Fundaciones.
Excavación estructural.
Zapatas.
Z1 =¿ 13 C/U
DIMENSIONES Z-1
Z1 = 1.2 m x 1.2 m x 1.25 m
Volumen.
V z−1 = 1.2 m x 1.2 m x 1.25 m
V z−1 = 1.80 m3
V T Z−1 = 23.4 m3
Volumen V-A
V V −A = 0.25 m x 0.45 m x 21.29 ml
V V −A = 2.39 m3
V T −Exc = 25.79 m3
V concreto = 2.08
zap.
m3
Pedestal.
V concreto = (0.20 m x 0.20 m x 0.75m) * 13 C/U
Pedestal
V concreto = 0.39 3
Pedestal .
m
Viga Asísmica.
V V −A = 0.25 m x 0.25 m x 43.99 m
V V −A = 2.75 m3
Volumen total concreto.
V Total = 2.08 m3 + 039 m3 + 2.75 m3
V Total = 5.22 m3
V Rell = 20.57 m 3
A Z−1 = 18.72 m2
AV − A = 43.99 m x 0.45 m
AV − A = 19.79 m2
V Total =¿ 1.93 m3
Acarreo de tierra
Botar material sobrante de excavación
V Botar = V concreto * F. de abundamiento
V Botar = 6.79 m3
Pedestal.
L=¿ 0.75 m + 0.25 m – 0.075 m
L=¿ 0.925 m + 0.30 m (traslape)
L=¿ 1.225 ml
Lt = 1.225 ml *( 4 varillas)(13 C/U)
Lt = 63.7 ml
Viga Asísmica.
Eje A, B y C.
Eje A
L=¿ 6 m + 0.40 m + 0.85 m + 0.40 m = 7. 65 ml
L=¿ (7.65 m)*(4 C/U)
L=¿ 30.6 ml
Eje B
L=¿ 6 m + 0.40 m + 0.85 m + 0.40 m + 0.40 m = 8.05 ml
L=¿ (8.05 ml)*(4 C/U)
L=¿ 32.2 ml
Eje C
L=¿ 6 m + 0.4 m + 0.4 m + 0.85 m + 0.4 m = 8.05 ml
L=¿ (8.05 ml)*(4 C/U)
L=¿ 32.2 ml
Eje 1
L=¿ (3.73 m)*(4 C/U)
L=¿ 14.92 ml
Eje 2
L=¿ 2.93 m + 0.4 m + 0.4 m = 3.73 ml
L=¿ (3.73 ml)*(4 C/U)
L=¿ 14.92 ml
Eje 3
L=¿ 0.4 m + 5.6 m + 0.4 m + 0.26 m + 0.4 m = 7.06 ml
L=¿ (7.06 ml)*(4 C/U)
L=¿ 28.24 ml
Eje 4
L=¿ 0.4 m + 5.6 m + 0.4 m + 0.26 m + 0.4 m = 7.06 ml
L=¿ (7.06 ml)*(4 C/U)
L=¿ 28.24 ml
Eje 5
L=¿ 0.4 m + 5.6 m + 0.4 m + 0.26 m + 0.4 m = 7.06 ml
L=¿ (7.06 ml)*(4 C/U)
L=¿ 28.24 ml
LTotal =¿ 209.56 ml
TAKE-OFF
long=L zapata + L pd + LV −A
Longest =¿ 0.72 m
Longestribo = 0.8 m
V −A
Longtotal=¿ 442.4 ml
Longitud total
Longtotal = 442 ml +121.68 ml
Longtotal = 563.68 ml
lbs
Pesototal = (563.68 ml)*(0.55 )
ml
Pesototal = 310.02 lbs
TAKE-OFF
long=Lestr pd + Lestr V − A
Tabla de materiales
Etapa Descripción U/M Cantidad
03 Fundaciones
Hierro corrugado #3 std qq 4.57
Hierro liso de construcción #2 std qq 3.23
Alambre de amarre #18 recocido Lbs 33.23