PROYECTO: Viviendo Unifamiliar

Universidad Tecnologica de los Andes


Escuela Profesional: Ingenieria Civil
" CRONOGRAMGA VALORIZADO EN LA OBRA"
Curso: Programacion de Obras
Docente: Ing. Luis Alberto Benites Ludeña
Alumno: Rely Cuellar Perez

UNIDA METRA COSTOS S/. MES JULIO -2022 MES AGOSTO - 2022 MES SEPTIEMBRE - 2022
Nº DESCRIPCION COSTO %FINAL
D DO COSTO PARCIAL Metrado Parcial % Metrado Parcial % Metrado Parcial %
UNITARIO
01 OBRAS PRELIMINARES Y OBRAS PROVICIONALES S/ 8,556.25 S/ 8,556.25 100.00% S/ 0.00 0.00% S/ 0.00 0.00% 100%
01.01 Obras Preliminares S/ 7,756.25 S/ 7,756.25 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
01.01.01 Limpieza de Terreno Manual m2 42.50 S/ 7.50 S/ 318.75 42.5 S/ 318.75 0.00 S/ 0.00 42.5 S/ 0.00
01.01.02 Eliminacion de Vegetacion y/o residuos m3 21.25 S/ 300.00 S/ 6,375.00 300 S/ 6,375.00 0.00 S/ 0.00 300 S/ 0.00
01.01.03 Trazo y Replanteo de Terreno m2 42.50 S/ 25.00 S/ 1,062.50 42.5 S/ 1,062.50 0.00 S/ 0.00 42.5 S/ 0.00
01.02 Obras Provicionales S/ 800.00 S/ 800.00 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
01.02.01 Almacen glb 1.00 S/ 800.00 S/ 800.00 1.00 S/ 800.00 0.00 S/ 0.00 0.00 S/ 0.00
02 ESTRUCTURAS S/ 58,977.25 S/ 27,382.20 46.43% S/ 31,595.05 53.57% S/ 0.00 0.00% 100%
02.01 Excavacion de Zapatas S/ 1,319.26 S/ 1,319.26 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.01.01 Excavaciones en Terreno S/ 437.96 S/ 437.96 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.01.01.01 Excavacion de Zapatas Conectadas m3 34.12 S/ 8.70 S/ 296.84 34.12 S/ 296.84 0.00 S/ 0.00 34.12 S/ 0.00
02.01.01.02 Excavacion de Cimientos Corridos m3 7.25 S/ 8.70 S/ 63.08 7.25 S/ 63.08 0.00 S/ 0.00 0.00 S/ 0.00
02.01.01.03 Excavacion de Cimientos m3 8.97 S/ 8.70 S/ 78.04 8.97 S/ 78.04 0.00 S/ 0.00 0.00 S/ 0.00
02.01.02 Eliminación de Material Excedente S/ 881.30 S/ 881.30 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.01.02.01 Eliminación de Material Excedente en Zapatas m3 34.12 S/ 17.50 S/ 597.10 34.12 S/ 597.10 0.00 S/ 0.00 0.00 S/ 0.00
02.01.02.02 Eliminación de Material Excedente en Cimientos m3 16.24 S/ 17.50 S/ 284.20 16.24 S/ 284.20 0.00 S/ 0.00 0.00 S/ 0.00
02.02 Compactado y perfilado de Terreno S/ 283.70 S/ 283.70 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.02.01 Compactado y perfilado para Zapatas m2 22.65 S/ 8.40 S/ 190.26 22.65 S/ 190.26 0.00 S/ 0.00 0.00 S/ 0.00
02.02.02 Compactado y perfilado para Cimientos m2 10.74 S/ 8.70 S/ 93.44 10.74 S/ 93.44 0.00 S/ 0.00 0.00 S/ 0.00
02.03 Acarreo de Materiales S/ 8,559.60 S/ 8,559.60 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.03.01 Acarreo de Agregado Fino y Grueso m3 48.20 S/ 60.00 S/ 2,892.00 48.20 S/ 2,892.00 0.00 S/ 0.00 0.00 S/ 0.00
02.03.02 Acarreo de Cemento Tipo 1 bls 186.15 S/ 24.00 S/ 4,467.60 186.15 S/ 4,467.60 0.00 S/ 0.00 0.00 S/ 0.00
02.03.03 Acarreo de Maquinaria Ligera und 10.00 S/ 120.00 S/ 1,200.00 10.00 S/ 1,200.00 0.00 S/ 0.00 0.00 S/ 0.00
02.04 Solado S/ 328.43 S/ 328.43 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.04.01 Solado en Zapatas m2 22.65 S/ 14.50 S/ 328.43 22.65 S/ 328.43 0.00 S/ 0.00 0.00 S/ 0.00
02.05 Concreto Armado S/ 23,016.22 S/ 16,891.22 73.39% S/ 6,125.00 26.61% S/ 0.00 0.00%
