CRONOGRAMA VALORIZADO

OBRA MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC-SEGUNDA ETAPA

ENTIDAD MUNICIPALIDAD PROVINCIAL DE ANDAHUAYLAS


UBICACIÓN APURIMAC - ANDAHUAYLAS - ANDAHUAYLAS

MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC- MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
SEGUNDA ETAPA
INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN
Item
Descripción de Actividades Und. Metrado Precio (S/.) Parcial (S/.) 4/10/2023 4/30/2023 5/1/2023 5/31/2023 6/1/2023 6/30/2023 7/1/2023 7/31/2023 8/1/2023 8/31/2023 9/1/2023 9/6/2023
S/. % S/. % S/. % S/. % S/. % S/. %
1 MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY 1,452,935.34

1.1 MEJORAMIENTO DE LA TRANSITAVILIDAD VEHICULAR Y PEATONAL DEL JIRON SANTA TERESA


1,452,935.34

1.1.1 COMPONENTE 01 TRANSITABILIDAD VEHICULAR 1,300,352.97


1.1.1.1 OBRAS PROVISIONALES 4,384.56
1.1.1.1.1 CARTEL DE IDENTIFICACION DE OBRA DE 3.60x 2.40m. und 1.00 1064.56 1,064.56 S/ 1,064.56 100% 0% 0% 0.00% 0.00% 0.00%
1.1.1.1.2 CAMPAMENTO Y ALMACEN DE OBRA PROVISIONAL mes 4.00 500.00 2,000.00 S/ 300.00 15% S/ 400.00 20% S/ 400.00 20% S/ 400.00 20.00% S/ 400.00 20.00% S/ 100.00 5.00%
1.1.1.1.3 SUMINISTRO DE AGUA PARA LA CONSTRUCCION mes 4.00 80.00 320.00 S/ 48.00 15% S/ 64.00 20% S/ 64.00 20% S/ 64.00 20.00% S/ 64.00 20.00% S/ 16.00 5.00%
1.1.1.1.4 SUMINISTRO DE ENERGIA ELECTRICA PARA LA CONSTRUCCION mes 4.00 250.00 1,000.00 S/ 150.00 15% S/ 200.00 20% S/ 200.00 20% S/ 200.00 20.00% S/ 200.00 20.00% S/ 50.00 5.00%
1.1.1.2 TRABAJOS PRELIMINARES 6,898.57 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.2.1 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 4200.00 4,200.00 S/ 4,200.00 100% 0% 0% 0.00% 0.00% 0.00%
1.1.1.2.2 TRAZO Y REPLANTEO INICIAL DEL PROYECTO m² 1752.32 0.72 1,261.67 S/ 1,261.67 100% 0% 0% 0.00% 0.00% 0.00%
1.1.1.2.3 LIMPIEZA DE TERRENO INICIAL m² 1752.32 0.82 1,436.90 S/ 1,436.90 100% 0% 0% 0.00% 0.00% 0.00%
1.1.1.3 MOVIMIENTO DE TIERRAS 60,806.29 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.3.1 CORTE DE MATERIAL NO CLASIFICADO A NIVEL DE SUB RASANTE m³ 1829.21 10.06 18,401.85 S/ 12,267.90 67% S/ 6,133.95 33% 0% 0.00% 0.00% 0.00%
1.1.1.3.2 ELIMINACIÓN DE MATERIAL CON MAQUINARIA DM=15KM m³ 2286.52 14.43 32,994.48 S/ 21,996.32 67% S/ 10,998.16 33% 0% 0.00% 0.00% 0.00%
1.1.1.3.3 PERFILADO Y COMPACTADO DE LA SUB RASANTE EN ZONAS DE CORTE m² 1752.32 5.37 9,409.96 0% 0% 0% S/ 9,409.96 100.00% 0.00% 0.00%
1.1.1.4 REUBICACION DE POSTE DE ENERGIA ELECTRICA 4,774.71 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.4.1 DEMOLICION DE CONCRETO CICLOPEO EN CIEMIENTO DE POSTES und 9.00 54.93 494.37 0% S/ 494.37 100% 0% 0.00% 0.00% 0.00%
1.1.1.4.2 EXCAVACION DE ZANJA HASTA H= 1.00m. m³ 4.52 27.47 124.16 0% S/ 124.16 100% 0% 0.00% 0.00% 0.00%
1.1.1.4.3 REUBICACION DE POSTE DE ILUMINACION und 9.00 400.00 3,600.00 0% S/ 3,600.00 100% 0% 0.00% 0.00% 0.00%
1.1.1.4.4 CONCRETO MEZCLA C-H 1:8 + 30% PM EN CIMIENTO DE POSTES m³ 1.77 293.65 519.76 0% S/ 519.76 100% 0% 0.00% 0.00% 0.00%
1.1.1.4.5 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m.) m³ 2.21 16.48 36.42 0% S/ 36.42 100% 0% 0.00% 0.00% 0.00%
