Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Plantilla Costos Unitarios
Plantilla Costos Unitarios
CONCEPT UNIDA
O D
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA -
HERRAMIENTAYEQUIP O
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $ -
UN
COSTO HORARIO ID
Ho
AD
ra
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
CARGOS
FIJOS
Intereses % 0.00041 $21,120.0 $8.
8 0 83
Despreciscion % 0.00023 $21,120.0 $5.
8 0 03
Ajuste para reposicion % 0.00014 $21,120.0 $3.
5 0 06
Impuestos, seguros y almacenaje % 0.00002 $21,120.0 $0.
1 0 44
Mantenimiento % 0.00016 $21,120.0 $3.
0 0 38
0.00000 $0.
0 00
0.00000 $0.
0 00
TOTAL DE COSTO HORARIO $20.74
CONSUMOS
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Gasolina Nova Lt 2.4 $5.7 $13.80
00 5
Aceite multigrado Lt 0.0 $33. $2.64
80 00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE CONSUMOS $16.44
NOTAS
SUMA
COSTO POR M3 = $37.18 x 8.00 Hrs / 12 m3/jor DEm3COSTOS DIRECTOS INDIRECTOS Y UTILIDADES %
= $24.78 $37.18
PRECIO UNITARIO
ANALISIS DE PRECIOS UNITARIOS Fecha: 7 de Octubre, 2003 Inciso: CO-01
CONCEPT Concreto f'c=100 kg/cm2 hecho en obra R.N. agregado max. de 3/4" UNIDA
O D
M
3
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cemento 0.266 + 3% TON 0.2 $1,420. $389.
74 00 08
Arena 0.507 + 7% M3 0.5 $267.00 $144.
40 18
Grava 0.614 + 7% M3 0.6 $252.00 $166.
60 32
Agua 0.217 + 25% M3 0.2 $50.00 $13.5
70 0
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $713.08
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cuadrilla No. 11 rendimiento 1 jor / 18.00 m3 J 0.0 $659.2 $36.2
O 55 6 6
R
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $36.26
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Revolvedora Joper de 1 saco M 1.0 $24.78 $24.7
3 00 8
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $24.78
NOTAS: SUMA DE COSTOS $774.12
DIRECTOS INDIRECTOS Y
UTILIDADES %
PRECIO UNITARIO
ANALISIS DE PRECIOS UNITARIOS Fecha: 7 de Octubre, 2003 Inciso: CO-02
CONCEPT Concreto f'c=150 kg/cm2 hecho en obra R.N. agregado max. de 3/4" UNIDA
O D
M
3
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cemento 0.317 + 3% TON 0.3 $1,420. $462.
26 00 92
Arena 0.501 + 7% M3 0.5 $267.00 $143.
36 11
Grava 0.608 + 7% M3 0.6 $252.00 $163.
50 80
Agua 0.211 + 25% M3 0.2 $50.00 $13.1
63 5
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $782.98
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cuadrilla No. 11 rendimiento 1 jor / 18.00 m3 J 0.0 $659.2 $36.2
O 55 6 6
R
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $36.26
HERRAMIENTAYEQUIP O
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Revolvedora Joper de 1 saco M 1.0 $24.78 $24.7
3 00 8
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $24.78
NOTAS: SUMA DE COSTOS $844.02
DIRECTOS INDIRECTOS Y
UTILIDADES %
PRECIO UNITARIO
ANALISIS DE PRECIOS Fecha: 7 de Octubre, Inciso: CO-03
UNITARIOS 2003
CONCEPT Concreto f'c=200 kg/cm2 hecho en obra R.N. agregado max. de 3/4" UNIDA
O D
M
3
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cemento 0.358 + 3% TON 0.3 $1,420. $523.
69 00 98
Arena 0.497 + 7% M3 0.5 $267.00 $142.
32 04
Grava 0.601 + 7% M3 0.6 $252.00 $162.