02.05.01 Armado de Acero S/ 7,696.10 S/ 7,696.10 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.01.01 Armado de acero para zapatas kg 37.10 S/ 72.50 S/ 2,689.75 37.10 S/ 2,689.75 0.00 S/ 0.00 0.00 S/ 0.00
02.05.01.02 Armado de acero para cimientos kg 8.00 S/ 61.40 S/ 491.20 8.00 S/ 491.20 0.00 S/ 0.00 0.00 S/ 0.00
02.05.01.03 Armado de acero para Columnas kg 34.10 S/ 67.50 S/ 2,301.75 34.10 S/ 2,301.75 0.00 S/ 0.00 0.00 S/ 0.00
02.05.01.04 Armado de acero para Vigas kg 31.00 S/ 71.40 S/ 2,213.40 31.00 S/ 2,213.40 0.00 S/ 0.00 0.00 S/ 0.00
02.05.02 Encofrado de Estructuras S/ 1,376.00 S/ 1,376.00 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.02.01 Encofrado de Columnas m2 45.00 S/ 21.50 S/ 967.50 45.00 S/ 967.50 0.00 S/ 0.00 0.00 S/ 0.00
02.05.02.02 Encofrado de Cimientos m2 14.00 S/ 21.50 S/ 301.00 14.00 S/ 301.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.02.03 Encofrado de Sobrecimientos m2 5.00 S/ 21.50 S/ 107.50 5.00 S/ 107.50 0.00 S/ 0.00 0.00 S/ 0.00
02.05.03 Concreto f'c=175 kg/cm2 S/ 2,060.00 S/ 2,060.00 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.03.01 Concreto f'c=175 kg/cm2 en columnas m3 8.24 S/ 250.00 S/ 2,060.00 8.24 S/ 2,060.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.04 Concreto f'c=210 kg/cm2 S/ 7,075.00 S/ 950.00 13.43% S/ 6,125.00 86.57% S/ 0.00 0.00%
02.05.04.01 Concreto f'c=210 kg/cm2 en vigas m3 3.80 S/ 250.00 S/ 950.00 3.80 S/ 950.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.04.02 Concreto f'c=210 kg/cm2 en losa aligerada m3 24.50 S/ 250.00 S/ 6,125.00 0.00 S/ 0.00 24.50 S/ 6,125.00 0.00 S/ 0.00
02.05.05 Losa Aligerada S/ 4,809.12 S/ 4,809.12 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.05.01 Encofrado y desencofrado m2 24.00 S/ 21.50 S/ 516.00 24.00 S/ 516.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.02 Colocación de ladrillo 0.30x0.30x0.15m (8 huecos) und 725.00 S/ 2.50 S/ 1,812.50 725.00 S/ 1,812.50 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.03 Colocación de Acero en Losa Aligerada kg 24.50 S/ 67.50 S/ 1,653.75 24.50 S/ 1,653.75 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.04.01 Instalaciones Eléctricas S/ 415.90 S/ 415.90 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.05.04.01.01 Colocacion de Tuberias para II.EE m 55.40 S/ 3.50 S/ 193.90 55.40 S/ 193.90 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.04.01.02 Colocacion de Codos PVC para II.EE und 24.00 S/ 4.00 S/ 96.00 24.00 S/ 96.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.04.01.03 Colocacion de Uniones PVC para II.EE und 28.00 S/ 4.50 S/ 126.00 28.00 S/ 126.00 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.04.02 Instalaciones Sanitarias S/ 410.97 S/ 410.97 100.00% S/ 0.00 0.00% S/ 0.00 0.00%
02.05.05.04.02.01 Colocacion de Tuberias para Agua m 37.10 S/ 5.20 S/ 192.92 37.10 S/ 192.92 0.00 S/ 0.00 0.00 S/ 0.00
02.05.05.04.02.02 Colocacion de Tuberias para Desague m 24.50 S/ 8.90 S/ 218.05 24.50 S/ 218.05 0.00 S/ 0.00 0.00 S/ 0.00
02.06 Escalera doble tramo S/ 2,661.45 S/ 0.00 0.00% S/ 2,661.45 100.00% S/ 0.00 0.00%
02.06.01 Encofrado y desencofrado m2 12.74 S/ 21.50 S/ 273.91 0.00 S/ 0.00 12.74 S/ 273.91 0.00 S/ 0.00

