Proyecto CREACIÓN DEL SERVICIO DE AGUA POTABLE Y DESAGÜE EN EL ASENTAMIENTO HUMANO LOS GIRASOLES, DISTRITO DE LA JOYA - AREQUIPA – AREQUIPA
Cliente MUNICIPALIDAD PROVINCIAL DE LA JOYA
Ubicación LA JOYA
SUBTOTAL ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO POR VALORIZAR
ITEM DESCRIPCIÓN UNIDAD METRADOS PRECIO U
METRADO MONTO METRADO MONTO % METRADO MONTO % METRADO MONTO %
4 SISTEMA DE ALCANTARILLADO
4.1 OBRAS PROVISIONALES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 S/ 10,000.00 S/ 10,000.00 1.00 S/ 10,000.00 S/ - 0.00 1.00 S/ 10,000.00 100% 0.00 S/ - 0%
1.02 SERVICIOS HIGUIENICOS PARA LA OBRA dia 100.00 S/ 200.00 S/ 20,000.00 100.00 S/ 20,000.00 S/ - 0.00 100.00 S/ 20,000.00 100% 0.00 S/ - 0%
4.2 TRABAJOS PRELIMINARES
2.01 TRAZO Y REPLANTEO INICIAL PARA ALCANTARILLADO m 4116.25 S/ 2.89 S/ 11,895.96 4116.25 S/ 11,895.96 S/ - 0.00 4116.25 S/ 11,895.96 100% 0.00 S/ - 0%
2.02 TRAZO Y REPLANTEO FINAL PARA ALCANTARILLADO m 4116.25 S/ 2.09 S/ 8,602.96 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4116.25 S/ 8,602.96 100%
2.03 TOPOGRAFIA PERMANENTE EN OBRA dia 100.00 S/ 695.86 S/ 69,586.00 25.00 S/ 17,396.50 25.00 S/ 17,396.50 0.25 50.00 S/ 34,793.00 50% 50.00 S/ 34,793.00 50%
2.04 TRANQUERA T/BARANDA 1.20 x 1.10m PROV. P/SEÑALIZ. PROTECCION und 8.00 S/ 60.05 S/ 480.40 8.00 S/ 480.40 S/ - 0.00 8.00 S/ 480.40 100% 0.00 S/ - 0%
2.05 CONO DE FIBRA DE VIDRIO FOSFORESCENTE und 6.00 S/ 30.00 S/ 180.00 6.00 S/ 180.00 S/ - 0.00 6.00 S/ 180.00 100% 0.00 S/ - 0%
2.06 CINTA PLASTICA SEÑALIZADORA P/LIMITE SEGURIDAD DE OBRA m 8232.50 S/ 1.02 S/ 8,397.15 8232.50 S/ 8,397.15 S/ - 0.00 8232.50 S/ 8,397.15 100% 0.00 S/ - 0%
2.07 PUENTE DE MADERA PROVISIONAL, PASE PEATONAL SOBRE ZANJA glb 8.00 S/ 130.63 S/ 1,045.04 8.00 S/ 1,045.04 S/ - 0.00 8.00 S/ 1,045.04 100% 0.00 S/ - 0%
4.3 SEGURIDAD Y SALUD EN OBRA (INC. EXAMENES MEDICOS)
3.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD DE TRABAJO glb 1.00 S/ 5,000.00 S/ 5,000.00 1.00 S/ 5,000.00 S/ - 0.00 1.00 S/ 5,000.00 100% 0.00 S/ - 0%
3.02 EQUIPOS DE PROTECCION INDIVIDUAL(EPI) glb 1.00 S/ 10,000.00 S/ 10,000.00 1.00 S/ 10,000.00 S/ - 0.00 1.00 S/ 10,000.00 100% 0.00 S/ - 0%
3.03 SEÑALIZACION TEMPORAL DE SEGURIDAD(ST) glb 1.00 S/ 5,000.00 S/ 5,000.00 1.00 S/ 5,000.00 S/ - 0.00 1.00 S/ 5,000.00 100% 0.00 S/ - 0%
3.04 CAPACITACIONES DE SEGURIDAD Y SALUD glb 1.00 S/ 5,000.00 S/ 5,000.00 1.00 S/ 5,000.00 S/ - 0.00 1.00 S/ 5,000.00 100% 0.00 S/ - 0%
3.05 SEGUROS CAR PARA PERSONAL DE OBRA glb 1.00 S/ 5,000.00 S/ 5,000.00 1.00 S/ 5,000.00 S/ - 0.00 1.00 S/ 5,000.00 100% 0.00 S/ - 0%
4.4 MOVIMIENTO DE TIERRAS
4.01 EXCAVACION DE ZANJA C/MAQ. EN TERRENO CONGLOMERADO, HASTA 1.50M. DE PROF/PROM. ml 2225.93 S/ 16.96 S/ 37,751.77 1112.97 S/ 18,875.89 1112.97 S/ 18,875.89 0.50 2225.93 S/ 37,751.77 100% 0.00 S/ - 0%
4.02 EXCAVACION DE ZANJA C/MAQ. EN TERRENO CONGLOMERADO, HASTA 1.75M. DE PROF/PROM. ml 697.19 S/ 18.73 S/ 13,058.37 0.00 S/ - 697.19 S/ 13,058.37 1.00 697.19 S/ 13,058.37 100% 0.00 S/ - 0%
