Está en la página 1de 3

BALANCE INICIAL DEL PRESUPUESTO GENERAL

PROYECTO: CONSTRUCCION SISTEMA MICRORIEGO MONDRAGON FASE II (POTOSI)


CODIGO FPS-05-00004175 MONTO: 967,588,34 Bs.
CONTRATO C-FPS-05-002988 PLAZO: 150 Dias Calendario
CONTRATISTA EMPRESA CONSTRUCTORA "ASIS" Fecha Inicio: 10-Sep-13
FECHA 7-Oct-13 Fecha concluision 9-Mar-14

Precio Unitario CONTRATO ORIGINAL CONTRATO ADJUDICADO BALANCE INICIAL


ITEM DESCRIPCION UNID. (PU) CANT. PRECIO CANT. P. U. PRECIO CANTIDAD PRECIO
Original PROGR. TOTAL Bs. Adjudicado Adjudicado TOTAL Bs. BALANCE TOTAL Bs.
M01 - CAMARA DE ENTRADA 15,788.18 9,762.44 11,154.76
1 REPLANTEO DE OBRAS m² 9.55 5.04 48.13 5.04 13.74 69.25 5.25 72.14
2 EXCAVACION DE 0-2 M SUELO DURO m³ 91.58 1.51 138.29 1,51 115,63 #VALUE! 5.80 #VALUE!
3 FILTRO CON MATERIAL GRADUADO m³ 268.46 0.44 118.12 0,44 199,15 #VALUE! 0.39 #VALUE!
4 SOLADURA DE PIEDRA m² - 5,04 37,29 #VALUE! 5.25 #VALUE!
5 REVOQUE ENLUCIDO DE CEMENTO CON SIKA m² - 10,01 170,77 #VALUE! 10.16 #VALUE!
6 COMPUERTA METALICA TIPO BASTON 0.30 X 0.30 pza 3,718.59 1.00 3,718.59 1,00 320,89 #VALUE! 1.00 #VALUE!
7 CAMARA DE LLAVES H C SEGUN DISEÑO pza 984.43 1.00 984.43 1,00 384,94 #VALUE! 1.00 #VALUE!
8 TAPA METALICA DE VISITA DE 1/8" pza - 1,54 204,86 #VALUE! 1.60 #VALUE!
9 TAPA LOSA DE Hº Aº R 21 m³ - 0,35 790,23 #VALUE! 0.35 #VALUE!
10 ACCESORIOS CAMARA DE ENTRADA glb 4,095.20 1.00 4,095.20 1,00 463,09 #VALUE! 1.00 #VALUE!
11 MURO DE H° A° H 21 m³ 3,056.79 1.42 4,340.64 1,55 3.150,66 #VALUE! 1.54 #VALUE!
12 LOSA DE FONDO DE Hº Aº E = 0.10 M M3 2,233.12 1.05 2,344.78 0,35 2.540,31 #VALUE! 0.70 #VALUE!
M02 - PROV. Y COLOC. DE ASPERSORES 30,193.00 77,924.40 77,924.40
13 PROVISION Y COLOCADO DE ASPERSORES MOVILES glb 1,509.65 20.00 30,193.00 20,00 775,72 #VALUE! 20.00 15,514.40
14 MANGUERA DE GOMA 1" P/ ASPERSION + ACCESORIOS pza - 1.000,00 62,41 #VALUE! 1,000.00 62,410.00
M03 - 2 PUENTES COLGANTES L = 15M +/- 5M 50,967.82 19,488.90 19,795.17
15 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ml 25,483.91 2.00 50,967.82 30,00 0,64 #VALUE! 30.00 #VALUE!
16 EXCAVACION DE 0-2 M SUELO DURO m³ - 10,00 115,63 #VALUE! 6.05 #VALUE!
17 PROV. Y TENDIDO DE TUBERIA F.G. D=4 PULG m - 34,00 213,62 #VALUE! 34.00 #VALUE!
18 Hº Cº FUNDACIONES (1:2:3-50% PD) m³ - 4,00 372,20 #VALUE! 6.05 #VALUE!
19 PROV. Y MONTAJE ACUEDUCTO L = 15 M +/- 5M glb - 2,00 1.504,90 #VALUE! 2.00 #VALUE!
20 TORRES F G PARA PUENTES PASARELAS pza - 4,00 109,53 #VALUE! 4.00 #VALUE!
