Está en la página 1de 193

Dias Horas Gratificacion Asigancion

21 9 4.8% 0.88

Trabajador Sueldo base Valor Dia Valor hora % Costo Medio Total
Residente $700,000 $33,333 $3,704 5.8% $1,926
Profesional ayudante $500,000 $23,810 $2,646 4.1% $983
Jefe administrativo $600,000 $28,571 $3,175 5.0% $1,415
Jefe de bodegas $520,000 $24,762 $2,751 4.3% $1,063
Ayudante de bodega $420,000 $20,000 $2,222 3.5% $693
Pañolero $390,000 $18,571 $2,063 3.2% $598
Jefe de obra $500,000 $23,810 $2,646 4.1% $983
Capataz $480,000 $22,857 $2,540 4.0% $905
Topografo $800,000 $38,095 $4,233 6.6% $2,515
Trazador $480,000 $22,857 $2,540 4.0% $905
Prevencionista de riesgo $480,000 $22,857 $2,540 4.0% $905
Maestro primera $600,000 $28,571 $3,175 5.0% $1,415
Carpintero obra Gruesa $450,000 $21,429 $2,381 3.7% $796
Albañil $560,000 $26,667 $2,963 4.6% $1,232
Enfierrador $600,000 $28,571 $3,175 5.0% $1,415
Concretero $560,000 $26,667 $2,963 4.6% $1,232
extructurero $600,000 $28,571 $3,175 5.0% $1,415
Soldador $750,000 $35,714 $3,968 6.2% $2,211
Ceramista $515,000 $24,524 $2,725 4.3% $1,042
Yesero $456,000 $21,714 $2,413 3.8% $817
Pintor $450,000 $21,429 $2,381 3.7% $796
Ayudante $385,000 $18,333 $2,037 3.2% $583
Jornal $320,500 $15,262 $1,696 2.6% $404
$576,976 64108.4656 1.0 $26,249

Valor dia $26,249


Valor hora $2,917

Ingreso Promedio anual


Itema Horas Cantidad Total
Diaria 9 5 45
Semanales 45 4 180
Anual 180 12 2160
Feriados 15 9 135

Horas efectivamente trabajadas Total horas


Anual 180 12 2160
Feriados 15 9 135
2025

Ingreso Promedio anual


Itema Horas Valor hora Total
Diaria 2025 $2,917 $ 5,905,972

se considenran dias por año trabajado 15

Dias meses Total dias por mes


15 12 1.25%

Porcentaje de 6.7%

Gratificaion 15
Locomocion
0.03

Gratificacion Gasto total trabajdor mes Valor dia Valor hora


$33,250 $733,250 $34,917 $3,880
$23,750 $523,750 $24,940 $2,771
$28,500 $628,500 $29,929 $3,325
$24,700 $544,700 $25,938 $2,882
$19,950 $439,950 $20,950 $2,328
$18,525 $408,525 $19,454 $2,162
$23,750 $523,750 $24,940 $2,771
$22,800 $502,800 $23,943 $2,660
$38,000 $838,000 $39,905 $4,434
$22,800 $502,800 $23,943 $2,660
$22,800 $502,800 $23,943 $2,660
$28,500 $628,500 $29,929 $3,325
$21,375 $471,375 $22,446 $2,494
$26,600 $586,600 $27,933 $3,104
$28,500 $628,500 $29,929 $3,325
$26,600 $586,600 $27,933 $3,104
$28,500 $628,500 $29,929 $3,325
$35,625 $785,625 $37,411 $4,157
$24,463 $539,463 $25,689 $2,854
$21,660 $477,660 $22,746 $2,527
$21,375 $471,375 $22,446 $2,494
$18,288 $403,288 $19,204 $2,134
$15,224 $335,724 $15,987 $1,776
Estimacion costo leyes sociales

Item % del Costo Fijo


Seguro de accidentes 3%
Seguro de desempleo 3%
Aporte Patronal 1.15%
Colacion 0.88%
Locomocion 0.03%

AFP 12%
Salud
7%
Desahicio
Indemnizacion 4%
Feriado anual 6.7%

Dias Festivos 1.25% 1.25%


Aguinaldos
Total 39%
ITEMIZADO GENERAL PROPUESTA
NOMBRE CONSTRUCTORA
R.U.T. CONSTRUCTORA
Especialidad:
Obra:
Fecha:
ITEM
1.-
1.1
1.1.1
1.1.2
1.1.3
1.1.4
1.1.4.1
1.1.4.2
1.1.4.3
1.1.5
1.1.6
1.1.7
1.1.8
1.1.9
1.1.10
1.1.11
1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.4 .1
1.2.4 .2
1.2.4 .3
1.2.4 .4
1.2.4 .5
1.2.5
1.2.6
1.2.7
1.2.7.1
1.2.7.2
1.2.7.3
1.2.7.3.1
1.2.7.3.2
1.2.7.4

2.-
2.1
2.1.1
2.1.2
2.1.3
2.1.3.1
2.1.3.2
2.1.4
2.1.5
2.1.5.1
2.1.5.2
2.1.6
2.1.7
2.1.7.1
2.1.7.2
2.1.7.3
2.1.7.4
2.1.7.5
2.1.7.6
2.1.7.7
2.1.7.8
2.1.7.9
2.1.7.10
2.1.7.11
2.1.7.12
2.1.7.13
2.1.7.14
2.1.7.15
2.1.9
2.1.9.1
2.1.9.2
2.2
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.3
2.3.1
2.3.2
2.3.3
2.3.4
2.4
2.4.1
2.4.1.1
2.4.1.3
2.4.2
2.4.4
2.4.4.1
2.4.4.3
2.4.6
2.4.8
2.4.8.2
2.4.8.3
2.5
2.5.2
2.5.5
2.7
2.7.1
2.7.2
2.8
2.8.1
2.8.2
2.12
2.12.1
2.12.2
2.14
2.14.1
2.14.2
2.14.3
2.14.6

4.-
4.2
4.2.1
4.2.1.1
4.3
4.3.1
4.3.1.1
4.4
4.4.1
4.4.1.1
4.4.2
4.4.2.1
4.5
4.5.1
4.5.2
4.6
4.6.1
4.7
4.7.1.1
4.7.1.2
4.7.1.3
4.9
4.9.1
4.9.2
4.10
4.10.1
4.10.3
4.17
4.17.4
4.17.5
ITEMIZADO GENERAL PROPUESTA
NOMBRE CONSTRUCTORA
R.U.T. CONSTRUCTORA
ITEMIZADO GENERAL PRESUPUESTARIO
EDIFICIO DUOC UC SEDE SAN ANDRES II - CONCEPCION

PARTIDA
GENERALIDADES
Descripción General del Proyecto
Archivo de Obra
Permiso de Edificación-Permiso de Grúa-Instalaciones de Faenas-Otros
Libro de Obras
Certificados de Ensayos de Materiales
Certificaciones para Obtención de Recepción Municipal
Ensayes de Hormigón y otros necesarios según B.A.G.
Otras certificaciones según B.A.G.
Planos
Especificaciones Técnicas y Consultas
Herramientas y Varios
Aseo y Orden da la Obra
Otros a Juicio del Proponente
Boletas de Garantía seg.B.A.G.
Pólizas de Seguro según B.A.G.
Instalacion de Faenas
Cierros Perimetrales de la Obra
Cierros al Interior del Edificio A
Protección de Vegetación Existente
Recintos Varios
Oficina ITO
Oficina Administrador
Oficina de Planos y Sala de Reuniones
Comedores, Baños, etc
Otros a Juicio del Proponente
Instalaciones Provisorias
Carteles
Trazados y Niveles
Verificación de Cotas, Niveles y Trazados
Nivel del Edificio
Trazado de la Obra
Cerco de Trazado
Mantención de Trazado durante el Desarrollo de la Obra
Recepción del Trazado y Niveles
Sub Total Generalidades
OBRA GRUESA
EXCAVACIONES
Escarpe del Terreno
Depresión de Napa
Saneamiento Provisorio de Aguas Lluvias
Excavaciones
Shotcret de Canaleta
Excavaciones a Máquina
Excavaciones a Mano
Excavaciones a Mano Para Talud
Excavaciones a Mano Para Fundaciones
Demolición Muro H.A. Existente
Estabilidad de Taludes con Sistema "Soil Nailing" (Proyecto Estratos)
Recepción de Taludes previo hormigón Proyectado
Lechada de cemento de protección previo Shotcret
Barbacanas de Drenaje
Anclajes de Acero de Prueba
Malla Hexagonal de Alambre
Anclaje de Malla
Zanja de Anclaje
Hormigón Proyectado (Shotcret) Permanente
Hormigón Proyectado (Shorcret) Temporal
Vaina Plastica
Instalación de Barras de Anclaje
Lechada de cemento de Inyección
Placa de Acero de 20 x 20 cm e= 10 mm Galvanizada
Aplicación de Torque de Apriete
Pruebas de Carga y Certificación
Retiro de Excedentes a Botadero
Retiro de Excedentes a Botadero
Certificado y Recibos del Botadero
FUNDACIONES
Emplantillado 7 cms. H 5
Enfierradura A 63
Enfierradura A 44
Moldajes
Hormigón H 35
Bases de Pavimento y Relleno entre Fundaciones
Estabilizado Compactado entre Losa Fundación y Radier
Polietileno 0.2 mm.
Radier Afinado 10 cms. H 25
Malla de Acero Acma C-188
Estructuras Principales
Hormigón Armado Muros, Vigas, Losas, Pilares, Cadenas H 35
Hormigón de Muros
Hormigón de Losas
Nivelación de Losas de Hormigón
Moldajes de Acero Peri Sistema Vario
Moldajes de Acero Peri Sistema Vario Muros
Moldajes de Acero Peri Sistema Vario Losas
Desmoldante (incoloro)
Acero Calidad A 63
Acero Calidad A 63 Muros
Acero Calidad A 63 Losas
Estructuras de Acero
Estructuras Acero A - 42 -27 Es Galvanizado en Caliente Puente Conexión
Estructuras Acero A - 42 -27 Es Galvanizado en Caliente Torre Ascensores
Tabiquería Metalcon
Tabiquería Metalcon e= 0,85 mm.
Refuerzos en Tabiques
Techumbre
Estructura Metalcón
Terciado Estructural 15 mm.
Aislación Térmica
Aislación Térmica Poliestireno Extruido 50 mm. Losa 6º Piso
Aislán Glass R141 e=50 mm.
Cubierta
Cubierta Verde
Membrana PVC Sanrnafil F610-12 Felt
Membrana Geotextil de 500 KG/m²
Planchas PV4 de 0.5 mm Zincalum
Sub Total Obra Gruesa
TERMINACIONES
Revestimientos Interiores
Tabiques Yeso/Cartón 15m + 10 m ambas caras
Aislán Glass 60 mm.
Cielos
Yeso Cartón 10 mm.
Yeso Cartón HR 10 mm.
Pavimentos
Porcelanatos
Porcelanato Cementi Gris 45/90 MK
Alfombras
Boucle Office Color Dakota 4086 C Etersol
Juntas de Dilatación
Junta para Muros Modelo CPSAL 50 x 100
Sikaflex 1 Plus con Cordón de Respaldo
Guardapolvos
Guardapolvos Porcelanatos H 10 cms
Aluminios y Cristales
Ventanas Exteriores
Puertas Vidriadas Simples
Puertas Vidriadas Dobles
Marcos, Centros, Pilastras y Endolados
Marcos Rebajados Trupán Enchapado
Centros Pino Finger Joint
Puertas
Puertas de Placa Llena
Celosías para Puertas
Pinturas y Barnices
Oleo Sintético Brillante Kem Pro
Esmalte Epoxico Sipa
Sub Total Terminaciones
TOTAL COSTO DIRECTO
GASTOS GENERALES %
UTILIDADES %
TOTAL NETO
19% IVA
TOTAL PRESUPUESTO

