ANEXO DE VOLUMEN DE OBRA

CONTRATISTA: CONSTRUCTECA AYORA


FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
1 Limpieza y nivelacion manual del terreno m2
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M2
1 A1 6.83 4.45 - 1 30.39 -
2 A2 7.99 6.83 - 1 54.57 -
3 A3 6.83 4.33 - 1 29.57 -
4 A4 6.94 4.52 - 1 31.37 -
5 A5 8.08 6.94 - 1 56.08 -
6 A6 6.94 4.40 - 1 30.54 -
7 A7 13.77 0.18 - 1 1.24 Se calcula como area de triangulo
-
-
233.76

TOTAL EJECUTADO EN ESTE PERIODO (A): 233.76


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 233.76
CANTIDAD PRESUPUESTADA 234.20
DIFERENCIA 0.44
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
2 Replanteo con equipo topografico m2
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M2
1 A1 6.83 4.45 - 1 30.39 -
2 A2 7.99 6.83 - 1 54.57 -
3 A3 6.83 4.33 - 1 29.57 -
4 A4 6.94 4.52 - 1 31.37 -
5 A5 8.08 6.94 - 1 56.08 -
6 A6 6.94 4.40 - 1 30.54 -
7 A7 13.77 0.18 - 1 1.24 Se calcula como a. de triangulo
-
-
233.76

TOTAL EJECUTADO EN ESTE PERIODO (A): 233.76


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 233.76
CANTIDAD PRESUPUESTADA 234.20
DIFERENCIA 0.44
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
3 Excavacion a mano de estructuras m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 P1 1.60 1.60 2.00 4 20.48 -
2 P2 3.00 3.00 2.00 2 36.00 -
3 P3 1.60 1.40 2.00 2 8.96 -
4 P4 2.10 2.10 2.00 2 17.64 -
5 P5 2.60 1.60 2.00 2 16.64 -
6 Cd1 3.82 0.40 0.40 1 0.61 -
7 Cd2 7.58 0.40 0.40 1 1.21 -
8 Cd3 3.89 0.40 0.40 1 0.62 -
9 Cd4 3.78 0.40 0.40 1 0.60 -
10 Cd5 7.45 0.40 0.40 1 1.19 -
11 Cd6 3.87 0.40 0.40 1 0.62 -
12 Cd7 3.91 0.40 0.40 1 0.63 -
13 Cd8 7.67 0.40 0.40 1 1.23 -
14 Cd9 3.80 0.40 0.40 1 0.61 -
15 Cd10 6.23 0.40 0.40 1 1.00 -
16 Cd11 6.26 0.40 0.40 1 1.00 -
17 Cd12 6.33 0.40 0.40 1 1.01 -
18 Cd13 6.32 0.40 0.40 1 1.01 -
19 Cd14 6.34 0.40 0.40 1 1.01 -
20 Cd15 6.18 0.40 0.40 1 0.99 -
21 Cd16 6.08 0.40 0.40 1 0.97 -
22 Cd17 6.13 0.40 0.40 1 0.98 -
- -
115.01

TOTAL EJECUTADO EN ESTE PERIODO (A): 115.01


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 115.01
CANTIDAD PRESUPUESTADA 51.93
DIFERENCIA (63.08)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
4 Relleno manual compactado m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 E1 1.60 1.60 2.00 4 20.48 -
2 E2 3.00 3.00 2.00 2 36.00 -
3 E3 1.60 1.40 2.00 2 8.96 -
4 E4 2.10 2.10 2.00 2 17.64 -
5 E5 2.60 1.60 2.00 2 16.64 -
6 R1 1.60 1.60 0.10 -4 (1.02) Se resta
7 R2 3.00 3.00 0.10 -2 (1.80) Se resta
8 R3 1.60 1.40 0.10 -2 (0.45) Se resta
9 R4 2.10 2.10 0.10 -2 (0.88) Se resta
10 R5 2.60 1.60 0.10 -2 (0.83) Se resta
11 P1 1.60 1.60 0.45 -4 (4.61) Se resta
12 P2 3.00 3.00 0.45 -2 (8.10) Se resta
13 P3 1.60 1.40 0.45 -2 (2.02) Se resta
14 P4 2.10 2.10 0.45 -2 (3.97) Se resta
15 P5 2.60 1.60 0.45 -2 (3.74) Se resta
16 M1 1.60 1.60 0.40 -4 (4.10) Se resta
17 M2 3.00 3.00 0.40 -2 (7.20) Se resta
18 M3 1.60 1.40 0.40 -2 (1.79) Se resta
19 M4 2.10 2.10 0.40 -2 (3.53) Se resta
20 M5 2.60 1.60 0.40 -2 (3.33) Se resta
21 C1 0.40 0.40 0.93 -8 (1.19) Se resta
22 C2 0.40 0.40 0.93 -2 (0.30) Se resta
23 C3 - 0.56 0.93 -2 (0.92) Se calcula como vol. de cilindro
- -
49.94

TOTAL EJECUTADO EN ESTE PERIODO (A): 49.94


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 49.94
CANTIDAD PRESUPUESTADA 15.53
DIFERENCIA (34.41)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
5 Replantillo de H S 180Kg/cm2. suelo compactado m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

NOTA: Todos los replantillos tienen un espesor de 0.10 m


ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 R1 1.60 1.60 0.10 4 1.02
2 R2 3.00 3.00 0.10 2 1.80
3 R3 1.60 1.40 0.10 2 0.45
4 R4 2.10 2.10 0.10 2 0.88
5 R5 2.60 1.60 0.10 2 0.83
- -
4.98

TOTAL EJECUTADO EN ESTE PERIODO (A): 4.98


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 4.98
CANTIDAD PRESUPUESTADA 4.70
DIFERENCIA (0.28)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
6 HS de 210Kg/cm2 agregado max=19mm en plintos m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

NOTA: Todos los plintos tienen un espesor de 0.45 m


ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 P1 1.60 1.60 0.45 4 4.61
2 P2 3.00 3.00 0.45 2 8.10
3 P3 1.60 1.40 0.45 2 2.02
4 P4 2.10 2.10 0.45 2 3.97
5 P5 2.60 1.60 0.45 2 3.74
- -
22.44

