INFORME MENSUAL AVANCE DE

OBRA N° 04
(Periodo del 15 de Octubre al 15 de Noviembre 2023)

OBRA:
CONSTRUCCIÓN DEL NUEVO TALLER DE MANTENIMIENTO MECANICO PARA
EQUIPOS PESADOS Y LIVIANOS - ECSERM QUIULACOCHA

ENTIDAD EJECUTORA : ECSERM QUIULACOCHA

MODALIDAD DE EJCUCION : ADMINISTRACION DIRECTA

PLAZO DE EJECUCION : 90 DIAS CALENDARIOS

MONTO ASIGNADO : S/. 301,359.52 INC. IGV

SUPERVISOR DE OBRA : ING° RICHARD CHAMORRO B.

Quiulacocha, 20/11/2023
1. AVANCE FISICO Y FINANCIERO

RESUMEN DE AVANCE MENSUAL - NOVIEMBRE 2023


PERIODO DEL 15 DE OCTUBRE AL 15 DE NOVIEMBRE 2023

CONSTRUCCION DEL NUEVO TALLER DE MANTENIMIENTO MECANICO PARA EQUIPOS


OBRA PLAZO DE EJECUCIÓN 90 días calendarios
PESADOS Y LIVIANOS - ECSERM QUIULACOCHA
EJECUTA EMPRESA COMUNAL DE SERVICIOS MULTIPLES QUIULACOCHA FECHA DE INICIO: 15-ago-23
MODALIDAD ADMINISTRACION DIRECTA FECHA DE TERMINO: 13-nov-23
SUPERVISIOR ING. RICHARD CHAMORRO BERNACHEA PRESUPUESTO REFERENCIAL S/. 301,359.52

PRESUPUESTO VALORIZACION SALDO


ITEM DESCRIPCIÓN
BASE
ANTERIOR %An ACTUAL %Ac ACUMULADO % Acm S/. %

01 AMPLIACION DEL TALLER DE MANTENIMIENTO ECSERM QUIULACOCHA


273,963.20 107,731.83 39.32% 43,380.47 15.83% 151,112.30 55.16% 122,850.91 44.84%

VALORIZACION NETA 273,963.20 107,731.83 43,380.47 151,112.30 122,850.91


GASTOS GENERALES 10.00% 27,396.32 10,773.18 4,338.05 15,111.23 12,285.09
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL 301,359.52
IGV 0.00% 0.00 0.00 0.00 0.00 0.00

MONTO TOTAL DE VALORIZACION MENSUAL S/.301,359.52 S/.118,505.01 39.32% S/. 47,718.52 15.83% S/.166,223.52 55.16% S/.135,136.00 44.84%

AVANCE PROGRAMADO DEL MES ACUMULADO SEGÚN CAAOV 62.70%


CONTROL DE AVANCES
AVANCE ELECUTADO DEL MES ACUMULADO SEGÚN VAL. ACTUAL N° 04 55.16%
ESTADO DE LA OBRA EJECUTADO - PROGRAMADO -7.55%

LA OBRA SE ENCUENTRA ATRASADA


2. % DE AVANCE PROGRAMADO – NOVIEMBRE
JULIO-AGOSTO 2023 AGOSTO-SETIEMBRE 2023 SETIEMBRE-OCTUBRE 2023 OCTUBRE2023-NOV. 2023 NOV. -DICIEMBRE 2023
DESCRIPCIÓN
15 15 15 15 15 15 15 15 15 15

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 78,459.89 S/. 93,326.70 S/. 102,176.61 S/. 0.00 S/. 0.00 S/. 0.00
% AVANCE DE MES 28.64% 34.07% 37.30% 0.00% 0.00% 0.00%
% AVANCE ACUMULADO MENSUAL 28.64% 62.70% 100.00% 100.00% 100.00% 100.00%
GASTOS GENERALES 10.00% S/. 7,845.99 S/. 9,332.67 S/. 10,217.66 S/. 0.00 S/. 0.00 S/. 0.00
UTILIDAD 0.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
SUBTOTAL S/. 86,305.88 S/. 102,659.37 S/. 112,394.27 S/. 0.00 S/. 0.00 S/. 0.00
IGV (0.00%) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
TOTAL MENSUAL S/. 86,305.88 S/. 102,659.37 S/. 112,394.27 S/. 0.00 S/. 0.00 S/. 0.00