1.1.1.5 OBRAS SANITARIAS 67,386.06 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.1 REPOSICION DE SISTEMA DE AGUA 25,681.35 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.1 DESMONTAJE DE CONEXIONES DOMICILIARIAS DE AGUA POTABLE 1,792.25 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.1.1 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 21.93 27.47 602.42 0% S/ 602.42 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.1.2 DESMONTAJE DE TUBERIA PVC m 73.10 2.75 201.03 0% S/ 201.03 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.1.3 DESMONTAJE DE CAJAS DE AGUA POTABLE und 30.00 32.96 988.80 0% S/ 988.80 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2 CONEXIONES DOMICILIARIAS DE AGUA 23,889.10 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 36.55 1.45 53.00 0% S/ 53.00 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.2 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 7.31 27.47 200.81 0% S/ 200.81 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.3 REFINE NIVELACIÓN Y CONFORMACIÓN DE FONDOS m 36.55 3.30 120.62 0% S/ 120.62 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.4 CAMA DE APOYO PARA TUBERIA m 73.10 15.12 1,105.27 0% S/ 1,105.27 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.5 RED DE DISTRIBUCION SUM. E INST. TUB. PVC C-10 SDR 21 DE 3/4" m 73.10 11.79 861.85 0% S/ 861.85 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.6 EMPALME DE TUBERIA PVC SAP DE 3/4" A RED MATRIZ DE AGUA und 43.00 491.37 21,128.91 0% S/ 21,128.91 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.1.2.7 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO m³ 21.93 19.09 418.64 0% S/ 418.64 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2 RED DE DESAGUE 30,190.34 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.1 DESMONTAJE DE CONEXIONES DOMICILIARIAS DE DESAGUE 3,115.56 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.1.1 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 58.05 27.47 1,594.63 0% S/ 1,594.63 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.1.2 DESMONTAJE DE TUBERIA PVC m 193.50 2.75 532.13 0% S/ 532.13 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.1.3 DESMONTAJE DE CAJAS DE DESAGUE und 30.00 32.96 988.80 0% S/ 988.80 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2 REPOSICION E INSTALACION NUEVA DE CONEX. DOMIC. DESAGUE 18,829.72 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 96.75 1.45 140.29 0% S/ 140.29 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.2 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 19.35 27.47 531.54 0% S/ 531.54 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.3 REFINE NIVELACIÓN Y CONFORMACIÓN DE FONDOS m 96.75 3.30 319.28 0% S/ 319.28 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.4 CAMA DE APOYO PARA TUBERIA m 193.50 15.12 2,925.72 0% S/ 2,925.72 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.5 CONEXIÓN DOMICILIARIA CON TUBERIA PVC SAL DE 4" und 43.00 255.18 10,972.74 0% S/ 10,972.74 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.6 EMPALME DE TUBERIA PVC SAL DE 4" und 43.00 65.86 2,831.98 0% S/ 2,831.98 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.2.7 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO m³ 58.05 19.09 1,108.17 0% S/ 1,108.17 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3 BUZONES DE DESAGUE 8,245.06 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.1 TRAZO, NIVELES Y REPLANTEO m² 10.62 1.45 15.40 0% S/ 15.40 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.2 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 4.25 27.47 116.75 0% S/ 116.75 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.3 ELIMINACIÓN DE MATERIAL EXCEDENTE DIST. APROX. DE 50m m³ 5.31 16.48 87.51 0% S/ 87.51 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.4 ACERO DE REFUERZO F'y=4200kg/cm2 kg 240.86 9.22 2,220.73 0% S/ 2,220.73 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.5 ENCOFRADO Y DESENCOFRADO EN PAREDES DE BUZONES m² 4.80 45.59 218.83 0% S/ 218.83 100% 0% 0.00% 0.00% 0.00%
CRONOGRAMA VALORIZADO
OBRA MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC-SEGUNDA ETAPA

