21 9 4.8% 0.88
Trabajador Sueldo base Valor Dia Valor hora % Costo Medio Total
Residente $700,000 $33,333 $3,704 5.8% $1,926
Profesional ayudante $500,000 $23,810 $2,646 4.1% $983
Jefe administrativo $600,000 $28,571 $3,175 5.0% $1,415
Jefe de bodegas $520,000 $24,762 $2,751 4.3% $1,063
Ayudante de bodega $420,000 $20,000 $2,222 3.5% $693
Pañolero $390,000 $18,571 $2,063 3.2% $598
Jefe de obra $500,000 $23,810 $2,646 4.1% $983
Capataz $480,000 $22,857 $2,540 4.0% $905
Topografo $800,000 $38,095 $4,233 6.6% $2,515
Trazador $480,000 $22,857 $2,540 4.0% $905
Prevencionista de riesgo $480,000 $22,857 $2,540 4.0% $905
Maestro primera $600,000 $28,571 $3,175 5.0% $1,415
Carpintero obra Gruesa $450,000 $21,429 $2,381 3.7% $796
Albañil $560,000 $26,667 $2,963 4.6% $1,232
Enfierrador $600,000 $28,571 $3,175 5.0% $1,415
Concretero $560,000 $26,667 $2,963 4.6% $1,232
extructurero $600,000 $28,571 $3,175 5.0% $1,415
Soldador $750,000 $35,714 $3,968 6.2% $2,211
Ceramista $515,000 $24,524 $2,725 4.3% $1,042
Yesero $456,000 $21,714 $2,413 3.8% $817
Pintor $450,000 $21,429 $2,381 3.7% $796
Ayudante $385,000 $18,333 $2,037 3.2% $583
Jornal $320,500 $15,262 $1,696 2.6% $404
$576,976 64108.4656 1.0 $26,249
Porcentaje de 6.7%
Gratificaion 15
Locomocion
0.03
AFP 12%
Salud
7%
Desahicio
Indemnizacion 4%
Feriado anual 6.7%
2.-
2.1
2.1.1
2.1.2
2.1.3
2.1.3.1
2.1.3.2
2.1.4
2.1.5
2.1.5.1
2.1.5.2
2.1.6
2.1.7
2.1.7.1
2.1.7.2
2.1.7.3
2.1.7.4
2.1.7.5
2.1.7.6
2.1.7.7
2.1.7.8
2.1.7.9
2.1.7.10
2.1.7.11
2.1.7.12
2.1.7.13
2.1.7.14
2.1.7.15
2.1.9
2.1.9.1
2.1.9.2
2.2
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.3
2.3.1
2.3.2
2.3.3
2.3.4
2.4
2.4.1
2.4.1.1
2.4.1.3
2.4.2
2.4.4
2.4.4.1
2.4.4.3
2.4.6
2.4.8
2.4.8.2
2.4.8.3
2.5
2.5.2
2.5.5
2.7
2.7.1
2.7.2
2.8
2.8.1
2.8.2
2.12
2.12.1
2.12.2
2.14
2.14.1
2.14.2
2.14.3
2.14.6
4.-
4.2
4.2.1
4.2.1.1
4.3
4.3.1
4.3.1.1
4.4
4.4.1
4.4.1.1
4.4.2
4.4.2.1
4.5
4.5.1
4.5.2
4.6
4.6.1
4.7
4.7.1.1
4.7.1.2
4.7.1.3
4.9
4.9.1
4.9.2
4.10
4.10.1
4.10.3
4.17
4.17.4
4.17.5
ITEMIZADO GENERAL PROPUESTA
NOMBRE CONSTRUCTORA
R.U.T. CONSTRUCTORA
ITEMIZADO GENERAL PRESUPUESTARIO
EDIFICIO DUOC UC SEDE SAN ANDRES II - CONCEPCION
PARTIDA
GENERALIDADES
Descripción General del Proyecto
Archivo de Obra
Permiso de Edificación-Permiso de Grúa-Instalaciones de Faenas-Otros
Libro de Obras
Certificados de Ensayos de Materiales
Certificaciones para Obtención de Recepción Municipal
Ensayes de Hormigón y otros necesarios según B.A.G.
Otras certificaciones según B.A.G.
Planos
Especificaciones Técnicas y Consultas
Herramientas y Varios
Aseo y Orden da la Obra
Otros a Juicio del Proponente
Boletas de Garantía seg.B.A.G.
Pólizas de Seguro según B.A.G.
Instalacion de Faenas
Cierros Perimetrales de la Obra
Cierros al Interior del Edificio A
Protección de Vegetación Existente
Recintos Varios
Oficina ITO
Oficina Administrador
Oficina de Planos y Sala de Reuniones
Comedores, Baños, etc
Otros a Juicio del Proponente
Instalaciones Provisorias
Carteles
Trazados y Niveles
Verificación de Cotas, Niveles y Trazados
Nivel del Edificio
Trazado de la Obra
Cerco de Trazado
Mantención de Trazado durante el Desarrollo de la Obra
Recepción del Trazado y Niveles
Sub Total Generalidades
OBRA GRUESA
EXCAVACIONES
Escarpe del Terreno
Depresión de Napa
Saneamiento Provisorio de Aguas Lluvias
Excavaciones
Shotcret de Canaleta
Excavaciones a Máquina
Excavaciones a Mano
Excavaciones a Mano Para Talud
Excavaciones a Mano Para Fundaciones
Demolición Muro H.A. Existente
Estabilidad de Taludes con Sistema "Soil Nailing" (Proyecto Estratos)
Recepción de Taludes previo hormigón Proyectado
Lechada de cemento de protección previo Shotcret
Barbacanas de Drenaje
Anclajes de Acero de Prueba
Malla Hexagonal de Alambre
Anclaje de Malla
Zanja de Anclaje
Hormigón Proyectado (Shotcret) Permanente
Hormigón Proyectado (Shorcret) Temporal
Vaina Plastica
Instalación de Barras de Anclaje
Lechada de cemento de Inyección
Placa de Acero de 20 x 20 cm e= 10 mm Galvanizada
Aplicación de Torque de Apriete
Pruebas de Carga y Certificación
Retiro de Excedentes a Botadero
Retiro de Excedentes a Botadero
Certificado y Recibos del Botadero
FUNDACIONES
Emplantillado 7 cms. H 5
Enfierradura A 63
Enfierradura A 44
Moldajes
Hormigón H 35
Bases de Pavimento y Relleno entre Fundaciones
Estabilizado Compactado entre Losa Fundación y Radier
Polietileno 0.2 mm.