TOTAL EJECUTADO EN ESTE PERIODO (A): 22.44


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 22.44
CANTIDAD PRESUPUESTADA 22.14
DIFERENCIA (0.30)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
7 H Ciclopeo de 180Kg/cm2 cimientos m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 Cd1 3.82 0.40 0.40 1 0.61
2 Cd2 7.58 0.40 0.40 1 1.21
3 Cd3 3.89 0.40 0.40 1 0.62
4 Cd4 3.78 0.40 0.40 1 0.60
5 Cd5 7.45 0.40 0.40 1 1.19
6 Cd6 3.87 0.40 0.40 1 0.62
7 Cd7 3.91 0.40 0.40 1 0.63
8 Cd8 7.67 0.40 0.40 1 1.23
9 Cd9 3.80 0.40 0.40 1 0.61
10 Cd10 6.23 0.40 0.40 1 1.00
11 Cd11 6.26 0.40 0.40 1 1.00
12 Cd12 6.33 0.40 0.40 1 1.01
13 Cd13 6.32 0.40 0.40 1 1.01
14 Cd14 6.34 0.40 0.40 1 1.01
15 Cd15 6.18 0.40 0.40 1 0.99
16 Cd16 6.08 0.40 0.40 1 0.97
17 Cd17 6.13 0.40 0.40 1 6.13 -
20.44

TOTAL EJECUTADO EN ESTE PERIODO (A): 20.44


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 20.44
CANTIDAD PRESUPUESTADA 17.80
DIFERENCIA (2.64)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
8 H S de 210Kg/cm2 agregado max=19mm en cadena, columnas y vigas peraltadas m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
SECCIÓN COLUMNA TIPO 1 SECCIÓN COLUMNA TIPO 1 SECCIÓN COLUMNA TIPO 1
N-1.50 - N+0.18 N+0.18 - N+1.68 N+1.68 - N+8.86

0.40 0.40 0.40

8Ø16Mc201 8Ø16 Mc201 8Ø16 Mc 201


0.40
0.40

0.40

EØ10 @ 10cm y 20cm Mc 202

EØ10 @ 10cm Mc 202 Ø8 @ 10cm y 20cm Mc 203 EØ10 @ 10cm y 20cm Mc 202
86EØ10Mc202 22Ø8Mc203
0.03 0.03 0.03

SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2
N-1.50 - N+0.18 N+0.18 - N+1.68 N+1.68 - N+8.86 N+8.86 - N+10.35

0.40 0.40 0.40 0.40

8Ø16Mc204 8Ø16 Mc 204 8Ø16 Mc 204 8Ø16 Mc 204


0.40

0.40

0.40

0.40

EØ10 @ 10cm y 20cm Mc 202

EØ10 @ 10cm Mc 202 Ø8 @ 10cm y 20cm Mc 203 EØ10 @ 10cm y 20cm Mc 202 EØ10 @ 20cm Mc 202
94EØ10Mc202 22Ø8Mc203
0.03 0.03 0.03 0.03

SECCIÓN COLUMNA TIPO 3 SECCIÓN COLUMNA TIPO 3


N-1.50 - N+0.18
Ø0
0.56 .56
0.03
0.56

EØ10 @ 10cm y 20cm Mc 206


60EØ10Mc206

10Ø16Mc205
ANEXO FOTOGRAFICO
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 Cd1 3.82 0.20 0.30 1 0.23
2 Cd2 7.58 0.20 0.30 1 0.45
3 Cd3 3.89 0.20 0.30 1 0.23
4 Cd4 3.78 0.20 0.30 1 0.23
5 Cd5 7.45 0.20 0.30 1 0.45
6 Cd6 3.87 0.20 0.30 1 0.23
7 Cd7 3.91 0.20 0.30 1 0.23
8 Cd8 7.67 0.30 0.30 1 0.69
9 Cd9 3.80 0.20 0.30 1 0.23
10 Cd10 6.23 0.20 0.30 1 0.37
11 Cd11 6.26 0.20 0.30 1 0.38
12 Cd12 6.33 0.20 0.30 1 0.38
13 Cd13 6.32 0.20 0.30 1 0.38
14 Cd14 6.34 0.20 0.30 1 0.38
15 Cd15 6.18 0.20 0.30 1 0.37
16 Cd16 6.08 0.20 0.30 1 0.36
17 Cd17 6.13 0.20 0.30 1 0.37
4 C1 0.42 0.40 2.58 1 0.43 Primer piso
5 C2 0.41 0.42 2.56 1 0.44 Primer piso
6 C3 0.41 0.41 2.57 1 0.43 Primer piso
7 C4 0.41 0.42 2.56 1 0.44 Primer piso
8 C5 0.40 0.40 2.56 1 0.41 Primer piso
9 C6 0.54 2.56 1 0.59 Se calcula como V. de cilindro PP
10 C7 0.54 2.56 1 0.59 Se calcula como V. de cilindro PP
11 C8 0.41 0.40 2.54 1 0.42 Primer piso
12 C9 0.40 0.40 2.53 1 0.40 Primer piso
13 C10 0.42 0.40 2.54 1 0.43 Primer piso
14 C11 0.40 0.41 2.55 1 0.42 Primer piso
15 C12 0.40 0.41 2.54 1 0.42 Primer piso
16 C13 0.30 0.30 2.53 1 0.23 Primer piso
17 C14 0.31 0.30 2.53 1 0.24 Primer piso
18 C1 0.42 0.40 2.37 1 0.40 Segundo piso
19 C2 0.41 0.42 2.37 1 0.41 Segundo piso
20 C3 0.41 0.41 2.37 1 0.40 Segundo piso
21 C4 0.41 0.42 2.36 1 0.41 Segundo piso
22 C5 0.40 0.40 2.37 1 0.38 Segundo piso
23 C6 0.54 2.38 1 0.55 Se calcula como V. de cilindro SP
24 C7 0.54 2.37 1 0.54 Se calcula como V. de cilindro SP
25 C8 0.41 0.40 2.37 1 0.39 Segundo piso
26 C9 0.40 0.40 2.38 1 0.38 Segundo piso
27 C10 0.42 0.40 2.39 1 0.40 Segundo piso
28 C11 0.40 0.41 2.40 1 0.39 Segundo piso
29 C12 0.40 0.41 2.38 1 0.39 Segundo piso
30 V1 3.82 0.30 0.35 1 0.40 V3 Seccion V +3.17
31 V2 7.58 0.30 0.35 1 0.80 V3 Seccion V +3.17
32 V3 3.89 0.30 0.35 1 0.41 V3 Seccion V +3.17
33 V4 3.78 0.30 0.35 1 0.40 V2 Seccion V +3.17
34 V5 7.45 0.30 0.35 1 0.78 V2 Seccion V +3.17
35 V6 3.87 0.30 0.35 1 0.41 V2 Seccion V +3.17
36 V7 3.91 0.30 0.35 1 0.41 V1 Seccion V +3.17
37 V8 7.67 0.30 0.35 1 0.81 V1 Seccion V +3.17
38 V9 3.80 0.30 0.35 1 0.40 V1 Seccion V +3.17
39 V10 6.23 0.30 0.35 1 0.65 V4 Seccion V +3.17
40 V11 6.26 0.30 0.35 1 0.66 V5 Seccion V +3.17
41 V12 6.33 0.30 0.35 1 0.66 V5 Seccion V +3.17
42 V13 6.32 0.30 0.35 1 0.66 V4 Seccion V +3.17
43 V14 6.34 0.30 0.35 1 0.67 V4 Seccion V +3.17
44 V15 6.18 0.30 0.35 1 0.65 V5 Seccion V +3.17
45 V16 6.08 0.30 0.35 1 0.64 V5 Seccion V +3.17
46 V17 6.13 0.30 0.35 1 0.64 V4 Seccion V +3.17
47 V18 3.38 0.30 0.20 1 0.20 Viga de soporte 1
48 Muro 1 6.23 0.20 1.34 1 1.67 Muro de A1 a A2
49 Muro 2 6.34 0.20 1.24 1 1.57 Muro de A2 a A3
50 Gradas - - - 1 4.92 Calculo anexado

