Sistema de refrigeración del reactor
PWR
Asignatura Centrales Nucleares
Gonzalo Jiménez y Nuria García-Herranz
Departamento de Ingeniería Energética
Escuela Técnica Superior de Ingenieros Industriales
Universidad Politécnica de Madrid
Curso 2020/2021
2
Centrales Nucleares ► Tema 3.4. Sistema de refrigeración del reactor PWR 2
Sistema de refrigeración
del reactor
https://econtent.unm.edu/digital/collection/nuceng/id/88
https://econtent.unm.edu/digital/collection/nuceng/id/88
Ref:
https://www.n
rc.gov/docs/M
L1122/ML1122
3A213.pdf
Ref: Diccionario
Tecnología
Nuclear. A.
Tanarro. 2ª
edición
Ref:
https://www.nrc.gov/docs/ML
1122/ML11223A213.pdf
Ref: https://www.nrc.gov/docs/ML1122/ML11223A213.pdf
Transferring a heated
ingot destined to be
forged into the
bottom section of a
steam generator for a
nuclear power plant.
http://enygf2015.org/program/technical-visits/chalon-le-creusot/
Centrales Nucleares ► Tema 3.4. Sistema de refrigeración del reactor PWR 18
Generador de vapor Forja del GV
https://www.theengineer.co.uk/power-struggle-developing-the-uks-nuclear-manufacturing-capacity/
https://www.theengineer.co.uk/power-struggle-developing-the-uks-nuclear-manufacturing-capacity/
Ref: https://twitter.com/OperadorNuclear/status/1229108621486829571
Centrales Nucleares ► Tema 3.4. Sistema de refrigeración del reactor PWR 28
Generador de vapor Transporte del GV
Central Nuclear de Ascó
Ref: https://twitter.com/OperadorNuclear/status/1229108621486829571
Centrales Nucleares ► Tema 3.4. Sistema de refrigeración del reactor PWR 29
Entrada en
Generador la
de vapor contención
https://www.theengineer.
co.uk/power-struggle-
developing-the-uks-
nuclear-manufacturing-
capacity/
Ref: Diccionario
Tecnología
Nuclear. A.
Tanarro. 2ª
edición
https://www.hindawi.com/journals/stni/2018/8150879/
Ref:
https://www.researchgate.ne
t/publication/281618387_Im
proving_reactor_coolant_pu
mp_seal_reliability_at_Domi
nion_Surry_nuclear_power_s
tation
Ref:
https://www.
nrc.gov/docs/
ML1122/ML1 Westinghouse High Temperature
1223A213.pdf Shutdown Seals (SDS)
• Olkiluoto 3: Installation of Heavy Components of the Primary Cooling System (muy recomendable)