ENTIDAD MUNICIPALIDAD PROVINCIAL DE ANDAHUAYLAS


UBICACIÓN APURIMAC - ANDAHUAYLAS - ANDAHUAYLAS

MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC- MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
SEGUNDA ETAPA
INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN
Item
Descripción de Actividades Und. Metrado Precio (S/.) Parcial (S/.) 4/10/2023 4/30/2023 5/1/2023 5/31/2023 6/1/2023 6/30/2023 7/1/2023 7/31/2023 8/1/2023 8/31/2023 9/1/2023 9/6/2023
1.1.1.5.2.3.6 ENCOFRADO Y DESENCOFRADO EN LOSA DE BUZONES m² 11.03 55.25 609.41 0% 0% 0% S/ 304.71 50.00% S/ 304.71 50.00% 0.00%
1.1.1.5.2.3.7 CONCRETO F'c=175 KG/CM2, EN BUZONES m³ 3.02 410.23 1,238.89 0% S/ 1,238.89 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.2.3.8 CONCRETO F'C=210 KG/CM2, EN LOSA DE BUZON m³ 1.33 487.11 647.86 0% 0% 0% S/ 323.93 50.00% S/ 323.93 50.00% 0.00%
1.1.1.5.2.3.9 CURADO DE CONCRETO m² 51.74 0.70 36.22 0% 0% 0% S/ 18.11 50.00% S/ 18.11 50.00% 0.00%
1.1.1.5.2.3.10 COLOCACIÓN DE TAPA DE FIERRO FUNDIDO P/BUZONES und 6.00 481.19 2,887.14 0% 0% 0% S/ 1,443.57 50.00% S/ 1,443.57 50.00% 0.00%
1.1.1.5.2.3.11 SOLAQUEADO DE BUZONES m² 4.80 34.65 166.32 0% S/ 166.32 100% 0% 0.00% 0.00% 0.00%
1.1.1.5.3 SISTEMA DE AGUAS PLUVIALES 11,514.37 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.3.1 CUNETA TRIANGULAR DE EVACUACION DE AGUAS PLUVIALES 11,514.37 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.5.3.1.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 172.55 1.45 250.20 0% 0% 0% 0.00% S/ 250.20 100.00% 0.00%
1.1.1.5.3.1.2 EXCAVACION DE ZANJA EN TERRENO NORMAL m³ 17.25 27.47 473.86 0% 0% 0% 0.00% S/ 473.86 100.00% 0.00%
1.1.1.5.3.1.3 NIVELADO Y COMPACTADO CON EQUIPO LIVIANO m² 345.09 3.12 1,076.68 0% 0% 0% 0.00% S/ 1,076.68 100.00% 0.00%
1.1.1.5.3.1.4 ELIMINACIÓN DE MATERIAL EXCEDENTE DIST. APROX. DE 50m m³ 21.57 16.48 355.47 0% 0% 0% 0.00% S/ 355.47 100.00% 0.00%
1.1.1.5.3.1.5 ENCOFRADO Y DESENCOFRADO m² 3.95 55.25 218.24 0% 0% 0% 0.00% S/ 218.24 100.00% 0.00%
1.1.1.5.3.1.6 CONCRETO f'c 210 kg/cm2 EN CUNETA TRIANGULAR m³ 17.78 487.11 8,660.82 0% 0% 0% 0.00% S/ 8,660.82 100.00% 0.00%
1.1.1.5.3.1.7 CURADO DE CONCRETO m² 172.55 1.70 293.34 0% 0% 0% 0.00% S/ 293.34 100.00% 0.00%
1.1.1.5.3.1.8 SELLADO DE JUNTAS m 19.17 9.69 185.76 0% 0% 0% 0.00% S/ 185.76 100.00% 0.00%
1.1.1.6 MUROS DE CONTENCIÓN DE CONCRETO ARMADO 705,630.32 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.6.1 TRAZO, NIVELES Y REPLANTEO EN MURO DE CONTENCION m² 404.14 1.46 590.04 S/ 590.04 100% 0% 0% 0.00% 0.00% 0.00%
1.1.1.6.2 CORTE DE MATERIAL SUELTO m³ 1849.95 10.06 18,610.50 S/ 12,321.43 66% S/ 6,289.07 34% 0% 0.00% 0.00% 0.00%
1.1.1.6.3 RELLENO Y COMPACTACION CON MATERIAL PRESTAMO m³ 1500.84 43.75 65,661.75 0% 0% S/ 65,661.75 100% 0.00% 0.00% 0.00%
1.1.1.6.4 ELIMINACIÓN DE MATERIAL CON MAQUINARIA DM=25KM m³ 2312.44 10.45 24,165.00 S/ 15,998.89 66% S/ 8,166.11 34% 0% 0.00% 0.00% 0.00%
1.1.1.6.5 CONCRETO PARA SOLADO F'C=100KG/CM2 m² 404.14 40.44 16,343.42 0% S/ 13,560.01 83% S/ 2,783.41 17% 0.00% 0.00% 0.00%
1.1.1.6.6 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION m² 1254.74 113.00 141,785.62 0% S/ 66,639.24 47% S/ 75,146.38 53% 0.00% 0.00% 0.00%
1.1.1.6.7 CONCRETO EN MUROS REFORZADOS F'C=210 KG/CM2 m³ 429.28 461.00 197,898.08 0% S/ 89,054.14 45% S/ 108,843.94 55% 0.00% 0.00% 0.00%
1.1.1.6.8 ACERO EN MUROS REFORZADOS GRADO 60 kg 26641.85 9.03 240,575.91 0% S/ 144,345.55 60% S/ 96,230.36 40% 0.00% 0.00% 0.00%
1.1.1.7 SARDINELES 15,543.67 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.7.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 73.30 1.46 107.02 0% 0% 0% S/ 71.35 66.67% S/ 35.67 33.33% 0.00%
