C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A

OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI : 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2019 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 28 DE FEBRERO - 2019 DEL 01 AL 31 DE MARZO - 2019 DEL 01 AL 30 DE ABRIL - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 15 21 23 25 27 28 1 3 5 7 15 23 25 27 29 31 1 3 5 7 15 23 25 27 29 30 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.

01 PAVIMENTACION 245.00 SUSPENSIÓN DE OBRA 2,141,532.09 2,141,532.09

01.01 OBRAS PROVISIONALES 3.00 SUSPENSIÓN DE OBRA 5,093.22


1,593.22
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.00 SUSPENSIÓN DE OBRA 1,593.22
3,500.00
01.01.02 CASETA, ALMACEN Y OFICINA 2.00 SUSPENSIÓN DE OBRA 3,500.00

01.02 OBRAS PRELIMINARES 244.00 SUSPENSIÓN DE OBRA 106,450.07


10,568.94 1,396.25 1,396.25 1,442.79 1,442.79 1,396.25 1,442.79 1,568.87
01.02.01 CONTROL TOPOGRAFICO DURANTE LA EJEC 200.00 SUSPENSIÓN DE OBRA 20,654.93
49,222.69 29,145.00 3,650.78 3,776.67
01.02.02 DEMOLICION DE PAVIMENTO DE CONCRETO 59.00 SUSPENSIÓN DE OBRA 85,795.14

01.03 MOVIMINETO DE TIERRAS 59.00 SUSPENSIÓN DE OBRA 281,010.91


15,498.83 7,497.60 13,017.84 13,466.74 16,926.51
01.03.01 CORTE A NIVEL DE SUBRASANTE PARA PAV 59.00 SUSPENSIÓN DE OBRA 66,407.52
11,475.33 27,295.58 28,236.81 2,621.47
01.03.02 CONFORMACION Y COMPACTACION DE SUB 59.00 SUSPENSIÓN DE OBRA 69,629.19
52,055.30 27,156.00 31,731.20 32,825.38 1,206.32
01.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON 59.00 SUSPENSIÓN DE OBRA 144,974.20

01.04 PAVIMENTO RIGIDO 125.00 SUSPENSIÓN DE OBRA 1,653,132.28


10,905.89 13,087.07 4,362.36
NIVELACION DE BUZONES AL NIVEL DE RASANTE EN PAVIMENTOS
01.04.01 65.00 SUSPENSIÓN DE OBRA 28,355.32
42,593.63 29,799.42 59,598.84 61,585.46 61,585.46 37,745.93 11,459.14
01.04.02 MEJORAMIENTO DE SUB RASANTE e=20cm, 126.00 SUSPENSIÓN DE OBRA 304,367.88
9,478.00 71,535.00 73,919.50 73,919.50 71,535.00 38,151.99 13,244.29
01.04.03 BASE GRANULAR e=20cm, EXTENDIDO, BATI 138.00 SUSPENSIÓN DE OBRA 351,783.28
62,746.59 194,514.43 194,514.43 188,239.77 194,514.43 50,197.26 34,612.19
01.04.04 CONCRETO EN PAVIMENTO RÍGIDO f'c= 21 k 141.00 SUSPENSIÓN DE OBRA 919,339.10
4,936.83 9,565.11 9,565.11 9,256.56 9,565.11 1,851.30
01.04.05 ENCOFRADO Y DESENCOFRADO EN PAVIMEN 145.00 SUSPENSIÓN DE OBRA 44,740.02
310.32 961.99 961.99 930.96 961.99 248.25 171.18
01.04.06 CURADO DE CONCRETO 141.00 SUSPENSIÓN DE OBRA 4,546.68

01.05 JUNTAS DE DILATACIÓN EN PAVIMEN 28.00 SUSPENSIÓN DE OBRA 58,986.04


25,121.61 16,255.16
JUNTAS DE DILATACIÓN ASFÁLTICA EN PAVIMENTO RÍGIDO
01.04.01 28.00 SUSPENSIÓN DE OBRA 41,376.77
17,609.27
01.04.02 DOWELLS EN LOSAS RÍGIDAS - JUNTA DE 0.00 SUSPENSIÓN DE OBRA 17,609.27

01.06 SEÑALIZACION HORIZONTAL 31.00 SUSPENSIÓN DE OBRA 36,859.57


9,864.94 9,864.93
01.04.04 PINTURA TRÁFICO EN PAVIMENTOS - LINEA 28.00 SUSPENSIÓN DE OBRA 19,729.87
6,729.53 10,400.17
01.04.05 PINTADO DE PAVIMENTOS (SIMBOLOS Y LET 28.00 SUSPENSIÓN DE OBRA 17,129.70

02.00 VEREDAS 47.00 SUSPENSIÓN DE OBRA 615,704.95 615,704.95

02.01 TRABAJOS PRELIMINARES 15.00 SUSPENSIÓN DE OBRA 10,202.12


4,826.48 3,853.56 1,522.08
02.01.01 CONTROL TOPOGRAFICO DURANTE LA EJEC 15.00 SUSPENSIÓN DE OBRA 10,202.12

02.02 DEMOLICIONES 6.00 SUSPENSIÓN DE OBRA 29,375.66


13,798.63 13,974.03 1,603.00
02.02.01 DEMOLICIÓN DE VEREDAS E=10CM 6.00 SUSPENSIÓN DE OBRA 29,375.66

02.03 MOVIMIENTO DE TIERRAS 21.00 SUSPENSIÓN DE OBRA 180,305.44


2,678.40 9,905.06 3,601.14 6,687.82 13,856.31
02.03.01 CONFORMACIÓN Y COMPACTACIÓN PARA 20.00 SUSPENSIÓN DE OBRA 36,728.73
42,260.57 10,366.41 24,188.28 46,535.36
02.03.02 BASE COMPACTADA PARA VEREDAS DE 4" 20.00 SUSPENSIÓN DE OBRA 123,350.62
6,836.62 8,670.58 4,718.89
02.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON 1.00 SUSPENSIÓN DE OBRA 20,226.09

02.04 CONCRETO SIMPLE 27.00 SUSPENSIÓN DE OBRA 354,394.61


3,755.44
02.04.01 NIVELACIÓN DE LAS CAJAS DE REGISTRO D 0.00 SUSPENSIÓN DE OBRA 3,755.44
9,585.36 6,512.49 2,342.68
02.04.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS 18.00 SUSPENSIÓN DE OBRA 18,440.53
132,859.99 104,689.99 92,344.96
02.04.03 VEREDAS DE CONCRETO F'c=175 KG/CM2, 20.00 SUSPENSIÓN DE OBRA 329,894.94
787.54 646.98 869.18
02.04.04 CURADO DE VEREDA DE CONCRETO 23.00 SUSPENSIÓN DE OBRA 2,303.70