Firma Contratista
STARIO
- CONCEPCION

UN CANT P.U. UF TOTAL UF


28,789

GL 1 1.0 1.0
GL 1 1,110 1,109.67
GL 40 0.31 12.21
0.00
GL 1 0.97 0.97
GL 0.00
GL 0.00
GL 50 0.54 27.02
GL 1 0.16 0.16
GL 1 5.61 5.61
GL 1 1.54 1.54
GL 1 0.00 0.00
GL 0.00 0.00
GL 0.00 0.00
0.00 0.00
ML 240 0.46 109.60
ML 88 0.25 22.23
GL 1 0.00 0.00
0.00 0.00
GL 1 10.55 10.55
GL 1 5.89 5.89
GL 1 3.31 3.31
GL 1 23.39 23.39
GL 1 0.00 0.00
GL 1 36.82 36.82
GL 2 2.49 4.98

GL 1 0.74 0.74
GL 1 1.11 1.11
GL 1 1.19 1.19
GL 1 8.31 8.31
GL 1 0.18 0.18
GL 1 0.18 0.18
1,214.66 1,386.67

M2 22,894 0.10 2,353.74


GL 1 0.03 0.03

M3 16 0.33 5.30
ML 263 1.08 283.51
M3 20,500 0.90 18,436.67

M3 4,158 0.74 3,097.05


M3 1,298 0.74 966.62
GL 1 0.12 0.12

GL 1 0.18 0.18
M2 2,160 1.66 3,578.76
CU 973 0.90 873.94
CU 675 12.58 8,499.71
M2 2,160 0.87 1,878.92
CU 547 1.25 683.24
ML 170 2.36 401.06
M2 2,160 1.62 3,507.39
M2 2,160 1.68 3,625.23
ML 675 0.88 596.59
CU 675 7.87 5,312.30
M3 1 5.15 7.10
CU 675 0.89 603.28
CU 675 0.39 264.86
CU 3 0.00 0.00
0.00
M3 4,173 0.63 2,637.10
CU 1 0.00 0.00
0.00
M3 163 1.27 206.78
KG 215,903 0.06 12,616.29
KG 0.00
M2 387 0.14 52.49
M3 1,444 2.03 2,929.91

M3 1,105 0.57 631.13


M2 2,329 0.03 76.97
M3 231 1.91 440.45
KG 6,926 0.07 486.48

M3 1,009 2.03 2,046.31


M3 1,053 2.08 2,191.45
M2 5,910 0.11 639.39

M2 6,817 0.56 3,831.59


M2 6,147 0.19 1,195.71
M2 12,964 0.05 627.10

KG 76,147 0.08 5,772.18


KG 109,388 0.54 58,958.99

KG 17,370 4.66 80,923.30


KG 0.00

M2 3,150 0.00
M2 36.00 0.00

KG 247 0.00
M2 36 0.00

M2 1,458 0.19 281.38


M2 222 0.20 44.70

M2 442 0.89 391.84


M2 1,458 1.08 1,570.90
M2 1,458 0.73 1,057.48
M2 36 0.94 33.59
63.36 234,619
28,788.59

M2 1,458 0.56 811.93


M2 1,458 0.20 294.05

M2 507 0.21 105.20


M2 332 0.26 86.91
M2 3,296 0.41 1,345.73

M2 359 0.59 211.56

ML 3,204 0.15 493.64


ML 3,988 0.25 1,012.64

ML 835 0.19 162.26

M2 2,059 3.52 7,244.29


CU 10 6.16 61.64
CU 2 8.23 16.47

ML 2,233 0.26 571.21


ML 980 0.11 105.08

CU 131 0.85 110.71


CU 72 0.24 17.25

M2 10,205 0.31 3,162.53


M2 9,222 0.18 1,660.89
23 17,473.96
1,301 253,480
25.00% UF 63,369.94
20.00% UF 50,695.95
UF 367,545.65
19% UF 69,833.67
UF 437,379.32
ANALISIS DE PRECIO UNITARIO

Partida Archivo de Obra Unidad Gl


Item 1.1.1 Precio unitario $ 28,630
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 contrato
2 bases administrativas uni 1 3890 $ 3,890
3 eett de arquitectura uni 1 4,590 $ 4,590
4 eett de especialidades uni 1 4,590 $ 4,590
5 Planos de arquirectura detalle uni 1 3,890 $ 3,890
6 planos de arquirectura general uni 1 3,890 $ 3,890
7 planos de especialidades uni 1 3,890 $ 3,890
8 planos de calculo estructural uni 1 3,890 $ 3,890

Total A $ 28,630

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B $0

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C $0

TOTAL $ 28,630
ANALISIS DE PRECIO UNITARIO

Partida Permiso de Edificación-Permiso de Grúa-Instalaciones de Faenas-Otros Unidad


Item 1.1.2 Precio unitario
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 permiso edificacion gl 1 29340000
2 permiso ocupacion bnup gl 1 947300

3 permiso obras
preliminares , instalacion de
gruas (Art. 5.1.3. o.g.u.c) gl 1 1,658,400
4
5

Total A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total C

TOTAL
Gl
$ 31,945,700

PRECIO
TOTAL
($)
$ 29,340,000
$ 947,300

$ 1,658,400

$ 31,945,700

PRECIO
TOTAL
($)

PRECIO
TOTAL
($)

$ 31,945,700
ANALISIS DE PRECIO UNITARIO

Partida Libro de Obras Unidad Gl


Item 1.1.3 Precio unitario $ 8,790
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Libro de obras manifold uni 1 8490 $ 8,490
2 lapiz pasta azul uni 1 300 $ 300
3
4
5

Total A $ 8,790

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C

TOTAL $ 8,790
ANALISIS DE PRECIO UNITARIO

Partida Certificaciones para Obtención de Recepción Municipal Unidad


Item 1.1.4.1 Precio unitario
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 certificado de recepcion gl 1 28000
2
3
4
5

Total A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total C

TOTAL
Gl
$ 28,000

PRECIO
TOTAL
($)
$ 28,000

$ 28,000

PRECIO
TOTAL
($)

PRECIO
TOTAL
($)

$ 28,000
ANALISIS DE PRECIO UNITARIO

Partida Certificaciones para Obtención de Recepción Municipal Unidad Gl


Item 1.1.5 Precio unitario $ 15,560
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 planos de arquitectura detalle uni 1 3890 $ 3,890
2 planos de arquitectura general uni 1 3890 $ 3,890
3 planos de especialidad uni 1 3890 $ 3,890
4 planos de calculo estructural uni 1 3890 $ 3,890
5

Total A $ 15,560

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C

TOTAL $ 15,560
ANALISIS DE PRECIO UNITARIO

Partida Especificaciones Técnicas y Consultas Unidad Gl


Item 1.1.6 Precio unitario $ 4,590
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 eett de la obra uni 1 4590 $ 4,590
2
3
4
5

Total A $ 4,590
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Herramientas y Varios Unidad


Item 1.1.7 Precio unitario
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 montacargas hr 0.03 15000
2 trompo bencinero 125lts mes 1 70205
3 vibradores hr 0.013 100,200
4 taladro uni 0.2 59,900
5 soldadora uni 0.2 88,990
6 carretilla uni 0.01 29,900
7 palas uni 0.1 6,990
8 chuzos uni 0.1 16,990
9 andamios uni 0.30 100,000
10 alzamprimas uni 0.30 15,000
11 retro excavadora hr 0.16 30,000
12 camion tolva hr 0.22 15,200
13 martillo uni 0.1 7,520
14 cascos uni 0.1 9,500
15 excavadora hr 0.16 30,000
16 huincha uni 0.02 16,020
17 cargador frontal hr 0.20 15,400

Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 soldador dia 0.025 $ 37,411
2 maestro primera dia 0.025 $ 29,929
3 carpintero dia 0.025 $ 29,929
4 albañil dia 0.025 $ 27,933
5 ayudante dia 0.003 $ 19,204
6 jornal dia 0.003 $ 15,987
7
8
9
10
11
12 SUBTOTAL
13 LEYES SOCIALES 35%
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
Gl
$ 161,377

PRECIO
TOTAL
($)

Precio unitario A

PRECIO
TOTAL
($)
$ 450
$ 70,205
$ 1,303
$ 11,980
$ 17,798
$ 329
$ 699
$ 1,699
$ 30,000
$ 4,500
$ 4,800
$ 3,344
$ 752
$ 950
$ 4,800
$ 320
$ 3,080

$ 157,009
Precio unitario B
PRECIO
TOTAL
($)
$ 935
$ 748
$ 748
$ 698
$ 58
$ 48

$ 3,236
$ 1,132
$ 4,368
Precio unitario C

$ 161,377
ANALISIS DE PRECIO UNITARIO

Partida Aseo y Orden da la Obra Unidad Gl


Item 1.1.8 Precio unitario $ 44,373
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 cargador frontal hr 0.3 25000 $ 7,500
2 botadero externo m3 1 3200 $ 3,200
3 escobillon uni 2.00 3,200 $ 6,400
4 camion tolva hr 0.21 15,200 $ 3,192
5 pala uni 2.00 6,990 $ 13,980
6