1.1.1.7.2 EXCAVACIÓN MANUAL DE MATERIAL SUELTO m³ 18.33 27.47 503.53 0% 0% 0% S/ 335.69 66.67% S/ 167.84 33.33% 0.00%
1.1.1.7.3 ELIMINACIÓN DE MATERIAL EXCEDENTE DIST. APROX. 50m m³ 22.91 16.48 377.56 0% 0% 0% S/ 251.71 66.67% S/ 125.85 33.33% 0.00%
1.1.1.7.4 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m² 29.32 56.27 1,649.84 0% 0% 0% S/ 1,099.89 66.67% S/ 549.95 33.33% 0.00%
1.1.1.7.5 CONCRETO F'c=175 KG/CM2, EN SARDINELES m³ 29.32 410.23 12,027.94 0% 0% 0% S/ 8,018.63 66.67% S/ 4,009.31 33.33% 0.00%
1.1.1.7.6 CURADO DE CONCRETO m² 219.91 0.70 153.94 0% 0% 0% S/ 102.63 66.67% S/ 51.31 33.33% 0.00%
1.1.1.7.7 SELLADO DE JUNTAS CON ASFALTO m 74.70 9.69 723.84 0% 0% 0% 0.00% S/ 723.84 100.00% 0.00%
1.1.1.8 PAVIMENTO 359,099.98 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.8.1 MEJORAMIENTO DE SUB_RASANTE 25,776.71 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.8.1.1 EXTRACCION Y APILAMIENTO DE MATERIAL PARA SUB RASANTE m³ 525.00 15.06 7,906.50 0% 0% S/ 1,581.30 20% S/ 6,325.20 80.00% 0.00% 0.00%
1.1.1.8.1.2 CARGUIO Y TRANSPORTE DE MATERIAL PARA SUB RASANTE m³ 525.00 12.51 6,567.75 0% 0% S/ 1,313.55 20% S/ 5,254.20 80.00% 0.00% 0.00%
1.1.1.8.1.3 MATERIAL PARA SUB RASANTE MEJORADA E=0.25m (FACT. COMPACT.=1.20) m² 1752.32 6.45 11,302.46 0% 0% S/ 1,257.12 11% S/ 10,045.34 88.88% 0.00% 0.00%
1.1.1.8.2 SUB - BASE GRANULAR E=0.20m. 25,608.29 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.8.2.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 1752.32 1.46 2,558.39 0% 0% 0% S/ 2,558.39 100.00% 0.00% 0.00%
1.1.1.8.2.2 EXTRACCION Y APILAMIENTO DE MATERIAL PARA SUB BASE m³ 350.46 15.06 5,277.93 0% 0% 0% S/ 5,277.93 100.00% 0.00% 0.00%
1.1.1.8.2.3 CARGUIO Y TRANSPORTE DE MATERIAL PARA SUB BASE m³ 350.46 12.51 4,384.25 0% 0% 0% S/ 4,384.25 100.00% 0.00% 0.00%
1.1.1.8.2.4 SUB - BASE GRANULAR E=0.20m (FACT. COMPACT.=1.20) m² 1752.32 6.45 11,302.46 0% 0% 0% S/ 11,302.46 100.00% 0.00% 0.00%
1.1.1.8.2.5 RIEGO m² 1752.32 1.19 2,085.26 0% 0% 0% S/ 2,085.26 100.00% 0.00% 0.00%
1.1.1.8.3 PAVIMENTO RIGIDO 307,714.98 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.8.3.1 SUMINISTRO Y COLOCACIÓN DE DOWELLS 1", L=0.41 m, @0.30 m und 480.00 26.93 12,926.40 0% 0% 0% S/ 3,877.92 30.00% S/ 9,048.48 70.00% 0.00%
1.1.1.8.3.2 BARRAS DE AMARRE CORRUGADO 1/2", L=0.76m @0.76m kg 241.74 24.47 5,915.38 0% 0% 0% S/ 1,774.61 30.00% S/ 4,140.77 70.00% 0.00%
1.1.1.8.3.3 ENCOFRADO Y DESENCOFRADO NORMAL m² 77.24 69.61 5,376.68 0% 0% 0% S/ 1,613.00 30.00% S/ 3,763.68 70.00% 0.00%
1.1.1.8.3.4 CONCRETO F'c=210kg/cm2 CON FIBRA METALICA, E=20 cm m³ 350.46 756.31 265,056.40 0% 0% 0% S/ 79,516.92 30.00% S/ 185,539.48 70.00% 0.00%
1.1.1.8.3.5 CURADO DE CONCRETO m² 1752.32 1.70 2,978.94 0% 0% 0% S/ 893.68 30.00% S/ 2,085.26 70.00% 0.00%
1.1.1.8.3.6 CORTE TEMPRANO m 291.23 14.89 4,336.41 0% 0% 0% 0.00% S/ 4,336.41 100.00% 0.00%
1.1.1.8.3.7 CORTE INTERMEDIO m 291.23 8.13 2,367.70 0% 0% 0% 0.00% S/ 2,367.70 100.00% 0.00%
1.1.1.8.3.8 SELLADO DE JUNTAS m 675.70 12.96 8,757.07 0% 0% 0% 0.00% S/ 8,757.07 100.00% 0.00%
1.1.1.9 SEÑALIZACION VIAL Y PINTADO 9,779.19 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.9.1 SEÑALES INFORMATIVAS und 1.00 646.60 646.60 0% 0% 0% 0.00% 0.00% S/ 646.60 100.00%
1.1.1.9.2 PINTADO DE EJE VIAL m 102.00 4.12 420.24 0% 0% 0% 0.00% 0.00% S/ 420.24 100.00%
1.1.1.9.3 PINTADO DE CRUCES PEATONALES Y OTRAS MARCAS m² 43.60 16.74 729.86 0% 0% 0% 0.00% 0.00% S/ 729.86 100.00%
CRONOGRAMA VALORIZADO
OBRA MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC-SEGUNDA ETAPA