02.05 JUNTAS DE DILATACIÓN EN VEREDAS 15.00 SUSPENSIÓN DE OBRA 9,137.90


9,137.90
02.05.01 JUNTAS ASFÁLTICAS DE DILATACIÓN PARA 15.00 SUSPENSIÓN DE OBRA 9,137.90

02.06 SEÑALIZACION HORIZONTAL EN VER 20.00 SUSPENSIÓN DE OBRA 32,289.22


16,144.61 16,144.61
02.06.01 PINTURA EN VEREDAS 20.00 SUSPENSIÓN DE OBRA 32,289.22

03.00 MURO DE CONTENCION 0.00 SUSPENSIÓN DE OBRA 119,066.81 119,066.81

03.01 TRABAJOS PRELIMINARES 0.00 SUSPENSIÓN DE OBRA 279.50


196.30
03.01.01 LIMPIEZA DE TERRENO MANUAL 0.00 SUSPENSIÓN DE OBRA 196.30
83.20
03.01.02 TRAZO Y REPLANTEO EN MURO DE CONTE 0.00 SUSPENSIÓN DE OBRA 83.20

03.02 MOVIMIENTO DE TIERRAS 0.00 SUSPENSIÓN DE OBRA 16,799.03


5,947.11
03.02.01 EXCAVACIÓN MANUAL PARA MUROS DE CO 0.00 SUSPENSIÓN DE OBRA 5,947.11
1,286.37
03.02.02 RELLENO CON MATERIAL PROPIO SELECCI 0.00 SUSPENSIÓN DE OBRA 1,286.37
5,267.76
03.02.03 DEMOLICIÓN DE MUROS EXISTENTES 0.00 SUSPENSIÓN DE OBRA 5,267.76
4,297.79
03.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON 0.00 SUSPENSIÓN DE OBRA 4,297.79

03.03 CONCRETO SIMPLE 0.00 SUSPENSIÓN DE OBRA 876.07


876.07
03.03.01 CONCRETO 1:8 PARA SOLADOS Y/O SUB BA 0.00 SUSPENSIÓN DE OBRA 876.07

03.04 CONCRETO ARMADO 0.00 SUSPENSIÓN DE OBRA 100,951.21


71,711.82
03.04.01 CONCRETO EN MUROS DE CONTENCION F'c = 0.00 SUSPENSIÓN DE OBRA 71,711.82
19,950.11
03.04.02 ACERO Fy = 4200KG/cm2 GRADO 60 0.00 SUSPENSIÓN DE OBRA 19,950.11
9,289.28
03.04.03 ENCOFRADO Y DESENCOFRADO EN MUROS 0.00 SUSPENSIÓN DE OBRA 9,289.28

03.05 JUNTAS ASFALTICAS 0.00 SUSPENSIÓN DE OBRA 161.00


161.00
03.05.01 JUNTAS ASFÁLTICAS DE DILATACIÓN 0.00 SUSPENSIÓN DE OBRA 161.00

04.00 MUROS DE PROTECCION EN VEREDAS 15.00 SUSPENSIÓN DE OBRA 378,444.46 378,444.46

04.01 TRABAJOS PRELIMINARES 2.00 SUSPENSIÓN DE OBRA 2,539.12


1,081.69 320.00 1,137.43
04.01.01 TRAZO Y REPLANTEO EN SARDINELES 2.00 SUSPENSIÓN DE OBRA 2,539.12

04.02 MOVIMIENTO DE TIERRAS 8.00 SUSPENSIÓN DE OBRA 22,658.37


1,197.87 5,848.22 7,575.00
04.02.01 EXCAVACIÓN MANUAL PARA SARDINELES 7.00 SUSPENSIÓN DE OBRA 14,621.09
633.14 3,240.12 4,164.02
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON 1.00 SUSPENSIÓN DE OBRA 8,037.28

04.03 CONCRETO ARMADO 10.00 SUSPENSIÓN DE OBRA 353,246.97


68,835.04 45,303.61 93,374.49
04.03.01 CONCRETO EN SARDINELES F'c = 210 kg/cm2 7.00 SUSPENSIÓN DE OBRA 207,513.14
26,514.51 12,760.01 54,241.48
04.03.02 ENCOFRADO Y DESENCOFRADO EN SARDIN 7.00 SUSPENSIÓN DE OBRA 93,516.00
11,308.54 9,260.00 31,649.29
04.03.03 ACERO Fy = 4200KG/cm2 GRADO 60 7.00 SUSPENSIÓN DE OBRA 52,217.83

05.00 SEGURIDAD VIAL Y MITIGACIÓN AM 200.00 SUSPENSIÓN DE OBRA 1,675.47 1,675.47


99.00 880.00 104.47 104.47 107.95 107.95 104.47 107.95 59.21
05.01 MITIGACION DE IMPACTO AMBIENTAL 200.00 SUSPENSIÓN DE OBRA 1,675.47
C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A
OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI : 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2019 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 28 DE FEBRERO - 2019 DEL 01 AL 31 DE MARZO - 2019 DEL 01 AL 30 DE ABRIL - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 15 21 23 25 27 28 1 3 5 7 15 23 25 27 29 31 1 3 5 7 15 23 25 27 29 30 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.

06.00 VARIOS 59.00 SUSPENSIÓN DE OBRA 126,101.87 126,101.87


29,619.38 18,134.31 6,239.43 6,454.59
06.01 MOVILIZACION Y DESMOVILIZACION DE MAQ 59.00 SUSPENSIÓN DE OBRA 60,447.71
6,565.42 45,301.37 6,776.84 7,010.53
06.02 FLETE TERRESTRE 59.00 SUSPENSIÓN DE OBRA 65,654.16

COSTO DIRECTO TOTAL 260,409.87 463,337.20 0.00 0.00 0.00 144,885.25 556,548.01 362,604.20 342,097.23 309,208.94 286,460.34 656,974.61 3,382,525.65
GASTOS GENERALES 5.00 % 13,020.49 23,166.86 0.00 0.00 0.00 7,244.26 27,827.40 18,130.21 17,104.86 15,460.45 14,323.02 32,848.73 169,126.28
UTILIDADES 10.00 % 26,040.99 46,333.72 0.00 0.00 0.00 14,488.53 55,654.80 36,260.42 34,209.72 30,920.89 28,646.03 65,697.46 338,252.57
SUB TOTAL 299,471.35 532,837.78 0.00 0.00 0.00 166,618.04 640,030.21 416,994.83 393,411.81 355,590.28 329,429.39 755,520.80 3,889,904.50
I.G.V. 18.00 % 53,904.84 95,910.80 0.00 0.00 0.00 29,991.25 115,205.44 75,059.07 70,814.13 64,006.25 59,297.29 135,993.74 700,182.81
DESEMBOLSO PARCIAL PROGRAMADO S/. 353,376.19 628,748.58 0.00 0.00 0.00 196,609.29 755,235.65 492,053.90 464,225.94 419,596.53 388,726.68 891,514.55 4,590,087.31
DESEMBOLSO ACUMULADO PROGRAMADO S/. 353,376.19 982,124.77 0.00 0.00 0.00 1,178,734.06 1,933,969.71 2,426,023.61 2,890,249.55 3,309,846.08 3,698,572.76 4,590,087.31
C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A
OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI : 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2019 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 28 DE FEBRERO - 2019 DEL 01 AL 31 DE MARZO - 2019 DEL 01 AL 30 DE ABRIL - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 15 21 23 25 27 28 1 3 5 7 15 23 25 27 29 31 1 3 5 7 15 23 25 27 29 30 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.

