UNIVERSIDAD ANDINA DEL CUSCO FACULTAD DE INGENIERÍA Y ARQUITECTURA

ESCUELA PROFESIONAL DE INGENIERÍA CIVIL


CANTIDAD DE LADRILLOS 23*12.5*0.9 EJE A(1-2):
MURO TIPO 1 (8)
DATOS Medida Und Dat. Muro Aa Ab Ac
Largo 0.23 m Largo 1.07 0.53 1.08
Ancho 0.125 m Altura 0.73 2.67 0.73
Espesor 0.09 m 0.14 0.01 1.00
Mortero 0.01 m 0.10
F.d 1.05
Tip Aparejo Cabeza
1
CL= = 74.07 ld/m
0.125 + 0.01 ∗ (0.09 + 0.01)
Aa= 1.07*0.73= 0.78
Ab= 0.53*2.67= 1.42 A+B+C= 2.99 m²
Ac= 1.08*0.73= 0.79
SubTotal= 2.99*74.07= 221.48 m²
F.D= 221.48*1.05= 232.56
Cant. Muros T1= 8.00
Total de Lad= 232.56*8= 1860.44 1861.00 UND
TOTAL SIN FD= 1771.85 1772.00

VOLUMEN DE MORTERO: (SOLO PARA 1 MURO)


VolMortero= VolMuro-VolLadrillo
VolMuro= (0.73*1.07*0.23) + (0.53*2.67*0.23)+ (0.73*1.08*0.23)= 0.69 m³
VolLadrillo= (0.23*0.125*0.09)*221.48= 0.57 m³
VolMortero= VolMuro-VolLadrillo= 0.69-0.57= 0.11 m³
VolMor*CantMuuro= 0.11*8= 0.91 m³
Con F.D= 0.95 m³

DOCENTE: Ing. Kildare Ascue Escalante


ESTUDIANTES: - Cruz Huamaní, Magaly - Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO FACULTAD DE INGENIERÍA Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
CANTIDAD DE LADRILLOS 23*12.5*0.9 EJE C(4-3) y EJE A(6-7):
MURO TIPO 2 (2)
DATOS Medida Und Dat. Muro Aa Ab Ac
Largo 0.23 m Largo 3.00
Ancho 0.125 m Altura 1.43
Espesor 0.09 m 0.14 0.01 1.00
Mortero 0.01 m 0.10
F.d 1.05
Tip Aparejo Cabeza
1
CL= = 74.07 ld/m
0.125 + 0.01 ∗ (0.09 + 0.01)
Aa=
Ab= 3.00*1.43=
0.53*2.67= 4.29
0.00 A+B+C= 4.29 m²
Ac= 1.08*0.73= 0.00
SubTotal= 4.29*74.07= 317.78 m²
F.D= 317.78*1.05= 333.67
Cant. Muros T1= 2.00
Total de Lad= 333.67*2= 667.33 668.00 UND
TOTAL SIN FD= 635.56 636.00 UND

VOLUMEN DE MORTERO: (SOLO PARA 1 MURO)


VolMortero= VolMuro-VolLadrillo
VolMuro= (3*1.43*0.23)= 0.99 m³
VolLadrillo= (0.23*0.125*0.09)*317.78= 0.82 m³
VolMortero= VolMuro-VolLadrillo= 0.99-0.82= 0.16 m³
VolMor*CantMuuro= 0.16*2= 0.33 m³
Con F.D= 0.35 m³