ENTIDAD MUNICIPALIDAD PROVINCIAL DE ANDAHUAYLAS


UBICACIÓN APURIMAC - ANDAHUAYLAS - ANDAHUAYLAS

MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC- MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
SEGUNDA ETAPA
INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN
Item
Descripción de Actividades Und. Metrado Precio (S/.) Parcial (S/.) 4/10/2023 4/30/2023 5/1/2023 5/31/2023 6/1/2023 6/30/2023 7/1/2023 7/31/2023 8/1/2023 8/31/2023 9/1/2023 9/6/2023
1.1.1.9.4 PINTADO DE SARDINELES LONGITUDINALES m² 511.37 15.61 7,982.49 0% 0% 0% 0.00% 0.00% S/ 7,982.49 100.00%
1.1.1.10 ENSAYO Y CONTROL DE CALIDAD 13,520.00 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.10.1 DISEÑO DE MEZCLAS DE CONCRETO und 2.00 350.00 700.00 0% S/ 700.00 100% 0% 0.00% 0.00% 0.00%
1.1.1.10.2 PRUEBA COMPACTACION SUELOS(PROCTOR MODIFICADO DENSIDAD CAMPO und 4.00 150.00 600.00 0% 0% 0% S/ 600.00 100.00% 0.00% 0.00%
1.1.1.10.3 ESTUDIO DE CANTERAS und 2.00 800.00 1,600.00 0% S/ 1,600.00 100% 0% 0.00% 0.00% 0.00%
1.1.1.10.4 ENSAYO DE COMPRESIÓN SIMPLE DE CONCRETO und 4.00 30.00 120.00 0% 0% S/ 60.00 50% S/ 30.00 25.00% S/ 30.00 25.00% 0.00%
1.1.1.10.5 ENSAYO DE DENSIDAD DE CAMPO (BASE Y SUB BASE) und 14.00 750.00 10,500.00 0% 0% S/ 1,792.50 17% S/ 8,707.50 82.93% 0.00% 0.00%
1.1.1.11 SEGURIDAD Y SALUD 51,303.00 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.11.1 ELABORACION E IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO 34,362.00 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.11.1.1 EQUIPOS DE PROTECCION INDIVIDUAL gbl 1.00 23241.00 23,241.00 S/ 3,486.15 15% S/ 4,648.20 20% S/ 4,648.20 20% S/ 4,648.20 20.00% S/ 4,648.20 20.00% S/ 1,162.05 5.00%
1.1.1.11.1.2 EQUIPOS DE PROTECCION COLECTIVA gbl 1.00 1156.00 1,156.00 S/ 173.40 15% S/ 231.20 20% S/ 231.20 20% S/ 231.20 20.00% S/ 231.20 20.00% S/ 57.80 5.00%
1.1.1.11.1.3 SEÑALIZACION TEMPORAL DE SEGURIDAD und 1.00 465.00 465.00 S/ 69.75 15% S/ 93.00 20% S/ 93.00 20% S/ 93.00 20.00% S/ 93.00 20.00% S/ 23.25 5.00%
1.1.1.11.1.4 CAPACITACION EN SEGURIDAD Y SALUD gbl 1.00 9500.00 9,500.00 S/ 1,425.00 15% S/ 1,900.00 20% S/ 1,900.00 20% S/ 1,900.00 20.00% S/ 1,900.00 20.00% S/ 475.00 5.00%
1.1.1.11.2 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO 16,941.00 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.11.2.1 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO gbl 1.00 2258.00 2,258.00 S/ 338.70 15% S/ 451.60 20% S/ 451.60 20% S/ 451.60 20.00% S/ 451.60 20.00% S/ 112.90 5.00%
