% DE EJECUCION
% SOBRE
VALOR DEL VALOR EJECUTADO
% EJECUTADO SOBRE VALOR MESES PORCENTAJES
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR TOTAL ITEM (1) SOBRE VALOR TOTAL DEL ACUMULADOS
CONTRATO (3)
ITEM (4)=(3)/(1) CONTRATO PROG./EJECUT.
(1)/(2)
(5)=(3)/(2)
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8
P 0.40%
LOCALIZACIÓN Y REPLANTEO $ 500,000 $ 790,176 $ 500,000 $ 601,683
3.1.2 ML 1,125.58081 $ 2,391,859 0.40% $ 1,290,176 53.94% 0.22%
PARA REDES
E 0.22%
$ 741,816 $ 495,167 $ 53,193
P 5.21%
RELLENO TIPO 2 - RECEBO $ 6,216,741 $ 9,406,304 $ 7,000,000 $ 8,372,916
8.6.2 M3 522.94 $ 30,995,961 5.21% $ 15,623,045 50.40% 2.62%
COMUN
E 2.62%
$ 9,411,288 $ 5,731,650 $ 480,107
P 0.83%
$ 360,905 $ 4,576,266
10.1.4 CONCRETO CLASE II DE 3000 PSI M3 6.84 $ 4,937,171 0.83% $ 4,937,171 100.00% 0.83%
E 0.83%
$ 4,330,000 $ 607,171
P 4.06%
$ 4,000,000 $ 5,138,549 $ 8,171,794 $ 2,000,000 $ 4,828,900
9.00 ACERO DE REFUERZO PDR 60 KG 5,539.70 $ 24,139,243 4.06% $ 19,139,243 79.29% 3.22%
E 3.22%
$ 1,589,616 $ 6,399,773 $ 9,320,954 $ 1,828,900
P 0.00%
NP-1 EXCAVACION MANUAL EN COMUN M3 0.00 $ - 0.00% $0 #DIV/0! 0.00%
E 0.00%
P 12.70%
EXCAVACION MANUAL EN $ 17,000,000 $ 22,355,710 $ 8,756,910 $ 9,000,000 $ 18,499,833
NP-2 M3 1,298.04 $ 75,612,453 12.70% $ 58,112,620 76.86% 9.76%
CONGLOMERADO
E 9.76%
$ 26,983,726 $ 20,085,613 $ 1,043,281 $ 10,000,000
pagina 1 de 5
CÓDIGO: F42-PM-DPAT-02
PROCESO: DESARROLLO DE PROYECTOS
FECHA: 01-03-2014
% DE EJECUCION
% SOBRE
VALOR DEL VALOR EJECUTADO
% EJECUTADO SOBRE VALOR MESES PORCENTAJES
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR TOTAL ITEM (1) SOBRE VALOR TOTAL DEL ACUMULADOS
CONTRATO (3)
ITEM (4)=(3)/(1) CONTRATO PROG./EJECUT.
(1)/(2)
(5)=(3)/(2)
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8
P 3.64%
EXCAVACION MECANICA EN $ 9,000,000 $ 568,246 $ 8,000,000 $ 4,091,437
NP-3 M3 211.43 $ 21,659,683 3.64% $ 14,568,246 67.26% 2.45%
ROCA INCLUYE RETIRO
E 2.45%
$ 6,142,527 $ 3,425,719 $ 5,000,000
RECONSTRUCCION EN P 0.09%
$ 526,471
NP-6 PAVIMENTO RIGIDO CONCRETO M3 0.82 $ 526,471 0.09% $ 526,471 100.00% 0.09%
DE 21 MPA - 3000 PSI E 0.09%
$ 526,471
POZOS Y CAMARAS DE
INSPECCION CIRCULARES Y DE P 2.07%
CAIDA ALTURA ENTRE 2,01 Y 3,00 $ 4,000,000 $ 5,847,720 $ 2,461,930
NP-7 UN 5.00 $ 12,309,650 2.07% $ 12,309,650 100.00% 2.07%
M D. 1,20 M Y ESPESOR 0,25 M
(INCLUYE TAPA, CILINDRO, E 2.07%