- -
35.30

CÁLCULOS: GRADAS
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 1 2.10 1.20 0.17 1 0.43 Grada 1 (Descanso)
2 2 1.50 0.30 0.17 1 0.04 Grada 2
3 3 1.50 0.30 0.17 1 0.04 Grada 3
4 4 1.50 0.30 0.17 1 0.04 Grada 4
5 5 1.50 0.30 0.17 1 0.04 Grada 5
6 6 1.50 0.30 0.17 1 0.04 Grada 6
7 7 1.50 0.30 0.17 1 0.04 Grada 7
8 8 1.50 0.30 0.17 1 0.04 Grada 8
9 L1 2.41 0.17 1.50 1 0.61 Espesor Losa gradas 1
10 9 4.20 1.50 0.26 1 1.64 Grada 9 (Descanso)
11 10 1.35 0.30 0.17 2 0.07 Grada 10
12 11 1.35 0.30 0.17 2 0.07 Grada 11
13 12 1.35 0.30 0.17 2 0.07 Grada 12
14 13 1.35 0.30 0.17 2 0.07 Grada 13
15 14 1.35 0.30 0.17 2 0.07 Grada 14
16 15 1.35 0.30 0.17 2 0.07 Grada 15
17 16 1.35 0.30 0.17 2 0.07 Grada 16
18 17 1.35 0.80 0.25 2 0.54 Grada 17
19 L2 2.46 0.17 1.35 2 1.13 Espesor Losa gradas 2
- -
5.12

TOTAL EJECUTADO EN ESTE PERIODO (A): 35.30


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 35.30
CANTIDAD PRESUPUESTADA 30.70
DIFERENCIA (4.60)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO
DESCRIPCIÓN UNIDAD
No.
9 Acero de refuerzo FY=4200Kg/cm Kg
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
SECCIÓN COLUMNA TIPO 1 SECCIÓN COLUMNA TIPO 1 SECCIÓN COLUMNA TIPO 1
N-1.50 - N+0.18 N+0.18 - N+1.68 N+1.68 - N+8.86

0.40 0.40 0.40

8Ø16Mc201 8Ø16 Mc201 8Ø16 Mc 201


0.40
0.40

0.40

EØ10 @ 10cm y 20cm Mc 202

EØ10 @ 10cm Mc 202 Ø8 @ 10cm y 20cm Mc 203 EØ10 @ 10cm y 20cm Mc 202
86EØ10Mc202 22Ø8Mc203
0.03 0.03 0.03

SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2 SECCIÓN COLUMNA TIPO 2
N-1.50 - N+0.18 N+0.18 - N+1.68 N+1.68 - N+8.86 N+8.86 - N+10.35

0.40 0.40 0.40 0.40

8Ø16Mc204 8Ø16 Mc 204 8Ø16 Mc 204 8Ø16 Mc 204


0.40

0.40

0.40

0.40

EØ10 @ 10cm y 20cm Mc 202

EØ10 @ 10cm Mc 202 Ø8 @ 10cm y 20cm Mc 203 EØ10 @ 10cm y 20cm Mc 202 EØ10 @ 20cm Mc 202
94EØ10Mc202 22Ø8Mc203
0.03 0.03 0.03 0.03

SECCIÓN COLUMNA TIPO 3 SECCIÓN COLUMNA TIPO 3


N-1.50 - N+0.18
Ø0
0.56 .56
0.03
0.56

EØ10 @ 10cm y 20cm Mc 206


60EØ10Mc206

10Ø16Mc205
UBICACIÓN
N-1.50
N+0.18
N+1.68
N+3.17
N+6.06
N+8.86
N+10.35

COLUMNA TIPO
Losa
Losa

Cadena

4Ø16Mc201
Tipo 1
Total 86 Estribos

4Ø16Mc201
A3, B3, C3, D3
A1, B1, C1, D1

21 Estribos 19 Estribos 23 Estribos


14Estribos
L L/4 L/2 L/4 L/4 L/2 L/4 L/4 L/2 L/4
14E@.1 5E@.2 5E@.2 7E@.2
8E@.1 8E@.1 7E@.1 7E@.1 8E@.1 8E@.1
Losa
Losa

Cadena

4Ø16Mc204
Total 94 Estribos

4Ø16Mc204

Tipo 2
A2, D2
21 Estribos 19 Estribos 23 Estribos 8Estribos
14Estribos
L L/4 L/2 L/4 L/4 L/2 L/4 L/4 L/2 L/4 L
14E@.1 5E@.2 5E@.2 7E@.2 8E@.2
8E@.1 8E@.1 7E@.1 7E@.1 8E@.1 8E@.1

Escala:1-------50
Losa
Losa

Cadena
5Ø16Mc205

Tipo 3
B2, C2
Total 60 Estribos

5Ø16Mc205
21 Estribos 19 Estribos
14Estribos
L L/4 L/2 L/4 L/4 L/2 L/4
14E@.1 5E@.2 5E@.2
8E@.1 8E@.1 7E@.1 7E@.1

Losa

Cadena
3Ø16Mc207
3Ø16Mc207

Total 21 Estribos

Tipo 4
E1, F1
21 Estribos
L/4 L/2 L/4
8E@.1 5E@.2 8E@.1
B C
0.30 0.30
8.00

7.70

2Ø16Mc314´
0.17

77 Estribos 2Ø16Mc314´
L
Total 77 Estribos
77E@.1

VIGA DE AMARRE 1
A B C D

1Ø16Mc409
3Ø16Mc401 6Ø12Mc408
1Ø12Mc438
1Ø16Mc402 3Ø16Mc406 3Ø16Mc407
6Ø12Mc403 1Ø12Mc439
0.82

14Ø16Mc404 14Ø16Mc405

1 1

3Ø12Mc416
11Ø12Mc410

6Ø16Mc412
20Ø12Mc421

4Ø12Mc415
2Ø12Mc414

VIGA DE AMARRE 1
1Ø12Mc440
8Ø16Mc422
11Ø12Mc423

A1' A1'
1Ø12Mc441

2 2
3Ø12Mc425

2Ø16Mc417
6Ø16Mc424

2Ø16Mc419
14Ø12Mc427

3Ø12Mc418
0.81

0.81
10Ø16Mc426

4Ø16Mc420
4Ø16Mc428

A'