C R O N O G R A M A D E A V A N C E D E O B R A V A L O R I Z A D O-D E A D I C I O N A L D E O B R A
OBRA : ADICIONAL DE OBRA Nº 01 "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PARCOY
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI : 75 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2019 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 28 DE FEBRERO - 2019 DEL 01 AL 31 DE MARZO - 2019 DEL 01 AL 30 DE ABRIL - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 15 21 23 25 27 28 1 3 5 7 15 23 25 27 29 31 1 3 5 7 15 23 25 27 29 30 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.

01.00 RED DE ALCANTARILLADO PLUVIAL 75.00 409,086.47 409,086.47

01.01 TRABAJOS PRELIMINARES 44.00 2,131.84


332.03 527.35
01.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUC 44.00 859.38
1,272.46
01.01.02 DEMOLICION DE CANAL EXISTENTE 1.00 1,272.46

01.02 MOVIMIENTO DE TIERRAS 25.00 87,791.93


6,853.27 4,111.96
01.02.01 EXCAV. ZANJA (MÁQ.) P/TUB. TERR-NORMAL D 8.00 10,965.23
136.66 956.60
01.02.02 REFINE Y NIVELACION DE ZANJA TERR-NORM 8.00 1,093.26
5,852.47
01.02.03 CONFORMACION DE CAMA DE APOYO CON ARE 8.00 5,852.47
60,325.06
01.02.04 RELLENO COMP. ZANJA CON MATERIAL GRANUL 8.00 60,325.06
9,555.91
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON 2.00 9,555.91

01.03 SUMINISTRO E INSTALACION DE TUB 11.00 52,304.21


47,940.23
01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC- 8.00 47,940.23
3,779.82
01.03.02 SUMINISTRO E INSTALACION DE CACHIMBA 3.00 3,779.82
584.16
01.03.03 SUMINISTRO E INSTALACION DE CODO PVC-UF 1.00 584.16

01.04 CONEXIONES DE ALCANTARILLADO 25.00 6,083.47

01.04.01 TRABAJOS PRELIMINARES 15.00 43.23


43.23
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.04.01.01 15.00 43.23

01.04.02 MOVIMIENTO DE TIERRAS 15.00 4,234.64


701.45
01.04.02.01 EXCAV. ZANJA MANUAL/TUB. TERR-NORMAL DN 4.00 701.45
43.55
01.04.02.02 REFINE Y NIVEL DE ZANJA TERR-NORMAL PA 4.00 43.55
318.15
01.04.02.03 CONFORMACION DE CAMA DE APOYO CON AR 4.00 318.15
2,734.16
01.04.02.04 RELLENO COMP. ZANJA CON MATERIAL GRANUL 4.00 2,734.16
437.33
01.04.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON 2.00 437.33

01.04.03 SUMINISTRO E INSTALACION DE TUB 5.00 1,805.60


902.27
RO E INSTALACION DE TUBERIA PVC-U UF NTP ISO 4435 S 20 DN 160 INCL. ANILLO + 2% DESPERDICIOS
01.04.03.01 4.00 902.27
903.33
01.04.03.02 SUMINISTRO E INSTALACION DE CACHIMBA T 2.00 903.33

01.05 CAMARA DE INSPECCION 41.00 86,280.40

01.05.01 TRABAJOS PRELIMINARES 31.00 89.49


63.51 25.98
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.05.01.01 31.00 89.49

01.05.02 MOVIMIENTO DE TIERRAS 15.00 5,122.44


3,271.92
01.05.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMA 8.00 3,271.92
113.85
01.05.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA 8.00 113.85
1,736.67
01.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON 2.00 1,736.67

01.05.03 OBRAS DE CONCRETO SIMPLE 15.00 3,816.97


3,816.97
CONCRETO 1:8 PARA SOLADO E=4"
01.05.03.01 2.00 3,816.97

01.05.04 OBRAS DE CONCRETO ARMADO 15.00 60,646.00


25,920.23
CONCRETO EN CAMARAS DE INSPECCION F'c = 210 kg/cm2
01.05.04.01 7.00 25,920.23
7,928.19 5,946.14
ACERO Fy = 4200KG/cm2 GRADO 60 EN CAMARAS DE INSPECCION
01.05.04.02 7.00 13,874.33
2,978.78 17,872.66
ENCOFRADO Y DESENCOFRADO DE CAMARAS DE INSPECCION
01.05.04.03 7.00 20,851.44

01.05.05 OBRAS DE CONCRETO ARMADO 15.00 16,605.50


3,711.82
TAPA METALICA TIPO I
01.05.05.01 4.00 3,711.82
12,893.68
TAPA METALICA TIPO II
01.05.05.02 12.00 12,893.68

01.06 CUNETA Y PARRILLAS PLUVIALES C 38.00 65,449.79

01.06.01 TRABAJOS PRELIMINARES 28.00 153.73


32.94 120.79
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.06.01.01 28.00 153.73

01.06.02 MOVIMIENTO DE TIERRAS 30.00 4,106.28


510.94 2,043.77
01.06.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMA 10.00 2,554.71
195.57
01.06.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA 10.00 195.57
1,356.00
01.06.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON 4.00 1,356.00

01.06.03 OBRAS DE CONCRETO SIMPLE 10.00 6,557.05


6,557.05
CONCRETO 1:8 PARA SOLADO E=4"
01.06.03.01 10.00 6,557.05

01.06.04 OBRAS DE CONCRETO ARMADO 20.00 29,679.08


18,207.55
CONCRETO EN CUNETA F'c = 210 kg/cm2
01.06.04.01 6.00 18,207.55
7,042.79
ACERO Fy = 4200KG/cm2 GRADO 60 EN CUNETA
01.06.04.02 7.00 7,042.79
4,428.74
ENCOFRADO Y DESENCOFRADO DE CUNETAS
01.06.04.03 8.00 4,428.74

01.06.05 CARPINTERIA METALICA 15.00 24,953.65


24,953.65
PARRILLA METALICA
01.06.05.01 15.00 24,953.65

01.07 RED DE ALCANTARILLADO SECUNDA 29.00 89,151.63

01.07.01 TRABAJOS PRELIMINARES 29.00 595.11


369.38 225.73
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.07.01.01 29.00 595.11

01.07.02 MOVIMIENTO DE TIERRAS 27.00 65,736.52


11,312.85
01.07.02.01 EXCAV. ZANJA MANUAL/TUB. TERR-NORMAL DN 10.00 11,312.85
713.42
01.07.02.02 REFINE Y NIVELACION DE ZANJA TERR-NORM 3.00 713.42
4,422.34
01.07.02.03 CONFORMACION DE CAMA DE APOYO CON AR 3.00 4,422.34
42,637.01
01.07.02.04 RELLENO COMP. ZANJA CON MATERIAL GRANUL 4.00 42,637.01
6,650.90
01.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON 1.00 6,650.90

