h= 0.50; F.D = 5%

Zn=[ ( largo∗ancho∗h )∗cant . de zapatas ]∗ F . D

Z1= 1.75*2.30*0.50=2.01 m3 *4=8.04 m3 *1.05=8.44 m3


Z2= 1.95*2.50*0.50=2.44 m3 *4=9.75 m3 * 1.05=10.24 m3
Z3= 1.20*1.20*0.50=0.72 m3 *5=3.60 m3 *1.05=3.78 m3
Z4= 2.55*1.85*0.50=2.36 m3 *2=4.75 m3 *1.05=4.95 m3
Z5= 1.65*1.35*0.50=1.11 m3 *1=1.11 m3 *1.05=1.17 m3
Z6= 2.85*1.85*0.50=2.63 m3 *2=5.27 m3 *1.05=5.53 m3
Z7= 1.95*1.65*0.50=1.61 m3 *1=1.61 m3 *1.05=1.68 m3
Z8=1.30*1.30*0.50=0.85 m3 *1=0.85 m3 *1.05=0.88 m3
Z9=1.10*1.10.*0.50=0.61 m3 *4=2.42 m3 *1.05=2.66 m3
Z10=2.05*1.70*0.50=1.74 m3 *2= 3.48 m3 *1.05= 3.65 m3
Total=42.98 m3

METRADO DE CONCRETO EN COLUMNAS:


h= 4.05 m; F.D. =5%
Cn=( ancho∗largo∗h )∗cant .de columnas∗F . D.

C1=0.30*0.60*4.05=0.73 m3 *2*1.05= 1.53 m3


C2=0.30*0.85*4.05=1.03 m3 *8*1.05=8.67 m3
C3= 0.30*0.30*4.05=0.36 m3 *7*1.05=2.67 m3
C4= 0.25*0.60*4.05=0.61 m3 *2*1.05=1.27 m3
C5= 0.30*0.30*4.05= 0.36 m3 *2*1.05=0.76 m3
C6= 0.30*0.30*4.05=0.36 m3 *1*1.05= 0.38 m3
MC1= 0.49*4.05=2 m3 *4*1.05=8.42 m3
UNIVERSIDAD ANDINA DEL CUSCO DOCENTE: Ing. Kildare Ascue Escalante
FACULTAD DE INGENIERÍA Y ARQUICTURA ALUMNAS:
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL - Cruz Huamani, Magaly
CONSTRUCCIONES II - Ochoa Quispe, Clara
Total=23.70 m ³

METRADO DE CONCRETO PARA VIGAS DE CONEXION:


V.C = 0.35 x 0.50 ; F.D= 5%
V .C n=( ancho∗largo∗h )∗F . D .

 Eje D ; tramo 6 – 12→ 23.03∗0.35∗0.50∗1.05=4.23 m3


 Eje C ; tramo 6 – 12 → no hay vigas de conexion
 Eje B ; tramo 6 – 12 → 23.03∗0.35∗0.50∗1.05=4.23 m3
 Eje A ; tramo 6 – 12 → 23.03∗0.35∗0.50∗1.05=4.23 m3
 Eje 6 ; tramo A – D → 9.1 0∗0.35∗0.50∗1.05=1.67 m3
 Eje 7 , tramo A – D → no hay vigas de conexion
 Eje 8 ; tramo A – D → 9.1 0∗0.35∗0.50∗1.05=1.6 7 m3
 Eje 9 ; tramo A – D → no hay vigas de conexion
 Eje 10 ; tramo A – D → 9.10∗0.35∗0.50∗1.05=1.67 m3
 Eje 11 ; tramo A – D → 9.10∗0.35∗0.50∗1.05=1.67 m3
 Eje 12 ; tramo A – D → 9.10∗0.35∗0.50∗1.05=1.67 m3
Total=2 1.04 m ³

Metrados Zapata Columnas Vigas de conexión


42.9 8 23.70 21.04
Concreto (m 3
¿
Redondeo 43 m 3 24 m 3 22 m3

cantidad t otal de con creto=89 m3