$ 7,385,790 $ 2,461,930 $ 2,461,930
CAÑUELA Y PLACA FONDO)
P 0.00%
DESMONTE ADOQUIN $ 23,188
NP-8 M2 7.64 $ 23,188 0.00% $ 23,188 100.00% 0.00%
PREFABRICADO
E 0.00%
$ 23,188
PAVIMENTO EN ADOQUINES DE
CONCRETO TIPO 3 CLASICO P 0.16%
$ 945,574
DIMENSIONES LONGITUD 50 - 250
NP-9 M2 7.64 $ 945,574 0.16% $ 945,574 100.00% 0.16%
MM ANCHO 50 - 80 MM -
ESPESOR 60 - 100 MM según E 0.16%
norma NTC 2017 $ 945,574
P 0.47%
MANEJO DE AGUAS PARA $ 900,000 $ 110,593 $ 1,000,000 $ 792,500
NP-10 ML 2.00 $ 2,803,103 0.47% $ 1,810,593 64.59% 0.30%
REPOSICION TUBERIAS
E 0.30%
$ 1,010,592 $1 $ 800,000
P 0.69%
RETIRO DE TUBERIA EXISTENTE $ 600,000 $ 243,718 $ 2,500,000 $ 748,500
NP-11 ML 525.58 $ 4,092,298 0.69% $ 1,843,718 45.05% 0.31%
DE GRES 12"
E 0.31%
$ 843,718 $ 1,000,000
P 0.02%
$ 100,000 $ 33,875
NP-12 DEMOLICION DE POZOS UN 4.00 $ 133,875 0.02% $ 133,875 100.00% 0.02%
E 0.02%
$ 100,406 $ 33,469
P 0.36%
DEMOLICION PISOS ANDENES EN $ 100,000 $ 463,355 $ 1,577,394
NP-13 M3 6.84 $ 2,140,749 0.36% $ 2,140,749 100.00% 0.36%
CONCRETO
E 0.36%
$ 2,000,000 $ 140,749
COLECTOR ZONA DE EXPANSION $ 2,386,289 $ 1,961,099 $0 $0 $0 $0 $0
P 0.00%
LOCALIZACIÓN Y REPLANTEO $ 21,675
3.1.2 ML 10.20 $ 21,675 0.00% $ 21,675 100.00% 0.00%
PARA REDES
E 0.00%
$ 21,675
P 0.04%
RELLENO TIPO 2 - RECEBO $ 216,938
8.6.2 M3 3.66 $ 216,938 0.04% $ 216,938 0.04%
COMUN
E 0.04%
$ 216,938
pagina 2 de 5
CÓDIGO: F42-PM-DPAT-02
PROCESO: DESARROLLO DE PROYECTOS
FECHA: 01-03-2014
% DE EJECUCION
% SOBRE
VALOR DEL VALOR EJECUTADO
% EJECUTADO SOBRE VALOR MESES PORCENTAJES
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR TOTAL ITEM (1) SOBRE VALOR TOTAL DEL ACUMULADOS
CONTRATO (3)
ITEM (4)=(3)/(1) CONTRATO PROG./EJECUT.
(1)/(2)
(5)=(3)/(2)
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8
P 0.02%
LOCALIZACIÓN Y REPLANTEO DE $ 117,670
3.1.1 ml 28.00 $ 117,670 0.02% $ 117,670 100.00% 0.02%
ESTRUCTURAS
E 0.02%
$ 117,670
P 0.41%
RELLENO TIPO 3 - PROVENIENTE $ 2,424,831
8.6.3 m3 125.29 $ 2,424,831 0.41% $ 2,424,831 100.00% 0.41%
DE EXCAVACIÓN SELECCIONADO
E 0.41%
$ 2,424,831
P 1.17%
$ 6,985,856
9 ACERO DE REFUERZO PDR 60 kg 1,603.18 $ 6,985,856 1.17% $ 6,985,856 100.00% 1.17%
E 1.17%
$ 6,985,856
P 2.22%
CONCRETO CLASE I DE 4000 PSI $ 13,214,769
10.1.3 m3 16.84 $ 13,214,769 2.22% $ 13,214,769 100.00% 2.22%
IMPERMEABILIZADO
E 2.22%
$ 6,000,000 $ 7,214,769
P 0.00%
