VALOR ME

LINEA DE NEGOCIO ESPESADORES


CODIGO OP: P2150
PROYECTO: FABRICACION DE CLARIFICADOR 1
CLIENTE: FLSMIDTH / ESTADOS UNIDOS

PTTO
PESO A PROCESAR (KG) :
TANQUE (KG) 22,391
ESTRUCTURA DE SOPORTE (kg) 15,504
PUENTE (kg) 13,300

AREA A PINTAR (M2) : 2,000

AREA A REVESTIR (M2) : -

TIEMPO DE PROYECTO ( SEMANAS ): 12.00


TIEMPO DE FABRICACION ( SEMANAS ): 13.25
MONEDA PRINCIPAL : DOLARES
TIPO DE CAMBIO CONTRACTUAL : 4.00

CONSIDERACIONES PRELIMINARES:

ESCENARIO 1: FABRICACION MOD HAUG

ESTRUCTURA DE COSTO LURIN VALOR VENTA

COSTOS DIRECTOS 142132.38

29649.47
MANO DE OBRA DIRECTA
MOD HAUG 29649.47
MOD SUBCONTRATADA 0.00
MATERIALES 93040.65
ACERO 67787.75
PINTURA 16137.25
ACCESORIOS / PERNERIA 1392.23
CONSUMIBLES FABRICACION 7027.71
MATERIALES HSE Y EPP 695.71
EQUIPOS Y HERRAMIENTAS 18221.80
EQUIPOS PROPIOS 9502.10
COMBUSTIBLE 1784.12
ALQUILER EQUIPOS TERCEROS 5504.84
HERRAMIENTAS 1430.75
MANTENIMIENTO EQUIPOS 0.00
SUBCONTRATOS 1220.47
DE FABRICACIÓN 330.85
DE CALIDAD 889.62
COSTOS INDIRECTOS 12046.78
MANO DE OBRA INDIRECTA 9025.61
DE PLANTA LURIN 1194.63
INGENIERIA 7830.98
TRANSPORTE MATERIAL 2746.48
SC TRANSPORTE 0.00
CONSUMIBLES EMBALAJE 2746.48
GASTO GENERAL 274.69
COSTO INDUSTRIAL LURIN 154179.16
DISTRIBUCION DE COSTOS INDIRECTOS 22090.33
COSTO FABRICACION LURIN 176269.49
GASTOS OFICINA CENTRAL (AOC) 11996.36
GASTOS FINANCIEROS 5201.06
UTILIDAD 23862.56
PRECIO VENTA 217329.48
%UTILIDAD 11%

Nota:
(1) CONSIDERAR 5142 KG (US$ 5656.2) DE ACERO DEL DUAL (STOCK ALMACEN).
COD. REPORTE
VM-2150-PL-Rev.0
VALOR META
FECHA REPORTE
29-oct-2021
SADORES

RICACION DE CLARIFICADOR 18 mts


MIDTH / ESTADOS UNIDOS

MESES : 3.0

VALOR META

123393.00

20204.45
20204.45
0.00
76901.00
52533 (1)
16137.00
940.00
6595.00
696.00
25067.00
16347.00
1784.00
5505.00
1431.00
0.00
1221.00
331.00
890.00
12047.00
9026.00
1195.00
7831.00
2746.00
0.00
2746.00
275.00
135440.00
22090.33
157530.00
11996.36
5201.06
42602.00
217329.48
20%

ALMACEN).
FECHA Wednesday, October 20, 2021
1 2 3

Nº Descripcion Material Ratio (m//ton)

1.1.1 Side Wall Acero al Carbono 38.00


1.1.2 Over flow box Acero al Carbono 40.00
1.1.3 Floor Acero al Carbono 38.00
1.1.4 Radial Beams Acero al Carbono 30.00
1.1.5 Support Legs Acero al Carbono 30.00
1.1.6 Bridge Acero al Carbono 30.00
1.1.7 Barandas 40.00
1.1.8 Pre-Ensamble Puente
1.1.9 Pre-Ensamble Gajo

Pintura Solo Exterior Area (m2/ton)