Radier Afinado 10 cms. H 25
Malla de Acero Acma C-188
Estructuras Principales
Hormigón Armado Muros, Vigas, Losas, Pilares, Cadenas H 35
Hormigón de Muros
Hormigón de Losas
Nivelación de Losas de Hormigón
Moldajes de Acero Peri Sistema Vario
Moldajes de Acero Peri Sistema Vario Muros
Moldajes de Acero Peri Sistema Vario Losas
Desmoldante (incoloro)
Acero Calidad A 63
Acero Calidad A 63 Muros
Acero Calidad A 63 Losas
Estructuras de Acero
Estructuras Acero A - 42 -27 Es Galvanizado en Caliente Puente Conexión
Estructuras Acero A - 42 -27 Es Galvanizado en Caliente Torre Ascensores
Tabiquería Metalcon
Tabiquería Metalcon e= 0,85 mm.
Refuerzos en Tabiques
Techumbre
Estructura Metalcón
Terciado Estructural 15 mm.
Aislación Térmica
Aislación Térmica Poliestireno Extruido 50 mm. Losa 6º Piso
Aislán Glass R141 e=50 mm.
Cubierta
Cubierta Verde
Membrana PVC Sanrnafil F610-12 Felt
Membrana Geotextil de 500 KG/m²
Planchas PV4 de 0.5 mm Zincalum
Sub Total Obra Gruesa
TERMINACIONES
Revestimientos Interiores
Tabiques Yeso/Cartón 15m + 10 m ambas caras
Aislán Glass 60 mm.
Cielos
Yeso Cartón 10 mm.
Yeso Cartón HR 10 mm.
Pavimentos
Porcelanatos
Porcelanato Cementi Gris 45/90 MK
Alfombras
Boucle Office Color Dakota 4086 C Etersol
Juntas de Dilatación
Junta para Muros Modelo CPSAL 50 x 100
Sikaflex 1 Plus con Cordón de Respaldo
Guardapolvos
Guardapolvos Porcelanatos H 10 cms
Aluminios y Cristales
Ventanas Exteriores
Puertas Vidriadas Simples
Puertas Vidriadas Dobles
Marcos, Centros, Pilastras y Endolados
Marcos Rebajados Trupán Enchapado
Centros Pino Finger Joint
Puertas
Puertas de Placa Llena
Celosías para Puertas
Pinturas y Barnices
Oleo Sintético Brillante Kem Pro
Esmalte Epoxico Sipa
Sub Total Terminaciones
TOTAL COSTO DIRECTO
GASTOS GENERALES %
UTILIDADES %
TOTAL NETO
19% IVA
TOTAL PRESUPUESTO
Firma Contratista
STARIO
- CONCEPCION
GL 1 1.0 1.0
GL 1 1,110 1,109.67
GL 40 0.31 12.21
0.00
GL 1 0.97 0.97
GL 0.00
GL 0.00
GL 50 0.54 27.02
GL 1 0.16 0.16
GL 1 5.61 5.61
GL 1 1.54 1.54
GL 1 0.00 0.00
GL 0.00 0.00
GL 0.00 0.00
0.00 0.00
ML 240 0.46 109.60
ML 88 0.25 22.23
GL 1 0.00 0.00
0.00 0.00
GL 1 10.55 10.55
GL 1 5.89 5.89
GL 1 3.31 3.31
GL 1 23.39 23.39
GL 1 0.00 0.00
GL 1 36.82 36.82
GL 2 2.49 4.98
GL 1 0.74 0.74
GL 1 1.11 1.11
GL 1 1.19 1.19
GL 1 8.31 8.31
GL 1 0.18 0.18
GL 1 0.18 0.18
1,214.66 1,386.67
M3 16 0.33 5.30
ML 263 1.08 283.51
M3 20,500 0.90 18,436.67
GL 1 0.18 0.18
M2 2,160 1.66 3,578.76
CU 973 0.90 873.94
CU 675 12.58 8,499.71
M2 2,160 0.87 1,878.92
CU 547 1.25 683.24
ML 170 2.36 401.06
M2 2,160 1.62 3,507.39
M2 2,160 1.68 3,625.23
ML 675 0.88 596.59
CU 675 7.87 5,312.30
M3 1 5.15 7.10
CU 675 0.89 603.28
CU 675 0.39 264.86
CU 3 0.00 0.00
0.00
M3 4,173 0.63 2,637.10
CU 1 0.00 0.00
0.00
M3 163 1.27 206.78
KG 215,903 0.06 12,616.29
KG 0.00
M2 387 0.14 52.49
M3 1,444 2.03 2,929.91
M2 3,150 0.00
M2 36.00 0.00
KG 247 0.00
M2 36 0.00
Total A $ 28,630
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B $0
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C $0
TOTAL $ 28,630
ANALISIS DE PRECIO UNITARIO
3 permiso obras
preliminares , instalacion de
gruas (Art. 5.1.3. o.g.u.c) gl 1 1,658,400
4
5
Total A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total C
TOTAL
Gl
$ 31,945,700
PRECIO
TOTAL
($)
$ 29,340,000
$ 947,300
$ 1,658,400
$ 31,945,700
PRECIO
TOTAL
($)
PRECIO
TOTAL
($)
$ 31,945,700
ANALISIS DE PRECIO UNITARIO
Total A $ 8,790
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
TOTAL $ 8,790
ANALISIS DE PRECIO UNITARIO
Total A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1
2
3
4
Total C
TOTAL
Gl
$ 28,000
PRECIO
TOTAL
($)
$ 28,000
$ 28,000
PRECIO
TOTAL
($)
PRECIO
TOTAL
($)
$ 28,000
ANALISIS DE PRECIO UNITARIO
Total A $ 15,560
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
TOTAL $ 15,560
ANALISIS DE PRECIO UNITARIO
Total A $ 4,590
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 montacargas hr 0.03 15000
2 trompo bencinero 125lts mes 1 70205
3 vibradores hr 0.013 100,200
4 taladro uni 0.2 59,900
5 soldadora uni 0.2 88,990
6 carretilla uni 0.01 29,900
7 palas uni 0.1 6,990
8 chuzos uni 0.1 16,990
9 andamios uni 0.30 100,000
10 alzamprimas uni 0.30 15,000
11 retro excavadora hr 0.16 30,000
12 camion tolva hr 0.22 15,200
13 martillo uni 0.1 7,520
14 cascos uni 0.1 9,500
15 excavadora hr 0.16 30,000
16 huincha uni 0.02 16,020
17 cargador frontal hr 0.20 15,400
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 soldador dia 0.025 $ 37,411
2 maestro primera dia 0.025 $ 29,929
3 carpintero dia 0.025 $ 29,929
4 albañil dia 0.025 $ 27,933
5 ayudante dia 0.003 $ 19,204
6 jornal dia 0.003 $ 15,987
7
8
9
10
11
12 SUBTOTAL
13 LEYES SOCIALES 35%
Total C
Precio unitario C
PRECIO
TOTAL
($)
Precio unitario A
PRECIO
TOTAL
($)
$ 450
$ 70,205
$ 1,303
$ 11,980
$ 17,798
$ 329
$ 699
$ 1,699
$ 30,000
$ 4,500
$ 4,800
$ 3,344
$ 752
$ 950
$ 4,800
$ 320
$ 3,080
$ 157,009
Precio unitario B
PRECIO
TOTAL
($)
$ 935
$ 748
$ 748
$ 698
$ 58
$ 48
$ 3,236
$ 1,132
$ 4,368
Precio unitario C
$ 161,377
ANALISIS DE PRECIO UNITARIO
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 cargador frontal hr 0.3 25000 $ 7,500
2 botadero externo m3 1 3200 $ 3,200
3 escobillon uni 2.00 3,200 $ 6,400
4 camion tolva hr 0.21 15,200 $ 3,192