21 DADOS DE HºCº ( 1:2:3 ) 50% PIEDRA m³ - 8,00 764,20 #VALUE! 8.00 #VALUE!
M04 - PUENTES COLGANTES L=30M +/- 5M 31,647.90 16,189.80 15,163.76
22 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ml 31,647.90 1.00 31,647.90 30.00 0.64 19.20 30.00 19.20
23 EXCAVACION DE 0-2 M SUELO DURO m³ - 12.00 115.63 1,387.56 3.03 350.36
24 PROV. Y TENDIDO DE TUBERIA F.G. DE 2 PULGADA m - 32.00 369.63 11,828.16 32.00 11,828.16
Precio Unitario CONTRATO ORIGINAL CONTRATO ADJUDICADO BALANCE INICIAL
ITEM DESCRIPCION UNID. (PU) CANT. PRECIO CANT. P. U. PRECIO CANTIDAD PRECIO
Original PROGR. TOTAL Bs. Adjudicado Adjudicado TOTAL Bs. BALANCE TOTAL Bs.
25 Hº Cº FUNDACIONES (1:2:3-50% PD) m³ - 3.00 372.20 1,116.60 3.03 1,127.77
26 PROV. Y MONTAJE ACUEDUCTO L = 30 M +/- 4M glb - 1.00 90.82 90.82 1.00 90.82
27 TORRES F G PARA PUENTES PASARELAS pza - 2.00 109.53 219.06 2.00 219.06
28 DADOS DE HºCº ( 1:2:3 ) 50% PIEDRA m³ - 2.00 764.20 1,528.40 2.00 1,528.40
M05 - OBRAS GENERALES 10,935.98 4,760.23 4,760.23
29 PROV. Y COLOCACION DE LETRERO OBRAS FPS pza 1,031.57 1.00 1,031.57 1.00 2,113.97 2,113.97 1.00 2,113.97
30 PLACA ENTREGA DE OBRAS (SEGUN DISEÑO) pza 3,681.96 1.00 3,681.96 1.00 164.02 164.02 1.00 164.02
31 ANALISIS BACTERIOLOGICO QMC Y FISICO MTR - 1.00 275.83 275.83 1.00 275.83
32 INSTALACION DE FAENAS glb 6,222.45 1.00 6,222.45 1.00 1,423.12 1,423.12 1.00 1,423.12
33 LETRERO DE OBRA DE LADRILLO E = 18 CM pza - 1.00 783.29 783.29 1.00 783.29
M06 - RED DE DISTRIBUCION 880,078.33 824,559.09 809,342.94
34 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ml 3.89 ### 17,770.38 4,568.22 0.64 2,923.66 4,530.00 2,899.20
35 EXCAVACION DE 0-2 M SUELO DURO m³ 103.03 594.41 61,242.06 594.41 115.63 68,731.63 714.00 82,559.82
36 RELLENO COMPACTADO MANUAL NO INCLUYE MATERIAL m³ 27.47 463.82 12,741.14 463.82 57.81 26,813.43 459.90 26,586.82
37 PROV. Y TENDIDO TUBERIA PVC E = 40 D=2 m 60.63 571.12 34,627.01 571.12 21.69 12,387.59 1,494.00 32,404.86
38 PROV. Y TENDIDO TUBERIA PVC 4 PULG ESQ 40 (ESPI m 98.29 ### 212,015.46 2,157.04 51.48 111,044.42 1,188.00 61,158.24
39 PROV. Y TENDIDO TUBERIA PVC 6 PULG ESQ. 40 ES m 171.08 ### 288,988.34 1,689.00 194.92 329,219.88 1,626.00 316,939.92
40 PROV. Y TENDIDO TUBERIA FG D=2"PULG m 118.27 60.00 7,096.20 60.00 163.67 9,820.20 66.00 10,802.22
41 PROV. Y TENDIDO DE TUBERIA F.G. D=4 PULG m 289.78 30.00 8,693.40 30.00 213.62 6,408.60 42.00 8,972.04
42 PROV. Y TENDIDO TUBERIA FºGº D =6" m 261.85 150.86 39,502.69 150.86 226.04 34,100.39 204.00 46,112.16