Chute 40.00
Cajon CC, CR 22.00
Canaleta 22.00
Baranda, escalera vertical 40.00
Estructura Liviana 35.00
Estructura Mediana 30.00
Estructura Pesada 25.00
Estructura Extra Pesada 20.00
Peldaño 55.00
Parrilla Metalica Liviano 55.00
Touch up 5%
Parrilla Metalica Pesado 50.00

m2 toneladas
fondo 508.9 13.44
Casco 339.3 8.82

Casco
Fondo
Estructuras
Barandas
165.675 12.71638751
4 5 6 7 8 9 10

Area Und Inc Peso Peso Unit (kg) Cant. Peso Tot (kg) Ratio (kg/hh)

335.22 kg 17% 8,821.61 1.00 8,821.61 38.00


5.36 kg 0% 133.88 1.00 133.88 4.50
510.57 kg 26% 13,435.99 1.00 13,435.99 20.00
268.40 kg 17% 8,946.51 1.00 8,946.51 12.50
196.74 kg 13% 6,557.88 1.00 6,557.88 12.50
368.24 kg 24% 12,274.80 1.00 12,274.80 8.00
41.01 kg 2% 1,025.20 1.00 1,025.20 4.00
kg 13,300.00 1.00 13,300.00 60.00
kg 3,617.55 1.00 3,617.55 60.00

1725.53 Totales 100% 51,195.87 50,170.67

Macroproceso
Habilitado
Habilitado
Caldereria
Caldereria
Caldereria
Rolado
Caldereria
Caldereria
Soldadura
Pre-Ensamble
Granallado
Pintura
Pasivado
0.35 4.9% 4.9%
Ratio 1.6 22.6% 22.6%
37.878801637 1.5 21.2% 21.2%
38.461550669 1.2 16.9% 16.9%
0.8 11.3% 11.3%
1.63 23.0% 23.0%
7.08
Habilitado
Habilitado
Caldereria
Caldereria
Caldereria
Rolado
Caldereria
Caldereria
Soldadura
Pre-Ensamble
Granallado
Pintura
Pasivado
11 12 13 14 15 16 17 18
CORTE BISEL CORTE
EFICIENCIA Ratio (kg/hh) HH CORT PAN CORT FICEP
AMOLAD C/AMOL OXICOR
90% 34.20 257.94 8.3% 0.0% 0.0% 0.0% 0.0%
90% 4.05 33.06 4.8% 0.0% 0.7% 0.0% 1.5%
90% 18.00 746.44 4.9% 0.0% 0.0% 0.0% 0.0%
90% 11.25 795.25 2.0% 1.1% 1.0% 0.3% 3.9%
90% 11.25 582.92 2.0% 1.1% 1.0% 0.3% 3.9%
90% 7.20 1,704.83 2.0% 1.1% 1.0% 0.3% 3.9%
90% 3.60 284.78 2.0% 1.1% 1.0% 0.3% 3.9%
100% 60.00 221.67 0.0% 0.0% 0.0% 0.0% 0.0%
100% 60.00 60.29 0.0% 0.0% 0.0% 0.0% 0.0%

4,687.18

TIPO DE CAMBIO 4.00

HH Por Categoria Cst HH por Cat (US$)


Proceso HH Inc% % Oer % Of HH Oper HH Ofic Op.
Hab. Pantogr 126.93 3% 50% 50% 63.46 63.46 4.75
Hab. Ficep 37.05 1% 50% 50% 18.52 18.52 4.75
Corte Amolad 33.91 1% 0% 100% - 33.91 4.75
Corte Oxicort 131.84 3% 100% 0% 131.84 - 4.75
Bisel Amolad 10.10 0% 100% 0% 10.10 - 4.75
Rolado 204.52 4% 50% 50% 102.26 102.26 4.75
Taladrado 348.51 7% 0% 100% - 348.51 4.75
Caldereria 1,951.66 41% 33% 67% 644.05 1,307.61 4.75
Soldadura 822.70 17% 100% 0% 822.70 - 5.34
Pre-Ensamble 281.96 6% 33% 67% 93.05 188.91 4.75
Granallado 320.34 7% 33% 67% 105.71 214.63 4.75
Pintura 541.36 11% 33% 67% 178.65 362.71 4.75
Pasivado 0.00 0% 33% 67% - - 4.75
Total 4,810.86

