OBRA N° 04
(Periodo del 15 de Octubre al 15 de Noviembre 2023)
OBRA:
CONSTRUCCIÓN DEL NUEVO TALLER DE MANTENIMIENTO MECANICO PARA
EQUIPOS PESADOS Y LIVIANOS - ECSERM QUIULACOCHA
Quiulacocha, 20/11/2023
1. AVANCE FISICO Y FINANCIERO
MONTO TOTAL DE VALORIZACION MENSUAL S/.301,359.52 S/.118,505.01 39.32% S/. 47,718.52 15.83% S/.166,223.52 55.16% S/.135,136.00 44.84%
TOTAL COSTO DIRECTO DE OBRA (CD) S/. 78,459.89 S/. 93,326.70 S/. 102,176.61 S/. 0.00 S/. 0.00 S/. 0.00
% AVANCE DE MES 28.64% 34.07% 37.30% 0.00% 0.00% 0.00%
% AVANCE ACUMULADO MENSUAL 28.64% 62.70% 100.00% 100.00% 100.00% 100.00%
GASTOS GENERALES 10.00% S/. 7,845.99 S/. 9,332.67 S/. 10,217.66 S/. 0.00 S/. 0.00 S/. 0.00
UTILIDAD 0.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
SUBTOTAL S/. 86,305.88 S/. 102,659.37 S/. 112,394.27 S/. 0.00 S/. 0.00 S/. 0.00
IGV (0.00%) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
TOTAL MENSUAL S/. 86,305.88 S/. 102,659.37 S/. 112,394.27 S/. 0.00 S/. 0.00 S/. 0.00
100% 100.00% 100.00% 100.00% 100.00%
90%
80%
70%
62.70%
60%
50%
40%
30% 28.64%
20%
10%
0% 0%
1 2 3 4 5 6 7
3. % AVANCE EJECUTADO – NOVIEMBRE
JULIO-AGOSTO 2023 AGOSTO-SETIEMBRE 2023 SETIEMBRE-OCTUBRE2023 OCTUBRE-NOV. 2023 NOV. -DICIEMBRE 2023
DESCRIPCIÓN
15 15 15 15 15 15 15 15 15 15
TOTAL COSTO DIRECTO DE OBRA (CD) S/. 26,668.22 S/. 19,882.93 S/. 61,180.67 S/. 43,380.47 S/. 0.00 S/. 0.00
% AVANCE DE MES 9.73% 7.26% 22.33% 15.83% 0.00% 0.00%
% AVANCE ACUMULADO MENSUAL 9.73% 16.99% 39.32% 55.16% 55.16% 55.16%
GASTOS GENERALES 10.00% S/. 2,666.82 S/. 1,988.29 S/. 6,118.07 S/. 4,338.05 S/. 0.00 S/. 0.00
UTILIDAD 0.00% S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
SUBTOTAL S/. 29,335.04 S/. 21,871.22 S/. 67,298.74 S/. 47,718.52 S/. 0.00 S/. 0.00
IGV (0.00%) S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
TOTAL MENSUAL S/. 29,335.04 S/. 21,871.22 S/. 67,298.74 S/. 47,718.52 S/. 0.00 S/. 0.00
100%
90%
80%
70%
60%
55.16% 55.16% 55.16%
50%
40% 39.32%
30%
20%
16.99%
10% 9.73%
0% 0%
1 2 3 4 5 6 7
4. CURVA “S” – PROGRAMADO VS EJECUTADO
5. REGISTRO FOTOGRAFICO – SEDIMENTADOR Y CANAL DE CONDUCCION
5.1 REGISTRO FOTOGRAFICO – COBERTURA METALICA
6. CONSIDERACIONES
CONSIDERACIONES TECNICAS DE LOS COMPONENTES:
CONCLUSIONES Y RECOMENDACIONES
- El proceso de construcción de la obra está desarrollando de acuerdo a los planos y especificaciones técnicas del proyecto en coordinación con la
gerencia y directorio.
- La construcción de la cobertura metálica tiene un avance físico del 20%, la obra se culminará el 27-12-2023,
- Se recomienda acelerar y reducir los tiempos en la entrega de materiales requeridos, con la finalidad de evitar retrasos en la obra.