5 pala uni 2.00 6,990 $ 13,980
6
Total B $ 34,272
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.25000 $ 29,929 $ 7,482
2
3 SUBTOTAL
4 LEYES SOCIALES 35% $ 2,619
Total C $ 10,101
Precio unitario C
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C
Total A $ 6,197
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.1 7520 $ 752
2 rodillo uni 0.1 3987 $ 399
3 huincha 8m uni 0.01 16,020 $ 160
4 brocha uni 0.02 1,990 $ 40
Total B $ 1,351
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 29000 $ 2,175
2 jonal dia 0.136 14500 $ 1,972
3 SUBTOTAL $ 4,147
4 LEYES SOCIALES 35% $ 1,451
Total C $ 5,598
Precio unitario C
Total A $ 1,154
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.1 7520 $ 752
2 huincha 8m uni 0.01 16,020 $ 160
3
4
Total B $ 912
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 $ 22,446 $ 1,683
2 jonal dia 0.136 $ 15,987 $ 2,174
3 SUBTOTAL $ 3,858
4 LEYES SOCIALES 35% $ 1,350
Total C $ 5,208
Precio unitario C
PARTIDA: CANTIDAD
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 container con baño(ito) mes 1 165000 $ 165,000
2 camion grua pluma hr 0.40 36000 $ 14,400
3 escritorio con cajonera uni 1 119,000 $ 119,000
4 linea telefonica con internet mes 1 50,000 $ 50,000
5
Total B $ 298,400
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante dia 0.2 $ 19,204 $ 3,841
2 $0
3 SUBTOTAL $ 3,841
4 LEYES SOCIALES 35% $ 1,344
Total C $ 5,185
Precio unitario C
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Contenedores Oficina 20´ Forrado mes 1.0000 143491 $ 143,491
2 camion grua pluma hr 0.44 36,000 $ 16,000
3 $0
4 $0
Total B $ 159,491
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante dia 0.2 $ 37,411 $ 7,482
2 $0
3 SUBTOTAL $ 7,482
4 LEYES SOCIALES 35% $ 2,619
Total C $ 10,101
Precio unitario C
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Container Oficina mes 1.0000 71745.5
2 camion grua pluma hr 0.167 36,000
3
4
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Ayudante dia 0.2 $ 37,411
2
3 SUBTOTAL
4 LEYES SOCIALES 35%
Total C
Precio unitario C
PRECIO
TOTAL
($)
$0
Precio unitario A
PRECIO
TOTAL
($)
$ 71,746
$ 6,000
$0
$0
$ 77,746
Precio unitario B
PRECIO
TOTAL
($)
$ 7,482
$0
$ 7,482
$ 2,619
$ 17,583
Precio unitario C
$ 95,329
ANALISIS DE PRECIO UNITARIO
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Container Bodega 20´ mes 1 114793 $ 114,793
2 Container Bodega 40 ´ mes 1 172182 $ 172,182
3 container de baño y duchas 40 mes 1 200,888 $ 200,888
4 container de comedor 40 uni 1 172,182 $ 172,182
5 camion grua pluma hr 0.16 36,000 $ 5,760
Total B $ 665,805
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal dia 0.2 $ 15,987 $ 3,197
2 $0
3 SUBTOTAL $ 3,197
4 LEYES SOCIALES 35% $ 1,119
Total C $ 7,514
Precio unitario C
A MATERIALES
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
5
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 caseta de guardia uni 1 90000 $ 90,000
2 camion grua pluma hr 0.4 36000 $ 14,400
3
4
Total B $ 104,400
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal dia 0.375 14500 $ 5,438
2 $0
3 $0
4 LEYES SOCIALES % $0
Total C $ 5,438
Precio unitario C
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 empalme provisorio gl 1 160000 $ 160,000
2 instalaciones electricas provisoria gl 1 260000 $ 260,000
3 empalme provisorio agua potable gl 1 160,000 $ 160,000
4 instalaciones a.p contruccion provisorias gl 1 160,000 $ 160,000
5 empalme provisorio alcantarillado gl 1 160,000 $ 160,000
6 instalaciones construccion provisorias gl 1 160,000 $ 160,000
Total B $ 1,060,000
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1
2
3
4
Total C
Precio unitario C
Total A $ 16,445
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 martillo uni 0.2 5390 $ 1,078
2 esmeril angular uni 0.10 28480 $ 2,848
3 soldadora bauker uni 0.20 166,390 $ 33,278
4
Total B $ 37,204
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero M2 0.2 $ 22,446 $ 4,489
2 soldador ML 0.2 $ 37,411 $ 7,482
3 ayudante M2 0.2 $ 19,204 $ 3,841
4
SUBTOTAL $ 15,812
LEYES SOCIALES 39% $ 6,167
Total C $ 21,979
Precio unitario C
TOTAL UNITARIO (A+B+C)
TOTAL $ 71,702
ANALISIS DE PRECIO UNITARIO
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 23,943 $ 24
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 62
LEYES SOCIALES 39% $ 24
Total C $ 87
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,237
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,237
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 Mazo de goma 24 Oz 1 0.005 $ 12,480 $ 62
4 Martillo carpintero 16 Oz acero 1 0.005 $ 5,990 $ 30
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,267
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.002 $ 39,905 $ 80
2 Ayudante 1 ml 0.002 $ 19,204 $ 38
3 Ayudante 2 ml 0.002 $ 19,204 $ 38
4 $ -
5 $ -
SUBTOTAL $ 157
LEYES SOCIALES 39% $ 61
Total C $ 218
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Cargador Frontal m2 1 $ 34,000 $ 71
2 Camion Tolva 12 m3 3 $ 10,000 $ 2,500
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 2,871
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal 1 m2 0.001 $ 15,987 $ 16
2 Jornal 2 m2 0.001 $ 15,987 $ 16
3 Jornal 3 m2 0.001 $ 15,987 $ 16
4 Jornal 4 m2 0.001 $ 15,987 $ 16
5 $ -
SUBTOTAL $ 64
LEYES SOCIALES 39% $ 25