% INCIDENCIA HH % INCIDENCIA COSTO


PROCESO HH % INCIDEN COSTO % INCIDEN
HABILITADO 163.97 3.4% 681.51 3.4%
ROLADO 204.52 4.3% 850.05 4.2%
CALDERERIA 2476.01 51.5% 9754.16 48.3%
SOLDADURA 822.70 17.1% 4396.28 21.8%
PRE-ENSAMBL 281.96 5.9% 1114.97 5.5%
GRANALLADO 320.34 6.7% 1266.74 6.3%
PINTURA 541.36 11.3% 2140.72 10.6%
PASIVADO 0.00 0.0% 0.00 0.0%
TOTAL 4810.86 100.0% 20204.45 100.0%

Cst HH por Cat (US$)


Op. Of.
Hab. Pantogr 2.71 2.71
Hab. Ficep 4.07 2.71
Corte Amolad 4.25 2.71
Corte Oxicort 4.25 2.71
Bisel Amolad 4.25 2.71
Rolado 3.90 3.31
Taladrado 4.25 2.71
Caldereria 4.25 2.71
Soldadura 4.77 2.18
Pre-Ensamble 4.25 2.71
Granallado 3.31 2.71
Pintura 3.62 2.71
Pasivado 3.62 2.71
19 20 21 22 23 24 25

ROLADO PLEGADO TALADR CALD SOLD GRN PIN PASIVADO

13.6% 0.0% 0.0% 9.2% 0.0% 29.6% 39.3% 0.0%


0.0% 0.0% 15.1% 40.8% 26.1% 4.1% 6.8% 0.0%
22.7% 21.2% 0.0% 16.9% 0.0% 11.3% 23.0% 0.0%
0.0% 0.0% 10.2% 53.1% 15.8% 4.7% 7.9% 0.0%
0.0% 0.0% 10.2% 53.1% 15.8% 4.7% 7.9% 0.0%
0.0% 0.0% 10.2% 53.1% 15.8% 4.7% 7.9% 0.0%
0.0% 0.0% 10.2% 53.1% 15.8% 4.7% 7.9% 0.0%
0.0% 0.0% 0.0% 0.0% 100.0% 0.0% 0.0% 0.0%
0.0% 0.0% 0.0% 0.0% 100.0% 0.0% 0.0% 0.0%

Cst HH por Cat (US$) Cst Tot por Cat (US$)


Of. Op. Of. Total (US$)
3.56 301.45 226.09 527.54
3.56 87.98 65.99 153.97
3.56 - 120.80 120.80
3.56 626.24 - 626.24
3.56 47.99 - 47.99
3.56 485.74 364.31 850.05
3.56 - 1,241.55 1,241.55
3.56 3,059.22 4,658.36 7,717.59
3.56 4,396.28 - 4,396.28
3.56 441.97 673.00 1,114.97
3.56 502.13 764.61 1,266.74
3.56 848.57 1,292.15 2,140.72
3.56 - - -
TOTAL MOD (US$) 20,204.45
PESO 50,170.67
RATIO (DÓLAR/KG) 0.40
RATIO (SOLES/KG) 1.61
TIPO DE CAMBIO 4.00
PAGO CONTRATA (DÓLAR/KG) 0.27
PAGO CONTRATA (SOLES/KG) 1.08

RESUMEN TOTAL PROYECTO


PROCESO % INCID COSTO
HABILITADO 3.4% 681.51
ROLADO 4.2% 850.05
CALDERERIA 48.3% 9,754.16
SOLDADURA 21.8% 4,396.28
PRE-ENSAMBLE 5.5% 1,114.97
GRANALLADO 6.3% 1,266.74
PINTURA 10.6% 2,140.72
PASIVADO 0.0% -
TOTAL CST MOD US$ 20,204.45
PESO (KG) 50,170.67
RATIO COSTO (US$/KG) 0.40
Total HH 4,810.86
RATIO (kg/hh) 10.43
RATIO (US$/hh) 4.20
26 27 28 29 30 31 32 33
CORTE BISEL CORTE
CORT PAN CORT FICEP ROLADO TALADR CALD
AMOLAD C/AMOL OXICOR
21.4 - - - - 35.1 - 23.7
1.6 - 0.2 - 0.5 - 5.0 13.5
36.6 - - - - 169.4 - 126.1
15.9 8.7 8.0 2.4 31.0 - 81.1 422.3
11.7 6.4 5.8 1.7 22.7 - 59.5 309.5
34.1 18.8 17.0 5.1 66.5 - 173.9 905.3
5.7 3.1 2.8 0.9 11.1 - 29.0 151.2
- - - - - - - -
- - - - - - - -
- - - - - - - -
126.9 37.0 33.9 10.1 131.8 204.5 348.5 1,951.7
34 35 36 37 38 42 43 44

SOLD GRN PIN PASIVADO HABILITADO ROLADO CALDERERIA

- 76.4 101.4 - 8.3% 13.6% 9.2%


8.6 1.4 2.2 - 4.8% 0.0% 58.1%
- 84.3 171.7 - 4.9% 22.7% 16.9%
125.6 37.4 62.8 - 3.1% 0.0% 68.5%
92.1 27.4 46.1 - 3.1% 0.0% 68.5%
269.4 80.1 134.7 - 3.1% 0.0% 68.5%
45.0 13.4 22.5 - 3.1% 0.0% 68.5%
221.7 - - - 0.0% 0.0% 0.0%
60.3 - - - 0.0% 0.0% 0.0%
- - -
822.7 320.3 541.4 -
45 46 47 48 49 50 51 52

SOLDAD GRANALL PINTURA PASIVADO HABILITADO ROLADO CALDERERIA SOLDAD

0.0% 29.6% 39.3% 0.0% 21.4 35.1 23.7 -


26.1% 4.1% 6.8% 0.0% 1.6 - 19.2 8.6
0.0% 11.3% 23.0% 0.0% 36.6 169.4 126.1 -
15.8% 4.7% 7.9% 0.0% 24.7 - 544.7 125.6
15.8% 4.7% 7.9% 0.0% 18.1 - 399.3 92.1
15.8% 4.7% 7.9% 0.0% 52.8 - 1,167.8 269.4
15.8% 4.7% 7.9% 0.0% 8.8 - 195.1 45.0
100.0% 0.0% 0.0% 0.0% - - - 221.7
100.0% 0.0% 0.0% 0.0% - - - 60.3

164.0 204.5 2,476.0 822.7


53 54 55

GRANALL PINTURA PASIVDO RATIO


(kg/hh) HH
76.4 101.4 - 0 0.00
1.4 2.2 - 0 0.00
84.3 171.7 - 0 0.00
37.4 62.8 - 0 0.00
27.4 46.1 - 0 0.00
80.1 134.7 - 0 0.00
13.4 22.5 - 0 0.00
- - - 60 221.67
- - - 60 60.29

320.3 541.4 - 120.0 282.0 4,810.9


Macroproce Proceso Equipo/Maquina HH Nº Operarios
Habilitado Hab. Pantografo Pantografo 126.93 2
Habilitado Hab. Ficep Ficep 37.05 2
Caldereria Corte Amoladora Amoladora 33.91 1
Caldereria Corte Oxicorte Equipo Oxicorte 131.84 1
Caldereria Bisel Amoladora Amoladora 10.10 1
Rolado Rolado Roladora Sertom 204.52 2
Caldereria Taladrado Taladro Magnetico 348.51 1
Caldereria Caldereria 1,951.66 3
Soldadura Soldadura Maq Soldar Multiproceso + Alimen. 822.70 1
Pre-EnsamblePre-Ensamble 281.96 2
Granallado Granallado Sistema Granallado Manual 320.34 3
Pintura Pintura Equipo Pint Neumatico Graco 541.36 3
Pasivado Pasivado 0.00 3
4,810.86
Horas Maquina Costo Hra Maq Cst Total Maq (US$)
63.5 20.54 1303.54
18.5 39.66 734.61
33.9 0.00
131.8 0.00
10.1 0.00
102.3 76.71 7844.47
348.5 0.89 310.17
650.6 0.00
822.7 1.98 1628.94
141.0 0.00
106.8 39.03 4167.62
180.5 1.98 357.29
0.0 0.00
16346.65