43 EXC. MANUAL DE 0 A 2 M EN ROCA m³ 183.16 178.63 32,717.87 178.63 147.21 26,296.12 345.00 50,787.45
44 CAMARA DE DISTRIBUCION SG. DISEÑO pza 1,024.37 23.00 23,560.51 23.00 1,095.13 25,187.99 23.00 25,187.99
45 EXCAVACION EN ROCA m³ 137.37 450.00 61,816.50 450.00 147.21 66,244.50 1.00 147.21
46 ACCESORIOS C/DISTRIBUCION TIP I DE 4" pza 2,090.11 15.00 31,351.65 15.00 393.68 5,905.20 4.00 1,574.72
47 ACCESORIOS C/DISTRIBUCION TIPO II 2" pza 829.59 5.00 4,147.95 5.00 3,996.41 19,982.05 15.00 59,946.15
48 ACCESORIOS C/DERIVACION TIPO I 2" pza 1,350.68 3.00 4,052.04 3.00 3,996.41 11,989.23 4.00 15,985.64
49 APOYO DE Hº Cº S/PLANO M3 666.46 37.00 24,659.02 37.00 1,104.54 40,867.98 37.00 40,867.98
50 RELLENO MANUAL C/TIERRA CERNIDA M3 48.82 309.22 15,096.12 309.22 86.14 26,636.21 306.60 26,410.52
M07 - MEDIDAS DE MITIGACION AMBIENTAL 9,075.69 6,347.15 6,347.15
51 LETRINA CON POZO ABSORCION PZA 4,929.22 1.00 4,929.22 1.00 79.38 79.38 1.00 79.38
52 CONTENEDORES DE RESIDUOS SOLIDOS pza - 4.00 369.33 1,477.32 4.00 1,477.32
53 LETRERO SEÑALIZACION AMBIENTAL pza 1,016.12 1.00 1,016.12 4.00 975.61 3,902.44 4.00 3,902.44
54 LIMPIEZA GENERAL DE LA OBRA GLB. 3,130.35 1.00 3,130.35 1.00 888.01 888.01 1.00 888.01
M08 - CAMARA ROMPE PRESION 10,366.50 8,556.34 9,078.75
55 REPLANTEO DE OBRAS m² 9.55 5.04 48.13 5.04 13.74 69.25 5.25 72.14
56 EXCAVACION DE 0-2 M SUELO DURO m³ 91.58 1.51 138.29 1.51 115.63 174.60 1.90 219.70
Precio Unitario CONTRATO ORIGINAL CONTRATO ADJUDICADO BALANCE INICIAL
ITEM DESCRIPCION UNID. (PU) CANT. PRECIO CANT. P. U. PRECIO CANTIDAD PRECIO
Original PROGR. TOTAL Bs. Adjudicado Adjudicado TOTAL Bs. BALANCE TOTAL Bs.
57 HORMIGON ARMADO LOSA FONDO 1:2:3 (H2O) m³ 2,233.12 1.05 2,344.78 0.35 2,122.49 742.87 0.70 1,485.74
58 SOLADURA DE PIEDRA m² - 5.04 37.29 187.94 5.25 195.77
59 REVOQUE ENLUCIDO DE CEMENTOCON SIKA m² - 10.01 170.77 1,709.41 7.72 1,318.34
60 CAMARA DE LLAVES Hº Cº SEGUN DISEÑO pza 984.43 1.00 984.43 1.00 384.94 384.94 1.00 384.94
61 ACCESORIOS CAMARA ROMPE PRESION glb 3,029.89 1.00 3,029.89 1.00 2,360.08 2,360.08 1.00 2,360.08
62 TAPA METALICA DE VISITA 1/8" pza - 1.54 320.89 494.17 2.16 693.12
63 TAPA LOSA DE Hº Aº R 21 M3 - 0.35 3,394.62 1,188.12 0.29 984.44
64 MURO H°A° H 21 m³ 3,056.79 1.25 3,820.99 1.25 995.97 1,244.96 1.37 1,364.48
MODULO ADICIONAL
CAMARA ROMPRE PRESION 9,078.75
MONTOS TOTALES DE CONTRATO 1,039,053.40 967,588.36 962,645.93
MONTO REFERENCIAL 1,112,245.10

También podría gustarte