1.1.1.11.2.2 INSUMOS PARA EL CUMPLIMIENTO DEL PLAN PARA LA VIGILANCIA, PREVENCIÓN Y CONTROL DE COVID -19 EN gbl 1.00 14163.00 14,163.00 S/ 2,124.45 15% S/ 2,832.60 20% S/ 2,832.60 20% S/ 2,832.60 20.00% S/ 2,832.60 20.00% S/ 708.15 5.00%
EL TRABAJO
1.1.1.11.2.3 SEÑALIZACION DE PREVENCION COVID-19 gbl 1.00 520.00 520.00 S/ 78.00 15% S/ 104.00 20% S/ 104.00 20% S/ 104.00 20.00% S/ 104.00 20.00% S/ 26.00 5.00%
1.1.1.12 MITIGACION DE IMPACTO AMBIENTAL 1,226.62 0% 0% 0% 0.00% 0.00% 0.00%
1.1.1.12.1 MITIGACIÓN DE IMPACTO AMBIENTAL m² 1752.32 0.70 1,226.62 S/ 183.99 15% S/ 245.32 20% S/ 245.32 20% S/ 245.32 20.00% S/ 245.32 20.00% S/ 61.33 5.00%
1.1.2 COMPONENTE 02 TRANSITABILIDAD PEATONAL 152,582.37 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1 VEREDAS,RAMPAS,GRADAS 151,830.45 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1.1 VEREDAS DE CONCRETO SIMPLE 57,106.45 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1.1.1 DEMOLICIÓN DE VEREDAS EXISTENTES m² 153.80 8.24 1,267.31 S/ 633.66 50% S/ 633.66 50% 0% 0.00% 0.00% 0.00%
1.1.2.1.1.2 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 405.49 1.46 592.02 0% 0% 0% S/ 592.02 100.00% 0.00% 0.00%
1.1.2.1.1.3 CONFORMACION DE BASE PARA VEREDAS m² 405.49 6.51 2,639.74 0% 0% 0% S/ 2,375.77 90.00% S/ 263.97 10.00% 0.00%
1.1.2.1.1.4 EMPEDRADO EN VEREDAS m² 405.49 42.17 17,099.51 0% 0% 0% S/ 11,586.76 67.76% S/ 5,512.75 32.24% 0.00%
1.1.2.1.1.5 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m² 23.64 13.09 309.45 0% 0% 0% S/ 207.33 67.00% S/ 102.12 33.00% 0.00%
1.1.2.1.1.6 CONCRETO F'c=175KG/CM2, EN VEREDAS INCL. BRUÑADO m³ 50.95 476.36 24,270.54 0% 0% 0% S/ 16,261.26 67.00% S/ 8,009.28 33.00% 0.00%
1.1.2.1.1.7 SELLADO DE JUNTAS m 157.60 9.69 1,527.14 0% 0% 0% 0.00% S/ 1,527.14 100.00% 0.00%
1.1.2.1.1.8 BRUÑADO EN VEREDAS C/3.60m und 1245.13 7.27 9,052.10 0% 0% 0% S/ 6,064.91 67.00% S/ 2,987.19 33.00% 0.00%
1.1.2.1.1.9 CURADO DE CONCRETO m² 498.05 0.70 348.64 0% 0% 0% S/ 233.59 67.00% S/ 115.05 33.00% 0.00%
1.1.2.1.2 VEREDAS DE CONCRETO ARMADO 66,644.23 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1.2.1 ENCOFRADO Y DESENCOFRADO m² 125.41 55.25 6,928.90 0% 0% S/ 4,619.27 67% S/ 2,309.63 33.33% 0.00% 0.00%
1.1.2.1.2.2 CONCRETO F'C=210 KG/CM2 m³ 18.90 487.11 9,206.38 0% 0% S/ 6,137.59 67% S/ 3,068.79 33.33% 0.00% 0.00%
1.1.2.1.2.3 ACERO GRADO 60 kg 2977.27 9.22 27,450.43 0% 0% S/ 18,300.28 67% S/ 9,150.15 33.33% 0.00% 0.00%