Cronograma Valorizado RELY CUELLAR PEREZ


07/07/2022 3 COD:201600546J
PROYECTO: Viviendo Unifamiliar
Universidad Tecnologica de los Andes
Escuela Profesional: Ingenieria Civil
" CRONOGRAMGA VALORIZADO EN LA OBRA"
Curso: Programacion de Obras
Docente: Ing. Luis Alberto Benites Ludeña
Alumno: Rely Cuellar Perez

UNIDA METRA COSTOS S/. MES JULIO -2022 MES AGOSTO - 2022 MES SEPTIEMBRE - 2022
Nº DESCRIPCION COSTO %FINAL
D DO COSTO PARCIAL Metrado Parcial % Metrado Parcial % Metrado Parcial %
UNITARIO
02.06.02 Armado de acero para escalera kg 26.10 S/ 61.40 S/ 1,602.54 0.00 S/ 0.00 26.10 S/ 1,602.54 0.00 S/ 0.00
02.06.03 Concreto f'c=175 kg/cm2 para escalera m3 3.14 S/ 250.00 S/ 785.00 0.00 S/ 0.00 3.14 S/ 785.00 0.00 S/ 0.00
02.07 Muro portante de Albañileria S/ 9,470.40 S/ 0.00 0.00% S/ 9,470.40 100.00% S/ 0.00 0.00%
02.07.01 Ladrillo KK 0.13x0.24x0.09m und 7424.00 S/ 1.20 S/ 8,908.80 0.00 S/ 0.00 7424.00 S/ 8,908.80 0.00 S/ 0.00
02.07.02 Mortero m3 4.32 S/ 130.00 S/ 561.60 0.00 S/ 0.00 4.32 S/ 561.60 0.00 S/ 0.00
02.08 Contra Piso S/ 11,760.00 S/ 0.00 0.00% S/ 11,760.00 100.00% S/ 0.00 0.00%
02.08.01 Contra Piso A:C 1:5 e=0.10m m2 78.40 S/ 150.00 S/ 11,760.00 0.00 S/ 0.00 78.40 S/ 11,760.00 0.00 S/ 0.00
02.09 Vereda S/ 1,578.20 S/ 0.00 0.00% S/ 1,578.20 100.00% S/ 0.00 0.00%
02.09.01 Encofrado y desencofrado m2 24.80 S/ 21.50 S/ 533.20 0.00 S/ 0.00 24.80 S/ 533.20 0.00 S/ 0.00
02.09.02 Concreto f'c=175 kg/cm2 m3 4.18 S/ 250.00 S/ 1,045.00 0.00 S/ 0.00 4.18 S/ 1,045.00 0.00 S/ 0.00
03 ARQUITECTURA S/ 29,222.36 S/ 148.00 0.51% S/ 5,088.28 17.41% S/ 23,986.08 82.08% 100%
03.01 Revoques S/ 2,720.58 S/ 0.00 0.00% S/ 2,720.58 100.00% S/ 0.00 0.00%
03.01.01 Tarrajeo Interiores e=10mm m2 245.40 S/ 5.50 S/ 1,349.70 0.00 S/ 0.00 245.40 S/ 1,349.70 0.00 S/ 0.00
03.01.02 Tarrajeo Exteriores e=10mm m2 187.10 S/ 5.50 S/ 1,029.05 0.00 S/ 0.00 187.10 S/ 1,029.05 0.00 S/ 0.00
03.01.03 Tarrajeo en Columnas m2 21.65 S/ 5.50 S/ 119.08 0.00 S/ 0.00 21.65 S/ 119.08 0.00 S/ 0.00
03.01.04 Tarrajeo en Vigas m2 14.70 S/ 5.50 S/ 80.85 0.00 S/ 0.00 14.70 S/ 80.85 0.00 S/ 0.00
03.01.05 Bruñas m 354.75 S/ 0.40 S/ 141.90 0.00 S/ 0.00 354.75 S/ 141.90 0.00 S/ 0.00
03.02 Cielorasos S/ 1,388.46 S/ 0.00 0.00% S/ 694.23 50.00% S/ 694.23 50.00%
03.02.01 Cielo Raso con Yeso e=10mm m2 95.10 S/ 14.60 S/ 1,388.46 0.00 S/ 0.00 47.55 S/ 694.23 47.55 S/ 694.23
03.03 Pisos S/ 1,243.15 S/ 0.00 0.00% S/ 0.00 0.00% S/ 1,243.15 100.00%
03.03.01 Piso con Mayólica 0.45x0.45m m2 68.40 S/ 16.50 S/ 1,128.60 0.00 S/ 0.00 0.00 S/ 0.00 68.4 S/ 1,128.60
03.03.02 Ceramica Antideslizante 0.45x0.45m m2 7.90 S/ 14.50 S/ 114.55 0.00 S/ 0.00 0.00 S/ 0.00 7.90 S/ 114.55
03.04 Zocalos y Contrazocalos S/ 877.05 S/ 0.00 0.00% S/ 0.00 0.00% S/ 877.05 100.00%
03.04.01 Zocalos S/ 320.10 S/ 0.00 0.00% S/ 0.00 0.00% S/ 320.10 100.00%
03.04.01.01 Zocalos con cerámica de 0.30x0.15m en SS.HH, h=1.50m m2 19.40 S/ 16.50 S/ 320.10 0.00 S/ 0.00 0.00 S/ 0.00 19.40 S/ 320.10