DOCENTE: Ing. Kildare Ascue Escalante


ESTUDIANTES: - Cruz Huamaní, Magaly - Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO FACULTAD DE INGENIERÍA Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
CANTIDAD DE LADRILLOS 23*12.5*0.9 EJE C(2-3) ; EJE C(5-6) y EJE C(10-11) :
MURO TIPO 3 (3)
DATOS Medida Und Dat. Muro Aa Ab Ac
Largo 0.23 m Largo 1.95
Ancho 0.125 m Altura 1.43
Espesor 0.09 m 0.14 0.01 1.00
Mortero 0.01 m 0.10
F.d 1.05
Tip Aparejo Cabeza
1
CL= = 74.07 ld/m
0.125 + 0.01 ∗ (0.09 + 0.01)
Aa=
Ab= 1.95*1.43=
0.53*2.67= 2.79
0.00 A+B+C= 2.79 m²
Ac= 1.08*0.73= 0.00
SubTotal= 2.79*74.07= 206.56 m²
F.D= 206.56*1.05= 216.88
Cant. Muros T1= 3.00
Total de Lad= 216.88*3= 650.65 651.00 UND
TOTAL SIN FD= 619.67 620.00 UND

VOLUMEN DE MORTERO: (SOLO PARA 1 MURO)


VolMortero= VolMuro-VolLadrillo
VolMuro= (1.95*1.43*0.23)= 0.64 m³
VolLadrillo= (0.23*0.125*0.09)*206.56= 0.53 m³
VolMortero= VolMuro-VolLadrillo= 0.64-0.53= 0.11 m³
VolMor*CantMuuro= 0.11*3= 0.33 m³
Con F.D= 0.35 m³

DOCENTE: Ing. Kildare Ascue Escalante


ESTUDIANTES: - Cruz Huamaní, Magaly - Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO FACULTAD DE INGENIERÍA Y ARQUITECTURA
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
CANTIDAD DE LADRILLOS 23*12.5*0.9:
MURO TIPO 4 (1)
DATOS Medida Und Dat. Muro Aa Ab Ac
Largo 0.23 m Largo 0.61 1.18
Ancho 0.125 m Altura 1.92 1.43
Espesor 0.09 m 0.14 0.01 1.00
Mortero 0.01 m 0.10
F.d 1.05
Tip Aparejo Cabeza
1
CL= = 74.07 ld/m
0.125 + 0.01 ∗ (0.09 + 0.01)
Aa= 1.07*0.73= 1.17
Ab=
Ac= 0.53*2.67=
1.08*0.73= 1.69
0.00 A+B= 2.86 m²

SubTotal= 2.86*74.07= 211.75 m²


F.D= 211.75*1.05= 222.34
Cant. Muros T1= 1.00
Total de Lad= 222.34*1= 222.34 223.00 UND
TOTAL SIN FD= 211.75 212.00

VOLUMEN DE MORTERO: (SOLO PARA 1 MURO)


VolMortero= VolMuro-VolLadrillo
VolMuro= (0.61*1.92*0.23) + (1.18*1.43*0.23)= 0.66 m³
VolLadrillo= (0.23*0.125*0.09)*221.48= 0.55 m³
VolMortero= VolMuro-VolLadrillo= 0.66-0.55= 0.11 m³
VolMor*CantMuuro= 0.11*1= 0.11 m³
Con F.D= 0.12 m³

DOCENTE: Ing. Kildare Ascue Escalante


ESTUDIANTES: - Cruz Huamaní, Magaly - Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO
FACULTAD DE INGENIERÍA Y ARQUITECTURA ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

MURO TIPO 5 (1)

METREADO DE CANTIDAD DE LADRILLOS: 23*12.5*0.9


1
𝐶𝐿 = = 74.07𝑙𝑑/𝑚 2
(0.125 + 0.01) ∗ (0.09 + 0.01)
Área de A = 1.53*1.37 = 2.096 m^2
A+B = 2.096 + 0.73 = 2.83 m^2
Área de B = 0.36*2.03 = 0.73 m^2

SUBTOTAL = 2.83*74.07 = 209.53 ladr


F.D(5%) = 209.53*1.05 = 220.01
Cant. Muros T5 = 1
Total, de ladrillos = 220.01*1= 220.01 = 221 unid ladrillos
Total, de ladrillos sin F.D = 209.53 = 210 unid de ladrillos