4.03 EXCAVACION DE ZANJA C/MAQ. EN TERRENO CONGLOMERADO, HASTA 2.50M. DE PROF/PROM. ml 809.27 S/ 22.29 S/ 18,038.63 0.00 S/ - 809.27 S/ 18,038.63 1.00 809.27 S/ 18,038.63 100% 0.00 S/ - 0%
4.04 EXCAVACION DE ZANJA C/MAQ. EN TERRENO CONGLOMERADO, HASTA 3.00M. DE PROF/PROM. ml 275.34 S/ 27.58 S/ 7,593.88 0.00 S/ - 275.34 S/ 7,593.88 1.00 275.34 S/ 7,593.88 100% 0.00 S/ - 0%
4.05 EXCAVACION DE ZANJA C/MAQ. EN TERRENO CONGLOMERADO, HASTA 3.50M. DE PROF/PROM. ml 108.52 S/ 32.91 S/ 3,571.39 0.00 S/ - 108.52 S/ 3,571.39 1.00 108.52 S/ 3,571.39 100% 0.00 S/ - 0%
4.06 NIVELACION Y REFINE DE FONDO DE ZANJA ml 4116.25 S/ 4.39 S/ 18,070.34 0.00 S/ - 2058.13 S/ 9,035.17 0.50 2058.13 S/ 9,035.17 50% 2058.13 S/ 9,035.17 50%
4.07 CONFORMACION DE CAMA DE APOYO, CON MATERIAL DE PRESTAMO H=10 CM ml 4116.25 S/ 7.38 S/ 30,377.93 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4116.25 S/ 30,377.93 100%
4.08 RELLENO DE ZANJA CON MATERIAL PROPIO C/MAQ. HASTA 1.50M. DE PROF/PROM. ml 2225.93 S/ 21.35 S/ 47,523.61 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2225.93 S/ 47,523.61 100%
4.09 RELLENO DE ZANJA CON MATERIAL PROPIO C/MAQ. HASTA 1.75M. DE PROF/PROM. ml 697.19 S/ 24.45 S/ 17,046.30 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 697.19 S/ 17,046.30 100%
4.1 RELLENO DE ZANJA CON MATERIAL PROPIO C/MAQ. HASTA 2.50M. DE PROF/PROM. ml 809.27 S/ 31.45 S/ 25,451.54 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 809.27 S/ 25,451.54 100%
4.11 RELLENO DE ZANJA CON MATERIAL PROPIO C/MAQ. HASTA 3.00M. DE PROF/PROM. ml 275.34 S/ 36.77 S/ 10,124.25 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 275.34 S/ 10,124.25 100%
4.12 RELLENO DE ZANJA CON MATERIAL PROPIO C/MAQ. HASTA 3.50M. DE PROF/PROM. ml 108.52 S/ 41.53 S/ 4,506.84 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 108.52 S/ 4,506.84 100%
4.13 RELLENO DE ZANJA CON MATERIAL PRESTAMO C/MAQ. HASTA 0.30M. DE PROF/PROM. ml 4116.25 S/ 17.11 S/ 70,429.04 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4116.25 S/ 70,429.04 100%
4.14 ELIMINACION DE MATERIAL EXCEDENTE, DIST. PROM. 10KM, CARGUIO C/MAQ m3 3067.86 S/ 29.95 S/ 91,882.41 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 3067.86 S/ 91,882.41 100%
4.07 SUMINISTRO E INSTALACION DE TUBERIAS
5.01 SUMINISTRO E INSTALACION DE TUBERIA PVC ISO4435 DN200MM S-20 m 2913.15 S/ 35.51 S/ 103,445.96 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2913.15 S/ 103,445.96 100%
5.02 ALINEAMIENTO Y AJUSTE DE TUBERIA PVC ISO 4435 DN 200MM m 2913.15 S/ 1.24 S/ 3,612.31 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2913.15 S/ 3,612.31 100%
5.03 DESVIO DE AGUAS SERVIDAS HASTA Q= 60L/S C/MOTOBOMBA 12HP 6" (Incluye manguera y accesorios) m 100.00 S/ 22.19 S/ 2,219.00 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 100.00 S/ 2,219.00 100%
4.06 CONSTRUCCION DE CAMARAS DE INSPECCION
6.01 CONSTRUCCION DE BUZON TIPO I HASTA 1.50m DE PROF. und 11.00 S/ 1,510.41 S/ 16,614.51 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 11.00 S/ 16,614.51 100%
6.02 CONSTRUCCION DE BUZON TIPO I HASTA 2.00m DE PROF. und 19.00 S/ 1,770.67 S/ 33,642.73 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 19.00 S/ 33,642.73 100%