Total B $ 34,272
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.25000 $ 29,929 $ 7,482
2
3 SUBTOTAL
4 LEYES SOCIALES 35% $ 2,619
Total C $ 10,101
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 44,373
ANALISIS DE PRECIO UNITARIO

PARTIDA: otros juicios del proponente CANTIDAD

A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Cierros Perimetrales de la Obra Unidad ml


Item 1.2.1 Precio unitario $ 13,147
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 plancha zincalum 5v uni 0.1 7339 $ 734
2 pino 2" x4" uni 0.1 2390 $ 239
3 latex blanco gl 0.4 12,950 $ 5,180
4 clavo corriente kg 0.05 890 $ 45
5

Total A $ 6,197
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.1 7520 $ 752
2 rodillo uni 0.1 3987 $ 399
3 huincha 8m uni 0.01 16,020 $ 160
4 brocha uni 0.02 1,990 $ 40
Total B $ 1,351
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 29000 $ 2,175
2 jonal dia 0.136 14500 $ 1,972
3 SUBTOTAL $ 4,147
4 LEYES SOCIALES 35% $ 1,451
Total C $ 5,598
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 13,147
ANALISIS DE PRECIO UNITARIO

Partida Cierros al Interior del Edificio A Unidad ml


Item 1.2.2 Precio unitario $ 7,274
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 osb estructural uni 0.1 8700 $ 870
2 pino 2" x4" uni 0.1 2390 $ 239
3 clavo corriente kg 0.05 890 $ 45
4
5

Total A $ 1,154
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.1 7520 $ 752
2 huincha 8m uni 0.01 16,020 $ 160
3
4
Total B $ 912
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 $ 22,446 $ 1,683
2 jonal dia 0.136 $ 15,987 $ 2,174
3 SUBTOTAL $ 3,858
4 LEYES SOCIALES 35% $ 1,350
Total C $ 5,208
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL

TOTAL UNITARIO (A+B+C)


TOTAL $ 7,274
ANALISIS DE PRECIO UNITARIO

PARTIDA: CANTIDAD

A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Protección de Vegetación Existente Unidad gl


Item 1.2.3 Precio unitario $0
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Oficina ITO Unidad gl


Item 1.2.4 .1 Precio unitario $ 303,585
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
$0

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 container con baño(ito) mes 1 165000 $ 165,000
2 camion grua pluma hr 0.40 36000 $ 14,400
3 escritorio con cajonera uni 1 119,000 $ 119,000
4 linea telefonica con internet mes 1 50,000 $ 50,000
5

Total B $ 298,400
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante dia 0.2 $ 19,204 $ 3,841
2 $0
3 SUBTOTAL $ 3,841
4 LEYES SOCIALES 35% $ 1,344
Total C $ 5,185
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 303,585
ANALISIS DE PRECIO UNITARIO

Partida Oficina Administrador Unidad gl


Item 1.2.4 .2 Precio unitario $ 169,592
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Contenedores Oficina 20´ Forrado mes 1.0000 143491 $ 143,491
2 camion grua pluma hr 0.44 36,000 $ 16,000
3 $0
4 $0
Total B $ 159,491
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante dia 0.2 $ 37,411 $ 7,482
2 $0
3 SUBTOTAL $ 7,482
4 LEYES SOCIALES 35% $ 2,619
Total C $ 10,101
Precio unitario C

TOTAL UNITARIO (A+B+C) $ 169,592


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Oficina de Planos y Sala de Reuniones Unidad


Item 1.2.4 .3 Precio unitario
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Container Oficina mes 1.0000 71745.5
2 camion grua pluma hr 0.167 36,000
3
4
Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Ayudante dia 0.2 $ 37,411
2
3 SUBTOTAL
4 LEYES SOCIALES 35%

Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
gl
$ 95,329

PRECIO
TOTAL
($)

$0
Precio unitario A

PRECIO
TOTAL
($)
$ 71,746
$ 6,000
$0
$0
$ 77,746
Precio unitario B

PRECIO
TOTAL
($)
$ 7,482
$0
$ 7,482
$ 2,619
$ 17,583
Precio unitario C

$ 95,329
ANALISIS DE PRECIO UNITARIO

Partida Oficina de Planos y Sala de Reuniones Unidad gl


Item 1.2.4 .3 Precio unitario $ 673,319
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Container Bodega 20´ mes 1 114793 $ 114,793
2 Container Bodega 40 ´ mes 1 172182 $ 172,182
3 container de baño y duchas 40 mes 1 200,888 $ 200,888
4 container de comedor 40 uni 1 172,182 $ 172,182
5 camion grua pluma hr 0.16 36,000 $ 5,760

Total B $ 665,805
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal dia 0.2 $ 15,987 $ 3,197
2 $0
3 SUBTOTAL $ 3,197
4 LEYES SOCIALES 35% $ 1,119
Total C $ 7,514
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 673,319
ANALISIS DE PRECIO UNITARIO

PARTIDA: otros juicios del oferente CANTIDAD

A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 caseta de guardia uni 1 90000 $ 90,000
2 camion grua pluma hr 0.4 36000 $ 14,400
3
4
Total B $ 104,400
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal dia 0.375 14500 $ 5,438
2 $0
3 $0
4 LEYES SOCIALES % $0
Total C $ 5,438
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 109,838
ANALISIS DE PRECIO UNITARIO

Partida Otros a Juicio del Proponente Unidad gl


Item 1.2.5 Precio unitario $ 1,060,000
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 empalme provisorio gl 1 160000 $ 160,000
2 instalaciones electricas provisoria gl 1 260000 $ 260,000
3 empalme provisorio agua potable gl 1 160,000 $ 160,000
4 instalaciones a.p contruccion provisorias gl 1 160,000 $ 160,000
5 empalme provisorio alcantarillado gl 1 160,000 $ 160,000
6 instalaciones construccion provisorias gl 1 160,000 $ 160,000

Total B $ 1,060,000
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL $ 1,060,000
ANALISIS DE PRECIO UNITARIO

Partida Carteles Unidad gl


Item 1.2.6 Precio unitario $ 71,702
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2 clavos kg 0.05 890 $ 45
3 pino 2x4 uni 0.25 2,390 $ 598
4 Plancha fierro laminada 0.5mm uni 1 12,690 $ 12,690
5 Perfil tubular cuadrado uni 0.2 13,990 $ 2,798
6 disco de corte uni 0.233 1,350 $ 315
7 $0
8 $0

Total A $ 16,445
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.2 5390 $ 1,078
2 esmeril angular uni 0.10 28480 $ 2,848
3 soldadora bauker uni 0.20 166,390 $ 33,278
4
Total B $ 37,204
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero M2 0.2 $ 22,446 $ 4,489
2 soldador ML 0.2 $ 37,411 $ 7,482
3 ayudante M2 0.2 $ 19,204 $ 3,841
4

SUBTOTAL $ 15,812
LEYES SOCIALES 39% $ 6,167

Total C $ 21,979
Precio unitario C
TOTAL UNITARIO (A+B+C)
TOTAL $ 71,702
ANALISIS DE PRECIO UNITARIO

Partida Verificación de Cotas, Niveles y Trazados Cantidad 1.0


Item 1.2.7.1 Unidad Gl Precio unitario $ 21,262
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Planos Gl 5 $ 3,200 $ 16,000
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ 16,000

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 23,943 $ 24
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 62
LEYES SOCIALES 39% $ 24
Total C $ 87

TOTAL UNITARIO (A+B+C) $ 21,262


ANALISIS DE PRECIO UNITARIO

Partida Nivel de edificio Cantidad 1.0


Item 1.2.7.2 Unidad Gl Precio unitario $ 31,966
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Estacas, 2 x 2 x 3,20 m Pino dimensionado seco Uni 132 $ 202 $ 26,620
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ 26,620

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,237

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109

TOTAL UNITARIO (A+B+C) $ 31,966


ANALISIS DE PRECIO UNITARIO

Partida Trazado de la obra Cantidad 1.0


Item 1.2.7.3 Unidad Gl Precio unitario $ 34,386
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Estacas, 2 x 2 x 3,20 m Pino dimensionado seco Uni 144 $ 202 $ 29,040
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ 29,040

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,237

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109

TOTAL UNITARIO (A+B+C) $ 34,386


ANALISIS DE PRECIO UNITARIO

Partida Cerco Trazado Cantidad 1.0


Item 1.2.7.3.1 Unidad Gl Precio unitario $ 239,316
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Estaca 1 x 6 x 3,20 m Pino dimensionado verde Uni 11 $ 2,050 $ 21,781
2 1 x 6 x 3,20 m Pino dimensionado verde Uni 68 $ 2,050 $ 139,400
3 Clavo corriente 2" x 12mm bolsa 1kg Kg 2 $ 1,350 $ 2,700
4 #14/1 kg Alambre negro recocido Kg 5 $ 13,990 $ 69,950
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ 233,831

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 Martillo carpintero 16 Oz acero 1 0.005 $ 5,990 $ 30
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,267

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.002 $ 39,905 $ 80
2 Ayudante 1 ml 0.002 $ 19,204 $ 38
3 Ayudante 2 ml 0.002 $ 19,204 $ 38
4 $ -
5 $ -
SUBTOTAL $ 157
LEYES SOCIALES 39% $ 61
Total C $ 218

TOTAL UNITARIO (A+B+C) $ 239,316


ANALISIS DE PRECIO UNITARIO

Partida Mantención de Trazado durante el Desarrollo de la Obra Cantidad 1.0


Item 1.2.7.3.2 Unidad Gl Precio unitario $ 5,284
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109

TOTAL UNITARIO (A+B+C) $ 5,284


ANALISIS DE PRECIO UNITARIO

Partida Mantención de Trazado durante el Desarrollo de la Obra Cantidad 1.0


Item 1.2.7.4 Unidad Gl Precio unitario $ 5,284
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109

TOTAL UNITARIO (A+B+C) $ 5,284


ANALISIS DE PRECIO UNITARIO

Partida Escarpe de Terreno Unidad m2


Item 2.1.1 Precio unitario $ 2,960
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Cargador Frontal m2 1 $ 34,000 $ 71
2 Camion Tolva 12 m3 3 $ 10,000 $ 2,500
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 2,871