VOLUMEN DE MORTERO = VOL. MURO – VOL. LADRILLO (SOLO PARA 1 MURO T5)
Vol.Muro = (1.53*1.37* 0.23) + (0.36*2.03*0.23) =0.65 m^3
Vol. Ladrillo = (0.23*0.125*0.09) *209.53 = 0.54m^3
VOLUMEN DEL MORTERO = 0.65 – 0.54 = 0.11
0.11*1=0.11m^3
Con F.D = 0.12m^3

DOCENTE: Ing. Kildare Ascue Escalante


Estudiantes: - Cruz Huamani, Magaly -Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO
FACULTAD DE INGENIERÍA Y ARQUITECTURA ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

MURO TIPO 6 (1)

METREADO DE CANTIDAD DE LADRILLOS: 23*12.5*0.9


1
𝐶𝐿 = = 74.07𝑙𝑑/𝑚 2
(0.125 + 0.01) ∗ (0.09 + 0.01)
Área de A = 0.36*2.03 = 0.73 m^2
A+B = 0.73 + 1.37 = 2.10 m^2
Área de B = 0.48*2.85 = 1.37 m^2

SUBTOTAL = 2.10*74.07 = 155.55 ladr


F.D(5%) = 155.55*1.05 = 163.33
Cant. Muros T6 = 1
Total, de ladrillos = 163.33*1= 163.33 = 164 unid ladrillos
Total, de ladrillos sin F.D = 155.55 = 156unid de ladrillos

VOLUMEN DE MORTERO = VOL. MURO – VOL. LADRILLO (SOLO PARA 1 MURO T6)
Vol.Muro = (0.36*2.03* 0.23) + (0.48*2.85*0.23) =0-48 m^3
Vol. Ladrillo = (0.23*0.125*0.09) *155.55 = 0.40m^3
VOLUMEN DEL MORTERO = 0.48 – 0.40 = 0.08m^3
0.08*1=0.08m^3
Con D.F = 0.084m^3

DOCENTE: Ing. Kildare Ascue Escalante


Estudiantes: - Cruz Huamani, Magaly -Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO
FACULTAD DE INGENIERÍA Y ARQUITECTURA ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

MURO TIPO 7 (20)

METREADO DE CANTIDAD DE LADRILLOS: 23*12.5*0.9


1
𝐶𝐿 = = 74.07𝑙𝑑/𝑚 2
(0.125 + 0.01) ∗ (0.09 + 0.01)

EJE 1:A-B (2.37*2.85) EJE 9:A-B (3.23*2.85)


Área de A -B=2.37*2.85 = 6.75 m^2 Área de A -B=3.23*2.85 = 9.21 m^2
EJE 1:B-C (3.27*2.85) EJE 10:A-B (3.23*2.85)
Área de B -C=3.27*2.85 = 9.32 m^2 Área de A-B=3.23*2.85 = 9.21m^2
EJE 2:A-B (2.32*2.85) EJE 10:B-C (2.32*2.85)
Área de A -B=2.32*2.85 = 6.61 m^2 Área de B-C=2.32*2.85 = 6.61 m^2
EJE 2:B-C (3.22*2.85) EJE 11:A-B (3.28*2.85)
Área de B -C=3.22*2.85 = 9.18 m^2 Área de B -C=3.28*2.85 = 9.35 m^2
EJE 5:A-B (3.28*2.85) EJE 11:B-C (3.28*2.85)
Área de A -B=3.28*2.85 = 9.35 m^2 Área de A -B=3.28*2.85 = 9.35 m^2
EJE 5:B-C (3.28*2.85) EJE B:1-2 (1.13*2.85) ; (1.80*2.85)
Área de B -C=3.28*2.85 = 9.35 m^2 Área de 1-2=(1.13*2.85)+(1.80*2.85) = 8.35m^2
EJE 6:A-B (3.28*2.85) EJE B:9-10 (2.80*2.85)
Área de A -B=3.28*2.85 = 9.35 m^2 Área de 9-10=2.80*2.85 = 7.98 m^2
EJE 6:B-C (3.33*2.85) EJE C:8-9 (1.53*2.85) ; (0.36*2.85)
Área de B -C=3.33*2.85 = 9.49 m^2 Área de 8-9=(1.53*2.85)+(0.36*2.85) = 5.37 m^2
EJE 7:A-B (3.28*2.85) AREA TOTAL = 172.37 m^2
Área de A -B=3.28*2.85 = 9.35 m^2
EJE 7:B-C (3.33*2.85)
Área de B -C=3.33*2.85 = 9.49 m^2
EJE 8:A-B (3.28*2.85)
Área de A -B=3.28*2.85 = 9.35 m^2
EJE 8:B-C (3.28*2.85)
Área de B -C=3.28*2.85 = 9.35 m^2
DOCENTE: Ing. Kildare Ascue Escalante
Estudiantes: - Cruz Huamani, Magaly -Ochoa Quispe, Clara
UNIVERSIDAD ANDINA DEL CUSCO
FACULTAD DE INGENIERÍA Y ARQUITECTURA ESCUELA PROFESIONAL DE INGENIERÍA CIVIL