6.03 CONSTRUCCION DE BUZON TIPO I HASTA 2.50m DE PROF. und 4.00 S/ 2,000.44 S/ 8,001.76 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4.00 S/ 8,001.76 100%
6.04 CONSTRUCCION DE BUZON TIPO I HASTA 3.00m DE PROF. und 6.00 S/ 2,255.65 S/ 13,533.90 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.00 S/ 13,533.90 100%
6.05 CONSTRUCCION DE BUZON TIPO II HASTA 3.50m DE PROF. und 5.00 S/ 3,615.62 S/ 18,078.10 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 5.00 S/ 18,078.10 100%
6.06 CONSTRUCCION DE BUZON TIPO II HASTA 4.00m DE PROF. und 2.00 S/ 3,858.82 S/ 7,717.64 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.00 S/ 7,717.64 100%
6.07 CONSTRUCCION DE DADOS DE EMPALME und 118.00 S/ 90.33 S/ 10,658.94 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 118.00 S/ 10,658.94 100%
4.07 CONEXIONES DOMICILIARIAS
7.01 CONEXION DOMICILIARIA DN 160MM ISO4435 S-20 A TUBERIA DN 200MM; L=4.50M. und 7.00 S/ 341.84 S/ 2,392.88 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 7.00 S/ 2,392.88 100%
7.02 CONEXION DOMICILIARIA DN 160MM ISO4435 S-20 A TUBERIA DN 200MM; L=5.80M. und 107.00 S/ 377.85 S/ 40,429.95 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 107.00 S/ 40,429.95 100%
7.03 CONEXION DOMICILIARIA DN 160MM ISO4435 S-20 A TUBERIA DN 200MM; L=6.20M. und 58.00 S/ 394.26 S/ 22,867.08 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 58.00 S/ 22,867.08 100%
7.04 CONEXION DOMICILIARIA DN 160MM ISO4435 S-20 A TUBERIA DN 200MM; L=6.60M. und 29.00 S/ 403.51 S/ 11,701.79 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 29.00 S/ 11,701.79 100%
4.08 PRUEBA HIDRAULICA
8.01 PRUEBA HIDRAULICA DE TUBERIA PVC ISO4435 DN 160MM m 1203.10 S/ 2.32 S/ 2,791.19 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1203.10 S/ 2,791.19 100%
8.02 PRUEBA HIDRAULICA DE TUBERIA PVC ISO4435 DN 200MM m 2913.15 S/ 3.24 S/ 9,438.61 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2913.15 S/ 9,438.61 100%
1 ESTACION DE BOMBEO
1.01 TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO MANUAL m2 21.32 S/ 2.93 S/ 62.47 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 21.32 S/ 62.47 100%
01.01.02 TRAZO, NIVELES Y REPLANTEO m2 21.32 S/ 3.05 S/ 65.03 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 21.32 S/ 65.03 100%
1.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION DE ZANJA CON MAQUINA m3 72.71 S/ 21.06 S/ 1,531.27 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 72.71 S/ 1,531.27 100%
01.02.02 NIVELACION INTERIOR Y COMPACTACION C/COMPACTADORA m2 13.2 S/ 10.98 S/ 144.94 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 13.20 S/ 144.94 100%
01.02.03 RELLENO Y COMPACTACION DE ZANJA CON MATERIAL DE PRESTAMO m3 31.41 S/ 102.90 S/ 3,232.09 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 31.41 S/ 3,232.09 100%
01.02.04 ELIMINACION DE MATERIAL EXCEDENTE, DIST. PROM. 10KM, CARGUIO C/MAQ m3 94.53 S/ 29.95 S/ 2,831.17 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 94.53 S/ 2,831.17 100%
1.03 CONCRETO SIMPLE