Total C $ 89
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Motobomba a gasolina 3" 7HP 1000l/L L/min 0.005 $ 211,990 $ 2
2 Gasolina litro L 1 $ 722 $ 722
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 724
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro L/min 0.00002 $ 29,929 $ 0
2 Joranal L/min 0.00002 $ 15,987 $ 0
3 Joranal L/min 0.00002 $ 15,987 $ 0
4 $ -
5 $ -
SUBTOTAL $ 1
LEYES SOCIALES 39% $ 0
Total C $ 1
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 1 $ 20,000 $ 1,250
2 Camion Tolva 12 m3 3 $ 10,000 $ 2,500
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 4,049
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.06250 $ 15,987 $ 999
2 jornal m3 0.06250 $ 15,987 $ 999
3 jornal m3 0.06250 $ 15,987 $ 999
4 jornal m3 0.06250 $ 15,987 $ 999
5 $ -
SUBTOTAL $ 3,997
LEYES SOCIALES 39% $ 1,562
Total C $ 5,559
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
2 CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
3 GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
4 COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
5 BARREDORA REMOLCADA CON MOTOR AUXILIAR dia 0.040 65,850 $ 2,634
6 $ -
7 $ -
8 $ -
Total B $ 14,601
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 concretero m3/dia 1 $ 27,933 $ 3,514
2 concretero m3/dia 1 $ 27,933 $ 3,514
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 jornal m3/dia 1 $ 15,987 $ 2,011
5 $ -
SUBTOTAL $ 11,455
LEYES SOCIALES 39% $ 4,478
Total C $ 15,933
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.25000 $ 15,987 $ 3,997
2 jornal m3 0.25000 $ 15,987 $ 3,997
3 jornal m3 0.25000 $ 15,987 $ 3,997
4 jornal m3 0.25000 $ 15,987 $ 3,997
5 $ -
SUBTOTAL $ 15,987
LEYES SOCIALES 39% $ 6,249
Total C $ 22,236
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.13333 $ 15,987 $ 2,132
2 jornal m3 0.13333 $ 15,987 $ 2,132
3 jornal m3 0.13333 $ 15,987 $ 2,132
4 jornal m3 0.13333 $ 15,987 $ 2,132
5 jornal m3 0.13333 $ 15,987 $ 2,132
6 jornal m3 0.13333 $ 15,987 $ 2,132
SUBTOTAL $ 12,789
LEYES SOCIALES 39% $ 5,000
Total C $ 17,789
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Picota acero uni 0.005 $ 19,990 $ 100
6 $ -
7 $ -
8 $ -
Total B $ 3,655
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal m3 0.13333 $ 15,987 $ 2,132
2 jornal m3 0.13333 $ 15,987 $ 2,132
3 jornal m3 0.13333 $ 15,987 $ 2,132
4 jornal m3 0.13333 $ 15,987 $ 2,132
5 jornal m3 0.13333 $ 15,987 $ 2,132
6 jornal m3 0.13333 $ 15,987 $ 2,132
SUBTOTAL $ 12,789
LEYES SOCIALES 39% $ 5,000
Total C $ 17,789
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Retroexcavadora m3 0.001 $ 20,000 $ 22
2 Camion Tolva 12 m3 4 $ 10,000 $ 3,333
3 Martillos Hidráulicos Cat H140Es m3 0.005 $ 30,952 $ 155
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 3,510
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 $ -
2 $ -
3 $ -
4 $ -
5 $ -
6
SUBTOTAL $ -
LEYES SOCIALES 39% $ -
Total C $ -
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Nivel Topcom Equipo Topográfico 1 0.005 $ 1,000,000 $ 5,000
2 Mira Telescopica 4 Mts Topográfica C/burbuja 1 0.005 $ 35,000 $ 175
3 $ -
4 $ -
5 $ -
6 $ -
7 $ -
8 $ -
Total B $ 5,175
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Topografo ml 0.001 $ 39,905 $ 40
2 Ayudante 1 ml 0.001 $ 19,204 $ 19
3 Ayudante 2 ml 0.001 $ 19,204 $ 19
4 $ -
5 $ -
SUBTOTAL $ 78
LEYES SOCIALES 39% $ 31
Total C $ 109
Total A $ 523
Precio unitario A x m2
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. PRECIO PRECIO
CANTIDAD
UNITARIA UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MOTOR AUXILIAR dia 0.040 65,850 $ 2,634
Total B $ 14,601
Precio unitario B x m2
MANO DE OBRA
DESIGNACION UNID. PRECIO PRECIO
CANTIDAD
UNITARIA UNITARIO TOTAL
C ($) ($)
ITEM concretero m3/dia 1 $ 27,933 $ 3,514
concretero m3/dia 1 $ 29,929 $ 3,765
ayudante m3/dia 1 $ 19,204 $ 2,416
jornal m3/dia 1 $ 15,987 $ 2,011
$ 11,706
SUBTOTAL $ 23,412
LEYES SOCIALES 39% $ 9,152
Total C $ 32,564
Precio unitario C x m2
Total A $ 1,105
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra Barreno Ahoyador cu 0.005 169990 $ 850
Total B $ 850
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL UNITARIO (A+B+C)
TOTAL $ 25,869
ANALISIS DE PRECIO UNITARIO
Total A $ 344,256
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra Barreno A cu 0.005 169990 $ 850
Total B $ 850
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 Ayudante m3/dia 1 $ 19,204 $ 2,416
3 $0
4 $ 6,181
5 SUBTOTAL $ 12,362
LEYES SOCIALES 39% $ 4,832
Total C $ 17,194
Precio unitario C
TOTAL $ 362,300
ANALISIS DE PRECIO UNITARIO
Total A $ 1,123
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Total B $0
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL $ 25,037
ANALISIS DE PRECIO UNITARIO
Total A $ 11,190
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra cu 0.005 169990 $ 850
Total B $ 850
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL $ 35,955
ANALISIS DE PRECIO UNITARIO
Total A $ 33,263
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
pala un 0.005 5690 $ 28
carretilla un 0.005 27000 $ 135
betonera un 0.005 300,000 $ 1,500
Total B $ 1,663
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 27,933 $ 3,514
2 Concretero m3/dia 1 $ 27,933 $ 3,514