SUBTOTAL = 172.37*74.07 = 12767.45 ladr


F.D(5%) = 12767*1.05 = 13405.35
Cant. Muros T7=20
Total, de ladrillos = 13405.35*20= 268107 = 268107 unid ladrillos
Total, de ladrillos sin F.D = 255349 = 255349 unid de ladrillos

VOLUMEN DE MORTERO = VOL. MURO – VOL. LADRILLO (SOLO PARA 1 MURO T6)
Vol.Muro EJE1 = (2.37*2.85*0.23) + (3.27*2.85*0.23) = 3.70
Vol.Muro EJE2 = (2.32*2.85*0.23) + (3.22*2.85*0.23) = 3.63
Vol.Muro EJE5 = (3.28*2.85*0.23) + (3.28*2.85*0.23) = 4.30
Vol.Muro EJE6 = (3.28*2.85*0.23) + (3.33*2.85*0.23) = 4.33
Vol.Muro EJE7 = (3.28*2.85*0.23) + (3.33*2.85*0.23) = 4.33
Vol.Muro EJE8 = (3.28*2.85*0.23) + (3.28*2.85*0.23) = 4.30
Vol.Muro EJE9 = (3.23*2.85*0.23) = 2.12
Vol.Muro EJE10 = (3.23*2.85*0.23) + (2.32*2.85*0.23) = 3.64
Vol.Muro EJE11 = (3.28*2.85*0.23) + (3.28*2.85*0.23) = 4.30
Vol.Muro EJEB = (1.13*2.85*0.23) + (1.80*2.85*0.23) + (2.80*2.85*0.23) = 3.76
Vol.Muro EJEC = (1.53*2.85*0.23) +(0.36*2.85*0.23) = 1.24
Vol.MuroTotal = 39.65 m^3
Vol. Ladrillo = (0.23*0.125*0.09) *12767.45 = 33.04 m^3
VOLUMEN DEL MORTERO = 39.65 – 33.04= 6.61m^3
6.61*20=132.20m^3
CON F.D = 138.81 m^3
CUADRO DE RESUMEN
TIPO CANT.LADRILLO (UNID) CANT. (m^3)
MORTERO
CON F.D SIN F.D SIN F.D CON F.D
T1 1860.44 1771.85 0.91 0.95
T2 667.33 635.56 0.33 0.35
T3 650.65 619.67 0.33 0.35
T4 222.34 211.75 0.11 0.12
T5 220.01 209.53 0.11 0.12
T6 163.33 155.55 0.08 0.084
T7 268107 255349 132.20 138.81
TOTAL 271891.1=271892 258952.91= 258953 134.07 140.784

DOCENTE: Ing. Kildare Ascue Escalante