01.07.03 SUMINISTRO E INSTALACION DE TUB 6.00 22,820.00


16,626.97 5,542.32
SUMINISTRO E INSTALACION DE TUBERIA PVC-U UF NTP ISO 4435 S 20 DN 250 INCL. ANILLO + 2% DESPERDICIOS
01.07.03.01 4.00 22,169.29
253.09
SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø250MM x Ø250MM+CODO DE 45º
01.07.03.02 1.00 253.09
271.09
SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø315MM x Ø250MM+CODO DE 45º
01.07.03.03 1.00 271.09
126.53
C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A
OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI : 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2019 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 28 DE FEBRERO - 2019 DEL 01 AL 31 DE MARZO - 2019 DEL 01 AL 30 DE ABRIL - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 15 21 23 25 27 28 1 3 5 7 15 23 25 27 29 31 1 3 5 7 15 23 25 27 29 30 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.
SUMINISTRO E INSTALACION DE CACHIMBA CODO DE 45 º PVC-UF, ISO 4435 ,Ø250MM
01.07.03.04 1.00 126.53

01.08 CUNETAS PLUVIALES SECUNDARIAS 5.00 4,585.69

01.08.01 TRABAJOS PRELIMINARES 5.00 684.50


39.50
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.08.01.01 5.00 39.50
645.00
DEMOLICION DE CUNETA EXISTENTE
01.08.01.02 1.00 645.00

01.08.02 MOVIMIENTO DE TIERRAS 2.00 197.89


120.89
01.08.02.01 ELIMINACION DE MATERIAL EXCEDENTE CON 1.00 120.89
77.00
01.08.02.02 PERFILADO Y COMPACTADO DE FONDO 1.00 77.00

01.08.03 OBRAS DE CONCRETO SIMPLE 2.00 3,703.30


1,138.20
ENCOFRADO Y DESENCOFRADO EN CUNETAS SECUNDARIAS
01.08.03.01 2.00 1,138.20
2,565.10
CONCRETO EN CUNETAS SECUNDARIAS F'c=175 kg/cm2
01.08.03.02 1.00 2,565.10

01.09 CUNETA PLUVIAL TRIANGULAR 12.00 15,307.51

01.09.01 TRABAJOS PRELIMINARES 5.00 227.52


227.52
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.09.01.01 5.00 227.52

01.09.02 MOVIMIENTO DE TIERRAS 4.00 1,877.42


893.01
01.09.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMA 3.00 893.01
605.22
01.09.02.02 PERFILADO Y COMPACTADO DE FONDO 3.00 605.22
379.19
01.09.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON 1.00 379.19

01.08.03 OBRAS DE CONCRETO SIMPLE 8.00 13,202.57


5,691.00
01.08.03.01 ENCOFRADO Y DESENCOFRADO EN CUNET 3.00 5,691.00
7,103.34
CONCRETO EN CUNETAS SECUNDARIAS F'c=175 kg/cm2
01.08.03.02 3.00 7,103.34
408.23
JUNTA DE DILATACION CON ASFALTO
01.08.03.03 2.00 408.23

02.00 MUROS DE CONTENCION EN VOLADI 75.00 481,532.88 481,532.88

02.01 TRABAJOS PRELIMINARES 61.00 7,779.95


196.43 346.63 161.76
02.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECU 61.00 704.82
7,075.13
02.01.02 DEMOLICION DE MUROS DE CONCRETO EXI 15.00 7,075.13

02.02 MOVIMIENTO DE TIERRAS 61.00 153,184.89


13,204.88 22,346.72
02.03.01 EXCAVACIÓN MANUAL EN TERRENO NORMA 35.00 35,551.60
49,939.43 46,610.13
02.03.02 RELLENO COMPACTADO CON MATERIAL GR 58.00 96,549.56
10,905.38 10,178.35
02.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON 58.00 21,083.73

02.03 CONCRETO SIMPLE 35.00 30,062.01


10,306.97 19,755.04
02.03.01 CONCRETO 1:8 PARA SOLADO E=4" 35.00 30,062.01

02.04 OBRAS DE CONCRETO ARMADO 56.00 290,506.03


22,404.46 96,019.13 48,009.56
02.04.01 CONCRETO EN MUROS DE CONTENCION EN VO 52.00 166,433.15
14,100.35 47,001.17 20,367.17
02.04.02 ACERO fy=4200 kg/cm2 GRADO 60 EN MUR 52.00 81,468.69
6,409.51 24,035.67 11,216.64
02.04.03 ENCOFRADO Y DESENCOFRADO EN MURO D 52.00 41,661.82
126.85 543.68 271.84
02.04.04 JUNTA DE DILATACION VERTICAL EN MUROS 52.00 942.37

03.00 MUROS DE CONTENCION POR GRAVE 45.00 110,801.73 110,801.73

03.01 TRABAJOS PRELIMINARES 45.00 2,480.18


151.56 249.62
03.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECU 45.00 401.18
2,079.00
03.01.02 DEMOLICION DE MUROS DE CONCRETO EXI 5.00 2,079.00

03.02 MOVIMIENTO DE TIERRAS 44.00 27,977.40


4,698.84 4,111.49
03.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMA 30.00 8,810.33
13,840.19
03.02.02 RELLENO COMPACTADO CON MATERIAL GR 10.00 13,840.19
5,326.88
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON 10.00 5,326.88

03.03 CONCRETO SIMPLE 27.00 80,344.15


18,126.54 38,842.57
03.03.01 CONCRETO CICLOPEO F'C=175 KG/CM2+ 30% 22.00 56,969.11
8,109.25 14,191.20
03.03.02 ENCOFRADO Y DESENCOFRADO EN MUROS 22.00 22,300.45
1,074.59
03.03.03 JUNTA DE DILATACION VERTICAL EN MUROS 10.00 1,074.59

04.00 VEREDAS EN VOLADIZOS 32.00 44,200.04 44,200.04

04.01 TRABAJOS PRELIMINARES 13.00 322.95


99.37 223.58
04.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECU 13.00 322.95

04.02 OBRAS DE CONCRETO ARMADO 23.00 43,877.09


16,234.76
04.02.01 CONCRETO F'C=210 KG/CM2 - VEREDA EN V 8.00 16,234.76
14,286.73
04.02.02 ACERO Fy = 4200KG/cm2 GRADO 60 - VERED 7.00 14,286.73
13,196.17
04.02.03 ENCOFRADO Y DESENCOFRADO - VEREDA 10.00 13,196.17
159.43
04.02.04 JUNTA DE CONTRACCION - VEREDA EN VOL 2.00 159.43

