Pb= S/.43,789.98
Fpb= 01/07/2012
INICIO: OCTUBRE
DURACIÓN: 3 MESES
PRESUPUESTO CONTRACTUAL
PRESUPUESTO CONTRACTUAL
ITEM DESCRIPCIÓN
UND. CANT. P.UNIT PARCIAL
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20
1.02.03 ACERO KG. 500.00 4.94 2,470.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40
1.03.03 ACERO KG. 700.00 4.94 3,458.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32
COSTO DIRECTO 35,031.98
GG (15%) 5,254.80
U ( 10%) 3,503.20
SUBTOTAL 43,789.98
IGV (18%) 7,882.20
PRESUPUESTO TOTAL 51,672.18
% AVANCE 100.00
VALORIZACIÓN DE OBRA PRINCIPAL N°02
DEL 01 AL 30 NOVIEMBRE 2019
Nota: Los Subindices "o" representan los Indices de Precios a la fecha del Presupuesto Base y los Subinddices
"r" son los indices a la fecha del reajuste
REINTEGROS
V = 16,749.39
k= 1.013
R = V x (K-1)
N° FECHA V K-1 R
1 OCT. 7,731.97 0.012 92.78
2 NOV 16,749.39 0.013 217.74
310.52
92.78
217.74
A PAGAR
Vb = V + R
IGV = 0.18 x Vb
TOTAL = Vn + IGV
CUADRO RESUMEN DE VALORIZACIÓN N° 02
(DEL 1 AL 30 NOVIEMBRE 2019)
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: S/.
PRESUPUESTO CONTRATADO: S/.
TOTAL CONTRACTUAL
Avances en porcentaje
DEDUCCIONES (D)
TOTAL DEDUCCIONES
AMORTIZACIONES (A)
16,967.13
VALORIZACIÓN NETA (VN = VB - A)
RETENCIONES ( C )
FONDOS DE GARANTIA (5% X VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL