RESUMEN PRESUPUESTO ANALÍTICO - COSTO DIRECTO

PROYECTO: "MEJORAMIENTO CAMINO VECINAL HUACCOTO, DISTRITO DE SAN JERONIMO - CUSCO - CUSCO."

CÓDIGO ESPECIFICA DE GASTOS C.DIRECTO


RETRIBUCIONES Y COMPLEMENTOS - CONTRATOS
2.6.23.24 A PLAZO FIJO (REGIMENES LABORALES PUBLICO Y 86,002.26
PRIVADO)
COSTO DE CONSTRUCCION POR ADMINISTRACION
2.6.23.25 315,189.89
DIRECTA - BIENES
COSTO DE CONSTRUCCION POR ADMINISTRACION
2.6.23.26 651,925.99
DIRECTA - SERVICIOS
TOTAL COSTO DIRECTO 1,053,118.14

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

COSTO DIRECTO

2.6.23.24 RETRIBUCIONES Y COMPLEMENTOS - CONTRATOS A PLAZO FIJO (REGIMENES LABORALES PUBLICO Y PRIVADO) S/. 86,002.26

01 JORNAL

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 5.64 606.46 3,420.44 3,420.44
OPERARIO HH 5.64 1,731.63 9,766.39 9,766.39
OFICIAL HH 5.12 1,294.79 6,629.31 6,629.31
PEON HH 4.88 10,381.75 50,662.96 50,662.96
TOTAL 70,479.10

02 TRASF. CORRIENTES: SNPS (13 %)

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 0.69 606.46 418.46 418.46
OPERARIO HH 0.69 1,731.63 1,194.82 1,194.82
OFICIAL HH 0.55 1,294.79 712.13 712.13
PEON HH 0.49 10,381.75 5,087.06 5,087.06
TOTAL 7,412.47

03 ESSALUD (9%)

DEL EMPLEADOR

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 0.48 606.46 291.10 291.10
OPERARIO HH 0.48 1,731.63 831.18 831.18
OFICIAL HH 0.38 1,294.79 492.02 492.02
PEON HH 0.34 10,381.75 3,529.79 3,529.79
TOTAL 5,144.10

04 AGUIONALDOS POR ESCOLARIDAD (1%)

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 0.05 606.46 30.32 30.32
OPERARIO HH 0.05 1,731.63 86.58 86.58
OFICIAL HH 0.04 1,294.79 51.79 51.79
PEON HH 0.04 10,381.75 415.27 415.27
TOTAL 583.97

05 AGUINALDOS POR FIESTAS PATRIAS (2%)

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 0.11 606.46 66.71 66.71
OPERARIO HH 0.11 1,731.63 190.48 190.48
OFICIAL HH 0.08 1,294.79 103.58 103.58
PEON HH 0.08 10,381.75 830.54 830.54
TOTAL 1,191.31
06 AGUINALDOS POR NAVIDAD (2%)

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL TOTAL


TOPOGRAFO HH 0.11 606.46 66.71 66.71
OPERARIO HH 0.11 1,731.63 190.48 190.48
OFICIAL HH 0.08 1,294.79 103.58 103.58
PEON HH 0.08 10,381.75 830.54 830.54
TOTAL 1,191.31