05.00 VARIOS 47.00 55,000.00 55,000.00


19,893.62 35,106.38
05.01 TRANSPORTE DE MATERIALES - TRUJILLO A 47.00 55,000.00

COSTO DIRECTO TOTAL 0.00 0.00 0.00 0.00 0.00 101,040.16 534,152.01 465,428.95 0.00 0.00 0.00 0.00 1,100,621.12
GASTOS GENERALES 5.00 % 0.00 0.00 0.00 0.00 0.00 5,052.01 26,707.60 23,271.45 0.00 0.00 0.00 0.00 55,031.06
UTILIDADES 9.00 % 0.00 0.00 0.00 0.00 0.00 9,093.61 48,073.68 41,888.61 0.00 0.00 0.00 0.00 99,055.90
SUB TOTAL 0.00 0.00 0.00 0.00 0.00 115,185.78 608,933.29 530,589.01 0.00 0.00 0.00 0.00 1,254,708.08
I.G.V. 18.00 % 0.00 0.00 0.00 0.00 0.00 20,733.44 109,607.99 95,506.02 0.00 0.00 0.00 0.00 225,847.45
DESEMBOLSO PARCIAL PROGRAMADO S/. 0.00 0.00 0.00 0.00 0.00 135,919.22 718,541.28 626,095.03 0.00 0.00 0.00 0.00 1,480,555.53
DESEMBOLSO ACUMULADO PROGRAMADO S/. 0.00 0.00 0.00 0.00 0.00 135,919.22 854,460.50 1,480,555.53 0.00 0.00 0.00 0.00
C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A
OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI: 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2018 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.

01 PAVIMENTACION 245.00 2,141,532.09 2,141,532.09

01.01 OBRAS PROVISIONALES 3.00 5,093.22


1,593.22
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 8.50X3.60 3.00 1,593.22
3,500.00
01.01.02 CASETA, ALMACEN Y OFICINA 2.00 3,500.00

01.02 OBRAS PRELIMINARES 244.00 106,450.07


10,568.94 1,396.25 1,396.25 1,442.79 1,442.79 1,396.25 1,442.79 1,568.87
01.02.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA 200.00 20,654.93
49,222.69 29,145.00 3,650.78 3,776.67
01.02.02 DEMOLICION DE PAVIMENTO DE CONCRETO DE 20 CM 59.00 85,795.14

01.03 MOVIMINETO DE TIERRAS 59.00 281,010.91


15,498.83 7,497.60 13,017.84 13,466.74 16,926.51
01.03.01 CORTE A NIVEL DE SUBRASANTE PARA PAVIMENTACIÓN 59.00 66,407.52
11,475.33 27,295.58 28,236.81 2,621.47
01.03.02 CONFORMACION Y COMPACTACION DE SUBRASANTE DE PAVIMENTAC 59.00 69,629.19
52,055.30 27,156.00 31,731.20 32,825.38 1,206.32
01.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 KM 59.00 144,974.20

01.04 PAVIMENTO RIGIDO 125.00 1,653,132.28


10,905.89 13,087.07 4,362.36
NIVELACION DE BUZONES AL NIVEL DE RASANTE EN PAVIMENTOS
01.04.01 65.00 28,355.32
42,593.63 29,799.42 59,598.84 61,585.46 61,585.46 37,745.93 11,459.14
01.04.02 MEJORAMIENTO DE SUB RASANTE e=20cm, MATERIAL GRANULAR 126.00 304,367.88
9,478.00 71,535.00 73,919.50 73,919.50 71,535.00 38,151.99 13,244.29
01.04.03 BASE GRANULAR e=20cm, EXTENDIDO, BATIDO, RIEGO Y COMPACTACI 138.00 351,783.28
62,746.59 194,514.43 194,514.43 188,239.77 194,514.43 50,197.26 34,612.19
01.04.04 CONCRETO EN PAVIMENTO RÍGIDO f'c= 21 kg/cm2, FROTACHADO 141.00 919,339.10
4,936.83 9,565.11 9,565.11 9,256.56 9,565.11 1,851.30
01.04.05 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO 145.00 44,740.02
310.32 961.99 961.99 930.96 961.99 248.25 171.18
01.04.06 CURADO DE CONCRETO 141.00 4,546.68

01.05 JUNTAS DE DILATACIÓN EN PAVIMENTO RÍGIDO 28.00 58,986.04


25,121.61 16,255.16
JUNTAS DE DILATACIÓN ASFÁLTICA EN PAVIMENTO RÍGIDO
01.04.01 28.00 41,376.77
17,609.27
01.04.02 DOWELLS EN LOSAS RÍGIDAS - JUNTA DE CONTRACCIÓN 0.00 17,609.27

01.06 SEÑALIZACION HORIZONTAL 31.00 36,859.57


9,864.94 9,864.93
01.04.04 PINTURA TRÁFICO EN PAVIMENTOS - LINEA DISCONTINUA 28.00 19,729.87
6,729.53 10,400.17
01.04.05 PINTADO DE PAVIMENTOS (SIMBOLOS Y LETRAS) 28.00 17,129.70

02.00 VEREDAS 47.00 615,704.95 615,704.95

02.01 TRABAJOS PRELIMINARES 15.00 10,202.12


4,826.48 3,853.56 1,522.08
02.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION 15.00 10,202.12

02.02 DEMOLICIONES 6.00 29,375.66


13,798.63 13,974.03 1,603.00
02.02.01 DEMOLICIÓN DE VEREDAS E=10CM 6.00 29,375.66

02.03 MOVIMIENTO DE TIERRAS 21.00 180,305.44


2,678.40 9,905.06 3,601.14 6,687.82 13,856.31
02.03.01 CONFORMACIÓN Y COMPACTACIÓN PARA SUBRASANTE 20.00 36,728.73
42,260.57 10,366.41 24,188.28 46,535.36
02.03.02 BASE COMPACTADA PARA VEREDAS DE 4" 20.00 123,350.62
6,836.62 8,670.58 4,718.89
02.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 KM 1.00 20,226.09

02.04 CONCRETO SIMPLE 27.00 354,394.61


3,755.44
02.04.01 NIVELACIÓN DE LAS CAJAS DE REGISTRO DE AGUA Y DESAGUE A NIV 0.00 3,755.44
9,585.36 6,512.49 2,342.68
02.04.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS, H=20cm 18.00 18,440.53
132,859.99 104,689.99 92,344.96
02.04.03 VEREDAS DE CONCRETO F'c=175 KG/CM2, ACABADO SEMIPULIDO 20.00 329,894.94
787.54 646.98 869.18
02.04.04 CURADO DE VEREDA DE CONCRETO 23.00 2,303.70

02.05 JUNTAS DE DILATACIÓN EN VEREDAS 15.00 9,137.90


9,137.90
02.05.01 JUNTAS ASFÁLTICAS DE DILATACIÓN PARA VERDAS 15.00 9,137.90

02.06 SEÑALIZACION HORIZONTAL EN VEREDAS 20.00 32,289.22


16,144.61 16,144.61
02.06.01 PINTURA EN VEREDAS 20.00 32,289.22

03.00 MURO DE CONTENCION 0.00 119,066.81 119,066.81

03.01 TRABAJOS PRELIMINARES 0.00 279.50


196.30
03.01.01 LIMPIEZA DE TERRENO MANUAL 0.00 196.30
83.20
03.01.02 TRAZO Y REPLANTEO EN MURO DE CONTENCION 0.00 83.20

03.02 MOVIMIENTO DE TIERRAS 0.00 16,799.03


5,947.11
03.02.01 EXCAVACIÓN MANUAL PARA MUROS DE CONTENCION 0.00 5,947.11
1,286.37
03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO 0.00 1,286.37
5,267.76
03.02.03 DEMOLICIÓN DE MUROS EXISTENTES 0.00 5,267.76
4,297.79
03.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 KM 0.00 4,297.79