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal 1 m2 0.001 $ 15,987 $ 16
2 Jornal 2 m2 0.001 $ 15,987 $ 16
3 Jornal 3 m2 0.001 $ 15,987 $ 16
4 Jornal 4 m2 0.001 $ 15,987 $ 16
5 $ -
SUBTOTAL $ 64
LEYES SOCIALES 39% $ 25
Total C $ 89

TOTAL UNITARIO (A+B+C) $ 2,960


ANALISIS DE PRECIO UNITARIO

Partida Escarpe de Terreno Unidad m2


Item 2.1.2 Precio unitario $ 725
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Motobomba a gasolina 3" 7HP 1000l/L L/min 0.005 $ 211,990 $ 2
2 Gasolina litro L 1 $ 722 $ 722
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 724

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro L/min 0.00002 $ 29,929 $ 0
2 Joranal L/min 0.00002 $ 15,987 $ 0
3 Joranal L/min 0.00002 $ 15,987 $ 0
4 $ -
5 $ -
SUBTOTAL $ 1
LEYES SOCIALES 39% $ 0
Total C $ 1

TOTAL UNITARIO (A+B+C) $ 725


ANALISIS DE PRECIO UNITARIO

Partida Excavacion Unidad m3


Item 2.1.3.1 Precio unitario $ 9,608
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 1 $ 20,000 $ 1,250
2 Camion Tolva 12 m3 3 $ 10,000 $ 2,500
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 4,049

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.06250 $ 15,987 $ 999
2 jornal m3 0.06250 $ 15,987 $ 999
3 jornal m3 0.06250 $ 15,987 $ 999
4 jornal m3 0.06250 $ 15,987 $ 999
5 $ -
SUBTOTAL $ 3,997
LEYES SOCIALES 39% $ 1,562
Total C $ 5,559

TOTAL UNITARIO (A+B+C) $ 9,608


ANALISIS DE PRECIO UNITARIO

Partida Shotcret canaleta Unidad ml


Item 2.1.3.2 Precio unitario $ 31,057
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 shotcrete fabricado en planta m3 0.01 52342 $ 523
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ 523

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
2 CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
3 GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
4 COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
5 BARREDORA REMOLCADA CON MOTOR AUXILIAR dia 0.040 65,850 $ 2,634
6 $ -
7 $ -
8 $ -
Total B $ 14,601

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 concretero m3/dia 1 $ 27,933 $ 3,514
2 concretero m3/dia 1 $ 27,933 $ 3,514
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 jornal m3/dia 1 $ 15,987 $ 2,011
5 $ -
SUBTOTAL $ 11,455
LEYES SOCIALES 39% $ 4,478
Total C $ 15,933

TOTAL UNITARIO (A+B+C) $ 31,057


ANALISIS DE PRECIO UNITARIO

Partida Excavacion Unidad m3


Item 2.1.4 Precio unitario $ 25,891
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.25000 $ 15,987 $ 3,997
2 jornal m3 0.25000 $ 15,987 $ 3,997
3 jornal m3 0.25000 $ 15,987 $ 3,997
4 jornal m3 0.25000 $ 15,987 $ 3,997
5 $ -
SUBTOTAL $ 15,987
LEYES SOCIALES 39% $ 6,249
Total C $ 22,236

TOTAL UNITARIO (A+B+C) $ 25,891


ANALISIS DE PRECIO UNITARIO

Partida Excavacion a Mano Para Talud Unidad m3


Item 2.1.5.1 Precio unitario $ 21,444
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.13333 $ 15,987 $ 2,132
2 jornal m3 0.13333 $ 15,987 $ 2,132
3 jornal m3 0.13333 $ 15,987 $ 2,132
4 jornal m3 0.13333 $ 15,987 $ 2,132
5 jornal m3 0.13333 $ 15,987 $ 2,132
6 jornal m3 0.13333 $ 15,987 $ 2,132
SUBTOTAL $ 12,789
LEYES SOCIALES 39% $ 5,000
Total C $ 17,789

TOTAL UNITARIO (A+B+C) $ 21,444


ANALISIS DE PRECIO UNITARIO

Partida Excavacion a Mano Para Fundaciones Unidad m3


Item 2.1.5.2 Precio unitario $ 21,444
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.13333 $ 15,987 $ 2,132
2 jornal m3 0.13333 $ 15,987 $ 2,132
3 jornal m3 0.13333 $ 15,987 $ 2,132
4 jornal m3 0.13333 $ 15,987 $ 2,132
5 jornal m3 0.13333 $ 15,987 $ 2,132
6 jornal m3 0.13333 $ 15,987 $ 2,132
SUBTOTAL $ 12,789
LEYES SOCIALES 39% $ 5,000
Total C $ 17,789

TOTAL UNITARIO (A+B+C) $ 21,444


ANALISIS DE PRECIO UNITARIO

Partida Demolicion Muro H.A Existente Unidad gl


Item 2.1.6 Precio unitario $ 3,510
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Martillos Hidráulicos Cat H140Es m3 0.005 $ 30,952 $ 155
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 3,510

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6
SUBTOTAL $ -
LEYES SOCIALES 39% $ -
Total C $ -

TOTAL UNITARIO (A+B+C) $ 3,510


ANALISIS DE PRECIO UNITARIO

Partida Recepción de Taludes previo hormigón Proyectado Unidad Gl


Item 2.1.7.1 Precio unitario $ 5,284
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 0 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
9 $ -
10 $ -
Total A $ -

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109

TOTAL UNITARIO (A+B+C) $ 5,284


ANALISIS DE PRECIO UNITARIO

Partida Lechada de cemento de protección previo Shotcret Unidad m2


Item 2.1.7.2 Precio unitario $ 47,688
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD UNITARIA PRECIO PRECIO
UNITARIO TOTAL
($) ($)
shotcrete fabricado en planta m3 0.01 52342 $ 523

Total A $ 523
Precio unitario A x m2

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. PRECIO PRECIO
CANTIDAD
UNITARIA UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MOTOR AUXILIAR dia 0.040 65,850 $ 2,634
Total B $ 14,601
Precio unitario B x m2

MANO DE OBRA
DESIGNACION UNID. PRECIO PRECIO
CANTIDAD
UNITARIA UNITARIO TOTAL
C ($) ($)
ITEM concretero m3/dia 1 $ 27,933 $ 3,514
concretero m3/dia 1 $ 29,929 $ 3,765
ayudante m3/dia 1 $ 19,204 $ 2,416
jornal m3/dia 1 $ 15,987 $ 2,011
$ 11,706
SUBTOTAL $ 23,412
LEYES SOCIALES 39% $ 9,152

Total C $ 32,564
Precio unitario C x m2

TOTAL UNITARIO (A+B+C)


TOTAL $ 47,688
ANALISIS DE PRECIO UNITARIO

Partida Barbacanas de Drenaje Unidad cu


Item 2.1.7.3 Precio unitario $ 25,869
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Tubo PVC-S 50mm x 6m mt 0.167 3,990 $ 665
Geotextil Nt-11 1X10M mt 0.04 10990 $ 440

Total A $ 1,105
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra Barreno Ahoyador cu 0.005 169990 $ 850

Total B $ 850
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C
TOTAL UNITARIO (A+B+C)
TOTAL $ 25,869
ANALISIS DE PRECIO UNITARIO

Partida Anclajes de Acero de Prueba Unidad cu


Item 2.1.7.4 Precio unitario $ 362,300
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
pernos de anclaje de 8 mt cu 1 344256 $ 344,256

Total A $ 344,256
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra Barreno A cu 0.005 169990 $ 850

Total B $ 850
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 Ayudante m3/dia 1 $ 19,204 $ 2,416
3 $0
4 $ 6,181
5 SUBTOTAL $ 12,362
LEYES SOCIALES 39% $ 4,832

Total C $ 17,194
Precio unitario C
TOTAL $ 362,300
ANALISIS DE PRECIO UNITARIO

Partida Malla Hexagonal de Alambre Unidad m2


Item 2.1.7.5 Precio unitario $ 25,037
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Malla Hexagonal
Galvanizada Inchalam m2 1 1122.7 $ 1,123

Total A $ 1,123
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total B $0
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C

TOTAL $ 25,037
ANALISIS DE PRECIO UNITARIO

Partida Anclaje de Malla Unidad cu


Item 2.1.7.6 Precio unitario $ 35,955
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Hilo un metro un 1 11190 $ 11,190

Total A $ 11,190
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra cu 0.005 169990 $ 850

Total B $ 850
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C
TOTAL $ 35,955
ANALISIS DE PRECIO UNITARIO

Partida Zanja de Anclaje Unidad ML


Item 2.1.7.7 Precio unitario $ 67,918
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
ripio m3 0.82 15000 $ 12,300
arena m4 0.48 16000 $ 7,680
cemento polpaicom5 3 4,025 $ 13,283

Total A $ 33,263
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
pala un 0.005 5690 $ 28
carretilla un 0.005 27000 $ 135
betonera un 0.005 300,000 $ 1,500

Total B $ 1,663
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 27,933 $ 3,514
2 Concretero m3/dia 1 $ 27,933 $ 3,514
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 Jornal m3/dia 1 $ 19,204 $ 2,416
5 $ 11,860
SUBTOTAL $ 23,720
LEYES SOCIALES 39% $ 9,272

Total C $ 32,992
Precio unitario C
TOTAL $ 67,918
ANALISIS DE PRECIO UNITARIO

Partida Hormigón Proyectado (Shotcret) Permanente Unidad M2


Item 2.1.7.8 Precio unitario $ 46,737
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
shotcrete fabricado en planta m3 0.1 52342 $ 5,234

Total A $ 5,234
Precio unitario A x m2

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MOTOR
dia 0.040 65,850 $ 2,634
total b $ 14,601
Precio unitario B x m2

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 29,929 $ 3,765
2 Concretero m3/dia 1 $ 29,929 $ 3,765
3 ayudante m3/dia 1 $ 15,987 $ 2,011
4 Jornal m3/dia 1 $ 15,987 $ 2,011
5 $ 11,552
SUBTOTAL $ 23,105
LEYES SOCIALES 39% $ 9,032