01.03.01 SOLADO DE CONCRETO C : H (1:12) m2 13.2 S/ 40.61 S/ 536.05 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 13.20 S/ 536.05 100%
01.03.02 PISO DE CONCRETO DE 4" SIN COLOREAR m2 1.56 S/ 44.32 S/ 69.14 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.56 S/ 69.14 100%
01.03.03 ENCOFRADO Y DEDESENCOFRADO DE PISO m2 0.37 S/ 55.62 S/ 20.58 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 0.37 S/ 20.58 100%
1.04 CONCRETO ARMADO
01.04.01 CAMARA HUMEDA
01.04.01.01 CONCRETO F'c= 210 KG/CM2 EN CAMARA HUMEDA m3 16.52 S/ 588.41 S/ 9,720.53 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 16.52 S/ 9,720.53 100%
01.04.01.02 ENCOFRADO Y DESENCOFRADO EN CAMARA HUMEDA m2 106.33 S/ 55.16 S/ 5,865.16 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 106.33 S/ 5,865.16 100%
01.04.01.03 ACERO DE REFUERZO F'Y=4200 KG/CM2 kg 1057.72 S/ 7.32 S/ 7,742.51 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1057.72 S/ 7,742.51 100%
01.04.02 COLUMNAS
01.04.02.01 CONCRETO EN COLUMNAS F'c= 210 KG/CM2 m3 0.52 S/ 526.02 S/ 273.53 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 0.52 S/ 273.53 100%
01.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 7.34 S/ 56.18 S/ 412.36 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 7.34 S/ 412.36 100%
01.04.02.03 ACERO DE REFUERZO F'Y=4200 KG/CM2 kg 112.96 S/ 7.32 S/ 826.87 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 112.96 S/ 826.87 100%
01.04.03 VIGAS
01.04.03.01 CONCRETO F'c= 210 KG/CM2 PARA VIGAS m3 0.95 S/ 404.28 S/ 384.07 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 0.95 S/ 384.07 100%
01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 12.68 S/ 63.81 S/ 809.11 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 12.68 S/ 809.11 100%
01.04.03.03 ACERO DE REFUERZO F'Y=4200 KG/CM2 kg 263.32 S/ 7.32 S/ 1,927.50 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 263.32 S/ 1,927.50 100%
01.04.04 LOSA DE TECHO
01.04.04.01 CONCRETO F'c= 210 KG/CM2 PARA LOSA DE TECHO m3 1.68 S/ 404.28 S/ 679.19 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.68 S/ 679.19 100%
01.04.04.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE TECHO m2 13.21 S/ 49.11 S/ 648.74 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 13.21 S/ 648.74 100%
01.04.04.03 ACERO DE REFUERZO F'Y=4200 KG/CM2 kg 80.39 S/ 7.32 S/ 588.45 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 80.39 S/ 588.45 100%
1.05 MUROS Y TABIQUES DE ALBAÑILERIA
01.05.01 MURO DE LADRILLO KK. ARCILLA DE SOGA, MEZCLA 1:4 m2 17.04 S/ 57.38 S/ 977.76 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 17.04 S/ 977.76 100%
1.06 REVOQUES ENLUCIDOS Y MOLDURAS
01.06.01 TARRAJEO INTERIOR C/IMPERMEAB. C:A 1:4, E= 1.5cm - LOSA DE FONDO m2 5.31 S/ 60.19 S/ 319.61 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 5.31 S/ 319.61 100%
01.06.02 TARRAJEO INTERIOR C/IMPERMEAB. C:A 1:4, E= 1.5cm - MUROS m2 38.8 S/ 46.75 S/ 1,813.90 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 38.80 S/ 1,813.90 100%
01.06.03 TARRAJEO INTERIOR C:A 1:4, E= 1.5cm m2 25.14 S/ 36.45 S/ 916.35 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 25.14 S/ 916.35 100%