11Ø12Mc411

6Ø16Mc413

3 3
A'

12Ø16Mc430
12Ø16Mc433
5Ø12Mc431 3Ø12Mc434
24Ø12Mc429 24Ø12Mc437
7Ø12Mc432 6Ø12Mc435

3Ø12Mc436

A B C D
Losa Nivel +3.17
A B C D
4.41 8.00 4.41

0.40 3.91 0.40 7.60 0.40 3.93 0.40

3 Estribos
0.80
3Ø16Mc312 3Ø16Mc313

3Ø16Mc314 3Ø16Mc315
30 Estribos 60 Estribos 30 Estribos
L/4 L/2 L/4 L/4 L/2 L/4 L/4 L/2 L/4
10E@.1 9E@.2 10E@.1 19E@.1 18E@.2 19E@.1 10E@.1 9E@.2 10E@.1
0.80 Total 120 Estribos

VIGA V1 - EJE 1- N+6.06

A B C D
4.41 8.00 4.41

0.40 3.83 0.56 7.44 0.56 3.85 0.40

3 Estribos
0.80
3Ø16Mc312 3Ø16Mc313

3Ø16Mc314 3Ø16Mc315
29 Estribos 59 Estribos 29 Estribos
L/4 L/2 L/4 L/4 L/2 L/4 L/4 L/2 L/4
10E@.1 9E@.2 10E@.1 18E@.1 19E@.2 18E@.1 10E@.1 9E@.2 10E@.1
0.80 Total 117 Estribos

VIGA V2 - EJE 2 - N+6.06

A B C D
4.41 8.00 4.57

0.40 3.91 0.40 7.60 0.40 4.09 0.40

0.80
3Ø16Mc312 3Ø16Mc316

3Ø16Mc314 3Ø16Mc317
30 Estribos 67 Estribos 30 Estribos
L/4 L/2 L/4 L/4 L/2 L/4 L/4 L/2 L/4
10E@.1 9E@.2 10E@.1 19E@.1 18E@.2 19E@.1 11E@.1 9E@.2 11E@.1
0.80 Total 127 Estribos

VIGA V3 - EJE 3 - N+6.06

1 2 3

6.65 6.65

0.40 6.25 0.40 6.25 0.40

0.80

3 Estribos
3Ø16Mc318 3Ø16Mc319

3Ø16Mc320 3Ø16Mc321
47 Estribos 50 Estribos
L/4 L/2 L/4 L/4 L/2 L/4
16E@.1 15E@.2 16E@.1 16E@.1 14E@.2 16E@.1
0.80 Total 97 Estribos

VIGA V4 - N+6.06
1 2
Ó
3

6.65 6.65

0.40 6.17 0.56 6.17 0.40


0.80

3 Estribos
3Ø16Mc318 3Ø16Mc319

3Ø16Mc320 3Ø16Mc321
47 Estribos 50 Estribos
L/4 L/2 L/4 L/4 L/2 L/4
16E@.1 14E@.2 16E@.1 16E@.1 14E@.2 16E@.1
0.80 Total 97 Estribos

VIGA V5 - N+6.06
Ó
ANEXO FOTOGRAFICO
ANEXO FOTOGRAFICO
CÁLCULOS:
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
MARCAS 100 200
Marca 100
101 C 12 88 1.44 0.13 0.00 0.00 1.70 149.60 132.84
102 C 12 80 2.84 0.13 0.00 0.00 3.10 248.00 220.22
103 C 12 18 1.44 0.13 0.00 0.00 1.70 30.60 27.17
104 C 12 22 1.24 0.13 0.00 0.00 1.50 33.00 29.30
105 C 12 56 1.94 0.13 0.00 0.00 2.20 123.20 109.40
106 C 12 34 1.44 0.13 0.00 0.00 1.70 57.80 51.33
107 C 12 22 2.44 0.13 0.00 0.00 2.70 59.40 52.27
108 L 12 2 4.85 0.25 0.00 0.00 5.10 10.20 9.06
109 I1 16 6 9.00 0.00 0.00 0.00 9.00 54.00 85.21
110 L 12 2 4.86 0.24 0.00 0.00 5.10 10.20 9.06
111 L 12 2 4.82 0.23 0.00 0.00 5.05 10.10 8.97
112 L 12 2 4.83 0.22 0.00 0.00 5.05 10.10 8.97
113 L 12 6 8.80 0.25 0.00 0.00 9.05 54.30 48.22
114 L 12 4 11.67 0.23 0.00 0.00 11.90 47.60 42.27
115 L 12 2 5.88 0.22 0.00 0.00 6.10 12.20 10.83
116 L 12 2 8.95 0.25 0.00 0.00 9.20 18.40 16.34
117 L 12 2 6.03 0.22 0.00 0.00 6.25 12.50 11.10
118 L 12 8 10.45 0.25 0.00 0.00 10.70 85.60 76.01
119 L 12 8 3.80 0.25 0.00 0.00 4.05 32.40 28.77
120 L 12 8 8.20 0.25 0.00 0.00 8.45 67.80 60.03
121 L 12 8 6.00 0.25 0.00 0.00 6.25 50.00 44.40
122 O 10 685 0.13 0.23 0.00 0.09 0.90 616.50 380.38
123 O 10 57 0.23 0.23 0.00 0.09 1.10 62.70 38.69
Marcas
200
201 C 16 64 10.23 0.31 0.00 0.00 10.85 694.40 1095.76
202 O 10 876 0.34 0.34 0.00 0.12 1.60 1401.60 864.79
203 C 8 220 0.34 0.13 0.00 0.00 0.60 132.00 52.14
204 L 16 16 11.70 0.30 0.00 0.00 12.00 192.00 302.98
205 C 16 20 7.43 0.31 0.00 0.00 8.05 161.00 254.06
206 O 10 120 0.40 0.40 0.00 0.00 1.60 192.00 118.46
207 C 16 6 3.39 0.28 0.00 0.00 3.95 23.70 37.40
208 O 10 21 0.24 0.24 0.00 0.12 1.20 25.20 15.55
RESUMEN DE MATERIALES
Ø (mm) 8 10 12 14 16 18 20 22 25 28
W (Kg/m) 0.395 0.617 0.89 1.208 1.578 2.000 2.466 2.984 3.853 4.834
L (m) 132.00 2298.00 1123.00 1125.10
PESO (Kg) 52.14 1417.87 988.24 1775.41
Wtot (Kg) 4233.66
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
MARCAS 300
Marca 300
301 L 16 9 8.80 0.55 0.00 0.00 9.35 84.15 132.79
302 L 16 6 9.01 0.54 0.00 0.00 9.55 57.30 90.42
303 L 16 9 11.50 0.50 0.00 0.00 12.00 108.00 170.42
304 L 16 6 6.26 0.54 0.00 0.00 6.80 40.80 64.38
305 L 16 3 9.16 0.54 0.00 0.00 9.70 29.10 45.92
306 L 16 3 6.41 0.54 0.00 0.00 6.95 20.85 32.90
307 L 16 12 10.45 0.55 0.00 0.00 11.00 132.00 208.30
308 L 16 12 4.00 0.55 0.00 0.00 4.55 54.60 86.16
309 L 16 12 8.20 0.50 0.00 0.00 8.70 104.40 164.74
310 L 16 12 6.20 0.50 0.00 0.00 6.70 80.40 126.87
311 O 10 752 0.24 0.54 0.00 0.12 1.80 1353.60 835.17
312´ C 16 4 4.45 0.15 0.00 0.00 4.75 19.00 29.98
313´ O 10 30 0.14 0.24 0.00 0.12 1.00 30.00 18.51
314´ C 16 4 8.21 0.17 0.00 0.00 8.55 34.20 53.97
315´ O 10 77 0.25 0.16 0.00 0.09 1.00 77.00 47.51