1.1.2.1.2.4 BARANDA METALICA DE F°G° DE 2", H=1.00m SEGUN DISEÑO m 114.01 202.25 23,058.52 0% 0% 0% 0.00% S/ 11,529.26 50.00% S/ 11,529.26 50.00%
1.1.2.1.3 GRADAS 26,265.14 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1.3.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 4.42 1.46 6.45 0% 0% 0% S/ 6.45 100.00% 0.00% 0.00%
1.1.2.1.3.2 EXCAVACIÓN MANUAL DE MATERIAL SUELTO m³ 0.88 27.47 24.17 0% 0% 0% S/ 24.17 100.00% 0.00% 0.00%
1.1.2.1.3.3 NIVELADO Y COMPACTADO DE FONDO DE RAMPAS m² 2.84 3.12 8.86 0% 0% 0% S/ 8.86 100.00% 0.00% 0.00%
1.1.2.1.3.4 ENCOFRADO Y DESENCOFRADO EN GRADAS m² 7.66 55.25 423.22 0% 0% 0% S/ 423.22 100.00% 0.00% 0.00%
1.1.2.1.3.5 CONCRETO F'c=175KG/CM2 EN GRADAS m³ 2.31 436.68 1,008.73 0% 0% 0% S/ 1,008.73 100.00% 0.00% 0.00%
1.1.2.1.3.6 CURADO DE CONCRETO m² 2.31 1.70 3.93 0% 0% 0% S/ 3.93 100.00% 0.00% 0.00%
1.1.2.1.3.7 BARANDA METALICA DE F°G° DE 2", H=1.00m SEGUN DISEÑO m 122.57 202.25 24,789.78 0% 0% 0% 0.00% S/ 12,394.89 50.00% S/ 12,394.89 50.00%
1.1.2.1.4 RAMPAS PARA VIVIENDAS Y DISCAPACITADOS 1,814.63 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.1.4.1 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m² 15.06 1.46 21.99 0% 0% 0% S/ 21.99 100.00% 0.00% 0.00%
1.1.2.1.4.2 EXCAVACIÓN MANUAL DE MATERIAL SUELTO m³ 2.26 27.47 62.08 0% 0% 0% S/ 62.08 100.00% 0.00% 0.00%
1.1.2.1.4.3 NIVELADO Y COMPACTADO DE FONDO DE RAMPAS m² 15.06 3.12 46.99 0% 0% 0% S/ 46.99 100.00% 0.00% 0.00%
1.1.2.1.4.4 EMPEDRADO EN RAMPAS E=4" m² 15.06 42.17 635.08 0% 0% 0% S/ 635.08 100.00% 0.00% 0.00%
1.1.2.1.4.5 ENCOFRADO Y DESENCOFRADO EN RAMPAS m 3.90 13.09 51.05 0% 0% 0% S/ 51.05 100.00% 0.00% 0.00%
1.1.2.1.4.6 CONCRETO F'c=175KG/CM2 EN RAMPAS INCL. BRUÑADO m³ 2.26 436.68 986.90 0% 0% 0% S/ 986.90 100.00% 0.00% 0.00%
1.1.2.1.4.7 CURADO DE CONCRETO m² 15.06 0.70 10.54 0% 0% 0% S/ 10.54 100.00% 0.00% 0.00%
1.1.2.2 AREAS VERDES 751.92 0% 0% 0% 0.00% 0.00% 0.00%
1.1.2.2.1 EXCAVACION MANUAL DE MATERIAL SUELTO m³ 1.51 32.96 49.77 0% 0% 0% 0.00% S/ 49.77 100.00% 0.00%
1.1.2.2.2 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA (50m.) m³ 1.89 27.47 51.92 0% 0% 0% 0.00% S/ 51.92 100.00% 0.00%
1.1.2.2.3 CARGUIO, TRASPORTE Y COLOCADO DE TIERRA AGRICOLA m³ 1.89 21.66 40.94 0% 0% 0% 0.00% S/ 40.94 100.00% 0.00%
1.1.2.2.4 SEMBRÍO DE GRASS m² 5.03 8.10 40.74 0% 0% 0% 0.00% S/ 40.74 100.00% 0.00%
CRONOGRAMA VALORIZADO
OBRA MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC-SEGUNDA ETAPA