Total C $ 32,136
Precio unitario C

TOTAL $ 46,737
ANALISIS DE PRECIO UNITARIO

Partida Hormigón Proyectado (Shorcret) Temporal Unidad m2


Item 2.1.7.9 Precio unitario $ 48,308
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
shotcrete fabricado en planta m3 0.03 52342 $ 1,570

Total A $ 1,570
Precio unitario A x m2

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAU dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MO
dia 0.040 65,850 $ 2,634
total b $ 14,601
Precio unitario B x m2

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 29,929 $ 3,765
2 Concretero m3/dia 1 $ 29,929 $ 3,765
3 ayudante m3/dia 1 $ 15,987 $ 2,011
4 Jornal m3/dia 1 $ 15,987 $ 2,011
5 $ 11,552
SUBTOTAL $ 23,105
LEYES SOCIALES 39% $ 9,032

Total C $ 32,136
Precio unitario C

TOTAL $ 48,308
ANALISIS DE PRECIO UNITARIO

Partida Vaina Plastica Unidad Ml


Item 2.1.7.10 Precio unitario $ 25,430
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Tubo PVC-S
50mm x 6m mt 0.167 3,990 $ 665

Total A $ 665
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Taladro Tierra
Barreno
Ahoyador
Motorizado
150mm cu 0.005 169990 $ 850

Total B $ 850
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C

TOTAL $ 25,430
ANALISIS DE PRECIO UNITARIO

Partida Instalación de Barras de Anclaje Unidad Ml


Item 2.1.7.11 Precio unitario $ 226,437
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

PERNOS DE
ANCLAJE PARA
SOIL NAILING cu 1 165000 $ 165,000

Total A $ 165,000
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

COMPRESOR 3.5
HP 10 BAR
BAUKER cu 0.015 249,571 $ 3,744

Camión con cesta


elevadora de brazo
articulado de 16 m
de altura h 0 10,243 $ 1,444

Equipo mecánico
para realización de
los trabajos de
perforación h 0.502 64,411 $ 32,334

Total B $ 37,522
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C

TOTAL $ 226,437
ANALISIS DE PRECIO UNITARIO

Partida Lechada de cemento de Inyección Unidad m3


Item 2.1.7.12 Precio unitario $ 148,314
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

lechada
fabricado en
planta m3 0.01 52342 $ 523

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Camión con
cesta elevadora
de brazo
articulado de 16
m de altura h 0 10,243 $ 1,444

Equipo para
inyecciones de
lechada de
cemento, con
bomba de
presión y carro
de perforación
para taladros. h 1 220,297 $ 128,874
BETONERA un 0.005 300,000 $ 1,500

Total B $ 131,818
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 27,933 $ 3,514
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3
4 $0
5 $ 5,930
SUBTOTAL $ 11,860
LEYES SOCIALES 39% $ 4,636

Total C $ 16,496
Precio unitario C

TOTAL $ 148,314
ANALISIS DE PRECIO UNITARIO

Partida Placa de Acero de 20 x 20 cm e= 10 mm Galvanizada Unidad cu


Item 2.1.7.13 Precio unitario $ 25,715
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Placa de Acero cm e= 10 mm
Galvanizada cu 1 3199 $ 3,199

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
maquina de soldar Ml 0.005 $ 359,990 $ 1,800

Total B $ 1,800
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721

Total C $ 23,915
Precio unitario C

TOTAL $ 25,715
ANALISIS DE PRECIO UNITARIO

Partida Aplicación de Torque de Apriete Unidad cu


Item 2.1.7.14 Precio unitario $ 11,290
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
tuerca cu 1 1000 $ 1,000

Total A $ 1,000
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Taladro
percutor
inalámbrico cu 0.005 $ 259,990 $ 1,300

Total B $ 1,300
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 25,689 $ 3,232
2 ayudante m3/dia 1 $ - $0
3 ayudante m3/dia 1 $ - $0
4 $0
5 $ 3,232
SUBTOTAL $ 6,463
LEYES SOCIALES 39% $ 2,527

Total C $ 8,990
Precio unitario C

TOTAL $ 11,290
ANALISIS DE PRECIO UNITARIO

PARTIDA: Pruebas de CANTIDAD


Carga y Certificación
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total B $0
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total C $0
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Retiro de Excedentes a Botadero Unidad cu


Item 2.1.9.1 Precio unitario $ 18,195
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Hormigón (hormigones,kg 2.093

Total A $0
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3hora 1 12,600 $ 12,600

Total B $ 12,600
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal m3/dia 1 $ 15,987 $ 2,011
2 Jornal m3/dia 1 $ 15,987 $ 2,011
3 $0
4 $0
5
SUBTOTAL $ 4,022
LEYES SOCIALES 39% $ 1,572

Total C $ 5,595
Precio unitario C
TOTAL $ 18,195
ANALISIS DE PRECIO UNITARIO

PARTIDA: Certificado y Recibos CANTIDAD


del Botadero
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total A
Precio unitario A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total B
Precio unitario B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Total C
Precio unitario C

TOTAL UNITARIO (A+B+C)


TOTAL
ANALISIS DE PRECIO UNITARIO

Partida Emplantillado 7 cms. H 5 Unidad m3


Item 2.2.1 Precio unitario $ 36,508
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 33,311 $ 33,311
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
6 $0
7 $0
8 $0
Total B $ 34,911

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 $ 26,600 $ 484
2 Ayudante 1 m3 0.0182 $ 18,288 $ 333
3 Ayudante 2 m3 0.0182 $ 18,288 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES $ 0 448.0
Total C $ 1,597

TOTAL UNITARIO (A+B+C) $ 36,508


ANALISIS DE PRECIO UNITARIO

Partida Enfierradura A 63 Unidad KG


Item 2.2.2 Precio unitario $ 1,682
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Fierro de construccion kg 1.000 700 $ 700
2 14/10 kg Alambre negro recocido ml 0.200 53 $ 11
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 711

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 4,990 $ 25
3 Disco de corte uni 0.2 1,070 $ 214
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 287

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0053 28500 $ 150
2 Enfierrador 2 KG 0.0053 28500 $ 150
3 Ayudante 1 KG 0.0053 18287.5 $ 96
4 Ayudante 2 0.0053 18287.5 $ 96
5 $0
SUBTOTAL $ 493
LEYES SOCIALES 39% 192.1
Total C $ 685

TOTAL UNITARIO (A+B+C) $ 1,682


ANALISIS DE PRECIO UNITARIO

Partida Moldajes Unidad M2


Item 2.2.4 Precio unitario $ 3,900
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Moldajes metalicos para fundacion m2 1.000 2750 $ 2,750
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,750

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 nivel de mano m2 0.005 $ 9,990 $ 50
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 50

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0111 28500 $ 317
2 Ayudante 1 KG 0.0111 21375 $ 238
3 Ayudante 2 KG 0.0111 21375 $ 238
4 $0
5 $0
SUBTOTAL $ 792
LEYES SOCIALES 39% 308.8
Total C $ 1,100

TOTAL UNITARIO (A+B+C) $ 3,900


ANALISIS DE PRECIO UNITARIO

Partida Hormigón H 35 Unidad m3


Item 2.2.5 Precio unitario $ 58,397
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 $0
8 $0
Total B $ 56,800

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597

TOTAL UNITARIO (A+B+C) $ 58,397


ANALISIS DE PRECIO UNITARIO

Partida Estabilizado Compactado entre Losa Fundación y Radier Unidad m3


Item 2.3.1 Precio unitario $ 16,437
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Estabilizado m3 1 $ 10,701 $ 10,701
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 10,701

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
PLACA COMPACTADORA 5,5HP - 95 KG MOTOR
1 m3 0.005 $ 999,990 $ 5,000
HONDA GX160 Y TANQUE DE AGUA
2 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
3 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
4 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
5 $0
6 $0
7 $0
8 $0
Total B $ 5,274

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante 1 m3 0.0091 $ 18,288 $ 166
2 Ayudante 2 m3 0.0091 $ 18,288 $ 166
3 $0
4 $0
5 $0
SUBTOTAL $ 333
LEYES SOCIALES $ 0 129.7
Total C $ 462

TOTAL UNITARIO (A+B+C) $ 16,437


ANALISIS DE PRECIO UNITARIO

Partida Polietileno 0.2 mm. Unidad M2


Item 2.3.2 Precio unitario $ 951
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Polietileno 0.2 mm. m2 1.000 700 $ 700
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 700

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Cuchillo cartonero rojo uni 0.005 $ 8,990 $ 45
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 45

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0021 28500 $ 59
2 Ayudante 1 KG 0.0021 21375 $ 45
3 Ayudante 2 KG 0.0021 21375 $ 45
4 $0
5 $0
SUBTOTAL $ 148
LEYES SOCIALES 39% 57.9
Total C $ 206

TOTAL UNITARIO (A+B+C) $ 951


ANALISIS DE PRECIO UNITARIO

Partida Radier Afinado 10 cms. H 25 Unidad m3


Item 2.3.3 Precio unitario $ 54,927
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 47,000 $ 47,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
8 $0
Total B $ 53,330

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597

TOTAL UNITARIO (A+B+C) $ 54,927


ANALISIS DE PRECIO UNITARIO

Partida Malla de Acero Acma C-188 Unidad KG


Item 2.3.4 Precio unitario $ 2,022
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Malla de Acero Acma C-188 kg 1.000 $ 641 $ 641
2 14/10 kg Alambre negro recocido ml 0.200 $ 53 $ 11
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 651

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 $ 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 $ 4,990 $ 25
3 Disco de corte uni 0.2 $ 1,070 $ 214
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 287

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0083 $ 28,500 $ 238
2 Enfierrador 2 KG 0.0083 $ 28,500 $ 238
3 Ayudante 1 KG 0.0083 $ 18,288 $ 152
4 Ayudante 2 0.0083 $ 18,288 $ 152
5 $0
SUBTOTAL $ 780
LEYES SOCIALES $ 0 304.1
Total C $ 1,084

TOTAL UNITARIO (A+B+C) $ 2,022


ANALISIS DE PRECIO UNITARIO

Partida Hormigón de Muros Unidad m3


Item 2.4.1.1 Precio unitario $ 58,397
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 $0
8 $0
Total B $ 56,800

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597

TOTAL UNITARIO (A+B+C) $ 58,397


ANALISIS DE PRECIO UNITARIO

Partida Hormigón de Losas Unidad m3


Item 2.4.1.3 Precio unitario $ 59,927
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
8 $0
Total B $ 58,330