10.1.4 CONCRETO CLASE II DE 3000 PSI m3 - $ - 0.00% $0 #DIV/0! 0.00%
E 0.00%
P 0.07%
$ 441,455
10.1.6 CONCRETO CLASE IV DE 2000 PSI m3 0.85 $ 441,455 0.07% $ 441,455 100.00% 0.07%
E 0.07%
$ 441,455
P 0.23%
CINTA DE RETENCION DE AGUA $ 1,371,496
12.4 ml 26.90 $ 1,371,496 0.23% $ 1,371,496 100.00% 0.23%
0.22 M
E 0.23%
$ 1,371,496
P 1.13%
$ 6,752,749
12.3.1 COMPUERTA LATERAL D=400 MM un 1.00 $ 6,752,749 1.13% $0 0.00% 0.00%
E 0.00%
P 1.09%
$ 6,503,665
12.3.2 COMPUERTA LATERAL D=200 MM un 2.00 $ 6,503,665 1.09% $0 0.00% 0.00%
E 0.00%
P 1.35%
VASTAGO DE COLUMNA DE $ 8,031,653
12.5 un 6.00 $ 8,031,653 1.35% $0 0.00% 0.00%
MANIOBRA (10" - 16")
E 0.00%
P 0.26%
$ 1,561,290
12.6 COLUMNA DE MANIOBRA m3 2.00 $ 1,561,290 0.26% $0 0.00% 0.00%
E 0.00%
pagina 3 de 5
CÓDIGO: F42-PM-DPAT-02
PROCESO: DESARROLLO DE PROYECTOS
FECHA: 01-03-2014
% DE EJECUCION
% SOBRE
VALOR DEL VALOR EJECUTADO
% EJECUTADO SOBRE VALOR MESES PORCENTAJES
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR TOTAL ITEM (1) SOBRE VALOR TOTAL DEL ACUMULADOS
CONTRATO (3)
ITEM (4)=(3)/(1) CONTRATO PROG./EJECUT.
(1)/(2)
(5)=(3)/(2)
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8
P 0.00%
12.7 RUEDA DE MANEJO (10" - 16") m3 - $ - 0.00% $0 #DIV/0! 0.00%
E 0.00%
P 0.05%
$ 325,633
12.8 RUEDA DE MANEJO (6" - 8") m3 2.00 $ 325,633 0.05% $0 0.00% 0.00%
E 0.00%
P 0.06%
$ 375,633
12.9 GUIA DE VASTAGO m3 2.00 $ 375,633 0.06% $0 0.00% 0.00%
E 0.00%
P 0.28%
$ 1,695,888
12.10 SOPORTE GUIA DE VASTAGO m3 2.00 $ 1,695,888 0.28% $0 0.00% 0.00%
E 0.00%
P 0.26%
PASAMURO AL CARBON CLASE 40 $ 1,526,110
12.11 m3 2.00 $ 1,526,110 0.26% $ 1,526,110 100.00% 0.26%
EXTREMO LISO L=0,5M DE 6"
E 0.26%
$ 1,526,110
P 0.10%
SUMINISTRO E INSTALACIÓN $ 586,050
11.1.8 m3 10.00 $ 586,050 0.10% $ 586,050 100.00% 0.10%
TUBERIA PVC DE 4" RDE 21
E 0.10%
$ 586,050
P 0.00%
12.12 UNION TIPO DRESSER DE 6" HD Kg 0.00 $ - 0.00% $0 #DIV/0! 0.00%
E 0.00%
P 0.37%
EXCAVACION MANUAL EN $ 2,000,000 $ 219,151
NP-2 M3 47.62 $ 2,219,151 0.37% $ 2,219,151 100.00% 0.37%
MATERIAL COMUN
E 0.37%
$ 2,219,151
P 0.50%
VALVULA COMPUERTA CON $ 2,975,558
11.2.2 ML 6.00 $ 2,975,558 0.50% $ 2,975,558 100.00% 0.50%
SELLO DE BRONCE 150 PSI EB 2"
E 0.50%
$ 1,500,000 $ 1,475,558
P 0.33%
PASAMURO HD EXTREMO LISO L $ 1,000,000 $ 982,708
12.20 UN 3.00 $ 1,982,708 0.33% $ 1,982,708 100.00% 0.33%
<= 0.5 M. 4"
E 0.33%
$ 1,982,708
CAMARA DE QUIEBRE DE 3"