03.04.02 Contrazocalos S/ 556.95 S/ 0.00 0.00% S/ 0.00 0.00% S/ 556.95 100.00%
03.04.02.01 Contrazocalos con Mayólica h=0.10m m2 38.41 S/ 14.50 S/ 556.95 0.00 S/ 0.00 0.00 S/ 0.00 38.41 S/ 556.95
03.05 Puertas S/ 1,190.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 1,190.00 100.00%
03.05.01 Puerta de madera T-01 und 2.00 S/ 120.00 S/ 240.00 0.00 S/ 0.00 0.00 S/ 0.00 2.00 S/ 240.00
03.05.02 Puerta de madera T-02 und 4.00 S/ 115.00 S/ 460.00 0.00 S/ 0.00 0.00 S/ 0.00 4.00 S/ 460.00
03.05.03 Puerta de madera T-03 und 5.00 S/ 98.00 S/ 490.00 0.00 S/ 0.00 0.00 S/ 0.00 5.00 S/ 490.00
03.06 Ventanas S/ 621.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 621.00 100.00%
03.06.01 Ventana T-01 und 3.00 S/ 57.00 S/ 171.00 0.00 S/ 0.00 0.00 S/ 0.00 3.00 S/ 171.00
03.06.02 Ventana T-02 und 3.00 S/ 45.00 S/ 135.00 0.00 S/ 0.00 0.00 S/ 0.00 3.00 S/ 135.00
03.06.03 Ventana T-03 und 7.00 S/ 45.00 S/ 315.00 0.00 S/ 0.00 0.00 S/ 0.00 7.00 S/ 315.00
03.07 Instalaciones Eléctricas S/ 655.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 655.00 100.00%
03.07.01 Colocado de Focos und 15.00 S/ 7.00 S/ 105.00 0.00 S/ 0.00 0.00 S/ 0.00 15.00 S/ 105.00
03.07.02 Colocado de Interruptores und 11.00 S/ 5.00 S/ 55.00 0.00 S/ 0.00 0.00 S/ 0.00 11.00 S/ 55.00
03.07.03 Colocado de Tomacorriente und 19.00 S/ 5.00 S/ 95.00 0.00 S/ 0.00 0.00 S/ 0.00 19.00 S/ 95.00
03.07.04 Colocado de Tablero und 1.00 S/ 150.00 S/ 150.00 0.00 S/ 0.00 0.00 S/ 0.00 1.00 S/ 150.00
03.07.05 Prueba de energia eléctrica glb 1.00 S/ 250.00 S/ 250.00 0.00 S/ 0.00 0.00 S/ 0.00 1.00 S/ 250.00
03.08 Instalaciones Sanitarias S/ 2,050.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 2,050.00 100.00%
03.08.01 Colocado de Apartos Sanitarios und 9.00 S/ 180.00 S/ 1,620.00 0.00 S/ 0.00 0.00 S/ 0.00 9.00 S/ 1,620.00
03.08.02 Empalmes de Tuberias de agua y desague m 4.50 S/ 40.00 S/ 180.00 0.00 S/ 0.00 0.00 S/ 0.00 4.50 S/ 180.00
03.08.03 Empalme de agua a red externa glb 1.00 S/ 250.00 S/ 250.00 0.00 S/ 0.00 0.00 S/ 0.00 1.00 S/ 250.00
03.09 Limpieza Permanente S/ 1,488.00 S/ 148.00 9.95% S/ 855.60 57.50% S/ 484.40 32.55%
03.09.01 Limpieza permanente en Obra m2 74.40 S/ 20.00 S/ 1,488.00 7.44 S/ 148.00 42.78 S/ 855.60 24.18 S/ 484.40
03.10 Pintura S/ 10,549.13 S/ 0.00 0.00% S/ 817.88 7.75% S/ 9,731.25 92.25%
03.10.01 Pintura en Columnas m2 21.65 S/ 22.50 S/ 487.13 0.00 S/ 0.00 21.65 S/ 487.13 0.00 S/ 0.00
03.10.02 Pintura en Vigas m2 14.70 S/ 22.50 S/ 330.75 0.00 S/ 0.00 14.70 S/ 330.75 0.00 S/ 0.00
03.10.03 Pintura en Interiores m2 245.40 S/ 22.50 S/ 5,521.50 0.00 S/ 0.00 0.00 S/ 0.00 245.40 S/ 5,521.50
03.10.04 Pintura en Exteriores m2 187.10 S/ 22.50 S/ 4,209.75 0.00 S/ 0.00 0.00 S/ 0.00 187.10 S/ 4,209.75
03.11 Limpieza Final en Obra S/ 5,940.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 5,940.00 100.00%

