OBRA : "MANT PERIODICO DEL CAMINO VECINAL NO PAVIMENTADO TRAMOS, PALLCCA-AREQUIPA-MATUCANA-CORAZON PATA-CHONGOS CARMEN PAMPA Y CHOLA

VALDIVIA, DE LOS CENTRO POBLADOS DE CORAZON PATA Y CHONGOS CARMEN PAMPA, DEL DISTRITO DE LLOCHEGUA - HUANTA - AYACUCHO"
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE LLOCHUEGUA
FECHA : AGOSTO - SETIEMBRE - OCTUBRE
MODALIDAD : CONTRATA

CALENDARIO DE EJECUCION DE OBRA

PRESUPUESTO TOTAL AGOSTO SETIEMBRE OCTUBRE


ITEM DESCRIPCION
UND. CANT. P. UNIT PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO %
01.00. MANTENIMIENTO DE CAMINO VECINAL
01.01. OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und 1.00 S/. 800.00 S/. 800.00 1.00 S/. 800.00 100.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00%
01.01.02 ALQUILER DE CASA PARA ALMACEN DE OBRA mes 3.00 S/. 400.00 S/. 1,200.00 3.00 S/. 1,200.00 100.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00%
01.01.03 CAMPAMENTO PROVISIONAL DE OBRA m2 100.00 S/. 97.05 S/. 9,705.00 100.00 S/. 9,705.00 100.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00%
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 S/. 24,409.47 S/. 24,409.47 0.50 S/. 12,204.74 50.00% 0.00 S/. - 0.00% 0.50 S/. 12,204.74 50.00%
01.02. TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA Y DEFORESTACION ha 6.49 S/. 1,422.77 S/. 9,233.78 3.49 S/. 4,965.47 53.78% 3.00 S/. 4,268.31 46.22% 0.00 S/. - 0.00%
01.02.02 TRAZO, NIVELACION Y REPLANTEO EN EJECUCION DE OBRA km 21.62 S/. 1,294.97 S/. 27,997.25 15.62 S/. 20,227.43 72.25% 6.00 S/. 7,769.82 27.75% 0.00 S/. - 0.00%
01.03. CONFORMACION DE SUPERFICIE DE RODADURA (21 km)
01.03.01 ESCARIFICADO, REGADO Y COMPACTADO A NIVEL DE SUB RASA m2 64860.00 S/. 1.12 S/. 72,643.20 30000.00 S/. 33,600.00 46.25% 30000.00 S/. 33,600.00 46.25% 4860.00 S/. 5,443.20 7.49%
01.03.02 EXTRACCION Y APILAMIENTO DE MATERIAL DE CANTERA m3 8107.50 S/. 3.56 S/. 28,862.70 5000.00 S/. 17,800.00 61.67% 3000.00 S/. 10,680.00 37.00% 107.50 S/. 382.70 1.33%
01.03.03 ZARANDEO DE MATERIAL DE AFIRMADO m3 8107.50 S/. 2.52 S/. 20,430.90 5000.00 S/. 12,600.00 61.67% 3000.00 S/. 7,560.00 37.00% 107.50 S/. 270.90 1.33%
01.03.04 CARGUIO DE MATERIAL AFIRMADO m3 8107.50 S/. 4.38 S/. 35,510.85 5000.00 S/. 21,900.00 61.67% 3000.00 S/. 13,140.00 37.00% 107.50 S/. 470.85 1.33%
01.03.05 TRANSPORTE DE MATERIALES GRANULARES PARA AFIRMADO m3 8107.50 S/. 9.90 S/. 80,264.25 5000.00 S/. 49,500.00 61.67% 3000.00 S/. 29,700.00 37.00% 107.50 S/. 1,064.25 1.33%
01.03.06 EXTENDIDO, COMPACTADO Y RIEGO DE AFIRMADO (e=0.10) m2 64860.00 S/. 1.03 S/. 66,805.80 30000.00 S/. 30,900.00 46.25% 30000.00 S/. 30,900.00 46.25% 4860.00 S/. 5,005.80 7.49%
01.04. OBRAS DE ARTE Y DRENAJE
01.04.01 LIMPIEZA DE CUNETAS LATERALES m 21620.00 S/. 0.79 S/. 17,079.80 10000.00 S/. 7,900.00 46.25% 10000.00 S/. 7,900.00 46.25% 1620.00 S/. 1,279.80 7.49%
01.04.02 LIMPIEZA DE BADENES und 8.00 S/. 213.42 S/. 1,707.36 0.00 S/. - 0.00% 8.00 S/. 1,707.36 100.00% 0.00 S/. - 0.00%