P 0.01%
LOCALIZACIÓN Y REPLANTEO $ 51,481
3.1.1 M2 12.25 $ 51,481 0.01% $ 51,481 100.00% 0.01%
PARA ESTRUCTURAS
E 0.01%
$ 51,481
P
0.47%
$ 2,807,836
10.1.4 CONCRETO CLASE II DE 3000 PSI M3 3.89 $ 2,807,836 0.47% $ 2,807,836 100.00% 0.47%
E
0.47%
$ 2,807,836
P 0.29%
$ 1,753,894
9.0 ACERO DE REFUERZO PDR 60 KG 402.50 $ 1,753,894 0.29% $ 1,753,894 100.00% 0.29%
E 0.29%
$ 1,753,894
P 0.11%
PASAMURO HD EXTREMO LISO L $ 660,903
12.20 UN 1.00 $ 660,903 0.11% $ 660,903 100.00% 0.11%
<= 0.5 M. 4"
E 0.11%
$ 660,903
pagina 4 de 5
CÓDIGO: F42-PM-DPAT-02
PROCESO: DESARROLLO DE PROYECTOS
FECHA: 01-03-2014
% DE EJECUCION
% SOBRE
VALOR DEL VALOR EJECUTADO
% EJECUTADO SOBRE VALOR MESES PORCENTAJES
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR TOTAL ITEM (1) SOBRE VALOR TOTAL DEL ACUMULADOS
CONTRATO (3)
ITEM (4)=(3)/(1) CONTRATO PROG./EJECUT.
(1)/(2)
(5)=(3)/(2)
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8
P 0.00%
VALVULA DE CIERRE CON
13.6 UN 0.00 $ - 0.00% $0 #DIV/0! 0.00%
FLOTADOR 4"
E 0.00%
P 0.04%
$ 221,319
13.9 CINTA CON PVC - V15 UN 5.40 $ 221,319 0.04% $ 221,319 100.00% 0.04%
E 0.04%
$ 221,319
OBRA DE REDES DE DISTRIBUCION
P 0.12%
LOCALIZACIÓN Y REPLANTEO DE $ 701,250
3.1.2 ML 330.00 $ 701,250 0.12% $ 701,250 100.00% 0.12%
REDES
E 0.12%
$ 624,750 $ 76,500
P 0.17%
RELLENO TIPO 3 - PROVENIENTE $ 1,021,878
8.6.3 M3 52.80 $ 1,021,878 0.17% $ 1,021,878 100.00% 0.17%
DE EXCAVACIÓN SELECCIONADO
E 0.17%
$ 910,400 $ 111,478
P 0.52%
SUMINISTRO E INSTALACIÓN $ 3,097,463
11.1.10 ML 330.00 $ 3,097,463 0.52% $ 3,097,463 100.00% 0.52%
TUBERÍA PVC 2" RDE 21
E 0.52%
$ 2,759,558 $ 337,905
P 0.83%
VALVULA COMPUERTA CON $ 4,959,263
11.2.2 ML 10.00 $ 4,959,263 0.83% $ 4,959,263 100.00% 0.83%
SELLO DE BRONCE 150 PSI EB 2"
E 0.83%
$ 4,959,263
P 0.90%
EXCAVACION MANUAL EN $ 5,382,415
NP-3 M3 92.40 $ 5,382,415 0.90% $ 5,382,415 100.00% 0.90%
CONGLOMERADO
E 0.90%
$ 4,795,243 $ 587,172
PORCENTAJE % 0.08% 23.85% 48.80% 57.59% 61.72% 67.48% 83.37% 100.00% 100.00%
PROGRAMADO:
VALOR MENSUAL $ $ - $ 165,798,464 $ 134,021,979 $ 44,265,158 $ 32,107,670 $ 13,700,142 $ 46,298,651 $ -
EJECUTADO:
$ 436,192,064
OBRA EJECUTADA VALOR ACUMULADO $ $ - $ 165,798,464 $ 299,820,443 $ 344,085,601 $ 376,193,271 $ 389,893,413 $ 436,192,064 $ 436,192,064
PORCENTAJE % 0.00% 27.85% 50.37% 57.81% 63.20% 65.50% 73.28% 73.28% 73.28%
Responsable:
pagina 5 de 5