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 Jornal m3/dia 1 $ 19,204 $ 2,416
5 $ 11,860
SUBTOTAL $ 23,720
LEYES SOCIALES 39% $ 9,272
Total C $ 32,992
Precio unitario C
TOTAL $ 67,918
ANALISIS DE PRECIO UNITARIO
Total A $ 5,234
Precio unitario A x m2
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAUKER dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MOTOR
dia 0.040 65,850 $ 2,634
total b $ 14,601
Precio unitario B x m2
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 29,929 $ 3,765
2 Concretero m3/dia 1 $ 29,929 $ 3,765
3 ayudante m3/dia 1 $ 15,987 $ 2,011
4 Jornal m3/dia 1 $ 15,987 $ 2,011
5 $ 11,552
SUBTOTAL $ 23,105
LEYES SOCIALES 39% $ 9,032
Total C $ 32,136
Precio unitario C
TOTAL $ 46,737
ANALISIS DE PRECIO UNITARIO
Total A $ 1,570
Precio unitario A x m2
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3 hora 0.04 12,600 $ 504
CAMION MIXER 6 M3 dia 0.1 28,660 $ 2,866
GUNITADORA DE TALUDES dia 0.1 48,533 $ 4,853
COMPRESOR 3.5 HP 10 BAR BAU dia 0.015 249,571 $ 3,744
BARREDORA REMOLCADA CON MO
dia 0.040 65,850 $ 2,634
total b $ 14,601
Precio unitario B x m2
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 29,929 $ 3,765
2 Concretero m3/dia 1 $ 29,929 $ 3,765
3 ayudante m3/dia 1 $ 15,987 $ 2,011
4 Jornal m3/dia 1 $ 15,987 $ 2,011
5 $ 11,552
SUBTOTAL $ 23,105
LEYES SOCIALES 39% $ 9,032
Total C $ 32,136
Precio unitario C
TOTAL $ 48,308
ANALISIS DE PRECIO UNITARIO
Total A $ 665
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro Tierra
Barreno
Ahoyador
Motorizado
150mm cu 0.005 169990 $ 850
Total B $ 850
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 maestro m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL $ 25,430
ANALISIS DE PRECIO UNITARIO
PERNOS DE
ANCLAJE PARA
SOIL NAILING cu 1 165000 $ 165,000
Total A $ 165,000
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
COMPRESOR 3.5
HP 10 BAR
BAUKER cu 0.015 249,571 $ 3,744
Equipo mecánico
para realización de
los trabajos de
perforación h 0.502 64,411 $ 32,334
Total B $ 37,522
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL $ 226,437
ANALISIS DE PRECIO UNITARIO
lechada
fabricado en
planta m3 0.01 52342 $ 523
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Camión con
cesta elevadora
de brazo
articulado de 16
m de altura h 0 10,243 $ 1,444
Equipo para
inyecciones de
lechada de
cemento, con
bomba de
presión y carro
de perforación
para taladros. h 1 220,297 $ 128,874
BETONERA un 0.005 300,000 $ 1,500
Total B $ 131,818
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Concretero m3/dia 1 $ 27,933 $ 3,514
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3
4 $0
5 $ 5,930
SUBTOTAL $ 11,860
LEYES SOCIALES 39% $ 4,636
Total C $ 16,496
Precio unitario C
TOTAL $ 148,314
ANALISIS DE PRECIO UNITARIO
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
maquina de soldar Ml 0.005 $ 359,990 $ 1,800
Total B $ 1,800
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 29,929 $ 3,765
2 ayudante m3/dia 1 $ 19,204 $ 2,416
3 ayudante m3/dia 1 $ 19,204 $ 2,416
4 $0
5 $ 8,597
SUBTOTAL $ 17,194
LEYES SOCIALES 39% $ 6,721
Total C $ 23,915
Precio unitario C
TOTAL $ 25,715
ANALISIS DE PRECIO UNITARIO
Total A $ 1,000
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Taladro
percutor
inalámbrico cu 0.005 $ 259,990 $ 1,300
Total B $ 1,300
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador m3/dia 1 $ 25,689 $ 3,232
2 ayudante m3/dia 1 $ - $0
3 ayudante m3/dia 1 $ - $0
4 $0
5 $ 3,232
SUBTOTAL $ 6,463
LEYES SOCIALES 39% $ 2,527
Total C $ 8,990
Precio unitario C
TOTAL $ 11,290
ANALISIS DE PRECIO UNITARIO
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Total B $0
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Total C $0
Precio unitario C
Total A $0
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
CAMION TOLVA 12m3hora 1 12,600 $ 12,600
Total B $ 12,600
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Jornal m3/dia 1 $ 15,987 $ 2,011
2 Jornal m3/dia 1 $ 15,987 $ 2,011
3 $0
4 $0
5
SUBTOTAL $ 4,022
LEYES SOCIALES 39% $ 1,572
Total C $ 5,595
Precio unitario C
TOTAL $ 18,195
ANALISIS DE PRECIO UNITARIO
Total A
Precio unitario A
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Total B
Precio unitario B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
Total C
Precio unitario C
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 33,311 $ 33,311
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
6 $0
7 $0
8 $0
Total B $ 34,911
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 $ 26,600 $ 484
2 Ayudante 1 m3 0.0182 $ 18,288 $ 333
3 Ayudante 2 m3 0.0182 $ 18,288 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES $ 0 448.0
Total C $ 1,597
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 4,990 $ 25
3 Disco de corte uni 0.2 1,070 $ 214
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 287
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0053 28500 $ 150
2 Enfierrador 2 KG 0.0053 28500 $ 150
3 Ayudante 1 KG 0.0053 18287.5 $ 96
4 Ayudante 2 0.0053 18287.5 $ 96
5 $0
SUBTOTAL $ 493
LEYES SOCIALES 39% 192.1
Total C $ 685
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 nivel de mano m2 0.005 $ 9,990 $ 50
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 50
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0111 28500 $ 317