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597

TOTAL UNITARIO (A+B+C) $ 59,927


ANALISIS DE PRECIO UNITARIO

Partida Nivelación de Losas de Hormigón Unidad m2


Item 2.4.2 Precio unitario $ 3,114
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $0

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
2 Regla De Aluminio Reforzada De 1-1 / 2 Pulgadas uni 0.005 $ 141,262 $ 706
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,236

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0100 26600 $ 266
2 Ayudante 1 m3 0.0100 18287.5 $ 183
3 Ayudante 2 m3 0.0100 18287.5 $ 183
4 $0
5 $0
SUBTOTAL $ 632
LEYES SOCIALES 39% 246.4
Total C $ 878

TOTAL UNITARIO (A+B+C) $ 3,114


ANALISIS DE PRECIO UNITARIO

Partida Moldajes de Acero Peri Sistema Vario Muros Unidad M2


Item 2.4.1.1 Precio unitario $ 16,180
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Moldajes de Acero Peri Sistema Vario Muros m2 1.000 $ 14,780 $ 14,780
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 14,780

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion Pluma uni 0.02 $ 25,000 $ 500
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 500

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0091 $ 28,500 $ 259
2 Ayudante 1 KG 0.0091 $ 21,375 $ 194
3 Ayudante 2 KG 0.0091 $ 21,375 $ 194
4 $0
5 $0
SUBTOTAL $ 648
LEYES SOCIALES $ 0 252.6
Total C $ 900

TOTAL UNITARIO (A+B+C) $ 16,180


ANALISIS DE PRECIO UNITARIO

Partida Moldajes de Acero Peri Sistema Vario Losas Unidad M2


Item 2.4.1.3 Precio unitario $ 5,600
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Moldajes de Acero Peri Sistema Vario Losas m2 1.000 $ 4,200 $ 4,200
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 4,200

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion Pluma uni 0.02 $ 25,000 $ 500
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 500

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0091 $ 28,500 $ 259
2 Ayudante 1 KG 0.0091 $ 21,375 $ 194
3 Ayudante 2 KG 0.0091 $ 21,375 $ 194
4 $0
5 $0
SUBTOTAL $ 648
LEYES SOCIALES $ 0 252.6
Total C $ 900

TOTAL UNITARIO (A+B+C) $ 5,600


ANALISIS DE PRECIO UNITARIO

Partida Desmoldante (incoloro) Unidad M2


Item 2.4.6 Precio unitario $ 1,393
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Desmoldante (incoloro) m2 1.000 $ 24 $ 24
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 24

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Brocha 3/8"x3" $ 1 0.005 $ 1,990 $ 30
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 30

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0135 $ 28,500 $ 385
2 Ayudante 1 KG 0.0135 $ 21,375 $ 289
3 Ayudante 2 KG 0.0135 $ 21,375 $ 289
4 $0
5 $0
SUBTOTAL $ 963
LEYES SOCIALES $ 0 375.5
Total C $ 1,338

TOTAL UNITARIO (A+B+C) $ 1,393


ANALISIS DE PRECIO UNITARIO

Partida Acero Calidad A 63 Muros Unidad KG


Item 2.4.8.2 Precio unitario $ 2,182
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Fierro de construccion kg 1.000 $ 700 $ 700
2 14/10 kg Alambre negro recocido ml 0.200 $ 53 $ 11
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 711

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 $ 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 $ 4,990 $ 25
3 Disco de corte uni 0.2 $ 1,070 $ 214
4 Camion Pluma uni 0.02 $ 25,000 $ 500
5 $0
6 $0
7 $0
8 $0
Total B $ 787

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0053 $ 28,500 $ 150
2 Enfierrador 2 KG 0.0053 $ 28,500 $ 150
3 Ayudante 1 KG 0.0053 $ 18,288 $ 96
4 Ayudante 2 KG 0.0053 $ 18,288 $ 96
5 $0
SUBTOTAL $ 493
LEYES SOCIALES $ 0 192.1
Total C $ 685

TOTAL UNITARIO (A+B+C) $ 2,182


ANALISIS DE PRECIO UNITARIO

Partida ENFIERRADURA DE LOSAS Unidad KG


Item Precio unitario $ 15,517
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION CANT UNI UNITARIO TOTAL
($) ($)

1 enfirradura 12D de 6mm 0.1 kg $ 4,000 $ 400


2 alambre recocido 0.2 kg $ 3,400 $ 680
3 enfirradura 10D de 6mm 0.4 kg $ 2,690 $ 995
4 enfirradura 8D 6m 0.1 kg $ 1,790 $ 179
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,254

B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 alicate 0.01 un $ 4,600 $ 23
2 machina 0.01 un $ 20,000 $ 100
3 transporte 0.01 un $ 140,000 $ 700
4 huincha 0.01 un $ 2,400 $ 12
5 grua torre 0.05 dia $ 232,608 $ 11,630
6 $0
7 $0
8 $0
Total B $ 12,465

C MANO DE OBRA
ITEM DESIGNACION CANT UNID PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 enfierrador 0.01 m3/dia $ 24,648 $ 246
2 ayudante 0.01 m3/dia $ 16,344 $ 163
3 ayudante 0.01 m3/dia $ 16,345 $ 163
4 $0
5 $0
SUBTOTAL $ 573
LEYES SOCIALES 39% 223.61222
Total C $ 797

TOTAL UNITARIO (A+B+C) $ 15,517


ANALISIS DE PRECIO UNITARIO

Partida ESTRUCTURA ACERO PUENTE DE CONEXIÓN


Item
A MATERIALES
ITEM
DESIGNACION UNID.

1 Perfil de Acero cuadrado 200mm x 200mm x 3mm x6m 0.2500


2 Perfil de Acero Cuadrado 150mm x 3mm x 6m 0.2500
3 Perfil de Acero Cuadrado 100mm x 3mm x 6m 0.2500
4 Perfil de Acero Canal 100mm x 50mm x 3mm x 6m 0.2500
5
6
7
8
9
10

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID.

1 caja de dados 0.005


2 pistola impacto 0.005
3 plana 0.005
4 valde concretero 0.005
5 camion pluma 1.000
6
7
8

C MANO DE OBRA
ITEM DESIGNACION CANT

1 maestro primera 0.0167


2 soldador 0.0167
3 ayudante 0.0167
4 ayudante 0.0167
5 ayudante 0.0167
SUBTOTAL
LEYES SOCIALES

TOTAL UNITARIO (A+B+C)


O UNITARIO

CONEXIÓN Unidad M2
Precio unitario $ 134,121

PRECIO PRECIO
CANTIDAD UNITARIO TOTAL
($) ($)

mt $ 94,554 $ 23,639
mt $ 94,554 $ 23,639
mt $ 61,975 $ 15,494
mt $ 30,188 $ 7,547
$0
$0
$0
$0
$0
$0
Total A $ 70,318

CANTIDAD PRECIO PRECIO


UNITARIO TOTAL
($) ($)

un $ 79,500 $ 398
un $ 96,000 $ 480
un $ 5,600 $ 28
un $ 3,290 $ 16
hora/dia $ 60,000 $ 60,000
$0
$0
$0
Total B $ 60,922

UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)

m3/dia $24,648.00 $ 411


m3/dia $30,310.00 $ 505
m3/dia $ 23,138 $ 386
m3/dia $ 23,138 $ 386
m3/dia $ 23,138 $ 386
$ 2,073
39% 808.4206
Total C $ 2,881

TOTAL UNITARIO (A+B+C) $ 134,121


ANALISIS DE PRECIO UNITARIO

Partida AISLACION TERMICA Unidad M2


Item Precio unitario $ 5,554
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION CANT UN UNITARIO TOTAL
($) ($)
1 aisslan glass r141 e 50mm 0.0347 M2 $ 58,317 $ 2,025
2 corchete 0.0600 caja $ 4,620 $ 277
3 cuchillas cartonero 0.0500 caja $ 2,690 $ 135
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,437

B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Huincha para medir 8 m fibra de 0.0050 Ml $ 11,890 $ 59
2 LAPIZ CARPINTERO 0.0050 M2 $ 290 $1
3 Cuchillo cartonero rojo 0.0050 Ml $ 8,990 $ 45
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 106

C MANO DE OBRA
ITEM DESIGNACION CANT UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Carpintero 0.0556 M2 $ 15,000 $ 833
2 Ayudante 1 0.0556 M2 $ 12,000 $ 667
3 Ayudante 2 0.0556 M2 $ 12,000 $ 667
4 $0
5 $0
SUBTOTAL $ 2,167
LEYES SOCIALES 39% 845
Total C $ 3,012

TOTAL UNITARIO (A+B+C) $ 5,554


ANALISIS DE PRECIO UNITARIO

Partida AISLAN GLASS PUENTE CONEXIÓN Unidad M2


Item Precio unitario $ 5,804
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION CANT UNI UNITARIO TOTAL
($) ($)
1 aisslan glass r141 e 50mm 0.0347 M2 $ 58,317 $ 2,025
2 corchete 0.0600 caja $ 4,620 $ 277
3 cuchillas cartonero 0.0500 caja $ 2,690 $ 135
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,437

B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Huincha para medir 8 m fibra de vid 0.0050 Ml $ 11,890 $ 59
2 LAPIZ CARPINTERO 0.0050 M2 $ 290 $1
3 Cuchillo cartonero rojo 0.0050 Ml $ 8,990 $ 45
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 106

C MANO DE OBRA
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal 0.0556 m3/dia $ 14,079 $ 782
2 jornal 0.0556 m3/dia $ 14,079 $ 782
3 jornal 0.0556 m3/dia $ 14,079 $ 782
4 $0
5 $0
SUBTOTAL $ 2,346
LEYES SOCIALES 39% 915.130666667
Total C $ 3,262

TOTAL UNITARIO (A+B+C) $ 5,804


ANALISIS DE PRECIO UNITARIO

Partida CUBIERTA VERDE Unidad M2


Item Precio unitario $ 25,516
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Palmeta pasto pr 1 m2 aprox.mt2 1.0 3,140 $ 3,140
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 3,140

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carretilla UN 0 $ 27,000 135
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 135

