO SE CONSIDERAN DIAS FESTIVOS DENTRO DEL CALENDARIO DE TRABAJO
EL TIEMPO DE DURACION DE LA OBRA SERA DE 6 MESES
INICIO DE OBRA: 27 DE MARZO DEL 2023
TERMINO DE OBRA: 07 DE OCTUBRE DEL 2023