TOTAL DE CADA DIA $1.500,00 $1.588,24 $661,76 $833,33 $833,33 $927,08 $843,75 $625,00 $625,00 $10.600,00 $66.014,71 $22.132,35 $9.665,44
TOTAL ACUMULADO $1.500,00 $3.088,24 $3.750,00 $4.583,33 $5.416,66 $6.343,74 $7.187,49 $7.812,49 $8.437,49 $19.037,49 $85.052,20 $107.184,55 $116.849,99
TOTAL DE CADA DIA $1.500,00 $1.588,24 $711,76 $833,33 $900,00 $938,75 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
TOTAL ACUMULADO $1.500,00 $3.088,24 $3.800,00 $4.633,33 $5.533,33 $6.472,08
AC.>COSTO REAL
DIAS
VALOR GANADO (EV)
DIA 1 DIA 2 DIA 3 DIA 4 DIA 5 DIA 6 DIA 7 DIA 8 DIA 9 DIA 10 DIA 11 DIA 12 DIA 13
ADECUACION DE GALPON Y ESTRUCTURAS PARA
A SEGUNDO GENERADOR
12,1 DIAS - $1.700,00 $1.588,24 $661,76 $833,33 $833,33 $927,08 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
TOTAL DE CADA DIA $1.700,00 $1.588,24 $661,76 $833,33 $833,33 $927,08 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
TOTAL ACUMULADO $1.700,00 $3.288,24 $3.950,00 $4.783,33 $5.616,66 $6.543,74
EV>VALOR GANADO
DIAS
variables para la curva S
DIA 1 DIA 2 DIA 3 DIA 4 DIA 5 DIA 6 DIA 7 DIA 8 DIA 9 DIA 10 DIA 11 DIA 12 DIA 13
TOTAL ACUMULADO PV $1.500,00 $3.088,24 $3.750,00 $4.583,33 $5.416,66 $6.343,74 $7.187,49 $7.812,49 $8.437,49 $19.037,49 $85.052,20 $107.184,55 $116.849,99
TOTAL ACUMULADO AC $1.500,00 $3.088,24 $3.800,00 $4.633,33 $5.533,33 $6.472,08 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
TOTAL ACUMULADO EV $1.700,00 $3.288,24 $3.950,00 $4.783,33 $5.616,66 $6.543,74 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
CURVA S
$120,000.00
$115,000.00
$110,000.00
$105,000.00
$100,000.00
$95,000.00
$90,000.00
$85,000.00
$80,000.00
$75,000.00
costo en dolares
$70,000.00
$65,000.00
$60,000.00
$55,000.00
$50,000.00 TOTAL ACUMULADO EV
$45,000.00 TOTAL ACUMULADO PV
$40,000.00
$35,000.00 TOTAL ACUMULADO AC
$30,000.00
$25,000.00
$20,000.00
$15,000.00
$10,000.00
$5,000.00
$0.00
1 2 3 4 5 6 7 8 9 10 11 12 13
TOTAL ACUMULADO EV $1,700.0 $3,288.2 $3,950.0 $4,783.3 $5,616.6 $6,543.7
TOTAL ACUMULADO PV $1,500.0 $3,088.2 $3,750.0 $4,583.3 $5,416.6 $6,343.7 $7,187.4 $7,812.4 $8,437.4 $19,037. $85,052. $107,184 $116,849
TOTAL ACUMULADO AC $1,500.0 $3,088.2 $3,800.0 $4,633.3 $5,533.3 $6,472.0
DIAS
NOMBRE FORMULA RESULTADO COMENTARIO
Variaciones de costo CV=EV-AC $71,66 No hay deficit que reuperar del proyecto
Variacion del cronograma SV=EV-PV $200,00 el proyecto esta adelantado por $200
Indice de desempeño del cronograma SPI=EV/PV 1,031527143 la cantidad de trabajo llevada a cabo es mayor que la prevista
indice de desempeño del costo CPI=EV/AC 1,011072175 costo inferior con respecto al desempño hasta la fecha
pronostico de la estimacion a la conclucion EAC=BAC/CPI $115.570,37 pronostico del EAC para el trabajo de la ETC con el CPI actual
pronostico de la estimacion a la conclucion EAC=AC+((BAC-EV)/(CPI*SPI)) $112.235,94
pronostico de la estimacion a la conclucion EAC=AC+(BAC-EV) $116.778,33
indice de desempeño del trabajo por
completar TCPI=(BAC-EV)/(BAC-AC) 0,999350776 mas facil de completar
indice de desempeño del trabajo por
completar TCPI=(BAC-EV)/(EAC-AC) 1 mas dificil de completar