43 04
Agua 0.202 + 25% M3 0.2 $50.00 $12.9
58 0
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $840.96
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cuadrilla No. 11 rendimiento 1 jor / 18.00 m3 J 0.0 $659.2 $36.2
O 55 6 6
R
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $36.26
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Revolvedora Joper de 1 saco M 1.0 $24.78 $24.7
3 00 8
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $24.78
ANALISIS DE PRECIOS Fecha: 7 de Octubre, Inciso: CO-03
UNITARIOS 2003
NOTAS: SUMA DE COSTOS $902.00
DIRECTOS INDIRECTOS Y
UTILIDADES %
PRECIO UNITARIO
ANALISIS DE PRECIOS Fecha: 7 de Octubre, Inciso: EX-001
UNITARIOS 2003
CONCEPT Excavacion de cepas de 0.00 a 1.150 m de profundidad en material incluye afine de UNIDA
O tal D
M
3
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cuadrilla No. 1 rendimiento 4.30 m3 / jor 1 jor / 4.30 m J 0.2 $81.69 $19.0
O 33 3
R
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $19.03
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $19.03 $0.57
30
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $0.57
ANALISIS DE PRECIOS Fecha: 7 de Octubre, Inciso: EX-001
UNITARIOS 2003
NOTAS: SUMA DE COSTOS $19.60
DIRECTOS INDIRECTOS Y
UTILIDADES %
PRECIO UNITARIO
ANALISIS DE PRECIOS UNITARIOS Fecha: 7 de Octubre, 2003 Inciso: PL-01
CONCEPT Plantilla de concreto hecho en obra, agregado max de 3/4" f 'c=100 kg/cm2 de 5 cm de UNID
O AD
espesor
M
2
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Concreto f 'c=100kg/cm2 1.00m2 X 0.05 + 2% M 0.051 $774.12 $39.48
3
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
TOTAL DE MATERIALES $39.48
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Cuadrilla No. 2 rendimiento 30.00 m2 / jor 1 jor / 30.00 m2 J 0.033 $197.03 $6.50
O
R
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
0.000 $0.00
TOTAL DE MANO DE OBRA $6.50
HERRAMIENTA Y EQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.030 $6.50 $0.20
0.000 $0.00
0.000 $0.00
0.000 $0.00
TOTAL DE HERRAMIENTA Y EQUIPO $0.20
J
O
R
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Peón J 1.0 $68.96 $68.9
O 00 6
R
Maestro % 0.1 $68.96 $6.90
00
Cabo % 0.0 $75.86 $3.79
50
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $79.65
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $79.65 $2.39
30
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
ANALISIS DE PRECIOS Fecha: 30 de Septiembre, Inciso: MO-2
UNITARIOS 2003TOTAL DE HERRAMIENTA Y EQUIPO $2.39
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial albañil J 1.0 $97.38 $97.3
O 00 8
R
Peón J 1.0 $68.96 $68.9
O 00 6
R
Maestro % 0.1 $166.3 $16.6
00 4 3
Cabo % 0.0 $166.3 $8.32
50 4
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $191.29
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $191.2 $5.74
30 9
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.74
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial azulejero J 1.0 $95.16 $95.1
O 00 6
R
Ayudante de azulejero J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $169.0 $16.9
00 1 0
Cabo % 0.0 $169.0 $8.45
50 1
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $194.36
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $194.3 $5.83
30 6
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.83
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial yesero J 1.0 $90.11 $90.1
O 00 1
R
Ayudante de yesero J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $163.9 $16.4
00 6 0
Cabo % 0.0 $163.9 $8.20
50 6
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $188.55
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $188.5 $5.66
30 5
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.66
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial fierrero J 1.0 $93.86 $93.8
O 00 6
R
Ayudante de fierrero J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $167.7 $16.7
00 1 7
Cabo % 0.0 $167.7 $8.39
50 1
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $192.87
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $192.8 $5.79
30 7
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.79
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial hierrero J 1.0 $93.86 $93.8
O 00 6
R
Ayudante de hierrero J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $167.7 $16.7
00 1 7
Cabo % 0.0 $167.7 $8.39
50 1
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $192.87
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $192.8 $5.79
30 7
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.79
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
TOTAL DE MATERIALES
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial pintor J 1.0 $93.10 $93.1
O 00 0
R
Ayudante de pintor J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $166.9 $16.7
00 5 0
Cabo % 0.0 $166.9 $8.35
50 5
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $191.99
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
TOTAL DE MATERIALES
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial plomero J 1.0 $93.32 $93.3
O 00 2
R
Ayudante de plomero J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $167.1 $16.7
00 7 2
Cabo % 0.0 $167.1 $8.36
50 7
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial electricista J 1.0 $95.16 $95.1
O 00 6
R
Ayudante de electricista J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $169.0 $16.9
00 1 0
Cabo % 0.0 $169.0 $8.45
50 1
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $194.36
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $194.3 $5.83
30 6
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.83
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial soldador J 1.0 $96.24 $96.2
O 00 4
R
Ayudante de soldador J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $170.0 $17.0
00 9 1
Cabo % 0.0 $170.0 $8.50
50 9
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $195.60
HERRAMIENTAYEQUIPO
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $195.6 $5.87
30 0
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.87
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial soldador J 1.0 $73.85 $73.8
O 00 5
R
Operador de revolvedora J 7.0 $68.96 $482.
O 00 72
R
Maestro % 0.1 $556.5 $55.6
00 7 6
Cabo % 0.0 $556.5 $27.8
50 7 3
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $640.06
HERRAMIENTAYEQUIP O
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $640.0 $19.2
30 6 0
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $19.20
MATERIALES
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MATERIALES $0.00
MANO DE OBRA
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Oficial carpintero de obra negra J 1.0 $90.80 $90.8
O 00 0
R
Ayudante de carpintero de obra negra J 1.0 $73.85 $73.8
O 00 5
R
Maestro % 0.1 $164.6 $16.4
00 5 7
Cabo % 0.0 $164.6 $8.23
50 5
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE MANO DE OBRA $189.35
HERRAMIENTAYEQUIP O
CONCEPTO UNIDAD CANTIDAD COSTO
IMPORTE
Herramienta menor % 0.0 $189.3 $5.68
30 5
0.0 $0.00
00
0.0 $0.00
00
0.0 $0.00
00
TOTAL DE HERRAMIENTA Y EQUIPO $5.68