RESUMEN DE COSTO EQUIPOS PROPIOS


Total Costo Equipos 16,346.65
Total Peso Proyecto (kg) 50,170.67
Ratio Costo (US$/kg) 0.33
EQUIPO H. MAQ Costo Hra Maq Cst Total Maq (US$)
Pantografo 63 20.54 1303.54
Ficep 19 39.66 734.61
Amoladora 0 0 0.00
Equipo Oxicorte 0 0 0.00
Roladora Sertom 102 76.71 7844.47
Taladro Magnetico 349 0.89 310.17
Maq Soldar Multiproceso + Alimen. 823 1.98 1628.94
Sistema Granallado Manual 107 39.03 4167.62
Equipo Pint Neumatico Graco 180 1.98 357.29
16346.65

48863.00
0.33
H. MA

63
19 0 0
H. MAQ
823

349 H. MAQ

180
102 107
9 0 0
SOLDADURA FCAW Total HH 822.70
Unds Ratio Cant Total Und PREC UNIT
Almbre kg Aporte/HH 0.52 425.3 Kg Aporte 3.1
Gases CO2 kg CO2/HH 1.09 464.5 Kg CO2 1.5
Discos Corte Nº Discos/HH 0.20 83.8 Nº Discos 2.5
Total
Peso (kg)
Ratio (US$/kg)

Total HH Biselado 10.10


Ratio Biselado (kg/hh) 1.20
BISELADO DE CASCOS Total Peso Removido (kg) 12.12
Unds Ratio Cant Total Und PREC UNIT
Disco Lija kg Removido/Nº Disco 0.80 18.9 nº Discos 4.5
Total
Peso (kg)
Ratio (US$/kg)
CST TOTAL
1,325.72
696.70
209.48
2,231.89
50,170.67
0.04

CST TOTAL
84.68
84.68
50,170.67
0.00
COSTO EPS
ÍTEM DESCRIPCIÓN
GALON

Sistema A-2 - Liviana


1 Inorganic zinc primer 4.00

Touch

Sistema A-2 - Mediana


1

Touch

Perfil m2/m
w6x25 0.924
w6x15 0.896
w8x18 0.929
L4xL4x1/4 0.401
L2 1/2xL2 1/2x1/4 0.25
L6xL3 1/2 x 5/16 0.475
L2xL2x1/4 0.2
w8x67 1.277
w8x24 1.042
w12x35 1.287
L3xL3x1/4 0.298
Cant. US$
Rteor Rpract %
% Vol Sold % desp Pintura -----
m2/gal m2/gal Dilusión
gal/m2 Galn.

0.0829

72 55% 26.82 12.07 0.0829 34.00 30%

Area (m2) RAL


Area interior humeda (casco y fondo) 620 5003
Area exterior (estructuras, columnas, vigas) 1247 5003
Cant US$
Diluyente ----- US$/m²
Galn/m2 Galn.

3.12

0.0249 12.00 3.12

-
Puente
Formato
Perfil 6 mts 9 mts 12 mts Stock
w6x25 1 4 0
w6x15 5 0
w6x12 1 5 0
w8x18 1 1 viga, en zona de
L4x4x1/4 30 6
L2 1/2x2 1/2 x 1/4 1 1 reemplazar angulo 2 1/2"
canal C8x11.5 2 1 canal de 6 mts, en zo

Espesador
Formato
Perfil 6 mts 9 mts 12 mts Stock
w8x24 2 8 0
w12x35 16 0
L4x4x1/4 11 11
L3x3x1/4 12 0

plancha ancho largo Stock O


38 1200 2400 1 stock almacén, cue
25 1500 3000 1 com
19 1200 2400 x sobrantes
8 3000 12000 2 sobrante del P2126, para pleg
10 1500 3000 0 com
6 2400 12000 18 com
Obs. Peso (kg)
compra 2157.60
compra 1361.52
compra 1253.49
viga, en zona de plegado, no tiene certificado 166.06
compra 1770.00
reemplazar angulo 2 1/2" x 2 1/2" x 3/8", cuenta con certificado 0.00
canal de 6 mts, en zona de plegado, no tiene certificado 410.00
###
###
###
Obs. Peso (kg)
compra 4142.59
compra 10166.02
stock almacen 0.00
compra 516.00
###
Obs. Peso (kg)
stock almacén, cuenta con certificado 0.00
compra 883.13
sobrantes del P2130 429.55
nte del P2126, para plegado de ángulo L6 x 3 1/2 x 5/16 4521.60
compra 353.25
compra 24416.64
Total (kg) 52547.45
Pesto total proyecto( kg) 48051.79
Merma (kg) 4495.66
9%