03.03 CONCRETO SIMPLE 0.00 876.07


876.07
03.03.01 CONCRETO 1:8 PARA SOLADOS Y/O SUB BASES 0.00 876.07

03.04 CONCRETO ARMADO 0.00 100,951.21


71,711.82
03.04.01 CONCRETO EN MUROS DE CONTENCION F'c = 210 kg/cm2 0.00 71,711.82
19,950.11
03.04.02 ACERO Fy = 4200KG/cm2 GRADO 60 0.00 19,950.11
9,289.28
03.04.03 ENCOFRADO Y DESENCOFRADO EN MUROS DE CONTENCION 0.00 9,289.28

03.05 JUNTAS ASFALTICAS 0.00 161.00


161.00
03.05.01 JUNTAS ASFÁLTICAS DE DILATACIÓN 0.00 161.00

04.00 MUROS DE PROTECCION EN VEREDAS 15.00 378,444.46 378,444.46


C R O N O G R A M A R E P R O G R A M A D O D E A V A N C E D E O B R A V A L O R I Z A D O-D E C O N T R A T O P R I N C I P A L D E O B R A
OBRA : "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCI: 245 DÍAS CALENDARIOS

Nº DEL 15 AL 31 DE DIC - 2018 DEL 01 AL 31 DE ENERO - 2019 DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 DEL 01 AL 31 DE AGOSTO - 2019 DEL 01 AL 30 DE SETIEMBRE - 2019 DEL 01 AL 31 DE OCTUBRE - 2019 DEL 01 AL 30 DE NOVIEMBRE - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 S/. S/.
04.01 TRABAJOS PRELIMINARES 2.00 2,539.12
1,081.69 320.00 1,137.43
04.01.01 TRAZO Y REPLANTEO EN SARDINELES 2.00 2,539.12

04.02 MOVIMIENTO DE TIERRAS 8.00 22,658.37


1,197.87 5,848.22 7,575.00
04.02.01 EXCAVACIÓN MANUAL PARA SARDINELES 7.00 14,621.09
633.14 3,240.12 4,164.02
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 KM 1.00 8,037.28

04.03 CONCRETO ARMADO 10.00 353,246.97


68,835.04 45,303.61 93,374.49
04.03.01 CONCRETO EN SARDINELES F'c = 210 kg/cm2 7.00 207,513.14
26,514.51 12,760.01 54,241.48
04.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES 7.00 93,516.00
11,308.54 9,260.00 31,649.29
04.03.03 ACERO Fy = 4200KG/cm2 GRADO 60 7.00 52,217.83

05.00 SEGURIDAD VIAL Y MITIGACIÓN AMBIENTAL 200.00 1,675.47 1,675.47


99.00 880.00 104.47 104.47 107.95 107.95 104.47 107.95 59.21
05.01 MITIGACION DE IMPACTO AMBIENTAL 200.00 1,675.47

06.00 VARIOS 59.00 126,101.87 126,101.87


29,619.38 18,134.31 6,239.43 6,454.59
06.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO 59.00 60,447.71
6,565.42 45,301.37 6,776.84 7,010.53
06.02 FLETE TERRESTRE 59.00 65,654.16

COSTO DIRECTO TOTAL 260,409.87 463,337.20 144,885.25 556,548.01 362,604.20 342,097.23 309,208.94 286,460.34 656,974.61 3,382,525.65
GASTOS GENERALES 5.00 % 13,020.49 23,166.86 7,244.26 27,827.40 18,130.21 17,104.86 15,460.45 14,323.02 32,848.73 169,126.28
UTILIDADES 10.00 % 26,040.99 46,333.72 14,488.53 55,654.80 36,260.42 34,209.72 30,920.89 28,646.03 65,697.46 338,252.57
SUB TOTAL 299,471.35 532,837.78 166,618.04 640,030.21 416,994.83 393,411.81 355,590.28 329,429.39 755,520.80 3,889,904.50
I.G.V. 18.00 % 53,904.84 95,910.80 29,991.25 115,205.44 75,059.07 70,814.13 64,006.25 59,297.29 135,993.74 700,182.81
DESEMBOLSO PARCIAL PROGRAMADO S/. 353,376.19 628,748.58 196,609.29 755,235.65 492,053.90 464,225.94 419,596.53 388,726.68 891,514.55 4,590,087.31
DESEMBOLSO ACUMULADO PROGRAMADO S/. 353,376.19 982,124.77 1,178,734.06 1,933,969.71 2,426,023.61 2,890,249.55 3,309,846.08 3,698,572.76 4,590,087.31
C R O N O G R A M A D E A V A N C E D E O B R A V A L O R I Z A D O - D E A D I C I O N A L D E O B R A Nº 01
OBRA : ADICIONAL DE OBRA Nº 01 "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCIÓN : 75 DÍAS CALENDARIOS
Nº DEL 01 AL 31 DE MAYO - 2019 DEL 01 AL 30 DE JUNIO - 2019 DEL 01 AL 31 DE JULIO - 2019 SUB TOTAL TOTAL
ITEM ACTIVIDAD
Dias 1 2 5 7 9 11 13 15 17 19 21 23 25 27 29 31 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 S/. S/.

01.00 RED DE ALCANTARILLADO PLUVIAL 75.00 409,086.47 409,086.47

01.01 TRABAJOS PRELIMINARES 44.00 2,131.84


332.03 527.35
01.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A. 44.00 859.38
1,272.46
01.01.02 DEMOLICION DE CANAL EXISTENTE 1.00 1,272.46

01.02 MOVIMIENTO DE TIERRAS 25.00 87,791.93


6,853.27 4,111.96
01.02.01 EXCAV. ZANJA (MÁQ.) P/TUB. TERR-NORMAL DN 315 DE 1.00 M A 1.20 M PROF. 8.00 10,965.23
136.66 956.60
01.02.02 REFINE Y NIVELACION DE ZANJA TERR-NORMAL PARA TUB. DN 315 8.00 1,093.26
5,852.47
01.02.03 CONFORMACION DE CAMA DE APOYO CON ARENA, H=10 CM - TUBERÍA MATRIZ 8.00 5,852.47
60,325.06
01.02.04 RELLENO COMP. ZANJA CON MATERIAL GRANULAR (PULSO) P/TUB - DN 315 DE 1.00 M A 1.20 M PROF. 8.00 60,325.06
9,555.91
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 2.00 9,555.91

01.03 SUMINISTRO E INSTALACION DE TUBERÍA 11.00 52,304.21


47,940.23
01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC-U UF NTP ISO 4435 S 20 DN 315 INCL. ANILLO + 2% DESPERDICI 8.00 47,940.23
3,779.82
01.03.02 SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø315MM x Ø315MM+CODO DE 3.00 3,779.82
584.16
01.03.03 SUMINISTRO E INSTALACION DE CODO PVC-UF, ISO 4435 ,Ø315MM x 90º 1.00 584.16