RESUMEN DE MATERIALES
Ø (mm) 8 10 12 14 16 18 20 22 25 28
W (Kg/m) 0.395 0.617 0.888 1.208 1.578 2.000 2.466 2.984 3.853 4.834
L (m) 0 1460.60 0 0 764.80 0 0 0 0 0
PESO (Kg) 0.00 901.19 0.00 0.00 1206.85 0.00 0.00 0.00 0.00 0.00
Wtot (Kg) 2108.04
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
MARCAS 300
Marca 300
312 L 16 9 8.80 0.45 0.00 0.00 9.25 83.25 131.37
313 L 16 6 9.01 0.44 0.00 0.00 9.45 56.70 89.47
314 L 16 9 11.50 0.40 0.00 0.00 11.90 107.10 169.00
315 L 16 6 6.26 0.44 0.00 0.00 6.70 40.20 63.44
316 L 16 3 9.16 0.44 0.00 0.00 9.60 28.80 45.45
317 L 16 3 6.41 0.44 0.00 0.00 6.85 20.55 32.43
318 L 16 12 10.45 0.45 0.00 0.00 10.90 130.80 206.40
319 L 16 12 4.00 0.45 0.00 0.00 4.45 53.40 84.27
320 L 16 12 8.20 0.40 0.00 0.00 8.60 103.20 162.85
321 L 16 12 6.20 0.40 0.00 0.00 6.60 79.20 124.98
322 O 10 752 0.24 0.44 0.00 0.12 1.60 1203.20 742.37
323 C 16 4 7.01 0.22 0.00 0.00 7.45 29.80 47.02
324 O 10 95 0.14 0.24 0.00 0.07 0.90 85.50 52.75
325 C 16 4 8.21 0.17 0.00 0.00 8.55 34.20 53.97
326 O 10 77 0.25 0.16 0.00 0.09 1.00 77.00 47.51
327 C 16 4 4.66 0.17 0.00 0.00 5.00 20.00 31.56
328 O 10 41 0.10 0.15 0.00 0.10 0.70 32.80 20.24

