SE TIENE LOS SIGUIENTES PRESUPUESTOS

Presupuesto Base 4,178,512.86 1.1.- CALCULAR EL FACTOR DE RELACION


Presupuesto Oferta 4,202,098.44
1.2.- CALCULAR LA DIFERENCIA ENTRE LA SUMATORIA DE LAS VALORIZACIONES
F.R. = 1.00564 COBRADAS APLICANDO EL FR Y EL PRESUPUESTO OFERTA

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 TOTAL


522,314.11 785,560.42 802,274.47 898,380.26 773,024.88 396,958.72 4,178,512.86

APLICANDO EL FR:

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 TOTAL


525,259.96 789,990.98 806,799.30 903,447.13 777,384.74 399,197.57 4,202,079.68

DIFERENCIA DE: -18.76

EXISTE UN DEFICIT, PERO LA DIFERENCIA DEBERÍA SER CERO, YA QUE SE PAGA POR EL MONTO OFERTADO,
NO POR EL PRESUPUESTADO, POR LO QUE SE APLICA LO SIGUIENTE:

1° CALCULAMOS EL FACTOR DE RELACIÓN CON REDONDEO A 5 DECIMALES:

F.R = 1.00564

2° CORROBORAMOS SI AL USAR ESTE FACTOR DE RELACIÓN AL FINAL NOS DARÁ EL MISMO MONTO OFERTADO

4,178,512.86 x 1.00564 = 4,202,079.68

4,202,098.44 - 4,202,079.68 = 18.76

Existe un deficit de S/. 18.76

3° ES POR ELLO QUE CUANDO SE REALICE EL PAGO DE LAS VALORIZACIONES EL ULTIMO MONTO DEBE SER EL SALDO DEL
MONTO OFERTADO Y EL PAGO DE VALORIZACIONES FINALMENTE QUEDARÍA COMO SE MUESTRA, SIENDO CERO LA DIFERENCIA:

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 TOTAL


528,222.43 794,446.53 811,349.65 908,542.57 781,769.19 377,768.07 4,202,098.44
IU DESCRIPCION
2 AL ACERO LISO
3 AC ACERO CORRUGADO FECHA BASE: Aug-14
4 AF AGREGADO FINO FECHA VALORIZACION Mar-15
5 AG AGREGADO GRUESO MONTO VALORIZADO 324,512.64
17 BL BLOQUE Y LADRILLOS
21 C CEMENTO TIPO I 2.1.- Calcular Kr :
39 GU IGPC 2.2.- Calcular el Reajuste :
47 J MANO DE OBRA
48 MN MAQUINARIA NACIONAL
53 P PETROLEO

FORMULA POLINOMICA

Jr 0.244BLr + 0.756Cr 0.185ALr + 0.815ACr


K= 0.214 + 0.186 + 0.161 +
Jo 0.244BLo + 0.756Co 0.185ALo + 0815ACo

0.246AFr + 0.754AGr 0.695MNr + 0.305Pr GUr


0.125 + 0.072 + 0.242
0.246AFo + 0.754AGo 0.695MNo + 0.305Po GUo

DESCIPCION SIMB. IU C. INC %PART IU - AGO 2014 IU - MAR 2015 k


MANO DE OBRA J 47 0.214 100.0% 523.70 523.15 0.21
BLOQUES Y LADRILLOS BL 17 24.4% 744.87 750.04
0.186 0.197
CEMENTO TIPO I C 21 75.6% 354.74 389.65
ACERO LISO AL 2 18.5% 483.35 522.3
0.161 0.177
ACERO CORRUGADO AC 3 81.5% 468.10 515.52
AGREGADO FINO AF 4 24.6% 1000.89 1,032.11
0.125 0.128
AGREGADO GRUESO AG 5 75.4% 393.59 400.7
MAQUINARIA NACIONAL MN 48 69.5% 339.02 352.93
0.072 0.063
PETROLEO P 53 30.5% 896.75 650.37
I.G.P.C GU 39 0.242 100.0% 402.37 409.9 0.247
k- MAR 2015 1.026

kr = 1.026

REAJUSTE = (kr-1)*V
REAJUSTE = 8,437.33
3.1.- Elaborar la formula polinomica, detallarlo
𝐾=0.190 𝐽𝑟/𝐽𝑜+0.259[(0.093𝐴𝐿𝑟+0.834𝐴𝐶𝑟+0.073𝑀𝑟)/(0.093𝐴𝐿𝑜+0.834𝐴𝐶𝑜+0.073𝑀𝑜)]+0.082[(0.244𝐴𝐹𝑟+0.756𝐴𝐺𝑟)/(0.244𝐴𝐹𝑜+0.756𝐴𝐺𝑜)]+0.120[(0.383𝐵𝐿𝑟+0.617𝐶𝑟)/(0.383𝐵𝐿𝑜+0.617𝐶𝑜)]
+0.082[(0.134𝐻𝑀𝑟+0.866𝑀𝑁𝑟)/(0.134𝐻𝑀𝑜+0.866𝑀𝑁𝑜)]+0.065[(0.256𝑀𝐼𝑟+0.354𝑃𝑟+0.232𝐷𝑟)/(0.256𝑀𝐼𝑟+0.354𝑃𝑟+0.232𝐷𝑟)]+0.202 𝐺𝑈𝑟/𝐺𝑈𝑜

AGRUPAMIENTO PREL.
IU DESCRIPCION MONTO (S/.) %INC COEF. INC. % PART. MONOMIO
47 MANO DE OBRA 68,127.36 0.190 0.190 0.190 1.000 1
2 ACERO LISO 8,480.96 0.024 0.093
3 ACERO CORRUGADO 77,389.57 0.216 0.259 0.259 0.834 2
43 MADERA NACIONAL 6,737.83 0.019 0.073
4 AGREGADO FINO 7,148.56 0.020 0.244
0.082 0.082 4
5 AGREGADO GRUESO 22,356.24 0.062 0.756
17 BLOQUES Y LADRILLOS 16,368.80 0.046 0.383
0.120 0.120 3
21 CEMENTO TIPO I 26,378.64 0.074 0.617
37 HERR. MANUALES 3,406.39 0.011 0.134
0.082 0.082 5
48 MAQ. NACIONAL 25,548.66 0.071 0.866
49 MAQ. IMPORTADA 7,672.18 0.021 0.256
53 PETROLEO 8,375.40 0.023 0.065 0.065 0.354 6
30 DÓLAR 7,462.14 0.021 0.323
39 IGPC 72,387.55 0.202 0.202 0.202 1.000 7
357,840.28 1.000 1.000 1.000