01.04.03 LIMPIEZA DE ALCATARILLAS und 44.00 S/. 320.12 S/. 14,085.28 20.00 S/. 6,402.40 45.45% 14.00 S/. 4,481.68 31.82% 10.00 S/. 3,201.20 22.73%
01.05. ENSAYOS DE CONTROL DE CALIDAD
01.05.01 ENSAYOS DE CONTROL DE COMPACTACION und 21.00 S/. 84.75 S/. 1,779.75 7.00 S/. 593.25 33.33% 7.00 S/. 593.25 33.33% 7.00 S/. 593.25 33.33%
01.06. MANTENIMIENTO DE SEÑALIZACION
01.06.01 SEÑALES INFORMATIVAS (DIMENS. VARIABLE) und 10.00 S/. 79.99 S/. 799.90 0.00 S/. - 0.00% 10.00 S/. 799.90 100.00% 0.00 S/. - 0.00%
01.06.02 SEÑALES PREVENTIVAS (0.60x0.60) und 15.00 S/. 79.99 S/. 1,199.85 0.00 S/. - 0.00% 10.00 S/. 799.90 66.67% 5.00 S/. 399.95 33.33%
01.06.03 HITOS KILÓMETRICOS und 21.00 S/. 79.99 S/. 1,679.79 0.00 S/. - 0.00% 10.00 S/. 799.90 47.62% 11.00 S/. 879.89 52.38%
02.00. MITIGACION AMBIENTAL
02.01. MEDIDAS DE MITIGACION
02.01.01 LIMPIEZA FINAL DE OBRA km 21.62 S/. 106.71 S/. 2,307.07 0.00 S/. - 0.00% 0.00 S/. - 0.00% 21.62 S/. 2,307.07 100.00%
02.01.02 RESTAURACION DE AREA OCUPADA PARA CAMPAMENTOS Y M m2 1500.00 S/. 6.52 S/. 9,780.00 0.00 S/. - 0.00% 0.00 S/. - 0.00% 1500.00 S/. 9,780.00 100.00%
02.02. MEDIDAS DE CONTROL
02.02.01 CONSTRUCCION DE RELLENO SANITARIO m3 15.00 S/. 72.49 S/. 1,087.35 15.00 S/. 1,087.35 100.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00%
02.02.02 CONSTRUCCION DE LETRINAS und 4.00 S/. 550.85 S/. 2,203.40 4.00 S/. 2,203.40 100.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00%
02.03. MEDIDAS DE PREVENCION
02.03.01 CAPACITACION EN EDUCACION AMBIENTAL event 2.00 S/.2,525.60 S/.5,051.20 1.00 S/. 2,525.60 50.00% 0.50 S/. 1,262.80 25.00% 0.50 S/. 1,262.80 25.00%
03.00. CONFORMACION Y ORGANIZACION DEL COMITE DE MANTENIMIENTO VIAL
03.01. SEGURIDAD Y SALUD
03.01.01 EQUIPAMIENTO DE PROTECCIÓN INDIVIADUAL ADECUADO glb 1.00 S/. 5,842.20 S/.5,842.20 0.50 S/. 2,921.10 50.00% 0.25 S/. 1,460.55 25.00% 0.25 S/. 1,460.55 25.00%
03.01.02 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD und 10.00 S/. 203.25 S/.2,032.50 5.00 S/. 1,016.25 50.00% 2.50 S/. 508.13 25.00% 2.50 S/. 508.13 25.00%
03.02. MODULO DE CAPACITACION
03.02.01 CONFORMACION DEL COMITÉ DE MANTENIMIENTO VIAL event 1.00 S/. 1,500.00 S/.1,500.00 0.50 S/. 750.00 50.00% 0.25 S/. 375.00 25.00% 0.25 S/. 375.00 25.00%
03.02.02 CAPACITACION DEL COMITÉ DE MANTENIMIENTO VIAL event 1.00 S/. 2,132.72 S/.2,132.72 0.50 S/. 1,066.36 50.00% 0.25 S/. 533.18 25.00% 0.25 S/. 533.18 25.00%

COSTO DIRECTO 448,131.37 241,868.34 158,839.78 47,423.25


GASTOS GENERALES 13.46% 60,302.44 32,546.82 21,374.15 6,381.47
UTILIDAD 7.01% 31,396.70 16,945.63 11,128.53 3,322.54
SUB TOTAL 539,830.51 291,360.79 191,342.46 57,127.26
IGV (18% ST) 18.00% 97,169.49 52,444.94 34,441.64 10,282.91
PRESUPUESTO DE OBRA 637,000.00 343,805.74 225,784.10 67,410.17
GASTOS DE SUPERVISION 45,238.40 15,079.47 15,079.47 15,079.47
PRESUPUESTO TOTAL 682,238.40 358,885.20 240,863.56 82,489.63

AVANCE FISICO DE OBRA PROGRAMADO 53.97% 35.44% 10.58%