2 Ayudante 1 KG 0.0111 21375 $ 238
3 Ayudante 2 KG 0.0111 21375 $ 238
4 $0
5 $0
SUBTOTAL $ 792
LEYES SOCIALES 39% 308.8
Total C $ 1,100
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 $0
8 $0
Total B $ 56,800
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
PLACA COMPACTADORA 5,5HP - 95 KG MOTOR
1 m3 0.005 $ 999,990 $ 5,000
HONDA GX160 Y TANQUE DE AGUA
2 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
3 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
4 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
5 $0
6 $0
7 $0
8 $0
Total B $ 5,274
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante 1 m3 0.0091 $ 18,288 $ 166
2 Ayudante 2 m3 0.0091 $ 18,288 $ 166
3 $0
4 $0
5 $0
SUBTOTAL $ 333
LEYES SOCIALES $ 0 129.7
Total C $ 462
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Cuchillo cartonero rojo uni 0.005 $ 8,990 $ 45
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 45
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0021 28500 $ 59
2 Ayudante 1 KG 0.0021 21375 $ 45
3 Ayudante 2 KG 0.0021 21375 $ 45
4 $0
5 $0
SUBTOTAL $ 148
LEYES SOCIALES 39% 57.9
Total C $ 206
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 47,000 $ 47,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
8 $0
Total B $ 53,330
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 $ 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 $ 4,990 $ 25
3 Disco de corte uni 0.2 $ 1,070 $ 214
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 287
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0083 $ 28,500 $ 238
2 Enfierrador 2 KG 0.0083 $ 28,500 $ 238
3 Ayudante 1 KG 0.0083 $ 18,288 $ 152
4 Ayudante 2 0.0083 $ 18,288 $ 152
5 $0
SUBTOTAL $ 780
LEYES SOCIALES $ 0 304.1
Total C $ 1,084
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 $0
8 $0
Total B $ 56,800
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion mixer m3 1 $ 52,000 $ 52,000
2 bombeo de hormigon m3 0.17 $ 7,800 $ 1,326
3 Carretilla acero 90 litros uni 0.005 $ 34,900 $ 175
4 Pala punta de huevo acero uni 0.005 $ 4,990 $ 25
5 Cinta Huincha Metrica Stanley Powerlock De 8 Metros uni 0.005 $ 14,900 $ 75
Vibrador 65mm interno alta frecuencia IRFU 65 Wacker
6 uni 0.005 $ 640,000 $ 3,200
Neuson
7 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
8 $0
Total B $ 58,330
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0182 26600 $ 484
2 Ayudante 1 m3 0.0182 18287.5 $ 333
3 Ayudante 2 m3 0.0182 18287.5 $ 333
4 $0
5 $0
SUBTOTAL $ 1,149
LEYES SOCIALES 39% 448.0
Total C $ 1,597
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Platacho Magnesio 1200 uni 0.005 305,990 $ 1,530
2 Regla De Aluminio Reforzada De 1-1 / 2 Pulgadas uni 0.005 $ 141,262 $ 706
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,236
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro concretero m3 0.0100 26600 $ 266
2 Ayudante 1 m3 0.0100 18287.5 $ 183
3 Ayudante 2 m3 0.0100 18287.5 $ 183
4 $0
5 $0
SUBTOTAL $ 632
LEYES SOCIALES 39% 246.4
Total C $ 878
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion Pluma uni 0.02 $ 25,000 $ 500
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 500
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0091 $ 28,500 $ 259
2 Ayudante 1 KG 0.0091 $ 21,375 $ 194
3 Ayudante 2 KG 0.0091 $ 21,375 $ 194
4 $0
5 $0
SUBTOTAL $ 648
LEYES SOCIALES $ 0 252.6
Total C $ 900
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Camion Pluma uni 0.02 $ 25,000 $ 500
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 500
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0091 $ 28,500 $ 259
2 Ayudante 1 KG 0.0091 $ 21,375 $ 194
3 Ayudante 2 KG 0.0091 $ 21,375 $ 194
4 $0
5 $0
SUBTOTAL $ 648
LEYES SOCIALES $ 0 252.6
Total C $ 900
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Brocha 3/8"x3" $ 1 0.005 $ 1,990 $ 30
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 30
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Primera KG 0.0135 $ 28,500 $ 385
2 Ayudante 1 KG 0.0135 $ 21,375 $ 289
3 Ayudante 2 KG 0.0135 $ 21,375 $ 289
4 $0
5 $0
SUBTOTAL $ 963
LEYES SOCIALES $ 0 375.5
Total C $ 1,338
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Alicate combinación 7" uni 0.005 $ 9,610 $ 48
2 Esmeril angular éctrico 4,5" 700W uni 0.005 $ 4,990 $ 25
3 Disco de corte uni 0.2 $ 1,070 $ 214
4 Camion Pluma uni 0.02 $ 25,000 $ 500
5 $0
6 $0
7 $0
8 $0
Total B $ 787
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Enfierrador 1 KG 0.0053 $ 28,500 $ 150
2 Enfierrador 2 KG 0.0053 $ 28,500 $ 150
3 Ayudante 1 KG 0.0053 $ 18,288 $ 96
4 Ayudante 2 KG 0.0053 $ 18,288 $ 96
5 $0
SUBTOTAL $ 493
LEYES SOCIALES $ 0 192.1
Total C $ 685
B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 alicate 0.01 un $ 4,600 $ 23
2 machina 0.01 un $ 20,000 $ 100
3 transporte 0.01 un $ 140,000 $ 700
4 huincha 0.01 un $ 2,400 $ 12
5 grua torre 0.05 dia $ 232,608 $ 11,630
6 $0
7 $0
8 $0
Total B $ 12,465
C MANO DE OBRA
ITEM DESIGNACION CANT UNID PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 enfierrador 0.01 m3/dia $ 24,648 $ 246
2 ayudante 0.01 m3/dia $ 16,344 $ 163
3 ayudante 0.01 m3/dia $ 16,345 $ 163
4 $0
5 $0
SUBTOTAL $ 573
LEYES SOCIALES 39% 223.61222
Total C $ 797
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID.