RESUMEN DE MATERIALES
Ø (mm) 8 10 12 14 16 18 20 22 25 28
W (Kg/m) 0.395 0.617 0.888 1.208 1.578 2.000 2.466 2.984 3.853 4.834
L (m) 0 1398.50 0 0 787.20 0 0 0 0 0
PESO (Kg) 0.00 862.87 0.00 0.00 1242.20 0.00 0.00 0.00 0.00 0.00
W (Kg) 2105.8 Wtotal
Wvigas 253.05 Resta viga de amarre 2, viga de amarre 3, viga de soporte 2
Wtot (Kg) 1852.75 Acero Total
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
Marca 400
401 C 16 3 6.81 0.22 0.00 0.00 7.25 21.75 34.32
402 C 16 1 7.11 0.22 0.00 0.00 7.55 7.55 11.91
403 C 12 6 6.31 0.22 0.00 0.00 6.75 40.50 35.96
404 L 16 14 11.68 0.22 0.00 0.00 11.90 166.60 262.89
405 L 16 14 6.18 0.22 0.00 0.00 6.40 89.60 141.39
406 C 16 3 2.61 0.22 0.00 0.00 3.05 9.15 14.44
407 C 16 3 2.61 0.22 0.00 0.00 3.05 9.15 14.44
408 C 12 6 6.36 0.22 0.00 0.00 6.80 40.80 36.23
409 C 16 1 7.46 0.22 0.00 0.00 7.90 7.90 12.47
410 L 12 11 11.63 0.22 0.00 0.00 11.85 130.35 115.75
411 L 12 11 2.83 0.22 0.00 0.00 3.05 33.55 29.79
412 L 16 6 11.63 0.22 0.00 0.00 11.85 71.10 112.20
413 L 16 6 2.83 0.22 0.00 0.00 3.05 18.30 28.88
414 C 12 2 1.21 0.22 0.00 0.00 1.65 3.30 2.93
415 C 12 4 0.66 0.22 0.00 0.00 1.10 4.40 3.91
416 C 12 3 5.01 0.22 0.00 0.00 5.45 16.35 14.52
417 C 16 2 9.76 0.22 0.00 0.00 10.20 20.40 32.19
418 C 12 3 6.91 0.22 0.00 0.00 7.35 22.05 19.58
419 C 16 2 6.91 0.22 0.00 0.00 7.35 14.70 23.20
420 C 16 4 7.31 0.22 0.00 0.00 7.75 31.00 48.92
421 C 12 20 2.10 0.20 0.00 0.00 2.50 50.00 44.40
422 C 16 8 4.00 0.20 0.00 0.00 4.40 35.20 55.55
423 C 12 11 4.00 0.20 0.00 0.00 4.40 48.40 42.98
424 C 16 6 2.10 0.20 0.00 0.00 2.50 15.00 23.67
425 C 12 3 2.10 0.20 0.00 0.00 2.50 7.50 6.66
426 C 16 10 2.10 0.20 0.00 0.00 2.50 25.00 39.45
427 C 12 14 2.10 0.20 0.00 0.00 2.50 35.00 31.08
428 C 16 4 2.50 0.20 0.00 0.00 2.90 11.60 18.30
429 C 12 24 1.45 0.20 0.00 0.00 1.85 44.40 39.43
430 C 16 12 3.85 0.20 0.00 0.00 4.25 51.00 80.48
431 C 12 5 3.85 0.20 0.00 0.00 4.25 21.25 18.87
432 C 12 7 3.25 0.20 0.00 0.00 3.65 25.55 22.69
433 C 16 12 4.05 0.20 0.00 0.00 4.45 53.40 84.27
434 C 12 3 4.05 0.20 0.00 0.00 4.45 13.35 11.85
435 C 12 6 3.40 0.20 0.00 0.00 3.80 22.80 20.25
436 C 12 3 2.70 0.20 0.00 0.00 3.10 9.30 8.26
437 C 12 24 1.55 0.20 0.00 0.00 1.95 46.80 41.56
438 C 12 1 6.41 0.22 0.00 0.00 6.85 6.85 6.08
439 C 12 1 3.81 0.22 0.00 0.00 4.25 4.25 3.77
440 C 12 1 3.81 0.22 0.00 0.00 4.25 4.25 3.77
441 C 12 1 6.41 0.22 0.00 0.00 6.85 6.85 6.08
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
Marca 500
501 L 16 2 3.38 0.22 0.00 0.00 3.60 7.20 11.36
502 L 16 2 10.28 0.22 0.00 0.00 10.50 21.00 33.14
503 L 12 3 3.38 0.22 0.00 0.00 3.60 10.80 9.59
504 L 12 3 10.28 0.22 0.00 0.00 10.50 31.50 27.97
505 C 16 3 6.91 0.22 0.00 0.00 7.35 22.05 34.79
506 C 16 1 7.46 0.22 0.00 0.00 7.90 7.90 12.47
507 C 12 3 6.31 0.22 0.00 0.00 6.75 20.25 17.98
508 L 16 12 11.68 0.22 0.00 0.00 11.90 142.80 225.34
509 L 16 12 6.18 0.22 0.00 0.00 6.40 76.80 121.19
510 C 16 1 3.51 0.22 0.00 0.00 3.95 3.95 6.23
511 C 16 3 2.61 0.22 0.00 0.00 3.05 9.15 14.44
512 C 16 3 2.61 0.22 0.00 0.00 3.05 9.15 14.44
513 C 12 3 6.36 0.22 0.00 0.00 6.80 20.40 18.12
514 L 16 6 11.63 0.22 0.00 0.00 11.85 71.10 112.20
515 L 16 6 2.83 0.22 0.00 0.00 3.05 18.30 28.88
516 L 12 7 11.63 0.22 0.00 0.00 11.85 82.95 73.66
517 L 12 7 2.83 0.22 0.00 0.00 3.05 21.35 18.96
518 C 12 7 2.16 0.22 0.00 0.00 2.60 18.20 16.16
519 C 12 6 2.26 0.22 0.00 0.00 2.70 16.20 14.39
520 C 16 2 11.36 0.22 0.00 0.00 11.80 23.60 37.24
521 C 12 3 6.91 0.22 0.00 0.00 7.35 22.05 19.58
522 C 16 2 6.91 0.22 0.00 0.00 7.35 14.70 23.20
523 C 12 4 8.66 0.22 0.00 0.00 9.10 36.40 32.32
524 C 16 4 7.31 0.22 0.00 0.00 7.75 31.00 48.92
525 C 12 20 2.10 0.20 0.00 0.00 2.50 50.00 44.40
526 C 12 11 3.90 0.20 0.00 0.00 4.30 47.30 42.00
527 C 16 8 3.90 0.20 0.00 0.00 4.30 34.40 54.28
528 C 16 6 2.10 0.20 0.00 0.00 2.50 15.00 23.67
529 C 12 3 2.10 0.20 0.00 0.00 2.50 7.50 6.66
530 C 16 10 2.10 0.20 0.00 0.00 2.50 25.00 39.45
531 C 12 14 2.10 0.20 0.00 0.00 2.50 35.00 31.08
532 C 16 4 2.50 0.20 0.00 0.00 2.90 11.60 18.30
533 C 12 24 1.45 0.20 0.00 0.00 1.85 44.40 39.43
534 C 16 12 3.85 0.20 0.00 0.00 4.25 51.00 80.48
535 C 12 9 3.85 0.20 0.00 0.00 4.25 38.25 33.97
536 C 12 3 3.35 0.20 0.00 0.00 3.75 11.25 9.99
537 C 12 3 3.40 0.20 0.00 0.00 3.80 11.40 10.12
538 C 16 12 4.05 0.20 0.00 0.00 4.45 53.40 84.27
539 C 12 4 2.65 0.20 0.00 0.00 3.05 12.20 10.83
540 C 12 5 3.00 0.20 0.00 0.00 3.40 17.00 15.10
541 C 12 18 1.55 0.20 0.00 0.00 1.95 35.10 31.17
542 C 12 1 6.41 0.22 0.00 0.00 6.85 6.85 6.08
543 C 12 1 3.81 0.22 0.00 0.00 4.25 4.25 3.77
544 C 12 1 3.81 0.22 0.00 0.00 4.25 4.25 3.77
545 C 12 1 6.41 0.22 0.00 0.00 6.85 6.85 6.08
Ø DIMENSIONES LONG. LONG. PESO
Mc TIPO No. Observ.
mm a b c g Desar. (m) TOTAL (Kg)
Marca 600
601 C 12 14 1.45 0.10 0.00 0.00 1.65 23.10 20.51
602 C 12 7 2.05 0.10 0.00 0.00 2.25 15.75 13.99
603 C 12 4 1.48 0.11 0.00 0.00 1.70 6.80 6.04
604 C 12 8 1.20 0.10 0.00 0.00 1.40 11.20 9.95
605 C 12 8 1.20 0.10 0.00 0.00 1.40 11.20 9.95
606 C 12 4 1.48 0.11 0.00 0.00 1.70 6.80 6.04
607 I1 12 22 0.20 0.00 0.00 0.00 0.20 4.40 3.91
608 G 12 8 1.45 0.10 0.15 0.00 1.70 13.60 12.08
609 G 12 8 4.44 0.11 0.15 0.00 4.70 37.60 33.39
610 V 12 8 2.50 0.10 0.10 0.00 2.70 21.60 19.18
611 C 12 8 4.15 0.15 0.00 0.00 4.45 35.60 31.61
612 C 12 7 4.15 0.15 0.00 0.00 4.45 31.15 27.66
613 C 12 2 1.28 0.11 0.00 0.00 1.50 3.00 2.66
614 C 12 26 1.30 0.10 0.00 0.00 1.50 39.00 34.63
615 G 12 16 2.55 0.10 0.10 0.00 2.75 44.00 39.07
616 G 12 16 5.10 0.10 0.15 0.00 5.35 85.60 76.01
617 G 12 16 1.55 0.10 0.15 0.00 1.80 28.80 25.57
618 C 12 2 1.28 0.16 0.00 0.00 1.60 3.20 2.84
619 C 12 3 1.28 0.16 0.00 0.00 1.60 4.80 4.26
620 C 12 17 1.28 0.11 0.00 0.00 1.50 25.50 22.64
621 G 12 8 1.80 0.11 0.19 0.00 2.10 16.80 14.92
622 G 12 8 5.18 0.10 0.17 0.00 5.45 43.60 38.72
623 C 12 8 2.40 0.10 0.00 0.00 2.60 20.80 18.47
624 C 12 6 2.63 0.11 0.00 0.00 2.85 17.10 15.18
625 C 12 1 1.28 0.11 0.00 0.00 1.50 1.50 1.33
626 C 12 7 2.63 0.11 0.00 0.00 2.85 19.95 17.72
627 C 12 8 2.40 0.10 0.00 0.00 2.60 20.80 18.47
628 G 12 8 5.06 0.18 0.11 0.00 5.35 42.80 38.01
629 G 12 8 1.81 0.18 0.11 0.00 2.10 16.80 14.92
630 C 12 2 1.28 0.11 0.00 0.00 1.50 3.00 2.66
631 C 12 3 1.28 0.16 0.00 0.00 1.60 4.80 4.26
632 C 12 14 1.28 0.11 0.00 0.00 1.50 21.00 18.65
RESUMEN DE MATERIALES
Ø (mm) 8 10 12 14 16 18 20 22 25 28
W (Kg/m) 0.395 0.617 0.888 1.208 1.578 2.000 2.466 2.984 3.853 4.834
L (m) 0 0 1931.20 0 1307.50 0 0 0 0 0
PESO (Kg) 0.00 0.00 1714.91 0.00 2063.24 0.00 0.00 0.00 0.00 0.00
W (Kg) 3778.15 W total
WL2 (Kg) 1567.47 Resta acero losa 2
WE2 (Kg) 233.05 Resta escaleras de segundo piso
Wtot (Kg) 1977.63 Acero Total