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante 0.4444 M2 $ 12,000 $ 5,333
2 Ayudante 0.4444 M2 $ 12,000 $ 5,333
3 Ayudante 0.4444 M2 $ 12,001 $ 5,334
4 $0
5 $0
SUBTOTAL $ 16,000
LEYES SOCIALES 39% 6240.17333333
Total C $ 22,241

TOTAL UNITARIO (A+B+C) $ 25,516


ANALISIS DE PRECIO UNITARIO

Partida MEMBRANA PVC SANMAFIL F610-12 FELT Unidad M2


Item Precio unitario $ 31,007
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 1 X 10 MT MEMBRANA PVC C/U 0.12 52,933 $ 6,352
2 TINETA 18 LT. IGOL PL C/U 0.05 70,748 $ 3,537
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 9,889

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha UNID. 0 $ 2,400 $ 160
2 remachadora UNID. 0.0050 $ 16,960 $ 85
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 245

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350
2 Ayudante DIA 0.4444 $ 12,000 $ 5,333
3 Ayudante DIA 0.4444 $ 12,000 $ 5,333
4 $0
5 $0
SUBTOTAL $ 15,017
LEYES SOCIALES 39% 5856.5
Total C $ 20,873

TOTAL UNITARIO (A+B+C) $ 31,007


ANALISIS DE PRECIO UNITARIO ANALISIS D

Partida MEMBRANA GEOTEXTIL DE 500 KG/M2 Unidad M2 Partida


Item Precio unitario $0 Item
A MATERIALES A
ITEM PRECIO PRECIO ITEM
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 MENMBRANA GEOTEXTIL M2 0.1 10,990 $ 1,099 1
2 $0 2
3 $0 3
4 $0 4
5 $0 5
6 $0 6
7 $0 7
8 $0 8
9 $0 9
10 $0 10
Total A $ 1,099

B MAQUINAS Y EQUIPO B
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO ITEM
UNITARIO TOTAL
($) ($)
1 huincha UNID. 0 $ 2,400 $ 160 1
2 remachadora UNID. 0.0050 $ 16,960 $ 85 2
3 $0 3
4 $0 4
5 $0 5
6 $0 6
7 $0 7
8 $0 8
Total B $ 245

C MANO DE OBRA C
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO ITEM
UNITARIO TOTAL
($) ($)
1 MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350 1
2 Ayudante DIA 0.4444 $ 12,000 $ 5,333 2
3 Ayudante DIA 0.4444 $ 12,000 $ 5,333 3
4 $0 4
5 $0 5
SUBTOTAL $ 15,017
LEYES SOCIALES 39% 5856.5
Total C $ 20,873
ANALISIS DE PRECIO UNITARIO

PLANCHAS PV4 DE 0,5 MM ZINCALUM Unidad M2


Precio unitario $0
MATERIALES
PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
PV4 05 ZINCALUN 6000 MMMT2 1 32,900 $ 32,900

Pernos autor Unidad 8.0000 $ 78 $ 626


$0
$0
$0
$0
$0
$0
$0
$0
Total A $ 33,526

MAQUINAS Y EQUIPO
DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)

Taladro perc M2 0.0050 $ 259,990 #REF!

Dado impactom2 0.0050 $ 7,490 #REF!


Huincha paraMl 0.0050 $ 11,890 #REF!
LAPIZ CARPM2 0.0050 $ 290 #REF!
Tizador 30 mMl 0.0050 $ 7,490 #REF!
Tijera para coMl 1.0050 $ 10,690 #REF!
$0
$0
Total B #REF!

MANO DE OBRA
DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350
MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350

Ayudante DIA 0.4444 $ 12,000 $ 5,333

Ayudante DIA 0.4444 $ 12,001 $ 5,334


$0
SUBTOTAL $ 19,367
LEYES SOCIALES 39% 7553.17333333
Total C $ 26,920
ANALISIS DE PRECIO UNITARIO

Partida Tabiques Yeso/Cartón 15m + 10 m ambas caras Unidad


Item Precio unitario
A MATERIALES
ITEM PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO
($)

1 Placas Yeso cartón RF 15 mm M2 1 $ 5,378


2 Tornillo montante auto perforantes 2 1/2" UNID. 23.0000 $ 45
3 Esquinero metálico tipo L de 40x40 mm
4
5
6
7
8
9
10
Total A

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Taladro percutor inalámbrico 13mm 18V 0.0050 M2 $ 259,990
2 Huincha para medir 8 m fibra de vidrio rojo 0.0050 Ml $ 11,890
3 LAPIZ CARPINTERO 0.0050 M2 $ 290
4 Tizador 30 m 0.0050 Ml $ 7,490
5 Cuchillo cartonero rojo 0.0050 Ml $ 8,990
6
7
8
Total B

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 carpintero DIA 0.0455 $18,986.00
2 Ayudante DIA 0.4444 $ 12,000
3 Ayudante DIA 0.4444 $ 12,000
4
5
SUBTOTAL
LEYES SOCIALES 39%
Total C
M2 Partida AISLAN GLASS Unidad M2
$0 Item Precio unitario $ 5,804
A MATERIALES
PRECIO ITEM PRECIO PRECIO
TOTAL DESIGNACION CANT UNI UNITARIO TOTAL
($) ($) ($)

$ 5,378 1 aisslan glas 0.0347 M2 $ 58,317 $ 2,025


$ 1,035 2 corchete 0.0600 caja $ 4,620 $ 277
$0 3 cuchillas cart 0.0500 caja $ 2,690 $ 135
$0 4 $0
$0 5 $0
$0 6 $0
$0 7 $0
$0 8 $0
$0 9 $0
$0 10 $0
$ 6,413 Total A $ 2,437

B MAQUINAS Y EQUIPO
PRECIO ITEM DESIGNACION CANT UNI PRECIO PRECIO
TOTAL UNITARIO TOTAL
($) ($) ($)
$ 1,300 1 Huincha para 0.0050 Ml $ 11,890 $ 59
$ 59 2 LAPIZ CARP 0.0050 M2 $ 290 $1
$1 3 Cuchillo carto 0.0050 Ml $ 8,990 $ 45
$ 37 4 $0
$ 45 5 $0
$0 6 $0
$0 7 $0
$0 8 $0
$ 1,443 Total B $ 106

C MANO DE OBRA
PRECIO ITEM DESIGNACION CANT UNI PRECIO PRECIO
TOTAL UNITARIO TOTAL
($) ($) ($)

$ 863 1 jornal 0.0556 m3/dia $ 14,079 $ 782


$ 5,333 2 jornal 0.0556 m3/dia $ 14,079 $ 782
$ 5,333 3 jornal 0.0556 m3/dia $ 14,079 $ 782
$0 4 $0
$0 5 $0
$ 11,530 SUBTOTAL $ 2,346
4496.57 LEYES SOCIALES 39% 915.130666667
$ 16,026 Total C $ 3,262

TOTAL UNITARIO (A+B+C) $ 5,804


ANALISIS DE PRECIO UNITARIO

Partida yeso carton 10mm Unidad M2


Item 4.3.1 Precio unitario $ 5,978
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 plancha yeso carton 10mm m2 0.312 4750 $ 1,482
2 tornillo volc.1000un uni 0.014 1929 $ 27
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 1,509

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 cuchillo caronero metalico uni 0.015 3890 $ 58
3 huincha de medir 8m uni 0.005 11890 $ 59
4 lapiz carpintero uni 0.01 290 $3
5 $0
6 $0
7 $0
8 $0
Total B $ 1,061

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 22446 $ 1,683
2 ayundante dia 0.02 19204 $ 384
3 ayundante dia 0.02 19204 $ 384
4 $0
5 $0
SUBTOTAL $ 2,452
LEYES SOCIALES 39% 956.13
Total C $ 3,408

TOTAL UNITARIO (A+B+C) $ 5,978


ANALISIS DE PRECIO UNITARIO

Partida yeso carton hr 10mm Unidad M2


Item 4.3.1.1 Precio unitario $ 7,535
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 plancha yeso carton hr 10mm uni 0.312 7750 $ 2,418
2 tornillo volc.1000un uni 0.014 1929 $ 27
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,445

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 cuchillo caronero metalico uni 0.015 3890 $ 58
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 999

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 29000 $ 2,175
2 ayundante 1 dia 0.02 19204 $ 384
3 ayundante 2 dia 0.02 19204 $ 384
4 $0
5 $0
SUBTOTAL $ 2,943
LEYES SOCIALES 39% 1147.83
Total C $ 4,091

TOTAL UNITARIO (A+B+C) $ 7,535


ANALISIS DE PRECIO UNITARIO

Partida porcelanato cementi gris 45x90 Unidad M2


Item 4.4.1 Precio unitario $ 11,756
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 adhesivo porcelanato en polvo doble 25kg kg 1 8220 $ 8,220
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 8,220

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha de medir 8m uni 0.005 11890 $ 59
2 llana dentada ultra ligera 28<11 uni 0.05 7490 $ 375
3 espatula acero80mm uni 0.12 2290 $ 275
4 esponja para piso uni 0.008 1990 $ 16
5 mazo de goma uni 0.005 12490 $ 62
6 nivel de mano uni 0.02 3790 $ 76
7 $0
8 $0
Total B $ 863

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 ceramista dia 0.03 25689 $ 771
2 ayudante 1 dia 0.03 19204 $ 576
3 ayudante 2 dia 0.03 19204 $ 576
4 $0
5 $0
SUBTOTAL $ 1,923
LEYES SOCIALES 39% 749.9349
Total C $ 2,673

TOTAL UNITARIO (A+B+C) $ 11,756


770670
ANALISIS DE PRECIO UNITARIO

Partida alfombra rollo boucle office dakota Unidad ml


Item 4.4.2.1 Precio unitario $ 16,969
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 alfombra rollo boucle office m2 1 12250 $ 12,250
2 articoll 125 1galon galon 0.06 20999 $ 1,260
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 13,510

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 cuchillo caronero metalico uni 0.015 3890 $ 58
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 58

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 alfombrero dia 0.045 29000 $ 1,305
2 ayudante dia 0.03 19024 $ 571
3 ayudante dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.11
Total C $ 3,401

TOTAL UNITARIO (A+B+C) $ 16,969


ANALISIS DE PRECIO UNITARIO

Partida junta para muros modelo CPSAL 50x100 Unidad ml


Item 4.5.1 Precio unitario $ 4,436
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 $0
2 cubrejunta cpsal 50x100 $0
3 tornillos 144uni uni 0.04 1,010 $ 35
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 35