01.06.04 TARRAJEO EXTERIOR C:A 1:4, E= 1.5cm m2 28.08 S/ 48.17 S/ 1,352.61 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 28.08 S/ 1,352.61 100%
01.06.05 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS m 20.4 S/ 20.50 S/ 418.20 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 20.40 S/ 418.20 100%
01.06.06 TARRAJEO EN CIELO RASO C/MORTERO C:A 1:4, E= 1.5cm m2 11.53 S/ 51.54 S/ 594.26 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 11.53 S/ 594.26 100%
1.07 CARPINTERIA METALICA
01.07.01 PUERTA METALICA INC. INSTALACION (1.00X2.50M) und 1 S/ 1,037.90 S/ 1,037.90 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 1,037.90 100%
01.07.02 VENTANA DE FIERRO SEGUN DISEÑO (0.60 x 0.60M) m2 2.16 S/ 205.16 S/ 443.15 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.16 S/ 443.15 100%
01.07.03 TAPA METALICA DE INGRESO INC. MARCO Y COLOCACION und 1 S/ 472.44 S/ 472.44 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 472.44 100%
01.07.04 TAPA METALICA RECTANGULAR INC. MARCO Y COLOCACION und 1 S/ 572.44 S/ 572.44 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 572.44 100%
01.07.05 ESCALERA TUB F.GVZDO. C/PARANTES DE 2" X PELDAÑOS DE 3/4" m 4.25 S/ 414.65 S/ 1,762.26 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4.25 S/ 1,762.26 100%
01.07.06 MALLA DE ALAMBRE GALVANIZADO, COCADA 2" BWG 8 m2 2.56 S/ 38.73 S/ 99.15 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.56 S/ 99.15 100%
1.08 CERRAJERIA
01.08.01 CERRADURA PARA PUERTAS 3 GOLPES und 1 S/ 55.88 S/ 55.88 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 55.88 100%
01.08.02 BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2" und 3 S/ 19.94 S/ 59.82 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 3.00 S/ 59.82 100%
1.09 PINTURA
01.09.01 PINTURA ANTICORROSIVA EN ESTRUCTURAS METALICAS m2 10.14 S/ 13.76 S/ 139.53 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 10.14 S/ 139.53 100%
01.09.02 PINTURA LATEX EN INTERIORES m2 28.2 S/ 22.21 S/ 626.32 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 28.20 S/ 626.32 100%
01.09.03 PINTURA LATEX EN EXTERIORES m2 32.4 S/ 27.56 S/ 892.94 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 32.40 S/ 892.94 100%
01.09.04 PINTURA LATEX EN CIELO RASO m2 11.53 S/ 15.83 S/ 182.52 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 11.53 S/ 182.52 100%
1.1 COBERTURA
01.10.01 COBERTURA CON LADRILLO PASTELERO DE 24 x 24 x 3mm ASENTADO CON MEZCLA m2 11.2 S/ 35.47 S/ 397.26 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 11.20 S/ 397.26 100%
1.11 INSTALACIONES HIDRAULICAS
01.11.01 ELECTROBOMBAS
01.11.01.01 ELECTROBOMBA DE SUMIDERO SUMERGIBLE INC. ACCESOSRIOS und 1 S/ 20,640.57 S/ 20,640.57 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 20,640.57 100%
01.11.01.02 ELECTROBOMBA DE SUMIDERO INMERSIBLE INC. ACCESOSRIOS und 1 S/ 19,140.57 S/ 19,140.57 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 19,140.57 100%
01.11.02 TUBERIAS
01.11.02.01 TUBERIA DE FFD DN 63MM m 5.6 S/ 178.24 S/ 998.14 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 5.60 S/ 998.14 100%