C MANO DE OBRA
ITEM DESIGNACION CANT
CONEXIÓN Unidad M2
Precio unitario $ 134,121
PRECIO PRECIO
CANTIDAD UNITARIO TOTAL
($) ($)
mt $ 94,554 $ 23,639
mt $ 94,554 $ 23,639
mt $ 61,975 $ 15,494
mt $ 30,188 $ 7,547
$0
$0
$0
$0
$0
$0
Total A $ 70,318
un $ 79,500 $ 398
un $ 96,000 $ 480
un $ 5,600 $ 28
un $ 3,290 $ 16
hora/dia $ 60,000 $ 60,000
$0
$0
$0
Total B $ 60,922
UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)
B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Huincha para medir 8 m fibra de 0.0050 Ml $ 11,890 $ 59
2 LAPIZ CARPINTERO 0.0050 M2 $ 290 $1
3 Cuchillo cartonero rojo 0.0050 Ml $ 8,990 $ 45
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 106
C MANO DE OBRA
ITEM DESIGNACION CANT UN PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Maestro Carpintero 0.0556 M2 $ 15,000 $ 833
2 Ayudante 1 0.0556 M2 $ 12,000 $ 667
3 Ayudante 2 0.0556 M2 $ 12,000 $ 667
4 $0
5 $0
SUBTOTAL $ 2,167
LEYES SOCIALES 39% 845
Total C $ 3,012
B MAQUINAS Y EQUIPO
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Huincha para medir 8 m fibra de vid 0.0050 Ml $ 11,890 $ 59
2 LAPIZ CARPINTERO 0.0050 M2 $ 290 $1
3 Cuchillo cartonero rojo 0.0050 Ml $ 8,990 $ 45
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 106
C MANO DE OBRA
ITEM DESIGNACION CANT UNI PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 jornal 0.0556 m3/dia $ 14,079 $ 782
2 jornal 0.0556 m3/dia $ 14,079 $ 782
3 jornal 0.0556 m3/dia $ 14,079 $ 782
4 $0
5 $0
SUBTOTAL $ 2,346
LEYES SOCIALES 39% 915.130666667
Total C $ 3,262
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carretilla UN 0 $ 27,000 135
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 135
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 Ayudante 0.4444 M2 $ 12,000 $ 5,333
2 Ayudante 0.4444 M2 $ 12,000 $ 5,333
3 Ayudante 0.4444 M2 $ 12,001 $ 5,334
4 $0
5 $0
SUBTOTAL $ 16,000
LEYES SOCIALES 39% 6240.17333333
Total C $ 22,241
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha UNID. 0 $ 2,400 $ 160
2 remachadora UNID. 0.0050 $ 16,960 $ 85
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 245
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350
2 Ayudante DIA 0.4444 $ 12,000 $ 5,333
3 Ayudante DIA 0.4444 $ 12,000 $ 5,333
4 $0
5 $0
SUBTOTAL $ 15,017
LEYES SOCIALES 39% 5856.5
Total C $ 20,873
B MAQUINAS Y EQUIPO B
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO ITEM
UNITARIO TOTAL
($) ($)
1 huincha UNID. 0 $ 2,400 $ 160 1
2 remachadora UNID. 0.0050 $ 16,960 $ 85 2
3 $0 3
4 $0 4
5 $0 5
6 $0 6
7 $0 7
8 $0 8
Total B $ 245
C MANO DE OBRA C
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO ITEM
UNITARIO TOTAL
($) ($)
1 MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350 1
2 Ayudante DIA 0.4444 $ 12,000 $ 5,333 2
3 Ayudante DIA 0.4444 $ 12,000 $ 5,333 3
4 $0 4
5 $0 5
SUBTOTAL $ 15,017
LEYES SOCIALES 39% 5856.5
Total C $ 20,873
ANALISIS DE PRECIO UNITARIO
MAQUINAS Y EQUIPO
DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
MANO DE OBRA
DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350
MAESTRO DE PRIMERA DIA 0.15 29,000 $ 4,350
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 Taladro percutor inalámbrico 13mm 18V 0.0050 M2 $ 259,990
2 Huincha para medir 8 m fibra de vidrio rojo 0.0050 Ml $ 11,890
3 LAPIZ CARPINTERO 0.0050 M2 $ 290
4 Tizador 30 m 0.0050 Ml $ 7,490
5 Cuchillo cartonero rojo 0.0050 Ml $ 8,990
6
7
8
Total B
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO
UNITARIO
($)
1 carpintero DIA 0.0455 $18,986.00
2 Ayudante DIA 0.4444 $ 12,000
3 Ayudante DIA 0.4444 $ 12,000
4
5
SUBTOTAL
LEYES SOCIALES 39%
Total C
M2 Partida AISLAN GLASS Unidad M2
$0 Item Precio unitario $ 5,804
A MATERIALES
PRECIO ITEM PRECIO PRECIO
TOTAL DESIGNACION CANT UNI UNITARIO TOTAL
($) ($) ($)
B MAQUINAS Y EQUIPO
PRECIO ITEM DESIGNACION CANT UNI PRECIO PRECIO
TOTAL UNITARIO TOTAL
($) ($) ($)
$ 1,300 1 Huincha para 0.0050 Ml $ 11,890 $ 59
$ 59 2 LAPIZ CARP 0.0050 M2 $ 290 $1
$1 3 Cuchillo carto 0.0050 Ml $ 8,990 $ 45
$ 37 4 $0
$ 45 5 $0
$0 6 $0
$0 7 $0
$0 8 $0
$ 1,443 Total B $ 106
C MANO DE OBRA
PRECIO ITEM DESIGNACION CANT UNI PRECIO PRECIO
TOTAL UNITARIO TOTAL
($) ($) ($)
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 cuchillo caronero metalico uni 0.015 3890 $ 58
3 huincha de medir 8m uni 0.005 11890 $ 59
4 lapiz carpintero uni 0.01 290 $3
5 $0
6 $0
7 $0
8 $0
Total B $ 1,061
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 22446 $ 1,683
2 ayundante dia 0.02 19204 $ 384
3 ayundante dia 0.02 19204 $ 384
4 $0
5 $0
SUBTOTAL $ 2,452
LEYES SOCIALES 39% 956.13
Total C $ 3,408
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 cuchillo caronero metalico uni 0.015 3890 $ 58
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 999
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.075 29000 $ 2,175
2 ayundante 1 dia 0.02 19204 $ 384
3 ayundante 2 dia 0.02 19204 $ 384
4 $0
5 $0
SUBTOTAL $ 2,943
LEYES SOCIALES 39% 1147.83
Total C $ 4,091
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha de medir 8m uni 0.005 11890 $ 59
2 llana dentada ultra ligera 28<11 uni 0.05 7490 $ 375
3 espatula acero80mm uni 0.12 2290 $ 275
4 esponja para piso uni 0.008 1990 $ 16
5 mazo de goma uni 0.005 12490 $ 62
6 nivel de mano uni 0.02 3790 $ 76
7 $0
8 $0
Total B $ 863
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 ceramista dia 0.03 25689 $ 771
2 ayudante 1 dia 0.03 19204 $ 576
3 ayudante 2 dia 0.03 19204 $ 576
4 $0
5 $0
SUBTOTAL $ 1,923
LEYES SOCIALES 39% 749.9349
Total C $ 2,673