ENTIDAD MUNICIPALIDAD PROVINCIAL DE ANDAHUAYLAS


UBICACIÓN APURIMAC - ANDAHUAYLAS - ANDAHUAYLAS

MEJORAMIENTO VIAL DEL JIRON SANTA TERESA Y JIRON ABANCAY DEL DISTRITO Y, PROVINCIA DE ANDAHUAYLAS - APURIMAC- MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
SEGUNDA ETAPA
INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN INICIO FIN
Item
Descripción de Actividades Und. Metrado Precio (S/.) Parcial (S/.) 4/10/2023 4/30/2023 5/1/2023 5/31/2023 6/1/2023 6/30/2023 7/1/2023 7/31/2023 8/1/2023 8/31/2023 9/1/2023 9/6/2023
1.1.2.2.5 TIERRA DE CHACRA EN JARDINES m³ 1.51 63.73 96.23 0% 0% 0% 0.00% S/ 96.23 100.00% 0.00%
1.1.2.2.6 SUMINISTRO E INSTALACION DE PLANTONES gbl 2.00 236.16 472.32 0% 0% 0% 0.00% S/ 472.32 100.00% 0.00%

COSTO DIRECTO S/1,452,935.34 S/80,148.81 S/415,755.58 S/394,897.37 S/231,936.96 S/293,700.81 S/36,495.82


0.07 GASTOS GENERALES S/105,662.00 S/5,828.67 S/30,235.05 S/28,718.17 S/16,867.18 S/21,358.84 S/2,654.09
0.02 GASTOS GENERALES COVID-19 S/23,990.00 S/1,323.37 S/6,864.71 S/6,520.31 S/3,829.60 S/4,849.41 S/602.60
0.03 GASTOS DE SUPERVISION S/37,065.50 S/2,044.66 S/10,606.25 S/10,074.14 S/5,916.89 S/7,492.53 S/931.04
0.01 GASTOS DE LIQUIDACION S/9,211.83 S/508.16 S/2,635.95 S/2,503.71 S/1,470.52 S/1,862.11 S/231.39
0.01 GASTOS DE EXPEDIENTE TECNICO S/9,303.75 S/513.23 S/2,662.26 S/2,528.69 S/1,485.19 S/1,880.69 S/233.70
PRESUPUESTO TOTAL CONTRATADO S/1,638,168.42 S/90,366.89 S/468,759.79 S/445,242.39 S/261,506.35 S/331,144.40 S/41,148.63

PORCENTAJE PROGRAMADO 100.00% 5.52% 28.61% 27.18% 15.96% 20.21% 2.51%

PORCENTAJE PROGRAMADO ACUMULADO 5.52% 34.13% 61.31% 77.27% 97.49% 100.00%