01.11.02.02 TUBERIA DE FFD DN 90MM m 6.6 S/ 336.36 S/ 2,219.98 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.60 S/ 2,219.98 100%
01.11.02.03 TUBERIA PVC ISO 1452 DN 110MM C-7.5 m 4 S/ 26.12 S/ 104.48 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4.00 S/ 104.48 100%
01.11.03 CODOS
01.11.03.01 CODO BB DIAM. 63MM x 90° FFD und 1 S/ 110.97 S/ 110.97 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 110.97 100%
01.11.03.02 CODO BB DIAM. 90MM x 45° FFD und 2 S/ 134.87 S/ 269.74 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.00 S/ 269.74 100%
01.11.04 REDUCCION
01.11.04.01 REDUCCION BB. DE 90MM A 63MM FFD und 1 S/ 350.79 S/ 350.79 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 350.79 100%
01.11.05 VALVULAS
01.11.05.01 VALVULA CHECK DE BOLA BB. 90MM FFD und 1 S/ 623.74 S/ 623.74 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 623.74 100%
01.11.05.02 VALVULA COMPUERTA MARIPOSA BB. DN 90MM FFD und 1 S/ 695.79 S/ 695.79 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 695.79 100%
01.11.06 TEES
01.11.06.01 TEE BB DN 90MM FFD und 1 S/ 304.90 S/ 304.90 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 304.90 100%
01.11.07 UNIONES
01.11.07.01 UNION FLEXIBLE TIPO DRESSER DE 90MM FFD und 2 S/ 352.95 S/ 705.90 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.00 S/ 705.90 100%
01.11.08 BRIDAS
01.11.08.01 BRIDA CIEGA FFD DN 90MM und 1 S/ 199.70 S/ 199.70 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 199.70 100%
01.11.08.02 BRIDA DE FFD DN 90MM und 13 S/ 199.70 S/ 2,596.10 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 13.00 S/ 2,596.10 100%
01.11.08.03 BRIDA DE FFD DN 63MM und 2 S/ 183.90 S/ 367.80 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.00 S/ 367.80 100%
01.11.09 VARIOS
01.11.09.01 MONTAJE E INSTALACION DE SISTEMA HIDRAULICO EN ESTACION DE BOMBEO GLB 1 S/ 7,000.00 S/ 7,000.00 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 7,000.00 100%
01.11.09.02 INSTALACION DEL SISTEMA ELECTRICO EN ESTACION DE BOMBEO INC. EQUIPOS Y ACCESORIOS GLB 1 S/ 18,000.00 S/ 18,000.00 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 18,000.00 100%
01.11.09.03 SOMBRERO DE VENTILACION PVC DN 110MM GLB 1 S/ 23.04 S/ 23.04 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 23.04 100%
01.11.09.04 INSTALACION DE RIEL DE APOYO + TECLE MANUAL 1 TON. INC. CADENA und 1 S/ 800.00 S/ 800.00 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 800.00 100%
01.11.09.05 JUNTA DE CONSTRUCCION C/WATER STOP 8" m 19.48 S/ 37.63 S/ 733.03 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 19.48 S/ 733.03 100%
01.11.09.06 DADOS DE CONCRETO F'c= 175 KG/CM2 und 2 S/ 30.03 S/ 60.06 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.00 S/ 60.06 100%
2 CAMARA DE REJAS
2.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.61 S/ 2.93 S/ 19.37 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.61 S/ 19.37 100%
02.01.02 TRAZO, NIVELES Y REPLANTEO m2 6.61 S/ 3.05 S/ 20.16 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.61 S/ 20.16 100%
