CONSORCIO SUPERVISOR CUSCO

GOBIERNO REGIONAL DEL CUSCO


GERENCIA GENERAL REGIONAL

OFICINA DE SUPERVISIÓN, LIQUIDACIÓN Y TRANSFERENCIA DE


PROYECTOS DE INVERSIÓN

GRAFICO CURVA "S"

GRÁFICO DEL AVANCE FÍSICO PROGRAMADO VS. AVANCE FÍSICO EJECUTADO

Obra : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO Y PLANTA DE TRATAMIENTO DE LA CAPITAL DE COLQUEPATA,
DISTRITO DE COLQUEPATA - PAUCARTAMBO - CUSCO"

CONTRATISTA : CONSORCIO SANEAMIENTO COLQUEPATA


RESIDENTE : ING. ESTHER AQUINO PRADO
SUPERVISOR : ING. ENRIQUE SAUCEDO RUIZ

GRAFICO CURVA "S"


GRÁFICO DEL AVANCE FÍSICO PROGRAMADO VS. AVANCE FÍSICO EJECUTADO

100.00%
100%
99.23%
94.41%
90%
(%)

80% 83.58%
AVANCE MENSUAL ACUMULADO

70%
70.34%

60%

55.43%
50%

40%
37.95%

30%

23.50%
20%
PROGRAMADO EJECUTADO
12.31%
10%
5.98%
3.24%
0%
may-19 jun-19 jul-19 ago-19 sep-19 oct-19 nov-19 dic-19 ene-20 feb-20 mar-20

PLAZO DE EJECUCIÓN (270 dias calendarios)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (Sin IGV) PORCENTAJES MONTOS (Sin IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
ago-17 0.00 0.00 0.00% 0.00% ago-17 0.00 0.00 0.00% 0.00%
jun-19 535,615.13 535,615.13 3.24% 3.24% jun-19 987,666.63 987,666.63 5.98% 5.98%
jul-19 1,497,738.05 2,033,353.18 9.06% 12.31% jul-19 0.00
ago-19 1,850,459.76 3,883,812.94 11.20% 23.50% ago-19 0.00
sep-19 2,386,751.86 6,270,564.80 14.44% 37.95% sep-19 0.00
oct-19 2,889,464.32 9,160,029.12 17.49% 55.43% oct-19 0.00
nov-19 2,462,905.35 11,622,934.47 14.90% 70.34% nov-19 0.00
dic-19 2,187,446.00 13,810,380.46 13.24% 83.58% dic-19 0.00
ene-20 1,790,121.31 15,600,501.77 10.83% 94.41% ene-20 0.00
feb-20 797,162.04 16,397,663.81 4.82% 99.23% feb-20 0.00
mar-20 126,866.88 16,524,530.69 0.77% 100.00% mar-20 0.00

TOTAL 16,524,530.69 100.00% TOTAL 987,666.63 5.98%