01.04 CONEXIONES DE ALCANTARILLADO PLUVIAL 25.00 6,083.47

01.04.01 TRABAJOS PRELIMINARES 15.00 43.23


43.23
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.04.01.01 15.00 43.23

01.04.02 MOVIMIENTO DE TIERRAS 15.00 4,234.64


701.45
01.04.02.01EXCAV. ZANJA MANUAL/TUB. TERR-NORMAL DN 160 DE 0.86 M A 1.00 M PROF. 4.00 701.45
43.55
01.04.02.02REFINE Y NIVEL DE ZANJA TERR-NORMAL PARA TUB. DN 160 4.00 43.55
318.15
01.04.02.03CONFORMACION DE CAMA DE APOYO CON ARENA, H=10 CM - CONEXIONES 4.00 318.15
2,734.16
01.04.02.04RELLENO COMP. ZANJA CON MATERIAL GRANULAR (PULSO) P/TUB -DN 160 DE 0.86 M A 1.00 M PROF. 4.00 2,734.16
437.33
01.04.02.05ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 2.00 437.33

01.04.03 SUMINISTRO E INSTALACION DE TUBERÍA 5.00 1,805.60


902.27
SUMINISTRO E INSTALACION DE TUBERIA PVC-U UF NTP ISO 4435 S 20 DN 160 INCL. ANILLO + 2% DESPERDICIOS
01.04.03.01 4.00 902.27
903.33
01.04.03.02SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø315MM x Ø160MM +CODO DE 2.00 903.33

01.05 CAMARA DE INSPECCION 41.00 86,280.40

01.05.01 TRABAJOS PRELIMINARES 31.00 89.49


63.51 25.98
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.05.01.01 31.00 89.49

01.05.02 MOVIMIENTO DE TIERRAS 15.00 5,122.44


3,271.92
01.05.02.01EXCAVACIÓN MANUAL EN TERRENO NORMAL 8.00 3,271.92
113.85
01.05.02.02REFINE Y NIVELACION DE FONDO DE ZANJA 8.00 113.85
1,736.67
01.05.02.03ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 2.00 1,736.67

01.05.03 OBRAS DE CONCRETO SIMPLE 15.00 3,816.97


3,816.97
CONCRETO 1:8 PARA SOLADO E=4"
01.05.03.01 2.00 3,816.97

01.05.04 OBRAS DE CONCRETO ARMADO 15.00 60,646.00


25,920.23
CONCRETO EN CAMARAS DE INSPECCION F'c = 210 kg/cm2
01.05.04.01 7.00 25,920.23
7,928.19 5,946.14
ACERO Fy = 4200KG/cm2 GRADO 60 EN CAMARAS DE INSPECCION
01.05.04.02 7.00 13,874.33
2,978.78 17,872.66
ENCOFRADO Y DESENCOFRADO DE CAMARAS DE INSPECCION
01.05.04.03 7.00 20,851.44

01.05.05 OBRAS DE CONCRETO ARMADO 15.00 16,605.50


3,711.82
TAPA METALICA TIPO I
01.05.05.01 4.00 3,711.82
12,893.68
TAPA METALICA TIPO II
01.05.05.02 12.00 12,893.68

01.06 CUNETA Y PARRILLAS PLUVIALES COLECTORAS 38.00 65,449.79

01.06.01 TRABAJOS PRELIMINARES 28.00 153.73


32.94 120.79
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.06.01.01 28.00 153.73

01.06.02 MOVIMIENTO DE TIERRAS 30.00 4,106.28


510.94 2,043.77
01.06.02.01EXCAVACIÓN MANUAL EN TERRENO NORMAL 10.00 2,554.71
195.57
01.06.02.02REFINE Y NIVELACION DE FONDO DE ZANJA 10.00 195.57
1,356.00
01.06.02.03ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 4.00 1,356.00

01.06.03 OBRAS DE CONCRETO SIMPLE 10.00 6,557.05


6,557.05
CONCRETO 1:8 PARA SOLADO E=4"
01.06.03.01 10.00 6,557.05

01.06.04 OBRAS DE CONCRETO ARMADO 20.00 29,679.08


18,207.55
CONCRETO EN CUNETA F'c = 210 kg/cm2
01.06.04.01 6.00 18,207.55
7,042.79
ACERO Fy = 4200KG/cm2 GRADO 60 EN CUNETA
01.06.04.02 7.00 7,042.79
4,428.74
ENCOFRADO Y DESENCOFRADO DE CUNETAS
01.06.04.03 8.00 4,428.74

01.06.05 CARPINTERIA METALICA 15.00 24,953.65


24,953.65
PARRILLA METALICA
01.06.05.01 15.00 24,953.65

01.07 RED DE ALCANTARILLADO SECUNDARIO 29.00 89,151.63

01.07.01 TRABAJOS PRELIMINARES 29.00 595.11


369.38 225.73
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.07.01.01 29.00 595.11

01.07.02 MOVIMIENTO DE TIERRAS 27.00 65,736.52


11,312.85
01.07.02.01EXCAV. ZANJA MANUAL/TUB. TERR-NORMAL DN 250 DE 0.95 M A 1.15 M PROF. 10.00 11,312.85
713.42
01.07.02.02REFINE Y NIVELACION DE ZANJA TERR-NORMAL PARA TUB. DN 250 3.00 713.42
4,422.34
01.07.02.03CONFORMACION DE CAMA DE APOYO CON ARENA, H=10 CM - TUBERÍA SECUNDARIA 3.00 4,422.34
42,637.01
01.07.02.04RELLENO COMP. ZANJA CON MATERIAL GRANULAR (PULSO) P/TUB - DN 250 DE 0.95 M A 1.15 M PROF. 4.00 42,637.01
6,650.90
01.07.02.05ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 1.00 6,650.90

01.07.03 SUMINISTRO E INSTALACION DE TUBERÍA 6.00 22,820.00


16,626.97 5,542.32
SUMINISTRO E INSTALACION DE TUBERIA PVC-U UF NTP ISO 4435 S 20 DN 250 INCL. ANILLO + 2% DESPERDICIOS
01.07.03.01 4.00 22,169.29
253.09
SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø250MM x Ø250MM+CODO DE 45º
01.07.03.02 1.00 253.09
271.09
SUMINISTRO E INSTALACION DE CACHIMBA TEE GIRATORIA PVC-UF, ISO 4435 ,Ø315MM x Ø250MM+CODO DE 45º
01.07.03.03 1.00 271.09
126.53
SUMINISTRO E INSTALACION DE CACHIMBA CODO DE 45 º PVC-UF, ISO 4435 ,Ø250MM
01.07.03.04 1.00 126.53