TOTAL EJECUTADO EN ESTE PERIODO (A): 10,172.08


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 10,172.08
CANTIDAD PRESUPUESTADA 5,616.00
DIFERENCIA (4,556.08)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
10 Contrapiso empedrado 12cm H S 180Kg/cm2. E=6cm m2
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M2
1 A1 6.83 4.45 - 1 30.39
2 A2 7.99 6.83 - 1 54.57
3 A3 6.83 4.33 - 1 29.57
4 A4 6.94 4.52 - 1 31.37
5 A5 8.08 6.94 - 1 56.08
6 A6 6.94 4.40 - 1 30.54
7 A7 8.43 1.64 - 1 13.83

- -
246.35

TOTAL EJECUTADO EN ESTE PERIODO (A): 246.35


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 246.35
CANTIDAD PRESUPUESTADA 234.20
DIFERENCIA (12.15)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
11 H S de 210Kg/cm2 Incluye encofrado Losa m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
A B C D

1 1

VIGA DE AMARRE 1

A1' A1'

2 2

A'
3 3

A'

A B C D
Losa Nivel +3.17
Escala:1-------100
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 losa 16.92 13.80 0.25 1 58.37 Dim. Medidas en obra
2 Casetones 0.40 0.20 0.20 -1306 (20.90) Casetones Volumen
3 Gradas 4.23 3.46 0.25 -1 (3.66) Hueco de Gradas
4 Ascensor 1.66 1.55 0.25 -1 (0.64) Hueco de "Ascensor"
5 Hueco C. 5.27 0.25 -1 (1.32) Hueco semicircular
6 Balcon 2.20 0.60 0.25 1 0.55 Balcon segundo piso
32.40

TOTAL EJECUTADO EN ESTE PERIODO (A): 32.40


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 32.40
CANTIDAD PRESUPUESTADA 38.16
DIFERENCIA 5.76
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
12 Bloque alivianado 40X20X20 cm u
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

A B C D

1 1

VIGA DE AMARRE 1

A1' A1'

2 2

A'

3 3
A'

A B C D
Losa Nivel +3.17
Escala:1-------100
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 Caseton 1.00 1.00 2.00 619 1,238.00 Casetones de dos bloques
2 Caseton 1.00 1.00 1.00 68 68.00 Casetones de un bloque
1,306.00

TOTAL EJECUTADO EN ESTE PERIODO (A): 1,306.00


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 1,306.00
CANTIDAD PRESUPUESTADA 1,144.00
DIFERENCIA (162.00)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
17 Tuberia PVC 110 mm m
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

Red existente a conectarse

Ø160mm Ø160mm
BAll 110mm Ø160mm Ø160mm BAll 110mm
11

Ø 16

110 L4
0
L9 10m

Ø200mm
0m
Ø1

Ø7

BASS 110mm
m
10

5m

Ø110mm
m

m
11
m

Ø160mm Ø160mm
L7

m
m

0
m
m

Ø50mm
m
0

10

L8
10
11

Ø1

Ø1
Ø1

5m
m

60m
m

Ø7
10
L6

Ø1

m
10 8 10
0

Ø75mm
11

11 7 11
Cocina
L5

12 12

Ø75mm
6
0
11

13 5 13
Ø75mm
14 4 14
15 3 15

Ø160mm
16 2 16
110 L1 17 17 Ø75mm

Sube

N+ 0.18

N+ 0.18

Sala de exposiciones

Oficina Multiuso

N+ 0.18
Ø200mm

N+ 0.18

110 L3
Ø110mm BASS 110mm
Ø110mm
BAll 110mm BAll 110mm

L.f Ingreso General L.f


N+ 0.18
110 L1 110 L2
Acera

N± 0.00
A la red publica

Calle Simon Bolivar


ANEXO FOTOGRAFICO
CÁLCULOS:
LARGO - - CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OBSERVACIONES
M - - u M
1 110 L1 7.76 - - 1 7.76
2 110 L2 7.86 - - 1 7.86
3 110 L3 7.89 - - 1 7.89
4 110 L4 3.27 - - 1 3.27
5 110 L5 3.00 - - 1 3.00
6 110 L6 0.82 - - 1 0.82
7 110 L7 0.39 - - 1 0.39
8 110 L8 0.33 - - 1 0.33
9 110 L9 0.30 - - 1 0.30
31.62

TOTAL EJECUTADO EN ESTE PERIODO (A): 31.62


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 31.62
CANTIDAD PRESUPUESTADA 12.00
DIFERENCIA (19.62)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
18 Caja de revision de 0.80x0.80 m (H=1-1.2M) incluye cerco metalico u
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
Red existente a conectarse