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 cuchillo caronero metalico uni 0.015 3890 $ 58
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 58
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 alfombrero dia 0.045 29000 $ 1,305
2 ayudante dia 0.03 19024 $ 571
3 ayudante dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.11
Total C $ 3,401
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 huincha de medir 8m uni 0.005 11890 $ 59
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 1,000
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.045 29000 $ 1,305
2 ayudnate dia 0.03 19024 $ 571
3 ayudante dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.1116
Total C $ 3,401
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pistola calafatera uni 1 3610 $ 3,610
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 3,610
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.045 29000 $ 1,305
2 ayudnate dia 0.03 19024 $ 571
3 ayudnate dia 0.03 19024 $ 571
4 $0
5 $0
SUBTOTAL $ 2,446
LEYES SOCIALES 39% 954.1116
Total C $ 3,401
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 huincha de medir 8m uni 0.005 11890 $ 59
2 llana dentada ultra ligera 28<11 uni 0.05 7490 $ 375
3 espatula acero80mm uni 0.12 2290 $ 275
4 esponja para piso uni 0.008 1990 $ 16
5 mazo de goma uni 0.005 12490 $ 62
6 nivel de mano uni 0.02 3790 $ 76
7 $0
8 $0
Total B $ 863
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 ceramista dia 0.03 25689 $ 771
2 ayudante dia 0.03 19204 $ 576
3 ayudante dia 0.03 19204 $ 576
4 $0
5 $0
SUBTOTAL $ 1,923
LEYES SOCIALES 39% 749.9349
Total C $ 2,673
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 camion capacho hr 0.2 15200 $ 3,040
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 3,040
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero m2/dia 0.022 29000 $ 644
2 ayudante 1 m2/dia 0.022 19204 $ 427
3 ayudante 2 m2/dia 0.022 19204 $ 427
4 $0
5 $0
SUBTOTAL $ 1,498
LEYES SOCIALES 39% 584.202666667
Total C $ 2,082
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano c/u 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano uni 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700
TOTAL UNITARIO (A+B+C) $ 237,040
ANALISIS DE PRECIO UNITARIO
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 114 uni 0.005 2350 $ 12
2 taladro percutor electrico uni 0.03 31340 $ 940
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 952
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 6x1 20uni c/u 0.2 755 $ 151
2 taladro percutor electrico uni 0.03 31340 $ 940
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 1,091
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 taladro percutor electrico uni 0.03 31340 $ 940
2 nivel de mano uni 1 1350 $ 1,350
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 2,290
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.10 29000 $ 2,900
2 ayudante 1 dia 0.05 19204 $ 960
3 ayudante 2 dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 4,820
LEYES SOCIALES 39% 1879.956
Total C $ 6,700
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 tornillo 6x1 20uni c/u 0.2 755 $ 151
2 $0
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 151
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 carpintero dia 0.01 29000 $ 290
2 ayudante dia 0.005 19204 $ 96
3 $0
4 $0
5 $0
SUBTOTAL $ 386
LEYES SOCIALES 39% 150.5478
Total C $ 537
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 brocha oleo 3" uni 0.01 5350 $ 54
2 rodillo 15cm uni 0.02 2790 $ 56
3 $0
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 109
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pintor dia 0.05 22446 $ 1,122
2 ayudante dia 0 19204 $0
3 ayudante dia 0.05 19204 $ 960
4 $0
5 $0
SUBTOTAL $ 2,083
LEYES SOCIALES 39% 812.175
Total C $ 2,895
B MAQUINAS Y EQUIPO
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 brocha oleo 3" uni 0.03 5350 $ 161
2 rodillo 15cm uni 0.2 2790 $ 558
3 diluyente 5 litros uni 0.01 9230 $ 92
4 $0
5 $0
6 $0
7 $0
8 $0
Total B $ 811
C MANO DE OBRA
ITEM DESIGNACION UNID. CANTIDAD PRECIO PRECIO
UNITARIO TOTAL
($) ($)
1 pintor dia 0.01 22446 $ 224
2 ayudante dia 0.005 19204 $ 96
3 ayudante dia 0.005 19204 $ 96
4 $0
5 $0
SUBTOTAL $ 417
LEYES SOCIALES 39% 162.435
Total C $ 579
Trabajador Sueldo base Valor Dia Valor hora % Costo Medio Total
Residente $700,000 $33,333 $3,704 5.8% $1,926
Profesional ayudante $500,000 $23,810 $2,646 4.1% $983
Jefe administrativo $600,000 $28,571 $3,175 5.0% $1,415
Jefe de bodegas $520,000 $24,762 $2,751 4.3% $1,063
Ayudante de bodega $420,000 $20,000 $2,222 3.5% $693
Pañolero $390,000 $18,571 $2,063 3.2% $598
Jefe de obra $500,000 $23,810 $2,646 4.1% $983
Capataz $480,000 $22,857 $2,540 4.0% $905
Topografo $800,000 $38,095 $4,233 6.6% $2,515
Trazador $480,000 $22,857 $2,540 4.0% $905
Prevencionista de riesgo $480,000 $22,857 $2,540 4.0% $905
Maestro primera $600,000 $28,571 $3,175 5.0% $1,415
Carpintero obra Gruesa $450,000 $21,429 $2,381 3.7% $796
Albañil $560,000 $26,667 $2,963 4.6% $1,232
Enfierrador $600,000 $28,571 $3,175 5.0% $1,415
Concretero $560,000 $26,667 $2,963 4.6% $1,232
extructurero $600,000 $28,571 $3,175 5.0% $1,415
Soldador $750,000 $35,714 $3,968 6.2% $2,211
Ceramista $515,000 $24,524 $2,725 4.3% $1,042
Yesero $456,000 $21,714 $2,413 3.8% $817
Pintor $450,000 $21,429 $2,381 3.7% $796
Ayudante $385,000 $18,333 $2,037 3.2% $583
Jornal $320,500 $15,262 $1,696 2.6% $404
$576,976 64108.4656 1.0 $26,249
Porcentaje de 6.7%
Gratificaion 15
Locomocion
0.03