01.08 CUNETAS PLUVIALES SECUNDARIAS 5.00 4,585.69


C R O N O G R A M A D E A V A N C E D E O B R A V A L O R I Z A D O - D E A D I C I O N A L D E O B R A Nº 01
OBRA : ADICIONAL DE OBRA Nº 01 "MEJORAMINETO DE PISTAS Y VEREDAS EN LA CIUDAD DE TAYABAMBA, DISTRITO DE TAYABAMBA, PATAZ - LA LIBERTAD" - QUINTA ETAPA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE PATAZ
FECHA : MAYO DEL 2019
TIEMPO DE EJECUCIÓN : 75 DÍAS CALENDARIOS
01.08.01 TRABAJOS PRELIMINARES 5.00 684.50
39.50
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.08.01.01 5.00 39.50
645.00
DEMOLICION DE CUNETA EXISTENTE
01.08.01.02 1.00 645.00

01.08.02 MOVIMIENTO DE TIERRAS 2.00 197.89


120.89
01.08.02.01ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 1.00 120.89
77.00
01.08.02.02PERFILADO Y COMPACTADO DE FONDO 1.00 77.00

01.08.03 OBRAS DE CONCRETO SIMPLE 2.00 3,703.30


1,138.20
ENCOFRADO Y DESENCOFRADO EN CUNETAS SECUNDARIAS
01.08.03.01 2.00 1,138.20
2,565.10
CONCRETO EN CUNETAS SECUNDARIAS F'c=175 kg/cm2
01.08.03.02 1.00 2,565.10

01.09 CUNETA PLUVIAL TRIANGULAR 12.00 15,307.51

01.09.01 TRABAJOS PRELIMINARES 5.00 227.52


227.52
CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - RED A.
01.09.01.01 5.00 227.52

01.09.02 MOVIMIENTO DE TIERRAS 4.00 1,877.42


893.01
01.09.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMAL 3.00 893.01
605.22
01.09.02.02PERFILADO Y COMPACTADO DE FONDO 3.00 605.22
379.19
01.09.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 1.00 379.19

01.08.03 OBRAS DE CONCRETO SIMPLE 8.00 13,202.57


5,691.00
01.08.03.01 ENCOFRADO Y DESENCOFRADO EN CUNETA TRIANGULAR 3.00 5,691.00
7,103.34
CONCRETO EN CUNETAS SECUNDARIAS F'c=175 kg/cm2
01.08.03.02 3.00 7,103.34
408.23
JUNTA DE DILATACION CON ASFALTO
01.08.03.03 2.00 408.23

02.00 MUROS DE CONTENCION EN VOLADIZO 75.00 481,532.88 481,532.88

02.01 TRABAJOS PRELIMINARES 61.00 7,779.95


196.43 346.63 161.76
02.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - MUROS 61.00 704.82
7,075.13
02.01.02 DEMOLICION DE MUROS DE CONCRETO EXISTENTES 15.00 7,075.13

02.02 MOVIMIENTO DE TIERRAS 61.00 153,184.89


13,204.88 22,346.72
02.03.01 EXCAVACIÓN MANUAL EN TERRENO NORMAL 35.00 35,551.60
49,939.43 46,610.13
02.03.02 RELLENO COMPACTADO CON MATERIAL GRANULAR 58.00 96,549.56
10,905.38 10,178.35
02.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 58.00 21,083.73

02.03 CONCRETO SIMPLE 35.00 30,062.01


10,306.97 19,755.04
02.03.01 CONCRETO 1:8 PARA SOLADO E=4" 35.00 30,062.01

02.04 OBRAS DE CONCRETO ARMADO 56.00 290,506.03


22,404.46 96,019.13 48,009.56
02.04.01 CONCRETO EN MUROS DE CONTENCION EN VOLADIZO, F'C= 210 KG/CM2 52.00 166,433.15
14,100.35 47,001.17 20,367.17
02.04.02 ACERO fy=4200 kg/cm2 GRADO 60 EN MURO DE CONTENCION EN VOLADIZO 52.00 81,468.69
6,409.51 24,035.67 11,216.64
02.04.03 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION EN VOLADIZO 52.00 41,661.82
126.85 543.68 271.84
02.04.04 JUNTA DE DILATACION VERTICAL EN MUROS 52.00 942.37

03.00 MUROS DE CONTENCION POR GRAVEDAD 45.00 110,801.73 110,801.73

03.01 TRABAJOS PRELIMINARES 45.00 2,480.18


151.56 249.62
03.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - MUROS 45.00 401.18
2,079.00
03.01.02 DEMOLICION DE MUROS DE CONCRETO EXISTENTES 5.00 2,079.00

03.02 MOVIMIENTO DE TIERRAS 44.00 27,977.40


4,698.84 4,111.49
03.02.01 EXCAVACIÓN MANUAL EN TERRENO NORMAL 30.00 8,810.33
13,840.19
03.02.02 RELLENO COMPACTADO CON MATERIAL GRANULAR 10.00 13,840.19
5,326.88
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO D. PROM ≤ 5 KM 10.00 5,326.88

03.03 CONCRETO SIMPLE 27.00 80,344.15


18,126.54 38,842.57
03.03.01 CONCRETO CICLOPEO F'C=175 KG/CM2+ 30% DE P.M 22.00 56,969.11
8,109.25 14,191.20
03.03.02 ENCOFRADO Y DESENCOFRADO EN MUROS DE CONTENCION POR GRAVEDAD 22.00 22,300.45
1,074.59
03.03.03 JUNTA DE DILATACION VERTICAL EN MUROS C.S 10.00 1,074.59

04.00 VEREDAS EN VOLADIZOS 32.00 44,200.04 44,200.04

04.01 TRABAJOS PRELIMINARES 13.00 322.95


99.37 223.58
04.01.01 CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA - VEREDA EN VOL. 13.00 322.95

04.02 OBRAS DE CONCRETO ARMADO 23.00 43,877.09


16,234.76
04.02.01 CONCRETO F'C=210 KG/CM2 - VEREDA EN VOLADIZO 8.00 16,234.76
14,286.73
04.02.02 ACERO Fy = 4200KG/cm2 GRADO 60 - VEREDA EN VOLADIZO 7.00 14,286.73
13,196.17
04.02.03 ENCOFRADO Y DESENCOFRADO - VEREDA EN VOLADIZO 10.00 13,196.17
159.43
04.02.04 JUNTA DE CONTRACCION - VEREDA EN VOLADIZO 2.00 159.43

05.00 VARIOS 47.00 55,000.00 55,000.00


19,893.62 35,106.38
05.01 TRANSPORTE DE MATERIALES - TRUJILLO A TAYABAMBA 47.00 55,000.00

COSTO DIRECTO TOTAL 101,040.16 534,152.01 465,428.95 1,100,621.12


GASTOS GENERALES 5.00 % 5,052.01 26,707.60 23,271.45 55,031.06
UTILIDADES 9.00 % 9,093.61 48,073.68 41,888.61 99,055.90
SUB TOTAL 115,185.78 608,933.29 530,589.01 1,254,708.08
I.G.V. 18.00 % 20,733.44 109,607.99 95,506.02 225,847.45
DESEMBOLSO PARCIAL PROGRAMADO S/. 135,919.22 718,541.28 626,095.03 1,480,555.53
DESEMBOLSO ACUMULADO PROGRAMADO S/. 135,919.22 854,460.50 1,480,555.53