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 huincha de medir 8m uni 0.005 11890 $ 59
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 1,000

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.045 29000 $ 1,305
2 ayudnate dia 0.03 19024 $ 571
3 ayudante dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.1116
Total C $ 3,401

TOTAL UNITARIO (A+B+C) $ 4,436


ANALISIS DE PRECIO UNITARIO

Partida Sikaflex 1 plus Unidad ml


Item 4.5.2 Precio unitario $ 7,310
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Sikaflex 1 plus con cordon uni 0.03 9990 $ 300
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 300

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pistola calafatera uni 1 3610 $ 3,610
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 3,610

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.045 29000 $ 1,305
2 ayudnate dia 0.03 19024 $ 571
3 ayudnate dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.1116
Total C $ 3,401

TOTAL UNITARIO (A+B+C) $ 7,310


ANALISIS DE PRECIO UNITARIO

Partida guardapolvos porcelanato 10cm Unidad Ml


Item 4.6.1 Precio unitario $ 5,596
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 porcelanato gris 45/90 uni 2.4 795 $ 1,908
2 adhesivo 25kg saco 0.02 5754 $ 115
3 frague topex 5kg kg 0.05 735 $ 37
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 2,060

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha de medir 8m uni 0.005 11890 $ 59
2 llana dentada ultra ligera 28<11 uni 0.05 7490 $ 375
3 espatula acero80mm uni 0.12 2290 $ 275
4 esponja para piso uni 0.008 1990 $ 16
5 mazo de goma uni 0.005 12490 $ 62
6 nivel de mano uni 0.02 3790 $ 76
7 $0
8 $0
Total B $ 863

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 ceramista dia 0.03 25689 $ 771
2 ayudante dia 0.03 19204 $ 576
3 ayudante dia 0.03 19204 $ 576
4 $0
5 $0
SUBTOTAL $ 1,923
LEYES SOCIALES 39% 749.9349
Total C $ 2,673

TOTAL UNITARIO (A+B+C) $ 5,596


ANALISIS DE PRECIO UNITARIO

Partida Ventanas exteriores Unidad M2


Item 4.7.1.1 Precio unitario $ 101,292
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 perfil tubular 40x20mm ml 3 2135 $ 6,405
2 ventana pvc termopanel m2 1 89765 $ 89,765
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 96,170

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 camion capacho hr 0.2 15200 $ 3,040
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 3,040

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero m2/dia 0.022 29000 $ 644
2 ayudante 1 m2/dia 0.022 19204 $ 427
3 ayudante 2 m2/dia 0.022 19204 $ 427
4 $0
5 $0
SUBTOTAL $ 1,498
LEYES SOCIALES 39% 584.202666667
Total C $ 2,082

TOTAL UNITARIO (A+B+C) $ 101,292


ANALISIS DE PRECIO UNITARIO

Partida Puertas vidriada simple Unidad C/U


Item 4.7.1.2 Precio unitario $ 177,441
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 puerta vidriada simple xelentina uni 1 88239 $ 88,239
2 quicio hidraulico 100kg uni 1 80211 $ 80,211
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 168,450

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano c/u 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700

TOTAL UNITARIO (A+B+C) $ 177,441


ANALISIS DE PRECIO UNITARIO

Partida Puertas vidriadas doble Unidad C/U


Item 4.7.1.3 Precio unitario $ 237,040
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 puerta doble uni 1 198250 $ 198,250
2 tipo dap 240 uni 1 29799 $ 29,799
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 228,049

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano uni 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700
TOTAL UNITARIO (A+B+C) $ 237,040
ANALISIS DE PRECIO UNITARIO

Partida marco rebajado enchapado Unidad ml


Item 4.9.1 Precio unitario $ 7,364
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 marco rebajado enchapado ml 2.5 2350 $ 5,875
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 5,875

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 114 uni 0.005 2350 $ 12
2 taladro percutor electrico uni 0.03 31340 $ 940
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 952

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537

TOTAL UNITARIO (A+B+C) $ 7,364


ANALISIS DE PRECIO UNITARIO

Partida Centro pino finger joint Unidad ML


Item 4.9.2 Precio unitario $ 3,087
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 Centro pino finger joint ml 1 1459 $ 1,459
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 1,459

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 6x1 20uni c/u 0.2 755 $ 151
2 taladro percutor electrico uni 0.03 31340 $ 940
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 1,091

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537

TOTAL UNITARIO (A+B+C) $ 3,087


ANALISIS DE PRECIO UNITARIO

Partida Puerta placa Unidad C/U


Item 4.10.1 Precio unitario $ 24,331
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 puerta placa uni 1 15340 $ 15,340
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 15,340

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano uni 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700

TOTAL UNITARIO (A+B+C) $ 24,331


ANALISIS DE PRECIO UNITARIO

Partida Celosia Puerta Unidad C/U


Item Precio unitario $ 6,898
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 celosia uni 1 6210 $ 6,210
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 6,210

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 6x1 20uni c/u 0.2 755 $ 151
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 151

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537

TOTAL UNITARIO (A+B+C) $ 6,898


ANALISIS DE PRECIO UNITARIO

Partida Oleo sintetico kem Unidad M2


Item 4.17.4 Precio unitario $ 8,922
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 oleo sintetico kem pro 1gl gl 0.2 29590 $ 5,918
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 5,918

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 brocha oleo 3" uni 0.01 5350 $ 54
2 rodillo 15cm uni 0.02 2790 $ 56
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 109

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pintor dia 0.05 22446 $ 1,122
2 ayudante dia 0 19204 $0
3 ayudante dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 2,083
LEYES SOCIALES 39% 812.175
Total C $ 2,895

TOTAL UNITARIO (A+B+C) $ 8,922


ANALISIS DE PRECIO UNITARIO

Partida Esmalte epoxito sipa Unidad M2


Item 4.17.5 Precio unitario $ 5,185
A MATERIALES
ITEM PRECIO PRECIO
DESIGNACION UNID. CANTIDAD UNITARIO TOTAL
($) ($)
1 oleo sintetico kem pro 1gl gl 0.2 18975 $ 3,795
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
9 $0
10 $0
Total A $ 3,795

B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 brocha oleo 3" uni 0.03 5350 $ 161
2 rodillo 15cm uni 0.2 2790 $ 558
3 diluyente 5 litros uni 0.01 9230 $ 92
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 811

C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pintor dia 0.01 22446 $ 224
2 ayudante dia 0.005 19204 $ 96
3 ayudante dia 0.005 19204 $ 96
4 $0
5 $0
SUBTOTAL $ 417
LEYES SOCIALES 39% 162.435
Total C $ 579

TOTAL UNITARIO (A+B+C) $ 5,185


Dias Horas Gratificacion Asigancion
21 9 4.8% 0.88

Trabajador Sueldo base Valor Dia Valor hora % Costo Medio Total
Residente $700,000 $33,333 $3,704 5.8% $1,926
Profesional ayudante $500,000 $23,810 $2,646 4.1% $983
Jefe administrativo $600,000 $28,571 $3,175 5.0% $1,415
Jefe de bodegas $520,000 $24,762 $2,751 4.3% $1,063
Ayudante de bodega $420,000 $20,000 $2,222 3.5% $693
Pañolero $390,000 $18,571 $2,063 3.2% $598
Jefe de obra $500,000 $23,810 $2,646 4.1% $983
Capataz $480,000 $22,857 $2,540 4.0% $905
Topografo $800,000 $38,095 $4,233 6.6% $2,515
Trazador $480,000 $22,857 $2,540 4.0% $905
Prevencionista de riesgo $480,000 $22,857 $2,540 4.0% $905
Maestro primera $600,000 $28,571 $3,175 5.0% $1,415
Carpintero obra Gruesa $450,000 $21,429 $2,381 3.7% $796
Albañil $560,000 $26,667 $2,963 4.6% $1,232
Enfierrador $600,000 $28,571 $3,175 5.0% $1,415
Concretero $560,000 $26,667 $2,963 4.6% $1,232
extructurero $600,000 $28,571 $3,175 5.0% $1,415
Soldador $750,000 $35,714 $3,968 6.2% $2,211
Ceramista $515,000 $24,524 $2,725 4.3% $1,042
Yesero $456,000 $21,714 $2,413 3.8% $817
Pintor $450,000 $21,429 $2,381 3.7% $796
Ayudante $385,000 $18,333 $2,037 3.2% $583
Jornal $320,500 $15,262 $1,696 2.6% $404
$576,976 64108.4656 1.0 $26,249

Valor dia $26,249


Valor hora $2,917

Ingreso Promedio anual


Itema Horas Cantidad Total
Diaria 9 5 45
Semanales 45 4 180
Anual 180 12 2160
Feriados 15 9 135

Horas efectivamente trabajadas Total horas


Anual 180 12 2160
Feriados 15 9 135
2025

Ingreso Promedio anual


Itema Horas Valor hora Total
Diaria 2025 $2,917 $ 5,905,972

se considenran dias por año trabajado 15

Dias meses Total dias por mes


15 12 1.25%

Porcentaje de 6.7%

Gratificaion 15
Locomocion
0.03

Gratificacion Gasto total trabajdor mes Valor dia Valor hora


$33,250 $733,250 $34,917 $3,880
$23,750 $523,750 $24,940 $2,771
$28,500 $628,500 $29,929 $3,325
$24,700 $544,700 $25,938 $2,882
$19,950 $439,950 $20,950 $2,328
$18,525 $408,525 $19,454 $2,162
$23,750 $523,750 $24,940 $2,771
$22,800 $502,800 $23,943 $2,660
$38,000 $838,000 $39,905 $4,434
$22,800 $502,800 $23,943 $2,660
$22,800 $502,800 $23,943 $2,660
$28,500 $628,500 $29,929 $3,325
$21,375 $471,375 $22,446 $2,494
$26,600 $586,600 $27,933 $3,104
$28,500 $628,500 $29,929 $3,325
$26,600 $586,600 $27,933 $3,104
$28,500 $628,500 $29,929 $3,325
$35,625 $785,625 $37,411 $4,157
$24,463 $539,463 $25,689 $2,854
$21,660 $477,660 $22,746 $2,527
$21,375 $471,375 $22,446 $2,494
$18,288 $403,288 $19,204 $2,134
$15,224 $335,724 $15,987 $1,776

También podría gustarte