100% 100.00% 100.00% 100.00% 100.00%

90%

80%


70%

62.70%
60%

50%

40%

30% 28.64%

20%

10%

0% 0%
1 2 3 4 5 6 7
3. % AVANCE EJECUTADO – NOVIEMBRE
JULIO-AGOSTO 2023 AGOSTO-SETIEMBRE 2023 SETIEMBRE-OCTUBRE2023 OCTUBRE-NOV. 2023 NOV. -DICIEMBRE 2023
DESCRIPCIÓN
15 15 15 15 15 15 15 15 15 15

TOTAL COSTO DIRECTO DE OBRA (CD) S/. 26,668.22 S/. 19,882.93 S/. 61,180.67 S/. 43,380.47 S/. 0.00 S/. 0.00
% AVANCE DE MES 9.73% 7.26% 22.33% 15.83% 0.00% 0.00%
% AVANCE ACUMULADO MENSUAL 9.73% 16.99% 39.32% 55.16% 55.16% 55.16%
GASTOS GENERALES 10.00% S/. 2,666.82 S/. 1,988.29 S/. 6,118.07 S/. 4,338.05 S/. 0.00 S/. 0.00
UTILIDAD 0.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
SUBTOTAL S/. 29,335.04 S/. 21,871.22 S/. 67,298.74 S/. 47,718.52 S/. 0.00 S/. 0.00
IGV (0.00%) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
TOTAL MENSUAL S/. 29,335.04 S/. 21,871.22 S/. 67,298.74 S/. 47,718.52 S/. 0.00 S/. 0.00


100%

90%

80%


70%

60%
55.16% 55.16% 55.16%
50%

40% 39.32%

30%

20%
16.99%
10% 9.73%

0% 0%
1 2 3 4 5 6 7
4. CURVA “S” – PROGRAMADO VS EJECUTADO
5. REGISTRO FOTOGRAFICO – SEDIMENTADOR Y CANAL DE CONDUCCION
5.1 REGISTRO FOTOGRAFICO – COBERTURA METALICA
6. CONSIDERACIONES
CONSIDERACIONES TECNICAS DE LOS COMPONENTES:

1. A la fecha ya de concluyo al 95% de las obras civiles.


2. Se culmino al 100% la construcción del canal de conducción y desarenador como se evidencia en el panel fotográfico.
3. A la fecha se continua con el siguiente proceso, que corresponde a la fabricación y montaje de la cobertura metálica (Ver panel fotográfico).
4. Con fecha 27/11/2023, se dio inicio a la ejecución de la cobertura metálica, a cargo de la empresa TECHAR – ESTRUCTURAS METALICAS.
5. A la fecha se tiene un avance físico del 20%, que corresponde a la fabricación de las estructuras metálicas de la cobertura.
6. El servicio cuenta con un TDR, previo al inicio y durante la ejecución se realizara el seguimiento y cumplimiento del mismo, ya que indican términos
contractuales como; costo, plazo de ejecución, modalidad de ejecución etc.).
7. Del proyecto integral que esta en ejecución, queda pendiente las instalaciones eléctricas y sanitarias y almacén interior, que básicamente
corresponden al taller de mantenimiento.

CONCLUSIONES Y RECOMENDACIONES
- El proceso de construcción de la obra está desarrollando de acuerdo a los planos y especificaciones técnicas del proyecto en coordinación con la
gerencia y directorio.
- La construcción de la cobertura metálica tiene un avance físico del 20%, la obra se culminará el 27-12-2023,
- Se recomienda acelerar y reducir los tiempos en la entrega de materiales requeridos, con la finalidad de evitar retrasos en la obra.
Gracias...