160 L6 160 L5 160 L4 160 L3


N+ 0..38
Ø160mm Ø160mm
BAll 110mm Ø160mm Ø160mm BAll 110mm
Ø75mm

110 L9
Ø50mm

160 L1 110 L4
m
m

Ø200mm
60
Ø1

Ø7

Ø1

Ø1

160 L7 BASS 110mm


10

10
5m

110 L7 110 L8 Ø110mm


m

m
m
m

Ø160mm Ø160mm
m

m
m

Ø50mm
m

Ø1
10

10

60
Ø1

9
Ø1

5m

110 L6 m
m

m
m

Ø7
10
Ø1

10 8 10
Ø75mm

11 7 11 160 L2
110 L5 Cocina
12 12

Ø75mm
6
13 5 13
Ø75mm
14 4 14
15 3 15

Ø160mm
16 2 16 160 L1
110 L1 17 17 Ø75mm

Sube
200 L1

N+ 0.18

N+ 0.18

Sala de exposiciones

Pasillo Oficina Multiuso

N+ 0.18
Ø200mm

N+ 0.18

110 L3
Ø110mm BASS 110mm
Ø110mm
BAll 110mm BAll 110mm

L.f Ingreso General L.f


N+ 0.18
110 L1 110 L2
Acera

N± 0.00
A la red publica

Calle Simon Bolivar


ANEXO FOTOGRAFICO
CÁLCULOS:
LARGO - - CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OBSERVACIONES
M - - u M
1 Caja 1.00 - - 4 4.00 60x60 con 10 de margen externo

4.00

TOTAL EJECUTADO EN ESTE PERIODO (A): 4.00


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 4.00
CANTIDAD PRESUPUESTADA 6.00
DIFERENCIA 2.00
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
19 Tuberia PVC 160 mm m
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
LARGO - - CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OBSERVACIONES
M - - u M
1 160 L1 1.66 - - 1 1.66
2 160 L2 3.06 - - 1 3.06
3 160 L3 3.33 - - 1 3.33
4 160 L4 3.93 - - 1 3.93
5 160 L5 3.89 - - 1 3.89
6 160 L6 3.42 - - 1 3.42
7 160 L7 1.03 - - 1 1.03
8 160 L8 3.65 - - 1 3.65
23.97

TOTAL EJECUTADO EN ESTE PERIODO (A): 23.97


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 23.97
CANTIDAD PRESUPUESTADA 23.70
DIFERENCIA
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
20 Tuberia PVC 220 mm m
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

Red existente a conectarse

Ø160mm Ø160mm
BAll 110mm Ø160mm Ø160mm BAll 110mm
Ø16
0

Ø200mm
mm
Ø1

Ø7

Ø1

BASS 110mm
10

5m

10

Ø110mm
m

m
m

Ø160mm Ø160mm
m
m

m
m

Ø50mm
m
10

10
Ø1

Ø1
Ø1

5m
m

60
m

Ø7
10

mm
Ø1

10 8 10
Ø75mm

11 7 11
Cocina
12 12

Ø75mm
6
13 5 13
Ø75mm
14 4 14
15 3 15

Ø160mm
16 2 16
110 L1 17 17 Ø75mm

Sube
200 L1

N+ 0.18

N+ 0.18

Sala de exposiciones

Oficina Multiuso

N+ 0.18
Ø200mm

N+ 0.18

Ø110mm BASS 110mm


Ø110mm
BAll 110mm BAll 110mm

L.f Ingreso General L.f


N+ 0.18

Acera

N± 0.00
A la red publica
ANEXO FOTOGRAFICO
CÁLCULOS:
LARGO - - CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OBSERVACIONES
M - - u M
1 200 L1 12.92 - - 1 12.92
12.92

TOTAL EJECUTADO EN ESTE PERIODO (A): 12.92


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 12.92
CANTIDAD PRESUPUESTADA 9.60
DIFERENCIA (3.32)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
RN.1 Mejoramiento de suelo m3
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

NOTA: Todas las zapatas tienen un mejoramiento de 0.40 m


ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 M1 1.60 1.60 0.40 4 4.10 -
2 M2 3.00 3.00 0.40 2 7.20 -
3 M3 1.60 1.40 0.40 2 1.79 -
4 M4 2.10 2.10 0.40 2 3.53 -
5 M5 2.60 1.60 0.40 2 3.33 -
- -
19.95

TOTAL EJECUTADO EN ESTE PERIODO (A): 19.95


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 19.95
CANTIDAD PRESUPUESTADA -
DIFERENCIA (19.95)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
RN.2 Malla electrosoldada 150x150x4.5 mm. m2
COMPONENTE DE PRESUPUESTO
GRÁFICOS:
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M2
1 A1 6.83 4.45 - 1 30.39 -
2 A2 7.99 6.83 - 1 54.57 -
3 A3 6.83 4.33 - 1 29.57 -
4 A4 6.94 4.52 - 1 31.37 -
5 A5 8.08 6.94 - 1 56.08 -
6 A6 6.94 4.40 - 1 30.54 -
7 A7 - - - 0 - -
8 Caja 0.80 0.80 - -1 (0.64) Caja de revision
9 Losa 16.92 13.80 - 1 233.50 Dim medidas en obra
10 Gradas 4.20 3.40 - -1 (14.28) -
11 Ascensor 1.65 1.57 - -1 (2.59) -
12 Hueco 5.27 1.00 - -1 (5.27) Semicirculo
13 Balcon 2.20 0.60 - 1 1.32 -
444.56

TOTAL EJECUTADO EN ESTE PERIODO (A): 444.56


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 444.56
CANTIDAD PRESUPUESTADA -
DIFERENCIA (444.56)
ANEXO DE VOLUMEN DE OBRA
CONTRATISTA: CONSTRUCTECA AYORA
FISCALIZADOR: ING. ANDRES DAVID FLORES RODRIGUEZ
ADMINISTRADOR: ING. MARCO CARGUACHI
PLANILLA No. 1
CONTRATO: MCO-GADPREE-004-2022
NOMBRE DEL PROYECTO
RUBRO No. DESCRIPCIÓN UNIDAD
RN.3 Malla electrosoldada 150x150x10 mm. m2
COMPONENTE DE PRESUPUESTO
GRÁFICOS:

0.20

0.20

Mallas Ø10 (15x15cm)


1.50

1.30
Mallas Ø10 (15x15cm)

0.50
0.50
0.03

0.03
0.20

0.20

Cadena Cd4 Ejes1-2 Cadena Cd4 Ejes2-3

MURO EJE A2-A3


MURO EJE A1-A2
ANEXO FOTOGRAFICO
CÁLCULOS:
ALTURA/PR
LARGO ANCHO/RAD CANTIDAD TOTAL
ÍTEM DESCRIPCIÓN OF OBSERVACIONES
M M M u M3
1 M1 6.23 - 1.34 1 8.35 -
2 M2 6.34 - 1.24 1 7.86 -
16.21

TOTAL EJECUTADO EN ESTE PERIODO (A): 16.21


TOTAL PLANILLADO ANTERIORMENTE (B): -
TOTAL A LA FECHA (C=A+B): 16.21
CANTIDAD PRESUPUESTADA -
DIFERENCIA (16.21)

Firmado electrónicamente por:


MIGUEL ESTEBAN
TERAN CAICEDO

CONSTRUCTECA AYORA ING. ANDRES DAVID FLORES RODRIGUEZ


CONTRATISTA FISCALIZACION