2.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION DE ZANJA CON MAQUINA m3 24.77 S/ 21.06 S/ 521.66 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 24.77 S/ 521.66 100%
02.02.02 NIVELACION INTERIOR Y COMPACTACION C/COMPACTADORA m2 6.61 S/ 10.98 S/ 72.58 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.61 S/ 72.58 100%
02.02.03 RELLENO Y COMPACTACION DE ZANJA CON MATERIAL PROPIO m3 17.67 S/ 8.12 S/ 143.48 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 17.67 S/ 143.48 100%
02.02.04 ELIMINACION DE MATERIAL EXCEDENTE, DIST. PROM. 10KM, CARGUIO C/MAQ m3 9.23 S/ 29.95 S/ 276.44 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 9.23 S/ 276.44 100%
2.03 CONCRETO SIMPLE
02.03.01 SOLADO DE CONCRETO C : H (1:12) m2 6.61 S/ 40.61 S/ 268.43 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6.61 S/ 268.43 100%
2.04 CONCRETO ARMADO
02.04.01 CONCRETO F'c= 210 KG/CM2 EN CAMARA DE REJAS m3 4.88 S/ 588.41 S/ 2,871.44 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 4.88 S/ 2,871.44 100%
02.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA DE REJAS m2 38.63 S/ 55.16 S/ 2,130.83 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 38.63 S/ 2,130.83 100%
02.04.03 ACERO DE REFUERZO F'Y=4200 KG/CM2 kg 328.41 S/ 7.32 S/ 2,403.96 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 328.41 S/ 2,403.96 100%
2.05 REVOQUES ENLUCIDOS Y MOLDURAS
02.05.01 TARRAJEO INTERIOR C/IMPERMEAB. C:A 1:4, E= 1.5cm - LOSA DE FONDO m2 1.77 S/ 60.19 S/ 106.54 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.77 S/ 106.54 100%
02.05.02 TARRAJEO INTERIOR C/IMPERMEAB. C:A 1:4, E= 1.5cm - MUROS m2 17.32 S/ 46.75 S/ 809.71 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 17.32 S/ 809.71 100%
2.06 VARIOS
02.06.01 TAPA METALICA DE INGRESO INC. MARCO Y COLOCACION GLB 1 S/ 472.44 S/ 472.44 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 472.44 100%
02.06.02 REJILLA DE FIERRO DE 3/8" und 1 S/ 201.38 S/ 201.38 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 1.00 S/ 201.38 100%
02.06.03 ESCALERA TUB F.GVZDO. C/PARANTES DE 2" X PELDAÑOS DE 3/4" m 2.2 S/ 414.65 S/ 912.23 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 2.20 S/ 912.23 100%
3 MITIGACION DE IMPACTO AMBIENTAL
3.01 RECUPERACION DE BOTADERO m3 6238.9 S/ 1.68 S/ 10,481.35 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 6238.90 S/ 10,481.35 100%
3.02 REMOCION DE SUELO CONTAMINADO PARQUE DE MAQUINAS. m2 600 S/ 11.64 S/ 6,984.00 0.00 S/ - S/ - 0.00 0.00 S/ - 0% 600.00 S/ 6,984.00 100%
COSTO DIRECTO S/ 2,939,038.96 S/ 194,002.21 S/ 374,803.42 12.75% S/ 568,805.60 19.35% S/ 2,369,153.72 80.61%
GASTOS GENERALES 10.0000% S/ 293,903.90 S/ 19,400.22 S/ 37,480.34 S/ 56,880.56 S/ 56,880.56
UTILIDAD (10 %) S/ 293,903.90 S/ 19,400.22 S/ 37,480.34 S/ 56,880.56 S/ 56,880.56
SUB TOTAL S/ 3,526,846.75 S/ 232,802.65 S/ 449,764.10 S/ 682,566.72 S/ 2,482,914.84
IGV (18 %) S/ 634,832.42 S/ 41,904.48 S/ 80,957.54 S/ 122,862.01 S/ 446,924.67
VALOR REFERENCIAL DE OBRA S/ 4,161,679.17 S/ 274,707.13 S/ 530,721.64 S/ 805,428.73 S/ 2,929,839.51