Cronograma Valorizado RELY CUELLAR PEREZ


07/07/2022 3 COD:201600546J
PROYECTO: Viviendo Unifamiliar
Universidad Tecnologica de los Andes
Escuela Profesional: Ingenieria Civil
" CRONOGRAMGA VALORIZADO EN LA OBRA"
Curso: Programacion de Obras
Docente: Ing. Luis Alberto Benites Ludeña
Alumno: Rely Cuellar Perez

UNIDA METRA COSTOS S/. MES JULIO -2022 MES AGOSTO - 2022 MES SEPTIEMBRE - 2022
Nº DESCRIPCION COSTO %FINAL
D DO COSTO PARCIAL Metrado Parcial % Metrado Parcial % Metrado Parcial %
UNITARIO
03.11.01 Limpieza final en obra para entrega m2 19.80 S/ 300.00 S/ 5,940.00 0.00 S/ 0.00 0.00 S/ 0.00 19.80 S/ 5,940.00
03.12 Entrega de Obra S/ 500.00 S/ 0.00 0.00% S/ 0.00 0.00% S/ 500.00 100.00%
03.12.01 Entrega de Obra para Inauguración glb 1.00 S/ 500.00 S/ 500.00 0.00 S/ 0.00 0.00 S/ 0.00 1.00 S/ 500.00

COSTO DIRECTO S/. S/ 96,755.86 S/ 36,086.45 S/ 36,683.33 S/ 23,986.08


GASTOS GENERALES 0.15% S/. S/ 14,513.38 S/ 5,412.97 S/ 5,502.50 S/ 3,597.91
UTILIDAD 0.10% S/. S/ 9,675.59 S/ 3,608.65 S/ 3,668.33 S/ 2,398.61
SUB TOTAL S/. S/ 120,944.82 S/ 45,108.06 S/ 45,854.16 S/ 29,982.59
IMPUESTO GENERAL A LAS VENTAS 0.18% S/. S/ 21,770.07 S/ 8,119.45 S/ 8,253.75 S/ 5,396.87
PRESUPUESTO TOTAL S/. S/ 142,714.89 S/ 53,227.52 37.30% S/ 54,107.91 37.91% S/ 35,379.46 24.79%

Cronograma Valorizado RELY CUELLAR PEREZ


07/07/2022 3 COD:201600546J