2.6.23.25 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES S/. 315,189.89

DESCRIPCION UNIDAD CANT P.U TOTAL


CLAVOS PARA MADERA C/C 2" kg 20.80 5.00 104.00
CLAVOS PARA MADERA C/C 3" kg 57.07 5.00 285.35
CLAVOS PARA MADERA C/C 5" kg 5.20 5.00 26.00
CLAVOS PARA MADERA C/C 4" kg 18.11 5.00 90.55
CLAVOS Fo No C/C 2" kg 0.19 5.00 0.95
CLAVOS Fo No C/C 4" kg 0.00 5.00 0.00
ALAMBRE NEGRO N°16 kg 21.02 5.00 105.10
ALAMBRE NEGRO N°8 kg 77.61 5.00 388.05
CLAVOS PARA CALAMINA kg 10.40 7.50 78.00
FIERRO CORRUGADO ESPECIFICADO G-60° kg 374.84 4.00 1,499.36
ARENA FINA (PUESTO EN OBRA) m3 0.05 120.00 6.00
PIEDRA GRANDE DE 8" m3 186.25 48.00 8,940.00
ARENA GRUESA (PUESTO EN OBRA) m3 63.03 90.00 5,672.70
PIEDRA CHANCADA DE 3/4" m3 127.57 90.00 11,481.30
MATERIAL CLASIFICADO PARA BASE. m3 9,020.97 6.00 54,125.82
CEMENTO PORTLAND TIPO I (42.5KG) BOL 1,343.15 25.00 33,578.75
GUIA DE AGUA m 12,000.21 0.70 8,400.15
FULMINANTE COMUN # 6 DE 35 mm pza 9,277.14 1.50 13,915.71
NITRATO DE AMONIO AL 34.5% kg 8,184.80 5.00 40,924.00
EXPLOSIVO SEMEXA 60 kg 2,082.35 15.00 31,235.25
MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS. GLB 1.00 6,000.00 6,000.00
MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL DURANTE LA EJECUCION. und 1.00 8,000.00 8,000.00
YESO DE 28 Kg BOL 42.54 7.00 297.78
BARRENO DE 7/8" X 3 PIES und 49.08 480.00 23,558.40
ALCANTARILLA METALICA TMC D=36", C=12 m 17.50 800.00 14,000.00
ADITIVO CURADOR DE CONCRETO CON PIGMENTO gln 14.12 33.00 465.96
PLANTON DE ESPECIE ARBUSTIVA. und 150.00 5.00 750.00
YESO BOL 7.79 7.00 54.53
FLETE TERRESTRE Y TRANSPORTE. GLB 1.00 3,000.00 3,000.00
AGUA m3 1,533.25 2.00 3,066.50
CARTEL DE OBRA EN GIGANTOGRAFIA 3.60x2.40 m.(INC BASTIDOR DE METAL) und 2.00 450.00 900.00
SEÑAL PREVENTIVA. und 51.00 260.00 13,260.00
SEÑAL INFORMATIVA. und 3.00 640.00 1,920.00
HITO KILOMETRICO (INC PINTADO) und 14.00 250.00 3,500.00
INSTALACION Y MANTENIMIENTO DE LETRINA. GLB 1.00 5,000.00 5,000.00
ESTACAS DE MADERA. p2 7.79 4.00 31.16
ESTACA DE MADERA p2 2,127.00 3.00 6,381.00
ROLLIZO DE EUCALIPTO DE 5" X 3.50 M pza 6.00 20.00 120.00
MADERA CORRIENTE CEPILLADA p2 1,293.55 4.20 5,432.91
MADERA CORRIENTE p2 416.00 4.00 1,664.00
TRIPLAY DE 4'x8'x 4 mm pln 62.40 32.00 1,996.80
THINER gln 2.02 18.00 36.36
PETROLEO gln 5.17 13.00 67.21
PINTURA ESMALTE SINTETICO gln 21.27 32.00 680.64
PINTURA ESMALTE SINTETICO DE TRAFICO. gln 3.36 65.00 218.40
CALAMINA GALVANIZADA 1.80 x 0.83 x 0.3mm pln 145.60 27.00 3,931.20
TOTAL 315,189.89
2.6.23.26 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS S/. 651,925.99

DESCRIPCION UND CANT. P.U. SUB TOTAL


HERRAMIENTAS MANUALES. %MO 0.00 0.00 3,895.13
NIVEL DE INGENIERO (INC. MIRA Y JALONES) día 21.27 35.00 744.45
ESTACION TOTAL (INC PRISMAS Y MIRAS) día 23.22 200.00 4,644.00
CAMION CISTERNA 4x2 (AGUA) 122 HP 1,500 hm 361.17 100.00 36,117.00
CAMION VOLQUETE DE 3 M3 DE 120 A 160 HP hm 64.80 60.00 3,888.00
ZARANDA METALICA CON FIERRO DE 5/8" día 12.63 300.00 3,789.00
VOLQUETE DE 10 M3 hm 29.77 120.00 3,572.40
VOLQUETE DE 15 M3 hm 687.65 160.00 110,024.00
CIZALLA PARA FIERRO. hm 11.28 4.00 45.12
COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP hm 2.64 7.10 18.74
RODILLO LISO VIBR AUTOP 101-135HP 10-12T hm 361.17 120.05 43,358.46
CARGADOR S/LLANTAS 125 HP 2.5 YD3. hm 383.42 156.34 59,943.88
TRACTOR DE ORUGAS DE 190-240 HP hm 1,128.35 229.96 259,475.37
COMPRESORA NEUMATICA 175 PCM hm 355.96 130.00 46,274.80
MARTILLOS NEUMATICOS 29 Kg hm 711.92 15.00 10,678.80
MOTONIVELADORA DE 145 - 150 HP hm 399.45 160.72 64,199.60
MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 hm 85.76 8.16 699.80
VIBRADOR DE 4 HP CAP.=1.50" hm 85.76 6.50 557.44
TOTAL 651,925.99

COSTO DIRECTO TOTAL S/. 1,053,118.14